ATS Consolidation Day22nd May 2019

Beam Instrumentation

Rhodri Jones (BE-BI)

Page 2: ATS Consolidation Day · 2019-06-04 · Introduction •Beam ... 2019 ATS Consolidation Day R. Jones –BE-BI 22.05.2019 SPS complex (Approved Activities) No. Activity / Workunit

Introduction

• Beam Instrumentation Consolidation Domains– Replacement of outdated electronics

• ~ 20 years lifetime for most systems

• Beyond this maintenance & repair is difficult– Increasing number of failures

– Components required no longer available

– Rely on limited stock of spares

– Replacement of radiation damaged components• Beamline components typically over 20 years old in high radiation areas

– Spares for mechanical systems• Project started during LS1 to identify all beamline components & class

then in terms of risk to operation

• Critical items identified & being consolidated on all machines

2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019

Page 3: ATS Consolidation Day · 2019-06-04 · Introduction •Beam ... 2019 ATS Consolidation Day R. Jones –BE-BI 22.05.2019 SPS complex (Approved Activities) No. Activity / Workunit

2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019

PS complex & AD

No. Activity / Workunit STATUS [EDMS] Description & Consequences

1BTV Acquisition Electronics

RenovationActive 1550949

Replacement of outdated electronics – repair no longer possible. Replace with new electronics.

2Consolidation of ISOLDE BI

MechanicsActive Missing

Consolidation of 7 very old transformers in L2 (L4) transfer line & 5 in Booster Injection line

3Consolidation of PSB BTV

mechanismsActive Missing

Profit from production of new bellowless design for LIU to consolidate all PSB screen mechanisms

4Mechanical Spares for

Critical PS SystemsActive Missing

Construction of spare parts for operationally critical BI. Full inventory in LS1 resulted in prioritised list with input from OP. Additional budget added to complete.

5Consolidation of AD

Electron CoolerActive Missing

Consolidation options recently reviewed – awaiting final report. Current budget foresees complete replacement of existing cooler.

Schedule/BUDGET[kCHF]

No. 2019 2020 2021 2022 2023 2024 2025 SUM

1 100 30 57 187

2 100 100

3 412 412

4 70 50 150 80 100 450

5 100 500 1200 509 2309

Page 4: ATS Consolidation Day · 2019-06-04 · Introduction •Beam ... 2019 ATS Consolidation Day R. Jones –BE-BI 22.05.2019 SPS complex (Approved Activities) No. Activity / Workunit

2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019

PS complex & AD (New requests)

No. Activity / Workunit STATUS [EDMS] Description & Consequences

1Replacement of Analogue

CamerasNew Missing

270kCHF (awarded 2015-2017) to buy all remaining spare tube cameras in stock. Need to foresee complete replacement of analogue cameras by digital cameras

2

3

4

5

Schedule/BUDGET[kCHF]

No. 2019 2020 2021 2022 2023 2024 2025 SUM

1

2

3

4

5

Page 5: ATS Consolidation Day · 2019-06-04 · Introduction •Beam ... 2019 ATS Consolidation Day R. Jones –BE-BI 22.05.2019 SPS complex (Approved Activities) No. Activity / Workunit

2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019

SPS complex (Approved Activities)

No. Activity / Workunit STATUS [EDMS] Description & Consequences

1Consolidation of SPS SEM

ElectronicsActive 1550773

Replacement of outdated electronics – repair no longer possible. Replace with new electronics. Electronics already consolidated in PS complex

2Mechanical Spares for Critical

SPS Beam InstrumentationActive Missing

Construction of spare parts for operationally critical BI. Full inventory in LS1 resulted in prioritised list with input from OP. May need additional budget.

3SPS DCCT & Transfer Line FBCT

ReplacementActive 1550945

Currently relying on industry with service contract. Will pay for itself in long run, need to cover both contract & development in short term

4Consolidation of SPS Ring BLM

SystemActive Missing

Was LIU-SPS but cannot be done until after LS2 (manpower constraints). SPS system already showing signs of degradation. Urgent request from OP & MPP for additional protection.

