Upload
sema-tekin
View
214
Download
0
Embed Size (px)
Citation preview
7/29/2019 Axial Effects of Borehole Design
1/8
The importance of axial effects for borehole design of geothermalheat-pump systems
D. Marcotte a,b,c,*, P. Pasquier a, F. Sheriffb, M. Bernier c
a Golder Associates, 9200 lAcadie, Montreal, (Qc), H4N 2T2 Canadab CANMET Energy Technology Centre-Varennes, 1615 Lionel-Boulet Blvd., P.O. Box 4800, Varennes, (QC), J3X 1S6 Canadac Departement des genies civil, Geologique et des mines, Ecole Polytechnique de Montreal, C.P. 6079 Succ. Centre-ville, Montreal, (Qc), H3C 3A7 Canada
a r t i c l e i n f o
Article history:
Received 13 May 2008
Accepted 18 September 2009
Available online 23 October 2009
Keywords:
Infinite line source
Finite line source
Ground loop heat exchangers
Hybrid systems
Underground water freezing
a b s t r a c t
This paper studies the effects of axial heat conduction in boreholes used in geothermal heat pump
systems. The axial effects are examined by comparing the results obtained using the finite and infinite
line source methods. Using various practical design problems, it is shown that axial effects are relatively
important. Unsurprisingly, short boreholes and unbalanced yearly ground loads lead to stronger axial
effects. In one example considered, it is shown that the borehole length is 15% shorter when axial
conduction effects are considered. In another example dealing with underground water freezing, the
amount of energy that has to be removed to freeze the ground is three times higher when axial effects
are considered.
2009 Elsevier Ltd. All rights reserved.
1. Introduction
Geothermal systems using ground-coupled closed-loop heat
exchangers (GLHE) are becoming increasingly popular due to
growing energy costs. Such a system is presented in Fig. 1.
The operation of the system is relatively simple: a pump circu-
lates a heat transfer fluid in a closed circuit from the GLHE to a heat
pump (or a series of heat pumps). Typically, GLHE consists
of boreholes that are 100150 m deep and have a diameter of
1015 cm. The number of boreholes in the borefield can range from
one, for a residence, to several dozens, in commercial applications.
Furthermore, several borehole configurations (square, rectangular,
L-shaped) are possible. Typically, a borehole consists of two pipes
forming a U-tube (Fig. 1). The volume between these pipes and the
borehole wall is usually filled with grout to enhance heat transferfrom the fluid to the ground. In some situations it is advantageous
to design so-called hybrid systems in which a supplementary heat
rejecter or extractor is used at peak conditions to reduce the length
of the ground heat exchanger.
Given the relatively high cost of GLHE, it is important to design
them properly. Among the number of parameters that can be
varied, the length and configuration of the borefield are important.
There are basically two ways to design a borefield. The first method
involves using successive thermal pulses (typically 10-years 1month 6 h) to determine the length based on a given configura-tion and minimum/maximum heat pump entering water temper-
ature [8,3]. There are design software programs that perform these
calculations. Some use the concept of the g-functions developed by
Eskilson [5]. The g-functions are derived from a numerical model
that, by construction, includes the axial effects. The other approach
is to perform hourly simulation. This last approach is essential for
design of hybrid systems in which supplemental heat rejection/
injection is used. There are several software packages that can
perform hourly borehole simulations. For example, TRNSYS [9] andEnergyPlus [4] use the DST [6] and the short-time step model [5],
respectively. Even though these packages account for axial effects,
they necessitate a high level of expertise. Furthermore, it is not
easily possible to obtain ground temperature distributions like the
ones shown later in this paper. In this paper hourly simulations are
performed using the so-called finite and infinite line source
approximations where the borehole is approximated by a line with
a constant heat transfer rate per unit length. These approximations
present, in a convenient analytical form, the solution to the tran-
sient 2-D heat conduction problem. Despite their advantages,
hourly simulations based on the line source approximation are
* Corresponding author. Departement des genies civil, geologique et des mines,
Ecole Polytechnique de Montreal, C.P. 6079 Succ. Centre-ville, Montreal, (Qc),
H3C 3A7 Canada. Tel.: 1 514 340 4711x4620; fax: 1 514 340 3970.E-mail address: [email protected] (D. Marcotte).
