AWS B2.1-1-007:2002 An American National Standard Standard Welding Procedure Specification (SWPS) for Gas Tungsten Arc Welding of Galvanized Steel (M-1), 18 through 10 Gauge, in the As-Welded Condition, with or without Backing Site License COPYRIGHT 2003; American Welding Society, Inc. Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/2003 01:37:50 MDT Questions or comments about this message: please call the Document Policy Group at 1-800-451-1584. --`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

AWS_B2.1-1-007-02

  • Upload
    czemen

  • View
    313

  • Download
    8

Embed Size (px)

Citation preview

Page 1: AWS_B2.1-1-007-02

AWS B2.1-1-007:2002An American National Standard

Standard Welding ProcedureSpecification (SWPS) for

Gas Tungsten ArcWelding of GalvanizedSteel (M-1), 18 through10 Gauge, in theAs-Welded Condition,with or without Backing

Site License

COPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 2: AWS_B2.1-1-007-02

Site License to Make Copies for Intra-Company Use

This License is issued by the American Welding Society (hereinafter referred to as “AWS”) to you(hereinafter referred to as “Licensee”) based upon your application and conditions:

1. By becoming a Licensee, Licensee agrees to all the terms contained in this License.

2. Licensee is authorized to reproduce this AWS B2 Standard Welding Procedure for intra-company use only. Copies may not be made available to any individual not employed byLicensee or for any purpose unrelated to the business being conducted by Licensee.

3. Any reproduction must include the following copyright notice: “Copyright by the AmericanWelding Society. Reproduced with the express written permission of the American WeldingSociety.”

4. Licensee may not enter into any sublicense agreement.

5. Reproduction of this Standard Welding Procedure signifies that you agree with the terms of theLicense. If you do not agree with the terms of this License please return this document, and anew document without the copyright notice will be issued.

6. The AWS B2 Standard Welding Procedures are not the subject of any warranty. AWS disclaimsany liability arising from the use of any Standard Welding Procedure. AWS is not liable for anyactual or consequential damages that may arise from the use of any Standard WeldingProcedure.

7. Licensee will notify AWS in writing if it becomes aware that any employee or other party hasmade copies or otherwise made use of any Standard Welding Procedure contrary to the terms ofthe License.

8. This License contains the entire understanding as between Licensee and AWS, and any changesmust be contained in a writing signed by both parties.

9. The terms of this License are governed under the laws of the State of Florida, and both partiesagree to submit to the jurisdiction of the cognizant court of law within Dade County, Florida toresolve any disputes.

COPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 3: AWS_B2.1-1-007-02

AWS B2.1-1-007:2002An American National Standard

Approved byAmerican National Standards Institute

June 10, 2002

Standard Welding Procedure Specification (SWPS) for

Gas Tungsten Arc Welding of Galvanized Steel

(M-1), 18 through 10 Gauge, in the As-Welded

Condition with or without Backing

Supersedes ANSI/AWS B2.1.007-90

Prepared byAWS B2 Committee on Welding Qualification

Under the Direction ofAWS Technical Activities Committee

Approved byAWS Board of Directors

AbstractThis standard contains the essential welding variables for welding galvanized steel in the thickness range of 18 through10 gauge using manual gas tungsten arc welding. It cites the base metals and operating conditions necessary to make theweldment, the filler metal specifications, and the allowable joint designs for fillet welds and groove welds.

Key Words— Welding procedure specification, WPS, standard welding procedure specification, SWPS, base metal, allowable joint designs, filler metal, galvanized steel, manual gas tungsten arc welding

550 N.W. LeJeune Road, Miami, Florida 33126

COPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 4: AWS_B2.1-1-007-02

Statement on Use of AWS American National Standards

All standards (codes, specifications, recommended practices, methods, classifications, and guides) of the AmericanWelding Society (AWS) are voluntary consensus standards that have been developed in accordance with the rules of theAmerican National Standards Institute (ANSI). When AWS standards are either incorporated in, or made part of,documents that are included in federal or state laws and regulations, or the regulations of other governmental bodies,their provisions carry the full legal authority of the statute. In such cases, any changes in those AWS standards must beapproved by the governmental body having statutory jurisdiction before they can become a part of those laws andregulations. In all cases, these standards carry the full legal authority of the contract or other document that invokes theAWS standards. Where this contractual relationship exists, changes in or deviations from requirements of an AWSstandard must be by agreement between the contracting parties.

International Standard Book Number: 0-87171-679-8

American Welding Society, 550 N.W. LeJeune Road, Miami, FL 33126

© 2002 by American Welding Society. All rights reservedPrinted in the United States of America

AWS American National Standards are developed through a consensus standards development process that bringstogether volunteers representing varied viewpoints and interests to achieve consensus. While AWS administers the processand establishes rules to promote fairness in the development of consensus, it does not independently test, evaluate, orverify the accuracy of any information or the soundness of any judgments contained in its standards.

AWS disclaims liability for any injury to persons or to property, or other damages of any nature whatsoever, whether spe-cial, indirect, consequential or compensatory, directly or indirectly resulting from the publication, use of, or reliance on thisstandard. AWS also makes no guaranty or warranty as to the accuracy or completeness of any information published herein.

In issuing and making this standard available, AWS is not undertaking to render professional or other services for or onbehalf of any person or entity. Nor is AWS undertaking to perform any duty owed by any person or entity to someoneelse. Anyone using these documents should rely on his or her own independent judgment or, as appropriate, seek the adviceof a competent professional in determining the exercise of reasonable care in any given circumstances.

