51
ATS Le Grandiose, Sector 150 Noida Energy Conservation Building Code (ECBC) Compliance Report

ATS Le Grandiose, Sector 150 Noida · Roof material As per ECBC 150 mm RCC with brick bat coba and 40 mm screed Roof U-value 0.046 0.124 Btu/hr ft2t F Glazing U Value 0.581 1.02 Btu/hr

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • ATS Le Grandiose, Sector 150 Noida

    Energy Conservation Building Code (ECBC) Compliance Report

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    1

    ATS Le Grandiose, Sector 150 Noida Energy Conservation Building Code (ECBC)

    Compliance Report

    For

    M/s. Nobility Estates Pvt. Ltd.

    CONTENTS

    ECBC .................................................................................................... 1

    1.0 INTRODUCTION ...................................................................... 4

    2.0 BUILDING & SITE INFORMATION ......................................... 5

    3.0 ENERGY MODELLING OVERVIEW ........................................ 5

    3.1 Building Geometry .................................................................. 5

    4.0 MODELING INPUT PARAMETERS ........................................ 6

    4.1 U Value Calculations .............................................................. 7

    5.0 ENERGY SIMULATION RESULTS ......................................... 8

    5.1 Tower 1 & 2 (Type B) ............................................................... 8

    5.2 Tower 3 -8 (Type A) ............................................................... 11 5.3 Tower 9 & 10 (Type B) .......................................................... 14 5.4 Tower 11 & 12 (Type C) ........................................................ 17 5.5 Tower 14 -19 (Type C) ........................................................... 20 5.6 Tower 20 & 21 (Type B) ........................................................ 23 5.7 Club 1 & 2 .............................................................................. 26

    ECBC

    ECBC is an acronym for

    Energy Conservation

    Building Code.

    The purpose of this code

    is to provide minimum

    requirements for the

    energy-efficient design

    and construction of

    buildings

    file:///E:/Green%20Buildings/UGreen/Projects/ATS/ATS%20GRANDIOSE_ECBC%20Compliance%20Report%20.docx%23_Toc494892115

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    2

    PROJECT BREIF

    M/s Nobility Estates Pvt. Ltd. has Proposed Group Housing Project (ATS Le Grandiose), At Plot

    No. – SC-01/C-A1, Sports City, Sector – 150, Noida, Uttar Pradesh, having Plot Area 80937.130

    sq. m. and built up area 316555.967 Sqm. ATS Le Grandiose is with 1172 dwelling units.

    Considering the nature of activities to be conducted and the various aspects of the project to

    be developed, our efforts in the approach for the planning of various systems, shall include

    the following considerations:

    In the operational phase, appropriate energy conservation measures and management plan will be adopted in order to minimize the consumptions of non-renewable fuel.

    CFL/LED will be used in place of incandescent lamps in office, common areas and parking.

    Percentage saving in energy consumption due to use of CFL/LED will be 15 -20 %. Lighting and switching of common area shall be designed keeping in mind day light

    integration.

    Roof insulation shall be planned to conserve energy. D.G. sets would be provided with auto cut and auto start mechanism. The water supply pumping system shall be provided with variable speed drive to

    conserve energy at part load.

    Glass opening will be provided with-in the ECBC limit of 40 %. Building will have appropriate design to shut out excess heat and gain loss.

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    3

    LOCATION & CLIMATIC DATA

    The Proposed Group Housing Project (ATS Le Grandiose), At Plot No. – SC-01/C-A1, Sports City,

    Sector – 150, Noida, Uttar Pradesh comes under composite climate conditions. Please find

    below the ECBC climatic zone map (India) for your kind reference.

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    4

    ECBC COMPLIANCE (Whole Building Performance Approach)

    1.0 Introduction The purpose of this report is to assess the compliance of the proposed design of the building

    and building systems in line with the Energy Conservation Building Code (ECBC).

