24

Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:
Page 2: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

•  Background  on  the  ALMA  Phasing  Project  – Delivers  an  ALMA  Phasing  System  to  allow  – All  the  antenna  signals  to  be  combined  to  allow  – ALMA  to  join  in  3mm  &  1mm  VLBI  networks  

•  Current  Status  &  Near  Future  •  Cycle  5/6  Development  •  OpKons  to  move  beyond  that  

Overview  of  the  talk  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System  

General  Acknowledgement  to  the  great  many  people  who  have  brought  us  to  this  point  

2  

Page 3: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

Project  Timeline  and  Milestones  

•  Fall  2011:  Project  incepKon  •  November  2012:  Preliminary  Design  Review  &  ALMA  Board  Approval  •  May  2013:  CriKcal  Design  Review  •  January  2014:  IniKal  phasing  system  (R10.6)  and  first  VLBI  recordings  •  June  2014:  InstallaKon  of  Hydrogen  Maser  •  July  2014:  Switchover  of  ALMA  to  Maser  •  October  2014:  CompleKon  of  Hardware  installaKon;  So\ware  verificaKon  of  all  major  

features  completed  (R2014.4)  •  November  2014:  Hydrogen  Maser  Acceptance  Review    •  December  2014:  Hardware  Acceptance  Review  (CondiKonal  Pass)  •  January  2015:  Start  of  Commissioning  and  Science  VerificaKon  (R2014.6)  •  March  2015:  First  InterconKnental  Fringes  with  Phased  System  •  July/August  2015:  Band  3/Band  6  VLBI  Commissioning  •  October  2015:  “Incremental  S/W  Acceptance”  (Cycle  3)  •  December  2015:  DemonstraKon  of  SB  operaKon  •  April  2016:  Band  6  SB-­‐driven  VLBI  ObservaKon  (R2015.8)  •  Sept  2016:  Cycle  4  Acceptance  •  Oct  2016  –  Sep  2017:  Cycle  4  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   3  

Page 4: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

Maser

VLBI

Phasing

Correlator: Control

Central Electronics

Central Variable Reference

Photonic LO

2 bits/sample

Each Quadrant:

2Pol x 32ch x 62.5MHz

Data Rate: 16 Gb/s

128 LVDS Pairs

Correlator: Baseline

H Maser

EPC

CDP Computer Cluster

Fast Phase Solver

TelCal Computer

Slow Phase Solver and Monitor

Fiber DEMUX

Fiber MUX

Correlator: Station

Front End

Samplers, WVR

Optical Fiber Tx

Antenna

Phasing Interface Card

GPS

Alma Observing Blocks

Connects to all sub−systemsALMA Control System

Correlator Hardware Protocols

TFB Commanding

Correlator Card (CC)

Cross Correlation

Form VLBI Sum

Delay to align VLBI sum

VLBI sum antenna mask

Scaling of VLBI Sum

Route data to corr cards

VLBI sum input

Correlator Interface Card (CIC)

Long Term Accum/Final Add

∆φ Phase Corrections (Fast)

Monitors phasing efficiency by

correlating sum with reference

to calculate phase corrections

Uses source model parameters

∆φ Phase Corrections (Slow)

Scaling of VLBI sum

Delay control for CIC input

Interface with Phasing Calculators

Synchronization command

Time setting

Monitor GPS−Maser Drift

VLBI Scheduler

Control of VLBI Recorders

Control of CIC VLBI sum input

Control of CC:

VLBI antenna sum mask

Control of TFB:

VLBI Observing Block

Sends Parameters to TelCal Computer

Control of Phasing Interace Cards:

Control of Source Model Monitor

Phase offsets

Station Card

Geometric Delay

Optical Fiber Rx/Demux

Form 32 x 62.5 MHz slices

Tunable Filterbank Card (TFB)

Phase shift each slice 2 Cards per Quadrant

8 x 10 GbE

Phased Sum Data

10 GbE Packetization

Synchronization

PPS/Clock Monitor

VDIF Formatting

Baseline Visibilities

Generate Channel Averages

AOS (high site)

OSF (low site)

OSF (low site)

