Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
PRODUCTIVITY IMPROVEMENT IN THE
ASEEMBLY FLOW-LINE
AZHAR RAJA DURAI PANDI KTH ROYAL INSTITUTE OF TECHNOLOGY Masters in Production Engineering and Management
2
Productivity Improvement in the Assembly
Flow-Line
School of Industrial Engineering and Management
Department of Production Engineering
MASTER THESIS
Report done by
Azhar Raja Durai Pandi
Supervisor at KTH
Daniel Tesfamariam Semere
Supervisor at FAIVELEY TRANSPORTS
Vinayagam
3
Abstract
As the material feeding system has the great impact on the assembly flow-line which enhances
the productivity thereby improves company’s profit. The purpose of this thesis is mainly focused
on the flexibility usage of the material handling/feeding system into the line which helps in
improving the productivity. The new design for the material handling trolley was designed and
also came up with the additional concept of kitting and palletizing the parts in the newly designed
trolley which helps in easy handling for the operators and improves the productivity as well. The
appropriate analysis and comparison corresponding to the productivity time was done with the
existing material handling trolley and with the newly designed trolley. In addition to this,
proposed ideas for enhancing the assembly flow line and successfully proved that material
handling system, kitting and palletizing plays a very important role in productivity improvement
of the assembly flow line.
4
5
Abstrakt
Eftersom materialmatningssystemet har stor inverkan på aggregatets flödesledning som förbättrar
produktiviteten förbättrar därmed företagets vinst. Syftet med denna avhandling är huvudsakligen
inriktat på flexibilitetsanvändningen av materialhanterings- / matningssystemet i linjen som
hjälper till att förbättra produktiviteten. Den nya konstruktionen för materialhanteringsvagnen är
utformad och har även tagit fram ytterligare konceptet med kittning och palletering av delarna i
den nybyggda vagnen, vilket hjälper till att hantera operatörerna enkelt och att förbättra
produktiviteten också. Den lämpliga analysen och jämförelsen som motsvarade
produktivitetstiden gjordes med den befintliga materialhanteringsvagnen och med den
nyutvecklade vagnen. Utöver detta har förslag till idéer för att förbättra sammansättningsflödet
och framgångsrikt visat att materialhanteringssystemet, kittning och palletering spelar en mycket
viktig roll i produktivitetsförbättring av aggregatets flödesledning.
6
7
Acknowledgement
First of all I would be much more gratitude to Department of Production Engineering and
Management, KTH Royal Institute of Technology for giving me this thesis opportunity. I
thank Mr. Lasse Wingård, Department head, Mr. Per Johansson, Mr. Ove Bayard, who rendered
his full support for this thesis work. I like to express my sincere and special gratitude to my
supervisor Mr. Daniel Tesfamariam Semere who supported me with the patience and guided me
well during my thesis work and helped to do this challenging task easily.
I am thankful and also express my gratitude to Mr. Vinayagam, General Manager, PED, Mr.
Saravanan, Assistant Manager, PED, Faiveley Transports – A Wabtec Company for assistance
and encouragement who are my supervisor to accomplish this assignment and their valuable
guidance and supported me to present this thesis report in a success manner. Also to Mr.
Somasundaram, Human Resource, Faiveley Transports – A Wabtec Company and also few
industry persons for giving such attention and time for supporting me with this thesis work.
Finally, the last but not least my happy gratitude goes to my parents and family members and
all of dear friends who directly or indirectly helped me to complete this thesis report
successfully.
8
Table of Contents
Abstract........................................................................................................................... 3
Abstrakt .......................................................................................................................... 5
Acknowledgement ........................................................................................................... 7
Table of Contents ............................................................................................................ 8
Abbreviations ................................................................................................................ 10
List of Figures ............................................................................................................... 11
List of Tables ................................................................................................................. 12
1. Company Introduction .......................................................................................... 13
2. Background ........................................................................................................... 14
2.1 Problem Description ......................................................................................................... 14
2.2 Limitations ....................................................................................................................... 15
2.3 Problems Identified in The Assembly Line ......................................................................... 16
3. Methodology .......................................................................................................... 18
4. Literature Review .................................................................................................. 19
4.1 Material Handling System ................................................................................................. 19
4.2 Continuous Supply............................................................................................................ 20
4.3 Batch Supply .................................................................................................................... 20
4.4 Kitting .............................................................................................................................. 21
4.5 Benefits of kitting ............................................................................................................. 21
4.6 Palletizing ........................................................................................................................ 22
5. Bogie Brakes .......................................................................................................... 24
5.1 TBU Assembly .................................................................................................................. 24
6. Production Lean Tools ........................................................................................... 27
6.1 Value Stream Mapping ..................................................................................................... 27
6.1.1 Current State ..................................................................................................................... 27
9
6.1.2 Analysis of Current State ................................................................................................. 27
6.1.3 Proposed Improvements ............................................................................................... 28
6.1.4 Result .................................................................................................................................. 28
6.2 5S .................................................................................................................................... 31
6.3 Kaizen .............................................................................................................................. 31
6.4 Toyota Way 14 Principles .................................................................................................. 32
7. Current Material Handling/Feeding System ............................................................. 33
7.1 Effects Of Current Material Feeding System ...................................................................... 34
7.2 Current Trolley ................................................................................................................. 35
7.3 Current Workbench and Bin trolley ................................................................................... 36
7.4 CAD Modelling ................................................................................................................. 38
7.5 Kitting Concept ................................................................................................................. 39
7.6 Palletizing Concept ........................................................................................................... 39
8. Discussion .................................................................................................................. 44
8.1 Operators Feedback ......................................................................................................... 44
8.2 Revision of the Design ...................................................................................................... 44
8.3 Selection of Materials ....................................................................................................... 45
9. Market Study for Suppliers ....................................................................................... 46
9.1 Benchmarking and Suppliers for Material Handling Trolley ................................................ 46
9.2 Evaluation of Suppliers and Outcomes .............................................................................. 46
10. Reconsideration of the Design.................................................................................. 48
11. Analysis and Result ................................................................................................. 50
12. Future Development ................................................................................................ 53
13. Conclusion ............................................................................................................... 56
14. Reference ................................................................................................................. 57
Appendix ....................................................................................................................... 60
10
Abbreviations
MHS - Material Handling System
VSM - Value Stream Mapping
TBU - Tread Brake Unit
PP - Poly-Propylene
HDPE - High Density Poly-Ethylene
SMH - Standard Man Hour
11
List of Figures
Figure 1: Flowchart of the Methodology ................................................................................. 18
Figure 2: Principles of MHS ...................................................................................................... 20
Figure 3: Current layout of workstations in TBU assembly line .............................................. 26
Figure 4: Current state of TBU assembly line (service brake).................................................. 29
Figure 5: Future state of TBU assembly line (service brake) ................................................... 30
Figure 6: Effects of current MHS .............................................................................................. 35
Figure 7: Current trolleys for TBU assembly line ..................................................................... 36
Figure 8: Current trolleys for TBU assembly lin ....................................................................... 36
Figure 9: Current workbench and bin trolley. ......................................................................... 37
Figure 10: New trolley design for MHS .................................................................................... 38
Figure 11: Shoe holder pallet ................................................................................................... 41
Figure 12: Housing pallet ......................................................................................................... 42
Figure 13: Parking unit pallet ................................................................................................... 43
Figure 14: Final design A .......................................................................................................... 48
Figure 15: Final design B .......................................................................................................... 48
Figure 16 : 2D drafting of final trolley design .......................................................................... 49
Figure 17: Current analysis of TBU assembly line (service brake) ........................................... 51
Figure 18: Future analysis of TBU assembly line (service brake) ............................................. 51
Figure 19: Before implementation of new MHS ...................................................................... 54
Figure 20: After implementation of new MHS ........................................................................ 54
12
List of Tables
Table 1: SMH time for service brake assembly ....................................................................... 25
Table 2: SMH time for parking brake assembly ...................................................................... 25
Table 3: MHS time study ......................................................................................................... 33
Table 4: Part list for shoe holder pallet .................................................................................... 41
Table 5: Parts list for housing pallet ........................................................................................ 42
Table 6: Parts list for parking unit pallet ................................................................................. 43
Table 7: Selection of materials ................................................................................................ 45
Table 8: Cost of trolley and pallets (in PP) in inr .................................................................... 46
Table 9: Cost of trolley and pallets (in HDPE) in inr .............................................................. 47
Table 10: Cost of trolley and pallets in sek.............................................................................. 47
13
1. Company Introduction
Faiveley Rail Transport India Limited is one among the leading manufacturer & exporter of
huge variety of train and metro rail products, developing trust for the customers by providing
the best quality with lot of comfort, managing best safety systems in the train, better
management of the electrical and electronic in the platform and also proving more services.
