8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
1/140
AUSTRALIAN GUIDELINES 23
FOR WATER RECYCLING:MANAGING HEALTH AND
ENVIRONMENTAL RISKS
(PHASE 2)
STORMWATER HARVESTING
AND REUSE
July 2009
Natural Resource Management Ministerial Council
Environment Protection and Heritage Council
National Health and Medical Research Council
N A T I O N A L W A T E R Q U A L I T Y M A N A G E M E N T S T R A T E G Y
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
2/140
Natural Resource Management Ministerial Council
Environment Protection and Heritage Council
National Health and Medical Research Council
Australian Guidelines for Water RecyclingStormwater Harvesting and Reuse
National Water Quality Management Strategy
Document No 23
July 2009
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
3/140
Web copy: ISBN 1 921173 45 9
Print copy: ISBN 1 921173 44 0
A publication of the Natural Resource Management Ministerial Council, the Environment
Protection and Heritage Council, and the National Health and Medical Research Council.
July 2009
This work is copyright. It may be reproduced in part subject to the inclusion ofacknowledgment of the source and no commercial sale.
The contents of this document have been compiled using a range of source materials; whilereasonable care has been taken in its compilation, the member governments of the NaturalResource Management Ministerial Council, the Environment Protection and HeritageCouncil, and the National Health and Medical Research Council, and the organisations andindividuals involved with the compilation of this document, shall not be liable for anyconsequences that may result from using the contents of this document.
Edited and produced by Biotext, Canberra
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
4/140
iii
Contents
1 Introduction ............................................................................................................. 1
1.1 Harvesting and reuse of stormwater and roofwater ......................................... 1
1.2 Purpose and scope of this document ............................................................... 2
1.3 Relationship to other national guidelines ........................................................ 3
1.4 Relationship to state and territory legislation and guidelines ........................... 4
1.5 How to use these guidelines ............................................................................ 5
2 Roofwater reuse ....................................................................................................... 9
2.1 Application of standard approach ................................................................... 9
2.2 Preparatory steps .......................................................................................... 10
2.2.1 Organisational support ...................................................................... 10
2.2.2 Legal requirements ........................................................................... 10
2.2.3 Roof characteristics ........................................................................... 10
2.3 Project design ............................................................................................... 11
2.3.1 Tanks ................................................................................................ 112.3.2 Gutters .............................................................................................. 12
2.3.3 Pipework and connections to mainswater .......................................... 12
2.4 Operations, maintenance and monitoring ...................................................... 13
2.5 Nonresidential roofwater reuse checklist....................................................... 15
3 Stormwater reuse ................................................................................................... 17
3.1 Reuse application ......................................................................................... 17
3.2 Preparatory steps .......................................................................................... 21
3.2.1 Organisational support ...................................................................... 21
3.2.2 Legal requirements ........................................................................... 21
3.2.3 Planning approval ............................................................................. 22
3.3 Project design ............................................................................................... 22
3.3.1 Stormwater extraction ....................................................................... 22
3.3.2 Stormwater quality risk management ................................................ 23
3.3.3 Stormwater storage ........................................................................... 27
3.3.4 Distribution pipework ....................................................................... 283.3.5 Irrigation system design .................................................................... 29
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
5/140
iv Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
3.4 Operations, maintenance and monitoring ................................................. 30
3.4.1 Qualified staff ................................................................................... 30
3.4.2 Scheme management plan ................................................................. 30
3.4.3 Scheme commissioning, validation and verification .......................... 31
3.4.4 Catchment surveillance ..................................................................... 32
3.4.5 Managing chemicals ......................................................................... 33
3.4.6 Incident response .............................................................................. 33
3.4.7 Occupational health and safety .......................................................... 34
3.4.8 Managing storage tanks .................................................................... 34
3.4.9 Access control .................................................................................. 36
3.4.10 Irrigation scheduling ......................................................................... 36
3.4.11 Operational monitoring ..................................................................... 37
3.4.12 Reporting .......................................................................................... 38
3.4.13 Record keeping ................................................................................. 38
3.4.14 Auditing scheme operations .............................................................. 38
3.4.15 Continuous improvement .................................................................. 39
3.5 Additional risk management actions for projects other thanirrigation of public open spaces ................................................................. 39
3.6 Stormwater irrigation scheme checklist .................................................... 39
Glossary ........................................................................................................................... 115
Tables, figures and boxes ................................................................................................. 123
References ......................................................................................................................... 125
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
6/140
v
Abbreviations and acronyms
General
AHMC Australian Health Ministers Conference
ANZECC Australian and New Zealand Environment and Conservation Council(replaced in 2001 by EPHC and NRMMC)
ARMCANZ Agriculture and Resource Management Council of Australia and NewZealand (replaced in 2001 by NRMMC)
AS Australian Standard
CFU colony forming unit
Ct term used in disinfection to describe the product of disinfectant concentration(C in mg/L) and contact time (t in minutes)
DALY disability adjusted life year/s
EPHC Environment Protection and Heritage Council
MPN most probable number
NHMRC National Health and Medical Research Council
NRMMC Natural Resource Management Ministerial Council
NTU nephelometric turbidity units
NZS New Zealand Standard
SAR sodium adsorption ratio
UV ultraviolet
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
7/140
vi Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
Units
cm centimetre
dS/m deci-Siemens per metre
g gram
km kilometre
L litre
m metre
mg milligram
mJ millijoule
mm millimetre
nm nanometre
g microgram
S microsiemens
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
8/140
vii
Acknowledgments
The Natural Resource Management Ministerial Council, the Environment Protection andHeritage Council and the National Health and Medical Research Council acknowledge the
contributions of the individuals listed below to the development of these guidelines.
Joint Steering Committee
Chair
Mr Chris BellMr John Williamson
Environment Protection Authority, Victoria
Members
Ms Jo Beatty Department of Sustainability and Environment, VictoriaMs Jan Bowman Department of Human Services, Victoria
Dr Paul Burrell Department of Natural Resources and Water, Queensland
Dr Helen Cameron Australian Government Department of Health and Ageing
Dr David Cunliffe Department of Health, South Australia
Mr Leon English Department of Water, Western Australia
Dr Helen FoardMs Kerry Olssen
Dr Paul Smith
National Water Commission
Dr Karin LederMs Cathy Clutton
National Health and Medical Research Council
Dr Robyn MaddalenaMr Ian MarshallDr Greg Jackson
Department of Health and Ageing, Queensland
Mr Peter Marczan Department of Environment and Climate Change, New SouthWales
Dr Kaye Power Department of Health, New South Wales
Mr Neil Power Department of Water, Land and Biodiversity Conservation, SouthAustralia
Ms Nina RogersMr Michael Barry
Australian Local Government Association
Ms Chris Schweizer Australian Government Department of the Environment, Water,Heritage and the Arts
Mr Ross Young Water Services Association of Australia
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
9/140
viii Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
Stormwater Reuse Working Group
Chair
Mr Mike Sharpin Department of Environment and Climate Change, New SouthWales
Members
Ms Jessica Davison Environment Protection Authority, Victoria
Mr David Duncan Environment Protection Authority, South Australia
Mr Ted Gardner Department of Natural Resources and Water, Queensland
Ms Jacqui GoonreyMr Charles Edlington
Australian Government Department of the Environment, Water,Heritage and the Arts
Dr Grace Mitchell Bureau of Meteorology
Dr Melita Stevens Melbourne Water
Health and environmental risk consultants reporting to Working Group
Dr Daniel Deere Water Futures Pty Ltd
Dr Nick OConnor Ecos Environmental Consulting Pty Ltd
Dr Daryl Stevens Arris Pty Ltd
Supply of stormwater and roofwater quality data
Officers of the following organisations are gratefully acknowledged for their provision ofvaluable data and information:
Brisbane City Council, Queensland
Department of Water, Western Australia
Environment Protection Authority, Victoria
Kogarah Council, New South Wales
Ku-ring-gai Council, New South Wales
Manly Council, New South Wales
Melbourne Water, Victoria
Department of Health, New South Wales.