    A building shall be called ECBC compliant by complying with the mandatory provisions (§4.2-

    Envelope, §5.2-HVAC, §6.2- SHW, §7.2 - Lighting, and §8.2 – Power) and either of the

    following:

    (a) Prescriptive Method (§4.3, §5.3, §7.3) (b) Whole Building Performance Method (Appendix B §10)

    Approach of Option B above is being followed to assess compliance for this project.

    Specialized building performance modelling software (eQUEST v3.63b) provided a platform for

    the energy modelling process. The proposed building geometry was translated into eQUEST

    v3.63b to create a 3-dimesional model, other modelling inputs into eQUEST v3.63b included;

    lighting, equipment & occupancy gains, operating profiles, plant efficiencies, thermal performance of constructions

    To show compliance through Option B, the annual energy consumption of the proposed

    building, as estimated by the modeling software, shall be less than the annual energy

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    5

    consumption of the ECBC compliant base building, as estimated by the same modeling

    software

    2.0 Building & Site Information The site included three types of apartments, namely Type A, B and C. There are 6 towers of

    Type A, 6 towers of Type B and 8 towers of Type C for a total of 20 towers. The site is in Noida

    which comes under composite climate zone as classified by ECBC.

    3.0 Energy Modelling Overview The “Proposed” energy model was defined and the proposed annual energy use calculated.

    Shell multiplier was used for all floors as they were typical in nature.

    The energy modelling undertaken included the use of both thermal modelling software

    (eQUEST v3.63b) and manual calculations. eQUEST v3.63b thermal modelling software

    simulated required plant sizes and annual energy use of the cooling systems for the proposed

    energy model. For simplicity, the 2 levels of basement were not modeled.

    3.1 Building Geometry The geometry of the proposed building was input in eQUEST v3.63b to create the 3-

    dimensional computer model shown in Figure 1

    FIGURE 1: MODELLED GEOMETRY

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    6

    4.0 Modeling Input Parameters

    Input Parameter Baseline Proposed Units

    Architectural

    Wall material As per ECBC 150 mm RCC wall work with 30 mm plaster

    Wall U-value 0.077 0.419 Btu/hr ft2 F

    Roof material As per ECBC 150 mm RCC with brick bat coba and 40

    mm screed

    Roof U-value 0.046 0.124 Btu/hr ft2t F

    Glazing U Value 0.581 1.02 Btu/hr ft2 F

    Glazing SHGC 0.25 0.55

    Frame Type N/A UPVC

    Window Shading &

    balconies

    N/A modelled

    HVAC (area under developer scope, for remaining area below mentioned guideline would be

    recommend to dwelling unit owner)

    Zone Cooling set

    point

    76 76 deg F

    Zone Heating set

    point

    70 70 deg F

    Cooling Sizing Ratio 1.15 1

    Heating Sizing

    Ratio

    1.25 1

    Cooling System Packed Single

    Zone

    Packed Single Zone

    Cooling COP

    (Dwelling)

    3.1 (BEE 3 Star) 3.1 (BEE 3 Star)

    Cooling COP (Club) 3.1 (BEE 3 Star) 3.1 (BEE 3 Star)

    Heating COP 2.5 2.5

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    7

    Lighting, Occupancy and Schedules

    Lighting Power

    Density (Building

    Area Method)

    0.70 0.49 W/ ft2

    Occupancy Bed Room -2; Bed Room -2; Person

    Living Room – 5 Living Room - 5

    Schedule Residential: Residential:

    8 am to 6pm-

    50%

    8 am to 6pm- 50%

    6 pm to 8 am –

    100 %

    6 pm to 8 am – 100 %

    4.1 U Value Calculations

    4.1.1 Wall Wall U-Value

    Material Thickness (m)

    K-Value (W/m K)

    R-Value (sq.m K/W)

    U-Value (W/sq.m K)

