23
Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 1 Vaclav Vrba Institute of Physics, AS CR, Prague Pixel Detector Status

Atlas OW, Praha, September 16, 2003Vaclav Vrba, Institute of Physics, AS CR 1 Vaclav Vrba Institute of Physics, AS CR, Prague Pixel Detector Status

Embed Size (px)

Citation preview

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 1

Vaclav Vrba

Institute of Physics, AS CR, Prague

Pixel Detector Status

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 2

• Mechanics and services

• System tests

• Rad-hard electronics

• Module production

• Sensors

• Schedule

Layout of the talk

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 3

Mechanics and servicesMechanics and services

Forward A

Forward C

Barrel

PST FlangesPP1 End Plug

A 7m long object

A 7m long object

The Pixel Support Tube (PST) has passed PRR on Feb03 it is in production it should be delivered on schedule (Jan05) to be installed with the

barrel ID

PST (half length shown)PST (half length shown)PP0PP0 PP1PP1

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 4

The global pixel support has been

delivered;

The local supports (staves and sectors) have accumulated some delay, sectors because of change in pressure specs (cooling) and staves because of several minor problems at start-up. Not on critical path.

Even if the number of staves produced to date is small (9), the yield is very high (9/9) and the production of parts is now going on well.

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 5

Services topology and names (not to scale)

Pixel PP1

PP2

PP3 Located on the service platform. Only a preliminary layout exist.

Tile Cal

Lar Cal

Beam Line

Muon Chambers

Cooling, Signal & Optical Readout

Power and HV cables

Type II - Twisted Pair Cables (~ 9 meters)

Cryostat inner bore (PPF1)

Power and HV cables

Type III - Twisted Pair Cables (~ 140 meters)

PP2

PP2 for cooling

Z = 0

Voltage regulation box

PP0

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 6

Service Panels

FDR in June ‘03

Beam Pipe Support Stru

cture

Beam Pipe Support Stru

cture

Pixel Detecto

r

Not Shown

Beam Pipe

Service Panels

PP1 Patch Panel(pipes and cables not shown!)

PP0 Patch Panel

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 7

More work than foreseen around services, FDR has been passed recently and PRR will be by within 2003. Cables and fibers (PP1outward) must

be installed in Fall 04, so procurements

have to begin (very) soon. PP0 & PP1 (US deliverables) are very

crowded and PP1 (the interface to be open

first when we install/deinstall) should also afford issues related to moisture, activation high-P coolant and gas and electrical seals.

Optofiber bundles (PP0PP1 and PP1US15) have been designed and are about to go for tender (F,G and Cz)

Type 2 cables (Italy deliverable) have been mostly defined, still missing some connector compatibility check-up at PP1 (mock-up ongoing), then ready for tender

Type 3 cables (F, G, I, and US) mostly defined,

Work in progress…

PP1APP1A

PP1BPP1B

toward IPtoward IP

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 8

System tests show that operation of modules is not affected by LV multiplicity (1 LV source going to N (16) rad-hard voltage regulators, then from 1 regulator to 1 module). This measurement has been done with realistic services (i.e. cable lengths and x-sections ).

threshold (~3ke-) and noise (~180e-) are the same for LV multiplicity 1 and mult. 6

right histograms indicate difference between the two cases (thr=17e-, noise=6e-)

System testsSystem tests

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 9

Voltage regulators boards have been designed, built and tested using the rad-hard chip . this will be placed in the PP2 box (close to -chambers) some 12 m

(of cable) away from the detector itself. few boards for system tests built all regulators needed for the final system (5500) will be purchased

this year.

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 10

System tests (with regulators and final cables) have been done both on: realistic set-up (i.e. 6 modules on a sector support) in lab under irradiation (7 modules on C-C support irradiated to >30

Mrad) at PS.

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 11

FE&MCC FDR passed (810 Oct 02) Submissions received back in mid May (FEI2) and on June,6

(MCCI2) many improvements correcting limitations, but… one fault in each design does not allow to use them in the planned

“advanced production”, this will squeeze our schedule (see later). FEI : the improvements

7-bit (was 5-bit) threshold on each channel, works fine and very linear

native threshold dispersions ~650e- (was ~1000e-) and 25e- after tuning

autotune circuitry (new feature) allows to tune to ~50e- in 30”/module (instead than 2h/module if an external PC is used).

bias compensation circuitry eliminates FEI1 non-uniformities

hit-bus scaler to find “hot” pixels (and later kill them) works fine yield above 90% (on 1 wafer), encouraging as we changed IBM foundry from FEI1 to FEI2.