This standard may be superseded by the issuance of new editions. Users should ensure that they have the latest edition.

Publication of this standard does not authorize infringement of any patent. AWS disclaims liability for the infringementof any patent resulting from the use or reliance on this standard.

Finally, AWS does not monitor, police, or enforce compliance with this standard, nor does it have the power to do so.

On occasion, text, tables, or figures are printed incorrectly (errata). Such errata, when discovered, are shown on theAmerican Welding Society web page (www.aws.org) under “Technical” in the Departments column.

Official interpretations of any of the technical requirements of this standard may be obtained by sending a request, in writing,to the Managing Director, Technical Services Division, American Welding Society, 550 N.W. LeJeune Road, Miami, FL33126 (see Annex A). With regard to technical inquiries made concerning AWS standards, oral opinions on AWS standardsmay be rendered. However, such opinions represent only the personal opinions of the particular individuals giving them.These individuals do not speak on behalf of AWS, nor do these oral opinions constitute official or unofficial opinions or inter-pretations of AWS. In addition, oral opinions are informal and should not be used as a substitute for an official interpretation.

This standard is subject to revision at any time by the AWS B2 Committee on Welding Qualification. It must be reviewedevery five years, and if not revised, it must be either reapproved or withdrawn. Comments (recommendations, additions,or deletions) and any pertinent data that may be of use in improving this standard are required and should be addressed toAWS Headquarters. Such comments will receive careful consideration by the AWS B2 Committee on Welding Qualifi-cation and the author of the comments will be informed of the Committee’s response to the comments. Guests are invitedto attend all meetings of the AWS B2 Committee on Welding Qualification to express their comments verbally. Proce-dures for appeal of an adverse decision concerning all such comments are provided in the Rules of Operation of theTechnical Activities Committee. A copy of these Rules can be obtained from the American Welding Society, 550 N.W.LeJeune Road, Miami, FL 33126.

COPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 5: AWS_B2.1-1-007-02

Personnel

AWS B2 Committee on Welding Qualification

J. J. Sekely, Chair Eichleay CorporationG. M. Wisbrock, 1st Vice Chair Lockheed Martin Missiles and Fire ControlJ. J. Fluckiger, 2nd Vice Chair Bechtel Babcock & Wilcox Idaho

P. B. Dickerson, 3rd Vice Chair ConsultantL. P. Connor, Secretary American Welding Society

T. J. Anderson Consultant*W. L. Ballis Consultant*H. B. Cary ConsultantJ. L. Cooley J. C. and Associates, IncorporatedW. D. Doty Doty and Associates

E. A. Gallagher Non Destructive Testing GroupE. H. Gray, P.E. U.S. Nuclear Regulatory Commission

M. Herrle ABS Group, Incorporated*J. E. Hinkel The Lincoln Electric Company*M. J. Houle Welding Engineering Services

R. W. Jackson ConsultantA. W. Johnson A. W. Johnson and Associates

*N. K. Kanaya BEAR Testing LaboratoryR. A. LaFave, P.E. Elliott Company*B. B. MacDonald United Association

K. M. McTague Factory MutualA. S. Olivares Hartford Steam Boiler Inspection and Insurance Company*G. W. Oyler Retired

S. Panezic Canadian Welding BureauJ. F. Pike NASA Langley Research Center

*B. J. Rampolla, P.E. J. J. McMullen and AssociatesW. M. Ruof Bechtel Plant Machinery, Incorporated

*J. B. Shore Brooks AutomationA. W. Sindel Sindel and Associates

C. E. Speader, Jr. Aristech Chemical Corporation*W. J. Sperko, P.E. Sperko Engineering Services

*R. F. Waite, P.E. ConsultantR. K. Wiswesser Welder Training and Testing Institute

AWS B2D Subcommittee on Standard Welding Procedure Specifications

R. W. Jackson, Chair ConsultantL. P. Connor, Secretary American Welding Society

W. D. Doty Doty and Associates*M. J. Houle Welding Engineering Services

K. M. McTague Factory MutualB. J. Rampolla J. J. McMullen Associates

J. J. Sekely Eichleay Corporation

*Advisor

iiiCOPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 6: AWS_B2.1-1-007-02

www.bzfxw.com

Foreword

(This Foreword is not a part of AWS B2.1-1-007:2002, Standard Welding Procedure Specification (SWPS) forGas Tungsten Arc Welding of Galvanized Steel (M-1), 18 through 10 Gauge, in the As-Welded Condition,

with or without Backing, but is included for informational purposes only.)

The American Welding Society and the Welding Research Council have joined in a cooperative effort to generatestandard welding procedures for industry. The need for pretested welding procedures that are supported by adequate testdata and that satisfy the technical requirements for the commonly used construction codes and specifications has beenexpressed by many individuals and organizations. The purpose of a welding procedure qualification is to provide testdata for assessing the properties of a weld joint.

This Standard Welding Procedure Specification is an outgrowth of the coordinated work of the Welding ProceduresCommittee of WRC and the Committee on Welding Qualification of the AWS. The Welding Procedures Committee hasprovided the test data documented on the Summary of Procedure Qualification Records, which are available from theWelding Research Council.