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
10/140
Acknowledgments ix
The following individuals are also gratefully acknowledged for contributing data:
John Argus Department of Water, Western Australia
Ana Deletic Institute for Sustainable Water Resources, Monash University
Tony Cartwright Sydney Water Corporation
Ted Gardner Department of Natural Resources and Water, Queensland
David McCarthy Institute for Sustainable Water Resources, Monash University
Grace Mitchell Institute for Sustainable Water Resources, Monash University
David Roser University of New South Wales
Monica Tewman Melbourne Water
Public comments
The councils wish to thank all those who provided comment during public consultation on thedraft guidelines.
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
11/140
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
12/140
1
1 Introduction
This publication is one of the three modules that comprise the second phase of theAustralianGuidelines for Water Recycling, which address health and environmental risks associatedwith water recycling (see Box 1.1 below).
The guidelines as a whole, including this module, are designed to provide an authoritativereference that can be used to support beneficial and sustainable recycling of waters generatedfrom sewage, grey water and stormwater, which represent an underused resource. Theguidelines describe and support a broad range of recycling options, without advocatingparticular choices. It is up to communities as a whole to make decisions on uses of recycledwater at individual locations. The intent of these guidelines is simply to provide the scientificbasis for implementing those decisions in a safe and sustainable manner.
Box 1.1 Summary of Australias existing and planned water recycling guidelines
National water recycling guidelines are being produced in two phases.
Phase 1
Australian Guidelines for Water Recycling: Managing Health and Environmental Risks (Natural Resource MinisterialManagement Council (NRMMC), Environment Protection and Heritage Council (EPHC), Australian Health MinistersConference (AHMC) 2006).Phase 1 of the guidelines provides a generic framework for management of recycled water quality and use that appliesto all combinations of recycled water and end uses. It also provides specific guidance on the use of treated sewage andgrey water for purposes other than drinking and environmental flows.
Phase 2
Australian Guidelines for Water Recycling: Augmentation of Drinking Water Supplies (NRMMCEPHCNationalHealth and Medical Research Council (NHMRC) 2008).The first module of Phase 2 of the guidelines extends the guidance given in Phase 1 on the planned use of recycledwater (treated sewage and stormwater) to augment drinking water supplies.
Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse.This current document is the second module of Phase 2 of the guidelines and extends the guidance given in Phase 1 tocover the harvesting and reuse of stormwater.
Australian Guidelines for Water Recycling: Managed Aquifer Recharge (NRMMCEPHCNHMRC 2009).The third module of Phase 2 of the guidelines focuses primarily on the protection of aquifers and the quality of therecovered water in managed aquifer recharge projects.
1.1 Harvesting and reuse of stormwater and roofwater
Harvesting roofwater and urban stormwater for safe reuse has many potential benefits. It canhelp to reduce the impact of urban development on water quality and stream flow, and canalso help to meet water conservation objectives. These potential benefits are important to theeconomic and environmental viability of many roofwater and stormwater reuse projects.Roofwater and stormwater reuse schemes are commonly used in water sensitive designstrategies for new urban developments.
Roofwater harvesting generally involves installing rainwater tanks to collect roofwater from
residential dwellings for uses such as garden watering and toilet flushing. There is increasing
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
13/140
2 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
demand for harvesting roofwater from larger buildings, such as community halls, schools andcommercial premises.
Stormwater harvesting involves collecting runoff from drains or creeks, and represents arelatively new form of water reuse compared to rainwater tanks and the reuse of effluent from
sewage treatment plants. However, reuse of stormwater is increasingly seen as a potentialoption for meeting water demands and other objectives. At present, harvested stormwater ismainly used for irrigating public parks and golf courses. Strictly speaking, harvesting ofstormwater might not be classified as reuse or recycling, because the water has not beenused previously. However, the term reuse is used here to be consistent with the otherpublications that comprise the water recycling guidelines.
Roofwater and stormwater should be harvested in a way that minimises health andenvironmental risks, or at least reduces such risks to acceptable levels. Stormwater maycontain chemicals and disease-causing microorganisms (pathogens). Roofwater generally haslower levels of chemical contaminants and pathogens than urban stormwater, which collects
contaminants during its passage over roads and other surfaces, picking up chemicals andpathogens from environmental and sewage sources. Consequently, the health andenvironmental risks associated with roofwater reuse are typically lower than those associatedwith stormwater reuse in similar applications. The most commonly recognised illnessassociated with polluted water is gastroenteritis (with symptoms such as diarrhoea andvomiting) arising from waterborne pathogens following the drinking of contaminated water.Potential environmental risks include impacts on plants and soils in irrigation areas. Thehealth risks tend to be acute, whereas environmental risks tend to be chronic, developing overtime.
These guidelines have been developed on the basis that most roofwater and stormwater reuse
schemes in Australia are relatively small compared to most wastewater recycling schemes(Hatt et al 2004, DEC NSW 2006), and are operated by organisations that are not waterutilities (eg metropolitan councils and golf clubs). The guidelines have therefore been writtento suit a nonspecialist reader involved in a small to medium-sized scheme, while alsoproviding information for a specialist reader involved in a large scheme.
1.2 Purpose and scope of this document
The primary purpose of this document is to provide guidance on managing potential publichealth and environmental risks associated with the reuse of:
roofwater collected from nonresidential buildings (including industrial buildings)
urban stormwater from sewered areas, including stormwater collected from drains,waterways and wetlands.
These guidelines cover only nonpotable (ie non-drinking water) potential end uses ofroofwater and stormwater (see Table A6.1 for a list of potential non-drinking uses ofharvested roofwater and stormwater).
This document extends the scope of Phase 1 of the water recycling guidelines (NRMMCEPHCAHMC 2006), which focuses primarily on reuse of wastewater and grey water. The
same risk-based management approach is used, and the technical approach adopted isidentical (eg the approach to completing the underlying risk assessment, given in
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
14/140
Introduction 3
Appendix 3). Appendix 1 outlines how these guidelines incorporate the 12-element riskmanagement framework for recycled water quality and use.
These guidelines are primarily intended to support health and environmental riskmanagement for proposed water harvesting and reuse schemes that draw source water from
stormwater systems. These guidelines are not intended for retrospective application toexisting schemes.
This document does not address:
the potential benefits and limitations of schemes and the sizing of a scheme to meet otherproject objectives (eg assessing yield through a water balance) (for relevant informationsee DEC NSW 2006, Mitchell et al 2006)
integrated urban water cycle planning or water sensitive urban design, which may providea strategic context for stormwater reuse (national guidelines on water sensitive urbandesign are being prepared)
rainwater reuse using domestic rainwater tanks (for relevant information see enHealth2004)
combined effluent and stormwater reuse schemes (for relevant information see NRMMCEPHCAHMC 2006)
harvesting stormwater from predominantly nonurban catchments (eg rural or forested)(see ANZECCARMCANZ (2000a) for details)
irrigation schemes using river water from largely nonurban catchments
other aspects of a schemes risk management, including public safety, occupational healthand safety, operation or construction-phase environmental management (for relevant
information see DEC NSW 2006)
potential environmental impacts due to the construction of infrastructure associated with ascheme (eg potential impacts on vegetation or threatened species)
other aspects of designing and operating a successful scheme, including cost-effectiveness.
The target audience for these guidelines includes:
planners, designers and operators of stormwater reuse schemes, which may include golfclubs, schools and other nonspecialist organisations
planners, designers and operators of roofwater reuse schemes
local councils, including the planning, environmental health, operational andenvironmental departments
state government authorities, including health, environmental protection, watermanagement and planning agencies
water utilities.
1.3 Relationship to other national guidelines
The national guidelines for urban stormwater management were prepared by the Australianand New Zealand Environment and Conservation Council (ANZECC) and the Agriculture
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
15/140
4 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
and Resource Management Council of Australia and New Zealand (ARMCANZ) (ANZECCARMCANZ 2000b) under the National Water Quality Management Strategy. The nationalguidelines focus on stormwater management in a water-quality protection context, and do notaddress stormwater reuse.
