ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS IN PUBLIC SECTOR: A CASE OF TEMEKE MUNICIPAL COUNCIL - DSM

ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT

PROCESS IN PUBLIC SECTOR:

A CASE OF TEMEKE MUNICIPAL COUNCIL - DSM

Page 2: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT

PROCESS IN PUBLIC SECTOR:

A CASE OF TEMEKE MUNICIPAL COUNCIL - DSM

By

Lynne Nuru Mshamu

A Proposal Submitted to Mzumbe University, Dar es Salaam Campus College in

Partial Fulfillment of the Requirements for the Award of the Degree of Master

of Science in Procurement and Supply Chain Management (MSc-PSCM)

of Mzumbe University.

2013

Page 3: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

i

CERTIFICATION

I undersigned certifies that I have read this research and hereby recommends for

acceptance by the Procurement and Supplies Professional and technical Board this

research paper titled “ Assessment of Effectiveness of Procurement Process in Public

Sector”: A Case of Temeke Municipal Council” in partial fulfillment of the

requirements for the Award of Certified Procurement and Supplies Professional and

Technical Board.

……………………………………

Major Supervisor

Date………………………………..

………………………………………

Internal Examiner

………………………………………

External Examiner

Accepted for the Board of ………………………………

.......................................................................................................

DEAN/DIRECTOR, FACULTY/DIRECTORATE/SCHOOL/BOARD

Page 4: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

ii

DECLARATION AND COPYRIGHT

I, Lynne N. Mshamu, declare that this research paper is my own original work and

has not been presented anywhere or will not be presented to any other institution for

any award.

Signature …………………………………

Date ………………………………………

©

Copy Right

This paper should not be produced by private study, critical scholarly review or

disclose with acknowledgement, without written permission of Executive Director,

Procurement and Supplies Professionals and Technicians Boards on behalf of both

the authors and the any means, in full or in part, except for short extract in fair

dealings, for research or Board.

Page 5: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

iii

ACKNOWLEDGEMENT

I wish to take this opportunity to thank the Lord for having brought me this far.

May honor and praise be unto Him.

My sincere gratitude goes to my supervisor Professor Shumbusho for his invaluable

guidance and assistance. His patience, availability and immense knowledge have

made a great impact in my career path. Thank you for your time and interest in this

work.

I’m greatly indebted to my beloved brother Boniface for his moral support and

understanding and the family at large for the support they gave me.

A lot of thanks go to all my friends for being an encouragement throughout my

academic life. I would especially wish to thank Nyakato, Legga, Fredric, Ally,

Maggie, Davie and all my colleagues in Msc. Procurement and Supply Chain

Management at Mzumbe University for the support they gave me.

I further wish to extend my gratitude to my immediate Supervisors Dr. Marzouk and

Jacintha and other staff members at Kigamboni hospital for their understanding,

encouragement and giving me time to pursue my studies.

To you all, thank you and God bless you abundantly.

Page 6: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

iv

DEDICATION

To my beloved brother Boniface for whom without his love, understanding, support

and encouragement I would not have gone this far. To the entire family and friends

for their prayers and continued support.

.

Page 7: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

v

LIST OF ABREVIATIONS

CTC Competitive Tendering and Contracting

et al and others

JIT Just in Time

NHS National Health Services

PPA Public Procurement Act

PPRA Public Procurement Regulatory Authority

UK United Kingdom

URT United Republic of Tanzania

PMU Procurement Management Unit

Page 8: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

vi

ABSTRACT

Effectiveness of procurement process is the key issue in the procurement

performance which is fundamental to guarantee cost-effective delivery of goods and

services in any organization(Public or Private). Regardless of its importance;

assessing procurement process effectiveness seems to be a challenge task especially

in government entities since it relates with the personnel target performance. This

study provides thoroughly assessment of effectiveness of procurement process in a

public sector considering Temeke Municipal Council as a Case of the study.

The study adopted a qualitative case-study design. A purposive sampling technique

which is a non-probability or judgmental sampling procedure was used to determine

sample unit of 20 respondents. Data were collected by the use survey and interview

method through structured questionnaire. Data analysis was done manually and

results presented in a form of percentages and tabulations form.

The findings revealed that; the procurement process was effective at Temeke

Municipal council with the tendering being the best method comparing to quotation.

But there was lack of proper knowledge and skills, accountability and corruption

which affected the procurement process to the greater extent.

The report concludes that: given the impact of procurement activities on the

operation and effectiveness of public sector, it is essential that these activities be

performed by qualified staff with high professional and ethical standards and using

sound procedures anchored in appropriate policies and regulations.

Moreover the study recommended that; specialized training programs should be

employed to procurement personnel with the skills to achieve procurement

objectives. Key issues such as employment of qualified procurement practitioners,

training and employment of leadership programs, development of an effective

monitoring and evaluation tool, and the creation of incentive programs to motivate

good performance should be employed.

Page 9: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

vii

TABLE OF CONTENTSCERTIFICATION ........................................................................................................ iDECLARATION AND COPYRIGHT........................................................................ iiACKNOWLEDGEMENT .......................................................................................... iiiDEDICATION ............................................................................................................ ivLIST OF ABREVIATIONS......................................................................................... vABSTRACT................................................................................................................ viTABLE OF CONTENTS...........................................................................................viiLIST OF TABLES ....................................................................................................... xLIST OF FIGURE........................................................................................................ x

CHAPTER ONE ........................................................................................................ 1INTRODUCTION...................................................................................................... 11.1Overview................................................................................................................. 11.2Background Information of the Study..................................................................... 11.3 Research Problem................................................................................................... 81.4Research Objectives ................................................................................................ 81.4.1General Objective................................................................................................. 81.4.2Specific Objectives............................................................................................... 81.5Research Question................................................................................................... 91.5.1General Question.................................................................................................. 91.5.2Specific Questions................................................................................................ 91.6Scope of the Study .................................................................................................. 91.7 Limitations ........................................................................................................... 101.8Significance of the Study ...................................................................................... 101.9Organization of the Study ..................................................................................... 10

CHAPTER TWO ..................................................................................................... 12LITERATURE REVIEW........................................................................................ 122.1Overview............................................................................................................... 122.2Theoretical Part ..................................................................................................... 122.2.1Definition of Key Concepts ............................................................................... 122.2.2Legal Public Procurement Procedures ............................................................... 132.2.3Public Procurement Approach ........................................................................... 162.2.4Procurement Governance ................................................................................... 232.3.1General Empirical .............................................................................................. 272.3.2The Case of Abroad ........................................................................................... 292.3.3The Case of Tanzania......................................................................................... 302.4Variable and Conceptual Framework.................................................................... 322.5Measurement of Variables .................................................................................... 33

Page 10: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

viii

CHAPTER THREE ................................................................................................. 34RESEARCH METHODOLOGY ........................................................................... 343.1Overview............................................................................................................... 343.2 Research Strategy................................................................................................. 343.3 Description of the Case Studied........................................................................... 353.4 Location of the Study........................................................................................... 363.5Nature of the Data Required ................................................................................. 363.6 Measurement of Variables from Conceptual Framework .................................... 373.7 Quality of Data Measurement .............................................................................. 373.8Data Collection Methods and Instruments............................................................ 383.9Sampling Procedures............................................................................................. 403.10 Field Work ......................................................................................................... 413.11Data Processing and Analysis ............................................................................. 41

CHAPTER FOUR.................................................................................................... 43FINDINGS AND ANALYSIS ................................................................................. 434.0 INTRODUCTION ............................................................................................... 434.1 Effectiveness of Procurement Process ................................................................. 434.1.1 Participation in procurement process ................................................................ 434.1.2 Difficulties in Procurement Process.................................................................. 434.1.3 Effectiveness of Procurement Process .............................................................. 444.1.4 Cost Efficiency.................................................................................................. 444.1.5 Lead Time Performance.................................................................................... 454.2.1 Procurement methods Used............................................................................... 464.2.2 Processing Speed............................................................................................... 464.2.3 Effectiveness of processing criteria .................................................................. 474.2.4 Effectiveness of Tendering Method .................................................................. 474.2.5 Effectiveness of Quotation method................................................................... 484.3 Personnel Performance ........................................................................................ 494.3.1 Performance of Procurement Personnel............................................................ 494.3.2 Information Coordination Performance ............................................................ 494.3.3 Decision making in the Procurement Process ................................................... 504.4 Problem Facing the Procurement Management ................................................... 504.4.1 Bureaucracy....................................................................................................... 504.4.2 Lack of proper knowledge, skills and capacity................................................. 504.4.3 Lack of Capacity Building in Public Procurement Act and Regulation ........... 514.4.4 Poor Specifications............................................................................................ 514.4.5 Delay in Payments............................................................................................. 514.4.6 Taking Too Long to Take Decision .................................................................. 524:4:7 Non-compliance with policies and regulations................................................. 524.4.8 Improper planning and linking demand to the budget ...................................... 52

Page 11: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

ix

4.4.9 Inadequate measures for monitoring and evaluation ........................................ 52

CHAPTER FIVE...................................................................................................... 54DISCUSSIONS ......................................................................................................... 545.1 Introduction .......................................................................................................... 545.2 Effectiveness of Procurement Process ................................................................. 545.3 Best Procurement Method and its Effectiveness.................................................. 555.4 Procurement Process Problems ............................................................................ 57

CHAPTER SIX ........................................................................................................ 58SUMMARY, CONCLUSION AND RECOMMENDATIONS............................ 586.1 Introduction .......................................................................................................... 586.2 Summary .............................................................................................................. 586.3 Conclusion ........................................................................................................... 596.4 Recommendations ................................................................................................ 616.5 Recommendations for Further Studies................................................................. 63REFERENCES ......................................................................................................... 64APPENDEX .............................................................................................................. 68

Page 12: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

x

LIST OF TABLES

Table4.1 Participation in Procurement Process ......................................................... 43

Table4.2 Difficulties in Procurement Process............................................................ 44

Table 4.3 Procurement Process Effectiveness ........................................................... 44

Table 4.4 Cost Efficiency........................................................................................... 45

Table 4.5 Lead Time Performance............................................................................. 45

Table 4.6 Best Procurement method .......................................................................... 46

Table4.7 Processing Speed......................................................................................... 47

Table 4.8 Processing Criteria Effectiveness .............................................................. 47

Table 4.9 Effectiveness of Tendering Method........................................................... 48

Table 4.10 Effectiveness of Quotation Method ......................................................... 48

Table 4.11 Performance of Procurement Personnel................................................... 49

Table4.12 Information Coordination Process………………………………………43

Table 4. 13 Decision making Performance ................................................................ 50

Page 13: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

1

CHAPTER ONE

INTRODUCTION

1.1 OverviewThis chapter presents an overview of the study. It outlines key issues while

introducing the kind of the problem that a study is going to undertake. It provides

clarifications on the background of the study, statement of the problem, objectives

and research questions, as well as significance of the study.

1.2 Background Information of the StudyProcurementencompasses the whole process of acquiring property and/or services. It

begins when an agency has identified a need and decided on its procurement

requirement. Procurement continues through the processes of risk assessment,

seeking and evaluating alternative solutions, contract award, delivery of and payment

for the property and/or services and, where relevant, the ongoing management of a

contract and consideration of options related to the contract. Procurement also

extends to the ultimate disposal of property at the end of its useful life (Waters

2004).

Procurement has direct and indirect costs that clearly affect the organization

effectiveness. The organizational structure, division of work and operation

efficiency; are components that modify the effectiveness of procurement function.

The procurement processes and procedures have a close relation to other functions

on the organization and on their efficiency as well. As an example, improvements in

quality issues and on the delivery times reflect to the total costs on the logistics and

production side. Reducing the total costs can be perceived as reduced quality of

products. Cost efficient procurement doesn’t imply that the quality of products would

decrease. (Iloranta 2008, 105.)

According to Thai (2001), the basic principles of good procurement practice include

accountability, where effective mechanisms must be in place in order to enable

procuring entities spend the limited resources carefully, knowing clearly that they are

accountable to members of the public; competitive supply, which requires the

Page 14: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

2

procurement be carried out by competition unless there are convincing reasons for

single sourcing; and consistency, which emphasizes the equal treatment of all bidders

irrespective of race, nationality or political affiliation.

The process should also uphold integrity by ensuring that there are no malpractices;

informed decision-making, which requires public bodies to base decisions on

accurate information and ensure that requirements are being met. More still, the

Procurement practice should be responsive to aspirations, expectations and needs of

the target society. Finally, there is need for transparency to enhance openness and

clarity on procurement policy and its delivery (World Bank, 2003).

Procurement is a noble activity in the organization. Its central role is to make the

activities of the firm successful. Without successful procurement activities the

organization cannot achieve its full potential goals.

