Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
ATS Consolidation Day22nd May 2019
Beam Instrumentation
Rhodri Jones (BE-BI)
Introduction
• Beam Instrumentation Consolidation Domains– Replacement of outdated electronics
• ~ 20 years lifetime for most systems
• Beyond this maintenance & repair is difficult– Increasing number of failures
– Components required no longer available
– Rely on limited stock of spares
– Replacement of radiation damaged components• Beamline components typically over 20 years old in high radiation areas
– Spares for mechanical systems• Project started during LS1 to identify all beamline components & class
then in terms of risk to operation
• Critical items identified & being consolidated on all machines
2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019
2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019
PS complex & AD
No. Activity / Workunit STATUS [EDMS] Description & Consequences
1BTV Acquisition Electronics
RenovationActive 1550949
Replacement of outdated electronics – repair no longer possible. Replace with new electronics.
2Consolidation of ISOLDE BI
MechanicsActive Missing
Consolidation of 7 very old transformers in L2 (L4) transfer line & 5 in Booster Injection line
3Consolidation of PSB BTV
mechanismsActive Missing
Profit from production of new bellowless design for LIU to consolidate all PSB screen mechanisms
4Mechanical Spares for
Critical PS SystemsActive Missing
Construction of spare parts for operationally critical BI. Full inventory in LS1 resulted in prioritised list with input from OP. Additional budget added to complete.
5Consolidation of AD
Electron CoolerActive Missing
Consolidation options recently reviewed – awaiting final report. Current budget foresees complete replacement of existing cooler.
Schedule/BUDGET[kCHF]
No. 2019 2020 2021 2022 2023 2024 2025 SUM
1 100 30 57 187
2 100 100
3 412 412
4 70 50 150 80 100 450
5 100 500 1200 509 2309
2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019
PS complex & AD (New requests)
No. Activity / Workunit STATUS [EDMS] Description & Consequences
1Replacement of Analogue
CamerasNew Missing
270kCHF (awarded 2015-2017) to buy all remaining spare tube cameras in stock. Need to foresee complete replacement of analogue cameras by digital cameras
2
3
4
5
Schedule/BUDGET[kCHF]
No. 2019 2020 2021 2022 2023 2024 2025 SUM
1
2
3
4
5
2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019
SPS complex (Approved Activities)
No. Activity / Workunit STATUS [EDMS] Description & Consequences
1Consolidation of SPS SEM
ElectronicsActive 1550773
Replacement of outdated electronics – repair no longer possible. Replace with new electronics. Electronics already consolidated in PS complex
2Mechanical Spares for Critical
SPS Beam InstrumentationActive Missing
Construction of spare parts for operationally critical BI. Full inventory in LS1 resulted in prioritised list with input from OP. May need additional budget.
3SPS DCCT & Transfer Line FBCT
ReplacementActive 1550945
Currently relying on industry with service contract. Will pay for itself in long run, need to cover both contract & development in short term
4Consolidation of SPS Ring BLM
SystemActive Missing
Was LIU-SPS but cannot be done until after LS2 (manpower constraints). SPS system already showing signs of degradation. Urgent request from OP & MPP for additional protection.
Schedule/BUDGET[kCHF]
No. 2019 2020 2021 2022 2023 2024 2025 SUM
1 150 50 150
2 50 50 70 70 105 345
3 100 60 160
4 20 100 150 250 200 180 900
2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019
SPS complex (New Requests)
No. Activity / Workunit STATUS [EDMS] Description & Consequences
5Consolidation of TT2/TT10
Transfer Line BPMElectronics
New Missing
Replacement of outdated electronics – repair becoming problematic. Replace with same electronics as SPS Ring. Need early decision to profit.
6Consolidation of TI2/TI8
Transfer Line BLMsNew Missing
Based on old SPS BLMs & electronics. Consolidate at same time as SPS ring system (LS3) or LHC (LS4)
7SPS & Transfer Line BLM
ionisation chamberreplacement
New Missing
Not originally foreseen in SPS BLM consolidation. Degradation of existing monitors & lack of spares imply 750 new monitors required for SPS consolidation.Proposed to be funded through in-kind Russian contribution as part of HL request
8Consolidation of SPS
Ionisation Profile Monitor (BGI)
New Missing
Replacement of current system based on MCP and radiation tolerant camera with system based on LIU-PS TIMEPIX solution. Reduces maintenance costs (MCP & camera ageing) while adding performance.