    U-Value (BTU/sq.ft hr F)

    ext. air film 0.04 2.37 0.419

    Plaster 0.02 0.57 0.04

    RCC 0.23 1.3 0.18

    Plaster 0.02 0.57 0.04

    int. air film 0.13

    Total 0.42

    4.1.2 Roof Roof U-Value

    Material Thickness (m)

    K-Value (W/m K)

    R-Value (sq.m K/W)

    U-Value (W/sq.m K)

    U-Value (BTU/sq.ft hr F)

    ext. air film 0.04 0.70 0.124

    plaster 0.01 0.57 0.02

    screed 0.1 0.09 1.11

    RCC 0.15 1.3 0.12

    plaster 0.02 0.57 0.04

    int. air film 0.10

    Total 1.42

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    8

    5.0 Energy Simulation Results Results are presented only based on the orientation and type of the building block.

    5.1 Tower 1 & 2 (Type B)

    FIGURE 2: 3D MODEL VIEW OF TOWER B

    TABLE 1: ENERGY END USE – PROPOSED & BASELINE IN KWH – TOWER 1 & 2 (TYPE B)

    DESCRIPTION UNITS LIGHTS MISC

    EQUIP

    SPACE

    HEATING

    SPACE

    COOLING

    VENT

    FANS

    TOTAL

    BASELINE - 0 DEG KWH 502323 327598 0 293698 47042 1170661

    BASELINE - 90 DEG KWH 502323 327598 0 293698 47042 1170661

    BASELINE - 180 DEG KWH 502323 327598 0 281234 46716 1157871

    BASELINE - 270 DEG KWH 502323 327598 0 293470 46870 1170261

    BASELINE - AVG KWH 502323 327598 0 290525 46918 1167364

    PROPOSED KWH 351626 327598 352 343262 51966 1074804

    ENERGY SAVINGS 8%

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    9

    FIGURE 3: SIMULATION OUTPUT - TOWER 1 & 2 (TYPE B) _ BASELINE 0

    FIGURE 4: SIMULATION OUTPUT - TOWER 1 & 2 (TYPE B) _ BASELINE 90

    FIGURE 5: SIMULATION OUTPUT - TOWER 1 & 2 (TYPE B) _ BASELINE 180

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    10

    FIGURE 6: SIMULATION OUTPUT - TOWER 1 & 2 (TYPE B) _ BASELINE 270

    FIGURE 7: SIMULATION OUTPUT - TOWER 1 & 2 (TYPE B) _ PROPOSED

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    11

    5.2 Tower 3 -8 (Type A)

    FIGURE 8:3D MODEL VIEW OF TOWER A

    TABLE 2: ENERGY END USE – PROPOSED & BASELINE IN KWH – TOWER 3 THROUGH 8 (TYPE A)

    DESCRIPTION UNITS LIGHTS MISC

    EQUIP

    SPACE

    HEATING

    SPACE

    COOLING

    VENT

    FANS

    TOTAL

    BASELINE - 0 DEG KWH 655273 474833 0 419617 64603 1614326

    BASELINE - 90 DEG KWH 655273 474833 0 424123 65321 1619550

    BASELINE - 180 DEG KWH 655273 474833 0 419735 64143 1613984

    BASELINE - 270 DEG KWH 655273 474833 0 423103 65292 1618501

    PROPOSED KWH 458688 474833 322 457692 69286 1460821

    ENERGY SAVINGS 9%

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    12

    FIGURE 9: SIMULATION OUTPUT - TOWER 3 THROUGH 8 (TYPE A) _ BASELINE 0

    FIGURE 10: SIMULATION OUTPUT - TOWER 3 THROUGH 8 (TYPE A) _ BASELINE 90

    FIGURE 11: SIMULATION OUTPUT - TOWER 3 THROUGH 8 (TYPE A) _ BASELINE 180

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    13

    FIGURE 12: SIMULATION OUTPUT - TOWER 3 THROUGH 8 (TYPE A) _ BASELINE 270

    FIGURE 13: SIMULATION OUTPUT - TOWER 3 THROUGH 8 (TYPE A) _ PROPOSED

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    14

    5.3 Tower 9 & 10 (Type B)

    FIGURE 14: 3D MODEL VIEW OF TOWER B

    TABLE 3: ENERGY END USE – PROPOSED & BASELINE IN KWH – TOWER 9 & 10 (TYPE B)