In order to ensure that, the procurement activities are performed successfully,

sufficiently and effectively, the procurement and supplies personnel should observe

all proper procedures required to be followed.

Professional ethics refer to moral principles that govern a professional’s behavior

when performing a given duty.

Professionals have specialist knowledge and skills and always strive to acquire more.

The specialist knowledge and skills give them authority, power and additional moral

responsibility over the ones held by the general public. Professionals are also

entrusted with resources such as inventories, finance and staff. These give them

additional powers and authority. They make decision on how to utilize resources on

behalf of their organizations. In this case they must be trustful.

Professionals, therefore, must be governed on how they apply the specialist

knowledge and skills when performing their duties. Moreover they must be governed

by on how they utilize resources made available to them for the benefits of their

organizations.

Professionals play a very critical role in preserving the integrity of their

organizations. Procuring entities through their professionals must ensure fair

treatment to bidders, suppliers, contractors and stakeholders in general. Failure to

Page 15: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

3

treat them fairly will compel them to lose confidence in the respective organizations.

Unfair treatment could as well lead to civil or criminal offences against the

professionals and or their organizations. The consequences of civil and criminal

offences could be grave.

Procurement Ethics prohibits professional from having financial interest when

performing their duties relating to suppliers of goods and services. Apart from

financial interest, professionals must avoid any acts which may cause their

impartiality be questioned. This may include dealing with procurement activities

involving their former employers, friends, relatives and potential employers.

Professionals must refrain from accepting and soliciting gifts from suppliers or their

employees. The supplier here includes the current and potential ones. It should be

noted that gifts affects professionals’ impartiality. However, gifts of promotional

items such as pens, calendars and diaries may be accepted.

Professionals must bear in mind that if they are required to refrain from accepting

and soliciting gifts, then they must repel bribes and corruption.

In their daily activities, professional obtain data and information from various

sources including their organizations. Some of the data and information are

classified. Disclosure of information without proper authority is unethical.

Professionals must therefore ensure that they perform their duties free from

impropriety. This is possible. Given by Ahmed S. K. Kilima - PSPTB Journal pg 1

issue No. 2 Jan-June 2010

Public Procurement

Public procurement is the process whereby public sector organisations acquire goods,

services and works from third parties. It includes much that supports the work of

government and ranges from routine items (e.g. stationery, temporary office staff,

furniture or printed forms), to complex spend areas (e.g. construction, Private

Finance Initiative projects, aircraft carriers or support to major change initiatives).

Page 16: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

4

It also includes a growing spend where the private and third sectors provide key

services directly to citizens in areas such as welfare-to-work, further education,

social care and health. Such services may also be provided by the public sector

directly, and in some cases even this public provision can be handled through

procurement mechanisms. A public body may bid for government work against

private sector firms through a formal competitive process.

Public procurement is the buying of goods and services on behalf of a public

authority, such as a government agency. Governments spend public monies to secure

inputs and resources to achieve their objectives and by doing so, create significant

impact on key stakeholders and wider society. In addition, government purchasing

impacts both domestic and international trade given that governments spend

approximately 10 to 15 percent of their GDP in the procurement marketplace. Hence,

public procurement plays a significant role in the global economy.

In public procurement the goals of fairness, competition and economic value are

paramount. To achieve these goals, effective and efficient procurement processes

must be established. This includes incorporating adequate controls to promote

competition and minimize the risk of fraud, corruption, waste, and the

mismanagement of public funds. In this context, transparency is considered to be one

of the most effective tools to deter corruption and ensure value for money.

Transparency in procurement takes form in a variety of practices, such as: publishing

procurement policies; advance publication of procurement plans; advertisement of

tender notices; disclosure of evaluation criteria in solicitation documents; publication

of contract awards and prices paid; establishing appropriate and timely complaint/

protest/dispute mechanisms; implementing financial and conflict of interest

disclosure requirements for public procurement officials; and publishing supplier

sanction lists.

Page 17: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

5

Public Procurement Law

Procurement law was drawn to make the public procurement more effective and cost

efficient. It also improves the process of purchasing quality products and increases

fair competition between different companies and organizations in the market.

The main principles in public procurement include organizing the procurement

operations in such a way that they produce the most cost efficient and well-planned

results and taking into ac-count the environmental issues. The procurement process

has to be implemented on a fair basis openly without discriminating any of the

participants. Framework agreements and joint procurement can be used as a tool for

reducing administrative work. (Act on Public Contracts 2007/348.)

The different variations of public contracts such as public works contracts, public

supply contracts and public service contracts are defined in detail in the procurement

law. Also other definitions such as “supplier” and “tenderer” are specified to avoid

the possible misunderstandings. Restricted and negotiated procedures are examples

of procurement procedures that need to be taken into account when organizing public

procurement. Technical standards and specifications have been set up to define the

technical requirements that need to be met. (Act on Public Contracts 2007/348.)

Contracting authorities including state and municipal authorities, the Evangelic

Lutheran Church, state enterprises and bodies that are governed by public law are

determined in the procurement law. (Act on Public Contracts 2007/348.)

Measuring procurement effectiveness has always been an interesting topic for

organisations and corporations. The pressure of reporting the effects of the

procurement function to the management is high and in many cases related to the

personal performance targets of procurement staff. It is not that easy to determine

the numerical estimation of cost savings produced. That’s why it is crucial to take

into account all the other factors that might influence the effectiveness of

procurement. These factors may include issues such as a new service model, better

payment terms or a de-creased number of suppliers.

Page 18: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

6

The Temeke Municipal Council, like other public institutions has been operating

following the rules and regulations establishment by the government. In the case of

procurement activities the Council has to comply with the Public Procurement Act of

2004. Before the Public Procurement Act 2004, there was no tender body at the

Municipal Council. However, after the Act, tender body was established.

However, some of the regulatory requirements have been met: there are issues that

indicate inadequacy performance of the Municipal council in the procurement

processes. It has been observed that the municipal council over several years has

been faced with the following challenges: poor procurement records where it has

been sometime difficult in retrieving procurement information and some files and

important documents, and in most cases, tenders are floated for shorter period than

what is allowed in the Regulations.

Moreover, the results of tender awards are not published in the PPRA’s website or

advertised in the newspapers. There are some cases in which notification of contract

awards are beyond the tender validity period. There are also delays in project

completion and project reports are not prepared.

It has been also noted that the Municipal procured goods mostly through quotations

on the basis of allowable threshold as stipulated in the Public Procurement

Regulations of 2005. However, the procedures for procurement under the quotations

methods are not properly followed. Furthermore, a number of small quotations could

have been combined for competitive tendering.

Generally the performance of the Municipal in complying with PPRA 2004 and its

Regulations according to the procurement performance indicators has been assessed

to be low. Therefore all these issues have been happening in the existence of Public

Procurement Act 2004, apart from several recommendations from the CAG; the

situation has continued to remain almost the same. Therefore, the problem is

probably on the actual procurement process effectiveness, which is the purpose of

conducting this study.

Historically, procurement capacity development efforts have focused on improving

procurement techniques (the means of achieving the acquisition of goods and

Page 19: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

7

services), with less emphasis on integrating this work into broader development or

reform activities in the public sector.

Initiatives and policies such as market testing, contracting out, private finance

initiative, competing for quality, National Health Service (NHS) internal market,

facilities management and partnering all affect how equipment, goods and services

are procured within government and the public sector. They help to shape that

approach to the market, the preparation of the specification and evaluation of the

most economically advantageous tender followed by pertinent relationships in order

to meet the requirement (Baily et al, 2008).

The government of Tanzania applied a competitive tendering for public procurement.

Competitive tendering and contracting (CTC) has embraced alternative mends of

procuring public sector facilities to the traditional reliance upon an in-house team

delivery approach. This is believed to provide greater in both procuring facilities and

managing them. CTC is a “process of selecting a preferred supplier from a range of

potential contractors by seeking offers (tenders) and evaluating these on the basis of

one or more selection criteria”

Effectiveness is a key of the procurement practice in the organizations and

corporations. Measuring procurement effectiveness has always been an interesting

topic fororganizations and corporations. The pressure of reporting of the effects of

the procurement function to the management is high and in many cases related to the

personal performance targets of procurement staff.

In order to increase efficiency and effectiveness of procurement, the government has

taken several efforts. These are enactment of procurement act, 2004 and

procurement regulations. Moreover the government established the Regulatory

authority entitled for supervision and monitoring public procurement activities in the

public sector. But, apart from all these efforts; there are evidences or misprocurement

practices. It is due to this, the study has aimed at evaluating the effectiveness of

procurement practices in the country.

Page 20: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

8

1.3 Research Problem

The performance of procurement process in the public sector depends on the players

in the field. Public officials use enacted laws and regulations for achieving

organization’s goals. It has been noted that some of the public goals are not met

because of inadequate implantation of procurement process. The public procurement

requires effective implementation of imposed procedures in order to get qualified

suppliers and eventually quality products and services. However the current

situation has some deficiencies.

Though there are outlined laws, regulations, rule and procedures for public

procurement; there are some problems such as inability for suppliers to take

advantage of other investment opportunities since they wait for a long time for the

approval and award of tender, suppliers failing to meet the criteria needed, and

biasness of the people in the tender board which leads to selection of unqualified and

inexperienced bidders which results in poor performance in procurement activities of

the Municipal. Therefore, it is from the above factors the researcher needs to

evaluate the effectiveness of procurement process in the public sector basing at the

Temeke Municipal Council in Dar es Salaam.

1.4 Research Objectives

1.4.1 General Objective

The overall objective of this study was to examine the procurement process

effectiveness in the public sector, a case of Temeke Municipal Council.

1.4.2 Specific Objectives(i) To examine the effectiveness of procurement process as applied at Temeke

Municipal Council.

(ii) To find out the best method of procurement process at Temeke Municipal

Council.

Page 21: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

9

(iii) To identify the problems facing the procurement process and procurement

department at Temeke Municipal council.

1.5 Research Question

1.5.1 General QuestionThe general question of the study was; Is the procurement process effectively

conducted in the public sectors?

1.5.2 Specific Questions(i) To what extent is procurements process effective at Temeke municipal

council?

(ii) Which is the best method of procurement process at Temeke municipal

council?

(iii) What are the problem facing the procurement process and procurement

department at Temeke municipal council?

1.6 Scope of the Study

The study only covered the effectiveness of procurement process in the public sector

basing at Temeke Municipal Council in Dar es Salaam. The researcher primarily

examined the effectiveness of procurement process in the public sector basing at the

Temeke Municipal Council in Dar es Salaam.

The outcomes of the study was limited only on the data gathered from the books and

journal and from the primary data gathered from the results of questionnaire survey

and interview conducted by the researcher.

Since the research had to be completed in a relatively short period of time, other

factors and variables were not considered. This might have brought an impact on the

results of the study.

Page 22: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

10

1.7 LimitationsAmong the limitations are;

(i) Financial

Since the employer did not have any financial support to the researcher, financial

constrain had been one of the limiting factor in conducting this study.

(ii) Time

Due to limited timeframe to handle over the report, it was difficult then to compile

data from user departments.

(ii) Data Accessibility

Sometimes it is very dangerous those interviewee/respondents are not willing to

disclose their information.

1.8 Significance of the StudyGenerally the importance of any study is either for acquisition or addition of new

knowledge or sometimes can be a problem solving. This study therefore has the

following importance.

Firstly: To the researcher as it is the partial fulfillment for the award of Masters

Degree in Procurement and Supply Chain Management.

Secondly: This study is important to the University as it may be a point of reference

to others Students who will conduct the research on a related topic.

Thirdly: The recommendations and conclusions drawn from this research may be

useful to the Temeke Municipal Council if the conclusions and recommendations

drawn could be taken into considerations.

1.9 Organization of the StudyThe study consists of six chapters. The first one consist of overview of the study

which was concerned with the presentation of the background of the study, statement

of the problem, research objectives, research questions, and significance of the study.

Chapter two presents literature review that is theoretical and empirical literature

Page 23: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

11

review. Chapter three presents methodology of the study which is concerned with

presentations of type of the study, area and population of the study, unity of analysis,

sample and sampling techniques, types and sources of data, data collection tools and

data analysis. Chapter four discovered facts, findings and analysis which is

concerned presentation of facts found during the study as per study objectives.

Chapter five presents discussions based on the findings presented in chapter four.

Chapter six presents summary, conclusions, recommendations and areas for further

studies whereby it summarises the whole work, answer the research questions and

provides recommendations and suggestions for areas for further studies.

Page 24: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

12

CHAPTER TWO

LITERATURE REVIEW

2.1 OverviewThe literature review deals with the theoretical basis of the study, empirical studies,

conceptual definitions and conceptual framework. It concentrates more on what

same different authors have said about effectiveness of procurement practise in

public sector.