Contents lists available at ScienceDirect
Renewable Energy
j o u r n a l h o m e p a g e : w w w . e l s e v i e r . c o m / l o c a t e / r e n e n e
0960-1481/$ see front matter 2009 Elsevier Ltd. All rights reserved.
doi:10.1016/j.renene.2009.09.015
Renewable Energy 35 (2010) 763770
mailto:[email protected]://www.sciencedirect.com/science/journal/09601481http://www.elsevier.com/locate/renenehttp://www.elsevier.com/locate/renenehttp://www.sciencedirect.com/science/journal/09601481mailto:[email protected]7/29/2019 Axial Effects of Borehole Design
2/8
rarely used in routine design due to the perceived computational
burden.
The major difference between the finite and infinite line source
lies in the treatment of axial conduction (at the bottom and top of
the borehole) which is only accounted for in the former. Thetheoretical basis of the finite line source, although more involved
than for the infinite line source, was first established by Ingersoll
et al. [7]. It has been rediscovered recently by Zeng et al. [15] who
improved the model by imposing a constant temperature at the
ground surface. Lamarche and Beauchamp [11] have made a useful
contribution to speed up the computation of Zengs model. Finally,
Sheriff[13] extended Zengs model by permitting the borehole top
to be located at some distance below the ground surface. She also
did a detailed comparison of the finite and infinite line source
responses, but did not examine the repercussion on borefield
design.
At first glance, the axial heat-diffusion is likely to decrease
(increase) the borehole wall temperature in cooling (heating)
modes respectively. Therefore, designing without consideringaxial effects appears to provide a safety factor for the design. But,
is it really always the case? Moreover, are the borehole designs
incorporating axial effects significantly different from those
neglecting it? Under which circumstances are we expected to
have significant design differences? These are the main questions
we seek to answer. The main contribution of this research is to
describe, using synthetic case studies, the impact of considering
axial effects on the GLHE design. Our main finding is that for
many realistic circumstances the axial effects cannot be neglec-
ted. Therefore, design practices should be revised accordingly to
include the axial effects.
We first review briefly the theory for infinite and finite linesource models. Then, we present three different design situations.
The first two situations involve the sizing of geothermal systems
with and without the hybrid option, under three different hourly
ground load scenarios. The last design problem examines the
energy required and ground temperature evolution in the context
of ground freezing for environmental purposes.
2. Theoretical background
The basic building block of both infinite and finite line source
models is the change in temperature felt at a given location and
time due to the effect of a constant point source releasing q0 units ofheat per second [7]:
DTr; t q0
4pksrerfc
r
2ffiffiffiffiffiat
p
(1)
where erfc is the complementary error function, r the distance to
the point heat source, and a is the ground thermal diffusivity.
The line is then represented as a series of points equally spaced.
In the limit, when the distance between point sources goes to zero,
Fig. 1. Sketch of a GLHE system.
Nomenclature
a Thermal diffusivity (m2 s1)A, B, C, D Synthetic load model parameters (kW)
b r/H
Cs Ground volumetric heat capacity (Jm3 K1)
erfc (x) Complementary error function
(erfcx 12ffiffiffip
pRN
x et2 dt
EWT Temperature of fluid entering the heat pump (K or C)Fo Fourier number, Fo at/r2ks Volumetric ground thermal conductivity (Wm
1 K1)H Borehole length (m)
HP Heat Pump
q0 Radial heat transfer rate (W)q Radial heat transfer rate per unit length (Wm1)
S Borehole spacing (m)
r Distance to borehole (m)
rb Borehole radius (m)
Rb Borehole effective thermal resistance (Km W1)
t Time
DT(r, t) Ground temperature variation at time tand distance r
from the borehole (K or
C)
Tf Fluid temperature (K orC)
Tg Undisturbed ground temperature (K orC)
Tw Temperature at borehole wall (K orC)
u H2ffiffiffiffiat
px, y Spatial coordinates (m)
z Elevation (m)
D. Marcotte et al. / Renewable Energy 35 (2010) 763770764
7/29/2019 Axial Effects of Borehole Design
3/8
the combined effect felt at distance rfrom the source is obtained by
integration along the line.