    DESCRIPTION UNITS LIGHTS MISC

    EQUIP

    SPACE

    HEATING

    SPACE

    COOLING

    VENT

    FANS

    TOTAL

    BASELINE - 0 DEG KWH 502323 327598 0 287686 45975 1163582

    BASELINE - 90 DEG KWH 502323 327598 0 293698 47042 1170661

    BASELINE - 180 DEG KWH 502323 327598 0 281234 46716 1157871

    BASELINE - 270 DEG KWH 502323 327598 0 293470 46870 1170261

    BASELINE - AVG KWH 502323 327598 0 289022 46651 1165594

    PROPOSED KWH 351626 327598 296 315085 47441 1042046

    ENERGY SAVINGS 11%

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    15

    FIGURE 15: SIMULATION OUTPUT - TOWER 9 & 10 (TYPE B) _ BASELINE 0

    FIGURE 16: SIMULATION OUTPUT - TOWER 9 & 10 (TYPE B) _ BASELINE 90

    FIGURE 17: SIMULATION OUTPUT - TOWER 9 & 10 (TYPE B) _ BASELINE 180

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    16

    FIGURE 18: SIMULATION OUTPUT - TOWER 9 & 10 (TYPE B) _ BASELINE 270

    FIGURE 19: SIMULATION OUTPUT - TOWER 9 & 10 (TYPE B) _ PROPOSED

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    17

    5.4 Tower 11 & 12 (Type C)

    FIGURE 20: 3D MODEL VIEW OF TOWER C

    TABLE 4: ENERGY END USE – PROPOSED & BASELINE IN KWH – TOWER 11 & 12 (TYPE C)

    DESCRIPTION UNITS LIGHTS MISC

    EQUIP

    SPACE

    HEATING

    SPACE

    COOLING

    VENT

    FANS

    TOTAL

    BASELINE - 0 DEG KWH 548768 357893 311 269539 56850 1233361

    BASELINE - 90 DEG KWH 548768 357893 1233 278928 56630 1243452

    BASELINE - 180 DEG KWH 548768 357893 939 265955 55943 1229498

    BASELINE - 270 DEG KWH 548768 357893 1158 280275 56789 1244883

    BASELINE - AVG KWH 548768 357893 910 273674 56553 1237799

    PROPOSED KWH 384136 357893 428 381430 70658 1194545

    ENERGY SAVINGS 3%

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    18

    FIGURE 21: SIMULATION OUTPUT - TOWER 11 & 12 (TYPE C) _ BASELINE 0

    FIGURE 22: SIMULATION OUTPUT - TOWER 11 & 12 (TYPE C) _ BASELINE 90

    FIGURE 23: SIMULATION OUTPUT - TOWER 11 & 12 (TYPE C) _ BASELINE 180

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    19

    FIGURE 24: SIMULATION OUTPUT - TOWER 11 & 12 (TYPE C) _ BASELINE 270

    FIGURE 25: SIMULATION OUTPUT - TOWER 11 & 12 (TYPE C) _ PROPOSED

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    20

    5.5 Tower 14 -19 (Type C)

    FIGURE 26: 3D MODEL VIEW OF TOWER C

    TABLE 5: ENERGY END USE – PROPOSED & BASELINE IN KWH – TOWER 14 THROUGH 19 (TYPE C)