This is a theoretical pan, which focuses on how authors explain on various issues,

terms and key element on effectiveness of procurement in public sector.

2.2 Theoretical Part

2.2.1 Definition of Key ConceptsBailey et al, (2008) define procurement as that function dealing with buying

materials of the right quality, at the right price, time and the right source of supply.

Bally (1999) argues that, the Procurement process is composed of several elements,

namely: deciding what to purchase, deciding who to purchase from, negotiating an

exchange rate and exchanging resources for goods or services.

Morris (2003) define procurement as the complete action or process of acquiring or

obtaining personnel material, services or property from outside a military service by

means authorized in pertinent directives. This is procurement is more specifically the

action or process of acquiring or obtaining materials, property or services at the

operational level.

Public procurement Act (PPA No. 21 of 2004) section 3 “procurement” means

buying, purchasing, renting, leasing or otherwise acquiring any goods, works or

services by a procuring entity spending public funds on behalf of a ministry,

department or regional administration of the Government or public body and

includes all functions that pertain to the obtaining of any goods, works or services,

Page 25: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

13

including description of requirements, selection and invitation of tenderers,

preparation and award of contracts.

Pienaar (2005) argued that; “Every business enterprise purchases its materials,

services and assets such as Machinery and equipment, Motor vehicles, Furniture and

Fittings from other Firms. These materials, services and assets are used in the

production, marketing, logistics and other operations of the enterprises”. The process

of purchasing these items is known as procurement.

According to Farmer and Weele (1995), “Procurement is a broader term, which

includes all activities required in order to obtain the product from the supplier and

get it to the place where it actually used. It encompasses the purchasing function,

stores, traffic and transportation, incoming inspection, and quality control and

assurance”. The process of procurement must ensure that, materials to be procured

should be based on five R’S (5R’S) which in general states that purchasing

responsibility to buy material of the right quality, in the right quantity, at the right

time, at a right price, from the right source with delivery at the right place.

In the context of procurement the public has its own direction of meaning especially

on for the ownership. According to Paul et al, (2008) argue that countries vary in

their preferences for public ownership of national infrastructure and services. For

example from 1945 until the late 1970s in the UK, the telephone health gas

electricity water rail bus and coal industries were publicly administered either by

civil servants or by managers characterized as having lie sector mentally such public

services are called utilities in addition utilities there were other organizations such as

parts of the automotive factoring industry and the national airline that were in public

owners variety of historical reasons.

2.2.2 Legal Public Procurement ProceduresIn order to ensure effective public procurement is conducted various laws regulations

have been enacted and established worldwide. Tanzania like other countries has been

Page 26: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

14

using such legal guidelines. There are two main legal documents that are used in

Tanzania for public procurement which are the guidelines procurement under IBRD

loans and IDA credits and the public procurement Act 2004 and the public

procurement regulations 2005

The Procurement Act 2004 provides that a procuring entity may procure from the

Government stores any item included in me approved current stores catalogue where

such item is available at lower prices than current market prices; the Government

Stores Department shall arrange for procurement of common use items by the

procuring entities through framework contracts and the government stores

department shall publish any quarterly year basis in the gazette the authority website

and in the local newspapers of wide circulation the names of items available on the

stores catalogue and names of suppliers awarded the framework contracts (URT,

2005).

According to World Bank (2006), the procedures outlined in the guidelines

procurement under IBRD loans and IDA credit apply to all contracts for goods and

works financed in whole or in part from bank loans. For the procurement of those

contracts for goods and works not financed from a Bank loan, the borrower may

adopt other procedures. In such cases the bank shall be satisfied that the procedures

to be used will fulfill the borrower’s obligations to cause the project to be carried out

diligently and efficiently and that the goods and words to be procured are of

satisfactory quality and are compatible with the balance of the project will be

delivered or completed in timely fashion and are priced so as not to affect adversely

the economic and financial viability of the project.

Public procurement policy in Tanzania elaborates several issues that ensures fair and

honesty conduction of public procurement. According to URT (2005) the public

procurement policies are based on the need to make merest possible use of public

funds, whilst conducting all procurement with honesty and fairness. It is further

stated that the purpose of the World Bank guidelines is to ensure funds granted

through grants loan or credits are effectively used in public projects as targeted and

Page 27: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

15

not mis-procured. The Bank does not finance expenditures for goods and works

which have not been procured in accordance with the agreed provisions in the loan

agreement and as further elaborated in the procurement plan. In such case, the bank

will declare mis-procurement and it is the policy of the Bank to cancel that portion of

the loan allocated to the goods and works that have been mis-procured. The Bank

may in addition exercise other remedies provided for under the loan agreement. Even

once the contract is awarded after obtaining “no objection” from the Bank, the Bank

may still declare mis-procurement if it concludes that the “no objection” was issued

on the basis of incomplete, inaccurate or misleading information furnished by the

Borrower or the terms and conditions of the contract has been modified without

Bank’s approval (World Bank, 2006).

The other purpose of curbing fraud and corruption problem as outline by the (World

Bank, 2006) that it is the Bank’s policy to require that borrowers (including

beneficiaries of the bank loan), as well as bidders, suppliers and contractors and their

subcontractors under bank financed contracts, observe the highest standard of ethics

during the procurement and execution of such contracts. Therefore the guidelines

provided definitions for corrupt practice, fraudulent practice, collusive practice,

coercive practice and obstructive practice.

In the cases of procurement Act 2004, URT (2005) demands public officers and

members of tender boards when undertaking or approving procurement or disposal of

public assets by tender shall choose appropriate procedures and causes the

procurement or dispose assets to be carried out diligently and efficiently so that the

prices or received by the procuring entity represent the best valve or net outcomes

that can reasonably be obtained for the funds applied.

At international procurement tendering the specifications shall be based on relevant

characteristics and/or performance requirements. References to brand names, catalog

numbers or similar classification shall be avoided. If it is necessary to quote a brand

name or catalog number of particular manufacturer to clarify an otherwise

incomplete specification, the words “or equivalent” shall be added after such

reference. The specification shall permit the acceptance of offers for goods which

Page 28: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

16

have similar characteristics and which provide performance at least substantially

equivalent to those specified (World Bank, 2006).

In national competitive tendering otherwise known as national competitive bidding a

procuring entity shall invite suppliers, service providers, contractors or asset buyers

regardless of their nationality by means of a tender notice advertised only in the

United Republic of Tanzania to submit priced tenders for goods services works or

purchase of public assets. Such form of tendering may be used in cases where

payment may be made wholly in Tanzanian shillings; the goods, works or services

are available locally at prices below the international market and the estimated cost

of the goods, works or services is small and does not exceed the threshold for open

international tendering prescribed in the second Schedule to those regulations works

or services are scattered geographically or spread over time works are labor

intensive. the advantages of international competitive tendering are clearly

outweighed by the administrative or financial burden are involved, the estimated

value of assets is small and does not exceed the threshold for open international

tendering prescribed in the Second Schedule to these Regulations (URT, 2005).

In payment of the contract price shall be made in the currency or currencies in which

the bid price is expressed in the bid of the successful bidder. When the bid price is

required to be stated in the local currency but the bidder has requested payment in

foreign currencies expressed as a percentage of the bid price the exchange rates to be

used for purposes of payments shall be those specified by the bidder in the bid so as

to ensure that the value of the foreign currency portions of the bid is maintained

without any loss or gain (World Bank, 2006)

2.2.3 Public Procurement ApproachConsiderable sums of money are spent annually in the public sector on goods and

services. The procurement of these is for good of the population at large and the

expenditure that is incurred is in effect the taxpayers’ money. Public sector buyers

are accountable to the public whose money is being spent including disappointed

tenders and potential suppliers. They must produce procedures and practices which

Page 29: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

17

will stand either to scrutiny during government audits or to the challenge through the

courts of any purchase decision that has been made. A primary purpose of public

accountability prevents abuses of taxpayers’ money. A secondary purpose is to let it

be that any such abuses have been prevented (Bailey et al, 2008)

The approach that has been taken for many years within the public sector can be

summarized as follows: purchasing should be based on value for money, competition

should be used to acquire goods and services (unless there are convincing reasons to

the contrary); there should be clear definition of the roles and responsibilities of

personnel involved in specifying the need giving financial authority making

procurement commitments; there should be a separation of the financial authority

and the purchase authority; there should be a separation of duties between personnel

who makes the contracts, those who receive goods or services and those who oath

payments; and requirements which are above a certain financial threshold are

normally required to be advertised in accordance with regulations on public

procurement (Bailey et al, 2008).

Public sector purchases have taken on the procedures without major upsets and in

general they appear to work well. Within the utility sector, it is possible for an

organization to have its in-house procedures inspected for compliance with the

procedures so that, provided they are always followed the organization will be

viewed as having followed the correct path. This process originally contained in the

Utilities Compliance Directive and not included in the public sector legislation is

called ‘attestation’. It enables organizations to develop acceptable (and thus ‘owned’)

procedures that make sense in local terms (and perhaps terminology) while also

ensuring that the requirements of the Directives are met (Cousins et al, 2008)

There are five sets of procedures and having decided that a contract is caught a

purchaser must choose one of them to follow: open procedure; restricted procedure;

competitive dialogue; negotiated procedure (without a call for competition (including

urgency procedure), and negotiated procedure with a call for competition); and

dynamic purchasing system (Cousin et al, 2008).

Page 30: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

18

Morris (2003) emphasizes that, when buying on very short demand or developing a

tight performance specification, the first move to a purchase is to define the product

or service required whereby several factors are examined including quality, cost,

availability, familiarity with the supplier, etc. Ultimately, the decision to buy is based

on how well the purchased item or service meets with expectations. Notably, the

specification can be developed for a ready-made item or for yet-to-be-designed

items. A specification may include the parameters for delivery, such as routine

periodic shipments or on as needed basis.

Cousins et al, (2008) argue that strategic supplier selection involves four main stages:

initial supplier qualification; agree measurement criteria obtain relevant information

and make selection. Supplier qualification is the first step towards supplier selection.

The goal is to identify suppliers who meet the requisite product and process

standards and are capable of supporting the buyer’s long-term objectives. Because

organizations are resource constrained, qualification helps to reduce the pool of

potential suppliers to a more manageable number for detailed evaluation and

selection (Cousin et al, 2008).

Morris (2003) emphasizes that, once the item or service being purchased has been

identified purchase specifications, a purchasing manager must identify from who to

purchase. That is, purchases can be made between individuals’, organization or

collectives of these. Purchasing managers, buyers and purchasing agents make up a

key component of a firm’s supply chain. Wholesale and retail buyers purchase good

for resale such as clothing or electronics and purchasing agents buy goods and

services for use by their own company or organization such as raw materials for

manufacturing or office supplies. Procurement agents and buyers of farm products

purchase goods such as grain, Christmas trees, and tobacco for further processing or

resale.

Johnson (2002) emphasizes that procurement professionals consider price, quality,

availability, reliability, and technical support when choosing suppliers and

merchandise. Those procurement professionals try to get the best deal for their

Page 31: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

19

company, meaning the highest quality goods and services at lowest possible cost to

their companies. In order to accomplish these tasks successfully, purchasing

managers, buyers, and procurement agents study sales records and inventory levels

of current stock, identity foreign and domestic suppliers and keep abreast of changes

affecting both the supply of, and demand for, needed products and materials.

The strategic selection process continues with identifying relevant and appropriate

selection criteria. Unfortunately, far too many businesses throw measures at supplier

selection and evaluation without considering why the measures are necessary and

what value they will add. Apart from price and delivery, quality is probably the most

common criterion used in the supplier decision and in some circumstances is given

primary importance. Furthermore buyer firms may also visit supplier plants to

ascertain the general altitude of management and workers to quality. Criteria used

here may range from the use of quality circles and continuous improvement

techniques through to very simple checks of the state of the plant floor and amount of

rework (Cousins et al, 2008).

Love et al (2008) put identified nine criteria that clients could use to select their

priorities for projects. These are: time certainty of cost price competition, flexibility,

quality responsibility and risk. It can be seen the criteria identified are different in

nature. The major challenge for clients when selecting a procurement method is

identifying the criteria for the project but the question is that if projects are different

in nature and clients’ needs are constantly changing due to internal and external

demands, would the same criteria be applicable for all projects? The weighting for

criteria will invariably change as would the criteria type.

Any such procurement begins with planning decision to make the purchase and this

will involve in the first place, deciding whether there is a need for the particular

goods or services, ensuring that the purchaser has the legal powers to undertake the

transaction, obtaining any relevant approvals within the government hierarchy and

arranging the necessary funding (Arrow smith et al, 2000).