Faiveley Rail Transport India Limited Transports (FTIL) has become the global leader in terms
of designing and manufacturing of huge variety of products which are used in the rail industry
and the products that are included are like, advanced braking systems, doors and doors
electronic systems, brake panels, coupler systems and more electronic products. The industry
in India, the company manufacture and supplies the products like, brake control panels, air
conditioning product, and service & parking brakes and couplers as well for the country's rail
network. The company supplies their product to many customers across India, they are, Delhi
metro Rail Corporation, Kochi Metro Rail Corporation, Chennai Metro Rail Corporation and
also to Indian Railways. Most of the orders for the company is from the Delhi Metro Rail
Corporation. In addition to designing complex systems for the Indian rail market, the highly
trained team of engineers at FTIL also support their five global centres of competence for
various design and development works [1].
FTIL is the rail industry that works under the Faiveley Group, which is in France and also the
company’s headquarters and has their operations in around 13 countries across the world. On
30 November 2016, Wabtec Corporation acquired a 51% majority ownership of Faiveley
Transport, after completing the purchase of the Faiveley family’s stake. The strategic
combination of Wabtec and Faiveley Transport creates one of the world’s largest public rail
equipment companies, with revenues of about $4.2 billion and a presence in all key transit and
freight rail markets worldwide [1].
14
2. Background
The project is about strategically planning and improvising the production line and also
balancing the flow line by using line balancing techniques and implementing kaizen
(continuous improvement) in the production line. This particular thesis work is well suitable
for the Production Engineering and Basic Manufacturing Technology skill set.
2.1 Problem Description
The problem description of this particular Thesis Work is,
the company being a manufacturing company has a production line, which is used to assemble
of braking systems for normal trains and also for metro trains. We have an existing production
line but since it is not optimized, this thesis work would be focused on improving the efficiency
of the production line thus optimizing production. An important and challenging task in this
thesis work would be, kaizen or continuous improvement which tends to productivity
improvement. Although this is a challenging task, this is something that the company has been
working on and we would the thesis work to come up with specific methods as to how this
could be implemented and implement it in the company. Further the purpose of the thesis work
should completely have focused on the material handling systems which helps in enhancing
the productivity such that all the parts which are required for the particular workstation have
to be loaded in a single material handling trolley and it has to done for three major workstations
of the TBU line. Besides these mentioned areas for improvement of the thesis work, the work
has to come up with better solutions to improve the productivity. In addition to this the
company has designed the new layout in which the possible proposal ideas for the productivity
improvement can be proposed considering the appropriate production lean tools.
The major problems are as follows,
• The existing production line is not well organized.
• The Material Handling System (MHS) is not well planned and designed (i.e the parts
feed into the assembly line through material handling trolley)
• Too much of manual operations.
• Non-value-added time during the Material Handing has impact on productivity
thereby increases the time for assembly process.
15
2.2 Limitations
As this is the master thesis which is the most important course which added the value to the
master degree student to fulfil his degree that is linked to the master program course. A few
limitations have to be made in order for this project to be feasible one.
Productivity improvement in the bogie brakes assembly. There are three assembly lines in the
bogie brakes assembly which includes TBU assembly line, Actuators assembly line and
Calipers assembly line. The project is to enhance the productivity in the TBU assembly line by
improving the better material feeding system. The TBU assembly lines has five major assembly
workstations. They are, shoe holder assembly, housing assembly, parking assembly,
suspension/support-arm link assembly and main assembly. Then followed by the testing,
inspection, storage and dispatch. There are three variants of products that are assembled in this
line, (i) Indian Railways, (ii) Riyadh Metro and (iii) Kochi Metro (KMRL). The TBU assembly
line consists of assembling of two products such as (i) service brakes and (ii) parking brakes
for all the three variants. Limited to work with Thread Brake Unit (TBU) assembly line and
further again limited to work on Service TBU . Trolley Design for both Service & Parking TBU.
In current scenario, there are two to three operators working for the five major assemblies
depends on the demand needed such that one person has to do the entire job of these five major
assemblies that are mentioned above. In a day there are two shifts, each shift has 8 hours in
which 45 minutes is for lunch and tea breaks. Each individual operator is managing to assemble
two complete TBU assembly in one shift. Whereas the actual plan is to complete 10 numbers
but they are assembling only 4 or 6 per shift based on the man power. The operators are walking
around 10 to 20 seconds for picking up the one part which is required for the assembly as the
trolleys are placed 3 to 3.5 meters from the workstation. On the whole, the operators are
walking around 15 minutes approximately for the material handling. Also, there are mixed up
of parts in the trolleys for different workstations. The reason behind this is, few parts are
coming from the paint shop and few parts are coming from the stores and the parts are of
different shapes and sizes. Then they are brought in separate trolley near to the workstation.
Each particular assembly consists of many small child parts which are stored in the bins in bin
16
trolley in front of the workstation. The tools required for the assembly operations are kept in a
rack below to the workbench.
For this case, the engineers in the process engineering development has designed one new
layout and in which they need this thesis work to be more focused on material feeding system
that helps in productivity improvement. In the new layout, the trolley is approximately around
0.8 meters from each workstation. The constraints for the new trolley design should be in such
a manner that, one trolley should hold almost all 10 complete assemblies’ A and B class parts
which are required for the appropriate workstation and the trolley should be more flexible and
easy for the operators to handle ergonomically and perform their job easily. Also, the cost of
the trolley should be very cost effective.
As mentioned, there are several different sizes of the parts which have to be loaded in the
material handling trolley. In this project, the focus is limited to develop the new material
handing trolley design for 3 major workstations. Apparently the productivity improvement
through the better solutions of material handling system includes a lot of processes and parts,
the focus will be towards the most time consuming processes which comes under non-value
activity such as walking and searching of parts. These processes are mainly concerning the
very basic processes of the activities carried out in the assembly line. Therefore, this project
focuses mainly on above mentioned parts with the given constraints.