The use of stormwater for drinking purposes and for managed aquifer recharge is covered inthe other two publications in Phase 2 of the water recycling guidelines.
The enHealth document Guidance on the Use of Rainwater Tanks (enHealth 2004) focuseson the management of public health risks for roofwater use from residential dwellings.Additional information is provided in theRainwater Tank Design and Installation Handbook(Standards Australia 2008).
TheAustralian and New Zealand Guidelines for Fresh and Marine Water Quality(ANZECCARMCANZ 2000a) addresses water quality requirements for irrigation usingriver water. The document applies to schemes where only a small proportion of a catchment
is urbanised.
1.4 Relationship to state and territory legislation and guidelines
These guidelines provide a risk management framework for the beneficial and sustainablemanagement of roofwater and stormwater reuse systems. However, they are not mandatoryand have no formal legal status. Alternative risk management practices can be used wherethese achieve the same outcomes for managing risks to health and the environment. Nationalguidelines provide a shared national objective while allowing flexible responses to differentcircumstances at regional and local levels. All states and territories are encouraged to adopt
the framework set out in this document, to help provide national consistency. Application ofthe framework may vary across states and territories depending on water managementarrangements.
The roofwater and stormwater reuse systems addressed in this document may be regulated bystates and territories, but are not regulated by the Australian Government. State or local
jurisdictions may use their own legislative and regulatory tools to develop their ownguidelines based on this document. Relevant state and territory regulations, standards orguidelines, where they exist, should be consulted to ensure that any local requirements aremet. Where state and territory guidelines differ from this document, the state and territoryguideline should be followed, or the local regulatory agency consulted to clarify
requirements.
State and territory legislation relevant to a roofwater or stormwater harvesting project mayrelate to:
planning approvals
water resource allocation
natural resource management, including works in watercourses or riparian zones
public health
pollution control
dam safety.
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
16/140
Introduction 5
1.5 How to use these guidelines
These guidelines assume that most roofwater schemes and small-to-medium stormwater reuseschemes involving open space irrigation can be readily managed using standard practices tominimise health and environmental risks. The document identifies some of these practices.
Where schemes are larger or more complex, or where alternative management practices areproposed, the document provides additional guidance on how to conduct a risk assessmentand identify appropriate risk management practices.
This approach is analogous to that adopted for regulating sewage treatment schemes in manystates and territories. Small sewage treatment plants (eg package plants) are usually managedby reference to best-practice guidance, and medium-to-large plants are generally regulated byan environment protection agency on a case-by-case basis. This ensures that the greatestmanagement effort is targeted at the highest risk plants.
In a stormwater reuse context the standard approach could be used, for example, for a scheme
involving irrigation of a sporting oval or a golf course. Thus, the risks associated with a smallirrigation scheme can be appropriately managed without the burden of a full risk assessment.However, for a larger municipal irrigation scheme or a scheme with other end uses (eg dualreticulation), a comprehensive risk assessment should be carried out using the 12-elementframework from Phase 1 of the water recycling guidelines (NRMMCEPHCAHMC 2006),combined with the information in Appendixes 25. Such an assessment is particularlyimportant when a scheme operator will be providing stormwater for reuse by a third party.
The standard management practices in these guidelines have been developed based on ananalysis of available data on roofwater and stormwater quality. An individual schemeoperator may carry out site-specific water-quality monitoring, and use this information to
conduct a project-specific risk analysis, to identify alternative management practices (see thePhase 1 guidelines for further details, NRMMCEPHCAHMC 2006). To ensure consistencyacross different water sources for reuse, this document frequently refers to the guidanceprovided in the Phase 1 guidelines.
To maximise its usefulness to nonspecialist project developers, this document follows aconventional project development process. Chapters 2 and 3 include sections on the standardapproach, project design and operations and maintenance. This structure differs from that ofPhase 1 of the guidelines, which was designed more for water industry specialists.Appendix 1 of this document explains how a specialist reader familiar with the riskmanagement framework in the Phase 1 guidelines can link the two sets of guidelines.
Figure 1.1 provides a flowchart for the use of these guidelines.
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
17/140
6 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
Figure 1.1 Structure and use of these guidelines
Chapter 2 describes a standard approach to managing health and environmental risks fromroofwater reuse projects, including planning, design, maintenance and monitoring. Thisapplies to roofwater schemes where the roofwater is stored in a tank and used on-site forlandscape watering and toilet flushing.
Chapter 3 describes a standard approach to managing health and environmental risks,including planning, design, maintenance and monitoring, arising from a small-to-mediumsized stormwater reuse project involving the irrigation of public open spaces this iscurrently the most common type of stormwater reuse scheme. This chapter enables users toeasily assess whether their stormwater reuse scheme has low health and environmental riskswhen standard management practices are used (effectively a deemed to comply approach).It also allows users to identify where additional investigation is needed if certain aspects oftheir project present higher risks.
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
18/140
Introduction 7
Appendixes provide detailed information on:
the risk management framework (Appendix 1)
the water-quality data used to develop the guidelines (Appendix 2)
public health management considerations (Appendix 3)
environmental risk management considerations (Appendix 4)
additional risk management actions for stormwater reuse schemes outside the standardscheme described in Chapter 3; this information is generally presented as tier 1 and 2actions, where a tier 1 action involves a relatively straightforward investigation and atier 2 investigation is more detailed, allowing the level of the investigation to reflect themagnitude of the risk (Appendix 5)
other applications (Appendix 6).
The information given in Appendixes 24 is intended to support the planning, design,
operation and maintenance of roofwater and stormwater reuse schemes; it is intended for amore specialist audience, familiar with the Phase 1 guidelines.
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
19/140
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
20/140
9
2 Roofwater reuse
2.1 Application of standard approach
This section describes a standard approach that can be adopted for managing health andenvironmental risks from a roofwater collection scheme from buildings larger than aresidential dwelling, such as:
community halls (eg scout halls)
public buildings
schools
commercial buildings (eg shopping centres, office blocks and warehouses).
Information on managing health risks associated with rainwater tanks for residentialdwellings is provided in the Guidance on Use of Rainwater Tanks (enHealth 2004) and the
Rainwater Tank Design and Installation Handbook(Standards Australia 2008). The approachin this section can, however, be used for a communal residential roofwater scheme where asingle entity, such as a body corporate, manages the collection of roofwater from multipleresidential dwellings for storage in one or more covered tanks and distribution for nonpotableuses.
This approach applies where the roofwater is not used as drinking water suitable usesinclude garden watering, irrigation, toilet flushing, vehicle washing, firefighting and clotheswashing and where the roofwater is stored in a covered tank rather than an open storage
(see Section A5.5 for information on open storages).
While there are many similarities between residential roofwater systems and those fromlarger nonresidential buildings, important differences that may affect the level of risk tohuman health include:
potentially greater exposure to larger, sensitive populations (eg schools, nursing homes)
liabilities associated with the supply of water by an organisation, rather than by ahomeowner for household uses
greater risk of cross-connections (ie the roofwater pipes being inadvertently connected to
the potable water system) due to larger networks and more complicated systems more complex arrangements, with different people involved in planning, design and
maintenance
increased potential for access to roofwater by people unfamiliar with the system (eg morevisitor access compared to access by household residents)
generally larger roof areas, increasing the area for bird or animal droppings.
Thus, although most actions to minimise health risks from nonresidential schemes andresidential reuse are similar, additional actions may be necessary to manage the risksidentified above. These actions (described in Sections 2.22.4) have a strong emphasis on
prevention and involve a number of different steps to prevent risks (often termed multiplebarriers in the water sector).
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
21/140
10 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
However, there is no requirement to follow this standard approach. Alternative riskmanagement practices can be used where these achieve the same health and environmentalrisk management outcomes.