Schedule/BUDGET[kCHF]

No. 2019 2020 2021 2022 2023 2024 2025 SUM

1 150 50 150

2 50 50 70 70 105 345

3 100 60 160

4 20 100 150 250 200 180 900

Page 6: ATS Consolidation Day · 2019-06-04 · Introduction •Beam ... 2019 ATS Consolidation Day R. Jones –BE-BI 22.05.2019 SPS complex (Approved Activities) No. Activity / Workunit

2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019

SPS complex (New Requests)

No. Activity / Workunit STATUS [EDMS] Description & Consequences

5Consolidation of TT2/TT10

Transfer Line BPMElectronics

New Missing

Replacement of outdated electronics – repair becoming problematic. Replace with same electronics as SPS Ring. Need early decision to profit.

6Consolidation of TI2/TI8

Transfer Line BLMsNew Missing

Based on old SPS BLMs & electronics. Consolidate at same time as SPS ring system (LS3) or LHC (LS4)

7SPS & Transfer Line BLM

ionisation chamberreplacement

New Missing

Not originally foreseen in SPS BLM consolidation. Degradation of existing monitors & lack of spares imply 750 new monitors required for SPS consolidation.Proposed to be funded through in-kind Russian contribution as part of HL request

8Consolidation of SPS

Ionisation Profile Monitor (BGI)

New Missing

Replacement of current system based on MCP and radiation tolerant camera with system based on LIU-PS TIMEPIX solution. Reduces maintenance costs (MCP & camera ageing) while adding performance.

Schedule/BUDGET[kCHF]

No. 2019 2020 2021 2022 2023 2024 2025 SUM

5 100 200 50 350

6 80 100 100 350 630

7 100 100 200 350 350 1100

8 50 120 190 360

Page 7: ATS Consolidation Day · 2019-06-04 · Introduction •Beam ... 2019 ATS Consolidation Day R. Jones –BE-BI 22.05.2019 SPS complex (Approved Activities) No. Activity / Workunit

2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019

East Experimental Area

No. Activity / Workunit STATUS [EDMS] Description & Consequences

1Consolidation of East Area

Beam InstrumentationActive Consolidation as part of general East Area CONS

2Consolidation of East Area

multi-wire proportional chambers

ActiveNo longer possible to easily maintain MWPCs or produce new ones. Will be replaced by scintillating fibre monitors developed for EHN1 (XBPF)

3Consolidation of East Area

BLM systemPartial

Funding

Schedule/BUDGET[kCHF]

No. 2019 2020 2021 2022 2023 2024 2025 SUM

1 33 50 11 94

2 23 30 53

3

Page 8: ATS Consolidation Day · 2019-06-04 · Introduction •Beam ... 2019 ATS Consolidation Day R. Jones –BE-BI 22.05.2019 SPS complex (Approved Activities) No. Activity / Workunit

2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019

North Experimental Area (Primary Lines)

No. Activity / Workunit STATUS [EDMS] Description & Consequences

1BSI and BSP Foil Monitor

RenovationNew 2141518

Consolidation of 8 foil monitors used for intensity and position monitoring. Degradation due to radiation and ageing electronics

2Student for BSI and BSP Foil

Monitor RenovationNew 2141518

Doctoral student to study SEM processes for high intensity beams. Possible collaboration with Liverpool (UK) 2Y CERN funding & 2Y Liverpool.

3 BTV Monitor Consolidation New2141518

Consolidation of 3 radiation damaged BTV systems to modern standards using optical line & digital cameras.

4Consolidation of North Area

BLM systemNew 2141518

Consolidation of BLMs. Ageing system already leading to SPS NA Physics downtime. Urgent, minimal, temporary intervention to ensure functioning to LS3 carried out in LS2.

