Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
PROJECT Profile
Client: Erie County Department of Public Works
"One of Western New York's first "Green
Design" public projects."
Urban Engineers (Urban) was a subconsultant to the
country's premier justice facility design team for the design
of the replacement of Erie County’s Secure Youth
Detention Facility, in Buffalo, NY. Urban provided
structural engineering, all civil/site design, utility design for
the new buildings, and engineering for the demolition of
the existing facility and utilities. Review of several
proposed alternate sites, and recommendations for
increasing the size of the existing site, were also Urban’s
responsibility. The new facility incorporates a school, pod
style resident halls, and a dramatic entrance canopy
designed by Urban.
The 68-bed, detention facility is a state-of-the-art temporary housing for troubled youth. The 67,000-SF project is a
secure building with space for education, counseling, and indoor and outdoor exercise facilities.
The project is one of Western New York's first public projects that introduced the elements of "Green Design" in both the
design and methods and materials of construction. During the site plan review process, Erie County required the
contractor to recycle as much construction and demolition debris as economically feasible. The demolition phase of the
project yielded more than 10,000 tons of recycled material, which saved Erie County taxpayers approximately $130,000
on this phase of the project.
Replacement of the Erie County Secure Youth Detention Facility
Erie County, NY
HIGHLIGHTS: A Dramatic, Structural Sculpture Entrance
Canopy Masonry, Steel, and Pre-Cast Concrete
Systems Combined for Security and Cost Effectiveness
Replaced Existing Facility in Place Structural and Civil/Site Engineering Services
B01-09-00
PROJECT Profile
Client: Niagara Falls Air Reserve 914th Airlift Wing
"Replacement of aging infrastructure to
enable base to meet modern day demands."
Urban Engineers (Urban) was retained by the Niagara
Falls Air Reserve Station to study and design a base-wide
water distribution system revitalization.
Urban constructed a hydraulic model of the base using
the WaterCAD software package to simulate available
domestic and fire flows available to locations throughout
the base. Following iterative runs of differing main sizes, ranging from 6-to-18 inches in diameter, a final sizing plan
consisted of approximately 8,000 LF of 12-inch, 10,200 LF of 10-inch, and 11,200 LF of 8-inch diameter pipe. The
resulting fire flow availability is in the range of 2,700-3,000 gpm.
The special needs of the air base included identifying and minimizing impacts to several on-site underground obstacles,
such as petroleum pipelines, communication lines, fiber optic lines, and security measures. To minimize disturbance to
these obstacles, Urban evaluated the possibility of trenchless technology, in addition to corridor alternatives and
contingency planning.
The design incorporated about 55 new hydrants spaced in accordance with military regulations for aircraft facilities.
Additionally, isolation valves were placed at watermain intersections and spaced as per military requirements, and new
water service connections were designed, including service piping up to and within buildings where services are 10 years
or older. All items were designed in accordance with military regulations as well as American Water Works Association
standards. The total estimate to construct the proposed facilities was approximately $1.8 million.
B03-04-00
Niagara Falls Air Force Base Water SystemNiagara Falls, NY
HIGHLIGHTS: Military Civil Design NPDES Stormwater Compliance Potable Water Transmission and Distribution
Design Water Distribution Modeling
PROJECT Profile
Client: City of Niagara Falls, NY
"The demolition was carefully planned and
executed to minimize impacts to an active
hotel and nearby infrastructure, including a
major drainage tunnel."
Urban Engineers (Urban) was retained by the City to
conduct an analysis of the structural condition of a 30-
year-old parking structure and recommend improvements
to refurbish the facility. After reviewing the report and
financial analysis of the alternatives, the City determined
demolition was the best option. The City hired Urban to
design the demolition and replace it with a new surface
lot.
Urban prepared construction drawings and specifications for the demolition of the 1,400-vehicle, 3.5-acre parking
facility. The ramp was constructed of pre-stressed concrete. Demolition activities were carefully planned to minimize
impacts to an active hotel located 10 feet to the south of the building and existing infrastructure, including a major
drainage tunnel located beneath the footprint of the structure.
The new surface lot required survey work, planning, layout, landscape layout, design of storm drainage, and utility
relocation. The design of the surface lot also posed interesting challenges, such as: an 11-foot drop in grade across the
site; the new facility had to be designed to incorporate part of the existing stormwater infrastructure from the ramp; and
the location of the lot lies in the heart of downtown Niagara Falls in proximity to the international bridge, Seneca Niagara
casino, surrounding hotels, and Third Street corridor.