    DESCRIPTION UNITS LIGHTS MISC

    EQUIP

    SPACE

    HEATING

    SPACE

    COOLING

    VENT

    FANS

    TOTAL

    BASELINE - 0 DEG KWH 548768 357893 143 263869 56465 1227138

    BASELINE - 90 DEG KWH 548768 357893 1233 278928 56630 1243452

    BASELINE - 180 DEG KWH 548768 357893 939 265955 55943 1229498

    BASELINE - 270 DEG KWH 548768 357893 1158 280275 56789 1244883

    BASELINE - AVG KWH 548768 357893 868 272257 56457 1236243

    PROPOSED KWH 384136 357893 299 351669 63606 1157603

    ENERGY SAVINGS 6%

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    21

    FIGURE 27: SIMULATION OUTPUT - TOWER 14 THROUGH 19 (TYPE C) _ BASELINE 0

    FIGURE 28: SIMULATION OUTPUT - TOWER 14 THROUGH 19 (TYPE C) _ BASELINE 90

    FIGURE 29: SIMULATION OUTPUT - TOWER 14 THROUGH 19 (TYPE C) _ BASELINE 180

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    22

    FIGURE 30: SIMULATION OUTPUT - TOWER 14 THROUGH 19 (TYPE C) _ BASELINE 270

    FIGURE 31: SIMULATION OUTPUT - TOWER 14 THROUGH 19 (TYPE C) _ PROPOSED

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    23

    5.6 Tower 20 & 21 (Type B)

    FIGURE 32: 3D MODEL VIEW OF TOWER B

    TABLE 6: ENERGY END USE – PROPOSED & BASELINE IN KWH – TOWER 20 & 21 (TYPE B)

    DESCRIPTION UNITS LIGHTS MISC

    EQUIP

    SPACE

    HEATING

    SPACE

    COOLING

    VENT

    FANS

    TOTAL

    BASELINE - 0 DEG KWH 502323 327598 0 281234 46716 1157871

    BASELINE - 90 DEG KWH 502323 327598 0 293698 47042 1170661

    BASELINE - 180 DEG KWH 502323 327598 0 281234 46716 1157871

    BASELINE - 270 DEG KWH 502323 327598 0 293470 46870 1170261

    BASELINE - AVG KWH 502323 327598 0 287409 46836 1164166

    PROPOSED KWH 351626 327598 87 329275 49953 1058539

    ENERGY SAVINGS 9%

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    24

    FIGURE 33: SIMULATION OUTPUT - TOWER 20 & 21 (TYPE B) _ BASELINE 0

    FIGURE 34: SIMULATION OUTPUT - TOWER 20 & 21 (TYPE B) _ BASELINE 90

    FIGURE 35: SIMULATION OUTPUT - TOWER 20 & 21 (TYPE B) _ BASELINE 180

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    25

    FIGURE 36: SIMULATION OUTPUT - TOWER 20 & 21 (TYPE B) _ BASELINE 270

    FIGURE 37: SIMULATION OUTPUT - TOWER 20 & 21 (TYPE B) _ PROPOSED

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    26

    5.7 Club 1 & 2

    FIGURE 38: 3D MODEL VIEW OF CLUB

    TABLE 7: ENERGY END USE – PROPOSED & BASELINE IN KWH – CLUB

    DESCRIPTION UNIT

    S

    LIGHTS MISC

    EQUIP

    SPACE

    HEATIN

    G

    SPACE

    COOLIN

    G

    VENT

    FANS

    TOTAL

    BASELINE - 0 DEG KWH 236883 157922 0 172512 28651 595968

    BASELINE - 90 DEG KWH 236883 157922 0 172397 28642 595844

    BASELINE - 180 DEG KWH 236883 157922 0 172193 28634 595632

    BASELINE - 270 DEG KWH 236883 157922 0 172425 28642 595872

    BASELINE - AVG KWH 236883 157922 0 172382 28642 595829

    PROPOSED KWH 165817 157922 2224 178270 30687 534920

    ENERGY / COST SAVINGS 10%

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    27

    FIGURE 39: SIMULATION OUTPUT – CLUB _ BASELINE 0

    FIGURE 40: SIMULATION OUTPUT - CLUB _ BASELINE 90

    FIGURE 41: SIMULATION OUTPUT - CLUB _ BASELINE 180

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    28

    FIGURE 42: SIMULATION OUTPUT - CLUB _ BASELINE 270

    FIGURE 43: SIMULATION OUTPUT - CLUB _ PROPOSED

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    29

    Annexure I: Proposed technical specification of additional

    equipment’s and materials complying to ECBC requirement

    i) Building Envelop

    S.No. Item Specification

    1 Fenestration

    (4.2.1)