The welding terms used in this specification shall be interpreted in accordance with the definitions given in the latestedition of AWS A3.0, Standard Welding Terms and Definitions. Welding symbols shall be those shown in the latest editionof AWS A2.4, Standard Symbols for Welding, Brazing, and Nondestructive Examination.

The AWS B2 Committee on Welding Qualification was formed in 1979 to provide welding standards concerning thesubject of qualification. The primary document developed by this committee is AWS B2.1, Standard for Welding Procedureand Performance Qualification. This document established the foundation and framework for Standard Welding ProcedureSpecifications.

The first two Standard Welding Procedure Specifications were published in 1990. Since then SWPSs are continuingto be developed and published by the American Welding Society. This is the first revision of B2.1.007.

Comments and suggestions for the improvement of this standard are welcomed. They should be sent to the Secretary,AWS B2 Committee on Welding Qualification, American Welding Society, 550 N.W. LeJeune Road, Miami, FL 33126.

ivCOPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 7: AWS_B2.1-1-007-02

www.bzfxw.com

AWS B2.1-1-007:2002Page 1 of 12

Standard Welding Procedure Specification (SWPS)

Gas Tungsten Arc Welding of Galvanized Steel (M-1),18 through 10 Gauge, in the As-Welded Condition,

with or without Backing

Welding Research Council1—Supporting PQR Numbers: 056B, 057A, 058A, 059A, 060A, 061A, 062B, 063A, 064A, 065A, 066A, 067A

Requirements forApplication of SWPSs

Scope. The data to support this Standard WeldingProcedure Specification (SWPS) have been derivedfrom the above listed Procedure QualificationRecords (PQRs) which were reviewed and validatedunder the auspices of the Welding Research Coun-cil. This SWPS is not valid using conditions and vari-ables outside the ranges listed. The AmericanWelding Society considers that this SWPS presentsinformation for producing an acceptable weld usingthe conditions and variables listed. The user needsa significant knowledge of welding and accepts fullresponsibility for the performance of the weld and forproviding the engineering capability, qualified per-sonnel, and proper equipment to implement thisSWPS.

Application. This SWPS is to be used only as per-mitted by the applicable fabrication document(s)[such as code, specification, or contract docu-ment(s)]. The fabrication document(s) should spec-ify the engineering requirements such as design,need for heat treatment, fabricating tolerances, qual-ity control, and examination and tests applicable tothe end product.

User’s Responsibility. A SWPS does not replaceor substitute for fabrication codes, specifications,

contract requirements, or capability and judgmenton the part of the user. A SWPS is to be used onlyas permitted by the applicable fabrication code,specification, or contract document.

The ability to produce production welds havingproperties suitable for the application depends uponsupplementing the SWPS with appropriate perfor-mance qualification tests and sound engineeringjudgment. The user is responsible for the quality andperformance of the final product in accordance withthe provisions of the fabrication document(s).

Supplementary Instructions. To adapt this SWPSto a specific application, a user may issue supple-mentary instructions. Such instructions may consistof tighter fit-up tolerances, higher minimum preheattemperature or any other instructions necessary toproduce a weldment that meets the requirements ofthe fabrication document(s). These instructions shallnot be less restrictive than provided in the SWPS.

Safety. Safety precautions shall conform to the lat-est edition of ANSI Z49.1, Safety in Welding, Cutting,and Allied Processes, published by the AmericanWelding Society.

This specification may involve hazardous mate-rials, operations, and equipment. The specificationdoes not purport to address all of the safety prob-lems associated with its use. It is the responsibility ofthe user to establish appropriate safety and healthpractices. The user should determine the applicabil-ity of any regulatory limitations prior to use.

1. Welding Research Council, Three Park Avenue, 27thFloor, New York, NY 10016-5902.

Permission to reproduce for intra-company use only is granted by the American Welding SocietyCOPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 8: AWS_B2.1-1-007-02

www.bzfxw.com

AWS B2.1-1-007:2002Page 2 of 12

Standard Welding Procedure Specification (SWPS)

LIMITATIONS

This procedure is not qualified for Notch Toughness or PWHT applications.

WELDING PROCESSES

Welding Process: GTAW (Gas Tungsten Arc Welding)Method of Application: Manual

BASE METALS

Base Metal:2 Galvanized Steel3, M-1 Group 1 with a G90 (max.) Coating thicknessThickness Range:4 Groove Weld: 18 gauge (0.0516 in.) through 10 gauge (0.1382 in.)

Fillet Weld: 18 gauge (0.0516 in.) through 10 gauge (0.1382 in.)Coating: G90 (max.). Removal of coating prior to welding is not required.

FILLER METALS

Filler Metal Specification:2 AWS A5.18 or ASME SFA 5.18A Number 1, F Number 6

Classification: ER70S-2 or 3Deposit Thickness Range: Groove Weld: Sheet metal thickness plus reinforcement, maximum

Fillet Weld Leg: Sheet metal thickness, minimumMaximum Bead Thickness: Sheet metal thickness plus reinforcementConsumable Inserts: Not PermittedPenetration Enhancing Flux: Not Permitted

JOINT DESIGNS

Allowable Joint Designs: See Figure 1.Backing: Optional

Backing Material: Uncoated or galvanized steel2, M-1, P-1, or S-1. Nonmetallic ornonfusing metal retainers are not permitted.