2.1. Infinite line source
In an infinite medium, the line-integration gives the so-called
(infinite) line source model [7]:
DTr; t q4pks
ZNr2=4at
eu
udu (2)
2.2. Finite line source
In the case of a finite line source, the upper boundary is
considered at constant temperature, taken as the undisturbed
ground temperature [15]. This condition is represented by adding
a mirror image finite line source with the same load, but opposite
sign, as the real finite line. Then, integrating between the limits of
the real and image line, one obtains [15],[13]:
DTr; t;z q4pks
ZH
0
0@erfc du2ffiffiffiffiatp du
erfc
d0u2ffiffiffiffiatp d0u
1Adu (3)where du
ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffir2 z u2
qand d0u
ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffir2 z u2
q, z is the
elevation of the point where the computation is done. The left part
of the integrand in Equation (3) represents the contribution by the
real finite line, the right part, the contribution of the image line.
Fig. 2 shows the vertical temperature profile obtained with
Equation (3) at radial distance r 2 m, after 200 days, and atr 1 m, after 2000 days of heat injection. The correspondinginfinite lines-source temperature is indicated as a reference. In this
example,the borehole is 50 m long, the groundthermal parameters
are ks 2.1 Wm1 K1 and Cs 2e06 Jm3 K1. The ground is inti-tially at 10 oC. The applied load is 60 W per m for a total heating
power of 3000 W. As expected, the importance of axial effects and
the discrepancy between infinite and finite models increases with
the Fourier number (at/r2 4.54 and 181.4 for these two cases).
In hourly simulations, the fluid temperature (Tf in Fig. 1) is
required. This necessitates knowledge of the borehole thermal
resistance Rb (i.e. from the fluid to the borehole wall), and of the
borehole wall temperature (Tw in Fig. 1) [2]. The average borehole
wall temperature it obtained by integrating Equation (3) along z.
However, this is computationally intensive due to the double
integration. Lamarche and Beauchamp [11] have shown, using an
appropriate change of variables, how to simplify Equation (3) to
a single integration. Accounting for small typos in [11] and [15] as
noted by Sheriff[13], the average temperature difference, between
a point located at distance rfrom the borehole and the undisturbed
ground temperature, is given by:
DTr; t q2pks
0BBB@
Zffiffiffiffiffiffiffiffiffib21p
b
erfcuzffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiz2 b2
q dz DA
Zffiffiffiffiffiffiffiffiffib24p
ffiffiffiffiffiffiffiffiffib21perfcuz
ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiz2 b2
qdz DB
1CCCA
(4)
where b r/H, r is the radial distance from the borehole center,u H
2ffiffiffiffiat
p and DA, and DB are given by:
DA ffiffiffiffiffiffiffiffiffiffiffiffiffiffib
2 1q
erfc
u
ffiffiffiffiffiffiffiffiffiffiffiffiffiffib
2 1q
b erfcub
eu2b21 eu2b2
uffiffiffip
p!
and
DB ffiffiffiffiffiffiffiffiffiffiffiffiffiffib2 1
qerfc
u
ffiffiffiffiffiffiffiffiffiffiffiffiffiffib2 1
q 0:5
b erfcub
ffiffiffiffiffiffiffiffiffiffiffiffiffiffib2 4q erfcu ffiffiffiffiffiffiffiffiffiffiffiffiffiffib2 4q
eu2b
21
0:5
eu2b2 eu2
b
24
uffiffiffip
p!
10 12 14 16 18 20 22 24
0
10
20
30
40
50
60
Temperature (oC)
Dept
h(m)
Vertical temperature profile
Infline, r=2, t=200 d
Fline, r=2, t=200 d
Fline average, r=2, t=200 d
Infline, r=1, t=2000 dFline, r=1, t=2000 d
Fline average, r=1, t=2000 d
Fig. 2. Vertical ground temperature profile at radial distances r1 m and r2 m after
respectively 2000 days and 200 days, Fo (r1, t2000)181.4 and Fo (r2,
t200)4.54.Constantheat injectionof 3000 W.Thermal parameters:ks2.1 Wm1 K1,
Cs
2e06 Jm3
K1
.
0 1000 2000 3000 4000 50000
2
4
6
8
10
12
Days
T(oC)
Infinite
Finite
FEM
Fig. 3. Comparison of Finite and Infinite line source model with finite element model
(FEM) for a 30 m borehole. Average temperature variation computed at 0.5 m from the
borehole axis, over the borehole length. Constant heat transfer rate of 1000 W.
Thermal parameters: ks
2.1 Wm1
K1
, Cs
2e06 Jm3
K1
.
D. Marcotte et al. / Renewable Energy 35 (2010) 763770 765
7/29/2019 Axial Effects of Borehole Design
4/8
The particular case r rb in Equation (4) gives the borehole walltemperature.