Schedule/BUDGET[kCHF]

No. 2019 2020 2021 2022 2023 2024 2025 SUM

1 50 160 240 150 600

2 44 44 88

3 70 100 50 220

4 40 50 50 100 240

TOTAL (kCHF) 1148

Page 9: ATS Consolidation Day · 2019-06-04 · Introduction •Beam ... 2019 ATS Consolidation Day R. Jones –BE-BI 22.05.2019 SPS complex (Approved Activities) No. Activity / Workunit

2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019

North Experimental Area (Secondary Lines)

No. Activity / Workunit STATUS [EDMS] Description & Consequences

1Consolidation of North Area

ElectronicsDraft 3 2141518

Ageing electronics. Already running with hardware patch to allow old cards to run with new processors under Linux. New estimate up from 500kCHF to 755kCHF

2Consolidation of 65 Wire

Chambers & FISCS with XBPF (scintillating fibre monitor)

Draft 3 2141518

No longer possible to easily maintain MWPCs or produce new ones. XBPF proven to be viable alternative in EHN1. Original request for 200kCHF to consolidate some in LS2 not granted. New request covers all 65 monitors in LS3 for 1890kCHF.

3Urgent Consolidation for Post

LS2 RunningNew 2141518 Items identified as urgent to consolidate during LS2

4 Consolidation of XSCI & XCET New 2141518 Various smaller consolidation items for XSCI & XCET

Schedule/BUDGET[kCHF]

No. 2019 2020 2021 2022 2023 2024 2025 SUM

1 50 50 150 265 240 755

2 220 320 590 560 200 1890

3 110 200 310

4 40 80 15 135

TOTAL (kCHF) 3090

Page 10: ATS Consolidation Day · 2019-06-04 · Introduction •Beam ... 2019 ATS Consolidation Day R. Jones –BE-BI 22.05.2019 SPS complex (Approved Activities) No. Activity / Workunit

2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019

LHC (1 of 3)

No. Activity / Workunit STATUS [EDMS] Description & Consequences

1Consolidation of LHC Interlock

BPM SystemActive 1550779

Existing system unable to cover complete dynamic range or cope with doublet bunches. Full vertical slice to be installed during LS2.

2 VME Fan Replacement Active MissingCurrently completing replacement of power supply fans with fan-tray fans foreseen next.

3Mechanical Spares for Critical

LHC Beam InstrumentationActive 1550775

Construction of spare parts for operationally critical BI. Presented & approved at LMC. (Wirescanners, Dump BTV & special flanges).

4Consolidation of LHC

Wirescanner ElectronicsActive Missing

Replacement of ageing electronics to improvereliability during operation.

5Consolidation of LHC

Wirescanner MechanicsNew Missing

Request to HL cut in first budget review. Current, old LEP mechanics not viable for HL era.

Schedule/BUDGET[kCHF]

No. 2019 2020 2021 2022 2023 2024 2025 SUM

1 100 109 209

2 100 100 96 296

3 50 100 150

4 50 79 129

5 50 150 250 180 50 680

Page 11: ATS Consolidation Day · 2019-06-04 · Introduction •Beam ... 2019 ATS Consolidation Day R. Jones –BE-BI 22.05.2019 SPS complex (Approved Activities) No. Activity / Workunit

2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019

LHC (2 of 3)

No. Activity / Workunit STATUS [EDMS] Description & Consequences

6Consolidation of Radiation

Hard BLM front-endsActive Missing

Addresses noise on long cables. Only development costs paid by CONS. Production paid by HL-LHC.

7Consolidation of Standard LHC

BLM SystemActive Missing

Replacement of surface electronics to address reliability issues with current digital aquisitionsystem. A vertical slice will be in place for end LS2.

8LHC Spares: BLM Ionisation

Chamber SparesNew Missing

XX spare ionisation chambers required for LHC.Proposed to be funded through in-kind Russian contribution as part of HL request along with same type to be procured for SPS.

