Upload
shannon-briggs
View
213
Download
0
Embed Size (px)
Citation preview
Avoided Costs of Generation
Current Avoided Cost Calculator
Calculates the long-run, all-in cost of a Combined Cycle Gas Turbine (CCGT) running 92% of the year.
• All-in cost is total fuel, O&M, and levelized capital costs of a new generator.
• All-in cost is then shaped into hourly profile from the CA PX day-ahead market price
• Capacity values included in the hourly market price.
Proposed Update
• Calculator updated to use new calculator currently used for Distributed Generation and Demand Response
• Transmission & Distribution avoided costs unchanged but input values updated to reflect more recent utility filings.
• Gas and electricity price inputs updated.• Discount rate changed from after-tax Weighted
Average Cost of Capital to before-tax WACC.
Avoided Costs of Electricity Generation has six component avoided costs
1. Generation capacity
2. Generation energy
3. Ancillary services
4. T&D capacity
5. Environmental (GHG) costs
6. 33% Renewables (RPS) costs
Avoided Costs of Generation Capacity• Prior to 2017, interpolated from the resource adequacy
value of $28.07/kW-yr in 2008 – the actual cost of capacity.
• 2017 and beyond, equal to fixed costs of a new CT less the net revenues that the CT would attain from selling to the real-time energy and ancillary service markets.
• 2017 is the Resource Balance Year – when system demand will equal system capacity.
• Allocated over the top 259 hours of the system load to roughly reflect peak hours.
• Generally results in more avoided capacity costs than current model, so that peakier measures are more cost-effective.
Avoided Cost of Energy
• Prior to resource balance year, the average energy cost is based on latest NYMEX market price forecast available.
• The long-run energy market price is used for resource balance and subsequent years. It begins with the 2010 MRTU day-ahead market price escalated to the natural gas burner tip forecast.
• Annual long-run energy market price is set so that the CCGT’s energy market revenue plus the capacity market payments equal the fixed and variable costs of the CCGT
Avoided Cost of T&D Capacity
• Potential deferral of T&D network upgrades from reduction in local peak loads
• Updated by climate zone for PG&E, from its 2011 GRC Phase II, Jan. 7, 2011.
• Updated at system level for SCE and SDG&E.
Avoided GHG costs
• Estimates of avoided CO2 emissions of energy saved.
• Uses the Synapse Consulting forecast• No longer uses an adder like the current
methodology• Note: took out NOX and PM-10 because
those are now captured in the capital costs of the new plants used to set the long-run cost of energy and capacity.
Avoided RPS costs
• Energy savings result in a decrease in the 33% renewables requirement, which results in additional savings.
• Based on the Renewable Premium, which is the difference between the cost of a typical group of renewables and the cost of conventional (CCGT) generation.