POSITIONS

Welding Positions: AllVertical Progression: Uphill or Downhill

2. M and P numbers for base metal and F and A numbers for filler metal and weld metal, respectively, are as detailed inAWS B2.1 and ASME Boiler and Pressure Vessel Code, Section IX.3. WARNING: Use enough ventilation, exhaust at the arc, or both, to keep zinc fumes from the breathing zone andsurrounding general area. See ANSI Z49.1, Safety in Welding, Cutting, and Allied Processes.4. See the applicable ASTM Specification for base metal thickness tolerances.

Permission to reproduce for intra-company use only is granted by the American Welding SocietyCOPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 9: AWS_B2.1-1-007-02

www.bzfxw.com

Standard Welding Procedure Specification (SWPS)

AWS B2.1-1-007:2002Page 3 of 12

GAS

Torch Shielding Gas: Welding Grade Argon or AWS A5.32, Class SG-AFlow Rate: 15 to 25 ft3/hGas Nozzle Size: 1/4 in. to 5/8 in I.D.Backing/Root Shielding Gas: NoneTrailing Gas: None

PREHEAT AND INTERPASS TEMPERATURE

Preheat Temperature: 50°F minimum, 120°F maximumInterpass Temperature: No maximumPreheat Maintenance: Continuous or special heating not required

POSTWELD HEAT TREATMENT

Postweld Heat-Treatment: None (not qualified for PWHT)

TUNGSTEN ELECTRODES

Specification: AWS A5.12, ASME SFA 5.12Classification: EWTh-2, EWLa-1.5Size: 1/8 in. diameter max. sharpened to a point.

ELECTRICAL CHARACTERISTICS

*Amperage is not to exceed the capacity of the Tungsten Electrodes.

Pulsing Current: Not permitted

TECHNIQUE

Beads: Stringer or weavePeening: NoInitial Cleaning: Mechanical or chemical, joint shall be dry prior to weldingInterpass Cleaning: Mechanical only

Base Metal

Filler Metal Amperes* Current

Classification Dia. (in.) Groove Fillet Type/Polarity

18 ga.17 ga.16 ga.15 ga.14 ga.13 ga.12 ga.11 ga.10 ga.

ER70S-2 or 3ER70S-2 or 3ER70S-2 or 3ER70S-2 or 3ER70S-2 or 3ER70S-2 or 3ER70S-2 or 3ER70S-2 or 3ER70S-2 or 3

1/161/161/161/163/323/323/323/323/32

45–6548–6951–7354–7757–8160–8563–9066–9570–100

50–5559–6468–7377–8286–9195–100

105–110115–120125–130

DCEN (Straight)DCEN (Straight)DCEN (Straight)DCEN (Straight)DCEN (Straight)DCEN (Straight)DCEN (Straight)DCEN (Straight)DCEN (Straight)

Permission to reproduce for intra-company use only is granted by the American Welding SocietyCOPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 10: AWS_B2.1-1-007-02

www.bzfxw.com

AWS B2.1-1-007:2002Page 4 of 12

Standard Welding Procedure Specification (SWPS)

TECHNIQUE (Cont’d)

Single or Multiple Electrodes: SingleSingle or Multipass: EitherBackgouging: Not required, mechanical or thermal if used.Repair: Defects in welds shall be removed by mechanical or thermal

methods. The repair cavity may differ in contour and dimensionsfrom a normal joint preparation and may present different restraintconditions.

COMPANY NAME _______________________________________________________________________

In the name of the Company stated above, I accept full responsibility for the application of this SWPS for usewith:

________________________________________________________________ Dated ________________Fabrication Document(s): (Such as Code, Specification, or Contract Document)

Date ____________ Approved By ___________________________________ Title__________________

Permission to reproduce for intra-company use only is granted by the American Welding SocietyCOPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 11: AWS_B2.1-1-007-02

www.bzfxw.com

Standard Welding Procedure Specification (SWPS)

Figure 1—Allowable Joint Designs

AWS B2.1-1-007:2002Page 5 of 12

JOINT 1

JOINT 2

JOINT 3

JOINT 4

JOINT 5

JOINT 6

Permission to reproduce for intra-company use only is granted by the American Welding SocietyCOPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 12: AWS_B2.1-1-007-02

www.bzfxw.com

Standard Welding Procedure Specification (SWPS)

Figure 1 (Continued)—Allowable Joint Designs

AWS B2.1-1-007:2002Page 6 of 12

JOINT 7

JOINT 8

JOINT 9

JOINT 10

JOINT 11

JOINT 12

Metric Conversions

in. mm °F °C ft3/h L/min.

0.05160.1382

1/161/321/81/45/8

1.3103.5101.60002.40003.20006.4000

15.9000

50120

1049

1525

7.111.8

Permission to reproduce for intra-company use only is granted by the American Welding SocietyCOPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 13: AWS_B2.1-1-007-02

www.bzfxw.com

Standard Welding Procedure Specification (SWPS)

AWS B2.1-1-007:2002Page 7 of 12

A1. IntroductionThe AWS Board of Directors has adopted a policy

whereby all official interpretations of AWS standardswill be handled in a formal manner. Under that policy, allinterpretations are made by the committee that is respon-sible for the standard. Official communication concern-ing an interpretation is through the AWS staff memberwho works with that committee. The policy requires thatall requests for an interpretation be submitted in writing.Such requests will be handled as expeditiously as possi-ble, but due to the complexity of the work and the proce-dures that must be followed, some interpretations mayrequire considerable time.

