Upload
harpreet-kaur
View
215
Download
0
Embed Size (px)
Citation preview
8/13/2019 Assignment IT Governance
http://slidepdf.com/reader/full/assignment-it-governance 1/14
Contemporary IT Practice & Governance
Contemporary ITPractice &Governance
Robin Vashishat
Course: Q702 IT Governance
Teacher : Milton D’souza
By
8/13/2019 Assignment IT Governance
http://slidepdf.com/reader/full/assignment-it-governance 2/14
1
Formal Technical Report
Integrated National
Computerized Information System
Abstract of Report
This report has been produced in relation to the
preparation of custom based software INCIS. There was another system
using by police in the past. Now, the users of that system are not satisfied
with the applications and features of that system. So, the preparation of the
new system takes place.
In the preparation process, lots of issues and complexities
takes place which resulted in delay of project. In this report, the
explanation and needs for the new system is mentioned. It also gives an
idea about the problems in implementations and other cost related issues.
This report is an example of why projects needs IT Governance. It also
describes the two IT Governance models and some recommendations that
should be followed by project team for their future IT projects.
8/13/2019 Assignment IT Governance
http://slidepdf.com/reader/full/assignment-it-governance 3/14
2
Purpose of Report
The purpose of this report is to provide new ways to
develop IT projects and improve the factors that delayed theimplementation of INCIS. It emphasis to develop a trend to opt for
customized package software rather than custom build. The new system
was developed to keep police record up to date automatically. This was a
replacement of old system. But because of over budget and complexity of
large project, police was failed to implement it properly.
The report discussed the problems that were encountered in
the development and implementation of the Police system INCIS. It is also
mentioned that how the police and Government can recoup the costs to
implement the new system-INCIS.
The report highlighted the lack of IT governance practiced
by the Government and IBM. The recommendations are given in this
report to the Police and Government regarding the development of future
IT projects and the handling of risks involved in such projects.
8/13/2019 Assignment IT Governance
http://slidepdf.com/reader/full/assignment-it-governance 4/14
3
Introduction to INCIS System
INCIS means Integrated National ComputerizedInformation System. It is the system used by the Police to create law andorder in their Jurisdiction. The main purpose of the INCIS is to reduce theoffice work and make more officers available for the field jobs. It helps in providing improved information, investigation and analysis capabilities. Itwould also help in minimizing the crimes and incidences by evaluating thekey reasons and will also suggest the time of action.
The main areas of INCIS are as follows:
Offenses or Suspects information
Case and investigation management
Crime trend analysisIntelligence analysis
Performance measurement
The main contractor of this system was IBM whowere to produce technical infrastructure and desktop computers.Originally the intended desktop was OS/2 but later was revised touse Windows New Technology. This system was primarily used to phaseout the Wanganui Intelligence System. But, because of being over budgeted and risky, the system was never practically used. The researcherssay that the need and requirement of the system wasn't clearly understood.
8/13/2019 Assignment IT Governance
http://slidepdf.com/reader/full/assignment-it-governance 5/14
4
Need for INCIS
The need of INCIS is to support operational Policing by providing improved information, investigation and analysis capabilities.Old system was not able to meet the needs and requirements of the staffand users of Police Department. Old system had lot of weak links. Withthe change of time, the requirements of the system and needs of workchanged a lot. All the paperwork needed to be turned into digital files tomake the data more organized and easily accessible. Old system had proved ineffective in the following ways:
System failure: Due to large amount of data access and transfer,sudden system failures and system jam took place from time to time whichlead to inefficiencies at work.
Slow response time: Processing speed of the system was too slow,especially at the peak times. System took lot of time in processing acertain request and sometimes, system froze for hours leading to wastageof time and delays in services and actions.
Administrative changes: In case of any administrative, there were no protocols to add new members and vary their access control accordingly.
Improve communication between regions: There was less or nocommunication between the Police force of the different areas. Due to this,even the small reports took days to get verified from outside the jurisdiction of that particular system. Hence, it was quite essential to buildthat intercommunication bridge between the different parts of the force.
Also, Wanganui Intelligence System was not able to meet the needs and
requirements of the staff and users of Police Department Because of some
reasons
Inefficiencies of work due to system failure and slow speed In case of any administrative, there were no protocols to add new
members and vary their access control accordingly. There was less or no communication between the Police force of
the different areas. Due to this, even the small reports took days toget verified from outside the jurisdiction of that particular system.Hence, it was quite essential to build that intercommunication bridge between the different parts of the force.