2.3. Numerical validation
Fig. 3 compares the variation in temperature over time
computed with finite and infinite line source to the numerical
results of a finite element model (FEM) constructed within
COMSOL. The finite element model is 2-D with axial symmetry
around the borehole axis. The ground is represented by a 50 m long
and 50 m radius cylinder. The borehole is represented by a 30 m
long and 0.075 m radius cylinder delivering 1000 W. The axis ofrevolution is located at the borehole center and constitutes
a thermal insulation boundary whereas all external boundaries are
set to the undisturbed ground temperature. Over 6000 triangular
elements equipped with quadratic interpolating functions are used
to discretize the model. The agreement between the FEM model
and the finite line source is almost perfect, the maximum absolute
difference in temperature over the 5000 days period being only
0.019 oC.
Fig. 4 compares the temperature obtained with the infinite
and finite line source models, at r 1 m and r 0.075 m (atypical value for rb), with the thermal parameters specified
above. A 1 oC temperature difference between the infinite and
finite models is obtained after 2.5 y and 2 y, at 1 m and 0.075 m
respectively. Note that the temperature reaches a plateau for the
finite line source model indicating that a steady-state condition
has been reached. In contrast, the infinite line source model
exhibits a linear behavior.
Fig. 5 shows the ground temperature, computed at a distance of1 m from the borehole, for increasing values of the borehole length.
As expected, the finite line source solution reaches the infinite line
source solution for long boreholes.
0.001 0.01 0.1 1 10 100 100010
20
30
40
50
60
70
80
r=0.07
5m
r=1m
Ground temperature
Time (y)
Temperature(oC)
Fig. 4. Comparison of Finite (solid) and Infinite (broken) line source model, computed
at distance 1 m and 0.075 m from the borehole. Constant heat transfer rate per unitlength of 100 W/m. Thermal parameters: ks2.1 Wm
1 K1, Cs2e06 Jm3 K1.
0 100 200 300 400 500 600 700 800 900 100012
12.5
13
13.5
Borehole length (m)
Temperature
(oC)
Average temperature vs borehole length
Infinite linesourceFinite linesource
Fig. 5. Infinite vs finite line source average temperature along a vertical profile. The load
is 20 W/m, thermal parameters: ks2.1 Wm1 K1, Cs2e06 Jm
3 K1. Temperature
computed after one year at r
1 m from the borehole.
1 2 3 4 5 6
100
0
100
Cooling (+) Heating () load
Time (h)
Load(kw)
1 2 3 4 5 6200
100
0
100
Load decomposition
Load(kw)
Fig. 6. Principle of temporal superposition for variable loads.
0 5 10 15 20 25 30 353
3.5
4
4.5
5
5.5
6
6.5
7
7.5
COP vs EWT
EWT
COP
Cooling
Heating
Fig. 7. COP as a function of EWT.
D. Marcotte et al. / Renewable Energy 35 (2010) 763770766
7/29/2019 Axial Effects of Borehole Design
5/8
3. Design of complete geothermal systems
In this section we compare the design length of borefields
obtained with the finite and infinite line source models for given
hourly ground load scenarios. These calculations imply that single
borehole solutions will need to be superimposed spatially. We have
already seen an instance of this principle of superposition while
computing the line source solution from a series of constant point
sources along a line [7], see Equations (1 and 2). The additivity of
effects (variation in temperature) stems from the linear relationbetween q and DT, and the fact that energy is an extensive and
additive variable. The temporal superposition also follows the same
general principle of addition of effects as described by Yavuzturk
and Spitler [14] and illustrated by Fig. 6. When the load is varying
hourly, a new pulse is applied each hour. It is simply the difference
between the load for two consecutive hours. More formally, for the
infinite line source as an example, with a single borehole, we have:
DTr; t X
i; tit
qi
4pk
ZNr2=4atti
eu
udu (5)
where: q*1 q1, and q*i qiqi1, i 2.I, tI t, is the incrementalload between two successive hours. With multiple boreholes,
DTx0; t Xn
j 1
Xi; tit
q0i
4pk
ZNkxjx0k2=4atti
eu
udu (6)
where: n is the number of boreholes, xj and x0 are the coordinate
vectors of borehole j and point where temperature is computed,
respectively. Note that for long simulation periods, the computa-
tional burden becomes important.