B03-06-00
Niagara Falls Parking Ramp Demolition and Surface Lot Development
Niagara Falls, NY
HIGHLIGHTS: Demolished Prestressed Concrete Structure 3.5-Acre Demolition Site in an Active City
Location Minimized Impact to Existing City and Private
Utility Infrastructure
PROJECT Profile
Client: County of Niagara, NY
Department of Public Works "This project included constructing a new bus
loop drop off area and additional parking."
Experiencing growth and an increasing demand for
parking facilities at the Niagara County Community
College Campus, Niagara County hired Urban Engineers
(Urban) to provide the design of a new campus entry and
drop off loop, a new parking lot facility, and a parking lot
expansion.
Urban reviewed historical campus record drawings of existing facilities to understand the conditions and developed a plan
for the proposed improvements in character with the campus facilities.
Urban conducted a traffic analysis of how the facilities would be used and presented the client with alternatives for internal
traffic circulation plans, which defined the appropriate layout and alignment of the new facilities. A stormwater pollution
prevention plan was also assembled for this project to address both temporary and permanent stormwater control
measures.
Urban developed the design plans and schedule to reduce any impact to campus operations.
B50-06-00
Niagara County Community College Entrance Improvements
Niagara County, NY
HIGHLIGHTS: ADA Site Compliance New Parking Facilities Reconfigured Entrance Loop
PROJECT Profile
Client: Jacques Whitford Company Ltd
"......an environmentally-friendly treatment
option for glycol-contaminated stormwater."
Urban Engineers (Urban) designed a new treatment
system to address glycol contamination of stormwater at
Buffalo-Niagara International Airport (BNIA). The system
utilizes an emerging technology of "Stormwater
Wetlands," which are entirely below ground surface
aerated gravel beds. As a subconsultant, Urban was
responsible for providing stormwater analysis/design, civil
design, structural design, and related specifications and
details.
The newly-engineered BNIA wetlands treat glycol-contaminated stormwater runoff and other wastewater during the de-
icing season. In addition, the wetlands treat the stormwater sewers' base flow and rainfall event first flush runoff year
round.
The wetlands consist of four rectilinear wetland cells excavated from an existing open area near the airport's main runway.
At ground level, only a field of wetland grasses is observable, growing from a "dry" mulch surface. The system is designed
to treat up to 0.2 MM gpd of concentrate from the de-icing pads from up to 300,000 gallons of pure propylene glycol
used annually during the average 190-day de-icing season. In addition, the system is designed to treat an average
stormwater flow rate of 1 MM gpd year round. The design also allows for treating a mix containing up to ~2,150 mg
BOD/L during the de-icing season and uses existing underground glycol and stormwater tanks for flow equalization.
Buffalo-Niagara International Airport Stormwater Treatment System
Buffalo, NY
HIGHLIGHTS: Developed Stormwater Model and
Management Plan Designed Stormwater Pump Stations Provided Airport Civil Design Designed 3,200-SF Utility Building Provided Substantial Soils Management Plan
B60-01-00
PROJECT Profile
Client: County of Sullivan, NY
Office of General Services "...also planned is the addition of a Photo
Voltaic Solar Array system for supplemental
electric power, which was not part of these
contracts."
Urban Engineers (Urban) was selected to provide
construction management services for the Sullivan County
Transportation Facility, located in southeastern New York,
approximately 90 miles northwest from New York City and
close to Route 17 (Future I-86.)
The new facility was constructed on partially-wooded lands
adjacent to the Sullivan County International Airport. The site encompasses seven acres of land of which five were
developed to provide a 9,000-SF, single-story pre-engineered office and garage building with road access and parking
for 54 vehicles. The building encompasses 3,600-SF of administrative offices, a training room, kitchen, restrooms, upper
level mechanical room, and 5,400-SF of garage space with six pull through bus bays.
The facility is served by a drilled water well, septic system, an underground propane storage tank, forced hot air heat, air
conditioning, and infrared radiant heaters in the garage area. Electrical and communication utilities are located
immediately adjacent to the site along County Rt. 183. Future plans allow for expanding two additional pull through bus
bays, which were postponed due to costs and requirements. Also planned is the addition of a Photo Voltaic Solar Array
system for supplemental electric power, which was not part of these contracts.
B61-02-00
Sullivan County Transportation FacilityMonticello, NY
HIGHLIGHTS: Construction Management of a Regional
Transportation Facility Future Plans to Allow for Expanding Two
Additional Pull Through Bus Bays New Facility on Partially Wooded Lands
PROJECT Profile
Client: New York State Thruway Authority
"This project utilized a new approach to
concrete pavement repair and was used as a
pilot project."
Urban Engineers (Urban) performed the construction
inspection for the pavement rehabilitation of four miles of
the Niagara section of the NYS Thruway.