2.2 Preparatory steps
2.2.1 Organisational support
The organisation that owns or maintains the building whose roof is to be used to collectroofwater should be committed to the appropriate management of water collection, storageand reuse. Maintenance of the roofwater system is required to effectively manage health andenvironmental risks. Thus, before deciding to proceed with a project, the organisation needsto ensure that adequate funding is allocated for long-term effective maintenance. Suchmaintenance should be carried out by a nominated suitable person within the organisation or
by an external contractor, such as a suitably qualified plumber. The organisation should alsobe committed to using monitoring data to improve the schemes performance where required.
2.2.2 Legal requirements
Before starting the project, the local council or other regulatory authority should be contactedto determine whether there are any specific requirements that need to be met for roofwaterharvesting schemes. The guidelines in this document do not override state and territory orcouncil requirements.
2.2.3 Roof characteristics
The particular characteristics of a roof affect roofwater quality. Before starting the project, itis recommended that the roof be inspected. Ideally, the roof should not have:
public access (roofs with maintenance access are acceptable)
vehicular access
structures above the roof that may rust or corrode (eg unpainted metal or concrete), orprovide a resting place for birds
discharge, overflow or bleed-off pipes from roof-mounted appliances, such as
airconditioning units, hot water services and solar heaters
a flue from a slow combustion heater that is not installed in accordance with the relevantAustralian standard
a chimney or flue from an industrial process within or adjacent to the building
exposure to chemical sprays from processes within the building (eg spray painting) thatmay be deposited on the roof
significant atmospheric deposition of pollutants (eg from industrial sources or from aerialspraying)
vegetation growing on the roof (eg a green roof).
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
22/140
Roofwater reuse 11
These characteristics may result in significant increases in pathogen levels or chemicalconcentrations, which may increase health risks. If a roof has these characteristics, roofwaterquality should be monitored for relevant contaminants, and any associated health andenvironmental risks should be assessed before proceeding with the project.
Any lead flashing or exposed areas painted with lead-based paints should be painted with anon-lead-based paint or otherwise sealed. Asbestos roofing material should, as far as ispracticable, be left undisturbed since fibres can be released into the air by actions such ascutting, grinding or drilling. High-pressure roof cleaning methods should also be avoided.Where the roof catchment area has deteriorated badly, it should be replaced with asbestos-free substitutes (enHealth 2004).
Roofwater quality can be further protected by excluding:
copper roofing material (see also Section 2.4)
overhanging vegetation that may attract birds and drop debris onto the roof
bitumen-based materials or lead-based paints
exposure to preservative-treated wood.
2.3 Project design
The design of a roofwater collection system can minimise health risks; relevant designaspects include the storage tank, gutters, pipework and the connection between the tank andthe mainswater supply.
Disinfection of roofwater is not required for the uses noted in Section 2.1, provided thesystem design and maintenance controls noted in Sections 2.3 and 2.4 are implemented.However, an individual scheme operator may choose to include disinfection to provide anadditional safety barrier.
2.3.1 Tanks
Tanks for storing roofwater are available in a range of suitable materials, includinggalvanised steel, fibreglass, polyethylene and concrete, and may be rigid or flexible. Themain requirements for these storages for nonpotable roofwater use are that they arestructurally sound, watertight and light-proof; that they incorporate access openings formonitoring and maintenance; and that any openings are appropriately screened, to minimisethe potential for mosquito-borne diseases (see below). The sizing of a tank and its roof area tomeet particular water supply needs is beyond the scope of this document.
The following guidance relating to the design and manufacturing of potable rainwater tanks(Standards Australia 2008) may be followed to meet or exceed the requirements fornonpotable roofwater storage:
above-ground polyethylene tanks may be designed and manufactured in accordance withAustralian Standard/New Zealand Standard (AS/NZS) 4766:2006 Polyethylene StorageTanks for Water and Chemicals
tanks manufactured from other materials may meet the requirements of AustralianTechnical Standard (ATS) 5200.0262004 Technical Specification for Plumbing and
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
23/140
12 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
Drainage Products Cold Water Storage Tanks, AS/NZS 1546.1 On-site DomesticWastewater Treatment UnitsSeptic Tanks, or AS 3735-2001 Concrete Structures
Retaining Liquids, as applicable
tanks may be lined with a coating that meets the requirements of AS 5200.000 TechnicalSpecification for Plumbing and Drainage Products.
Overflows from above-ground tanks and vents should be provided with a securely fastenedvermin and insect-proof screen mesh, with holes less than 1.6 mm in diameter. Where a tankreceives roofwater directly from a downpipe, the tank inlet should be provided with a screento prevent leaf entry, and a robust insect-proof mesh to prevent entry of mosquitoes and otherinsects.
The access openings for above-ground tanks should have a close-fitting, impervious lid toprevent the entry of animals, insects and rubbish. Access and inspection openings forunderground tanks should be either watertight or raised above ground level, to prevent theentry of surface runoff.
If an underground tank is buried in contaminated land, or near petroleum or chemical storagetanks or septic tanks, the tank needs to be designed to prevent any contamination of theroofwater.
Where the overflow pipe from an underground tank is connected to a stormwater system, theoverflow should be designed to prevent any stormwater surcharging back into the tank.
2.3.2 Gutters
Gutters should not be rusty or corroded and should freely drain to the downpipe/s used tocollect the roofwater (ie there should be no ponding of water in the gutter or downpipes).
Roof drainage systems should be designed in accordance with AS/NZS 3500.3 Plumbing andDrainage Stormwater Drainage. To avoid ponding of water in gutters or downpipes, thefall on eaves, gutters or downpipes should be at least 1:500 (0.2%) and at least 1:200 (0.5%)for box gutters and internal guttering. Leaf-protection devices can be installed on gutterswhere needed.
2.3.3 Pipework and connections to mainswater
Pipework connecting the tank to plumbing fixtures should comply with AS/NZS 3500.1Plumbing and Drainage Water Services, and any local requirements, including:
marking the pipe with the word RAINWATER, in capital letters
where the roofwater system includes a connection to the mainswater supply (eg for top-upsupply), ensuring that reliable and, ideally, testable backflow prevention systems (or anappropriate air gap) are in place to prevent roofwater entering the mainswater supplynetwork.
Where roofwater is used to supply essential services, such as toilet flushing, an appropriate
backup water supply, such as top-up from mainswater, needs to be included, to ensure that
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
24/140
Roofwater reuse 13
services will continue to function when there is inadequate rainfall to meet demand or theroofwater harvesting system fails.
A DO NOT DRINK sign with appropriate symbols should be installed next to the tap inplace of the recommendations for tap signage contained in AS/NZS 3500.1 Plumbing and
Drainage Water Services. Signs should comply with AS 1319 Safety Signs for theOccupational Environment. These signs are particularly important where a building also hasexternal taps connected to the drinking water system.
Where sensitive groups could be exposed, additional controls to reduce the likelihood ofexposure should be considered, such as locating external taps approximately 1.5 m above theground. Sensitive groups include people who come from a non-English speaking backgroundor who might not understand or follow signage (eg in childcare centres and health-carefacilities).
2.4 Operations, maintenance and monitoring
Where sensitive groups are likely to be exposed, garden watering and irrigation usingroofwater should be carried out at times and locations that reasonably minimise the chancesof public contact with the roofwater. As with any irrigation scheme, the irrigation rate shouldmeet the needs of the irrigated plants, and not cause excessive runoff or soil saturation.
If the roofwater is to be used for garden watering or irrigation, environmentally hazardouschemicals, such as roof-cleansing biocides, should not be used.
Irrigation or garden watering using roofwater from copper or zinc-coated roofs including
galvanised roofs or structures with exposed galvanised or zinc-containing materials(eg galvanised or zincaluminium roofing material, galvanised bracing and antenna supports)should generally be limited to an application rate of less than 300 mm/year.