2.3 Problems Identified in The Assembly Line
The detail study of the whole TBU assembly line and also all the possible details necessary for
the material handling system was done successfully. From the above mentioned case study,
there are many risks and problems are identified and also got the feedbacks from the operator
such that the risks they are facing with the current material handling trolleys.
The following risks and problems that are identified in the assembly flow-line are as
follows,
• The parts are loaded in the three different trolleys like, painted parts in one trolley,
other stores parts in another two trolleys and child parts in bin trolleys. By this there
17
is no standard trolleys for particular workstation and operators take more time in
searching of parts to pick up.
• Most of the operations are performed manually which tends to very time
consuming.
• The material feeding system is not standardized and its time consuming.
• Non-value activities such as walking and searching for tools & parts.
• Picking up the tools are in the rack below the workbench which is not ergonomic.
• Lifting of heavy parts manually from the major 3 workstations to the main assembly
workstation which is also not ergonomic.
• In some cases, if the unavailability of parts which is required for the appropriate
workstation then the entire line stops as the whole assembly operation is done by a
single operator.
• Child parts in bin trolleys are not loaded with sequence of the assembly order which
results in confusion and time consuming.
• MHS is not standard and also not flexible.
18
3. Methodology
This is the methodology to be followed for the successful completion of the project.
Figure 1: Flowchart of the Methodology
19
4. Literature Review
The literatures which are closely related to this thesis is taken as reference and also those
literature helped to finish this challenging thesis work in efficient way.
4.1 Material Handling System
Surinder Kumar et al [2] examined about the material handling system (MHS) and in which it
is clearly seen that the material handling system (MHS) in the assembly line plays a vital role
among the performance and the productivity of the assembly line. So that, MHS should be
properly planned and designed and also it should be placed at right time, right sequence and so
on.
Art Smalley [3] investigated about the Toyota's New Material-Handling System that shows
TPS's Flexibility states that Toyota Motor Corporation has introduced a new material-handling
system based on kitting to reduce complexity and improve quality in assembly areas. Also the
kiting concept helps in minimizing three-forth the time of the MHS.
Seran Akincilar et al [4] have planned to design an in-plant MHS that could be more ergonomic
and improves production efficiency. In recent modern industries, the scenario is that in order
to stay competitive in the industrial market, companies need to achieve the quality in both
customer satisfaction and cost reduction in production operations. Material Handling Systems
(MHS) is the place to achieve this challenging goal, as such it have the direct impact on
production.
Vieira, G. B. B. et al [5] focused on improvements in internal materials handling management,
approaching the high profile company like the automotive industry. Materials handling system
and the production flow are well co-related in general. Due to this, transit time, resources usage,
and service levels were having high impact through MHS. The authors’ objectives were,
evaluation of the impact based on materials handling management over the internal customers’
perceptions of cost, safety, service, agility and satisfaction which is a systematic approach.
20
Johansson [6] analysed about the materials feeding has the important role in identifying the
right principle, and which will suits well for feeding the materials to a workstation or an
assembly line. have categorised some various principles upon feeding materials to a
workstation or an assembly line which includes continuous supply, batch supply and kitting.
These are shown in Figure 1 as follows, and the categorised principles are based on,
• Selection of part numbers or all part numbers
• Sorted by part numbers or assembly object.
Figure 2: Principles of MHS
4.2 Continuous Supply
Johansson [6] gave the description about continuous supply such that the materials are
distributed to the assembly stations in units suitable for handling for an assembly operation and
where these units are replaced when they are empty. There is no replacements of different part
numbers rather than that all parts are available at the assembly station at every time for the
assembly of products. Reloading of parts are often done by store person, either in bins, or in
trolleys.
4.3 Batch Supply
Johansson [6] gave the brief description on Batch Supply such that the materials are supplied
for various products to be assembled. The batch of materials can be a batch of required part
numbers or in fixed batch quantities. Apparently it differs from the continuous supply such that
only less part numbers which are required for the batch assembly have to be loaded and stored
near the work station.
BATCH CONTINUOUS
KITTING -
SELECTION OF PART NUMBERS
SORTED BY PART NUMBER
ALL PART NUMBERS
SORTED BY ASSEMBLY OBJECT
21
4.4 Kitting
In most of production/manufacturing companies, the loading of parts required for sub-
assemblies and major assemblies operation to the shop floor in pre-determined numbers that
are placed near workstation either in bins or trolleys is known as kitting.
Johansson [6] view on kitting states that for one complete assembled product, the parts which
are required for that product will be collected and kept as a kitting parts near the work station.
Also the kitting is completely different from the batch supply and also kitting helps in
productivity improvement. Further the kitting is then discussed in detail.
Jimesh M. Gajjar [7] demonstrated that the material feeding/handling principle of kitting
across the in-plant the material supply in the assembly line. With this principle, parts are loaded
very close to the appropriate workstation to perform the assembly operations in pre-sorted kits,
such that the each kit containing parts for one complete assembly of the part of that particular
workstation.
Johansson [8] examined the kiting concept in which a kitting process is well-suited for
parallelized flow in an assembly line, product that assembled with many part numbers, quality
assurance products and parts of high value.
Ding et al [9] describes the concept of kitting which plays a key role in industries which
includes electronics industry, which co-relates with small parts and performs assembly
operations repeatedly, JIT-system which manages larger parts to be assembled has more
benefits from kitting concept.
4.5 Benefits of kitting
Bozer Y.A. et al [10-13] analysed about the benefits of kiting. The kitting the most effective
principle in MHS has some benefits which are as follows:
• Saves shop-floor space in manufacturing/production plant
• Reduces assembly operators’ walking and searching times which are non-value added
activities
22
• Controls production time at every workstations in assembly line and reduces Work In
Progress (WIP).
• Reduces or facilitates material delivery to workstations by eliminating the need to
supply individual component containers.
• Increases product quality, reducing the frequency of wrong parts in the end product or
missing parts in the end product.
• By reducing operators search time for parts through kitting which becomes very flexible
for assembly operations and makes easy for training the new employees.
4.6 Palletizing
In manufacturing/production industries, the loading and unloading of parts or components to
or from pallets are basically known as palletizing.
Rahul. V. Mahajan et al [14] explained about the palletizing systems plays a key role in flexible
way of material handling system to enhance productivity. Palletizing system is a concept which
is designed concerning the performance and flexibility of the productivity in the
assembly/manufacturing line. In recent scenario, palletizing system and its installation and then
its integration with material handling system within the in-plant are the parameters to concern
highly for the good industrial engineer.
Adsavakulchai S (2014) [15] describes that palletizing play a vital role in
manufacturing/production industries in flexible transportation in shop-floor. Palletizing helps
to enhance fast transport of parts and reduces transport cost and helps to optimize space in
shop-floor and also carries heavy load capacity.
4.7 Polymers (HDPE Vs PP)
Sihama E. Salih et al [16] has investigated various effects of the blend ratio of HDPE : PP and
LDPE : PP with its mechanical properties and the end results of this particular investigation
are: (i) The mechanical properties of HDPE : PP blends resulted with the higher values when
compared to mechanical properties of LDPE : PP blends. 2) Mechanical properties that
includes Tensile strength, Fracture stress, Young modulus, Bending modulus, creep modulus
23
and hardness of both HDPE : PP and LDPE : PP blend are clearly seen that its mechanical
properties increases based on the increment of PP weight percentage. But there is the
exceptional on elongation which seems to be decreased.