This work included full-depth concrete pavement repairs,
partial-depth pavement repairs, dowel bar retrofits, and
diamond grinding. Maintenance and protection of traffic
was important due to the high volume of traffic on the
Thruway.
Urban's staff devised an innovative use of aerial photographs and transparent overlays to produce daily maintenance and
protection of traffic layouts in advance of the work. This allowed them to rapidly adapt to changes in the contractors'
schedule, in addition to promote clear, concise communication between Urban's team and the contractors.
B70-02-08
I-90 Concrete Pavement RehabilitationNew York, NY
HIGHLIGHTS: Construction Management Construction Inspection Maintenance and Protection of Traffic Coordination with Other Projects
®
PROJECT Profile
Client: New York Department of Transportation
"altered the drainage plan...resulting in
significant savings to the contract."
Urban Engineers of New York, P.C. (Urban) is performing construction inspection services for the New York State Department of Transportation for the reconstruction of Transit Road, US Route 78, in the Towns of Amherst, Cheektowaga, Clarence, and Lancaster. Urban is responsible for providing construction inspection and record keeping services for the more than $28 million reconstruction of Transit Road. The project's objective is to fully reconstruct approximately three kilometers of Transit Road between Main Street and Genesee Street from five to seven lanes. The project operations include installing and/or relocating the underground drainage system, including installing a seven-foot diameter, reinforced concrete pipe to facilitate the drainage of this highly-commercialized area. The project also included installing new waterlines and sanitary sewer facilities, most of which required blasting of rock for excavation purposes. A major concern is the maintenance and protection of traffic. Urban developed complex scenarios to maintain the four lanes of traffic needed to handle the congestion along this critical urban arterial. The new pavement sections include both Portland cement concrete pavement and asphalt cement concrete pavement. During the project, the prime contractor submitted and received approval of an extensive value engineering change proposal, which altered the drainage plan and eliminated a planned box culvert, resulting in significant savings. Urban's team consists of a Chief Inspector, Office Engineer, three Senior Transportation Inspectors, and a Transportation Inspector Trainee.
Reconstruction of Route 78 (Transit Road)Amherst, Cheektowaga, Clarence, and Lancaster, NY
HIGHLIGHTS: Maintaining Four Lanes of Traffic Three-Year, Nearly $30 Million Project Drainage Relocation Extensive Maintenance and Protection of Traffic
B70-03-00
PROJECT Profile
Client: Trautman Associates
"Portland cement concrete replacement and
full depth repairs on 1.5 mile long military
taxiway system."
Urban Engineers of NY, PC was retained by the United
States Air Force in conjunction with Trautman Associates
to provide civil engineering design services for
replacement, repairs and drainage system improvements
to the military taxiway system at the Niagara Falls Air
Force Base.
The taxiway is constructed of Portland cement concrete
pavement and a field survey was done to inspect over
3,000 slabs for replacement and full depth concrete
repairs. Soil borings were also done to confirm thickness
of the existing pavement sections, condition of the sub-base and type of underlying soils. TV video inspections were also
performed to assess conditions of the existing drainage system and it's outfalls to Cayuga Creek.
Final design plans included over 10,000 cubic yards of concrete pavement demolished and replaced, full depth repairs
with dowels/tiebars, a unique sub-base underdrain system, new underdrain in grass shoulder areas, joint
sawcutting/sealing and replacement of pavement markings. Total estimated costs are $6.25 million and bids are
expected to be taken soon for the 2009 season.
B70-17-00
Niagara Falls Air Force Base Taxiway Repairs and Drainage Improvements
Buffalo, NY
HIGHLIGHTS: Airfield Pavement Markings Concrete Pavement Replacement and Repair
Methods Field Survey of Entire Length to Assess
Conditions Stormwater Analysis and Video Survey of
Existing Systems Sub-base Drainage and Perimeter Underdrain
PROJECT Profile
Client: Town of Tonawanda, NY
"This project featured the reconstruction of a
heavily damaged park roadway following an
early season snow storm."
In October of 2006, Western New York was hard hit by a
surprise early season snow storm. Since the leaves had
not yet fully fallen from the trees, thousands of trees lost a
significant portions of their limbs, which created a number
of regional states-of-emergency.
In the emergency cleanup effort, the Town of Tonawanda utilized Lincoln Park as a staging area for temporary storage
and handling of storm debris. The significant use of the road by hundreds of trucks hauling debris resulted in severe
damage to the roadway.
The Town of Tonawanda hired Urban Engineers to complete the design and oversee the construction of a full road
replacement, which was funded in part by Federal Emergency Management (FEMA) monies.
The project included nearly 2,000 feet of roadway, concrete gutters, new storm drainage design, and stabilized roadside
parking areas for park users.
