Upload
hoangduong
View
218
Download
2
Embed Size (px)
Citation preview
Dong Energy is a leading offshore wind developer, having built around half of all offshore wind farms globally. (50%)
E.ON is one of the world’s leading power and gas companies. It’s renewable division (E.ON Climate and Renewables) is one of the largest renewable energy companies in the world. (30%)
The Masdar Initiative is Abu Dhabi’s multi-faceted, multi-billion dollar investment in the development and commercialisation of innovative technologies in renewables, alternative and sustainable energies as well as sustainable design. (20%)
Consortium partners
Project overview
• 1000MW consented
• 20km from coast (Kent & Essex)
• Export cables >50km
• Wind farm area up to 245 km2
• 50 year lease
• Phase 1 – 630MW
• Phase 2 – 370MW
• Phase 2 depends on successful bird studies
Crown Estate Rounds 1 and 2
As the owner of the seabed the Crown Estate has a central role in the delivery of UK offshore wind
Round 2 – Fully Commercial
• 15 Sites• Agreements for lease in
Territorial Waters and UKCS• 40/50 year leases depending
on site capacity
• Option fees according to size
Round 1 – Demonstration Projects
•18 Projects, 13 locations•30 turbines maximum•20MW minimum installed•10 km2 maximum area•22 year leases
London Array is a Round 2 Project
Crown Estate Round 3
• Rapid development of offshore wind capacity is key to the delivery of the UK's share of the EU target of 20 per cent renewable energy by 2020.
• Round 3 leasing programme anticipates the delivery of up to 25 GW (gigawatts) of new offshore wind farm sites by 2020.
• The Crown Estate will be inviting potential partners to bid for development zones
• Successful bidders will have exclusive rights to develop wind farms in specified zones.
• The selected partners will remain wholly responsible for construction and operation of wind farm sites.
Phase one overview
• FID – May 2009
• Wind farm area c. 100 km2
• Siemens 3.6MW turbines
• 175 turbines, 630MW
• Monopile foundations
• 2 x offshore substations
• 4 x 150kV cables
• Onshore substation at Graveney, North Kent
• Construction/O&M at Ramsgate, Kent
Project Gestation
Apr 01 – First Project Heads of Terms
Dec 03 – Crown Estate agreement for lease
Jun 05 – Consent applications submitted
Jun 06 – Swale BC rejected application for substation
Dec 06 – Offshore consents granted
Mar 07 – Substation public inquiry - decision Aug 07
Jul 08 – Shell’s share to DONG (50%) and E.ON (50%)
Oct 08 – E.ON sold 40% of its share to Masdar
Apr 09 – Budget assistance for Round 2 projects
May 09 – Investment decision & turbine contract
Jul 09 - Construction of onshore substation started
Mar 11 - Offshore construction started
11
(Resolution)
Development
• Environmental Impact Assessment
• Technical Design Statement (FEED)
• Environmental Statement
• Consent Applications
• Offshore and onshore consents received
Procurement and Construction
• Framing Workshop
• Review 1 – Pre-Tender (contract strategy & design concepts)
• Review 2A – Pre-FID
• Review 2B – Pre-Construction
• Review 3 – After 1 year full operation
Project Management Process
12
• Multi-contract approach adopted by the Participants
• 12 Contract Packages, including installation vessels and O&M facilities
• JV Project Team managing ITT, tender negotiations and contracting
• Legal advice on contracts provided by Pinsent Masons
• Interfaces between packages managed by Project Team
• Participant Procurement Compliance Panel (PPCP) ensures compliance with Contracting and Procurement Policy
• Contract strategy changed as result of the tender process:
• Turbine supplier declined to install turbines
• Foundation contractor agreed to install turbines in addition to foundations but did not have the right vessels
• London Array had to free issue the installation vessels
Procurement approach
13
Wind turbines
Foundations
Offshore substations
Siemens Wind Power to supply 175 3.6MW turbines, fitted with new 120m rotor
JV between Par Aarsleff A/S and Bilfinger Berger GmBH to supply 177 monopiles and 175 transition pieces
WTG and foundation installation
Installation by Aarsleff A/S and Bilfinger Berger GmBH