Barbara O. Calcagno et al [17] described that the HDPE and PP polymers are basically
processed by injection moulding. They are highly useful in many applications and it has a wide
range of industrial and household applications. Polypropylene (PP) and high-density
polyethylene (HDPE) are known as semi-crystalline polymers which are widely used in
industrial applications such as packaging, coatings, composite materials, and house and
automobile functional parts. HDPE generally a tough polymer with low strength and stiffness,
high elongation at break and also less dense than other polymers. Coming to PP, the properties
of PP reveals that it has high dynamic loading capacity and higher strength and stiffness
compared to HDPE.
24
5. Bogie Brakes
All brakes which are used in railways are generally air brakes. They use fail-safe brake system
(even the brake fails it manage to apply the brake). Different types of bogie brakes, in that
1)TBU (Tread brake unit)
2)WMD (Wheel mounted disc brake)
3)AMD (Axle mounted disc brake)
4)BMBE (Bogie mounted brake equipment)
5.1 TBU Assembly
TBU work based on the Pneumatic - Mechanical operated brakes (A mechanism which
pushes the brake shoe to tread of wheels driven by compressed air). It is based on fail brake
system. One bogie consists of 8 Service TBU and other 4 are Parking TBU. It has the
capability for the speed of 120 kmph.
Productivity improvement in the TBU assembly line is the main goal of this thesis work. There
are three assembly lines in the bogie brakes assembly which includes TBU assembly line,
Actuators assembly line and Calipers assembly line. The project is to enhance the productivity
in the TBU assembly line by improving the better material feeding system. Then the TBU is
categorized into two types of brakes such as service brake and parking brake. The TBU lines
has four major assemblies with three workstations. The four major assemblies are, shoe holder
assembly, housing assembly, suspension/support-arm link assembly and main assembly. The
above mentioned four assemblies are combined to for TBU service brake and for parking brake
there is one more workstation is included and apparently the assembly so called parking unit
assembly. Then the assembly line of TBU is followed by the testing, finishing work, inspection,
package and dispatch. There are three variants of products that are assembled in this TBU
assembly line, which are as follows
(i) Indian Railways,
(ii) Riyadh Metro and
(iii) Kochi Metro (KMRL).
As discussed above, the TBU line consists of assembling of two products such as service brakes
and parking brakes which are same for all the three variants. The Standard Man Hour (SMH)
25
for the complete service and parking brake of TBU unit assembly are tabulated as shown below.
For all three variants, the SMH time are found to be same.
The SMH time for the service brake of TBU unit assembly is done with average time study
which is tabulated in table 1 as follows.
SL NO TASK SMH (MIN)
1 Housing Assembly 110
2 Shoe Holder Assembly 70
3 Main Assembly 35
4 Testing 45
5 Finishing Work 30
6 Inspection 10
Table 1: SMH time for service brake assembly
The SMH time for the parking brake of TBU unit assembly is done with average time study
which is tabulated in table 2 as follows.
SL NO TASK SMH (MIN)
1 Housing Assembly 110
2 Parking Unit Assembly 80
3 Shoe Holder Assembly 70
4 Main Assembly 35
5 Testing 45
6 Finishing Work 30
7 Inspection 10
Table 2: SMH time for parking brake assembly
26
The current layout of workstations in TBU assembly line is shown in figure 3. It is seen clearly
that the assembly line consists of 4 workstations and main assembly fixture where main
assembly is done and a test rig. The yellow checked box denotes the bin trolley and KT denotes
the Kanban trolley which feeds the parts to all work stations for the TBU assembly line. And
there is one big rectangular box denoted by KT near the storage area is the trolley only used
for suspension link arm part for the Indian Railways which is used in workstation 1. On the
whole, the layout is not well designed and optimized and therefore the company also needs
some improvement over this issue.
Figure 3: Current layout of workstations in TBU assembly line
27
6. Production Lean Tools
Many production lean tools like VSM, 5S and so on helps in to do the possible improvements in the assembly line and are as follows.
6.1 Value Stream Mapping
VSM is the production lean tool to find out the value and non-value activities in the production flow and helps in eliminating the wastes which improves productivity. It is done for only Service TBU assembly.
6.1.1 Current State
The company faces a number of challenges with their current production layout. To enhance
their profitable production of TBU line assembly some of the problems need to be identified
and then have to be eliminated. The problems are as follow.
• Not standard material handling system
• The customer orders are pushed through the production control system. Further, which
results in increase with the lead-times.
• Sometimes parts are not available in stock when the order comes in and has to be
ordered from the supplier, further increase with the lead-times.
• There is no proper organization of shop floor. Operators often can’t find the parts
needed, and WIP are kept near the shop floor. These WIP occupies more floor space.
6.1.2 Analysis of Current State
The company mainly focus on MHS which has the high impact on productivity growth. And
the assembly flow line seems to be push system. There are many inventories before the starting
of assembly line and also before inspection, packing and shipping processes. On the whole the
waiting time seems to be 1 to almost 3 days. The total lead time for each product is sound to
be under 4 days and 17.5 minutes (i.e 0.5 minutes = 30 seconds), while the time for which
value is added to the product is found to be 390 minutes. (Note: two operators are working the
same assembly process for shoe holder, housing and main assemblies)
28
6.1.3 Proposed Improvements
As this thesis work is focused more on MHS, the new trolley is advisable to design with kitting
of parts in the pallets. And also kitting of child parts that is C class parts are also can be made
as kitting type so as to improve productivity which in turn reduces cycle time and also reduces
MHS time. The parts stocks will be managed by the production control through the new
automatic reorder technology system, with the safety inventory parts that lasts for two working
days. Hence, there will be a safety parts which will be on stock that manages till the reorder
time. Production control will send orders each morning to all the workstations as earlier and
finally the finished products are shipped at the end of 2nd day, so as to manage transportation
cost.
6.1.4 Result
On the whole, by the implementation of these proposed improvements the lead time can be
reduced nearly 4 days and 17.5 minutes to 1day and 17.5 minutes approximately (i.e 0.5
minutes = 30 seconds). By the implementation of new material handling system, the company
gets profit by improving their productivity which shown in the chapter of analysis. By the new
MHS, the cycle time can be reduced from 390 minutes to 380 minutes by eliminating few nan-
value added activities. The non-value activities which includes the operators walking and
searching of parts time and so on.
The current state map and future state map and done successfully using VSM tool in Microsoft
Visio and are shown in figures 4 and 5 as follows.
29
Figure 4: Current state of TBU assembly line (service brake)
PROD
UCTIO
N CON
TROL
SUPP
LIER
CUST
OMER
SHOW
HOLD
ER
ASSE
MBLY
HOUS
ING A
SSEMB
LYMA
IN AS
SEMB
LYTE
STING
FINISH
ING W
ORK
INSPE
CTIO
NPA
CKIN
G
C/T =
70 M
INS
AVAIL
ABILIT
Y = 0.
95
OPER
ATOR
S = 1
MHS T
IME =
6 MI
NS
C/T =
110 M
INS
AVAIL
ABILIT
Y = 0.
90
OPER
ATOR
S = 1
MHS T
IME =
7 MI
NS
C/T =
35 M
INS
AVAIL
ABILIT
Y = 0.
95
OPER
ATOR
S = 1
MHS T
IME =
2 MI
NS
C/T =
45 M
INS
AVAIL
ABILIT
Y = 0.