A2. ProcedureAll inquiries must be directed to:

Managing Director, Technical ServicesAmerican Welding Society550 N.W. LeJeune RoadMiami, FL 33126

All inquiries must contain the name, address, and af-filiation of the inquirer, and they must provide enough in-formation for the committee to fully understand the pointof concern in the inquiry. Where that point is not clearlydefined, the inquiry will be returned for clarification. Forefficient handling, all inquiries should be typewritten andshould also be in the format used here.

A2.1 Scope. Each inquiry must address one single pro-vision of the standard, unless the point of the inquiry

involves two or more interrelated provisions. That provi-sion must be identified in the scope of the inquiry, alongwith the edition of the standard that contains the provi-sions or that the inquirer is addressing.

A2.2 Purpose of the Inquiry. The purpose of the inquirymust be stated in this portion of the inquiry. The purposecan be either to obtain an interpretation of a standardrequirement, or to request the revision of a particular pro-vision in the standard.

A2.3 Content of the Inquiry. The inquiry should beconcise, yet complete, to enable the committee to quicklyand fully understand the point of the inquiry. Sketchesshould be used when appropriate and all paragraphs, fig-ures, and tables (or the Annex), which bear on the in-quiry must be cited. If the point of the inquiry is to obtaina revision of the standard, the inquiry must provide tech-nical justification for that revision.

A2.4 Proposed Reply. The inquirer should, as a pro-posed reply, state an interpretation of the provision that isthe point of the inquiry, or the wording for a proposedrevision, if that is what inquirer seeks.

A3. Interpretation of Provisions of the Standard

Interpretations of provisions of the standard are madeby the relevant AWS Technical Committee. The secretaryof the committee refers all inquiries to the chairman ofthe particular subcommittee that has jurisdiction over theportion of the standard addressed by the inquiry. Thesubcommittee reviews the inquiry and the proposed replyto determine what the response to the inquiry should be.

Annex A

Guidelines for Preparation of Technical Inquiriesfor AWS Technical Committees

(This Annex is not a part of AWS B2.1-1-007:2002, Standard Welding Procedure Specification (SWPS) forGas Tungsten Arc Welding of Galvanized Steel (M-1), 18 through 10 Gauge, in the As-Welded Condition,

with or without Backing, but is included for informational purposes only.)

Permission to reproduce for intra-company use only is granted by the American Welding Society

Nonmandatory Annex

COPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 14: AWS_B2.1-1-007-02

www.bzfxw.com

AWS B2.1-1-007:2002Page 8 of 12

Standard Welding Procedure Specification (SWPS)

Following the subcommittee’s development of the re-sponse, the inquiry and the response are presented to theentire committee for review and approval. Upon approvalby the committee, the interpretation will be an official in-terpretation of the Society, and the secretary will transmitthe response to the inquirer and to the Welding Journalfor publication.

A4. Publication of InterpretationsAll official interpretations will appear in the Welding

Journal.

A5. Telephone InquiriesTelephone inquiries to AWS Headquarters concerning

AWS standards should be limited to questions of a gen-eral nature or to matters directly related to the use of thestandard. The Board of Directors’ policy requires that allAWS staff members respond to a telephone request for

an official interpretation of any AWS standard with theinformation that such an interpretation can be obtainedonly through a written request. The Headquarters staffcannot provide consulting services. The staff can, how-ever, refer a caller to any of those consultants whosenames are on file at AWS Headquarters.

A6. The AWS Technical CommitteeThe activities of AWS Technical Committees in regard

to interpretations, are limited strictly to the interpretationof provisions of standards prepared by the committee orto consideration of revisions to existing provisions on thebasis of new data or technology. Neither the committeenor the staff is in a position to offer interpretive or con-sulting services on: (1) specific engineering problems, or(2) requirements of standards applied to fabrications out-side the scope of the document or points not specificallycovered by the standard. In such cases, the inquirer shouldseek assistance from a competent engineer experienced inthe particular field of interest.

Permission to reproduce for intra-company use only is granted by the American Welding SocietyCOPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 15: AWS_B2.1-1-007-02

www.bzfxw.com

AWS B2.1-1-007:2002Page 9 of 12

List of AWS Documents on Welding Procedure and Performance Qualification

Designation Title

B2.1:2000 Specification for Welding Procedure and Performance Qualification

B2.1-001-90 Standard Welding Procedure Specification (WPS) for Shielded Metal Arc Welding of CarbonSteel (M-1/P-1, Group 1 or 2), 3/16 through 3/4 inch in the As-Welded Condition, With Backing

B2.1-002-90 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding of CarbonSteel (M-1/P-1, Group 1 or 2), 3/16 through 7/8 inch in the As-Welded Condition, With orWithout Backing

B2.1-1-003:2002 Standard Welding Procedure Specification (SWPS) for Gas Metal Arc Welding (Short CircuitingTransfer Mode) of Galvanized Steel (M-1), 18 through 10 Gauge, in the As-Welded Condition,with or without Backing

B2.1-1-004:2002 Standard Welding Procedure Specification (SWPS) for Gas Metal Arc Welding (Short CircuitingTransfer Mode) of Carbon Steel (M-1, Group 1), 18 through 10 Gauge, in the As-WeldedCondition, with or without Backing

B2.1-8-005:2002 Standard Welding Procedure Specification (SWPS) for Gas Metal Arc Welding (Short CircuitingTransfer Mode) of Austenitic Stainless Steel (M-8, P-8, or S-8), 18 through 10 Gauge, in theAs-Welded Condition, with or without Backing