Rad-hard electronicsRad-hard electronics

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 12

FEI: the problem chip operates up to ~1.7V, then the register

loading stops to operate correctly and there

are errors in writing some configurations. this has been traced back to verify conditions

in the command and global shift registers those registers have been triplicated

(+ majority vote) to reduce the SEU rate

in order to safely operate the b_layer. in doing so, the size of the registers

became much larger.

Voltage at which Voltage at which configuration of configuration of FEI2 starts FEI2 starts failingfailing

FEI1FEI1

FEI2FEI2

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 13

FEI2: the problem (cont.)The clock distribution was not optimized for the SEU tolerant layout. problems could be traced to some section of the shift registers and those

appear to have clock lines sensibly longer than data lines, thus supporting the race hypothesis (a late arriving clock on one section of the SR does not strobe the correct bit, but the one just following)

FEI2: the fix Quick fix: route manually the ck against the data (casuality will avoid race

conditions) this change has been done on 6 back-up wafers (back Aug.15)=FEI2.1

Final fix: use proper simulation tools for the clock tree optimization, this may be necessary (submit Oct.2, wafers back at Nov. 26)= FEI3 (start design NOW)

How the clock How the clock moves through moves through one SEU one SEU tolerant shift tolerant shift register.register.One place One place where the error where the error happens is happens is indicated with indicated with yellow arrowsyellow arrows

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 14

Module production

Bump-bonding and flip-chip 2 syncronized tenders with same specs went out (Uni Bonn and

INFN Genoa). INFN tender is over with the choice of AMS (1500 modules), UniBonn

will be over soon and likely to end-up with IZM (600 modules). Two bump sources are critical to meet the schedule, they also are a safety measure against one firm loosing interest.

In the meantime modules produced with FEI1 (~40 per firm) allows to detect the most common yield losses and find corrective actions. PDB is precious for this trace back.

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 15

Production rate still low, but firms (and us) not yet in production mode.

Bare modules produced by firms, flex module produced

in labs (dressing and testing bare modules)

Bare module production

0

10

20

30

40

mod

ules

IZM

AMS

Flex module production

0

10

20

30

40m

odul

esIZM

AMS

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 16

some reworking may be necessary to keep the yield up (even if we operate on KGDs) as yield_module = (yield_chip)16

techniques for reworking in hand both for In and SnPb bumps and results ok (even if further parameter tuning for In is necessary to go below 30 defects/reworked chip)

Reworked chips

Venturi Vacum PumpZ-Axis

Pickup tool with load cell

Hot plate withPeltier cell

X-Y stage

Peltier Power supply

Motion control

IZM reworkedModulo Bonn-5

Tool per reworkingIn bump (AMS)

Milano

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 17

Flex1st 1000 flex delivered by Dyconnex. Quality is good, bow is small

enough not to cause problems. Starting-up loading now, first sample of 50 indicate chemical

cleaning problems and solder on bond pads in some cases. These must be solved before going into mass production, but believed to be easy.

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 18

Sensor production and testing

Dortmund

Prague

Udine

deliveries

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 19

Sensors Sensors

CiS production of 600 good tiles (all tested) done, next 400 delivery to resume next month after factory moved to a new site and restarted.

Tesla recently qualified for the mass production of pixel sensors for ATLAS. Production will start in January 04; end of production in

summer 05. We got a positive answer from both vendors for our request to

extend the option for buying more sensors up to Feb 05.

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 20

ScheduleSchedule

Advanced production was supposed to happen from summer to Dec03 this would have allowed a smooth start-up of all the (firm+lab) activities

related to module construction would have also allowed to build a couple of disks at least, thus reducing

the pressure on the forthcoming “real” production due to the delay of electronics we may now only hope to begin a smaller

advanced production with the 6 wafers of FEI2.1 this may at most give 1 disk plus the necessary modules to keep going with the qualification of the stave production labs.

all that translates into: delivery of the pixel system delayed by 2 months more compact production schedule with sharper start-up curve (and

therefore more risk) in the following are shown some details of the electronics and module

schedule.

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 21

Can this be anticipated?

Electronics scheduleElectronics schedule

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 22

Module scheduleModule scheduleXmas! Assumes 4w from wafer delivery

8w from wafers to dies

2m delay

Atlas OW, Praha, September 16, 2003 Vaclav Vrba, Institute of Physics, AS CR 23

Conclusions

Achieved technical progress is excellent, it has been demonstrated that pixels can really meet all LHC requirements,

Problems in electronics are not very serious and can certainly be corrected in the timescale indicated.

The sensor production is well in schedule – a half of the production is ready, end of the production in summer 2004.

Due to the present development with FE chips only in Spring04 we will be in position to safely extrapolate to the “ready to install” day.