Page 32: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

20

In fact, Thai, (2004), maintained that forums and procedures may be convenient and

useful tools, but the planning effort will succeed only with complete commitment

and involvement of top management, along with appropriate personnel that have a

stake. This implies that without thorough procurement planning, the subsequently

procurement process will not yield substantial benefits. The consequences of poor or

lack of procurement planning can never therefore be amusing.

Poterba (2001) emphasizes that evaluating suppliers is one of the most critical

functions of a purchasing manager, buyer, or purchasing manager, buyer or

purchasing agent. Many firms now run on a lean manufacturing schedule and use

just-in-time inventories so as nay delays in the supply chain can shut down

production and cost the firm its customers and reputation. Purchasing and

procurement professionals use many resources to find out all they can about potential

suppliers. The internet has become an effective too in searching catalogs trade

journals and industry and company publications and directories. Notably, purchasing

and procurement professionals are important to make certain that the supplier is

capable of delivering the desired goods or services on time, in time correct quantities

without sacrificing quality.

JIT is concerned with reducing safety stock and lot sizes. This will impact

significantly on how delivery from suppliers is structured. Buyer firms using JIT will

require suppliers to deliver exactly to their build schedule and more frequently with

smaller lot sizes. This should be reflected in the original supplier selection criteria,

creating the need to measure on-time delivery performance and minimum lot size

(Cousins et al, 2008)

Procurement of equipment, goods and services for the government and the public

sector generally is complex. On one hand there is a need to ensure best value for

money on behalf of the tax payer and the need to ensure that the processes to achieve

this are fair and open to scrutiny. On the other hand there is considerable pressure to

make savings (especially in the light of constantly reducing budgets) and to utilize

some or all of the best practice philosophies mentioned earlier. This has led to many

challenges for those undertaking procurement. Many observers will comment that

Page 33: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

21

procurement in the public sector is about following procedures and yet, many say,, if

the procedures are followed then innovation and improvement in cost performance

(in line with commercial best practice) can be stifled (Bailey et al, 2008)

Cousins et al, (2008) highlight that it is important that the information is comparable

across suppliers so that for example information on quality from supplier A can be

compared to information on quality from supplier B. information should also be

timely and accurate. The supplier selection procedure relies on having up-to-date

information that provides an accurate representation of suppliers. Supply Strategists

can obtain information from a variety of sources, including information from

suppliers, supplier visits and supplier performance measures.

The selection of a procurement method is more than simply establishing a

contractual relationship. It involves creating a unique set of social relationships

where by forums of power within a coalition of competing or cooperative interest

groups are established. The selection of a procurement method is more than simply

establishing a contractual relationship. It involves creating a unique set of social

relationships where by forms of power with in a coalition of competing or

cooperative interest groups are established (Love et al, 2008).

The one credible complaint about procedure is that, as all applicants that meet the

purchaser’s minimum standards must be invited to bid, large numbers of bids must

be sought for some contracts, which can be expensive for both purchasers and

suppliers. The advantage of the open procedure is that the contracting time scales are

shorter than for the others procedures. However, the open procedure is not suitable

for contracts where the costs of bidding and assessment of bids are high unless there

are only few suppliers in the market. Thus, whereas using the open procedure

(properly) should ensure that a purchaser is safe from subsequent attack, it may be

preferable to opt for less open procedure, bearing the burden of justifying the

restricted invitation. The directives present a number of ways of doing this: the first

is called the restricted procedure (Cousins et al, 2008).

Page 34: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

22

For the European Union Public Contracts directive provides the following main

features to the coordination of procedures for the award of public service contracts.

Provision is made, however, for a range of exclusions, including: rent of land,

existing buildings or other immovable property; development of programmer

material by broadcasters; contracts for broadcasting time; contracts for certain

telecommunication; contracts for arbitration and conciliation services; central bank

services; certain other financial services contracts; employment contracts and certain

research and development service contracts (Bailey et al, 2008).

The rules in relation to the use of the negotiated procedure without a call for petition

are very restrictive and apply to both the public and utility sectors, include urgency

for reasons not due to the purchaser or reasons which were seeable by the purchaser,

in other words urgency due to reasons outside the control of the purchaser. Other

reasons include that contracts have been advertised under the open and restricted

procedures and no responses have been receive that there is only one supplier

available or the requirements are additions to existing contracts where to change

suppliers would result in major technical problem (Cousins et al, 2008).

The negotiated procedure with a call for competition may be by the public service

sector when they have advertised under the open and restricted, procedure and

received only non-compliant or unacceptable bids or when the purchaser unable to

define their requirements to the level that would allow to award the contract under

the rules applicable to the open and restricted procedures (Cousin et al, 2008).

Just like a purchase decision, the selection of a management consultancy is complex

and is considered to be difficult. This is because it requires the purchaser to assess a

supplier’s ability to deliver an intangible product, the consultancy. Add to this that

consultancy cannot be realistically tested prior to purchase and that the buyer

typically has limited experience with purchasing such a service, and the level of

associated difficulty becomes apparent. It is important that purchasers have sufficient

access to information to be able to select management consultancies (Corocan and

McLean, 1998)

Page 35: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

23

Whilst price is becoming an increasingly important factor in these days of cutbacks,

in the private as well as in the public sector, it is widely recognized that competitive

tendering on price alone is rarely a suitable means of selection as the professional

approach of firms can vary widely (Wimmer, 2003). Therefore, companies in the

private sector use a variety of criteria to judge the suitability of a consultant: the

previous experience of the supplier; the image or reputation of the consultant: the

buyer’s interaction with the consultant and recommendations by others.

These selection criteria are however not common for the public sector, because of the

European legislation prohibiting or at least impeding, this type of selection criteria

within the public sector. Although it is recognized that the value for money is “not

the lowest price’ and it involves some elements of the balance – that is – weighting

what was provided against price (Wimmer, 2003), the lowest price is one of the few

selection criteria supported by the European Public Tendering Process (PTP)

legislation. And even if the price criterion is not rated as a dominant attribute in the

selection process, it nevertheless plays an important role if the selection is based on

the most “economically advantageous” tender, the other selection criterion permitted

by PTP legislation. The price criterion is also important because of its capacity to

discriminate among a shortlist of similar proposals.

2.2.4 Procurement GovernanceThe Governance refers to how an institution is managed. It includes how a set of

activities in a given institution are undertaken in order to meet objectives of the

institution. It involves how resources such as human, materials, assets and money are

optimally utilized. Governance includes also how in institution relates and interacts

with its various stakeholders such as customers, suppliers, creditors and the general

public.

Procurement Governance as a subset on the other hand refers to how a set of

activities in a procurement cycle are performed according to laws, policies,

regulations and rules governing operations of a given institution.

Page 36: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

24

Salient elements of good governance principles include; commitment and dedication

to the institutions, honesty, and integrity responsibility, accountability, transparency,

selflessness and mutual respect. These elements may form core values of some

procurement entities in general and procurement units in particular.

Good Procurement Governance has a number of benefits as it;

i. Facilitates optimal utilized of scarce resources

ii. Enables the institution to acquire goods and services of the right quality as

and when required

iii. Facilitates establishments and operation of best practices

iv. Minimize or eliminate stakeholders’ complaints

v. Improves the image of the institution

vi. Enables competitive and wise procurement

vii. Minimize the risk of buying of inferior goods and associated costs

In order to undertake such as task they should establish performance indicators and

benchmarks. It is however worth mentioning that Public Procurement Regulatory

Authority (PPRA) have developed some indicators and compliance indicators

(Procurement Journal Vol. III No. 9).

i. The compliance indicators are of five groups:

ii. Organization set up and functioning

iii. Procurement planning

iv. Tender process

v. Records Management

vi. Contract Management

Public institutions are required to work according to the indicators and the set

benchmarks. Private sectors may make use of theme as they are very beneficial. Thus

the importance of good procurement governance requires no overemphasis as its

benefits outweigh its costs by far. . Given by Ahmed S. K. Kilima - PSPTB Journal

pg 3 issue No. 3 July-Dec. 2010

Page 37: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

25

Poor governance has been one of the major stumbling blocks to the economic

development of Africa and it has been clear that a number of African countries have

not paid adequate attention to the proper management of public resources. An

efficient public procurement system is vital to the advancement of African countries

and is a concrete expression of the national commitment to making the best possible

use of public resources (Kabaj, 2003)

It is an issue of concern in both developed and developing countries but many

developing countries have increasingly realized that a well-organized procurement

system contributes to good governance by increasing confidence that public funds

are well spent (Arrowsmith et al, 2000). Good governance is accountable,

participatory and transparent and it ensures that political social and economic

priorities are based on board consensus in society and that the voice of the poorest of

the poor and the most vulnerable are heard in decision making over the allocation of

resources.

The management of public procurement process is one of the functions that have

probably a wider implication in ensuring good governance because all government

departments charged with providing services are dependent on this process.

Reforming and strengthening systems of public procurement must be given a high

priority in the efforts to improve systems of governance in the African Countries

(Kabaj, 2003).

Planning both as a concept and function is probably one of the extensively talked

about concepts in the management literature. It is a function that forms the

foundation for the rest of management functions. When planning is properly

conceived and implemented, it can serve as an important mechanism for extracting

distributing and allocating resources (James, 2004). Planning generally enhances the

gathering, evaluating and interpreting of essential data and information in order to

produce knowledge relevant to good policy making.

Page 38: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

26

The planning function encompasses defining an organization’s goals, establishing an

overall strategy for achieving those goals, and developing a comprehensive hierarchy

of plans to integrate and coordinate the activities. Procurement planning is the

primary function that sets the stage for subsequent procurement activities. It ‘fuels

and then ignites’ the engine of the procurement process (James, 2004).

In order to ensure public accountability, yet to gain optimum impact through the use

of commercial best practice, there is a need for professional training and education of

those personnel responsible for strategic direction and practical application of

procurement action. Professionalism can only come from a full understanding of all

the issues involved a sound knowledge, a sound knowledge of legal and commercial

aspects and the confidence to make decisions that effectively balance these tensions

(Bailey et al, 2008).

The internal regulatory mechanisms of government-accounting, procurement and

personnel have long received sustained attention as the centerpiece of reforms to

promote accountability (World Bank, 2000). Accountability of public officials is

critical in deterring corrupt practices and it creates an enabling environment for

vibrant private sector activity (Kabaj, 2013). Problems of accountability arise when

government ignore or transgress social ethics and constitutional and legal provisions

in conducting public affairs, administrative systems are fragmented, tasks to be

performed are so complex or unspecified that it is difficult to identity who is

responsible for what, activities are underfunded so that implementation is very

difficult or impossible (Therkildsen, 2001).

Perceptions which appear anecdotal, view politicians as only being engaged in

discussions on the conditions of contract, contract awards and purchasing initiation,

while concerned about image; together with public accountability being viewed as a

hindrance, present a negative and very narrow perspective, yet there does not

actually appear to have been a balance of empirical research into the actual roles and

potential roles of politicians in public procurement strategy and management. Indeed

such perceptions of politicians’ engagement with public procurement may undermine

the very democratic process so fundamental to public procurement and highlight the

Page 39: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

27

need for a wider understanding of how public procurement fits within democratic

governance (Soudry, 2007).

2.3 Empirical Studies

2.3.1 General EmpiricalPooler (1997) emphasizes that; Materials Management sets itself the tasks of

understanding why materials needed, stored and or developing new methods of

making them available all activities concerned with material locomotion. That is, the

science and Technology of managing materials is more important because all areas

of applications are prudently included, that is from purchasing to warehouse, from

production control to inventory control, from transportation to physical distribution.

Pooler (1999), argue that Material Management is a managerial process that goes far

of beyond simply buying materials and warehousing whereby includes tactful

planning policy and procedures that cover a wider range of related activities,

including research and development as required for the proper selection of materials

and sources, ascertainment of delivery, inspection of documents on incoming

shipments to ensure quality and quantity compliance, development of procedures to

implement buying policies and stores policies, coordination or purchasing activities

with other internal division of the concern such as engineering, production, and

accounting, and development of effective communication with top management in

order to ensure a complete appraisal of the performance of the Materials

management function.

Romano (2000) argue that material management is concerned with the input process

of manufacturing and includes the flow of raw materials, spares, components and

finished goods to supply the sales and marketing functions with a final product. The

input process (Suppliers and Product) is separated from the output (Distribution and

marketing to consumers) because in a manufacturing concern the function involves

Page 40: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

28

in the input process finally change the physical state of the product, and the functions

involved in the output process chance the location of the product, and the functions

involved in the output process change the location of the product in its same state.

The results of the reduction analysis have been applied to a larger body of research,

which has developed a best value tender analysis support tool that has the capability

to enable the identified attributes to be assessed on a project specific basis using a

combination of the analytic hierarchy principle, multi attribute utility theory and

whole life costing. The methodology underpinning the support tool has already been

used by RSL’s to assist them in best value decision making processes and as the

support tool has been produced as window based software it is anticipated what it

can be used to assist RSL’s in evaluating the high volume of best value tenders in a

more effective and efficient manner (Phillips et al, 2007).

In February 2004, the European Union adopted a set of new rules simplifying and

modernizing the Directives that outline EU law on public procurement. The new

Directives were published in the UE Official Journal on 30 April 2004. Member

States now have 21 months in which to amend national laws to implement them.

This means that the new rules will come into force on 31 January 2006. The main

themes of the reform were the simplification and modernization of the legal

framework and its adaptation to modern administrative needs, by for example

facilitating electronic procurement and improving the flexibility of certain

purchasing solutions (Pourbaix, 2004)

While recognizing the importance of a clear procurement process, guided by public

tendering, publication of winning bidder and mechanism for appeal for aggrieved

parties, various countries insert in their law provisions that are intended to protect

their national ‘sovereignty’. Such provisions usually take into account the country’s

industrial policy (e.g. protection of the country’s local industries), social policy (e.g.

protecting the role of women or the physically disabled) or protection of a country’s

strategic economic objectives such as regional integration. These provisions

although deemed desirable, especially for developing countries, have serious

Page 41: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

29

connotations in as far as promoting free trade is concerned. These discriminatory

tendencies constitute a subtle protectionism to trade (Arrow smith et al, 2000)

Discrimination refers to a government’s tendency to favour its own domestic

industry’s supplies and disregard foreign firm supplies. There are two classical

forms of discrimination against foreign bidders in public procurement; explicit and

implicit. Explicit forms of discrimination can take various forms, two of which are

the “preferential price margin” and “domestic content requirement.” Under

“preferential price margin”, purchasing entities accept bids of domestic suppliers

over foreign suppliers as long as the difference in price does not exceed a specific

margin of preference. The price preference margin can result from an explicit “buy

local policy” e.g. ‘Buy America Act’. The United States government offered a 6%

preference for domestic suppliers. The preference can be raised to 12% in case of

small business and firms in regions of high unemployment and 50% of military

equipment. Explicit domestic preferences have also been applied in Canada,

Australia, New Zealand and Turkey (Naegelen and Mougeot, 1998). Under the

“domestic content requirement”, government purchases from foreign sources only if

the latter commit to purchase some components form domestic firms.

2.3.2 The Case of AbroadGershon, (2003) found that too much public procurement is undertaken without

professional support which results in sub-optimal value for money and unnecessarily

high prices being paid for goods, works and services. Most procurement is not

carried out by designated procurement staff, the procurement staffs are often

consulted too late in the procurement process and the majority of procurement staff

do not hold professional qualifications. Simply advising organizations to take up

“best practice” is impractical and unlikely to lead to achieving high performance

unless continuous support is provided.

Jones and O’Brien, (2002) found that the procurement problems are further

exacerbated by the fact that value for money must also be considered in parallel with

Page 42: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

30

collaborative working. Present criteria used to evaluate the performance of

contractors often include: the quality of products and services, cost predictability,

time predictability, and their health and safety record. However, in longer term

relationships the RSL also needs to be as clear as possible with respect to its

corporate policies and strategies so their contractors can be assessed on new factors

such as: their willingness to work collaboratively and synergistically as partners;

their understanding of RSL objectives and cultures; and their openness and

willingness to share information and their ability to manage supply chains.

Murray (2007) demonstrated, form a small number of action learning research

projects, that, within UK local government, politicians, in collaboration with chief

officers, exhibited an enthusiasm and appeared to have the capabilities to be engaged

in strategic procurement management, specifically, determining the corporate

procurement strategy and mapping the procurement portfolio; challenging the desired

procurement outcome; challenging procurement delivery options; supplier selection

and contract award; and post contract management and review.

Romano (2000) emphasized that; Purchase decentralization is always associated with

purchase freedom, employee growth and task fulfillment, high delegation of

purchase decision making, authority and all purchasing efficiency and effectiveness.

However, he continues to emphasis that, the importance of efficient management of

material resources in any economy, need an efficient management of material not

only effect a particular industry or a particular organization but indeed the whole

economy of a national may easily be bogged if sound and acceptable principles

managing materials are not observed.

2.3.3 The Case of TanzaniaPPRA (2007) found that Public Procurement Act 2004 complies to a large extent

with applicable obligations deriving form national and international requirements. It

provides for competitive tendering procedures and access to complaints and

procurement appeals mechanism. From the interview, it was revealed that most of

the stake holders are not familiar with the PPRA of 2004. Only 30% are familiar with

Page 43: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

31

the Act and 85% do not have a copy of the PPRA 2004. The associations

interviewed showed that out of five associations, only three indicated that their

members were familiar with the Act.

URT (2003) found that a number of weaknesses were observed in the

implementation of the current regulations including: lack of procurement planning in

government financed procurements; weaknesses in the advertisement of tenders;

non-compliance of contract award procedures and criteria; and weak complaints and

administrative review process. One of the most critical issues in the current practices

is the lack of procurement planning in government financed projects. Procurement

planning is essential for public procurement to achieve one of its major goals of

providing value for money.

PPRA (2007) reported that the PPA 2004 and its Regulations contain adequate

provisions emphasizing the use of the Standard Tender Documents and the use of

neutral specifications in any public procurement. Assessment revealed that technical

specification for 73.7% of the tenders assessed were developed by internal staff,

17.76% were developed by the responsible Ministry 5.4% were developed internally

and approved by the responsible Ministry while 3% of the samples data were not

available to reveal the source of the specifications.

The assessment has revealed that 5.56% of the tenders received form bidders were

rejected due to failure to comply with technical specifications, 23.36% were rejected

due to failure to comply with other requirements. By summing up the above analysis

we can conclude that 29% of bidders don’t know how to prepare responsive bids.

This indicates that there is a need to build capacity on how to prepare responsive

bids. It was also recommended that pre-bidding meeting with bidders to be

mandatory. In the pre-bid meeting PEs will debrief and clarify to the bidders their

requirements which will enable them to prepare responsive bids (PPRA, 200).

URT (2003) observed that for those tenders that use the open competitive process, it

was observed that there is no central media for advertisement of tenders or awards.

Page 44: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

32

As a result, the notices are scattered in local and East African papers which might

explain why the same set of contractors (including foreign) have been participating

in most of the works contracts. The CPAR team was also informed that the rules and

procedures for bid submission and opening are often not adhered to. Instances

reported include breaches of confidentiality and collusion between the procuring

entity and bidders leading to competitors’ bids being revealed before the official

opening and bidders being allowed to replace their bids based on this information.

2.4 Variable and Conceptual Framework

The public procurement is an important function for national development. It is

through public procurement the government may efficiently use its funds (whether

own revenue or donor based revenue) for development activities. However, effective

public procurement depends on the various practices; procurement procedures,

procurement methods and procurement management. The performance of all these

may entail effective public procurement. However, the current situation does not

reflect better performance of procurement in the public sector. Moreover, there is

limited information in this area of concern. Due to this, the study is interested to fill

the gap.

It is envisaged that the use of a smaller number of named core attributes could

increase the efficiency of the tender analysis procedure and may assist the non-

professional support staff in their understanding of the process. However, as there is

no single authoritative and comprehensive listing of the different quality attributes

considered by all the stakeholders during a best value tender analysis.

Therefore, public procurement management includes the broad management

functions of planning, organization, and leadership, staffing, controlling, and

communicating procurement processes and activities across the spectrum of the

‘upstream’ supply chain activities of both public and organizations. A supply chain;

is a network of activities involving the suppliers on one hand and the customers on

the other hut being linked by an organization. Procurement; and its management, is

Page 45: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

33

one of the activities of the supply chain. Two broad sectors of the economy do exist-

public and private sectors; and procurement take place in both sectors.

Public procurement is different form private procurement because in public

procurement, the economic results must be measured against more complex and long

term criteria and it must be transected with other considerations accountability, non-

discrimination among potential suppliers and respect for international obligations- in

mind besides the economy. The basic tenet of public procurement is to acquire the

right item at the right time, and at the right price, to support government actions but

although the formulae is simple, it involves questions of accountability, integrity and

value with effects far beyond the actual buyer\seller transactions at its center.

As government departments operate within a framework of public accountability and

cost effectiveness, considerable emphasis is placed on the fair treatment of suppliers,

compliance, competitive tendering and procedures for ensuring propriety and

regularity, hindering the development of collaborative procurement arrangements.

2.5 Measurement of VariablesThe measurement for the study involves the dependent variables and independent

variable. The dependent variables are compliance to procedures, benefits and of

tendering and quotation methods and procurement management. Therefore they will

be measured against independent variables. Compliance to procedures will be

measured against effectiveness of procedures, cost saving, reduction of lead time.

The benefits of tendering and quotation methods will be measured against speed of

processing, accuracy of documentation, quality of criteria used, acquisition of needed

supplies; and procurement management will be measured against information

coordination, proper decision making, flow.

Page 46: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

34

CHAPTER THREE

RESEARCH METHODOLOGY

3.1 OverviewResearch methodology is systematic approach through which research is undertaken.

The research methodology include research paradigm, design[strategy], description

of the case study, location of the study, nature of data required, measurement of

variables from conceptual framework, quality of data measurement, data collection

methods and instruments, sampling procedures, field work, data processing and

analysis, expected results.

3.2 Research StrategyResearch Approaches

Is a systematic way of dealing with a research problem. Solution for the research

problem will be found through methodology, methods and techniques which will

help the researcher to answer the research questions which address the research

problem. Primary data from the field and secondary data from various documents

will be collected and analysed in order to identify factors affecting effectiveness of

procurement process in public sector.

According to (Churchill et al 1984), there are two paradigms of doing research

namely positivism and phenomenological approach. The research used

phenomenological approach for qualitative research

Research paradigm is a way of examining social phenomenon from which particular

understandings of these phenomenon can be gained and explanations attempted

(Sounders et al, 2009). Therefore, for this study, a regulatory perspective paradigm

will be followed as a research philosophy. This is a perspective that seeks to explain

the way in which organizational affairs are regulated and offered suggestions as to

how they may be improved within the framework of the way things are done at

present (Sounders et al, 2009

Page 47: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

35

Research Design

This is a plan that specifies how data were collected and analysed from the study. In

case of this study, the research design used was a Case study. A cases study is in

depth study of limited number of events/conditions and their interrelations. It deals

with the process that takes place and their interrelationships. It is a behavior –

patterns of the given unit as an integrated totality.

The case study was chosen because it will enable the researcher to obtain information

needed for the study, also it specifically helped the researcher to focus on a single

unit of study due to limited time and fund and also intensive investigation for the

study. The Temeke Municipal Council was selected as a case study due to the

following reasons:

(i) It is flexible in respect to data collection methods, it permit the use of

different data collection methods like observation, interview and documentary

review.

(ii) It can be used jointly with other designs example survey design.

3.3 Description of the Case Studied

The study was carried out at the Temeke Municipal Council in Dar es Salaam. It was

chosen because it enabled the researcher to obtain information needed for the study,

it also helped the researcher to focus on a single unit of study due to limited time and

fund and also intensive investigation for the study. The Temeke Municipal Council

was selected as a case study due to the following reasons:

(i) It is flexible in respect to data collection methods, it permit the use of

different data collection methods like observation, interview and

documentary review.

(ii) It is the place where a researcher is working, thus somehow somewhere it

will increase the accessibility of data during the process of data collection.

Page 48: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

36

3.4 Location of the Study

Temeke Municipal Council headquarters’ office is located along Mandera and Taifa

road. Temeke Municipal council is one among other Municipal councils in Tanzania

which was established under District Act No 7 of 1982.And the Local Government

Authority Act which makes provision for city authorities and provides the related

matter.

TMC is formed by councils which operates a political organ and major is the Head of

the council; he is appointed by members of the council (Councilors) from 41 wards

of the TMC. Temeke Municipal council has all the responsibility of planning,

coordinating, supervising, and implementing all Development projects in the city of

Arusha as provided by LGA and Registration.

To ensure effective performance in management of these projects the Municipal

Organization structure is composed of three Directorate commeets which are;

planning, statistics, and Economics, internal Audit Legal and Security services.

Within these Directorates committees there are eight (8) operation Departments

which are headed by heads of Departments these are;

1. Administration and Human Resource,

2. Education and culture

3. Health and Waste

4. Agriculture and Livestock

5. Works and Fire Rescue,

6. Urban planning,

7. Planning and Monitoring,

8. Finance,

9. Industries and Trade

3.5 Nature of the Data RequiredThe researcher used different types of data for the study. The researcher collected

both primary and secondary data.

Page 49: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

37

(i) Primary data were obtained from respondents who are knowledgeable with

procurement activities at the Council. These data were obtained as first-hand

information. The primary data were obtained from respondents by interview,

and observation.

(ii) Secondary data were collected from Temeke Municipal Council operating

reports, requisitions, purchase forecasts and funds earmarked for purchase

activities. These were second hand information. Secondary data means data

that are readily available that is the data which have already been collected

and analyzed by someone else. Secondary data may either be published or

unpublished data. Usually published data is available in various publications

of the Municipal council, technical and trade journals, books, magazines and

newspapers, different reports, etc.

3.6 Measurement of Variables from Conceptual FrameworkThe measurement for the study involves the dependent variables and independent

variable. The dependent variables are compliance to procedures, benefits and of

tendering and quotation methods and procurement management. Therefore they will

be measured against independent variables. Compliance to procedures will be

measured against effectiveness of procedures, cost saving, reduction of lead time.

The benefits of tendering and quotation methods will be measured against speed of

processing, accuracy of documentation, quality of criteria used, acquisition of needed

supplies; and procurement management will be measured against information

coordination, proper decision making, flow.

3.7 Quality of Data MeasurementThe researcher makes sure that all the data obtained had the required quality. Thus

ensuring they were valid and reliable.

(i) Reliability of data

Reliability is consistency of measurement or, the degree to which an instrument

measures the same way each time are used under the same condition with the same

subjects. The collected data from different staff covered relevant information

Page 50: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

38

required by the researcher. This means that internal estimates reliability by grouping

question in questionnaires that measure the same concept.

(ii) Validity of Data

This refers to quality of an instrument used in research to measure what is supposed

to measure. The researcher ensured that the data obtained through interview using

questionnaires were collected from authority personnel in order to maintain the

validity and reliability of data in this research.

3.8 Data Collection Methods and Instruments

(i) Data Collection Methods

The research adopted various approaches of data collection which led to obtaining

information relevant to the study, where interview, observation and survey

approaches were used.

Interview

This is a data collection technique in which an interviewer reads the same set of

questions to the respondent in a predetermined order and records his/her responses

(Saunders et al, 2007). The interview was also applied so as to collect further data.

The researcher in this study administered the questionnaire to the respondents by

asking the questions to the respondent and recording the responses as provided by the

respondent. For closed ended questions, the researcher read the questions and the

respondent was supposed to choose the best answer among the options provided by

the researcher. For open ended questions, the researcher read the question and gave

the respondent a chance to provide answer while the researcher records the answer

provided by the respondent to the respective questionnaire.

Survey

This refers to data collection using a survey strategy usually by information that has

already been analyzed for their original purpose (Saunders et al, 2007). The use of

documents as part of source for data collection is important. Secondary data were

Page 51: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

39

collected from the documents. These were forms, reports and various reading

available related to the subject matter under the study.

Observation

This is the method or process whereby the researcher paid a personal visit on the

field ground. The researcher was involved in a day-to-day activities concerning

procurement process effectiveness. This enabled the researcher to understand clearly

about assessing the effectiveness of procurement process at Temeke Municipal

Councils, and it helped the researcher to gain high level of understanding of the

subject.

Documentation

This included the information from documentary records, published data and

internet, also various document such as store ledger, issue voucher, LPO, RV,

contract manual, procurement news, tender documents and reports from various

meeting that have been done at Temeke and Kinondoni Municipal Council

(ii) Data Collection Instruments

These are instruments normally used to gather data for the study. For the case of this

study the researcher used questionnaire as a data collecting tool.

Questionnaire

A questionnaire is data collection instrument in which a person is asked to respond to

the same set of written down questions in a predetermined order (Saunders et al,

2007). The application of questionnaire helps a researcher to collect primary data.

The questionnaires were administered by a researcher. This instrument was applied

because it was easy to use and had good impact on general data collection.

Page 52: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

40

3.9 Sampling Procedures

(i) Target Population

As the area of interest in this research was to the measurement of effectiveness of

procurement process in a public sector, the unit of the study was employees of

Temeke Municipal Council. Allemployees who are procurement officer at PMU or

any other employees working in different departments with the procurement

activities form the population of the study.

The target population comprised of procurement personnel from the PMU and other

different user departments such as Administration and Human resource, Education

and Culture, Health and Waste, Industries and Trade, Urban planning, Work and Fire

rescue, Planning and Monitoring, Finance. The research consisted of 20

employees/respondents and this was because of the difficult to study the whole

population. Since the center of interest was procurement effectiveness at the

Municipal Council, the information was drawn from Procurement Management

Unity (PMU) office and stores departments. These departments dealt with various

transactions at the Municipal related to procurement. Therefore drawing a sample

from these departments enabled and enhanced the achievement of right respondents

and data for the study.

(ii) Sample Size

A random sample size of 20 respondents was drawn from different procurement

personnel available at PMU office (8) and stores of different user departments such

as Administration and Human resource (1), Education and Culture (2), Health and

Waste (2), Industries and Trade (1), Urban planning (2), Work and Fire rescue (2),

Planning and Monitoring (2). Basically at Temeke municipal council the sample for

the study were 20 respondents whereby all 20 were procurement personnel selected

from PMU office and other departments.

Page 53: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

41

(iii) Sampling Technique

The non- probabilistic sampling techniques was adopted, that enabled the researcher

to select respondents with necessary and relevant information. The technique was

less costly and it was quick to select a sample. The decision as to what sampling

method to be used depends on the aim of study, the expected degree of accuracy of

the study results and the sampling cost.

In this non-probabilistic sampling, the purposive sampling was applied because it

helped to access respondents who are knowledgeable about procurement activities as

they are undertaken at the Municipal Council. Twenty procurement personnel were

obtained as respondents from different sub departments at the Municipal Council

who were expected to provide reliable data (Sounders et al, 2007)

3.10 Field WorkThe researcher began data collection at the beginning of May, 2013. For the period

of two weeks, the researcher visited the head offices of Temeke municipal council.

At the head office the questionnaires were administered to the required respondents

as sample described thus procurement specialists at different departments of the head

office.

By the end of May, 2013 data collection was accomplished and the researcher went

back and continued with other steps of data compiling and report writing.

3.11 Data Processing and Analysis

(i) Data Processing

Data management entails the whole process of handling data form their collection,

processing and analysis. Better data management leads to availability of liability and

validity of data. The researcher administered data collection tools during data

collection by providing further details (when needed) to support proper answers.

Moreover, the data were inspected and corrected form the first stage of data

collection. The inspection and correction of data was based on the measurement

criteria established. Further, the data were processed for error cleaning so as to get

Page 54: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

42

only useful data for analysis, which was done basing on the variables and

measurement.

(ii) Data Analysis

For the matter of easy interpretation of study findings the researcher analyzed data

manually. With the use of statistics in the form of tables data were interpreted. The

interpretation was done from data presented in terms of frequencies and percentages.

However, the bases for interpretation depended on knowledge gained form the

literature review in relation to the research questions established before.

Page 55: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

43

CHAPTER FOUR

FINDINGS AND ANALYSIS

4.0 IntroductionThis chapter present the findings found during the study. The findings are presented

in accordance to the research objectives established before.

4.1 Effectiveness of Procurement Process

4.1.1 Participation in procurement process

The procurement process requires different employees associated in order to ensure

effective procurement process. The results show that all respondent (100 percent)

reported to participate in the procurement process. Effective participation in the

procurement process is important in order to assure effective management in the

purchase of government services and materials.

Table 4.1Participation in Procurement ProcessVariables Frequency Percentage

Yes 20 100

No 0 0

TOTAL 20 100

Sources: Survey data

4.1.2 Difficulties in Procurement Process

The results show that there are difficulties in the procurement process. This was

reported by all the respondents (100 percent). This shows that while procurement is

conducted employees find some difficulties in processing the procurement in various

ways or forms and therefore in that sense the process is not conducted smoothly. This

will further be detailed in the coming chapter.

Page 56: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

44

Table 4. 2 Difficulties in Procurement ProcessVariables Frequency Percentage

Yes 20 100

No 0 0

TOTAL 20 100

Source: Survey data

4.1.3 Effectiveness of Procurement Process

The study aimed at determining the effectiveness of procurement process as

conducted at Temeke Municipal Council. The results show that the procurement

process is effective as reported by 55.0 percent of the respondents where as 10

percent of respondents said the process is very effective. 30.0 percent of the

respondents reported that there is moderate performance of the procurement process

while 5.0percent of the respondents reported that the procurement process is

ineffective. Generally it was found that the procurement process is at better position

at the Municipal Council.

Table 4. 3Procurement Process EffectivenessVariables Frequency Percentage

Very Effective 2 10.0

Effective 11 55.0

Moderate 6 30.0

Ineffective 1 5.0

Very ineffective 0 0.0

TOTAL 20 100

Source: Survey data

4.1.4 Cost EfficiencyThe public procurement, one among other things, requires efficient use of the public

funds. Following this fact, it was important for the study to find out the performance

of the procurement process at the Temeke Municipal Council to the cost efficiency or

cost minimization. The results show that there is moderate cost reduction in the

Page 57: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

45

process of implementing various procurement activities, as reported by 65.0 percent

of the respondent. 35.0 percent of the respondent said that the cost efficient is high.

Table 4. 4Cost EfficiencyVariables Frequency Percentage

High 7 35.0

Moderate 13 65.0

Low 0 0

TOTAL 20 100

Source: Survey data

4.1.5 Lead Time Performance

Lead time performance is the area of procurement process efficiency

implementation. From the study it was found that 55.0 percent of the respondents

agreed that the procurement process has reduced lead time at the Temeke municipal

council. But 35.0 percent of the respondents disagree that the procurement process

reduce lead time while 15.0 percent of the respondents strongly agree that the

procurement process reduces lead time.

Table 4. 5 Lead Time PerformanceVariables Frequency Percentage

Strongly Agree 3 15.1

Agree 11 55.0

Neutral 0 0

Disagree 6 30.0

Strongly disagree 0 0.0

TOTAL 20 100

Source: Survey data

Page 58: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

46

4.2 Best Procurement Method

4.2.1 Procurement methods Used

The respondents were exposed to two procurement methods which are regularly used

at Temeke Municipal Council. These are Quotation and Tender methods. They were

requested to indicate which one among the two is the best in procurement based on

the experience.80.0 percent of the respondent reported tendering to be the best

method while only 20.0 percent of the respondents choose quotation as the preferred

method in procurement process.

Table 4. 6Best Procurement methodVariables Frequency Percentage

Tender 16 80.0

Quotation 4 20.0

TOTAL 20 100

Source: Survey data

4.2.2 Processing Speed

In the procurement process, speed is very important. Speed can help to satisfy

customers on one hand and can assist timely implementation of different activities,

programs and projects of the Municipal council. However, the results show that with

the tendering method speed is moderate as reported by 70.0 percent of the

respondents, while 20.0 percent and 10.0 percent of the respondents said the speed is

high and low respectively. In the case of quotation method of procurement, speed

was found to be high as reported by 75.0 percent of the respondent where as 25.0

percent of the respondents said that the speed is moderate.

Page 59: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

47

Table 4.7 Processing SpeedHigh Moderate Low

Tender Frequency 4 14 2

Percentage 20.0 70.0 10.0

Quotation Frequency 15 5 0

Percentage 75.0 25.0 0

Source: Survey data

4.2.3 Effectiveness of processing criteriaThe study found that processing criteria are effective as reported by 95.0 percent of

the respondent where as 5.0 percent of the respondent reported that the processing

criteria are not effective. From those results it shows that the set criteria for

procurement process at Temeke Municipal Council are good. Thus, based on the

criteria available the procurement process can be effectively conducted.

Table 4. 8 Processing Criteria EffectivenessVariables Frequency Percentage

Yes 19 95.0

No 1 5.0

Total 20 100

Source: Survey data

4.2.4 Effectiveness of Tendering Method75.0 percent of the respondents show that the tendering method is effective where as

15.0 percent of the respondent said the tendering method is moderate. But 10.0

percent of the respondent said tendering method as conducted at the municipal

council is very effective.

Page 60: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

48

Table 4. 9 Effectiveness of Tendering MethodVariables Frequency Percentage

Very effective 2 10.0

Effective 15 75.0

Moderate 3 15.0

Ineffective 0 0

Very ineffective 0 0

TOTAL 20 100

Source: Survey data

4.2.5 Effectiveness of Quotation methodIn the case of quotation method as applied at Temeke Municipal Council, it was

found that 55.0 percent of the respondents said the effectiveness of quotation method

is moderate. 20.0 percent of the respondents said it is effective and 15.0 percent of

the respondents said it is ineffective. 10.0 percent of the respondent said the

application of quotation method is very ineffective where as 5.0 percent of the

respondent said is very effective.

