ASTRA Update
Sunflower ProjectStatewide Management, Accounting and Reporting Tool (SMART)
May 14, 2009
2
Agenda
• Project Status and Activities
• Project Decisions
• Upcoming Events, Activities and Reminders
3
Project Timeline
Plan & Analyze
Oct ‘08—Dec ’08
Design
Jan ‘09—Apr ’09
Build
May ‘09—Oct ’09
Test & Deploy
Nov ‘09—Jun ’10
Support
Jul ‘10—On
· Host Project Kickoff · Launch Website· Identify Agency
Contacts· Conduct Conference
Room Pilots· Publish Project Charter· Complete Agency
Skills Assessment· Launch Project
Newsletter
· Conduct Agency Introduction Meetings
· Launch Change Agent Network
· Conduct Configuration Workshops
· · Distribute Initial Agency Readiness Assessment
· Design Agency Interface
· Create Agency Conversion Strategy
· Design Training Curriculum
· Conduct Change Agent Meetings
· Conduct Business Process Workshops
· Conduct Configuration Workshops
· Distribute Agency Readiness Assessments
· Modify System · Adjust Agency
Interfaces· Clean Up Data· Build Data Conversion
Processes· Build Training
Curriculum
· Conduct Change Agent Meetings
· Pilot Training Curriculum
· Conduct Train-the-Trainer Programs
· Train End-Users· Distribute Agency
Readiness Assessments
· Plan Cutover· Test Agency Interfaces· Test and Load Data for
Conversion· Reconcile Data· Establish Help Desk· Perform User
Acceptance Testing· Validate System· Cutover to New
System: July 1, 2010
· Support Production· Respond to Agency
Feedback· Decommission
Redundant Agency Systems
4
Project Status & Activities
• Data conversion workshops held on May 5th:• Approx 150 attendees• Provided overview of conversion process• Discussed data conversion strategies and considerations
such as on-line vs. automated• Reviewed agency and project responsibilities and timeline
• Data Warehouse Advisory Group• Held 1st meeting• Engaged group with lots of good ideas• Homework assigned – prototype a management dashboard
for CFO or other high-level manager• Hands-on workshop in late June using data warehouse and
query/reporting tools and dashboards
5
• Agencies will use a combination of either a Purchase Order (PO) or General/Ledger (GL) to encumber funds at year end
• If the vendor is known create a Purchase Order in SMART
• If the vendor is not known, i.e. “blanket” encumbrance use a G/L encumbrance
• G/L encumbrances must be manually converted to a Purchase Order on-line in SMART to establish a PO encumbrance (normally a fiscal person)
• Then the INF02 interface (voucher load containing the PO#) can be processed to liquidate the encumbrance
Project Decisions - Encumbrances
6
• Agencies are encouraged to use the best practice of allowing SMART to auto-number transactions.
or
• Agencies may choose to “smart” numbering to avoid major changes to systems and change management issues
Project Decisions – Auto-Numbering
7
• Solution will use Accounts Receivable and Accounts Payable modules and associated interfaces (INF02 and INF44)
• Interagency receivables and payables are recorded on the books• Selling agency enters a deposit in Accounts Receivable (AR)• Buying agency enters and pays the voucher in Accounts Payable
(AP)
• SMART will be modified to match the paired transactions so that an agency can view both sides of the transaction
• Each agency controls the entry and approvals of its side of the entry
• Agency-to-agency notifications via workflow or email
• Each agency can view both sides of the entry
• No identified changes expected to INF02 and INF44 to support interfunds
Project Decisions – Interfund
8
•Year End Concurrent Processing
•Cutover Strategy
Project Activities – Pending Decisions
9
Upcoming Events & Activities
• Change Agent Network Meeting #3 on May 20, 2009 from 9:00 to 11:00 a.m. at Topeka & Shawnee County Public Library Marvin Auditorium – Invitations sent May 6, 2009
• Testing Overview• Training Update• Project Decisions – Including detail on new Chart
of Accounts structure• Shared Services Center• SMART Demo
• Publish 3rd edition of the Sunflower Project Newsletter – mid-June 2009
10
Configuration Workshops are being conducted to help agencies complete more complex configuration activities
•Program and Department ID ChartFields Configuration Workshop
•June 1 – 4 and June 15 – 18 •(attend one 2 hour session)
•Refer to invitation sent 5/7/09
•Project Setup Configuration Workshop•June 2 – 4, June 9 – 11, and June 16 – 18
•(attend one 2 hour session)•Refer to invitation sent 5/7/09
Upcoming Events & Activities
11
Roles and ResponsibilitiesAgency Contacts
• Advocate the Sunflower Project and communicate information throughout all levels of your agency – forward emails, etc.
• Attend project presentations, workshops, training, etc
• Proactively follow up with Agency Readiness Liaisons as needed for clarifications and to bridge knowledge and communication gaps
• Work through items on the Agency Task List. Adhering to project quality standards and timeline
• Assess and communicate Agency’s readiness for the transition to SMART
12
Project Resources
• Sunflower Project website: http://www.da.ks.gov/smart/
• Sunflower Project Email Address: [email protected]
• Sunflower Project List-serv– Sunflower Infolist– Subscribe at http://www.da.ks.gov/smart/
• Sunflower Project Site: Sunflower Project, 915 SW Harrison, Room 1181, Topeka, Kansas 66612
13
Questions
For additional information on the project, please seethe project website: