10
Asset Management Risk Planning and Project Prioritization Bringing PacifiCorp to the Next Level in Asset Management Presented at the EEI TD&M Conference in Charlotte, NC April 20, 2004

Asset Management Risk Planning and Project Prioritization

Embed Size (px)

DESCRIPTION

Asset Management Risk Planning and Project Prioritization. Bringing PacifiCorp to the Next Level in Asset Management. Presented at the EEI TD&M Conference in Charlotte, NC April 20, 2004. PacifiCorp is the USA-based subsidiary of Scottish Power - PowerPoint PPT Presentation

Citation preview

Page 1: Asset Management Risk Planning         and Project Prioritization

Asset Management Risk Planning and Project PrioritizationBringing PacifiCorp to the Next Level in Asset Management

Presented at the EEI TD&M

Conference in Charlotte, NC April 20, 2004

Page 2: Asset Management Risk Planning         and Project Prioritization

2

PacifiCorp is the USA-based subsidiary of Scottish PowerAnd is one of the West’s largest and lowest-cost electric utilities

A little history and some basic statistics1881 – Salt Lake City is 5th city in US with central

station electricity1910 - Pacific Power & Light in OR & WA1912 - Utah Power & Light in UT & ID 1989 - PacifiCorp merger1999 - Scottish Power merger  Headquarters: Portland, OR Employees: 6,400Territory: More than 135,000 square miles Line-miles: Transmission: 15,000

Overhead distribution: 44,000 Underground distribution: 12,000

Generation capacity: 8,300 megawatts Customers: Total 1,544,895

Utah 689,709 Oregon 510,254 Wyoming 122,493 Washington 120,094 Idaho 59,407 California 42,895

  

Page 3: Asset Management Risk Planning         and Project Prioritization

3

T&D is a significant part of PacifiCorp’s CAPEX With a projection for declining T&D CAPEX in the next few years

PacifiCorp CAPEX Actual & Estimated

0

100

200

300

400

500

600

700

800

2003 2004 2005 2006

FY Ending March 31

$M

illio

ns

Other

Generation & Mining

Transmission & Distribution

Judi JohansenPresident & CEO

Matthew WrightEVP Power Delivery

Darrell GerrardVP T&D Engineering & Asset Management

Alec Burden (ret.)MD Asset Management

Tom WatersDir. Asset Planning

Tom EyfordRisk Manager

Page 4: Asset Management Risk Planning         and Project Prioritization

4

Option Development Developing cost-effective alternatives for possible funding

- Additions- Upgrades- Replacement- Maintenance- Standards- Systems

Results Monitoring

Measuring & managing the drivers of the funded projects and processes

- Benchmarking- Unit costs- Failure rates- Event impacts- Value added

Recall the context within which prioritization is donePrioritization is only a part of asset management and risk planning

10-Year Present Value Project Cost and Value Funding Curve

$

$500

$1000

$1500

$2000

$2500

$ $200 $400 $600 $800 $1000 $1200 $1400

Cumulative PV of Project Cost ($ Millions)

Cum

ulat

ive

PV o

f Pro

ject

Val

ue ($

Mill

ions

) Funding Curve

2005 Project Cost and Value Funding Curve (Capital)

-$200

$

$200

$400

$600

$800

$1000

$1200

$ $50 $100 $150 $200 $250 $300 $350 $400

2005 Project Cost ($ Millions)

2005

Pro

ject

Val

ue ($

Mill

ions

)

Page 5: Asset Management Risk Planning         and Project Prioritization

5

2005 Project Cost and Value Funding Curve (Capital)

-$200

$

$200

$400

$600

$800

$1000

$1200

$ $50 $100 $150 $200 $250 $300 $350 $400

2005 Project Cost ($ Millions)

2005

Pro

ject

Val

ue

($ M

illio

ns)

‘Must Do’ is limited at about half the budget These categories need to be forecast well, and then fully funded

Po

ssib

le F

ina

nci

al T

arg

et

Pro

ject

s w

ith V

alu

e/C

ost

> 1

.0

Illustrative

Page 6: Asset Management Risk Planning         and Project Prioritization

6

Today’s utility has to have a different story to tell investorsThe shift is from global energy traders to regional asset owner/managers

Load relief is a major part of the capital budgetRecommended funding reduces risk to acceptable levels

Load Relief Funding Curve and Risk Measure

0

50

100

150

200

250

300

350

400

450

0 10 20 30 40 50 60 70

Load Relief Spending ($Millions)

Val

ue

($M

il), R

isk

(Exp

MV

AH

rs) ExpMVAHrs at Risk

Cumulative Value Added

Load Relief Cost and Value Drivers

0

50

100

150

200

250

300

350

400

450

0 10 20 30 40 50 60 70

Load Relief Spending ($Millions)

MV

A

Capacity Added (MVA)