8 x 10 GbE

VLBI 16 Gbps Recorders

Tu

nab

le F

ilte

rban

k C

om

man

ds

10 MHz

1 PPS

5 MHz

CRG: 125 MHz, &c

MASER_V_GPS_COUNTER

APP  System  Block  Diagram  

FuncKonal  area  

Exists   New  

Timing  

Back  End  

Phase  sum  

Phase  soluKon  

Observing  block  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   4  

Page 5: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

APP  So\ware  Block  Diagram  

PI

Control Device

Hardware Side

Control Device

Correlator

Scheduler

Operator

Correlator

TelCal

ALMA Operator Display

VOM Schedule Block

Maser−GPS Monitor

Maser

AOSTiming

VLBI Recorder

VLBI OFLS

LTA Protocol

PIC Control

VLBI Observing Mode (VOM)

Phase Solver

Efficiency Monitor

Source Modeler

VEX2VOM Translator

VLBI Observation Status

VLBI Hardware Status

TelCal Results Display

CCC Phase Updates

VOM Observing ScriptVOM Configuration Data

VEX file

Configures ALMA for VLBIRuns the experiment

Phase Update (TFB)

Data Pathways

Prepares ALMA Sched BlockIngests VEX & PI intents

Maser

VLBIController

InterferometryController

PhasingController

Phasing

VLBI

Data

ChannelAverage

PhasingCorrections

FuncKonal  area  

Exists   New  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   5  

Page 6: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

VLBI  Observing  Mode,  new  in  Cycle  4  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System  

Standard  Interferometry  

Standard  VLBI  

Standard  Single  Dish  

Standard  Solar  (is  also  new  in  Cycle  4)  

6  

The  VLBI  inherits  from  Interferometry  to  pull  in  antenna  control,  &c....  

Page 7: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

Some  APS  Nomenclature  

•  Scan  Hierarchy  –  VLBI  Scans  refer  to  the  recordings  –  Correlator  Sub  Scans  –  “Slow”  Scan  phase  correcKons  from  TelCal  –  “Fast”  phase  correcKons  made  by  CORR  

•  DisKnguished  Antennas  –  Reference  Antenna  –  Phased  Antennas  (N  of  these)  –  The  “Analog”  Sum  Antenna  –  Comparison  Antennas  

•  (<Sum  .  Comp>)  /  (<Ref  .  Comp>)  ~  Sqrt(N)    

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   7  

Page 8: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

Scan  Strategy  

Phased Phased PhasedUnphased ∆ ∆ ∆

TFB Commands

. . .

WVR Data

. . .

. . .

TelCal Solving

Correlator Scan Sequence

. . .

. . .

VLBI Scan Record On

Time

Slow  Loop  

Fast  Loop  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   8  

Page 9: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

TelCal  Phasing  Engine  

Active!

Source'2'VLBI scan

ALMA scan (= subscan)

TelCal activity

Phasing solution validity

flagged data interval

Time

Active! Active!Active! Active! Active! Active! Active!

Source'1'

G.  Crew,  the  ALMA  Phasing  System  

TelCalResults*

Engines*

Libraries*

TelCalPublisher*

GetTelCalResult*

Control*

DataCapture*

Correlator*

Bulk*

TelCalDataManager*

ParameterTuning*

ReceivingDataManager*ReceivingDataManager*

ReceivingDataManager*

use

Bulk data

Meta data

•  TelCal  driven  by  scan  intents  •  Least-­‐squares-­‐fijer  exists  in  a  

TelCal  library  •  On  each  scan  the  engine  solves  

for  slow  phase  (and  delay)  errors  which  remain  a\er  fast  WVR  correcKons  

•  Publishes  (new)  ASDM  table  •  Provides  feedback  on  quality  

(phasing  efficiency,  opKmal  antenna  choices,  &c.)  