B2.1-1/8-006:2002 Standard Welding Procedure Specification (SWPS) for Gas Metal Arc Welding (Short CircuitingTransfer Mode) of Carbon Steel to Austenitic Stainless Steel (M-1 to M-8, P-8, or S-8), 18through 10 Gauge, in the As-Welded Condition, with or without Backing

B2.1-1-007:2002 Standard Welding Procedure Specification (SWPS) for Gas Tungsten Arc Welding of Galva-nized Steel (M-1), 18 through 10 Gauge, in the As-Welded Condition, with or without Backing

B2.1-1-008:2002 Standard Welding Procedure Specification (SWPS) for Gas Tungsten Arc Welding of CarbonSteel (M-1, P-1, or S-1), 18 through 10 Gauge, in the As-Welded Condition, with or withoutBacking

B2.1-8-009:2002 Standard Welding Procedure Specification (SWPS) for Gas Tungsten Arc Welding of AusteniticStainless Steel (M-8, P-8, or S-8), 18 through 10 Gauge, in the As-Welded Condition, with orwithout Backing

B2.1-1/8-010:2002 Standard Welding Procedure Specification (SWPS) for Gas Tungsten Arc Welding of CarbonSteel to Austenitic Stainless Steel (M-1, P-1, or S-1 to M-8, P-8, or S-8), 18 through 10 Gauge,in the As-Welded Condition, with or without Backing

B2.1-1-011:2002 Standard Welding Procedure Specification (SWPS) for Shielded Metal Arc Welding of Galva-nized Steel (M-1), 10 through 18 Gauge, in the As-Welded Condition, with or without Backing

B2.1-1-012:2002 Standard Welding Procedure Specification (SWPS) for Shielded Metal Arc Welding of CarbonSteel (M-1, P-1, or S-1 to M-1, P-1, or S-1), 10 through 18 Gauge, in the As-Welded Condition,with or without Backing

B2.1-8-013:2002 Standard Welding Procedure Specification (SWPS) for Shielded Metal Arc Welding ofAustenitic Stainless Steel (M-8/P-8/S-8, Group 1), 10 through 18 Gauge, in the As-WeldedCondition, with or without Backing

B2.1-1/8-014:2002 Standard Welding Procedure Specification (SWPS) for Shielded Metal Arc Welding of CarbonSteel to Austenitic Stainless Steel (M-1 to M-8/P-8/S-8, Group 1), 10 through 18 Gauge, inthe As-Welded Condition, with or without Backing

B2.1-22-015:2002 Standard Welding Procedure Specification (SWPS) for Gas Tungsten Arc Welding of Aluminum(M/P/S-22 to M/P/S-22), 18 through 10 Gauge, in the As-Welded Condition, with or withoutBacking

Permission to reproduce for intra-company use only is granted by the American Welding SocietyCOPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 16: AWS_B2.1-1-007-02

www.bzfxw.com

Designation Title

AWS B2.1-1-007:2002Page 10 of 12

B2.1-1-016-94 Standard Welding Procedure Specification (WPS) for Shielded Metal Arc Welding of CarbonSteel (M-1/P-1/S-1, Group 1 or 2), 1/8 through 1-1/2 inch Thick, E7018, As-Welded or PWHTCondition

B2.1-1-017-94 Standard Welding Procedure Specification (WPS) for Shielded Metal Arc Welding of CarbonSteel (M-1/P-1/S, Group 1 or 2), 1/8 through 1-1/2 inch Thick, E6010, As-Welded or PWHTCondition

B2.1-1-018-94 Standard Welding Procedure Specification (WPS) for Self-Shielded Flux Cored Arc Weldingof Carbon Steel (M-1/P-1/S-1, Group 1 or 2), 1/8 through 1-1/2 inch Thick, E71T-8, As-WeldedCondition

B2.1-1-019-94 Standard Welding Procedure Specification (WPS) for CO2 Shielded Flux Cored Arc Weldingof Carbon Steel (M-1/P-1/S-1, Group 1 or 2), 1/8 through 1-1/2 inch Thick, E70T-1 andE71T-1, As-Welded Condition

B2.1-1-020-94 Standard Welding Procedure Specification (WPS) for 75% Ar/25% CO2 Shielded Flux CoredArc Welding of Carbon Steel (M-1/P-1/S-1, Group 1 or 2), 1/8 through 1-1/2 inch Thick,E70T-1 and E71T-1, As-Welded or PWHT Condition

B2.1-1-021-94 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding Followedby Shielded Metal Arc Welding of Carbon Steel (M-1/P-1/S-1, Group 1 or 2), 1/8 through1-1/2 inch Thick, ER70S-2 and E7018, As-Welded or PWHT Condition

B2.1-1-022-94 Standard Welding Procedure Specification (WPS) for Shielded Metal Arc Welding of CarbonSteel (M-1/P-1/S-1, Group 1 or 2), 1/8 through 1-1/2 inch Thick, E6010 (Vertical Uphill)Followed by E7018, As-Welded or PWHT Condition

B2.1-8-023-94 Standard Welding Procedure Specification (WPS) for Shielded Metal Arc Welding ofAustenitic Stainless Steel (M-8/P-8/S-8, Group 1), 1/8 through 1-1/2 inch Thick, As-WeldedCondition