Soils in the irrigation area should be monitored after 10 years and then after every 5 years totest whether copper and zinc levels have reached potentially hazardous levels (seeAppendix 4). Specific monitoring requirements may apply in sensitive environments, such asan area where groundwater is a source for domestic consumption.
Alternatively, where roofwater from copper or zinc-coated roofs is used, roofwater qualitymonitoring could be carried out before use. Where this monitoring indicates that the
environmental risk is low, the recommended limits to application rates would not apply.
Indicative inspection and maintenance actions for roofwater reuse systems are given inTable 2.1. A maintenance schedule should be set up during the design phase, and aninspection and maintenance log prepared to enable staff or contractors to sign off oncompletion of the activities. Where the pipework of the roofwater scheme is complex(ie more complex than that for a simple residential rainwater tank scheme), drawings showingthe pipework and the backflow prevention devices should be kept with the maintenance log.This is important for effective maintenance, particularly to ensure that critical knowledge isnot lost with staff changes.
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
25/140
14 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
Table 2.1 Inspection and maintenance of roofwater reuse systems
Indicative
frequency
Inspection and criteria Maintenance action (where
required)
Quarterly Check whether any tree branches
overhang the roof or are likely to growto overhang the roof
If safe and where permitted, consider
pruning back overhanging branches
Check that access covers to storagetanks are closed
Secure open access covers to preventrisk of entry
Check that screens on inlets, overflowsand other openings do not have holesand are securely fastened
Repair defective screens to keep outmosquitoes
Inspect tank water for presence of rats,birds, frogs, lizards or other animals
Remove infestations, identify pointof entry and close using gnaw-proof
mesh with holes no greater than 2 cmin diameter
Inspect tank water for presence ofmosquito larvae (inspect morefrequently based on local requirementsin subtropical and tropical northernAustralia)
Identify point of entry and close withinsect-proof mesh with holes nogreater than 1.6 mm in diameter
Inspect gutters for leaf accumulationand ponding
Clean leaves from gutters; removemore regularly if required. If water isponding, repair gutter to ensure water
flows to downpipe
Check signage at external roofwatertaps
Replace or repair the missing ordamaged signage
Check first-flush diverter if present Clean first-flush diverter; repair andreplace if necessary
Check health of irrigation area andirrigated grass or plants
Investigate observed adverse impactsthat could be due to irrigation
Everyyear
Check for cross-connections andinappropriate tappings by checking
visible plumbing fittings, alternativelyturning off supplies. Also check afterany plumbing work
Remove cross-connections andinappropriate tappings
Check condition of roof and coatings Investigate and resolve apparentchanges to roof condition, such asloss of material coatings
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
26/140
Roofwater reuse 15
Table 2.1 (continued)
Indicative
frequency
Inspection and criteria Maintenance action (where
required)
Every
3 years
Drain, clean out and check the
condition of the tank walls and roof toensure no holes have arisen due totank deterioration
Repair tank defects
Check sediment levels in the tank Organise a suitable contractor toremove accumulated sediment iflevels are threatening to block tankoutlets or are affecting water quality
Undertake a systematic review ofoperational control of risks to thesystem
Identify the reason for any problemsidentified and take actions to preventfailures occurring in future
After10 yearsand thenevery5 years
Monitor soil copper and zinc levels Stop roofwater irrigation if levelsexceed criteria
After20 yearsand thenevery5 years
Monitor the effectiveness of anyirrigation equipment over 20 years oldfor clogging due to algal growth
Clean or replace any cloggedequipment
Note: These recommendations do not supersede any relevant state or territory requirements.
Maintenance should also include inspection and follow up on any complaints or concernsraised that could indicate problems with the system.
Monitoring should be designed to identify any problems with the systems operations(eg potentially system-related health problems where a reasonably static population isexposed, such as childcare facilities, and effects on plants watered by roofwater). However, itis not necessary to undertake routine monitoring of the quality of roofwater used for gardenwatering, toilet flushing and laundry use.
2.5 Nonresidential roofwater reuse checklist
This checklist summarises the key health and environmental risk management actions for anonresidential roofwater scheme where there is no intentional drinking or contact withroofwater.
o Planning and other regulatory requirements are met.o The operating organisation is committed to the safe collection and use of roofwater,
including ensuring appropriate operation and maintenance.
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
27/140
16 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
o The likelihood of accidental drinking of roofwater is minimised through appropriatesignage and tap design.
o Backflow prevention devices protect the public water supply off-site.o
Reliable insect-proofing prevents mosquitoes breeding in tanks.
o Backup water supplies are available for essential services.o Time, method and location of any roofwater irrigation are selected to reasonably
minimise public contact with the roofwater and avoid runoff or soil saturation.
o Roof-cleansing biocides or environmentally hazardous chemicals are not used on theroof.
o Irrigation or garden watering using roofwater from copper or zinc roofs is avoidedunless roofwater quality monitoring is undertaken or irrigation is limited, unless soilmonitoring is carried out.
o Risk management actions are documented.o Appropriate maintenance is carried out.
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
28/140
17
3 Stormwater reuse
3.1 Reuse application
This section describes a standard approach that can be adopted for managing the health andenvironmental risks from an urban stormwater reuse scheme involving the irrigation of small-to-medium scale open-space irrigation schemes, such as:
playing fields
golf courses
bowling greens
parks and gardens.
There is no requirement to follow this standard approach. Alternative risk managementpractices can be used to achieve the same health and environmental risk managementoutcomes, as described in Appendixes 3 and 4, and the Phase 1 guidelines (NRMMCEPHCAHMC 2006).
For large schemes, schemes with other applications and schemes where stormwater issupplied to a third party, a risk assessment should be carried out, as described in Appendix 6,which links to the Phase 1 guidelines (NRMMCEPHCAHMC 2006). A risk assessmentshould also be done when the primary purpose is open-space irrigation but possible ancillaryuses result in higher public exposure (eg toilet flushing in the amenities building of a sportsfield). Applications other than irrigation of public open spaces include:
toilet flushing
washing machine use
car washing
roadmaking or dust control
street cleaning
firefighting
water features and ponds
food crop irrigation (home grown) food crop irrigation (commercial)
agricultural uses (crops other than food)
dual reticulation
industrial uses.
Stormwater quality varies considerably between storm events, and between catchments (seeAppendix 2). This variability is greater than that observed in roofwater quality. The approachoutlined here is relatively conservative, and an individual operator could undertake site-
specific monitoring to assess whether less conservative risk management actions would beappropriate. This should involve reference pathogen monitoring (see Appendix 3), because
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
29/140
18 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
no statistically valid relationship has been found between levels of pathogens and of indicatorbacteria such asEscherichia coli (E. coli) (see Appendix 2).
The approach involves:
using a project screening tool to assess whether a stormwater public, open-space
irrigation project can be readily designed to manage associated health and environmentalrisks
implementing the standard risk management actions outlined in Sections 3.23.4
carrying out any additional investigations triggered by the screening tool, andimplementing any associated risk management actions.
The project screening tool is presented in Table 3.1 and its derivation is described inAppendix 5. Use of the tool involves:
collecting data and information about the reuse project being considered
identifying any other risks that need to be managed beyond those readily managed by thestandard approach (managing these additional risks requires additional investigations, asdetailed in Appendix 5).
Figure 3.1 illustrates how to use the project screening tool. Other risk management actionsmay be required to meet statutory requirements or other project objectives on a case-by-casebasis.