Table 4.10Effectiveness of Quotation MethodVariables Frequency Percentage

Very Effective 1 5.0

Effective 4 20.0

Moderate 10 50.0

Ineffective 3 15.0

Very ineffective 2 10.0

TOTAL 20 100

Source: Survey data

Page 61: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

49

4.3 Personnel Performance

4.3.1 Performance of Procurement PersonnelThe results show that 60.0 percent of the respondent reported that performance of

procurement personnel is good while 40.0 percent of the respondent reported the

performance of the procurement personnel was better.

Table 4. 11 Performance of Procurement PersonnelVariables Frequency Percentage

Better 8 40.0

Good 12 60.0

Poor 0 0

TOTAL 20 100

Source: Survey data

4.3.2 Information Coordination PerformanceInformation coordination is one of the important factors in the whole process of

procurement. When coordination is well conducted, procurement can thus be

conducted effectively, the performance on information coordination as reported by

the respondents show that 65.0 percent of the respondents said it is good, 30.0

percent of the respondents said it is better and 5.0 percent of the respondent said it is

poor.

Table 4. 12 Information Coordination ProcessVariables Frequency Percentage

Better 6 30.0

Good 3 65.0

Poor 1 5.0

TOTAL 20 100

Source: Survey data

Page 62: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

50

4.3.3Decision making in the Procurement ProcessAnother area of procurement performance is decision making. Timely and proper

decisions are key indicators to the effective procurement process. The decision

making plays a great role in facilitating the performance of the procurement process.

The results show 100percent (all respondents) said there is a proper decision making.

Table 4.13Decision making PerformanceVariables Frequency Percentage

Yes 20 100

No 0 0

TOTAL 20 100

Source: Survey data

4.4 Problem Facing the Procurement Management

4.4.1 Bureaucracy

Bureaucracy is one of the mentioned problems in the procurement process at theMunicipal Council. It was found that bureaucracy affects procurement performanceand management performance since it creates unnecessary difficulties especiallywhen documents need to be signed for further process. It was also discovered thatdelegation in procurement activities is not widely done. On the other hand it was saidthat the problem appears in the form of decision making. Some officers do not makeproper decisions as required. As a result of all these, the performance of procurementbecomes low because of unnecessary delays which then affect the implementation ofother activities.

4.4.2 Lack of proper knowledge, skills and capacity

Adequate capacity in the form of appropriate structures with fully skilled and professional

procurement personnel is a key success factor for effective procurement process

implementation. However, in the case of Temeke Municipal Council, lack of proper

knowledge, skills and capacity was found to be a problem. It was said that therelack

Page 63: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

51

of profession skills in tender and evaluation. For this reason tender processing has

been sometimes ineffectively implemented.

4.4.3 Lack of Capacity Building in Public Procurement Act and Regulation

In addition to the stated above problems, there is a low capacity building in areas of

public procurement act and regulation. Most of the employees used to work on

customary bases. This is because, apart from establishment of new laws and

regulations in order to build awareness and application abilities, little has been done.

As a result some of employees become weak in preparing and processing

procurement activities, although they have to do them as part of their studies.

4.4.4 Poor Specifications

It was reported also there is a problem of poor specification of materials or

documents in the Municipal Council. Contradictions have been occurring in this

process. Specifications were named as causing difficulties in determining right

documents and materials. Moreover, it was learned that due to poor specifications,

there are loss occurrence because of purchasing or supplying unrelated materials. For

instance the supply of poor quality material or unrelated materials, cost the

Municipal Council to either purchase new materials or use them within a short period

of time.

4.4.5 Delay in Payments

The problem of delay was named as most paining one. Delays were found in the

document processing, decision making and delivery of materials. It was learned that

most of the time delays occurs only because of being busy for other activities.

However, decision making was the most factor causing procurement process delays

rather than other factors. Moreover, sometimes work load and inadequate personnel

have been leading to the delays.

Page 64: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

52

4.4.6 Taking Too Long to Take Decision

As it has been pointed above decision making has been a problem in a procurement

process effectiveness at Temeke Municipal Council. Generally, the respondents

reported that senior officers have a tendency of making late decisions on account of

having many procurement activities within a short period of time. They are very

occupied therefore they cannot read and make timely decisions as required.

However, although some of these senior officers can delegate such duties to their

subordinates, they always don’t do that. The effects of all these is poor performance

of procurement process.

4:4:7 Non-compliance with policies and regulationsCompliance with Procurement policies and regulations was also found to be a

problem at the Municipal Council, some of the practices relating to non-compliance

with rules and procedures such as: the tendency not to utilize a competitive process

for both quotations and bids, and incorrect utilization of the preference points

system, use of unqualified suppliers, passing over of bids for incorrect reasons;

utilization of the incorrect procurement process in respect of the thresholds;

extensions of validity periods; and incorrect utilization of the limited bidding process

were observed.

4.4.8 Improper planning and linking demand to the budgetIt was also reported that: there is a problem of improper planning and linking

demand to budget at Temeke Municipal Council. Planning and demand management

is integral to the procurement process. It actually defines the decision-making

process that allows departments to procure at the right time, at the right place and at

the right cost but Temeke Municipal Council is still faced with this challenge of

improper planning and linking demand to budget.

4.4.9 Inadequate measures for monitoring and evaluationIt was also reported that there was inadequate measures for monitoring and

evaluation systems. Inadequate monitoring and evaluation is normally linked to the

Page 65: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

53

absence or the poor presence of a control environment, and the government entities

are placed in a difficult position to give effect to or implement SCM as required by

the policy. Hence, deviations or non-compliance goes undetected or is identified after

the fact

Page 66: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

54

CHAPTER FIVE

DISCUSSIONS

5.1 IntroductionThis chapter undertakes discussions of the findings which have been reported in

chapter four. It tries to make linkage of different matters as presented before. But the

discussion is based on the objectives of the study.

5.2 Effectiveness of Procurement ProcessThe study wanted to understand the procurement process effectiveness. The purpose

of examining the procurement process effectiveness was to discover the real situation

at the Temeke Municipal Council, whether the procurement process is properly

conducted. Several issues have been examined and their results presented in chapter

four.

One of the areas showing effectiveness of procurement process is employees’

participation in the whole or part of the procurement process. The results showed that

all respondents which is equivalent to 100 percent of the respondents reported to

participate in the procurement process. This is a good indication that procurement

process is effectively conducted.

Although there is good participation in procurement process, the employees have

been facing difficulties in conducting it as it was reported by 100 percent of the

respondent. It was found that some of the difficulties appear in the form of decision

making, compliance of procurement procedures, inadequate and untimely

presentation of information and inadequate knowledge on procurement activities. All

these issues have been affecting the procurement process especially during tender

preparation and evaluation. There are difficulties in evaluating the submitted tender

documents as per criteria. This is due to technical documents presented where by

some employees lack such knowledge to determine proper and qualified documents.

However, apart from all these, the general results show that there is effective

Page 67: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

55

procurement process at the Municipal Council as reported by 55.0 Percent of the

respondents.

The effectiveness of procurement process was viewed also against cost efficiency. It

was assumed that cost efficiency in procurement is directly related to the way

procurement activities are undertaken. If the activities associated with procurement

are well considered the cost can be minimized and therefore it is possible to think

that the procurement process is effective, otherwise the vice versa can take part. The

evidence from the study shows that, as reported by 65.0 percent of the respondents,

cost efficiency is moderate. Based on this fact, the procurement at the Municipal

Council is not effective in the sense that there are some loopholes that causes further

expenses during the procurement process.

With moderate cost efficiency, it means that there are added costs whether

intentionally or un intentionally which ultimately affects the government budget.

Furthermore; the procurement process is associated with lead time. The effectiveness

in lead time signifies the better performance of the procurement process. However,

the study found that 55.0 percent of the respondents agree that the procurement has

reduced lead time at Temeke Municipal Council.

5.3 Best Procurement Method and its Effectiveness

The study aimed at determining the best method of procurement process and how

effective it was. Two methods were compered thus tendering and quotation method.

When asked to state which among the two is most effective 80.0 percent of the

respondents said tendering process is the best method than quotation. It was learned

that for the Municipal’s procurement activities to be effectively conducted should use

tendering method. It ensures perfect and proper way of purchasing government

materials or services as well as help minimizing public funds misuse. However, the

results show that with the tendering method, speed is moderate as reported by 70.0

percent of the respondents. Since processing speed is moderate it reflects that the

performance of tendering method is moderate from speed respective.

Page 68: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

56

Tendering depends on specific criteria for assessment and selection of winners as set

by the Procurement Act 2004. The study found that processing criteria are effective

as reported by 100 percent of the respondents whereas none of the respondent

reported the processing criteria to be not effective. These results indicate that the

criteria are actually good, though their application may be inefficient in some of the

areas. But in the case of quotation, it was said that, the criteria are not good at all

because the decision for procurement remains to the few who may decide for the

organization. Therefore, the quotation is mostly leading to loss of public funds and

misuse.

Under this situation 75.0 percent of the respondents show that the tendering method

is effective. In the case of quotation method as applied in the Municipal, it was found

that 55.0 percent of the respondent said that the effectiveness of quotation method is

moderate. The results are due to the nature of methods application and the end

results. Respondents weighed the performance of these methods based on the

archiving quality materials or services and the management of public funds.

In reality the personnel were found to have good performance. The results showed

that 60.0 percent of the respondents reported that there is good performance of the

procurement personnel. Employees were found to conduct their duties in accordance

to the profession.

In addition to the information in procurement activities is very important and key to

the procurement effectiveness. The performance of the information coordination as

reported by the respondents it shows that 65.0 percent said it is good. Together with

information and personnel, decision making is the area of importance. The results

show that 60.0 percent of the respondents said the decision making in the

procurement management is proper. Thus, the performance of procurement process

is good because of proper decision making during the process from the preparations

and implementation.

Page 69: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

57

5.4 Procurement Process ProblemsSome of the listed procurement difficulties involve; preparation of tender documents

and evaluation, bureaucracy, there are many such as poor specifications, delays in

procurement process, inadequate knowledge in procurement processing, procurement

takes long time, and payments are not done at right time.

The sustainability of Public Procurement Act No.3 2004 is at risk because there is

not a clear understanding as to its full potential as a financial and budgetary control

mechanism. The risk is increased due to stated problems, for instance bureaucracy

has undermined the procurement process where as commitment to the managing it

has been low. The tendency of most seniors’ authorizers has been working under

personal motives rather than stated guidelines.

Page 70: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

58

CHAPTER SIX

SUMMARY, CONCLUSION AND RECOMMENDATIONS

6.1 IntroductionThis chapter presents the conclusion and recommendations of the study. These are

based on the findings of the study.

6.2 SummaryThe overall objective of the study was to examine the procurement process

effectiveness in the public sector, a case of Temeke Municipal Council. Specifically,

to examine the effectiveness of procurement process at Temeke Municipal Council.,

to identify the best procuring method at the Municipal Council and to identify the

problem facing the procurement management unit and procurement department at

Temeke Municipal Council.

The research design used was the case study. Types of data used were primary and

secondary data. The tools used for data collection were questionnaire and interview.

Samples for the study were 20 respondents. A purposive sampling technique which is

a non-probability or judgmental sampling procedure was used to determine the

sample units. Data analysis was done manually.

The study findings are put under the study objectives.

The first objective of the study covered the effectiveness of procurement process.

Several matters were examined. First: personnel participation in the procurement

process and results show that 100 percent of the respondents reported to participate

in the procurement process. Second: difficulties in procurement process and results

show that there are difficulties faced in procurement process as reported by 100

percent of the respondents. Third: effectiveness of procurement process and results

show that procurement process is effective as reported by 55.0 percent of the

Page 71: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

59

respondents. Fourthly: cost efficiency, results show that there is moderate cost

reduction in the process of implementing various procurement activities as reported

by 65.0 percent of the respondent. Fifth: lead time performance, it was found that

55.0 percent of the respondent agree that procurement process has reduced lead time

at Temeke Municipal Council. Sixth: performance of procurement personnel, the

results shows that 60.0 percent of the respondents reported that there is good

performance of procurement personnel. Seventh: information coordination

performance, the performance of the information coordination as reported by 65.0

percent of the respondent is good. Eighth and finally: decision making in

procurement process, the results show 60.0 percent of the respondent said the

performance decision making in procurement is proper.

