Global Project News (Asia): July’ 2018 PROJECT EXPORTS PROMOTION COUNCIL OF INDIA Update: July’ 2018 Vol. 121 Focus Market by Satpreet Kaur PROJECT EXPORTS PROMOTION COUNCIL OF INDIA (Set up by Ministry of Commerce & Industry, Government of India) 1112 Arunachal Building, 19 Barakhamba Road, New Delhi Tel.:+91-11-41563287, 41514673, 41514284 E-mail: [email protected] ; [email protected] Web-site: www.projectexports.com 0

Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

  • Upload
    leminh

  • View
    214

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

PROJECT EXPORTS PROMOTION COUNCIL OF INDIA

Update: July’ 2018

Vol. 121

Focus Market

by

Satpreet Kaur

PROJECT EXPORTS PROMOTION COUNCIL OF INDIA

(Set up by Ministry of Commerce & Industry, Government of India)

1112 Arunachal Building, 19 Barakhamba Road, New DelhiTel.:+91-11-41563287, 41514673, 41514284

E-mail: [email protected]; [email protected]: www.projectexports.com

0

Page 2: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

INDEX

Tenders

Project Country Dead Line Page no.

Water/ Irrigation

Construction of 02 nos Boat Landing Station in Amtali Pourashava, District: Barguna

Bangladesh 14 August 2018 3

Khujand Water Supply Improvement Programme (Phase III) Tajikistan 30 August 2018 4

Social Infrastructure

Construction of 3600m RCC Drainage system from Mora Gorai to Trimohoni Mohr along Right side Ch.000- 3600m under Kushtia Pourashava

Bangladesh 13 August 2018 e-tender

7

Construction of Municipal Market Two Storied Building with Five Storied Foundation at Kishoreganj Pourashava

Bangladesh 07 August 2018 e-tender

9

Secondary Cities Development Project: Construction of Dien Bien Phu road (section from Km6+309.8 to Km8+106.2)

Vietnam 27 July 2018 10

Energy

Raghuganga Hydropower Limited Rahughat Hydroelectrtc Project (40 MW) Lot 2: Electro-Mechanical Works Contract

Nepal 06 September 2018

12

Design, Supply, Installation and Commissioning of New Butwal- Bardghat 220 kV Double Circuit Transmission Line

Nepal 13 August 2018 15

Procurement of Plant, Design, Supply, Installation, Testing and Commissioning of the Refurbishment of Rouna 1 & Sirinumu Hydropower Plants

Papua New Guinea

15 August 2018 17

Procurement of Lot A2 – Main Civil Works for Green Power Development and Energy Efficiency Improvement Investment Program - Tranche 1

Sri Lanka 22 August 2018 19

Kostanay District Heating: Construction of DN 500 interconnection pipeline

Kazakhstan 21 August 2018 22

Consultancy

Enguri Hydro Power Plant Rehabilitation Project - Maintenance Audit

Bangladesh 02 August 2018 24

Annual maintenance audit on the Enguri and Vardnili Georgia 26 September 26

1

Page 3: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

hydropower scheme 2018

Enguri Hydro Power Plant Rehabilitation Project –Climate Resilience Upgrade

Georgia 14 August 2018 28

News Items

Malaysia seeks 'drastic' price cut in $20 bn China backed rail link project 31

343 infra projects show cost overrun of Rs 2.16 trn over delays: Report 31

Asian Infra Investment Bank to pump in $1.9 bn into various Indian projects 32

2

Page 4: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

Construction of 02 nos Boat Landing Station in Amtali Pourashava, District: Barguna

Invitation for Bids – Rebidding

1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project (CTEIP). Part of this financing will be used for payments under the contract named above. Bidding is open to Bidders from eligible source countries of the ADB.

2. The Amtali Pourashava, District: Barguna, ("the Employer") invites online bids/tenders from eligible Bidders for the Construction of 02 nos Boat Landing Station in Amtali Pourashava ("the Works").

3. National competitive bidding will be conducted in compliance with ADB's Procurement Guidelines through electronic Government Procurement (e-GP) system and is open to all Bidders from eligible countries as described in the Bidding Documents.

4. Only eligible Bidders with the following key qualifications should participate in this bidding:

• Specific Similar Experience: at least one contract within the last 5 (five) years where the value of the Bidder’s participation exceeds BDT 10.00 million.

• Average Annual Construction Turnover: minimum BDT 13.00 million over the last 5 (five) years

• Liquid Assets or Credit Facilities: minimum BDT 1.86 million More details of qualification requirements are mentioned in the biding documents

5. This is an online bidding where only e-Tender (e-bid) will be accepted in the Bangladesh National e-GP System Portal and no offline/hard copies will be accepted. To obtain further information and to submit e-Tender for this works package bearing e-tender ID no. mentioned above, registration in the e-GP portal (http://www.eprocure.gov.bd) is required.