    U- Factor

    Solar Heat Gain

    Coefficient

    (SHGC)

    Air Leakage

    All fenestration complying with the following

    requirement:

    U-factors & Solar Heat Gain Coefficient (SHGC) is

    determined for the overall fenestration product

    (including the sash and frame) in accordance with ISO-

    15099, as specified in ECBC, by an accredited

    independent laboratory, and labeled and certified by

    the manufacturer or other responsible party.

    Air leakage for glazed swinging entrance doors and

    revolving doors does not exceed 5.0 l/sm2.

    Air leakage for other fenestration and doors does not

    exceed 2.0 l/s-m2.

    2 Opaque

    Construction

    (4.2.2)

    The proposed opaque construction (Walls & Roofs) is as

    follows :

    U-factors are determined from the ECBC or determined

    from data or procedures contained in the ASHRAE

    Fundamentals, 2005.

    3 Building

    Envelope Sealing

    (4.2.3)

    The following areas of the enclosed building envelope is

    to be sealed, caulked, gasketed, or weather-stripped to

    minimize air leakage:

    (a) Joints around fenestration and door frames

    (b) Openings between walls and foundations and

    between walls and roof and wall panels

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    30

    (c) Openings at penetrations of utility services through,

    roofs, walls, and floors

    (d) Site-built fenestration and doors

    (e) Building assemblies used as ducts or plenums

    (f) All other openings in the building envelope

    4 Shading All vertical fenestration (Glazed doors & windows) are

    well shaded by the balcony overhang of at least 1500

    mm depth.

    5 Cool Roofs The terraces to be with high reflective material finish.

    The overall SRI would be more than 78.

    6 Skylight Not Proposed

    ii) Heating, Ventilation and Air Conditioning

    S.No

    .

    Item Specification

    1 Natural

    Ventilation

    (5.2.1)

    Openable doors/ windows are proposed in all dwelling units

    ensuring the natural ventilation complying with the design

    guidelines provided for natural ventilation in the National

    Building Code of India 2005 Part 8 Section 1, 5.4.3 and 5.7.1

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    31

    2 Minimum

    Equipment

    Efficiencies

    (5.2.2)

    BEE Star Unitary Air Conditioners (Dwelling Units) would be

    recommended to all owners by the project developer meeting

    IS 1391 (Part 1), Split air conditioner would be BEE 5 star to

    meet IS 1391 (Part 2).

    Cooling equipment to meet the minimum efficiency

    requirements presented in Table 5.1 (provided below). Heating

    and cooling equipment not listed here would comply with

    ASHRAE 90.1- 2004 §6.4.1.

    Unitary Air Conditioners (Dwelling Units) would meet IS 1391

    (Part 1), Split air conditioner would meet IS 1391 (Part 2),

    Packaged air conditioner would meet IS 8148 and Boilers

    would meet IS 13980 with above 75% thermal efficiency.

    3 Controls

    (5.2.3)

    All mechanical cooling and heating systems are controlled by a

    Time clock that:

    (a) Can start and stop the system under different schedules for

    three different day-types per week

    (b) Is capable of retaining programming and time setting

    during loss of power for a period of at least 10 hours, and

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    32

    (c) Includes an accessible manual override that allows

    temporary operation of the system for up to 2 hours

    Exceptions:

    (a) Cooling systems < 28 kW (8 tons)

    (b) Heating systems < 7 kW (2 tons)

    All heating and cooling equipment are with temperature

    controlled. Where a unit provides both heating and cooling,

    controls would be capable of providing a temperature dead

    band of 3°C (5°F) within which the supply of heating and

    cooling energy to the zone is shut off or reduced to a

    minimum. Where separate heating and cooling equipment

    serve the same temperature zone, thermostats would be

    interlocked to prevent simultaneous heating and cooling.