Data  are  flagged  relaKve  to  phase  adjustments  for  the  

benefit  of  fimng  engine  

May  3,  2016   9  

Page 10: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

Phase  CorrecKons  from  TelCal  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   10  

This  scan  had  CM,  DA,  DV  and  PM  antennas  

INPUT   OUTPUT  

Page 11: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

General  Phasing  Sequence  

«CORBAInterface»:SingleFieldInterferometryObservingMode

«CORBAInterface»:ObservationControl

Operator

Scheduling «CORBAInterface»:AutomaticArray2

«CORBAInterfa...:ParameterTuning

«CORBAInterfa...:GetTelCalResults

«CORBAInterface»:ReceivingDataManager

«CORBAInterfa...:ScriptExecutor

«CORBAInterfa...:DataCapturer

«CORBAInterfa...:ExecutionState

callback

«CORBAInte...:SkyDelayServer

corrSubscanSeqCalback

createArray()

startSB()

observeNow(sbId, sessionId)

runObservationScriptAsync(script, callback)

beginExecution()

startSB(arrayName, startTime)

ExecBlockStarted()

«event»

getSFIOffshoot() :SingleFieldInterferometryObservingMode

setAppSumAntenna(location, cableDelay)

setAppParameters(sourceModel, algorithm)

setSubArray(subarrayId, antennaList, bdStreamInfo)

setAppParameters(subarrayId, mask, refAntenna, algorithmMode)

doScanSequence(ScanSpecSeq, SimpleCallback) :Time

wait()

beginScan(ScanIntentDataSeq)

ScanStarted()

«event»parseIntents()

sendAppParametersData(mask, refAntenna)

getReconfigurationTimes(subarrayId, calibrations, durations) :SubscanTimingSeq

compute timings()

startSubscanSequence(subarrayId, startTime, executeBlockID, executeBlockNumber, subscanInfos, callback)

startSubscanSequence(arrayName, subscanIntents)

binary data()

report(status)

sendSubScanCorrelatorData(arrayId, subscanNumber, data)

ScanProcessedEvent()

«event»

getFinalMetaDataQL(scanNum) :ASDMDataSetIDL

publishAppResults()

isAppPhaseResultAvailable()

AppPhaseReducedEvent()

«event»

getAppPhaseResult()

AppPhaseReducedEvent()

«event»getAppPhaseResult()

setAppSlow(subarrayId, mask, refAntenna, phaseSeq)

sendAppParametersData(mask, refAntenna)

binary data()

report(status)

report()

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   11  

Too  much  detail  to  present—see  the  Design  Document  

Time  

Different  So\ware  Components  

Page 12: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

Correlator  Phasing  Sequence  

Corr HW «CORBAInte...:Node

«CORBAInte...:Master

PhasingCallback

«CORBAInterf...:ObservationControl

«CORBAInterface»:SingleFieldInterferometryObservingMode

consider one ALMA subscan

loop for each ALMA scan

loop fast phase corrections

setSubArray(subarrayId, antennaList, bdStreamInfo)

setSubArray(array, bddStreamInfo)

setArray(array)

setAppParameters(subarrayId, mask, refAntenna)

configureLTA(mask, scalingData)

setupPIC(VDIFchannels)

setPICcontrol()

setPICheader()

doAppScanSequence(...)

setAppScanParameters(algorithmMode)setAppMode(algorithmMode)

setAppMode(algorithmMode)

beginScan(intents)

getReconfigurationTimes(subarrayId, calibrations,durations) :SubscanTimingSeq

computeTimings()

startSubscanSequence(subarrayId, startTime, executeBlockID,executeBlockNumber, subscanInfos, callback)

startSubscanSequence(arrayId, startTime, executeBlockID,executeBlockNumber, subscanInfos, callback)

startSubscanSequence(arrayId, startTime, subscanInfos)configureLTA(sumSwitch=on)

flagDataInvalid()subscanStarted()

slowPhaseLoop()

setAppSlow(subarrayId, mask, refAntenna, phaseSeq, interval) :timestamp

configureLTA(mask, scalingData)

applyTFBPhases(phaseSeq)

setAppSlow(arrayId, phaseSeq, timestamp, cb)

setAppSlow(arrayId, phaseSeq, timestamp)

flagDataValid()

calculatePhases()updatePhases(phaseSeq)

updatePhases(phaseSeq)

applyTFBPases(phaseSeq)

report(status)