In the test cases that follow we assume that all of the buildingheating and cooling loads are to be provided by the GLHE system,
i.e. there is no supplementary heat rejection/injection. Synthetic
building loads are used to enhance the reproducibility of our
results. These building loads are simulated using:
Qt A B cos
t
87602p
C cos
t
242p
D cos
t
242p
cos
2t
87602p
(7)
In Equation (7), t is in hours, A controls the annual load
unbalance, B the half-amplitude of annual load variation, C and D
40 30 20 10 0 10 20 30 40
40
30
20
10
0
10
20
30
40
1
2
3 4
5
6 7
8 9
10
11 12
13
14 15
16 17
18 19
20 21
22 23
24 25
26
27 28
29
30 31
32 33
34 35
36 37
38 39
40 41
42 43
44 45
46
47 48
49
50 51
52 53
54 55
56 57
58 59
60 61
62 63
64 65
66 67
68 69
70
71 72
73 74
75 76
77 78
79 80
81
82 83
84 85
86 87
88 89
90 91
92 93
94 95
96 97
98 99
100 101
102 103
104 105
106 107
108 109
110
111 112
113
114 115
116 117
118 119
120 121
122 123
124 125
126 127
128 129
130 131
132 133
134 135
136 137
138 139
140 141
142 143
144 145
146
147 148
149
150 151
152 153
154 155
156 157
158 159
160 161
162 163
164 165
166 167
168 169
170 171
172 173
174 175
176 177
178 179
180 181
182 183
184 185
186 187
188 189
190 191
192 193
194 195
196 197
198 199
200 201
202 203
204 205
206 207
208 209
210 211
212 213
214 215
216 217
218 219
220 221
222 223
224 225
Borehole location and priority number
Coord. x (m)
Coord.y(m)
Fig. 8. Borehole grid and priority number. Number indicates order of inclusion in the design when required.
Table 1
Number of boreholes required, complete geothermal system. Constant T assumes
a constant ground surface temperature of 10 oC, Periodic T assumes a periodic
ground surface temperature with an amplitude of 20 oC in phase with the heatload.
Scenar io Borehole length Infinite li ne Fini te l in e
Constant T Periodic T
Balanced (A 17) 100 m 33 33 34Balanced 50 m 76 74 80
Cooling dominant (A 17) 100 m 39 36 37Cooling dominant 50 m 93 79 81
Heating dominant
(A 30)100 m 57 53 56
Heating dominant 50 m 134 115 124
Table 2
Number of boreholes required, hybrid system. HP capacity represents 40% of
maximum building load. The last two column represent the percentage of the
building load supplied by the HP for each mode.
Scenario Borehole
length
Number of
boreholes
% Energy
Infinite Finite Cooling Inf.
(Fin.)
Heating Inf.
(Fin.)
Balanced 100 m 19 19 69 (69) 77 (78)
Balanced 50 m 37 37 67 (67) 72 (73)
Cooling dominant 100 m 24 24 69 (69) 86 (86)
Cooling dominant 50 m 41 39 70 (69) 90 (88)
Heating dominant 100 m 37 37 67 (67) 83 (86)
Heating dominant 50 m 55 53 72 (70) 70 (73)
D. Marcotte et al. / Renewable Energy 35 (2010) 763770 767
7/29/2019 Axial Effects of Borehole Design
6/8
the half-amplitude of daily load fluctuations. D/C controls the
relative importance of the damped component used to simulate
larger daily fluctuations in winter and summer. Coefficients A to D
are in kW.
We consider three different load scenarios, each with B 100,C 50, and D 25. One is approximately balanced (A 17), one isa cooling dominated load (A 17) and the other is a heating domi-natedload(A 30).Conversionof buildingloads to ground loads isdone with: qground qbuilding(1 1/COP). The heat pump COP variesas a function of entering water temperature as depicted in Fig. 7.
For all scenarios, we consider a unique set of possible locations
for the boreholes. The locations are at the nodes of a regular grid of
mesh S
6 m. The boreholes are assigned a priority number (lower
number / highest priority), moving excentrically from the grid
center to the fringes (see Fig. 8). The system is simulated with
100 m and then, 50 m long boreholes. The borehole heads are
located at the ground surface.