    All cooling towers and closed circuit fluid coolers would have

    variable speed drives controlling the fans.

    4 Piping and

    Ductwork

    (5.2.4)

    Piping for heating systems with a design operating

    temperature of 60°C (140°F) or greater have at least R-0.70 (R-

    4) insulation. Piping for heating systems with a design

    operating temperature less than 60°C (140°F) but greater than

    40°C (104°F), piping for cooling systems with a design

    operating temperature less than 15°C (59°F), and refrigerant

    suction piping on split systems would have at least R- 0.35 (R-

    2) insulation. Insulation exposed to weather would be

    protected by aluminum sheet metal. Cellular foam insulation

    would be protected as above.

    Ductwork would be insulated to achieve R value of 1.4

    5 System

    Balancing

    (5.2.5)

    All HVAC systems would be balanced in accordance with

    generally accepted engineering standards. A written balance

    report is to be provided to the owner or the designated

    representative of the building owner for HVAC systems serving

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    33

    zones with a total conditioned area exceeding 500 m2 (5,000

    ft2).

    Air System Balancing

    Air systems would be balanced in a manner to first minimize

    throttling losses. Then, for fans with fan system power greater

    than 0.75 kW (1.0 hp), fan speed would be adjusted to meet

    design flow conditions.

    Hydronic System Balancing

    Hydronic systems would be proportionately balanced in a

    manner to first minimize throttling losses; then the pump

    impeller would be trimmed or pump speed would be adjusted

    to meet design flow conditions.

    iii) Service Hot Water and Pumping

    S.No. Item Specification

    1 Solar Water

    Heating (6.2.1)

    Residential facilities to have solar water heating for at

    least 25% of the total energy required to meet hot water

    demand ( liters/day) at roof top

    2 Equipment

    Efficiency

    (6.2.2)

    Service water heating equipment meets the performance

    and minimum efficiency requirements presented in

    available Indian Standards

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    34

    (a) Solar water heater meets the performance/ minimum

    efficiency level mentioned in IS 13129 Part (1&2)

    (b) Electric water heater meets the performance /

    minimum efficiency level mentioned in IS 2082.

    3 Piping

    Insulation

    (6.2.4)

    Piping insulation would comply with 5.2.4 ECBC. The

    entire hot water system including the storage tanks,

    pipelines would be insulated conforming to the relevant IS

    standards on materials and applications.

    4 Heat Traps

    (6.2.5)

    Vertical pipe risers serving storage water heaters and

    storage tanks not having integral heat traps and serving a

    non-recirculating system would have heat traps on both

    the inlet and outlet piping as close as practical to the

    storage tank.

    iv) Lighting

    S.No. Item Specification

    1 Lighting

    Control (7.2.1)

    Automatic Lighting Shutoff

    Interior lighting systems in buildings lobby would be

    equipped with an automatic control device. Within these

    buildings, all school classrooms, and all lobbies would be

    equipped with occupancy sensors.

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    35

    Space Control

    Each space enclosed by ceiling-height partitions would

    have at least one control device to independently control

    the general lighting within the space. Each control device

    would be activated either manually by an occupant or

    automatically by sensing an occupant.

    Exterior Lighting Control

    Lighting for all exterior applications would be controlled

    by astronomical time switch that is capable of

    automatically turning off the exterior lighting when

    daylight is available or the lighting is not required.

    2 Exit Signs

    (7.2.2)

    Internally-illuminated exit signs would not exceed 5W per

    face.

    3 Exterior

    Building

    Grounds

    Lighting (7.2.3)

    Lighting for exterior building grounds luminaires which

    operate at greater than 100W would contain lamps having

    a minimum efficacy of 60 lm/W unless the luminaire is

    controlled by a motion sensor.