B2.1-8-024:2001 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding of AusteniticStainless Steel (M-8/P-8/S-8, Group 1), 1/16 through 1-1/2 inch Thick, ER3XX, As-WeldedCondition, Primarily Plate and Structural Applications

B2.1-8-025:2001 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding followedby Shielded Metal Arc Welding of Austenitic Stainless Steel (M-8/P-8/S-8, Group 1), 1/8through 1-1/2 inch Thick, ER3XX and E3XX-XX, As-Welded Condition, Primarily Plate andStructural Applications

B2.1-1-026-94 Standard Welding Procedure Specification (WPS) for Shielded Metal Arc Welding of CarbonSteel (M-1/P-1/S-1, Group 1 or 2). 1/8 through 1-1/2 inch Thick, E6010 (Vertical Downhill)Followed by E7018, As-Welded or PWHT Condition

B2.1-1-027:1998 Standard Welding Procedure Specification (WPS) for Self-Shielded Flux Cored Arc Weldingof Carbon Steel (M-1/P-1/S-1, Group 1 or 2), 1/8 through 1/2 inch Thick, E71T-11, As-WeldedCondition

B2.1-1-201-96 Standard Welding Procedure Specification (WPS) for Shielded Metal Arc Welding of CarbonSteel (M-1/P-1/S-1, Group 1 or 2), 1/8 through 3/4 inch Thick, E6010 (Vertical Uphill)Followed by E7018 (Vertical Uphill), As-Welded Condition, Primarily Pipe Applications

B2.1-1-202-96 Standard Welding Procedure Specification (WPS) for Shielded Metal Arc Welding of CarbonSteel (M-1/P-1/S-1, Group 1 or 2), 1/8 through 3/4 inch Thick, E6010 (Vertical Downhill)Followed by E7018 (Vertical Uphill), As-Welded Condition, Primarily Pipe Applications

Permission to reproduce for intra-company use only is granted by the American Welding SocietyCOPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 17: AWS_B2.1-1-007-02

www.bzfxw.com

AWS B2.1-1-007:2002Page 11 of 12

Designation Title

B2.1-1-203-96 Standard Welding Procedure Specification (WPS) for Shielded Metal Arc Welding of CarbonSteel (M-1/P-1/S-1, Group 1 or 2), 1/8 through 3/4 inch Thick, E6010 (Vertical Uphill), As-Welded Condition, Primarily Pipe Applications

B2.1-1-204-96 Standard Welding Procedure Specification (WPS) for Shielded Metal Arc Welding of CarbonSteel (M-1/P-1/S-1, Group 1 or 2), 1/8 through 3/4 inch Thick, E6010 (Vertical Downhill Rootwith the Balance Vertical Uphill), As-Welded Condition, Primarily Pipe Applications

B2.1-1-205-96 Standard Welding Procedure Specification (WPS) for Shielded Metal Arc Welding of CarbonSteel (M-1/P-1/S-1, Group 1 or 2), 1/8 through 1-1/2 inch Thick, E6010 (Vertical Uphill)Followed by E7018 (Vertical Uphill), As-Welded or PWHT Condition, Primarily PipeApplications

B2.1-1-206-96 Standard Welding Procedure Specification (WPS) for Shielded Metal Arc Welding of CarbonSteel (M-1/P-1/S-1, Group 1 or 2), 1/8 through 1-1/2 inch Thick, E6010 (Vertical Downhill) Fol-lowed by E7018 (Vertical Uphill), As-Welded or PWHT Condition, Primarily Pipe Applications

B2.1-1-207-96 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding of CarbonSteel (M-1/P-1/S-1, Group 1 or 2), 1/8 through 1-1/2 inch Thick, ER70S-2, As-Welded orPWHT Condition, Primarily Pipe Applications

B2.1-1-208-96 Standard Welding Procedure Specification (WPS) for Shielded Metal Arc Welding of CarbonSteel (M-1/P-1/S-1, Group 1 or 2), 1/8 through 1-1/2 inch Thick, E7018, As-Welded or PWHTCondition, Primarily Pipe Applications

B2.1-1-209-96 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding Followedby Shielded Metal Arc Welding of Carbon Steel (M-1/P-1/S-1, Group 1 or 2), 1/8 through1-1/2 inch Thick, ER70S-2 and E7018, As-Welded or PWHT Condition, Primarily PipeApplications

B2.1-1-210:2001 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding with Con-sumable Insert Root of Carbon Steel (M-1/P-1/S-1, Group 1 or 2), 1/8 through 1-1/2 inchThick, INMs-1 and ER70S-2, As-Welded or PWHT Condition, Primarily Pipe Applications

B2.1-1-211:2001 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding withConsumable Insert Root followed by Shielded Metal Arc Welding of Carbon Steel (M-1/P-1/S-1, Group 1 or 2), 1/8 through 1-1/2 inch Thick, INMs-1, ER70S-2, and E7018, As-WeldedCondition, Primarily Pipe Applications

B2.1-8-212:2001 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding of AusteniticStainless Steel (M-8/P-8/S-8, Group 1), 1/16 through 1-1/2 inch Thick, ER3XX, As-WeldedCondition, Primarily Pipe Applications

B2.1-8-213-97 Standard Welding Procedure Specification (WPS) for Shielded Metal Arc Welding of AusteniticStainless Steel (M-8/P-8/S-8, Group 1), 1/8 through 1-1/2 inch Thick, E3XX-XX, As-WeldedCondition, Primarily Pipe Applications

