ATF 202 – Project Management. UNIT 1. Project Management. Module Leader: Ken Robson Lecturer: David Baglee & Phil Johnson email: [email protected] Industry Centre Wessington Way Telephone: 0191515 2869. Project Management. ATF202 20 credit module Assessment by - PowerPoint PPT Presentation

Citation preview

Page 1: ATF 202 – Project Management

ATF 202 – Project Management

UNIT 1

Page 2: ATF 202 – Project Management

Project Management

Module Leader: Ken Robson Lecturer: David Baglee & Phil Johnson

email: [email protected]

Industry CentreWessington Way

Telephone: 01915152869

Page 3: ATF 202 – Project Management

Project Management

ATF202

20 credit module Assessment by

Semester 1 – Individual Assignment: 50%Semester 2 - Examination 50%

Page 4: ATF 202 – Project Management

Module Operation

Driven by study notes and Key text book Study notes available Ken’s home page

www.cet.sunderland.ac.uk/~cs0kro

Key Text : Project Management – Rory Burke 4th ed 2003 or

Project Management – Rory Burke 3rd ed 1999

Page 5: ATF 202 – Project Management

Project Management

Course

Lectures/tutorials: David Baglee

Labs – Microsoft Project : Phil Johnson

Page 6: ATF 202 – Project Management

Lesson Objectives

Investigate the characteristics of ‘a project’ Investigate what is involved in managing

projects Assess the importance of managing a

project Evaluate the likely problem areas within

projects Develop the basic skills to use Microsoft

Project

Page 7: ATF 202 – Project Management

Project Management in context

Where does Project Management fit with Operations Improvement?

The main emphasis of this programme is concerned with operations and this module the management of Capital Projects

Page 8: ATF 202 – Project Management

What do Operations Manager need to balance ?

Significant•BPR•CapitalProjects•Equipmentre-design

Incremental e.g. Reduce downtime

Changeoversscrap

‘Day to day business’.

Make widgets!Safety, budgets,

planning,people

management

OPERATEAND

MAINTAIN

IMPROVE REGENERATE

Page 9: ATF 202 – Project Management

Project Management

What do you think a Project is?

Page 10: ATF 202 – Project Management

Project Management Various definitions for a project

A temporary endeavour undertaken to create a unique product or service.

Planned activity. ‘A project is a set of co-ordinated activities that

contribute to the achievement of a common goal or goals.

British Standards have defined a project as:

“ a unique set of co-ordinated activities, with definite starting and finishing points, undertaken by an individual or organization to meet specific objectives within defined schedule, cost and performance parameters.”

Page 11: ATF 202 – Project Management

Projects vs Functional work

Key characteristics of projects a start and finish a budget planning is required specific objects are to be met or a specified product is to be created the project has a predetermined time span a lifecycle unique and non-repetitive tasks or activities single point of responsibility

Functional work - is normally repetitive, ongoing and predictable

Page 12: ATF 202 – Project Management

Exercise - Categorise the following

1. Launch a new product. Project/Functional2. Manage a research unit. Project/Functional3. Conduct an appraisal. Project/Functional4. Raise £50,000 in sponsorship. Project/Functional5. Sell Company services. Project/Functional6. Review existing procedures. Project/Functional7. Administer a Theatre Company.Project/Functional8. Supervise the office Project/Functional9. Build a house. Project/Functional10. Write a book. Project/Functional11. Editing a magazine. Project/Functional

Page 13: ATF 202 – Project Management

Exercise - Categorise the following

1. Launch a new product. Project2. Manage a research unit. Functional3. Conduct an appraisal. Functional4. Raise £50,000 in sponsorship. Project5. Sell Company services. Functional6. Review existing procedures. Project7. Administrate Theatre Company. Functional8. Supervise the office Functional9. Build a house. Project10. Write a book. Project11. Editing a magazine. Functional

Functional = ongoing and repetitive, Projects = have a beginning and end and non

repetitive.

Page 14: ATF 202 – Project Management

The Project Life Cycle

Generally considered to be four stages within the life cycle.

1. Concept and Initiation – establishes need or opportunity, feasibility of project is investigated.

2. Design & Development – uses guidelines to design product, service etc and develop detailed plans for implementing the project

3. Implementation – implements plan as in baseline plan developed in previous phase.

4. Commissioning and Handover – confirms the project has been implemented and the project is terminated.

Page 15: ATF 202 – Project Management

The Project Life Cycle

Key points:

Rate of effort and expenditure is higher during the implementation phase.

Normally some knowledge transfer occurs between phases

Potential to influence the project is highest during the concept and design phases.

Each of the four main phases can be managed as a separate project.

Page 16: ATF 202 – Project Management

Project Management

What is Project Management?

Project Management ‘the application of knowledge, skills, tools and techniques to project activities in order to meet stakeholders needs and expectations’ (PMBOK)

Page 17: ATF 202 – Project Management

PMBOK –Project Management Bodies of Knowledge

Several PM bodies have proposed knowledge frameworks: PMI – Project Management Institute, APM - Association of Project Managers

Some differences, but general agreement on key elements within P.M.