B70-06-00
Lincoln Park Road ReconstructionKenmore, NY
HIGHLIGHTS: Full Town Park Road Reconstruction New Drainage System Design Stabilized Road Side Parking Area
PROJECT Profile
Client: City of Buffalo, NY
"Brownfield redevelopment of former railroad
right-of-way to meet a demand for housing
in North Buffalo."
After a developer purchased a 22-acre parcel of former
railroad right-of-way located in a thriving residential area
in North Buffalo, NY, Urban Engineers (Urban) was hired
to coordinate with the City of Buffalo's Planning and Public
Works Department to prepare site plans for subdivision
approval. Urban was also charged with designing the
necessary infrastructure to support the new 126-unit,
single-family housing development.
The infrastructure design included a new 4,000-foot-long
residential street with a roundabout as a traffic calming measure. Other infrastructure design elements included ductile
iron watermain, PVC sanitary sewer, underground stormwater retention system, street lighting, traffic controls, extensive
site regrading, entrance walls, and landscaping.
Urban also led coordination efforts with electric, gas, cable, and phone for necessary easements, design, and service
requirements.
In addition, Urban coordinated the approvals obtained from the Erie County Department of Health, NYSDEC, Buffalo
Sewer Authority, Water Authority, and Public Works.
B80-04-00
Colvin Estates Subdivision Residential Housing Development
Buffalo, NY
HIGHLIGHTS: Highway Design Land Development Sanitary Sewer Design Site Plan Approval Stormwater Retention System Roundabout Design Utility Coordination Watermain Design
PROJECT Profile
Client: Niagara Falls Bridge Commission
"This scenic bridge spans between Niagara
Falls, New York, USA and Niagara Falls,
Ontario, Canada."
The Niagara Falls Bridge Commission hired Urban
Engineers (Urban) to perform construction management
services for Phase II work on the Whirlpool Rapids
Bridge, which spans the Niagara River between Niagara
Falls, New York, USA and Niagara Falls, Ontario,
Canada. It is a 550-foot-long steel deck arch bridge
with a conventional floor system consisting of built-up
steel girders and floor beams.
The work included 100% blast cleaning of all the steel, removing and disposing of lead paint, repairing the structural steel
necessary, and re-painting the steel. The pedestrian walkway also needed to be removed and replaced with new sidewalk
planks and nailers.
Urban coordinated the construction work with the United States and Canadian Customs and Immigration Offices, US
Border Patrol/Local Police, Niagara Parks Commission, NYS Power Authority, and NYS Office of Parks, Recreation and
Historic Preservation to continuously monitor bridge activity. Also coordinated with NYSDEC to make sure clean up
occurred if any lead-filled paint chips fell below the bridge to the hiking trail.
B80-07-00
Whirlpool Rapids Bridge Cleaning Painting & Structural Steel Repair
Niagara Falls, NY
HIGHLIGHTS: Removed and Replaced Sidewalk Planks and
Nailers Extensive Coordination including US &
Canadian Customs, US Border Patrol, Local Police, and NYSDEC
Blast Cleaning and Lead-Based Paint Removal Bridge Painting
®
PROJECT Profile
Client: Seneca Construction Management Corporation
"Demolition of failing structure for site
redevelopment."
Urban Engineers (Urban) was retained by the Seneca
Construction Management Corporation (SCMC) to
prepare design plans for demolishing various structures
on four separate sites owned by the Seneca Nation. The
demolition included the former Salamanca Hospital
Complex with ancillary office and maintenance buildings,
Killbuck School, a commercial masonry building, and a
four-unit, wood-frame residential structure.
Plans were not available for any of the structures to be demolished and, as a result, Urban had to perform extensive
surveys at each site to define site conditions, locate structures, plot utilities, and establish site topography. Urban also
undertook mandated hazardous material and asbestos surveys, analyzed samples taken, and documented the results in a
report for each site. In addition, due to the age and condition of the structures, each one was inspected for structural
integrity to evaluate safe access for asbestos removal and demolition activities. As a result, the main structure at the
Killbuck School site was condemned requiring variances for the asbestos removal and disposal.
Urban then prepared construction drawings and specifications for removing, transporting, and disposing of hazardous
materials, demolitions, utility issues, and site restoration. As directed by the SCMC, all foundations, basement walls, and
floors were totally removed and backfilled with compacted stone to allow for future development. Demolition activities
and site restoration were carefully detailed to minimize impacts on adjacent properties, vehicular/pedestrian traffic, and
drainage patterns .
Seneca Nation DemolitionsSalamanca, NY
HIGHLIGHTS: Asbestos Abutment Design at Each Location Demolition of Failing Structures at Four
Locations Full Demolition Plans and Utility Cut Off
Design
®
B80-14-00