95
OPER
ATOR
S = 1
C/T =
30 M
INS
AVAIL
ABILIT
Y = 0.
95
OPER
ATOR
S = 1
C/T =
10 M
INS
AVAIL
ABILIT
Y = 0.
95
OPER
ATOR
S = 1
C/T =
300 M
INS
AVAIL
ABILIT
Y = 0.
90
OPER
ATOR
S = 2
C/T =
180 M
INS
AVAIL
ABILIT
Y = 0.
95
OPER
ATOR
S = 3
35 M
INS
17.5
MINS
55MI
NS17
.5 MI
NS22
.5 MI
NS
12 HO
URS
15 M
INS
1 DAY
5 MIN
S
1 DAY
150 M
INS
4 DAY
S 17.5
MIN
UTES
390 M
INS
90 M
INS
1 DAY
12 HO
URS
DAILY
SCHE
DULE
ORDE
RS FR
OM
CUST
OMER
ORD
ER
DAILY
CU
STOM
ER
ORDE
RS
1 PIEC
E
CURR
ENT S
TATE
MAP
1 DAY
2 DAY
S2 D
AYS
SHIPP
ING
35 M
INS
17.5
MINS
55MI
NS17
.5 MI
NS22
.5 MI
NS
12 HO
URS
15 M
INS
1 DAY
5 MIN
S
1 DAY
150 M
INS
4 DAY
S 17.5
MIN
UTES
390 M
INS
90 M
INS
1 DAY
12 HO
URS
30
Figure 5: Future state of TBU assembly line (service brake)
PROD
UCTIO
N CON
TROL
SUPP
LIER
CUST
OMER
SHOW
HOLD
ER
ASSE
MBLY
HOUS
ING A
SSEMB
LYMA
IN AS
SEMB
LYTE
STING
FINISH
ING W
ORK
INSPE
CTIO
NPA
CKIN
G
C/T =
65 M
INS
AVAIL
ABILIT
Y = 0.
95
OPER
ATOR
S = 1
MHS T
IME =
1 MI
NS
C/T =
105 M
INS
AVAIL
ABILIT
Y = 0.
90
OPER
ATOR
S = 1
MHS T
IME =
2 MI
NS
C/T =
45 M
INS
AVAIL
ABILIT
Y = 0.
95
OPER
ATOR
S = 1
MHS T
IME =
2 MI
NS
C/T =
45 M
INS
AVAIL
ABILIT
Y = 0.
95
OPER
ATOR
S = 1
C/T =
30 M
INS
AVAIL
ABILIT
Y = 0.
95
OPER
ATOR
S = 1
C/T =
10 M
INS
AVAIL
ABILIT
Y = 0.
95
OPER
ATOR
S = 1
C/T =
300 M
INS
AVAIL
ABILIT
Y = 0.
90
OPER
ATOR
S = 2
C/T =
180 M
INS
AVAIL
ABILIT
Y = 0.
95
OPER
ATOR
S = 3
32.5
MINS
17.5
MINS
52.5
MINS
17.5
MINS
22.5
MINS
15 M
INS
5 MIN
S
1 day
150 M
INS
1 DAY
17.5
MINU
TES
385 M
INUT
ES90
MIN
S
DAILY
SCHE
DULE
ORDE
RS W
HEN
REOR
DER P
OINT
RE
ACHE
D
DAILY
CU
STOM
ER
ORDE
RS
1 PIEC
E
FUTU
RE ST
ATE M
AP
SHIPP
ING
1 day
32.5
MINS
17.5
MINS
52.5
MINS
17.5
MINS
22.5
MINS
15 M
INS
5 MIN
S
1 day
150 M
INS
1 DAY
17.5
MINU
TES
385 M
INUT
ES90
MIN
S
31
6.2 5S
Yamagar A.C [18] studied about a lean tool 5S and its importance. 5S is a system which helps
to reduce waste and optimize productivity through maintaining an clean, safe, standard,
organized workplace and helpful to achieve the consistent operational results. The 5S is
generally defined as Sort(Seiri), Set in Order(Seiton), Shine (Seiso), Standardize (Seiketsu),
and Sustain (Shitsuke), provide a methodology for organizing, cleaning, developing, and
sustaining a productive and well organized work environment. 5S encourages workers to
improve their work standard and provides them the knowledge in how to reduce waste,
downtime, and inventory due to process failure and lack of parts. 5S helps the line to sort and
set the process in sequence and use standard procedures and make a clean environment around
the workbench and thereby improve the productivity.
6.3 Kaizen
Kitano et al [19] studied about the continuous improvement and explained about its importance
in industries. The Japanese word for continuous improvement is mostly termed as kaizen.
Kaizen is most frequently used where there is the essential need for the continuous
improvement. From the Japanese work ‘kai’ which means ‘change’ and ‘zen’ means good and
on the whole it means to the term known as improvement. Masaaki Imai [20] elaborates that
Kaizen is an essential needs required always for the MHS which is the key role for the
production growth. There are many kaizen proposals for this assembly line such as
improvement with the trolley, also improvement with the workbench, using fixtures for the
workstation for easy operation, automatic torque tool can be used and so on.
32
6.4 Toyota Way 14 Principles
Liker [21] gave the summary on The Toyota Way 14 Principles, in that the principle 6 is more
helpful to perform standard trolley and pallet designs in new MHS of this thesis work. Principle
6 -‘Standardized tasks and processes are the foundation for continuous improvement and
employee empowerment’. With this help the principle 6 the standard procedure for MHS and
standard design of trolley size and pallet size and then it should be documented which will be
beneficial for new employees to work easily.
33
7. Current Material Handling/Feeding System
The material handling/feeding system is very much important for the operators who are
working in the assembly line. Also the material handling system plays a vital role in
productivity improvement which should be made easy for the operators in performing their
jobs. The current material handling system, in which the trolleys are placed is found out to be
approximately 2.5 to 3 metres from the the workstation and the bin trolleys are placed in front
of the workstation which is easy reach of the operators hands. The parts are categorised into
three class such as A, B and C class parts. The A class parts are the painted parts, those are
kept in a separate trolley (1 trolley) and B class parts are the parts from the stores, those are
kept in another separate trolley (2 trolleys) and finally the child parts know as C class parts are
also from the stores, those are kept in bin trolley (2 bin trolleys). The above mentioned parts
are not kept according to the particular workstation rather than that they are kept in accordance
to A, B and C class parts. Because of this there were confusion in identifying the parts and also
it affects the performance and the productivity of the TBU assembly line.
The MHS time study is on average and tabulated as shown in table 3 below. A simple stop
watch is used for the study. It is noted visually that picking one part from the trolley and placing
it in the workstation, the operator takes approximately 15 to 20 seconds.
Sl No Workstation MHS - time
(Trolley) in mins
MHS – time (Bin
trolley) in mins
Total MHS
time in mins
1 Shoe holder assembly 5 1.2 6.2
2 Housing assembly 4.33 3 7.33
3 Parking Unit assembly 3.67 3 6.67
Table 3: MHS time study
This thesis work helps in designing the trolley according to the specific workstation and also
helps in kitting of the parts which helps in improving the performance and the productivity of
the TBU assembly line.
34
7.1 Effects Of Current Material Feeding System
From the data that were collected during thesis work is to analyse the current material feeding
system in assembly line. Parts quantity, inventory plans are the very useful data which became
easy for analysis. The effects of current material feeding system are described and shown in
figure 6 below.