For each scenario and given number of boreholes, we simulate
the hourly fluid temperature for a 10-year period. We repeat this
simulation for different number of boreholes and finally keep the
lowest number of boreholes ensuring that the fluid temperature at
the HP entrance never exceeds the HP limit specifications. We do
this computation using both the infinite and finite line source
models. Thermalparameters of the ground are: thermal conductivity
ks 2 Wm1 K1, volumetric heat capacity Cs 3.4e06 Jm3 K1and borehole thermal resistance Rb 0.1 m KW1. The ground isinitially at 10 oC and all the boreholes have a radius of rb
0.075 m.
Table 1 gives the number of boreholes required for a specificscenario and model. The choice of model does not have a strong
impact on the balanced load scenario. However, for cooling and
heating dominant scenarios, the finite line source model indicates
a reduction in the number of boreholes of approximately 7% and
15% for the 100 m and 50 m borehole length. As expected, the
shorter the borehole length, the greater are the discrepancies
between both models.
3.1. Seasonal effects
The finite line source model assumes a constant temperature at
the ground surface equal to the undisturbed ground temperature.
This hypothesis would more or less correspond to the case of
geothermal boreholes located under a building slab. However, in
many cases, the boreholes are located outside the building area
where the ground surface temperature varies in phase with the
heat load. One can expect the axial effect at the ground surface will
be less than under the constant temperature assumption. The
influence of ground surface temperature variation on the ground
temperature, at any depth and time, can be computed for a periodic
signal [7]. Using the principle of superposition, the influence on the
design can be assessed.
Last column of Table 1 gives the number of boreholes required
when the groundsurface temperature is periodic, in phase with the
heat load, and shows a yearly variation of 20 oC. The boreholeheads are located at the ground surface, a feature that maximizes
the seasonal effects on the design. As expected, the designs with
periodic ground surface temperature require more boreholes than
with constant ground surface temperature. For unbalanced
scenarios, the periodic ground surface temperature solutions
obtained are intermediate between the infinite and the finite line
source designs.
0 5 10 15 20 25 306
4
2
0
2
4
6
8
Time (year)
o
Temperature(
C)
Rock temperature at x=(13,5,12.0)
Infinite linesource
Finite linesource
15 10 5 0 5 10 1515
10
5
0
5
10
15Control point
x (m)
y(m)
Fig. 9. Vertical average rock temperature at point x (13.5, 12.0). Thermal parameters: ks2 Wm1 K1, Cs3.4e06 Jm
3 K1.
0 5 10 15 20 25 301000
900
800
700
600
500
400
300
200
100
0
Time (year)
Load(W)
Ground cooling load / borehole
Infinite linesource
Finite linesource
Fig. 10. Evolution of average load per borehole.
D. Marcotte et al. / Renewable Energy 35 (2010) 763770768
7/29/2019 Axial Effects of Borehole Design
7/8
4. Design of hybrid geothermal systems
The design situation borrows its essential features (borehole
grid, thermal parameters, heat load scenarios) from the previous
complete geothermal system example. The main difference is that
the HP and auxiliary system power are respectively selected at 40%
and 60% of the maximum building load. The simulation works thesame way as previously with the following modification. Each hour,
the fluid temperature at the HP entrance (EWT) is computed. If
EWT, at any hour, exceeds the HP specification limit, it is assumed
that the HP cycles to keep the EWT at its limit value, the excess load
being taken by the auxiliary system. We keep track of all the loads
provided by the auxiliary system. At the end of the 10-year simu-
lation, we verify that the load to the auxiliary system never exceeds
its capacity. If exceeded, we add more boreholes. The final design is
obtained with the smallest number of boreholes compatible with
the auxiliary system capacity.
Table 2 shows the number of boreholes for a specific scenario
and computation model. The proportion of energy provided by the
geothermal system, relative to the total building energy required
for the 10-year period, is also given. Unbalanced scenarios with
short boreholes display reduction of only 6% for the number of
boreholes required. However, comparison of Tables 1 and 2 reveals
striking reduction in numberof boreholes. The hybrid systems need
only between 46% and 70% of the number of boreholes for the
complete geothermal system. Yet, the geothermal components of
hybrid systems are able to supply between 67% and 70% of the
cooling load and between 73% and 88% of the heating load for thevarious scenarios examined. As the borehole construction cost
represents the main investment in a geothermal system, it indi-
cates that hybrid systems can be economically advantageous.
Even though hourly simulations are computationally more
involved, efficient methods exist to speed up the computations
[1,10,12]. For example, a hybrid system 10-years hourly simulation
for a 45 boreholes field is computed in less than 2 min on a stan-
dard laptop.