Collect data on project
and catchment
If promptedby a question
Answer questions in
project screening tool
Additional investigationsas described in
Appendix 5
Return to screening tool
Implement additional oralternative planning, design and
operational risk managementactions, as described in Appendix 5
Implement standard planning,design and operational risk
management actions, as describedin Sections 3.2 to 3.4
If triggered byinvestigation
Figure 3.1 How to use the project screening tool
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
30/140
Stormwater reuse 19
Table 3.1 Project screening tool checklist for stormwater reuse in public, open-
space irrigation
Topic Question Response
Purpose
(intendedend uses ofthestormwater)
1. Does the scheme involve stormwater irrigation of
public parks and gardens, roadsides or sportingfacilities (including golf courses)?
q Yes next
question
q No seeAppendix 6
Thecatchment
2. Is the catchment land use limited to residential orcommercial uses, with no significanta additionalpollution sources, such as:
agricultural or industrial land use
a significant proportion of the catchment
comprising corroding roofs extensive construction activity, eroding stream
banks or other significant sources of sediment
on-site sewage management systems (eg septictanks)
wastewater (eg sewage) treatment plantsdischarging into the catchment
contaminated sites or areas with acid sulphatesoils?
q Yes nextquestion
q No or not known
see Section A5.1
3. Is the number of sewer overflows reported by thelocal water utility in the catchment relatively low,that is, below 14 per 100 km of sewer pipe peryear as an average over the past five years?
q Yes nextquestion
q No or not known
see Section A5.2
4. Are there any other stormwater harvesting orwater extraction schemes in the catchment?
q Yes or not known
see Section A 5.3
q No nextquestion
Thestormwater
5. Will the amount of stormwater withdrawn fromthe scheme be less than 10% of the mean annualstormwater runoff volume from the catchmentabove the collection point?
q Yes nextquestion
q No seeSection A5.3
6. Is the stormwater drain where the stormwater iscollected free from tidal influence, and is thecatchment free from significanta areas of high soilsalinity (eg > 2dS/m) or known salty lakes?
q Yes nextquestion
q No seeSection A5.4
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
31/140
20 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
Table 3.1 (continued)
Topic Question Response
Theproposed
waterstorage
7. Will the irrigation water be stored in a tank(either underground or above ground)?
q Yes nextquestion
q No see Section3.3.3 and SectionA5.5
8. Will stormwater be collected by pumping from awaterway or water body?
q Yes nextquestion
q No seeSection A5.6
9. Is the irrigation area outside any designated (byutility, council or water resources agency)
vulnerable groundwater protection zonesincluding groundwater protection zones for townwater supply bores?
q Yes nextquestion
q No or not known
see Section A5.7
10. Are the characteristics of the irrigation arearelatively favourable, that is:
slope (for sprinkler irrigation)
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
32/140
Stormwater reuse 21
obtained from the National Water Commissions (NWCs)National Performance Reports(NWC 2007ab) or similar state documents (eg DWE NSW 2007). Some site-specificinvestigations may be required, particularly to obtain irrigation area information.
If a schemes proponent or operator cannot readily obtain some or all of this information
(eg catchment information), site-specific monitoring can be carried out (see Section A5.1).However, the cost of adequate monitoring (ie of sufficient statistical and methodologicalquality) may well exceed the cost of obtaining the services of a suitable person to collect theinformation to complete the project screening tool. The interpretation of the monitoring datawill also require suitable expertise.
3.2 Preparatory steps
3.2.1 Organisational support
The organisation that will operate the stormwater reuse scheme should be committed to theappropriate and ongoing management of the health and environmental risks. The organisationshould either nominate suitably qualified staff to maintain the system, or arrange formaintenance to be contracted out by suitably qualified contractors.
Achieving organisational commitment is simpler where the schemes operator is also theschemes developer. If the staff members that are likely to be involved in operating a schemeare also involved in the schemes development, operational risk management actions aremore likely to be appropriate and able to be accommodated within the organisationsoperating budget.
An organisation considering a stormwater reuse scheme should also ensure that ongoingfunding is available for the proposed schemes operations and maintenance, before a finaldecision is made to proceed with the project.
Where stormwater reuse schemes are to be constructed as part of a new urban or commercialdevelopment project, the developer is normally responsible for the schemes design andconstruction. Responsibility for operations is often transferred to a separate organisation(eg council, water utility, golf course or body corporate) following construction. Theschemes operator should be involved in the development of the scheme, to ensure that theproposed risk management actions for the operational aspects of the scheme and their
financial implications are acceptable. The developer and operator should prepare a writtenagreement detailing risk management roles and responsibilities.
A similar arrangement on agreed risk management roles and responsibilities should bedeveloped in circumstances where one organisation collects, treats and distributes thestormwater for reuse by another organisation. This should be noted in the schememanagement plan and reviewed regularly.
3.2.2 Legal requirements
Before starting the project, the local council or other regulatory authority should be contactedto determine whether there are any specific requirements for stormwater reuse schemes,including requirements for planning and operational approval. The scheme should be
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
33/140
22 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
developed and operated to meet any such requirements. These guidelines do not override anystate, territory or council requirements.
3.2.3 Planning approval
The authority responsible for issuing planning approvals for a stormwater reuse scheme(commonly a local council) should seek information from applicants relating to health andenvironmental risk management, including:
how public health and safety risks will be addressed during the design and operation ofthe system
how environmental impacts will be considered during construction
how the system will be managed on an ongoing basis
what (if any) risks or financial obligations will be transferred to council if it operates thescheme (eg operations, maintenance, monitoring and reporting costs).
The planning authoritys development consent for a stormwater reuse scheme should includeconditions relating to managing health and environmental risks, including:
requiring appropriate management arrangements to be in place if the local council is notthe schemes operator (eg a club-operated golf course or a body corporate)
implementing an environmental management plan (or similar) to manage constructionimpacts on the environment
implementing an operating plan for the scheme, including regular reviews and updates ofthe plan
reporting monitoring results (including any exceedences see Section 3.4.12) andimplementing any corrective actions.
3.3 Project design
3.3.1 Stormwater extraction
The potential direct environmental impacts of pumping stormwater from a naturalwatercourse or waterway for reuse are:
drawing aquatic fauna into the pump
local erosion around the pump site.
Intake of aquatic fauna can be minimised by screening the pump intake or installingscreening around the pump sump. Screening of pump intakes is common, to avoid pumpblockages. Potential environmental risks associated with other forms of stormwater extractionand online storages (where stormwater flows directly into the storage) are discussed inAppendix 5.
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
34/140
Stormwater reuse 23
3.3.2 Stormwater quality risk management
Stormwater harvesting schemes should include stormwater treatment to minimise operationalrisks, with additional treatment possibly used to manage health and environmental risks.
In addition, a scheme should incorporate a minimum 72-hour buffer time between thecollection of stormwater and its release for irrigation. This is intended to achieve twoobjectives:
averaging (or equalising) the concentrations of pollutants and pathogens before reuse orfurther treatment, to minimise any effects on the quality of irrigation water from anyspikes in the concentration of the raw stormwater (eg to minimise any first flush effect)and to optimise the performance of subsequent treatment processes such as disinfection
a contingency arrangement to stop the stormwater from being used if there is a spill or anunexpected water quality event (eg major sewer overflow) in the catchment.
This buffer is recommended because it takes into account the common variability in rawstormwater quality and the limited control that a scheme operator usually has on catchmentactivities that could affect stormwater quality. The 72-hour period should provide a suitabletime for operator notification and response (see Section 3.4.6); longer or shorter periods mayapply in specific circumstances.
Depending on the design of the scheme, there are different ways to achieve a buffer. Where aseparate (eg offline) storage is provided before treatment, the schemes storage volumeshould be sufficient to hold a minimum of 72 hours worth of irrigation water at maximumdemand. Alternatively, the residence time in any online constructed wetland or pond used topretreat the stormwater should have a minimum average residence time of 72 hours for at
least 90% of the time (preferably 95%). This can also apply where a wetland is used topretreat stormwater before aquifer injection in a managed aquifer recharge scheme.
If a water quality incident occurs, the water in an offline storage should be treated (ifrequired) and discharged. For an online constructed pond or wetland, pumping of water forthe irrigation scheme should not recommence until the water-quality issue has been resolved(eg through dilution or treatment).