3

Project ID No. e-GP/CTEIP/2017-18/AMT/BLS-01Project Name: Coastal Towns Environmental Infrastructure Project Country: BangladeshDescription: Construction of 02 nos Boat Landing Station in Amtali Pourashava,

District: Barguna

Funding agency: Asian Development Bank (ADB)Last date of bid submission: 14 August 2018, 14:00 hours (Bangladesh Standard Time)

Address for bid submission: Attention: Executive Engineer Amtali Pourashava, Barguna Telephone: +880 4452 56191 Fax: +880 4452 56195 Email: [email protected]

Page 5: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

6. The fees for downloading the e-Tender Documents from the e-GP portal, and the tender security as mentioned in the documents have to be deposited online through any branch of the banks registered in the e-GP system.

7. The deadline for submission of e-Tenders (bids) is on 14 August 2018, 14:00 hours Bangladesh Standard Time (BST), and online opening will be done on the same date at 14:00 hours BST.

8. Further information and guidelines are available in the e-GP portal and from e-GP help desk ([email protected]). To obtain further information, please contact the official inviting the tender as follows: Attention: Executive Engineer Amtali Pourashava, Barguna Telephone: +880 4452 56191 Fax: +880 4452 56195 Email: [email protected]

Khujand Water Supply Improvement Programme (Phase III)

This Invitation for Tenders follows the General Procurement Notice for this project which was published inProcurement Opportunities at www.ebrd.com on 22 September 2017.

Khujand Water Company (Khujandvodokanal), hereinafter referred to as “the Employer”, intends using part of the proceeds of a loan from the European Bank for Reconstruction and Development (the Bank) and grant from State Secretariat for Economic Affairs SECO towards the cost of Khujand Water Supply Improvement Programme (Phase III).

The Employer now invites sealed tenders from contractors for the following contract to be funded from part of the proceeds of the loan and grant:

Tender 4.2_Rehabilitation of water supply network : Khujand city water supply system:

Lot 1    Rehabilitation of water network on left Bank of Syrdaria River (approx. 10.5 km)

Lot 2    Rehabilitation of water supply network on right bank of Syrdaria River (approx. 5.0 km)

4

Project ID No. 9171-IFT-44753Project Name: Khujand Water Supply Improvement Programme (Phase III)Country: TajikistanDescription: Rehabilitation of water supply network : Khujand city water supply

system

Funding agency: EBRDLast date of bid submission: 30 August 2018

Address for bid submission: Rahmat Burhanov, Head of PIUKhujandvodokanal office,27 micro district, Khujand city, Tajikistan, 735700Tel.: +992 92 8450244,Email: [email protected]

Page 6: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

Tenders are invited for one or more lots. Time for Completion under each Lot is 365 days following with 365 days of DNP, both Lots are to be performed concurrently. Each lot must be priced separately.  Tenders for more than one lot may offer discounts and such discounts will be considered in the comparison of tenders.

To be qualified for the award of a contract(s), tenderers must satisfy the following minimum criteria:

1. The tenderer shall have an average annual turnover as prime contractor the last 3 years (2015-2017) not less than

-USD 1,500,000- for Lot 1 equivalent

-USD 600,000- for Lot 2 equivalent

2. The Tenderer shall demonstrate that it has access to, or has available, liquid assets, unencumbered real assets, lines of credit, and other financial means sufficient to meet the construction cash flow for a period of 4 months, estimated as not less than:

-USD 300,000 - for Lot 1

-USD 120,000 - for Lot 2

or equivalent, taking into account the applicant's commitments for other contracts.

3. Participation as contractor or management contractor in at least two (2) contracts within the last five (5) years (from 2013 to 2017), with a value of at least

- USD 600,000 for Lot 1, and

- USD 200,000 for Lot 2,

that have been successfully and substantially completed and that are similar to the proposed Works contracts. The similarity shall be based on the physical size, complexity, methods/technology or other characteristics as described in Section VI, Employer’s Requirements.

Having experience in the construction of city water supply networks in urban areas and major traffic routes, including network construction and rehabilitation, civil and earth works, delivery and installation of water pressure pipes (HDPE, ductile iron, and steel), road works and reinstatement of roads after construction and civil construction.

The tenderer or its agent will be able to carry out the supplier’s obligation on maintenance during the warranty period of the manufacturer or producer and spare parts stocking obligations prescribed in these tender documents. The tenderer has to provide the necessary certificates, licenses or letter of authorization.

4. In case the tender is submitted by JVCA, it shall meet the following qualification requirements:

a)         The JVCA must satisfy collectively all qualification criteria, for which purpose the relevant figures for each of the partners shall be added to arrive at the joint venture's total capacity. 

b)         Each partner shall meet not less than thirty percent (30%) while the lead partner shall meet not less than seventy percent (70%) of all the qualifying criteria for the turnover and the availability of the financial means.

c)         Each partner shall satisfy the requirements with regard to the soundness of the financial position and non-performance history.