Part Shortages in MHS is defined as the major issue in the assembly line being affected was
because of lack of getting right part at right time. This is due to the parameters like, supplier
delays, improper inventory control.
Poor Kanban Quantity in MHS is defined as the storage is not managed in the proper balanced
condition. Some parts will be stay fixed in the inventory at line side. This tends to waste
according to lean production system.
Unstandardized Work in MHS is defined as the parts picking is done manually by the operators,
they started collecting parts in batches required for one shift and this affected their standard
work procedure which in turn leads to affect the production.
Jimesh M. Gajjar [7] gives the review on material handling system (MHS) in the shop floor.
As continuous supply from stores is being practiced, all parts were loaded and stored at line
side such that even few parts were used less frequently. This lead to occupy more shop floor
space. This results in time consuming activity for the operators to walk and search for parts
required for assembly operation. Therefore, there is no 5s is strictly practiced in the line. This
affects the production rate apparently. Also the current MHS is tough to handle by the operators
which is also not in the ergonomic way
35
Figure 6: Effects of current MHS
7.2 Current Trolley
Parts from stores are known as B class parts and parts from the paint shop are known as A,
class parts are loaded in the tow different trolleys as shown in the figures 7 and 8 below. These
are the parts which are required for all work stations in the TBU assembly line. But
unfortunately, the parts are not kept according to the workstation which further tends to make
the confusion and searching of parts for the operators to work with. Also, this trolley is not
standardized which tends to the lot of time consuming for the production.
EFFECTS OF CURRENT
MHS
NO STANDARD RULES TO FOLLOW
TOUGH TO HANDLE
NOT ERGONOMIC
POOR KANBAN
QUANTITY
PARTS SHORTAGE
36
Figure 7: Current trolleys for TBU assembly line
Figure 8: Current trolleys for TBU assembly lin
7.3 Current Workbench and Bin trolley
The workbench and the bin trolley for the TBU assembly line is show in figure 9. The
workbench is not much ergonomic for the worker to perform their job as there are no fixtures
to hold the parts in one position. Also, the tools are kept under the rack below the workbench
as shown in figure which is also not ergonomic and tends to time consuming with the handling
of these tools. Further, it results in affecting the productivity of the TBU assembly line.
37
Coming to bin trolleys, the child parts are not kept in the sequence order according to the
assembly instruction and they are all meshed up which results in confusion for the operators to
work with that leads to time consuming in production and affects the productivity.
Figure 9: Current workbench and bin trolley.
38
7.4 CAD Modelling
Figure 10: New trolley design for MHS
The new trolley is design shown in figure 10 was designed according to the given constraints.
The constraints for the new trolley design should be designed in such a manner that, one trolley
should hold almost all 10 complete assembly parts which are required for the appropriate
workstation and the trolley should be more flexible and easy for the operators to handle and
perform their job. Also, the cost of the trolley should be very cost effective.
For which the design ends up with a new concept of kitting of the parts and store it in one pallet
such that one complete assembly can be done in that particular workstation. Also, the new
trolley design can able to hold 12 complete assembly parts. Considering there are 12 numbers
39
of complete TBU assembly part is required for the one bogie and also the design has meet that
requirements successfully. From the above design two assemblies are merged to a single
workstation which is shoe holder assembly and suspension/support-arm assembly. The design
of the new trolley is of standard size for the three-assembly workstation such as shoe holder
assembly, housing assembly and parking unit assembly. Also, the pallet design is of standard
size and only the partitions in the pallets are different for different assembly workstation.
The following picture gives the clear pictorial representation of the new trolley design. The
design and assembly is done using CatiaV5 and Pro-E Creo software. The new trolley design
has 4 racks and in which three pallets can be placed in one rack and totally there will be 12
pallets placed in the trolley. The yellow color pins are known as safety stopper which ensures
the pallets to be supported in its place.
7.5 Kitting Concept
The kitting plays an important role in this thesis work which has great impacts on MHS, as the
existing MHS of the assembly line is not flexible and it is very time consuming. Hence, the
kitting of parts has more advantageous things for the operator as well for the productivity
improvement.
In this thesis work, the kitting of parts are made based on the requirement of parts of that
specific workstation. Now the both A and B class parts necessary for the assembly of the
specific workstation are kitted and placed in the pallets and then the pallets are placed in the
appropriate trolleys.
7.6 Palletizing Concept
The pallets are designed in such a way that it holds all the A and B class parts of all three
variants mention earlier. The pallets are designed using a software CatiaV5. The pallets also
have some design constraints such that it should hold all the parts for one complete assembly
for particular workstation. Another constraint is that the pallets should be be designed such that
it should hold both the parts of normal train and metro trains, as the size of the parts are
40
different. For instance, one pallet is designed in a such a manner that it holds all the A and B
class parts for that particular workstation and also for both normal trains and metro trains.
The pallets for easy assembly workstation are shown below in figures and apparently the parts
that the pallets should holds are tabulated below each figure. Also, the partitions in the pallets
have some design constraints, that it should be 3mm thickness minimum.
41
Shoe Holder Pallet is shown in figure 11 below and the parts that it should hold are listed in
the table 4 below as follows.
Figure 11: Shoe holder pallet
SL NO PART NAME QUANTITY
1 Shoe holder part 1
2 Cradle 1
3 Friction spring 1
4 Spindle 1
5 Leaf spring 1
6 Shoe holder cover 1
7 Screws 4
8 Suspension link/Support arm 2
9 Bearing 1 2
10 Bearing 2 2
11 O-ring 4
12 Sleeve 1 1
13 Sleeve 2 1
14 Flexible arm 2
15 Bellow 1
Table 4: Part list for shoe holder pallet
42
Housing Pallet is shown in figure 12 below and the parts that it should hold are listed in the
table 5 below as follows.
Figure 12: Housing pallet
Sl.no Part name Quantity
1 Housing part 1
2 Return spring 1
3 Control socket 1
4 Liner 1
5 Piston spring 1
6 SB Cover 1
7 Spring sleeve 1
8 Bush sleeve 1
9 Yoke 1
10 Bearing pin 1
11 Piston 1
12 Slide ring 1
13 Packing cup 1
Table 5: Parts list for housing pallet
43
Parking Unit Pallet is shown in figure 13 below and the parts that it should hold are listed in
the table 6 below as follows.
Figure 13: Parking unit pallet
SL.NO Part name Quantity
1 Parking unit cover 1
2 Intermediate housing 1
3 Ratchet wheel unit 1
4 Ratchet nut 1
5 Piston 1
6 Spindle unit 1
7 Liner 1
8 Stop sleeve 1
9 Guide sleeve 1
10 Spring outer 1
11 Spring inner 1
Table 6: Parts list for parking unit pallet
44
8. Discussion
Once the new trolley design model and pallets design model are completed, the next step is to
get the feedbacks from the line manager, line supervisor and the line operators of the Bogie
Brake assembly. And also made the literature study for the selection of material for the new
trolley design and the pallets design. Finally got the feedbacks for the material selection for the
newly designed trolley.
8.1 Operators Feedback
The supervisor and the operators were satisfied with the new trolley design and also with the
new concepts of kitting and palletizing. They found it is very flexible MHS which makes them
stress relief from searching of parts and also in avoiding confusion while performing their job.