Future Energy (JV of Fabricom, lemants and Geosea) to supply and install offshore substation platforms (electrical eqpt from Siemens T&D) and to supply transition pieces
Export cable supply Nexans Norway to supply 220km of 150kV export cable
Main contractors (Phase one)
14
Main contractors (Phase one)
Array cable supply
Offshore installation vessels
JDR Cable Systems to supply 210km of 33kV array cables
Export and array cable installation
Installation by by Visser and Smit Marine Contracting and Global Marine Systems Limited
Onshore substation Siemens Transmission and Distribution Ltd
MPI Adventure and A2SEA Sea Worker
O&M base design and construction
Designed by BBLB Architects, contractor Mansell
15
(Resolution)
Implementation schedule for phase one
Q2Q4Q3Q2Q1
2012
Q1
2013
Q3 Q4 Q1
2011
Foundation installation
Grid connection
Offshore substation installation
Export cable installation 2011 & 2012
Array cable installation
Wind turbine installation
Wind farm fully operational
Onshore substation
16
• Strong local opposition to onshore substation
• Public Inquiry – Jul 06 to Aug 07
• Architectural competition - winner accepted by Inspector
• Competitive tender for layout design for local authority approval
• Negotiated contract for onshore & offshore electrical equipment
• Siemens T&D started onshore construction in Jul 09
• Civil works and landscaping for Phase 2 completed with Phase 1
• Oct 11 grid connection date for 125MW
• Jun 12 grid connection date for 630MW
• Phase 1 transmission assets to be transferred to an OFTO
Cleve Hill - 400kV onshore substation
20
(Resolution)
• Max tidal range: 5.40m
• Water depths between 0 and 25 m LAT + tide:Shallow areas problematic for installation vesselsDeep areas need large foundations, long jack-up legs
• Tidal currents: NW to SW and 0.8 to 1.5m/s:Implications for diving operations and scour
• Large global seabed changes:Cable exposure, foundation stability, structural frequencies
• Relatively poor soil conditions:Large piles and deep seabed pile penetration requiredJack-up leg penetrationUXOs and marine archaeology
Phase one site characteristics
21
Foundation Installation (Aarslef Bilfinger Berger)• Monopiles and TP's shipped from Aalborg to Harwich by barge• Installation vessel loaded with monopiles and TP's, relocates to
specific foundation location and jacks up• Monopiles installed to correct level• Transition piece placed on top and grouted in place
Wind Turbine Installation (Aarslef Bilfinger Berger)• Turbines shipped from Esbjerg to Harwich by barges • Installation vessel loaded with turbines, relocates to specific
foundation location and jacks up• Turbines installed (turbines commissioned by Siemens WP)
Installation Vessels (Free issue by London Array)• MPI Adventure: self-propelled jack up barge.• A2Sea Sea Worker: non-propelled jack up barge.
Foundation and turbine installation
22
Installation vessels
A2Sea SeaWorker
MPI Adventure (new build)• Adventure built in China for MPI by COSCO
• Free LAL issue to ABJV
• Due to mobilise with ABJV May 2011
• Sea Worker on site Feb 11
• Needed for shallow locations
23
• Failure of DNV designed grout
connections on operational
projects after contract placed
with Aarsleff Bilfinger Berger
(ABJV)
• Redesign of monopiles and TPs
has caused delay, needing
acceleration measures to
maintain programme
• London Array has adopted DNV
conical rather than the shear
key solution to the problem
Foundations - monopiles and transition pieces
27
• Two 1400t offshore substations transform 33kV from turbines to 150kV
• Substations assembled in Belgium by FE JV, Siemens are supplying and installing electrical equipment
• Substations to be shipped to site by barge and installed by “The Rambiz”.
Image: Gunfleet Sands, courtesy of Dong Energy
Offshore substations
• Substation TPs heavier than those for turbines and require heavy lift vessel – Matador 3
29
New build Stemat Spirit
•4600 tonnes of export cable
•Deep locations and able to beach
•Avoids unnecessary joints
Cable installation
Generic cable installation issues
•Overruns from previous contracts
•Financial strength of contractors
•Cable damage during installation
Array Cable – shallow – Jan Steen Deep – CS Sovereign