5

Page 7: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

d)         The lead partner of the JVCA shall demonstrate that he acted as a main contractor [supplier] on contract(s) of similar magnitude.

Tenderers submitting tenders for more than one lot have to demonstrate that they meet cumulative requirements to average annual turnover and cash-flow of respective lots and specific experience at the highest requirement.

Tendering for contracts to be financed with the proceeds of a loan from the Bank is open to firms from all countries. The proceeds of the Bank’s loan will not be used for the purpose of any payment to persons or entities, or for any import of goods, if such payment or import is prohibited by a decision of the United Nations Security Council taken under Chapter VII of the Charter of the United Nations.

The tender shall be accompanied by a tender security. The amount and currency of the tender security is:

USD 12,000.- (twelve thousand) for Lot 1

USD 4,000.- (four thousand) for Lot 2

The tender documents will be issued upon showing the bank invoice as confirmation of payment done by tenderer for receiving tender package. The tender package is available at cost of USD 100 or equivalent in a convertible currency. For payments done in TJS, the exchange rate on the date of payment shall apply. The Khujandvodokanal Bank accounts details for payment are as below:

Beneficiary: State Communal Unitary Enterprise Khujandvodokanal (Tax ID 510001819)

BANK DETAILS FOR PAYMENT IN US DOLLARS:

Beneficiary Bank: State Saving Bank of Tajikistan “AMONATBONK”, Khujand branchAccount No. (USD) 2020 6840 2180 3422 4000SWIFT: ASSETJ22Bank Correspondent: Commerzbank AG Frankfurt/MainSWIFT: COBADEFFCorr.Acc. 4008 8655 9400 BANK DETAILS PAYMENT IN TAJIK SOMONI:Beneficiary Bank: State Saving Bank of Tajikistan “AMONATBONK”, Khujand branchAccount No. (TJS) 2020 2972 8000 3922 4000Loro account: 2040 2972 3162 64MFO: 350 101 626Upon receiving appropriate evidence of payment of the non-refundable fee, the documents will be promptly dispatched by electronically through email as PDF format. No hard copy will be sent. If tenderer prefer to have hard copy, him/her can collect it from Khujandvodokanal office at the address indicated below. In the event of discrepancy between electronic and hard copies of the documents, the hard copy shall prevail.

Tenders should be delivered to the office at the address below on or before 14.00 (local time) on 30 August 2018 at which time they will open in the presence of those tenderers’ representatives who choose to attend:

State Committee on Investment and State Property Management27 Shotemur Street, 2nd floorDushanbe, 734025, Tajikistan

6

Page 8: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

Tel: +992 37 2211573, 992 37 2218384

The applicable procurement rules are the Bank’s Procurement Policies and Rules (PP&R) which can be located at:

http://www.ebrd.com/news/publications/policies/procurement-policies-and-rules.html

A register of potential tenderers who have purchased the tender documents may inspect at the address below.

Prospective tenderers may obtain further information from, and also inspect and acquire the tender documents at the following office.

Rahmat Burhanov, Head of PIUKhujandvodokanal office,

27 micro district, Khujand city, Tajikistan, 735700Tel.: +992 92 8450244,

Email: [email protected]

Social Infrastructure

Construction of 3600m RCC Drainage system from Mora Gorai to Trimohoni Mohr along Right side Ch.000- 3600m under Kushtia Pourashava

Invitation for Bids

1. The People’s Republic of Bangladesh has received financing from the Asian Development Bank (ADB) toward the cost of Third Urban Governance and Infrastructure Improvement (Sector) Project - Additional Financing (UGIIP-III). Part of this financing will be used for payments under the contracts named above. Bidding is open to Bidders from eligible source countries of the ADB.

2. The Local Government Engineering Department (LGED, “the Employer”) invites online bids from eligible Bidders for the Construction of 3600m RCC Drainage system from Mora Gorai to Trimohoni Mohr along Right side Ch.000-3600m under Kushtia Pourashava (“the Works) as detailed below.

Package No. e-Tender ID Description of Work Duration

7

Project ID No. UGIIP-III-2/AF/KUSH/DR-02/2017Project Name: Third Urban Governance and Infrastructure Improvement (Sector)

Project (UGIIP-III)Country: BangladeshDescription: Construction of 3600m RCC Drainage system from Mora Gorai to

Trimohoni Mohr along Right side Ch.000- 3600m under Kushtia Pourashava

Funding agency: Asian Development BankLast date of bid submission: 13 August 2018; 13:00 hours (Bangladesh Standard Time) For e-Tender

ID -210585Address for bid submission: e-tender

Page 9: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

(Days)UGIIP-III2/AF/KUSH/DR-02/2017

210585 Construction of 3600m RCC Drainage system from Mora Gorai to Trimohoni Mohr along Right side Ch.000-3600m under Kushtia Pourashava.

365

3. National Competitive Bidding (NCB) will be conducted in accordance with ADB’s Procurement Guidelines through electronic Government Procurement (e-GP) system and is open to all Bidders from eligible source countries as described in the Bidding Documents.

