Energy Community SecretariatEnergy Community Secretariat 1
ECS
Assessing adequacy in WB6
Energy Community SecretariatEnergy Community Secretariat 2
TA under WB6 x-border balancing
1. Assessment of national balancing markets of beneficiary countries
2. Assessment of impact of existing Control Blocks on balancing market cooperation
3. Models of regional cooperation for balancing energy – Exchange of balancing energy
4. Models of regional cooperation for balancing energy – Imbalance netting
5. Development of a roadmap towards a regional/European balancing cooperation/market
Launched end of 2017 – completed (final fine tuning)
Energy Community SecretariatEnergy Community Secretariat 3
GLEB => into EnC
Electricity BalancingGuidelines (GLEB)
Adopted December 2018
Process Proposal by TSOs
Status Platform to be ready
Hostplatform/project
WB6 XBB project:
Targetmodel
Demo platform
Imbalance Netting
Nov2017
submitted to ACER and EC (Jun18)
End 2019 IGCC IN IN platform
Exchange of aFRR
March 2018
public consultation
End 2021 PICASSO
/ /
Exchange of mFRR
May 2018
public consultation
End 2021 MARI mFRRmFRR & RR platformExchange
of RRJune 2018
submitted to ACER and EC (Jun18)
End 2019 TERRE RR
Energy Community SecretariatEnergy Community Secretariat4
Existing initiatives - IGCC
• The International Grid Control Cooperation (IGCC)
• Reference project for Imbalance Netting platform – advanced initiative
• Optimizes the use of FRR (avoids the use in opposite direction)
• Multilateral TSO-TSO model
Energy Community SecretariatEnergy Community Secretariat5
Existing initiatives - MARI
• Manually Activated Reserves Initiative (MARI)
• Reference project for mFRR platform
• Dimensioning of mFRR – local responsibility in line with GLEB
• Integration of balancing energy markets for mFRR is in the focus
• Multilateral TSO-TSO model with cross-border marginal price (principle similar to day ahead market) – an auction per 15min. blocks
Energy Community SecretariatEnergy Community Secretariat6
Existing initiatives - TERRE
• Trans European Replacement Reserves Exchange (TERRE)
• Reference project for RR platform – advanced initiative
• Dimensioning of mFRR – local responsibility in line with GLEB
• Multilateral TSO-TSO model with cross-border marginal price
• Scheduled activation (30min full activation time)
• 15min blocks; one auction per hour
Energy Community SecretariatEnergy Community Secretariat 7
IN savings in WB6
Energy Community SecretariatEnergy Community Secretariat 8
IN recommendation
• Imbalance Netting is beneficial in any conditions
• Larger the IN area is, benefits are larger
• NOS BiH reported plans to join INC (AT, SI, HR), being the member of SHB block
• EMS already non-operating member of IGCC
• Since CGES already in dry runs with EMS, pre-netting within IGCC can be well permanent solution
• As well as with MEPSO (being part of SMM block), when ready
• Other TSOs to join whenever ready
Energy Community SecretariatEnergy Community Secretariat 9
mFRR and RR recommendation
• The proposal for the exchange of mFRR and RR in the Western Balkans is also based on the TSO-TSO model.
• activations of Balancing Service Providers (BSPs) of both mFRR and RR energy in another area of responsibility are realized through the connecting TSO.
• The conducted dry runs based on the recorded data (activations, bids, prices), provide tentative estimation of annual benefits at a level of EUR 4.3 million per year, from introduction of mFRR & RR cooperation in the WB6 region
• Objective; joining EU platforms
• Intermediate step – WB6 early implementation
Energy Community SecretariatEnergy Community Secretariat 10
www.energy-community.org
Thank you!