8/13/2019 Assignment IT Governance
http://slidepdf.com/reader/full/assignment-it-governance 6/14
5
Problems Encountered during Implementation
But due to lack of documentation, IT governance, schedule,
cost and Technology, the project was not implemented as required togovernment vision. At the time of initiation, INCIS was a high risk project.
Visits by managerial police staff to other law enforcement agencies
confirmed that the technology requirements for INCIS at that time had not
been designed or implemented as an integrated system of sufficient
standard to meet the needs of police.
Following were the problems encountered during the implementation
phase of INCIS:
Phase Out OS/2 and Move towards Window NT:
The construction of the INCIS project was well done and they were
having towards the completion of the system .In the year 90’s, IBM
was working on the INCIS system with the help of OS2 (Operating
system 2) and till this particular instance, on the one side, all the work
was going well and on the other side Window NT was holding a good
market share and it was also a very good operating system. As the
Window NT was a good/strong enterprise level operating system ,
IBM decided to phase out OS/2 and change all the work of INCIS to
Window NT and as a result cost went up. This transition gave a delay
in the project development.
Police Failed To Present Required Reports:
All the procedure of the system was facing irregularities because the
reports which were supposed to be produced by the police were not
actually happened. In this way neither the reporting requirements nor
the quarterly report was produced by the police in front of STA andMinister of police respectively. After this, when the Andersen report
came then some bitter truths came in spotlight which were internally
responsible for delay in project development .There were some
requirements of the system which were not actually available in the
8/13/2019 Assignment IT Governance
http://slidepdf.com/reader/full/assignment-it-governance 7/14
6
request for proposal i.e. traffic , firearms and statistics. The delays in
reports were also the reason for the delay of project implementation.
Conflicts within top management:
There are two organizations within the IBM i.e. SWAIG and ISSC
management issues, the work and responsibilities of these two
organizations were changed. In the way of alteration of the
responsibilities from SWAIG to ISSC there were so many problems
created like breach in the relationship within the organization and the
way of thinking .The main problem was the different types of decision
like objective and doubtful accountability which were creating trouble
between the Police project Director and IT Director. The conflicts
within the IBM were also the cause of delay in system development.
8/13/2019 Assignment IT Governance
http://slidepdf.com/reader/full/assignment-it-governance 8/14
7
Cost Related Issues
We will consider the problems associated with resource
utilization, accounting, monitoring and control during a project. Theintegrated national computerized information system was a law
enforcement information management system that includes the all aspects
of police investigation. But because of the cost blowouts and delays in
implementation, the project was not delivered on time. The main problem
with this system was under-estimation of the cost and complexity of the
project because it was divided in many phases that were delivered late not
on supposed dates.
Moreover, the project team was unable to deliver key IT
systems. The system was supposed to recoup $114 million in comingyears by reducing administration requirement and also generate to $45
million by selling this technology to other law enforcement agencies but
this was not actually happened. The project team had spent 3 million
dollars just to search packaged application for the INCIS because. The
worst thing in this project was to divide this project in three stages because
every stage increased the cost. The project involved up to $7 million cost
when project team decided to migrate INCIS to NT.
Then in 1998 $20.17 million was approved by the Cabinet
to meet the capital cost of INCIS which IBM charges for the changedfunctions but it increased because more people are involved that made
project more complexes and risky. This cost included more $8.67 million
only to maintain the project team due to the projected delays from IBM
because IT people are not clear to their vision to aligned IT with their
project. The project was behind schedule that involve more $8 million by
March 1997. These all issues raised because of the improper delivery
schedules, accountability and cost.
8/13/2019 Assignment IT Governance
http://slidepdf.com/reader/full/assignment-it-governance 9/14
8
Lack of IT Governance
Lot of delays and over budget this project was not
delivered at estimated time. This happened because of lack of ITgovernance in project as follows:
IT Governance initiatives are very often instigated by top management
of the organization, and they have the initial support of the senior
management. So this is important to sustain this support throughout
the project. But this was not happened in the case of INCIS project
because there was not clear IT governance vision of NZ government.
IBM had its own internal problems which needed to be resolved. The
transition process between the two companies SWAIG and ISSCresulted in many problems like intercommunication between the
different parts of the organization, skills and knowledge imbalanced
because of this. Delays in achieving deadlines was the problem which
was most significantly repeated in the above case study. This, not only
lead to wastage of time but wastage of resource as well.