4. Only eligible Bidders with the following key qualifications should participate in this bidding:

Specific Similar Experience: Experience in implementing a minimum of one (1) similar contract as per bid document during the last five (5) years where the value of Bidder’s participation exceeds BDT 90,000,000.00.

Average annual construction turnover: Minimum average annual construction turnover shall be greater than BDT 168, 000,000.00 over the last five (5) years.

Liquid Assets or Credit Facilities: Minimum amount of Liquid Assets or Credit Facilities shall be greater than BDT 33,000,000.00.

The qualification criteria are more completely described in the Bidding Document.

5. This is an online bidding where only e-Tender (e-bid) will be accepted in the Bangladesh National e-GP System Portal and no offline/hard copies will be accepted. To obtain further information and to submit e-Tender for this package bearing e-tender ID no. mentioned above, registration in the e-GP portal (http://www.eprocure.gov.bd) is required.

6. The fees for downloading the e-Tender Documents from the e-GP portal, and the tender security as mentioned in the documents have to be deposited online through any branch of the banks registered in the e-GP system.

7. The deadline for submission of e-Tenders (bids) is on 13 August 2018 at 13:00 hours Bangladesh Standard Time (BST) and online opening will be done on the same date at 13:00 hours Bangladesh Standard Time (BST).

8. Further information and guidelines are available in the e-GP portal and from e-GP help desk ([email protected]). To obtain further information, please contact the official inviting the tender as follows: ATTENTION: Executive Engineer Kushtia Pourashava District: Kushtia E-mail: [email protected] Mobile: 01720536444

8

Page 10: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

Construction of Municipal Market Two Storied Building with Five Storied Foundation at Kishoreganj Pourashava

Invitation for Bids

1. The People’s Republic of Bangladesh has received financing from the Asian Development Bank (ADB) toward the cost of Third Urban Governance and Infrastructure Improvement (Sector) Project - Additional Financing (UGIIP-III). Part of this financing will be used for payments under the contracts named above. Bidding is open to Bidders from eligible source countries of the ADB.

2. The Local Government Engineering Department (LGED, “the Employer”) invites online bids from eligible Bidders for the Construction of Municipal Market Two Storied Building with Five Storied Foundation (“the Works) as detailed below.

Package No. e-Tender ID Description of Work Duration (Days)

UGIIP-III2/AF/KISH/MF/01/2017

209393 Construction of Municipal Market Two Storied Building with Five Storied Foundation at Kishoreganj Pourashava

450

3. National Competitive Bidding (NCB) will be conducted in accordance with ADB’s Procurement Guidelines through electronic Government Procurement (e-GP) system and is open to all Bidders from eligible source countries as described in the Bidding Documents.

4. Only eligible Bidders with the following key qualifications should participate in this bidding:

Specific Similar Experience: Experience in implementing a minimum of one (1) similar contract as per bid document during the last five (5) years where the value of Bidder’s participation exceeds BDT 119,000,000.00.

Average annual construction turnover: Minimum average annual construction turnover shall be greater than BDT 180, 000,000.00 over the last 5 (five) years.

Liquid Assets or Credit Facilities: Minimum amount of Liquid Assets or Credit Facilities shall be greater than BDT 29,500,000.00. The qualification criteria are more completely described in the Bidding Document.

5. This is an online bidding where only e-Tender (e-bid) will be accepted in the Bangladesh National e-GP System Portal and no offline/hard copies will be accepted. To obtain further information and to

9

Project ID No. UGIIP-III-2/AF/KISH/MF/01/2017Project Name: Third Urban Governance and Infrastructure Improvement (Sector)

Project (UGIIP-III)Country: BangladeshDescription: Construction of Municipal Market Two Storied Building with Five

Storied Foundation at Kishoreganj Pourashava

Funding agency: Asian Development BankLast date of bid submission: 7 August 2018; 13:00 hours (Bangladesh Standard Time) (e-Tender)

Address for bid submission: e-tender

Page 11: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

submit e-Tender for this package bearing e-tender ID no. mentioned above, registration in the e-GP portal (http://www.eprocure.gov.bd) is required.

6. The fees for downloading the e-Tender Documents from the e-GP portal, and the tender security as mentioned in the documents have to be deposited online through any branch of the banks registered in the e-GP system.

7. The deadline for submission of e-Tenders (bids) is on 7 August 2018 at 13:00 hours Bangladesh Standard Time (BST) and online opening will be done on the same date at 13:00 hours Bangladesh Standard Time (BST).

8. Further information and guidelines are available in the e-GP portal and from e-GP help desk ([email protected]). To obtain further information, please contact the official inviting the tender.

Secondary Cities Development Project: Construction of Dien Bien Phu road (section from Km6+309.8 to Km8+106.2)

1. The Government of the Socialist Republic of Vietnam has received financing from the Asian Development Bank (hereinafter called "ADB") toward the cost of the Secondary Cities Development Project Part of this financing will be used for payments under the contract package named above. Bidding is open to Bidders from eligible source countries of ADB.

2. The Projects Construction Investment Management Authority of Quang Nam Province (“the Employer”) invites sealed bids from eligible Bidders for the construction of class II road and bridges in Tam Ky city, which has total length of 1,796.42m (Start point: rescue road, End point: Tam Thanh sea dyke). The scope of works includes:

• Bridges with spans includes eight (8) super-T beams, Ltc = 330.5m.

• Road approaches has two (2) lanes, speed design is 80km/h, length of 1,469.9m.

3. National Competitive Bidding (NCB) will be conducted in accordance with the ADB’s Single Stage – One Envelope procedure and is open to all eligible Bidders as described in the Bidding Document.

10

Project ID No. Package TK-03Project Name: Secondary Cities Development ProjectCountry: VietnamDescription: Construction of Dien Bien Phu road (section from Km6+309.8 to

Km8+106.2)

Funding agency: Asian Development BankLast date of bid submission: 27 July 2018, 8:00 hours (local time)

Address for bid submission: Projects Construction Investment Management Authority of Quang Nam Province No. 510 Hung Vuong street, Tam Ky citi, Quang Nam province Tel: +84253. 3818.191 Email: bqldaquangnam @yahoo.com

Page 12: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

4. Only eligible Bidders with the following key qualifications should participate in this bidding:

Experience:

• Participation in at least one (1) contract within the last three (3) years that have been successfully or substantially completed and that are similar to the proposed works which deems to include traffic work (plain road/bridges) of class II or higher, and the value of the Bidder’s participation exceeds VND 146,000,000,000.

Financial:

• Minimum average annual construction turnover of VND 350,000,000,000 calculated as total certified payments received for contracts in progress or completed, within the last five (5) years (2013, 2014, 2015, 2016, 2017).

• Bidder must demonstrate access to, or availability of, liquid assets, lines of credit, or other financial resources (other than any contractual advance payments) to meet the Bidder’s financial resources requirement for the subject contract of VND 45,700,000,000. The qualification criteria are more completely described in the Bidding Document.

5. Interested eligible Bidders may obtain further information from the Employer and inspect the Bidding Document starting on 29 June 2018 from 8:00 to 16:30 hours during Mondays to Fridays (except during weekends and holidays) until before 8:00 hours on 27 July 2018, at the address given below: Projects Construction Investment Management Authority of Quang Nam Province No. 510 Hung Vuong street, Tam Ky citi, Quang Nam province Tel: +84253. 3818.191 Email: bqldaquangnam @yahoo.com

6. To purchase the Bidding Documents in Vietnamese, eligible Bidders should:

• Submit an official letter to the above-mentioned address:

Fifth floor, The Public Administration and Investment Promotion Center of Quang Nam Province, No. 159B Chan Quy Cap Street, Tam Ky city, QuangNam province requesting the Invitation for Bid documents for Package TK-03: Construction of Dien Bien Phu road (section from Km6+309.8 to Km8+106.2).

• Pay a non-refundable fee of VND 2,000,000 by cash.

7. Deliver bids:

• To the address above (para 5)

• On or before 27 July 2018 at 8:00 hours

• All Bids must be accompanied with a Bid Security as specified in the Bidding Documents.

Late bid shall be rejected. Bids will be opened immediately after the bid submission deadline at the above-mentioned address (para 5) in the presence of Bidders’ representatives who wish to attend.

8. The Employer will not be responsible for any cost or expense incurred in the preparation and delivery of bids.

Energy

11

Page 13: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

Raghuganga Hydropower Limited Rahughat Hydroelectrtc Project (40 MW) Lot 2: Electro-Mechanical Works Contract

01. This invitation for bids has been issued to all Electro-Mechanical Contractors, who are eligible and qualified in accordance with the conditions stated in the Bidding Documents, and are interested to participate in undertaking PLANT and Design – Build Contract (PDB) of Lot - 2: Electro-Mechanical Works of Rahughat Hydroelectric Project (RGHEP) of capacity 40MW. The Project is located in Raghuganga Rural Municipality of Myagdi District in Province 4 of Nepal.

2. Raghuganga Hydropower Limited (RGHPL), the "Employer", a Company promoted by Nepal Electricity Authority (NEA), has completed the financial closure including soft loan portion being provided by the EXIM Bank of India and funds from Nepal Electricity Authority (NEA) and Government of Nepal (GON). It is intended to apply the part of the proceeds of these resources for eligible payments under the contract for which this invitation to Bid is issued.

3. The Works are based on FIDIC Conditions of Contract for PLANT and Design - Build (PDB) - First Edition, 1999. The Electro-Mechanical Works include Design, Manufacture, Supply, Delivery, Installation, Testing and Commissioning of all Electro-Mechanical equipment as stated in the Bid Documents.

4. Bidding will be conducted in accordance with Single Stage, Two Envelope Bidding Procedure, as set forth in the Bidding Document, Volume I.

5. The bidder must be an Indian Entity/Party or Joint Venture among Indian Entities registered in India and /or incorporated / established under any law in force in India. Maximum number of joint venture partners shall be limited to three (3) and lead partner shall meet at least 51 % while other partners shall meet at least 20% of the requirement.

6. The Bidder shall be legally registered in their home country for the last 10 (ten) years prior to the date of submission of the Bid. In case of a joint venture, the lead partner shall be manufacturer or contractor legally registered for at least ten (10) years. The other partner(s) of the JV shall be manufacturer(s) or contractor(s) legally registered for at least six (6) years.

12

Project ID No. RGHPL/074 – 75/ LOT - 2Project Name: Raghuganga Hydropower Limited Rahughat Hydroelectrtc Project (40

MW)Country: NepalDescription: Lot 2: Electro-Mechanical Works of Rahughat Hydroelectric Project

(RGHEP) of capacity 40MWFunding agency:Last date of bid submission: 06.09.2018

Address for bid submission: Address: The Managing Director Raghuganga Hydropower Limited Room No. 217 Nepal Electricity Authority Durbarmarg, Kathmandu Tel: 014153217, 014153196 Email: [email protected]

Page 14: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

7. Indian Entity/Party should have manufacturing & testing facilities in India for Turbines and Generator and the same shall be manufactured in India.

8. Bidders are required to meet the following qualification criteria:

a. Experience as a Prime Contractor or Lead Partner in a joint venture on PLANT and Design – Build (PDB)Project of at least two Electro-Mechanical contracts in a Hydroelectric Project of capacity ≥ 40 MW within the last (10) years ending last day of month previous to the one in which Bids are invited. At least one such project shall be outside the bidder’s country.

b. Successfully completed, either by the bidder company itself or by associate manufacturer(s) who have given authorization to the bidder in required format, design, manufacturing, supply, erection and commissioning of the following Electro-Mechanical items and/or works in preceding (10) ten years ending last day of month previous to the one in which Bids are invited.

i) Must have done design, engineering, manufacturing, supply, erection and commissioning of at least four Pelton turbines of minimum 20 MW single unit capacity. At least two such turbines must have been in successful operation outside the country of manufacturer for at least 24 months from the date of commissioning.

ii) Must have done design, engineering, manufacturing, supply, erection and commissioning of at least four generators with related equipments for hydroelectric scheme of minimum 20MW single unit capacity. At least two such generators must have been in successful operation outside the country of manufacturer for at least 24 months from the date of commissioning.

c. Possess minimum average annual construction turnover of US $ Seven million (US $ 7,000,000/-) calculated as total certified payments received for contracts in progress or completed, during preceding three (3) financial years.

d. Able to demonstrate a financial resource requirement of US $ Eight Hundred Thousand (US $ 800,000/-).

e. Able to demonstrate a positive Net Worth.

f. Able to demonstrate adequate Manpower to be used for the project.

9. Bidders may obtain further information and inspect the Bidding Documents at the address given below during office hours (10:00 to 17:00 hours) on working days. A complete set of Bidding Documents in English may be purchased by interested bidders from 8th July, 2018 to 5th September, 2018 during office hours on submission of written application to the address given below accompanied by a bank voucher evidencing a non-refundable cash deposit of NRs 20,000/- (Nepalese Rupees Twenty Thousand Only) in Project Account Number 01000105200845 at Everest Bank Limited, Teku, Kathmandu, Nepal in favor of RGHPL.

10. A Pre-Bid meeting will be held at 14:00 hours on 8 th August, 2018 at the address given below. Attendance is strongly advised for all Bidders and their representatives.

11. One (1) set of original and two (2) sets of duplicate Bidding Documents, signed by authorized personnel, must be submitted in wax sealed envelopes to the address below on or before 12:00 hours on 6th September, 2018. Documents received after this deadline will not be accepted. Bids (Technical) shall be opened in the presence of Bidder’s representatives who choose to attend at 14:00 hours local time on 6th September, 2018 at the address given below.

Bids must be valid for a period of 180 days counting from the day of Bid Opening and must be accompanied by Bid security, amounting to NRs. 32,700,000/- ( Nepalese Rupees Thirty Two Million Seven Hundred Thousand only ) or equivalent amount in US $ at the selling rate published by Nepal

13

Page 15: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

Rastra Bank, 28 days prior to the deadline for submission of Bids which shall be valid for a minimum 60 days beyond the Bid validity period. Bid Security issued by any Foreign Bank outside Nepal must be provided with a Counter Guarantee issued by an “A” Class Commercial Bank in Nepal.

12. If the last date of receiving Bidding Documents, submission and/or opening falls on a government holiday, then the next working day shall be considered the last day.