The second objective covered the best procurement methods as preferred by

procurement personnel and its effectiveness. Several matters were examined. First:

the best method of procurement and 80.0 percent of the respondents said tendering is

the best method. Second: processing speed, results show that with the tendering

method speed is moderate as reported by70.0 percent of the respondent. Third:

effectiveness of processing criteria, the study found that processing criteria are

effective as reported by 100 percent. Fourth: effectiveness of tendering method and

75.0 percent of the respondents reported that the tendering method is effective. Fifth:

effectiveness of quotation method, it was found that 55.0 percent of the respondent

reported that the effectiveness of quotation is moderate.

The third objective covered problems facing procurement process. The following

problems were found; bureaucracy, lack of knowledge, lack of capacity building in

procurement act and regulations, poor specifications, delays in payment, and taking

too long to make decision.

6.3 ConclusionThe conclusions are made against research questions. Therefore, these are the

answers for those research questions.

Page 72: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

60

One of the questions was ‘to what extent is procurement process effective at Temeke

Municipal Council. The findings show the following: 100 percent of the respondents

reported to participate in the procurement process. Although the employees have

been facing some difficulties in the procurement process as reported by all the

respondent (100 percent), but general results show that there is effective procurement

process at the Municipal Council as reported by 55.0 percent of the respondent. The

evidence from the study shows that, as reported by 65.0 percent of the respondent,

cost efficient is moderate while 55.0 percent of the respondents agree that the

procurement process has reduced lad time. The results show that 60.0 percent of

respondent reported that there is good performance of procurement personnel. The

performance of the information coordination as reported it shows that 65.0 percent of

the respondent said is good and 65.0 percent of the respondent reported that the

performance decision making in procurement is proper.

Conclusion: It is concluded that procurement process is effective at Temeke

Municipal Council.

Another question was ‘which is the best procurement method at Temeke Municipal

Council and how effective it is. The findings show the following. When asked to

state which among the two methods is most effective, 80.0 percent of the respondents

reported tendering is the best method comparing to quotation. The results show that

with the tendering method, speed is moderate as reported by 70.0 percent of the

respondents but processing criteria are effective as reported by 100 percent of

respondents and 75.0 percent of the respondents show that the tendering process is

effective. In the case of quotation method as applied in Temeke Municipal Council, it

was found that 55.0 percent of the respondent said the effectiveness is moderate.

Conclusion: It is concluded that the tendering method is the best in the procurement

process at Temeke Municipal Councel and it is effective.

The final question was ‘what were the problems faced by procurement personnel

during the whole process of procurement at Temeke Municipal Council? The

Page 73: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

61

findings show the following: bureaucracy, poor specifications, delay in procurement

process, are some of the problem affecting procurement performance. There were

many others such as procurement process takes longtime, payments are not done at

right time, lack of knowledge and lack of capacity building in procurement act and

regulations.

Conclusion: It is concluded that, there are several problems that affect the

performance of procurement process at Temeke Municipal Council.

6.4 RecommendationsThere are a number of issues that could be considered in order to enhance

procurement process in public sector specifically at Temeke Municipal Council. The

researcher has addressed the following recommendations in order to improve the

situation:-

Training to procurement staffs and Tender Board members

The organization should ensure that workers especially in PMU and Tender Board

are well trained by taking key persons to further training to increase their knowledge

and competencies on procurement process in general. Also Tender Board members

who are selected from heads of various departments should attend short courses and

seminars in order to know their responsibilities in tender process and procurement in

general. Against this background, it is evident that public procurement practitioners

require specific knowledge about the procurement objective, SCM policy, preference

procurement policies and so forth in order to manage the procurement process

effectively. Specialised training programmes are therefore required to equip actors

with the skills to achieve procurement objectives.

Key issues such as employment of qualified procurement practitioners, training and

employment of learnership programmes, development of an effective monitoring and

evaluation tool, and the creation of incentive programmes to motivate good

performance should be employed.

Page 74: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

62

In addition, institutions of higher learning and other service providers should equip

learners and practitioners with appropriate skills and knowledge through the

development of a syllabus that ensures sustainable procurement in Tanzania.

Number of employees should be increased

Staffs in PMU are not enough and competent to handle all activities of procurement

as required. The organization should ensure that it employs competent and skilled

people who can handle procurement activities and if happen can perform contract

management activities. It should employ people with skills in contract, laws and

negotiations.

Transparent and accountable systems

Accountability constitutes a central pillar to public procurement. Without transparent

and accountable systems, the vast resources channeled through public procurement

systems run the danger of being entangled with increased corruption and misuse of

funds.

To fight the scourge of maladministration, mismanagement of finances, fraud and

corruption, government needs to strengthen and review existing internal control

systems to detect deficiencies.

Compliance with policies and regulations

Procurement process is guided by a number of related policies and regulations. It is

very important for the procurement staffs to comply with the policies and regulations

in order to enhance the whole process of procurement.

Effective policy-making requires information on whether governments are doing

things right and whether they achieve the results intended. Strong monitoring and

evaluation systems provide the means to compile and integrate this valuable

information into the policy cycle, thus providing the basis for sound governance and

accountable public policies.

Page 75: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

63

6.5 Recommendations for Further Studies

The study reviewed that there a lot of external factors affecting the procurement

process. To this end therefore a further study should be carried to establish external

factors affecting procurement process of supplies in the public sector. Moreover, a

study should also be carried out to establish the challenges faced while carrying out

procurement process of supplies in the public sector.

Page 76: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

64

REFERENCES

Arrowsmith, S; Linarelli j and Wallace D jr (2000), Regulating Public Procurement:

National and International Perspectives, Kluwer Law International.

Bailey Peter; Farmer David; Crocker Barry; Jessop David (2008), Procurement

Principles and Management, 10th Edition, Prentice Hall, London.

Bally P. H. (1999), Purchasing and Supply Management, 4th Edition

Corcoran J McLean F. (1998), The Selection of Management Consultants, How are

Governments Dealing with this Difficult Decision? An exploratory

study, International Journal of Public Sector Management, Vol. 11

No.1, pp. 37-54

Cousins Paul; Lamming Richard; Lawson Benn; and Squire Brian (2008), Strategic

Supply Management, Principles, Theories and Practice, Prentice Hall,

London

Gershon p. (2003), Releasing Resources to the Front Line: Independent Review of

Public Sector Efficiency, the Stationary Office, London.

James U.V (2004), Public Policy and the African Environment: An Examination of

the Theory and Practical of the planning process of the continent, In

Kalu, A.K. (E.D) Agenda Setting and Public Policy in Africa;

Ashagte, England

Johnson G. (2002), Exploring Corporate Strategy (3rd Edition), Hemel Hempstead,

UK: Prentice Hall

Jones M. O’Brien v. (2002), Best Practice in Social Housing Development, Thomas

Telford, and London.

Page 77: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

65

Kabaj O. (2003), the Challenge of African Development, Oxford University Press

Kothari C.R. (2006). Research methodology: Methods & techniques India: New Age

International Publishers.

Love Peter E. D; Davis, Peter R, and Edwards, David J. (2008), Uncertainty

avoidance: public sector clients and procurement selection,

International Journal of Public Sector Management, Vol. 21 No 7 pp.

753-776

Morris Stephen (2003), Purchasing Principals and Management: 4th Edition.

Murray J.G. (2007), “Strategic Procurement in UK Local Government: The Role of

Elected Members.” Journal of Public Procurement, 7(2): 194-212

Naegelen F. and Mougeot M. (1998), Discriminatory Public Procurement Policy and

Cost Reduction Incentives, Journal of Public Economic 67(1998) pp.

349-367

Otieno (2004). Procurement activities in public institutions. Unpublished thesis.

Jomo Kenyatta University of Science and Technology, Kenya

Phillips S, Martin J, Dainty A, Price A.D.F. (2007), Uncertainty in best value

decision making Journal of Financial Management of Property and

Construction, Vol. 12 No. 2, pp. 63-72

Pooler David J. (1999), Purchasing and Supply Management Published by University

of Michigan, Michigan.

Poterba D. (2001), Speculative Dynamics, Review of Review of Economics Studies

58.

Page 78: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

66

Pourbaix N. (2004), the New Public Procurement Directives of the European Union,

Business Law Review, No. November, pp. 202-205

PPRA (2007), Assessment of the country’s Procurement System, Final Report,

September 2007

Romano (2000), Supply Chain Management: Europe Journal of purchasing, Volume

6

Saunders Mark, Phillip Lewis, Thornhill, Adrian (2007), Research Methods for

Business Studies, Fourth Edition, Prentice Hall, London

Shoshanna (2004), Strategic Supply Chain Management, Published by Springer,

London

Soudry O. (2007), A Principal-Agent Analysis of Accountability in Public

Procurement, In Piga, P. & Thai, K.V. (Eds), Advancing Public

Procurement: Practices, Innovation and Knowledge-sharing, (pp. 432-

451). Boca Raton, FL: Pr Academics Press.

Thai K.V. (2004) Introduction to Public Procurement, First Edition, Florida Atlantic

University

Thai, K.V. (2001). "Public procurement re-examined", Journal of Public

Procurement, Vol. 1 No.1, pp.9-50.

Therkildsen O. (2001), Efficiency, Accountability and Implementation: Public sector

Reform in East and Southern Africa; Democracy, Governance and

Human rights programmed paper Number 3, February 2001

URT (2003), Tanzania Country Procurement Report (CPAR) Executive Summary

April 30, 2003

Page 79: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

67

URT (2004), the Public Procurement Act, 2004 and the Public Procurement

Regulations, 2005

Waters D. (2004). Introduction To Supply Chain Management, (2rd Edition), Pal

grave Macmillan, Britain

Wimmer S. J. (2003), Purchasers strike a balance with best value Procurement,

Government Procurement, August, pp. 6-9

World Bank (2000), Can Africa Claim the twenty first century? The World Bank,

Washington D.C

World Bank (2006), World Bank Procurement Guideline, Guidelines Procurement

Under IBRD Loans and IDA Credits, Revised October 2006

Page 80: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

68

APPENDEX

Dear Respondents

The researcher is carrying out “the research on the effectiveness of public

procurement process in public sector”. These are research questions; you are kindly

requested to answer the questions so as to make her research successful.

PERSONAL QUESTIONS

1. What is your profession? ...................................................................................

2. What is your position held? ...............................................................................

3. What level of education?

(i) Certificate

(ii) Diploma

(iii) Degree

(iv) Postgraduate

General Questions

4. Do you participate in the procurement processing?

(i) Yes

(ii) No

5. Are you experiencing difficulties in public Procurement Processing?

(i) Yes

(ii) No

If yes, what are they?

…………………………………………………………………………………

Page 81: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

69

6. How effective are procurement procedures followed?

(i) Very effective

(ii) Effective

(iii) Moderate

(iv) Ineffective

(v) Very Ineffective

7. Do you think that the procurement procession reduce costs?

(i) Yes

(ii) No

8. To what extent is the procurement process is cost effective.

(i) High

(ii) Moderate

(iii) Low

9. Procurement process has reduced lead time. Agree or Disagree.

(i) Strongly Agree

(ii) Agree

(iii) Neutral

(iv) Disagree

(v) Strongly Disagree

10. What do you think is the best method of procuring among the two?

(i) Tender

(ii) Quotation

(iii)

11. How is the processing speed in the two procurement methods? Tick where

appropriate.

High Moderate LowTenderQuotation

Page 82: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

70

High Moderate LowTenderQuotation

How accuracy of documentation in the procurement methods? Tick where

appropriate

13. Are the procurement criteria effective?

(i) Yes

(ii) No

14 Is the quality criteria contribute into getting of qualified suppliers?

(i) Yes

(ii) No

16. To what extent does tendering method is effective?

(i) Very effective

(ii) Effective

(iii) Moderate

(iv) Ineffective

(v) Very Ineffective

17. To what extent does quotation method is effective?

(i) Very effective

(ii) Effective

(iii) Moderate

(iv) Ineffective

(v) Very Ineffective

18. Do you have adequate procurement personnel in your department?

(i) Yes

(ii) No

Page 83: ASSESSMENT OF EFFECTIVENESS OF PROCUREMENT PROCESS …

71

19 Is there any relationship between procurement performance and available

personnel?

(i) Yes

(ii) No

20. How is the performance of procurement personnel at the Municipal?

(i) Better

(ii) Good

(iii) Poor

21. How is the information coordination performance for procurement

management?

(i) Better

(ii) Good

(iii) Poor

22. Is the management provides proper decision making in the procurement

process?

(i) What are the Yes

(ii) No

23. Problems affecting the effectiveness of public procurement?

…………………………………………………………………………………

…………………………………………………………………..

THANK YOU FOR YOUR KINDNESS