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   12  

Page 13: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

TelCal  Phasing  Sequence  

«CORBAInter...:GetTelCalResults

«CORBAInterface»:ReceivingDataManager

«CORBAInterf...:ParameterTuning

«CORBAInte...:DataCapturer

«CORBAInterface»:SingleFieldInterferometryObservingMode

«CORBAInte...:ExecutionState

«CORBAInterf...:ObservationControl

consider first ALMA scan

loop for each ALMA scan

consider asynchronos processing

Phase processing done.

setSubArray(subarrayId, antennaList, bdStreamInfo)

setAppParameters(subarrayId, mask, refAntenna)

sendAppParametersData(mask, refAntenna, timestamp)

doAppScanSequence(...)

setAppScanParameter(sourceModel, algorithmMode)

setAppScanParameters(sourceModel, algorithmMode)

beginScan(intents)ScanStarted()

«event»

parseIntents()

startSubscanSequence(arrayName, subscanIntents)

startSubscanSequence(subarrayId, startTime, executeBlockID, executeBlockNumber, subscanInfos, callback)

report(status)

sendSubScanCorrelatorData(arrayId, subscanNumber, data)

ScanProcessedEvent()

«event»

getFinalMetaDataQL(scanNum) :ASDMDataSetIDL

calculatePhaseResults()

beginScan(intents)

ScanStarted()

«event»startSubscanSequence(arrayName, subscanIntents)

startSubscanSequence(subarrayId, startTime, executeBlockID, executeBlockNumber, subscanInfos, callback)

publishAppResults()

isAppPhaseResultAvailable()

AppPhasedReducedEvent()

«event»

AppPhaseReducedEvent()

«event»

getAppPhaseResult()

getAppPhaseResult() :AppPhaseResultgetAppPhaseResult() :AppPhaseResult

analyzePhaseResults()

setAppSlow(subarrayId, mask, refAntenna, phaseSeq, interval) :timestamp

sendAppParametersData(mask, refAntenna, timestamp)

*fastPhaseLoop()

report(status)

sendSubScanCorrelatorData(arrayId, subscanNumber, data)

ScanProcessedEvent()

«event»May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   13  

Page 14: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

Project  Timeline  and  Milestones  

•  Fall  2011:  Project  incepKon  •  November  2012:  Preliminary  Design  Review  &  ALMA  Board  Approval  •  May  2013:  CriKcal  Design  Review  •  January  2014:  IniKal  phasing  system  (R10.6)  and  first  VLBI  recordings  •  June  2014:  InstallaKon  of  Hydrogen  Maser  •  July  2014:  Switchover  of  ALMA  to  Maser  •  October  2014:  CompleKon  of  Hardware  installaKon;  So\ware  verificaKon  of  all  major  

features  completed  (R2014.4)  •  November  2014:  Hydrogen  Maser  Acceptance  Review    •  December  2014:  Hardware  Acceptance  Review  (CondiKonal  Pass)  •  January  2015:  Start  of  Commissioning  and  Science  VerificaKon  (R2014.6)  •  March  2015:  First  InterconKnental  Fringes  with  Phased  System  •  July/August  2015:  Band  3/Band  6  VLBI  Commissioning  •  October  2015:  “Incremental  S/W  Acceptance”  (Cycle  3)  •  December  2015:  DemonstraKon  of  SB  operaKon  •  April  2016:  Band  6  SB-­‐driven  VLBI  ObservaKon  (R2015.8)  •  Sept  2016:  Cycle  4  Acceptance  •  Oct  2016  –  Sep  2017:  Cycle  4  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   14  

We  are  here  

Page 15: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

Immediate  Next  Steps  

•  Correlate  and  analyze  April  1mm  session  – “Sample”  Cycle4  1mm  observaKon  – Bring  PolConvert  to  OperaKonal  Readiness  

•  SKll  need  to  capture  3mm  session  (June/July?)  – DemonstraKng  that  VEX2VOM’d  phase2  schedule  blocks  play  nicely  with  the  Archive  

– Need  to  finalize  VLBI  operaKonal  details  (reconciling  VLBI  scheduling  with  ALMA)  