13. It is recommended that Bidders familiarize themselves with the local conditions and visit the project site to obtain all information that may be necessary for preparing the Bid. Cost incurred for preparation of Bidding Documents and the site visit will be solely at the expense of the Bidder and the Employer will in no case be responsible or liable for the costs associated with it.

14. The RGHPL reserves the right to accept or reject, wholly or partly any or all the Bids without assigning any reason, whatsoever.

15. Bidders may obtain further information from the address below or from NEA website www.nea.org.np.

Address: The Managing Director Raghuganga Hydropower Limited Room No. 217 Nepal Electricity Authority Durbarmarg, Kathmandu Tel: 014153217, 014153196 Email: [email protected]

14

Page 16: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

Design, Supply, Installation and Commissioning of New Butwal- Bardghat 220 kV Double Circuit Transmission Line

INVITATION FOR BIDS: REBIDDING First Date of Publication: 29 June, 2018

1. The Government of Nepal has received financing from the Asian Development Bank (ADB) toward the cost of South Asia Subregional Economic Cooperation (SASEC) Power System Expansion Project. Part of this financing will be used for payments under the contract named above. Bidding is open to Bidders from eligible source countries of ADB.

2. The Nepal Electricity Authority (“the Employer”) invites sealed bids from eligible bidders for the Design, Supply, Installation and Commissioning of New Butwal- Bardghat 220 kV Double Circuit Transmission Line (“the Facilities”). Completion period is 540 days from contract effective date.

3. International competitive Bidding (ICB) will be conducted in accordance with ADB's Single-Stage: Two-Envelope bidding procedure and is open to all Bidders from eligible countries as described in the Bidding Document.

4. Only eligible Bidders with the following key qualification shall participate in this bidding:

Bidders shall have minimum average annual turnover of USD 8.3 Million.

Bidders are required to have satisfactory experience in at least 2 (Two) contracts within the last 10 (Ten) years, with a value of at least USD 4.94 Million each, wherein the Bidder has Supplied, Installed and Commissioned 220kV and above Double Circuit Transmission Line of a complete Length of not less than 21 kms having bundled conductors.

5. To obtain further information and inspect the bidding documents, bidders should contact:

15

Project ID No. RE:ICB-PMD-KGTCP-073/74-02Project Name: South Asia Subregional Economic Cooperation (SASEC) Power System

Expansion Project

Country: NepalDescription: Design, Supply, Installation and Commissioning of New Butwal-

Bardghat 220 kV Double Circuit Transmission Line

Funding agency: Asian Development Bank (ADB)Last date of bid submission: 13 August, 2018, 12:00 Hours (Nepal Standard Time)

Address for bid submission: Kaligandaki Transmission Corridor Project Project Management Directorate Satungal-Bauthali Chowk Marga, Chandragiri Municipality-11, Matatirtha Substation, Kathmandu, Nepal Telephone: +977-1-5164091, 5164177 Facsimile number: +977-1-5164099 Electronic mail address: [email protected]

Page 17: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

Kaligandaki Transmission Corridor Project Project Management Directorate Satungal-Bauthali Chowk Marga, Chandragiri Municipality-11, Matatirtha Substation, Kathmandu, Nepal Telephone: +977-1-5164091, 5164177 Facsimile number: +977-1-5164099 Electronic mail address: [email protected]

6. To purchase the bidding documents in English, eligible bidders should:

write to address above requesting the bidding documents for RE: ICB-PMD-KGTCP073/74-02:

Design, Supply, Installation and Commissioning of New ButwalBardghat 220 kV Double Circuit Transmission Line

pay a non-refundable fee of NRs. 20,000 by or an equivalent amount in US Dollars by bank voucher to the Current Account No 660 10 10000 125 at the Global IME Bank, Kushma, Parbat, Nepal or any of its branches.

7. Deliver your bid:

to the address above on or before the deadline: 13 August, 2018, 12:00 Hours (Nepal Standard Time)

together with a Bid Security indicated in Section 2, Bid Data Sheet, Clause ITB 21.1 of Bidding Document or an equivalent amount in a freely convertible currency.

For the purpose of determining the equivalent amount of the required Bid Security in a freely convertible currency, the exchange rates published by Nepal Rastra Bank prevailing on the date 28 days prior to the deadline for bid submission shall be applied. Technical bids will be opened at Project Manager’s Office immediately after the deadline of the bid submission in the presence of Bidders’ representatives who choose to attend at the address above, whereas the Financial Bids shall remain sealed and unopened and shall be placed locked. The Financial Bids of only Technically Responsive and Qualified Bidders shall be opened after Technical Bid Evaluation, whereas, the Financial Bids of those Bidders whose Technical Bids are not responsive and qualified shall be returned unopened after the contract is awarded.

8. When comparing Bids, ADB’s Domestic Preference Scheme will be applied in accordance with the provisions stipulated in the Bidding Document.