Load Relief: (n-1) MVA at Risk 2006

Load Relief: (n-0) MVA at Risk 2009

Load Relief: (n-0) MVA at Risk 2006

Load Relief Sensitivity Analysis

0 2 4 6 8 10 12 14 16 18

Percent Field Tie

Mobile Time/Restorationtime

XFMR Failure Rate

Total Cost

Load Growth Rate

Peak Load

Ratio

0

10

20

30

40

50

60

70

80

90

100

2005 2006 2007 2008 2009

0

50

100

150

200

250

300

350

400

450

Original SpendingSpending @ 1.0Capacity AddedRisk Avoided @ 1.0

Page 7: Asset Management Risk Planning         and Project Prioritization

7

Today’s utility has to have a different story to tell investorsThe shift is from global energy traders to regional asset owner/managers

Feeder reliability has a direct impact on SAIDI-SAIFIRecommended funding reduces risk to acceptable levels

Feeder Reliability Cost Effectiveness

$- $200 $400 $600 $800 $1,000

$1,200

$1,400

$1,600

$1,800

Wasatch Front Distribution AutomationWorst Circuit Program Tier 1Worst Circuit Program Tier 2Worst Circuit Program Tier 3Worst Circuit Program Tier 4Worst Circuit Program Tier 5

Tree Trimming (UT/ID/WA/WY)Tree Trimming Oregon and California

Storm HardeningOH Three ph Structure PM Replacement

OH Single-phase Structure PM ReplacementLine inspection and repair- Backbone

Line inspection and repair- LateralsUG Sw itches(G&W) in Vaults PM

URD Tier 1 PM ReplacementURD Tier 2 PM Replacement

Feeder Overload Tier 1Feeder Overload Tier 2Feeder Overload Tier 3

Feeder Undervoltage Tier 1Feeder Undervoltage Tier 2

Pole Replacement

$ Per Customer Interruption Avoided

Vegetation Management

0.8 0.9 1 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8

Mitigation Deterioration Rate

Restoration colst

Cycle

CI per outage

Value of Avoided Interruption

Mitigation Effectiveness

Cost Per mile

Total Cost

Ratio

Feeder Funding Curve & Risk Measure

0

50

100

150

200

250

300

350

400

0 10 20 30 40 50 60 70 80

Feeder Reliability Spending 2005

Val

ue

($M

il),

Avo

ided

CIs

(ks

)

Impact of Spending on SAIFI

1.0

1.2

1.4

1.6

1.8

2.0

2.2

2005 2006 2007 2008 2009

SA

IFI

Cutoff = 2.0

Cutoff = 1.5

Cutoff = 1.0

0 200 400 600 800 1000 1200 1400 1600

$ Per Customer Interruption Avoided

Page 8: Asset Management Risk Planning         and Project Prioritization

8

The capital prioritization process has become a board-level issueBoards want to see what is driving the business’ needs for cash

Substation reliability addresses selected assetsWith programs to replace the most trouble-prone assets

CB Replacement Sensitivity Analysis

1.5 1.55 1.6 1.65 1.7 1.75 1.8 1.85 1.9 1.95 2

Total Cost

Addition to Tgt Population

CI per CB outage

Collateral Damage

PM Unit Cost

% CB causing XFMR Outage

Avg Duration

Avg XFMR MVA

Failure Rate

New Breaker Cost

Ratio

Substation Reliability Funding Curve & Risk Measure

0

20

40

60

80

100

120

140

0 5 10 15 20

Substation Reliability Spending 2005 ($Mil)

Va

lue

($

Mil)

, Ex

pM

VA

Hrs

Weibull Curve - MV Circuit Breakers

0.0%

0.1%

0.2%

0.3%

0.4%

0.5%

0.6%

0.7%

0.8%

0.9%

0% 20% 40% 60% 80% 100%

Annual Percent Maintained

An

nu

al F

ailu

re R

ate

Inventory of Failure-Prone Devices

-

50

100

150

200

250

300

350

400

2005 2006 2007 2008 2009

# o

f D

evic

es

MV CBs

Battery Banks

Regulators

HV CBs

LTCs

Page 9: Asset Management Risk Planning         and Project Prioritization

9

Each project is modeled from cost to impacts to valueThe process has brought some key insights Which will allow PacifiCorp to save money and reduce risk

• Optimal timing of load relief projects

- Model shows that some should be deferred, some accelerated

- Emphasizes the need for exploration of cost-effective alternatives

• Identifies critical data based on sensitivity analysis

- Failure rates, condition of certain assets, load growth rates, unit costs

• Quantifies how reliability value can drive allocation

- $25,000/MWH, $25/CI are good baselines for further refinement

• Causal relationships built in

- Weibull curves and condition-state models address key questions on PM

• Good feedback for planners

- Gives an early indication of project value versus cost

• Improved cost-effectiveness

- ‘Sharper pencil’ on URD, worst circuits, etc. from analysis of failure rates

Page 10: Asset Management Risk Planning         and Project Prioritization

10

Next StepsWhile initial estimates are satisfactory, more can be learned

• 10-year plan

• 2006 Plan and Budget

• Transmission grid

• Model and data refinements (continuous)