But they gave few feedbacks which is posted in the appendix. Most of the feedbacks are stated
that the parts for that particular workstation should not miss. Also they were asked for removal
of the suspension link table and that part should be included in the shoe holder pallets. Further
they suggested to select long life materials for the pallets
.
8.2 Revision of the Design
The revision of the trolley is made as per the feedbacks of the operators and the line supervisor.
They were asked for the removal of the suspension arm table and that part to be come within
the pallet of shoe-holder which will be more helpful for them and also it tends to provide much
more space/place in the TBU assembly-line. On the whole, the operators essentially need the
kitting of parts for major parts and also for the child parts. This requisitions are asked due to
they find lot of confusions in searching for the components and it is not flexible for them to
work. Finally, this thesis work gives the better solutions for their requisitions and also some of
the feedbacks. Hence, the new trolley and also the pallets are designed as per the operators’
essential need and gave the good result which is more ergonomic and flexible for the operators
to work. Thus, this new designed trolley completely avoids confusion during work and thereby
help in productivity improvement.
45
8.3 Selection of Materials
The next step is selection of materials for the new trolley design. The following table shown
below shows that the components required for the new trolley design and also the appropriate
materials that can be used for the mentioned components as per the constraints. The material
that are using for this newly designed trolley should have more durability and also must be cost
effective.
Components Required Materials
Body of the Trolley Mild Steel
Wheels 6-inches Heavy Duty Polyurethane
Pallets Aluminum alloy or Magnesium alloy or
Poly-propylene or High density
polyethylene.
Pins/Stopper High Density Polyethylene
Handle Mild Steel
Table 7: Selection of materials
Aa discussed above the selection of material for the pallets came to the end with Poly-
propylene(PP) and High-Density Polyethylene(HDP). PP and HDP are chosen such that the
pallets should hold the heavy loads of the components/parts and also it should be more rigid.
And for rest of the components are same as shown in the table 7.
46
9. Market Study for Suppliers
The market analysis has the high impact and plays an important role before adopting any new
technique or developments in the manufacturing/production industries. The market study of
this particular thesis work was done by analyzing the MANIKANDAN ENTERPRISES and
also other suppliers those who are producing and supplying bins, trolleys, pallets and so on for
industrial purposes. The market research helped in identifying few similar suppliers those who
are producing the things which are beneficial for industrial purposes.
9.1 Benchmarking and Suppliers for Material Handling Trolley
The easy and simple way of understanding about benchmarking is “Improving ourselves by
learning the best qualities from other persons”. The next task in this thesis work is to do
benchmarking for the suppliers who are producing items for industrial purposes. Benchmarked
the supplier known as Manikandan Enterprises who is the leading supplier for this company.
The other suppliers are also found with the benchmark of the Manikandan Enterprises supplier.
And found another superior supplier similar to above mentioned supplier named Right
Engineers.
9.2 Evaluation of Suppliers and Outcomes
The suppliers who are well capable to do this new trolley design are contacted and then had
the meeting with those appropriate suppliers in order to explain the design and finally asked
for the quotations. The quotations from different suppliers are collected and thereby reviewed
in such a manner that it should be cost effective. The above-mentioned quotations are posted
in the appendix.
SL NO SUPPLIER TROLLEY
COST IN INR
PALLET (PP)
COST IN INR
TOTAL COST
IN INR
1 MANIKANDAN 14690 2750 * 12NOS 47,690
2 RIGHT ENGG 15500 3500 * 12NOS 57,500
Table 8: Cost of trolley and pallets (in PP) in inr
47
SL NO SUPPLIER TROLLEY
COST IN INR
PALLET
(HDPE) COST
IN INR
TOTAL COST
IN INR
1 MANIKANDAN 14690 2500 * 12 NOS 44,690
2 RIGHT ENGG 15500 3000 * 12 NOS 51,500
Table 9: Cost of trolley and pallets (in HDPE) in inr
SL NO SUPPLIER TOTAL COS IN
SEK (FOR PP)
TOTAL COST IN
SEK (FOR HDPE)
1 MANIKANDAN 6358 5958
2 RIGHT ENGG 7666 6866
Table 10: Cost of trolley and pallets in sek
On the whole, from the above tables 8, 9 and 10 the Manikandan Enterprises supplier seems to
be very good and cost effective. Hence, the quotation of Manikandan Enterprises supplier is
recommended to give the purchase order for the newly designed trolley and pallets.
48
10. Reconsideration of the Design
Figure 14: Final design A
Figure 15: Final design B
49
As the cost of the newly design trolley is very high, hence the reconsideration of the trolley
design was made with the reduction of materials where-ever it is possible to make it cost
effective. Finally, the new design again end up with the L-angle plate can be used replacing
the bracket and plate, and then the centre rod is replaced with two plates in order to with-stand
the whole trolley when it is loaded fully. Also the stopper is kept at the sides with the stopper
holder such that it can be handled easily for loading and unloading of the pallets. And the base
plate thickness of pallet is 8mm. The final design of the trolley is shown in figures 14 and 15.
The finally design of the trolley is shown in 2D drawing with drafting which is shown in figure
16 below.
Figure 16 : 2D drafting of final trolley design
50
11. Analysis and Result
The analysis was done for the process flow of service TBU using the software known as
ExtendSim9. With the help of above mentioned software the simulation was done in order to
find of how much the productivity will be improve by the successful implementation of newly
designed trolley for the MHS.
On consideration of existing MHS time, the new designed trolley with kitting and palletizing
concepts helps in improvement in MHS. In the newly designed trolley, there will be only one
heavy loaded parts which should be handle manually and then the whole pallet can be placed
on the specified workbench. By this the MHS will become easy and fast with much more time
saving and thereby enhances the productivity. The analysis is done by proposing that the trolley
should be within 1 meter far from the workstations and also the child parts should be in
sequential order in the bin trolleys with the kitting of the child parts for each subassemblies.
Finally, the result will be hardly less than 1 minute for the MHS.
For the analysis, considering how much will one operator will able to produce TBU unit
assembly annually with the consideration of 6 working days in a week for one shift which is 8
hours of working/shift. Also analysis is done efficiently with the support of VSM data done
earlier.
In the current state, one operator will end up with the assembly of totally 600 units
approximately annually whereas in the future state he will be able to produce 628 units annually
which is more 28 products additionally. With the comparison mentioned above the productivity
is improved through the material feeding system. There are 2 operators are working, therefore,
in current state they are producing 1200 products and in the future it will be 1256 products
annually which is more 56 products additionally.
The analysis done using ExtendSim9 is shown in Figure 17 and 18 below.
51
Figure 17: Current analysis of TBU assembly line (service brake)
Figure 18: Future analysis of TBU assembly line (service brake)
52
. Finally, it adds more benefits and profits for the company. The results are as follows,
• On the whole, by this thesis work the company can increase the productivity from 1200
to 1254 products annually.
• The MHS for the Shoe Holder assembly and Housing assembly is reduced by 5 minutes
on average.
• As MHS is the part of the cycle time, % minutes of SMH time is saved which enhances
the productivity.
• About 4 to 5 minutes of walking time and searching of parts which are the non-value
added activity is decreased.
• With the VSM, cycle time is saved up-to 5 minutes for shoe holder and housing
assemblies.
• With the VSM, the current state non-value-added time is about 4 days 17.5 minutes (i.e.
0.5 minutes = 30 seconds) which is reduced to 1 day 17.5 minutes in future state.
53
12. Future Development
The future development for after implementation of this particular thesis work in the assembly
line are as follows in order for productivity improvement.