Treatment for operational risks
The potential operational risks relating to stormwater quality are:
coarse material (or gross pollutants) such as sediment and leaves entering the scheme andpotentially blocking pipes, irrigation nozzles or drip irrigation systems, or damagingpumps
high loadings of organic matter (eg leaves and grass clippings) resulting in reduceddissolved oxygen levels during decomposition, potentially creating odours and releasingpollutants from sediments
high nitrogen and phosphorus levels supporting algal growth in open storages, potentiallyincreasing turbidity and possibly reaching bloom levels, and biofilms clogging irrigationequipment
high iron concentrations potentially blocking irrigation systems over time and impairingthe effectiveness of the disinfection system
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
35/140
24 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
high hardness (ie high levels of calcium carbonate) of stormwater, which can blockirrigation systems over time.
The treatment criteria for managing operational risks will depend on the nature of thescheme. Advice on design criteria could be sought from the manufacturers of pumps and
irrigations system components likely to be sensitive to stormwater pollution. A furtherconsideration is the expected design life of sensitive elements (eg irrigation nozzles ordrippers). Table 3.2 provides an indication of potentially suitable treatment criteria for public,open-space irrigation, in the absence of product-specific information (most elements arelikely to have a design life of less than 20 years).
Table 3.2 Indicative stormwater treatment criteria for public, open-space irrigation
managing operational risks
Parameter Stormwater treatment criteria
Design life up to 20 years Design life up to 100 years
Suspended solids
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
36/140
Stormwater reuse 25
Treatment for health risks
Where stormwater from a sewered residential catchment is used for public, open-spaceirrigation, health risks can be managed by either of the following:
using on-site access controls to minimise exposure to irrigation water (see Section 3.4.10)
providing additional stormwater treatment (ie beyond that required for managingoperational risks).
Treatment criteria
Table 3.3 presents the recommended stormwater treatment criteria where no access controlsare used. Appendix 3 describes the derivation of these criteria and contains criteria for otherapplications.
The recommendations in Table 3.3 apply where there has been no catchment-specificassessment of the health risks posed by the quality of the stormwater. Where such a risk
assessment has been carried out, alternative risk management practices can be used (eg lowerstormwater treatment criteria may apply where microbial source tracking has foundnegligible human sources of pathogens in a catchment).
The disinfection and turbidity criteria in this table could be considered to be less stringentthan those in the Phase 1 guidelines (NRMMCEPHCAHMC 2006) for wastewaterirrigation. The reason for this is that levels of faecal-derived microbial indicators andpathogens in stormwater are commonly less than 1% of those found in sewage (based on theratio of the meanE. coli concentrations from Table A2.4 and the corresponding concentrationin raw sewage from the Phase 1 guidelines). This means that less stringent treatment orexposure control requirements will achieve the same degree of health risk management.
Table 3.3 Stormwater treatment criteria for public, open-space irrigation (no access
control) managing health risks
Parameter Stormwater treatment criteria
Disinfection >1.5 log10 (96%) reductiona of viruses and bacteria
>0.8 log10 (82%) reductiona of protozoan parasites
E. coli
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
37/140
26 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
Due to the relatively low reduction in pathogen levels required relative to those forwastewater, the turbidity criteria is less stringent than noted in the Phase 1 guidelines(NRMMCEPHCAHMC 2006). As noted in Appendix 3, elevated turbidity levels canreduce disinfection effectiveness; however, given the lower log reductions required, turbidityimpacts are less important. The criteria for stormwater are derived from evidence of
disinfection capability in turbid surface waters, where the pathogens are largely in suspensionand the turbidity is derived from material other than sewage floccs.
In most schemes, the iron criteria are unlikely to result in the need for stormwater treatment,because the 95th percentile total iron level in Appendix 2 is approximately half of the notedcriteria. Any reduction in iron levels is likely to be required only where very high iron levelsare known to occur within a catchment.
Disinfection
For most small-to-medium sized schemes, ultraviolet (UV) disinfection is the most practicaland commonly used disinfection technique for achieving the required log reductions,
although other techniques can also be used (eg chlorination or ozonation), as detailed in thePhase 1 guidelines (NRMMCEPHCAHMC 2006). Any UV disinfection unit should bevalidated or should meet the requirements of a suitable standard (eg National SanitationFoundation/American National Standards Institute (NSF/ANSI) 55-2007 Ultraviolet
Microbiological Water Treatment Units). Disinfection by chlorination is also suitable forstormwater reuse schemes, particularly for larger schemes. Chlorine disinfection to meet theprotozoa targets is likely to require a relatively high Ct value (disinfectant concentration contact time), because inactivation of protozoa (particularly Cryptosporidium) requires higherlevels of chlorine disinfection than bacteria and viruses.
The log reductions noted in Table 3.3 effectively provide the design criteria for thedisinfection system. Suppliers of commercial disinfection systems have normally tested andvalidated the log reductions achieved by their products. There is no requirement to monitorpathogen log reductions for each scheme (see Section A3.4).
Most disinfection systems do not achieve the same degree of log reduction for bacteria,viruses and protozoa. Commonly, levels of bacteria are reduced more readily than those ofviruses or protozoa. Therefore, a disinfection system designed to achieve a 1.5 log reductionof viruses, protozoan parasites and bacteria will normally achieve a greater reduction ofbacteria. When potential disinfection systems are being evaluated, it is important to confirmthat the system achieves the reduction required across all of the pathogen groups.
The retention of indicator bacteria in conventional stormwater treatment measures(eg constructed wetlands) is highly variable, and no information is currently available on theretention of reference pathogens. If these measures are to be used as the only technique formanaging health risks, their retention of reference pathogens or suitable surrogates must bevalidated (see Appendix 3); however, these measures can be used to reduce turbidity beforedisinfection and to manage operational risks.
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
38/140
Stormwater reuse 27
Turbidity
High levels of turbidity decrease the effectiveness of UV disinfection; however, most of theinformation on turbidity impacts on disinfection effectiveness relates to wastewater ratherthan stormwater (see Appendix 3). Various techniques are available to reduce stormwaterturbidity levels, including:
many types of stormwater treatment measures, including ponds, wetlands, bioretentionsystems and sand filters
stormwater storage with appropriate draw-off arrangements (eg a floating draw-off in atank storage)
withdrawal of stormwater from a managed aquifer recharge scheme
an in-line filter of the type used for drinking or recycled water applications.
The most reliable of these techniques is an in-line filter; the performance of the other optionsis more variable, particularly in the case of the options involving open storages and
stormwater treatment measures. However, an in-line filter may also be the most expensiveoption.
An approach that could be adopted to minimise costs is to initially use a technique other thanan in-line filter. This may be a cost-effective option where the technique is proposed to meetanother objective; for example, treatment to meet operational risk criteria or storage of rawstormwater. Where this approach is adopted, an allowance should be made in the design andconstruction of the treatment system for easily installing a filter, should subsequentmonitoring indicate it is required. Turbidity monitoring would occur during thecommissioning phase, and a filter would be installed if the turbidity levels exceeded thecriteria noted in Table 3.2. This is likely to be a suitable approach when stormwater is
collected from catchments where the soils are not dispersive and the stormwater is stored in acovered tank with a relatively long minimum hydraulic residence time (eg >2 days) to allowfor sedimentation. It may also be appropriate for open storages designed to minimise wind re-suspension, where the stormwater is drawn from a location near the storages outlet and thereis a relatively long hydraulic residence time.
Alternatively, if initial filtration is not planned, the capability of the selected treatmentprocess can be validated by an independent expert, based on verifiable, traceable informationand standards (eg US EPA 2006). This can be done either through a desktop assessment(coupled with in situ monitoring during a validation after commissioning of a previouslyvalidated standard design), or through more extensive validation of a novel design before
procurement.
3.3.3 Stormwater storage
Stormwater storage in tanks
The potential environmental risks associated with storing stormwater in tanks are low, andrelate primarily to changes in stormwater quality during storage (the environmental impactsassociated with open storages are discussed in Section A5.5). Anaerobic conditions candevelop in stormwater storage tanks where the stormwater has high levels of organic matter
and the residence time is long. Bacterial decomposition of organic matter can lead to odourproblems. Unless the stormwater has high organic loading (eg from a catchment with high
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
39/140
28 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
sewer overflows), potential impacts can be managed by appropriate operations andmaintenance (see Section 3.4).
