19
Atwood Osprey Construction, Commissioning & Operations John Connor Chevron Sr. D&C Superintendent Gorgon Mark Stewart Operations Manager Atwood Osprey Perth 8 September 2011

Atwood Osprey Construction, Commissioning & Operations. Shipyard Rig... · 2012-04-16 · Perth 4th March, 2010 Click to edit Master title style Click to edit Master subtitle style

  • Upload
    dothuy

  • View
    213

  • Download
    0

Embed Size (px)

Citation preview

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

Atwood Osprey Construction, Commissioning & Operations

John Connor Chevron Sr. D&C Superintendent Gorgon Mark Stewart Operations Manager Atwood Osprey

Perth 8 September 2011

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

F&G Enhanced Pacesetter

• Water Depth = 6,600 ft Conventional 8,500 ft with presets • 12 point NOV Amclyde Mooring System • Drilling depth = 32,000 ft • VDL - 7,000MT

Drilling Systems

• NOV Active Heave Dwks. • Dual NOV Hydrarackers • Offline stand building capability (4” to 13 5/8”) • NOV ST-120 Iron Roughnecks (2) • 2,200HP LEWCO mud pumps (4) • 5,000+ BBL surface pit capacity • 7,500 psi HP mud system

Atwood Osprey Specifications

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

Well Control Systems

• Hydril 5 Ram – 15 ksi BOP • 2 x 10 ksi Annular Preventers • Full MUX controls • 6 x N-Line riser Tensioners

(3,600,000 lbs capacity) • Aker 21 ¼ Clip riser

Power System

• 4 x Caterpillar C-280 • Output 4,800 eKW each

Quarters

• 200 Man POB

Atwood Osprey Specifications

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

CVX and Atwood Objectives during construction and commissioning

Influence HSE Performance •Design focused on Safe Operations •Influence day to day construction work practices by engagement and cooperation with builder from the outset of construction •Encourage workforce involvement & commitment •Collectively develop operational and integrated testing JSA’s

Improve initial rig performance • Review Quality of construction completion • Ensure System commissioning 100% complete • Implement and execute detailed Builder and Chevron Integrated Acceptance Test plan • Implement and complete a very thorough training plan for Atwood personnel both technical and operational • Integrate Chevron and Atwood Operations teams on site early during construction and commissioning activities •Collectively develop operational and integrated acceptance testing procedures

Ensure greater level of Business Partner Preparation • Install majority of Chevron business partners equipment in the shipyard and incorporate interface and testing into builders integrated acceptance testing. • Fully Commission and perform additional testing of business partner equipment

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

Combined HSE Results during Construction and Commissioning

• Construction Safety Performance - Managed by Jurong Shipyard and actively influenced by Chevron and Atwood management

• 9.8 million man-hours (Jurong Shipyard, Atwood and Chevron) • 0.10 TRIR (Total recordable Incident rate ) • 3 Days away from work incidents • 2 Medical Treatment Incidents • 11 First Aid Incidents

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

Combined Performance Results During Construction and Commissioning

Construction

• Complete construction (100%) with no carryover to operations

• 80% of Business Partners equipment installed and operational.

Commissioning

• 370 individual systems commissioned. Integration & Acceptance

• Systems proved operational in shipyard Power generation & distribution Mud System operations Tubular handling systems drill floor and deck BOP & marine systems Mooring and Ballasting (limited)

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

Atwood Osprey Newbuild - Keys to Success

• Collective Factory Acceptance Test participation • Collective Design review and comment • Collective Commissioning Procedure development • Collective Integration Acceptance Test development & execution • Early Involvement of Atwood Operations and Chevron Site Team • Early & Extensive Business Partner involvement • Shared Lessons Learned from / to other Chevron rig construction teams • Joint Development of Operating procedures • Establish Osprey team Vision and First Year Goals •Safety, Reliability and Efficiency Sessions with entire Osprey team before commencing operations. • Collective initial drilling program reviews (DWOPs) • Daily planning communications between Chevron and Atwood

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

Operational Performance

• Atwood Osprey conditionally accepted in Singapore: 06:00 hrs 28 April 2011

• Atwood Osprey underway to the NW Shelf of Western Australia: 15:30 hrs 29 April 2011

• Additional Deep water acceptance testing involving the Mooring,

Cementing, BOP and Drilling systems completed simultaneously with Zagreus well operations.

• Chevron Australia's well Zagreus 1 spud 21:30 hrs 16 May 2011

• The Atwood Osprey commenced operations with a clearly defined and Osprey team developed “Vision” and set of first year goals

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

Osprey Underway to Zagreus 1 Location

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

“Osprey Vision”

Atwood Osprey Recognized for Safety, Reliability,

Efficiency and Teamwork.

¨Always, exceeding your expectations¨

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

Safety: • No one gets hurt • No harm to the environment

• No damage to equipment Reliability:

• ≥ 80% Overall productive time per well • ≥ 95% Rig productive time

Efficiency:

• Establish performance benchmarks and continuously improve

• Minimize impact of unplanned events

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

Teamwork: • Develop a true team environment by understanding

yourself and those who work with you • Maintain team stability by having less than 3% of

personnel electing not to return • All team members on time, ready to work, for a full

rotation

Expectations: • All supervisors and their team members will ensure

that there is a clear understanding of each others expectations

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

Osprey HES Performance

Since acceptance by Chevron on 28 April 2011 until 2 September 2011 • LTI 0

• Restricted Duty 1 (Fractured bone left hand - slip on stairs)

• Medical Treatment 0

• First Aid 4

• Spills to Water 0

• Spills to Containment 4

• Near Misses 8

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

Atwood Osprey Operational Reliability

• 3018 Operating Hours since conditional acceptance in Singapore

• Total surface or subsea equipment related unscheduled event downtime since acceptance: 4.26%

• Total downtime inclusive of contractually agreed zero rate for equipment verification and testing: 8.47%

• Preventative Maintenance System successfully implemented and personnel trained in use.

• Vendor service personnel released after 45-60 day operating period

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

Operational Reliability Zagreus 1

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

Operational Reliability Gorgon 3C

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

Operational Efficiency • Successfully moored on 2 Chevron locations (Zagreus and Gorgon M3) with

12 point mooring system. The second rig move only incurred 30 minutes of equipment related non productive time.

• Successfully moved the Osprey from Zagreus to Gorgon M3 at drilling draft

with all tubulars in the Derrick. • Successfully made up all drill pipe and majority of BHA components offline

reducing the impact to critical path time.

• Successfully made up 4 casing strings “offline” and racked and ran them into the well in stands from the Derrick.

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

Operational Efficiency • Successfully deployed and retrieved BOP stack in +/- 4000’ water depth at

Zagreus. Average riser running speed of +/- 4.5 joints/hour over first two wells (75 ft riser jts)

• Successfully unloaded , prepared and ran 10 casing strings to date.

• Developed and continue to improve +/- 280 rig specific operating procedures

• Maintain 90% compliance with Atwood training matrix • 90% compliant and continuing to improve on “Crew Familiarization” training

(Internal Atwood Competency Program)

Perth 4th March, 2010

Click to edit Master title style

Click to edit Master subtitle style

Click to edit Master title style

Click to edit Master subtitle style

Thank You