5. Comparing performances for a rock freezing problem
In some environmental problems, like those involving DNAPL
(dense non-aqueous phase liquid), the contaminants reach the
bedrock and then can propagate through the rock fractures. In such
X coordinate (m)
Ycoordinate(m
)
Infinite line: Temperature after 5 years
15 10 5 0 5 10 15
15
10
5
0
5
10
15
12
10
8
6
4
2
0
2
X coordinate (m)
Ycoordinate(m
)
Finite line: Temperature after 5 years
15 10 5 0 5 10 15
15
10
5
0
5
10
15
12
10
8
6
4
2
0
2
X coordinate (m)
Ycoordinate(m)
Infinite line: Temperature after 20 years
15
10
5
0
5
10
15
12
10
8
6
4
2
0
2
X coordinate (m)
Ycoordinate(m)
Finite line: Temperature after 20 years
15 10 5 0 5 10 15 15 10 5 0 5 10 1515
10
5
0
5
10
15
12
10
8
6
4
2
0
2
Fig. 11. Ground temperature after 5 years (top) and 20 years (bottom). Infinite line source model (left) and finite line source model (right).
D. Marcotte et al. / Renewable Energy 35 (2010) 763770 769
7/29/2019 Axial Effects of Borehole Design
8/8
circumstances, remediation can be extremely difficult and expen-
sive. One solution is to catch and treat all the contaminants flowing
through the fractures. This requires designing a series of wells
forming an hydraulic trap. The pumping andtreatment is expensive
and it has to be maintained typically for hundreds of years. More-
over, the flow of water to treat could be relatively important. An
alternative is to permanently freeze the liquid within the fractures
to avoid any movement of the contaminant.
In the following example, we consider the problem of freezing
water inside rock fractures, in a domain 30 m by 30 m by 30 m, for
the purpose of long term confinement of toxic DNAPLs. A 10 10borefield is considered (see Fig. 9). Thermal parameters of the rock
are: thermal conductivity ks 2 Wm1 K1 and volumetric heatcapacity Cs 3.4e06 Jm3 K1. The borehole thermal resistance isRb 0.1 m KW1. The rock is initially at 10 oC. The rock porosity issmall enough so as to neglect the latent heat of water and the
increase of rock thermal conductivity occurring when water
freezes. The total HP capacity is 100 kW (one kW per borehole)
and the EWTlimitis 8 oC. Themass flow of the circulating fluid is19 l/s (or 0.19 l/s for each borehole). The simulation is run for 30
years. The HP capacity is kept at its maximum until the EWT has
reached the limiting value of
8 oC. Then, the HP cycles to
maintain the EWT at this temperature. The performance of thesystem is monitored by computing rock temperature at a control
point located at the borefield periphery at (x, y) (13.5, 12) m (seeFig. 9).
Fig. 9 shows the rock temperature obtained at this control point
using the infinite and finite line source models. Fig. 10 shows the
corresponding average hourly load per borehole. In both figures,
the rugged nature of the load curves is due to intermittent opera-
tion of the HP. As shown in Fig. 9, the rock becomes permanently
frozen after 10 months and 2.2 years for the infinite and finite
models, respectively. The temperature difference between both
models increases steadily with time, to reach approximately 2 oC
after 30 years. The finite line source model predicts that about
150 W per borehole are required compared to only 50 W per
borehole for the infinite line source model (Fig. 10). Thus, despitea higher heat transfer rate per borehole, the finite line source model
predicts a higher rock temperature at the control point.
In this next example, the same 10 10 borefield is cooled ata rate of 10 W/m (300 W/borehole) for the first year and then
3.33 W/m (100 W/borehole) permanently. The temperature distri-
bution in the ground is computed using the infinite and finite line
source models after 5 and 20 years. Results are presented in Fig. 11.
The proportion of the domain with temperature below freezing is
79% and 100% after 5 and 20 years for the infinite line source
calculation whereas it is only 10% and 52% with the finite line
source model. Therefore, a design based on the use of the infinite
line source would have wrongly predicted ground freezing. Thus,
contrary to the two previous examples, the infinite model does not
provide a conservative design.