Schedule/BUDGET[kCHF]
No. 2019 2020 2021 2022 2023 2024 2025 SUM
5 100 200 50 350
6 80 100 100 350 630
7 100 100 200 350 350 1100
8 50 120 190 360
2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019
East Experimental Area
No. Activity / Workunit STATUS [EDMS] Description & Consequences
1Consolidation of East Area
Beam InstrumentationActive Consolidation as part of general East Area CONS
2Consolidation of East Area
multi-wire proportional chambers
ActiveNo longer possible to easily maintain MWPCs or produce new ones. Will be replaced by scintillating fibre monitors developed for EHN1 (XBPF)
3Consolidation of East Area
BLM systemPartial
Funding
Schedule/BUDGET[kCHF]
No. 2019 2020 2021 2022 2023 2024 2025 SUM
1 33 50 11 94
2 23 30 53
3
2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019
North Experimental Area (Primary Lines)
No. Activity / Workunit STATUS [EDMS] Description & Consequences
1BSI and BSP Foil Monitor
RenovationNew 2141518
Consolidation of 8 foil monitors used for intensity and position monitoring. Degradation due to radiation and ageing electronics
2Student for BSI and BSP Foil
Monitor RenovationNew 2141518
Doctoral student to study SEM processes for high intensity beams. Possible collaboration with Liverpool (UK) 2Y CERN funding & 2Y Liverpool.
3 BTV Monitor Consolidation New2141518
Consolidation of 3 radiation damaged BTV systems to modern standards using optical line & digital cameras.
4Consolidation of North Area
BLM systemNew 2141518
Consolidation of BLMs. Ageing system already leading to SPS NA Physics downtime. Urgent, minimal, temporary intervention to ensure functioning to LS3 carried out in LS2.
Schedule/BUDGET[kCHF]
No. 2019 2020 2021 2022 2023 2024 2025 SUM
1 50 160 240 150 600
2 44 44 88
3 70 100 50 220
4 40 50 50 100 240
TOTAL (kCHF) 1148
2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019
North Experimental Area (Secondary Lines)
No. Activity / Workunit STATUS [EDMS] Description & Consequences
1Consolidation of North Area
ElectronicsDraft 3 2141518
Ageing electronics. Already running with hardware patch to allow old cards to run with new processors under Linux. New estimate up from 500kCHF to 755kCHF
2Consolidation of 65 Wire
Chambers & FISCS with XBPF (scintillating fibre monitor)
Draft 3 2141518
No longer possible to easily maintain MWPCs or produce new ones. XBPF proven to be viable alternative in EHN1. Original request for 200kCHF to consolidate some in LS2 not granted. New request covers all 65 monitors in LS3 for 1890kCHF.
3Urgent Consolidation for Post
LS2 RunningNew 2141518 Items identified as urgent to consolidate during LS2
4 Consolidation of XSCI & XCET New 2141518 Various smaller consolidation items for XSCI & XCET
Schedule/BUDGET[kCHF]
No. 2019 2020 2021 2022 2023 2024 2025 SUM
1 50 50 150 265 240 755
2 220 320 590 560 200 1890
3 110 200 310
4 40 80 15 135
TOTAL (kCHF) 3090
2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019
LHC (1 of 3)
No. Activity / Workunit STATUS [EDMS] Description & Consequences
1Consolidation of LHC Interlock
BPM SystemActive 1550779
Existing system unable to cover complete dynamic range or cope with doublet bunches. Full vertical slice to be installed during LS2.
2 VME Fan Replacement Active MissingCurrently completing replacement of power supply fans with fan-tray fans foreseen next.
3Mechanical Spares for Critical
LHC Beam InstrumentationActive 1550775
Construction of spare parts for operationally critical BI. Presented & approved at LMC. (Wirescanners, Dump BTV & special flanges).
4Consolidation of LHC
Wirescanner ElectronicsActive Missing
Replacement of ageing electronics to improvereliability during operation.