•  Ready  for  Cycle  4,  except  for  – Final  details  for  operaKng  the  VLBI  arrays,  and…  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   15  

Page 16: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

ICT-­‐5401:  Aug  27th  phasing  (25  ant.  phased)  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   16  

Page 17: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

March  23,  2016  (VLBI  Regression  Test)  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   17  

Page 18: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

Appear  to  have  resolved  some  things  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System  

ICT-­‐7128  remains  

18  

Amp  v  Time  for  <Sum  .  Comp>  for  9  comparison  antennas  

Page 19: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

Working  on  ICT-­‐7218  (side  discussion…)  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   19  

CASA  Plots  of  Real  v  Imag  visibiliKes  for  6  phased  antennas  during  one  scan,  colors  by  integraKon  

DGCK  fine  delays  as  logged  at  several  of  these  antennas,  integrated,  linear  fit  subtracted  

Colors  bars  correspond  to  sub-­‐scans  reported  by  Controller  or  CCC      

Page 20: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

Things  which  follow  the  sine  qua  non  for  Cycle  4  

•  Le\-­‐over  from  APP  – GUI  (Python  version)  – Source  Modeler  (could  appear  as  needed)  

•  ADF  Cycle  3  Study  (Majhews):  – Turn  Baseband  Delay  back  on  in  CDP  – Mismatched  Channel  OpKons  – Band  7  (see  next  slide)  – Analysis  Support  for  Observers  

•  ADF  Cycle  3  Study  (Cordes):  – Using  the  APS  for  pulsar  work  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   20  

Page 21: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

Second  Band7  Session  (Aug  2015)    Amplitude  of  small  array  on  (3  sources)  

1337-­‐129,  3c279,  1337-­‐129  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   21  

Page 22: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

Example  DA58  (reference  antenna)  &  DV11    

We  used  8  channel  averages;  We  can  use  16  or  32  on  bright  sources  (phased  in  most  scans;  un-­‐phased  for  some)  

 

Delay  when  un-­‐phased    

Delay  when  phased    

15    

Bejer  Baseband  Delay  Fix  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   22  

Frequency  

CDP  Residual  Delay  CorrecKon  normally  also  includes  the  much  larger  Baseband  delay  

Page 23: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

Cycle  5/6  under  Discussion  (at  OBSMODE)  

•  Implement  the  Delay  Fix  –  TelCal  looks  up  Baseband  Delays  the  same  way  that  the  CDP  does  and  undoes  the  CDP  work  prior  to  calculaKng  phases  

–  Requires  some  changes  to  the  phase  pack/unpack  library  •  Remove  the  current  500  mJy  restricKon  •  Add  a  Spectral  Line  mode  for  VLBI  – Mostly  a  data-­‐rate,  OT  limitaKon  –  Spectral  averaging  puts  line  details  into  oblivion  –  Spectral  Setup  is  currently  aimed  at  conKnuum  – We  should  be  using  the  FDM  Frequency  agility  [or  MulK-­‐resoluKon  modes  (see  Ray/Rich  talks)].  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   23  

Page 24: Background+on+the+ALMA+Phasing+Project · 2016. 5. 4. · Maser VLBI Phasing Correlator: Control Central Electronics Central Variable Reference Photonic LO 2 bits/sample Each Quadrant:

Beyond  Cycle  6:  Sub-­‐arrays  

VLBI  does  not  play  well  with  sub-­‐arrays.  •  OperaKonal:  required  “start”  Kme  •  There  is  only  one  “sum”  antenna  •  There  is  only  one  LTA  “sum”  antenna  switch  •  PICs  are  not  owned  by  any  sub-­‐array  •  Slow  phasing  adjustments  assume  no  other  CAN  bus  traffic  

•  WVR  correcKons  assumes  a  single  array  •  hjps://ictwiki.alma.cl/twiki/bin/view/Control/AppMulKSubarrays  •  hjps://ictwiki.alma.cl/twiki/bin/view/Control/AppPhase2TaskIdeas  

May  3,  2016   G.  Crew,  the  ALMA  Phasing  System   24