6. Conclusion
This paper studies the effect of axial heat conduction in bore-
holes used in geothermal heat pump systems. The axial effects are
examined by comparing the results obtained using the finite and
infinite line source methods. Using various practical design prob-
lems it is shown that axial effects are relatively important. Even
with a borehole spacing / borehole length (S/H) as lowas 0.06, the
finite line source model indicated that 7% less boreholes are
required,for a complete geothermal system, when the yearly load is
unbalanced either in cooling or in heating. The reduction in the
number of boreholes due to axial effects increases to 15% for 50 m
long boreholes (ratio S/H 0.12). Differences between the finite
and infinite line source models were noticeably smaller for the
hybrid system but still indicate that less boreholes are generally
required with the finite line source model. As sizing of geothermal
system is a determining factor for the profitability of a project, axial
effects should certainly be considered in similar circumstances.
Also, the value of using hybrid systems to substantially reduce the
number of boreholes, yet preserving most energy savings, was
confirmed.
In another example dealing with underground water freezing,
the amount of energy that has to be removed to freezethe ground is
three times higher when axial effects are considered. Furthermore,
for this particular example, a design based on the infinite line
source would not achieve the ground freezing goal. Indeed, while
the infinite line source calculations show that 100% of the ground
would be frozen, the finite line source model predicts that only 52%
of the ground would be frozen.
Together, these examples clearly indicate that axial effects are
problem dependent. The magnitude of these effects is difficult to
anticipate and cannot generally be neglected. Moreover, neglecting
the axial effects (i.e. using the infinite line source model) does not
always provide a conservative design. Since the computing cost of
finite line source model, when properly implemented, is only
slightly superior to the computing cost of the infinite line sourcemodel, there is no reason to overlook axial effects in any borefield
design.
Acknowledgments
Part of this research was financed by the National Science and
Engineering Research Council of Canada. We thank Jeremie
Gaucher for English editing. Helpful suggestions from anonymous
reviewers are acknowledged.
References
[1] Bernier M, Pinel P, Labib R, Paillot R. A multiple load aggregation algorithm forannual hourly simulations of gchp systems. HVAC&R Research2004;10(4):47187.
[2] Bernier M. Ground-coupled heat pump system simulation. ASHRAE Trans-actions 2001;107(1):60516.
[3] Bernier M. Closed-loop ground-coupled heat pumps systems. ASHRAE Journal2006;48(9):129.
[4] Crawley D, Lawrie L, Pedersen C, Strand R, Liesen R, Winkelmann F, et al.Energyplus: creating a new-generation building energy simulation program.Energy and Buildings 2001;33(4):31931.
[5] Fisher D, Rees S, Padhrmanabhan S, Murugappan A. Implementation andvalidation of ground-source heat pump system models in an integratedbuilding and system simulation environment. IJHVAC &R Research2006;13(3a):693710.
[6] Hellstrom G. Ground heat storage. Thermal analysis of duct storage systems:Part i, theory, Ph.D. dissertation, University of Lund, Sweden, 1991.
[7] Ingersoll L, Zobel O, Ingersoll A. Heat conduction with engineering, geologicaland other applications. New York: McGraw-Hill; 1954.
[8] S. Kavanaugh and K. Rafferty. Ground-source heat pumps. Design of
geothermal systems for commercial and institutional buildings. ASHRAE,editor. ASHRAE, 1997.
[9] Klein S, Beckman W, Mitchell J, Duffie J, Duffie N, Freeman T, et al. In: S.E.Laboratory, editor. TRNSYS 16 A transient system simulation program, usermanual. Madison: University of Wisconsin; 2004.
[10] Lamarche L. A fast algorithm for the hourly simulations of ground-source heatpumps using arbitrary response factors. Renewable Energy 2009;10:22528.
[11] Lamarche L, Beauchamp B. A new contribution to the finite line-source modelfor geothermal boreholes. Energy and Buildings 2007;39:18898.
[12] Marcotte D, Pasquier P. Fast fluid and ground temperature computation forgeothermal ground-loop heat exchanger systems. Geothermics 2008;37:65165.
[13] F. Sheriff. "Generation de facteurs de reponse pour champs de puits geo-thermiques verticaux." Masters thesis, Ecole Polytechnique de Montreal.2007.
[14] Yavuzturk C, Spitler J. A short time step response factor model for verticalground loop heat exchangers. ASHRAE Transactions 1999;105:47585.
[15] Zeng H, Diao N, Fang Z. A finite line-source model for boreholes in geothermal
heat exchangers,". Heat Transfer - Asian Research 2002;31:55867.
D. Marcotte et al. / Renewable Energy 35 (2010) 763770770