PMBOK provided by the PMI is a good example

PMBOK

Page 18: ATF 202 – Project Management

PMBOK

PROJECT INTEGRATION MANAGEMENTA subset of project management that includes the processes required to ensure that the various elements of the project are

properly coordinated. It consists of: Project plan development - integrating and coordinating all project plans to create a consistent, coherent document. Project plan execution - carrying out the project plan by performing the activ ities included therein. Integrated change control - coordinating changes across the entire project.

PROJECT SCOPE MANAGEMENTA subset of project management that includes the processes required to ensure that the project includes all the work

required, and only the work required, to complete the project successfully. It consists of: Initiation - authorizing the project or phase. Scope planning - developing a written scope statement as the basis for future project decisions. Scope definition - subdividing the major project deliverables into smaller, more manageable components. Scope verification - formalizing acceptance of the project scope. Scope change control - controlling changes to project scope.

PROJECT TIME MANAGEMENTA subset of project management that includes the processes required to ensure timely completion of the project. It consists

of: Activity definition - identifying the specific activities that must be performed to produce the various project deliverables. Activity sequencing - identifying and documenting interactivity dependencies. Activity duration estimating - estimating the number of work periods that will be needed to complete individual

activities. Schedule development - analysing activity sequences, activity durations, and resource requirements to create the

project schedule. Schedule control - controlling changes to the project schedule.

Page 19: ATF 202 – Project Management

PMBOK

PROJECT QUALITY MANAGEMENTA subset of project management that includes the processes required to ensure that the project will satisfy the

needs for which it was undertaken. It consists of: Quality planning - identifying which quality standards are relevant to the project and determining how to

satisfy them. Quality assurance - evaluating overall project performance on a regular basis to provide confidence that the

project will satisfy the relevant quality standards. Quality control - monitoring specific project results to determine if they comply with relevant quality

standards and identifying ways to eliminate causes of unsatisfactory performance.

PROJECT HUMAN RESOURCE MANAGEMENTA subset of project management that includes the processes required to make the most effective use of the

people involved with the project. It consists of: Organizational planning - identifying, documenting, and assigning project roles, responsibilities, and reporting

relationships. Staff acquisition - getting the needed human resources assigned to and working on the project. Team development - developing individual and group skills to enhance project performance.

PROJECT COMMUNICATIONS MANAGEMENTA subset of project management that includes the processes required to ensure timely and appropriate

generation, collection, dissemination, storage, and ulti mate disposition of project information. It consists of: Communications planning - determining the information and communica tions needs of the stakeholders: who

needs what information, when they will need it, and how it will be given to them. Information distribution - making needed information available to project stakeholders in a timely manner. Performance reporting - collecting and disseminating performance information. This includes status reporting,

progress measurement, and forecasting. Administrative closure - generating, gathering, and disseminating information to formalize phase or project

completion.

Page 20: ATF 202 – Project Management

PMBOKPROJECT RISK MANAGEMENTRisk management is the systematic process of identifying, analysing, and responding to project risk. It includes maximizing the probability and conse

quences of positive events and minimizing the probability and consequences of adverse events to project objectives. It includes: Risk management planning - deciding how to approach and plan the risk management activities for a project. Risk identification - determining which risks might affect the project and doc umenting their characteristics. Qualitative risk analysis - performing a qualitative analysis of risks and con ditions to prioritise their effects on project objectives. Quantitative risk analysis - measuring the probability and consequences of risks and estimating their implications for project objectives. Risk response planning - developing procedures and techniques to enhance opportunities and reduce threats from risk to the project’s objectives. Risk monitoring and control - monitoring residual risks, identifying new risks, executing risk reduction plans, and evaluating their effectiveness

throughout the project life cycle.

PROJECT PROCUREMENT MANAGEMENTA subset of project management that includes the processes required to acquire goods and services to attain project scope from outside the performing

organi zation. It consists of: Procurement planning - determining what to procure and when. Solicitation planning - documenting product requirements and identifying potential sources. Solicitation - obtaining quotations, bids, offers, or proposals, as appropriate. Source selection - choosing from among potential sellers. Contract administration - managing the relationship with the seller. Contract closeout - completion and settlement of the contract, including resolution of any open items.

PROJECT COST MANAGEMENTA subset of project management that includes the processes required to ensure that the project is completed within the approved budget. It consists of: Resource planning - determining what resources (people, equipment, mate rials) and what quantities of each should be used to perform project

activities. Cost estimating - developing an approximation (estimate) of the costs of the resources needed to complete project activities. Cost budgeting - allocating the overall cost estimate to individual work activities. Cost control - controlling changes to the project budget.

Page 21: ATF 202 – Project Management

Project Management

If projects are not managed?

THEY’RE GONNA FAIL!

Project management - Not ‘rocket science’

Its common sense, isn’t it?

Page 22: ATF 202 – Project Management

Projects not delivered on time

Confirmation by Airbus of the delays came

after Australian airline Qantas revealed last week that delivery of

the first of its 12 A380s had been put back

from October 2006 to April 2007 and still not

complete.

Lead contractor Multiplex has missed three completion

deadlines since taking on the £757 million

project.

Page 23: ATF 202 – Project Management

Work and pensions IT projects £315m over budget As completion date slips from 2007 to 2011

Channel TunnelOriginal estimated cost:£4.8bnFinal cost: £10bn one year late

Projects not delivered on time

Page 24: ATF 202 – Project Management

Poor planning

Page 25: ATF 202 – Project Management

Next week

Project Evaluation