They want invent something own but they were unable to relate thenew technology with this large project. They divided this project in 3
increments that made this project more complicated. Also many political leaders involved in it that created lot of conflicts among them.IT Governance practices requires a well-defined plan, it is important tostick to this measure against any resistance but INCIS project teamwas not stick to plan.
The project team did not monitor the size and complexity of their IT
infrastructure. This system was developed without remarkable
supervision. When they over budgeted, they don’t know how to handle
this situation by using less IT Resources.
8/13/2019 Assignment IT Governance
http://slidepdf.com/reader/full/assignment-it-governance 10/14
9
COBIT/ITIL as IT Governance Model
This is not the first time the Police have suffered delays
in delivering key IT systems. Companies need a strong governance modelin place to align IT investments with business requirements. There are two
governance models which can be implemented by Government to enhance
outcome from the department.
COBIT
The business process within IT has improved as a result of using
COBIT for ongoing IT governance related projects. COBIT is an
internationally accepted set of tools organized into a framework that
executives can use to ensure their goals and objectives. It ensures IT is
working as effectively as possible to minimize IT-related risks and
maximize the benefits of technology invest
How does the COBIT support the governance of IT
COBIT supports IT governance in by providing a framework that ensures
that:
IT is aligned with the business
IT enables the business and maximizes the benefits.
IT resources are used responsibly.
IT risks are managed appropriately.
Benefits of implementing COBIT
Improves IT efficiency and effectiveness
Maintain high-quality information to support business decisions.
Optimize the cost of IT services and technology
Helps executives understand and manage IT investments
throughout their life cycle
Support compliance with relevant laws, regulations, contractual
agreements and policies.
8/13/2019 Assignment IT Governance
http://slidepdf.com/reader/full/assignment-it-governance 11/14
10
ITIL
ITIL is the most widely accepted approach to IT service management
in the world. ITIL provides a cohesive set of best practice, drawn from the
public and private sectors internationally. The Information TechnologyInfrastructure Library (ITIL) is a set of practices for IT service
management (ITSM) that focuses on aligning IT services with the needs of
business. It provides a practical, no-nonsense framework for identifying,
planning, delivering and supporting IT services to the business.
Benefits of ITIL
ITIL advocates that IT services must be aligned to the needs of the business and underpin the core business processes. It provides guidance to
organizations on how to use IT as a tool to facilitate business change,
transformation and growth.
8/13/2019 Assignment IT Governance
http://slidepdf.com/reader/full/assignment-it-governance 12/14
11
The main steps the entire ITIL service lifecycle, beginning with the
identification of customer needs and derives of IT requirement, through
the design and implementation of the service into operation and finally, on
the monitoring and improvement phase of the service.
Adopting ITIL can offer users benefits that include:
improved IT services reduced costs improved productivity improved use of skills and experience Improved delivery of third party service. improved customer satisfaction through a more professional
approach to service delivery
8/13/2019 Assignment IT Governance
http://slidepdf.com/reader/full/assignment-it-governance 13/14
12
Recommendations for future IT Projects
INCIS Project have led the report to make the following
recommendations for future IT projects: Emphasize on using conventional technology.
Separating the infrastructure from technology.
Adopting a proper form of contract with the delivery of business
benefits in modules.
Projects should normally use proven technology. Where it is
necessary to use unproven technology, this should be reflected in
an increased risk management process.
There must be comprehensive quality and risk management
processes.
The appropriate form of contract should be signed only when the
Government agency is satisfied that it has addressed and resolved
all relevant issues including technology, resources and risks.
Any conflict or dispute that adversely affects the project must be
addressed promptly and in an effective way.
To maximize the prospects of success, a projects needs to have
tight and effective management.
The approval and monitoring structures need to be resourced to
enable them to effectively meet the expectations of Government
The approval of any future IT project by Government shouldcontain directions that ensure that the monitoring by the
monitoring agencies is as effective as practicable.
8/13/2019 Assignment IT Governance
http://slidepdf.com/reader/full/assignment-it-governance 14/14
13
Referencing
Ministerial inquiry to INCIS
http://www.justice.govt.nz/publications/global-publications/m/ministerial-
inquiry-into-incis
ISACA
https://www.isaca.org/Pages/default.aspx
Wikipedia
http://en.wikipedia.org/wiki/Minimum-cost_flow_problem
http://www.cosc.canterbury.ac.nz/research/RG/svg/tony/papers/incis.html
http://cio.co.nz/cio.nsf/spot/police-rescue
http://computerworld.co.nz/news.nsf/news/computerworld-25-years-ibm-
incis-and-the-internet