B2.1-8-214:2001 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding followed byShielded Metal Arc Welding of Austenitic Stainless Steel (M-8/P-8/S-8, Group 1), 1/8 through1-1/2 inch Thick, ER3XX and E3XX-XX, As-Welded Condition, Primarily Pipe Applications

B2.1-8-215:2001 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding withConsumable Insert Root of Austenitic Stainless Steel (M-8/P-8/S-8, Group 1), 1/8 through1-1/2 inch Thick, IN3XX and ER3XX, As-Welded Condition, Primarily Pipe Applications

B2.1-8-216:2001 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding withConsumable Insert Root followed by Shielded Metal Arc Welding of Austenitic Stainless Steel(M-8/P-8/S-8, Group 1), 1/8 through 1-1/2 inch Thick, IN3XX, ER3XX, and E3XX-XX, As-Welded Condition, Primarily Pipe Applications

Permission to reproduce for intra-company use only is granted by the American Welding SocietyCOPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---

Page 18: AWS_B2.1-1-007-02

www.bzfxw.com

Designation Title

AWS B2.1-1-007:2002Page 12 of 12

B2.1-4-217:1999 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding ofChromium-Molybdenum Steel (M-4/P-4, Group 1 or 2), ER80S-B2, 1/8 through 1/2 in.Thick, As-Welded Condition, 1/8 through 3/4 in. Thick, PWHT Condition, Primarily PipeApplications

B2.1-4-218:1999 Standard Welding Procedure Specification (WPS) for Shielded Metal Arc Welding ofChromium-Molybdenum Steel (M-4/P-4, Group 1 or 2), E8018-B2, 1/8 through 1/2 in.Thick, As-Welded Condition, 1/8 through 1-1/2 in. Thick, PWHT Condition, Primarily PipeApplications

B2.1-4-219:1999 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding followed byShielded Metal Arc Welding of Chromium-Molybdenum Steel (M-4/P-4, Group 1 or 2), 1/8through 1/2 in. Thick, As-Welded Condition, 1/8 through 1-1/2 in. Thick, PWHT Condition,ER80S-B2 and E8018-B2, Primarily Pipe Applications

B2.1-4-220:1999 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding (Consum-able Insert Root) of Chromium-Molybdenum Steel (M-4/P-4, Group 1 or 2), E8018-B2, 1/8through 1/2 in. Thick, As-Welded Condition, 1/8 through 3/4 in. Thick, PWHT Condition,IN515 and ER80S-B2, Primarily Pipe Applications

B2.1-4-221:1999 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding (Consum-able Insert Root) followed by Shielded Metal Arc Welding of Chromium-Molybdenum Steel(M-4/P-4, Group 1 or 2), 1/8 through 1/2 in. Thick, As-Welded Condition, 1/8 through 1-1/2 in.Thick, PWHT Condition, IN515, ER80S-B2, and E8018-B2, Primarily Pipe Applications

B2.1-5A-222:1999 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding ofChromium-Molybdenum Steel (M-5A/P-5A), ER90S-B3, 1/8 through 1/2 in. Thick, As-WeldedCondition, 1/8 through 3/4 in. Thick, PWHT Condition, Primarily Pipe Applications

B2.1-5A-223:1999 Standard Welding Procedure Specification (WPS) for Shielded Metal Arc Welding ofChromium-Molybdenum Steel (M-5A/P-5A), E9018-B3, 1/8 through 1/2 in. Thick, As-WeldedCondition, 1/8 through 1-1/2 in. Thick, PWHT Condition, Primarily Pipe Applications

B2.1-5A-224:1999 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding followed byShielded Metal Arc Welding of Chromium-Molybdenum Steel (M-5A/P-5A), 1/8 through 1/2 in.Thick, As-Welded Condition, 1/8 through 1-1/2 in. Thick, PWHT Condition, ER90S-B3 andE9018-B3, Primarily Pipe Applications

B2.1-5A-225:1999 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding (Consum-able Insert Root) of Chromium-Molybdenum Steel (M-5A/P-5A), 1/8 through 1/2 in. Thick,As-Welded Condition, 1/8 through 3/4 in. Thick, PWHT Condition, IN521 and ER90S-B3,Primarily Pipe Applications

B2.1-5A-226:1999 Standard Welding Procedure Specification (WPS) for Gas Tungsten Arc Welding (Consum-able Insert Root) followed by Shielded Metal Arc Welding of Chromium-Molybdenum Steel(M-5A/P-5A), 1/8 through 1/2 in. Thick, As-Welded Condition, 1/8 through 1-1/2 in. Thick,PWHT Condition, IN521, ER90S-B3, and E9018-B3, Primarily Pipe Applications

For ordering information, contact Global Engineering Documents, an Information Handling Services (IHS) Group company,15 Inverness Way East, Englewood, Colorado 80112-5776; telephones: (800) 854-7179, (303) 397-7956; fax (303) 397-2740; Internet: www. global.ihs.com.

Permission to reproduce for intra-company use only is granted by the American Welding SocietyCOPYRIGHT 2003; American Welding Society, Inc.

Document provided by IHS Licensee=Fluor Corp/2110503106, User=, 09/04/200301:37:50 MDT Questions or comments about this message: please call the DocumentPolicy Group at 1-800-451-1584.

--`,``,,``,`,``````,,,`,`,```-`-`,,`,,`,`,,`---