5Consolidation of LHC
Wirescanner MechanicsNew Missing
Request to HL cut in first budget review. Current, old LEP mechanics not viable for HL era.
Schedule/BUDGET[kCHF]
No. 2019 2020 2021 2022 2023 2024 2025 SUM
1 100 109 209
2 100 100 96 296
3 50 100 150
4 50 79 129
5 50 150 250 180 50 680
2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019
LHC (2 of 3)
No. Activity / Workunit STATUS [EDMS] Description & Consequences
6Consolidation of Radiation
Hard BLM front-endsActive Missing
Addresses noise on long cables. Only development costs paid by CONS. Production paid by HL-LHC.
7Consolidation of Standard LHC
BLM SystemActive Missing
Replacement of surface electronics to address reliability issues with current digital aquisitionsystem. A vertical slice will be in place for end LS2.
8LHC Spares: BLM Ionisation
Chamber SparesNew Missing
XX spare ionisation chambers required for LHC.Proposed to be funded through in-kind Russian contribution as part of HL request along with same type to be procured for SPS.
9Consolidation of Standard LHC BLM System Tunnel front-end
ElectronicsNew Missing
BLM tunnel electronics to be replaced during LS4. Will profit from SPS development and production. Budget for initial development and procurement of special components required before LS3
Schedule/BUDGET[kCHF]
No. 2019 2020 2021 2022 2023 2024 2025 >2025 SUM
6 50 100 150
7 380 100 100 27 607
8
9
2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019
LHC (3 of 3)
No. Activity / Workunit STATUS [EDMS] Description & Consequences
10Consolidation of Standard LHC
BPM SystemActive 1550846
Needs complete renovation of all electronics to maintain reliability for HL-LHC era. Assume that fibre-optic cabling is re-used.• 2.275MCHF from R2E
R2E pays for development of radiation tolerant tunnel components & EP fellows developing single mode fibre transmission system. R2E fellow foreseen for production of these components recently cut – but essential to the project!
• CONS pay for the production, non-radiation tolerant electronic components, crates & infrastructure
Schedule/BUDGET[kCHF]
No. 2019 2020 2021 2022 2023 2024 2025 SUM
10 100 150 200 500 1000 1500 759 4209
2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019
Summary of New Requests
Request PriorityBudget(kCHF)
Consequence if not done
Ionisation Chamber replacement 1 1100+LHCEssential for SPS, TL CONS & LHC Spares.Reduced reliability of BLM system if not done.Hoping for in-kind contribution from Russia.
Replacement of Analogue Cameras 1Production of current cameras being phased out.Majority need replacing by digital cameras by LS3
LHC Wirescanner Mechanics 1 680
Essential calibration tool for beam size in LHC.Consequence would be further degradation of accuracy & reproducibility.
LHC BLM System Tunnel Electronics 1End of life foreseen by LS4. Consequence would be loss of availability of LHC BLM system.
North Area Primary Lines 1/2/3 1148Priorities & consequences being addressed by BI-EA Working Group
North Area Secondary Lines 1/2/3 3090Priorities & consequences being addressed by BI-EA Working Group
TT2/TT10 BPM Electronics 2 350Maintenance problematic.No spares beyond LS3.
TI2/TI8 BLMs 2 630Reduced availability.Maintenance difficult beyond LS3.
SPS Ionisation Profile Monitor 2 360 Reduced performance & higher maintenance costs
Open Points
• Production of Spare Ionisation Chambers– Not originally planned to exchange for SPS, but delay from LS2 to LS3
with recent issues & few spares means this should be reconsidered– Also required for transfer lines & LHC spares– Has been targeted for Russian (IHEP) in-kind delivery through HL-LHC
• Awaiting outcome of decision
• North Area Consolidation– Huge effort by BE-BI, EN-EA & TE-ABT to define the needs for
consolidation throughout the North Area and its primary lines• BI-EA working group set-up to agree on scope & define priorities
– Input now provided to North Area consolidation project with BI needs• Priorities still to be clearly defined
• Consolidation of the LHC BPM System– Need to ensure finance for R2E fellow to complete the production and
test of up to 10,000 laser transmitter/receivers.
2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019