9Consolidation of Standard LHC BLM System Tunnel front-end

ElectronicsNew Missing

BLM tunnel electronics to be replaced during LS4. Will profit from SPS development and production. Budget for initial development and procurement of special components required before LS3

Schedule/BUDGET[kCHF]

No. 2019 2020 2021 2022 2023 2024 2025 >2025 SUM

6 50 100 150

7 380 100 100 27 607

8

9

Page 12: ATS Consolidation Day · 2019-06-04 · Introduction •Beam ... 2019 ATS Consolidation Day R. Jones –BE-BI 22.05.2019 SPS complex (Approved Activities) No. Activity / Workunit

2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019

LHC (3 of 3)

No. Activity / Workunit STATUS [EDMS] Description & Consequences

10Consolidation of Standard LHC

BPM SystemActive 1550846

Needs complete renovation of all electronics to maintain reliability for HL-LHC era. Assume that fibre-optic cabling is re-used.• 2.275MCHF from R2E

R2E pays for development of radiation tolerant tunnel components & EP fellows developing single mode fibre transmission system. R2E fellow foreseen for production of these components recently cut – but essential to the project!

• CONS pay for the production, non-radiation tolerant electronic components, crates & infrastructure

Schedule/BUDGET[kCHF]

No. 2019 2020 2021 2022 2023 2024 2025 SUM

10 100 150 200 500 1000 1500 759 4209

Page 13: ATS Consolidation Day · 2019-06-04 · Introduction •Beam ... 2019 ATS Consolidation Day R. Jones –BE-BI 22.05.2019 SPS complex (Approved Activities) No. Activity / Workunit

2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019

Summary of New Requests

Request PriorityBudget(kCHF)

Consequence if not done

Ionisation Chamber replacement 1 1100+LHCEssential for SPS, TL CONS & LHC Spares.Reduced reliability of BLM system if not done.Hoping for in-kind contribution from Russia.

Replacement of Analogue Cameras 1Production of current cameras being phased out.Majority need replacing by digital cameras by LS3

LHC Wirescanner Mechanics 1 680

Essential calibration tool for beam size in LHC.Consequence would be further degradation of accuracy & reproducibility.

LHC BLM System Tunnel Electronics 1End of life foreseen by LS4. Consequence would be loss of availability of LHC BLM system.

North Area Primary Lines 1/2/3 1148Priorities & consequences being addressed by BI-EA Working Group

North Area Secondary Lines 1/2/3 3090Priorities & consequences being addressed by BI-EA Working Group

TT2/TT10 BPM Electronics 2 350Maintenance problematic.No spares beyond LS3.

TI2/TI8 BLMs 2 630Reduced availability.Maintenance difficult beyond LS3.

SPS Ionisation Profile Monitor 2 360 Reduced performance & higher maintenance costs

Page 14: ATS Consolidation Day · 2019-06-04 · Introduction •Beam ... 2019 ATS Consolidation Day R. Jones –BE-BI 22.05.2019 SPS complex (Approved Activities) No. Activity / Workunit

Open Points

• Production of Spare Ionisation Chambers– Not originally planned to exchange for SPS, but delay from LS2 to LS3

with recent issues & few spares means this should be reconsidered– Also required for transfer lines & LHC spares– Has been targeted for Russian (IHEP) in-kind delivery through HL-LHC

• Awaiting outcome of decision

• North Area Consolidation– Huge effort by BE-BI, EN-EA & TE-ABT to define the needs for

consolidation throughout the North Area and its primary lines• BI-EA working group set-up to agree on scope & define priorities

– Input now provided to North Area consolidation project with BI needs• Priorities still to be clearly defined

• Consolidation of the LHC BPM System– Need to ensure finance for R2E fellow to complete the production and

test of up to 10,000 laser transmitter/receivers.

2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019