To minimise the risks of mosquito-borne disease, tanks storing stormwater should bedesigned with the same features as described for rainwater tanks (see Section 2.3), including:
close-fitting, impervious lids on maintenance access holes
vermin-proof and insect-proof mesh on overflows and vents.
Stormwater storage in open storages
Stormwater may be stored in online open storages such as constructed wetlands and ponds,and offline open storages (eg turkeys nest dams). Additional risk management actions areusually needed to manage the additional potential health and environmental risks. These aredetailed in Section A5.5 and include:
requiring an additional 1 log reduction ofCampylobacterconcentrations unless faecal
inputs from waterbirds are controlled
minimising the potential for mosquito breeding
minimising the likelihood of resuspending deposited sediment in the storage, to avoidincreasing turbidity levels
reducing nitrogen and phosphorus concentrations and/or designing the storage with ashort hydraulic residence time, to minimise algal growth
assessing the environmental impacts of any online storage, particularly if located on anatural creek
undertaking additional monitoring to ensure that the additional controls are beingeffectively implemented.
Stormwater storage through managed aquifer recharge
TheAustralian Guidelines for Water Recycling: Managed Aquifer Recharge (NRMMCEPHCNHMRC 2009) provides guidance on aquifer storage in a managed aquifer rechargescheme.
3.3.4 Distribution pipework
The distribution pipework for a stormwater irrigation scheme should minimise the potentialfor contamination between the final treatment facility (eg disinfection) and the end use. Thisis usually achieved by employing a piped distribution system.
The likelihood of accidental cross-connections between the stormwater distribution networkand the mainswater system, or of inappropriate connections to the stormwater pipe system,should be minimised. This is particularly important for schemes using mainswater as asupplementary water supply. To achieve this, the distribution system should incorporate thefollowing elements:
Where mainswater is used as supplementary water, an external, visible air gap should be
incorporated between the mainswater system and the stormwater system.
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
40/140
Stormwater reuse 29
Where practicable, the stormwater distribution scheme should be operated at lowerpressure than the mainswater system.
An appropriate testable backflow prevention device or approved air gap should beinstalled at the meter.
Underground and above-ground pipes in a stormwater distribution system should becolour-coded (eg purple). The top of each underground pipe should be marked withidentification tape warning that the pipe contains recycled or reclaimed water and is notsuitable for drinking.
Hose taps for dual-reticulation schemes should have a removable handle and a differentconnection to that used for mainswater supply (eg nonstandard inlet thread).
Signs with symbols should be provided, reading, for example, Recycled water not fordrinking. The sign should also include relevant symbols indicating that the supply is notfor drinking purposes. For sign design, refer to Australian Standard (AS) 13191994Safety Signs for the Occupational Environment.
All external taps should be fitted with hose connection vacuum breakers.
Flush valves in surface boxes should be installed to allow periodic flushing for systemcleaning. Cross-connections should be inspected during installation.
For detailed information on the design of the distribution systems plumbing see the Phase 1guidelines (NRMMCEPHCAHMC 2006) and AS/NZS 3500.1 Plumbing and Drainage Part 1: Water Services.
The pipework for a stormwater reuse scheme should also be designed to incorporateappropriate flow meters and sampling taps, to ensure monitoring is safe, efficient and
representative.
3.3.5 Irrigation system design
Managing health and environmental risks from stormwater irrigation should be consideredduring the design of the irrigation system, particularly application rates and sprayarrangements where access to the irrigation area is controlled. Drippers (surface or subsurfaceespecially) can also minimise human exposure (Table 3.2) and the level of stormwatertreatment that is required.
Calculating the appropriate application rate is important to minimise surface runoff, andimpacts on groundwater and soils (eg soil saturation). The application rates should take intoaccount the site characteristics (particularly soils) and the vegetation to be irrigated.Stormwater should be applied uniformly and at a rate less than the nominal soil infiltrationrate, to avoid surface runoff.
Where practical, signage should be displayed at all public access points to areas irrigated withstormwater, warning not to drink the water. In public access areas where untreated sprayirrigation is used, facilities such as drinking water fountains, swimming pools and picnictables should be placed outside the area irrigated by treated stormwater, or be protected fromdrift and direct spraying.
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
41/140
30 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse
Where spray irrigation with restricted access is used to manage exposure to the stormwater,the irrigation system should be designed to include:
clear delineation of the irrigation area, for example, using fencing or vegetative borders
signs, including words and pictures, on all designated entry points to the irrigation area,
warning the public that the water in use is not for drinking and that the irrigated area mustnot be entered from the time irrigation begins until the irrigated area is dry
a minimum 25 m buffer from the irrigation schemes wetted perimeter to the nearest pointof public access and spray drift control using low-throw sprinklers (180 inward throw),vegetation screening or anemometer switching.
These arrangements are adequate to manage the additional health risks potentially associatedwith open storages, as noted in Section 3.3.3, when combined with the access controls inSection 3.4.9.
Where drip irrigation of garden beds is proposed, this provides effective access control
provided appropriate advisory signs are erected. This is based on the assumption that peoplemay be in the area during the irrigation, but are unlikely to enter garden beds.
3.4 Operations, maintenance and monitoring
3.4.1 Qualified staff
Only appropriately qualified staff should manage and operate the scheme. Depending on thenature of the scheme, plumbers, electricians and specialist technicians may all be involved in
operations. These staff should be trained in relevant aspects of the schemes operations andshould follow operational procedures.
If an organisation does not have the capacity to operate part or the entire scheme, externalcontractors should be suitably qualified, and should be informed about operational proceduresand protocols.
The operator should maintain details of competencies, qualifications, licences, trainingprograms undertaken, training needs identified and training records for employees andcontractors.
3.4.2 Scheme management plan
A scheme management plan should be prepared during the design phase, to describe thehealth and environmental risk management actions to be implemented during operations. Thiswill ensure critical knowledge is not lost with staff changes. The plan should highlight theroles and responsibilities of relevant parties, and provide a framework for appropriateoperation. It should be made available to all staff involved in operations. The content andextent of the management plan will vary, depending on the nature and scale of the scheme,but could include the information in Table 3.4.
8/3/2019 Australian Guidelines for Water Recycling: Stormwater Harvesting and Reuse, July 2009 - National Health
42/140
Stormwater reuse 31
Table 3.4 Indicative contents of a scheme management plan
Section Contents
Background Statutory requirements
Relevant permits or approvalsDescription, process flow diagram and map of the scheme,including the location of public warning signs and all undergroundpipes
Water quality and treatment objectives against which monitoringdata is measured
Roles andresponsibilities
How responsibilities are shared between treated stormwatersuppliers and end users (if applicable)
Responsibilities of any third parties (eg councils)
Operations Information on operating plant and equipment
Information on operating the irrigation scheme (if applicable),such as loading rates, access restrictions and irrigation timing
Procedures for responding to noncompliance with schemeobjectives (eg water-quality criteria)
Qualifications of personnel involved in the schemes operations
Maintenance Inspection schedules
Maintenance requirements
Statements of safe working methods to protect workersAsset management procedures
Incident (emergency)response(contingency) actions
Incident response protocols
Incident communications procedures
List of key stakeholders with current, verified contact details
Monitoring Operational monitoring requirements, including samplingmethods
Reporting procedures
Decommissioning Proposed arrangements for the safe decommissioning of thescheme
As part of the operators commitment to continuous improvement, the management planshould be reviewed regularly (eg every three to five years and after any major incident) andupdated as required.
3.4.3 Scheme commissioning, validation and verification
To prove a scheme is operating as designed, it should go through a three-phase process ofcommissioning, validation and verification (NRMMCEPHCAHMC 2006).
8/3/2019 Australian Guideline