    4 Lighting Power

    Densities (LPD)

    20% reduction in ECBC prescribed values with use of LED

    higher efficacy LED lighting fixtures.

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    36

    v) Electric Power

    S.No. Item Specification

    1 Transformers

    (8.2.1)

    Maximum Allowable Power Transformer Losses

    Power transformers of the proper ratings and design

    must be selected to satisfy the minimum acceptable

    efficiency at 50% and full load rating. In addition, the

    transformer must be selected such that it minimizes the

    total of its initial cost in addition to the present value of

    the cost of its total lost energy while serving its

    estimated loads during its respective life span.

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    37

    2 Energy Efficient

    Motors (8.2.2)

    Motors would comply with the following:

    (a) All permanently wired poly phase motors of 0.375 kW or more serving the building and expected to operate more than 1,500 hours per year and all permanently wired poly phase motors of 50kW or more serving the building and expected to operate more than 500 hours per year would have a minimum acceptable nominal full load motor efficiency not less than IS 12615 for energy efficient motors.

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    38

    (b) Motors of horsepower differing from those listed in the table would have efficiency greater than that of the next listed kW motor

    (c) Motor horsepower ratings would not exceed 20% of the calculated maximum load being served

    (d) Motor nameplates would list the nominal full-load motor efficiencies and the full-load power factor

    (e) Motor users should insist on proper rewinding practices for any rewound motors. If the proper rewinding practices cannot be assured, the damaged motor should be replaced with a new, efficient one rather than suffer the significant efficiency penalty associated with typical rewind practices

    (f) Certificates would be obtained and kept on record indicating the motor efficiency. Whenever a motor is rewound, appropriate measures would be taken so that the core characteristics of the motor is not lost due to thermal and mechanical stress during removal of damaged parts. After rewinding, a new efficiency test would be performed and a similar record would be maintained

    3 Power Factor Correction (8.2.3)

    All electricity supplies exceeding 100 A, 3 phases would maintain their power factor between 0.95 lag and unity at the point of connection.

    4 Check-Metering

    and Monitoring

    (8.2.4)

    (a) Services exceeding 1000 kVA would have permanently installed electrical metering to record demand (kVA), energy (kWh), and total power factor. The metering would also display current (in each phase and the neutral), voltage (between phases and between each phase and neutral), and total harmonic distortion (THD) as a percentage of total current

    (b) Services not exceeding 1000 kVA but over 65 kVA would have permanently installed electric metering to record demand (kW), energy (kWh), and total power factor (or kVARh)

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    39

    (c) Services not exceeding 65 kVA would have permanently installed electrical metering to record energy (kWh)

    5 Power

    Distribution

    System Losses

    (8.2.5)

    The power cabling would be adequately sized as to maintain the distribution losses not to exceed 1% of the total power usage. Record of design calculation for the losses would be maintained.

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    40

    Annexure II: Proposed Building Plans

    Site Plan

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    41

    Building Plan (Type A)

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    42

    Building Plan (Type B)

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    43

    Building Plan (Type C)

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    44

    Clubs

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    45

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    46

    Annexure III: Estimated Solar PV Generation

    The proposed solar photovoltaic system of 10 KWp would generate approximately 14596 Kwh estimated through PVwatts India Calculator.

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    47

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    48

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    49

    Annexure III: Certificates

    Date: 01/10/2017

    To whom it may concern

    This is to certify that on implementation of all above mentioned ECBC mandatory

    compliances, the project ATS Grandiose, Sector 150 Noida is ECBC compliant.

    Thanks & Regards,

    Udit Gaurav

    Green Building & ECBC Professional

    GRIHA Evaluator & Trainer

    Indian Green Building Council Accredited Professional

    +91 8527532970

    [email protected]

  • ATS

    Le

    Gra

    nd

    iose

    , Sec

    tor

    150

    No

    ida

    50