• Picking and placing of pallets can be automated by implementing automated material
handling system such as Articulated Robot or Over Hanging Crane
• The conveyor belt can be implemented in each workstation of the TBU line which also
enhances productivity
• The tools can be organized in the shadow board in front of the workbench which will
be easy reach for the workers and can handle in in efficient way
• The child parts are also placed according to the sequence order of the assembly which
results in easy handling and improves productivity
• The child parts can also be kitted as per the subassembly sequence order which helps
in 75% of time saving in MHS and thereby productivity is improved
• The workbench can be replaced with the aluminium workbench with height adjustment
which will be more ergonomic and also has longer lifetime
• A rotating fixture is suggested to be placed at each workstation for easy operations.
Also the new layout proposal is given during the analysis of current layout. And proposed the
idea to make some changes in the assembly line in order to improve productivity. The proposal
ideas are as follows,
• Allocating one operator for each workstation.
• Housing assembly workstation can be categorised into two namely, housing assembly
1 and housing assembly 2.
• Inspection is combined with the finishing work as a single process/activity.
• Gangway is suggested to be laid at end of the assembly line such that after the material
handling trolleys which makes easier MHS and reduces walking of operators.
The analysis is also done for the above proposed ideas which are shown in figure 19 and 20
below.
54
Figure 19: Before implementation of new MHS
Figure 20: After implementation of new MHS
From the above analysis done, it seems to be that for service brake assembly of TBU can be
able to produce 1841 products annually. Further with the implementation of this thesis work
such that with the new material handling trolley, the company can able to produce 1982
products annually which is more 141 products additionally.
55
M. Alper Corakci suggested the future development of this current thesis topic are as follows.
In my personal opinion the next future research of the kitting concept in some of the following
areas would be more effective. They are,
• Can be implemented in business cases.
• Kitting of larger parts since the literature is mostly on small and medium sized parts for
instance, like electronic parts.
• Elimination of waste from kitting activities since it is known that it’s the never ending
process.
56
13. Conclusion
Thus this thesis work successfully improved the productivity improvement in the TBU
assembly line with the support lean tools of 5s, VSM, Kaizen and Toyota’s 14 principles.
Hence, on the whole the productivity improvement resulted in the company’s benefits from
this particular thesis work. The new MHS proposed with this thesis work has been a very huge
impact in productivity improvement of the assembly line. Also the concept of kitting and
palletizing as well which also gives the added advantages for the new MHS proposed with this
thesis work. On the whole, by this thesis work the company can increase the production rate
from 1200 to 1982 products annually which is more 782 products additionally. Whereas with
this new MHS the company can additionally able to produce 56 products annually. It is proved
that the MHS has the great impact and more essential thing for the productivity growth.
On the whole, by this thesis work the company can increase the production rate about 4.5%.
Approximately 85% of non-value-added activity time such as walking and searching of parts
were decreased. From the feedback of the employees in the company, the design is done good
and also with more flexibility to use. The concept of kitting and palletizing as well which gives
the added advantages for the new MHS proposed with this thesis work. It is proved that the
MHS has the great impact and more essential thing for the productivity growth. Also from
VSM, saved about 5 minutes of cycle for each assembly through new MHS. Further, the current
state non-value-added time is about 4 days 17.5 minutes (i.e. 0.5 minutes = 30 seconds) which
is reduced to 1 day 17.5 minutes in future state.
Finally, from this thesis work, the MHS proved that it has great impact on cycle time of the
assembly process and apparently helps in enhancing the productivity.
57
14. Reference
[1] http://www.faiveleytransport.com/sites/default/files/press_release_faiveley_transport_
fy_results_2016_16022017_v6.pdf
[2] Surinder Kumar and Tilak, Selection Of Material Handling Equipment For Flexible
Manufacturing System Using Fahp Vol.5, February 2016.
[3] Art Smalley (1997), Toyota’s New Material handling Systems Shows TPS’s Flexibility,
Retrieved on June
2012,http://www.leaninstitute.nl/publications/1106/ToyotaNewMaterialHandlingSyst
em.pdf.
[4] Sera Akincilar Cameron Rad done Master Thesis on Material Handling System Design:
A Case-Study in Bosch Rexroth Japan 2013
[5] Vieira, G. B. B., Pasa, G. S., Borsa, M. B. N. O., Milan, G. S., Pandolfo, A.: Materials
Handling Management: a Case Study Journal of Operations and Supply Chain
Management 4 Vol., December 2011.
[6] Johansson M.I., Kitting systems for small parts in manual assembly systems:
Production Research Approaching the 21st Century, Taylor & Francis, 1991.
[7] Jimesh M. Gajjar and Prof. Hemant R. Thakkar, A Review Study on Improvement in
Material feeding system Through Introducing Kitting Concept in Lean Environment of
MSME,Vol.2, 2014.
[8] Johansson B., Johansson M.I., High automated kitting system for small parts – A case
study from the Uddevalla plant, Automotive Technology and Automation, Vienna,
1990.
[9] Ding F.Y., Balakrishnan P., Kitting in Just-In-Time production, Production and
Inventory Management Journal, Vol. 31, 1990.
58
[10] Bozer Y.A., Mc. Ginnis L.F., Kitting versus line stocking: A conceptual
framework and a descriptive model, International Journal of Production Economics,
Vol. 28, 1992.
[11] Medbo L., Assembly work execution and materials kit functionality in parallel
flow assembly systems. International Journal of Industrial Ergonomics, Vol. 31, 2003.
[12] Schwind G.F., How storage systems keep kits moving, Material Handling
Engineering, Vol. 47, 1992.
[13] Ding F.Y., Kitting in JIT production: A Kitting Project At Tractor Plant,
Industrial Engineering, Vol. 24, 1992.
[14] Rahul. V. Mahajan, S. T. Bagde, Development of low cost Palletizing cell for
handling different carton sizes VOL.2, October 2012.
[15] Adsavakulchai S, Optimization of Pallet management for Transportation
Efficiently. International Journal of Management Science. Vol. 1, No. 2, 2014.
[16] Sihama E. Salih1 , Abdullkhaliq F. Hamood1 & Alyaa H. Abd alsalam,
Comparison of the Characteristics of LDPE : PP and HDPE : PP Polymer Blends Vol.
7, 2013.
[17] Prof. Barbara O. Calcagno, Prof. Dr. Roderic Lakes, Prof. Dr. Tim Osswald,
Prof. Dr. Wendy - Comparison of visco-plastic Properties for Polycarbonate,
Polypropylene, and High Density Polyethylene, 2010.
[18] Yamagar A.C and Ravanan P.M , a case study, Material Management By Using
Lean Manufacturing Principles.
[19] Kitano, 1997, “Toyota Production System ”, at http://www.MfgEng.com.
59
[20] Masaaki Imai, 1991, ”Kaizan”, International Edition, McGraw Hill
Inc.,Singapore.
[21] Liker, The 14 Principles of the Toyota Way: An Executive Summary of the
Culture Behind TPS in Chapter 4, 2003,
http://imaging.ubmmedica.com/all/p2files/tools/Liker041.pdf.
[22] M. Alper Corakci done Master thesis, An Evaluation of Kitting Systems in Lean
Production, 2008.
60
Appendix Operators Feedback:
61
62
Quotations of supplier 1:
63
64
65
66
Quotations of supplier 2:
67
68