NEPAL ELECTRICITY AUTHORITY PROJECT MANAGEMENT DIRECTORATE KALIGANDAKI TRANSMISSION CORRIDOR PROJECT Satungal-Bauthali Chowk Marga, Chandragiri Municipality, Matatirtha, Kathmandu, Nepal Telephone: +977-1-5164091, 5164177 Facsimile number: +977-1-5164099 Electronic mail address: [email protected]

16

Page 18: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

Procurement of Plant, Design, Supply, Installation, Testing and Commissioning of the Refurbishment of Rouna 1 & Sirinumu Hydropower Plants

Invitation for Bids

1. The Independent State of Papua New Guinea (PNG) has received financing from the Asian Development Bank (ADB) toward the cost of the Port Moresby Power Grid Development Project. Part of this financing will be used for payments under the Contract named above. Bidding is open to Bidders from eligible source countries of ADB.

2. The PNG Power Ltd (PPL) (“the Employer”) invites sealed Bids from eligible Bidders for the design, supply, installation, testing and commissioning of the Refurbishment of Rouna 1 & Sirinumu Hydropower Plants.

3. International Competitive Bidding (ICB) will be conducted in accordance with the ADB’s Single Stage – One Envelope procedure and is open to all eligible Bidders as described in the Bidding Document.

4. Only eligible Bidders with the following key qualifications should participate in this bidding:

• The Bidder must demonstrate that it has the financial resource to meet its current contract commitments, plus the requirements for the subject contract of US$ 5.5 million or its equivalent for the first twelve (12) months. Similar participation in at least two (2) contracts that have been successfully or substantially completed within the last eight (8) years, where the value of the Bidder’s participation exceeds US$ 42 million. Bidder’s participation based on the physical size, nature of works, complexity, methods, technology or other characteristics as described.

• Dismantling of old equipment, design, manufacture, adapting new generators, turbines, open surface steel penstock, surge shaft, manifold, to suit refurbished plant of a similar size and type. Design and manufacture of ONAN/ONAF transformers of similar voltage level and rating including commissioning of GIS switchgear of a similar voltage level and rating to that required for this Project.

• Successful design, implementation and completion of similar cofferdam, concrete structure incorporated into an earthfill dam, intake structure with a design flow of at least 7m³/s, forensic investigations of at least two concrete structures, concrete repair works, grout injection for water tightness on concrete civil structures and structural amalgamation. Re-commissioning of steel

17

Project ID No. PPL/PGW01-002-ICBV1-02/18Project Name: Port Moresby Power Grid DevelopmentCountry: Papua New Guinea Description: Procurement of Plant, Design, Supply, Installation, Testing and

Commissioning of the Refurbishment of Rouna 1 & Sirinumu Hydropower Plants

Funding agency: Asian Development Bank (ADB)Last date of bid submission: 15 August 2018 at 14:00 hours (local PNG time)

Address for bid submission: Peter Tangwari - Project Manager PNG Power Ltd National Office, Level 3 / PMU Office Corner Wards Rd & Cordia St, PO Box 1105, Boroko Port Moresby 111 National Capital District Papua New Guinea Tel: +675 324 3254 E-mail: [email protected] Fax No: +675 325 0185 Website: www.pngpower.com.pg

Page 19: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

penstock of similar type and complexity. The qualification criteria are more completely described in the Bidding Document.

5. To obtain further information and inspect the Bidding Documents, Bidders should contact the address below commencing 4 July 2018 to 15 August 2018 from 8:00 – 16:30 hours, Monday – Friday except Saturday, Sunday and Public Holidays.

Peter Tangwari - Project Manager PNG Power Ltd National Office, Level 3 / PMU Office Corner Wards Rd & Cordia St, PO Box 1105, Boroko Port Moresby 111 National Capital District Papua New Guinea Tel: +675 324 3254 E-mail: [email protected] Fax No: +675 325 0185 Website: www.pngpower.com.pg

6. To purchase the Bidding Documents in English, eligible Bidders should:

• write to the address above requesting the Bidding Documents for PPL/PGW01-002- ICBV1-02/18, Refurbishment of Rouna 1 and Sirinumu Hydropower Plants.

• pay a non-refundable fee of US$200.00 or PGK equivalent by cash, telegraphic transfer or cheque made payable to PNG Power Ltd. The PNG Power Ltd bank account details are:

Account Name: PNG POWER LIMITED, PORT MORESBY POWER GRID DEVELOPMENT PROGRAM

Bank: Bank South Pacific (BSP)

Branch: GORDONS COMMERCIAL CENTRE

Branch No: 088951

Account: 1012516918

Swift Code No. BOSPPGPM

7. Deliver your bid:

• to the address above

• on or before the deadline: 14:00 hours on 15 August 2018

• together with a Bid Securing Declaration as described in the Bidding Document.

• Electronic submission of Bids is not allowed.

Bids will be opened immediately after the deadline for bid submission in the presence of Bidders’ representatives who choose to attend.

18

Page 20: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

Procurement of Lot A2 – Main Civil Works for Green Power Development and Energy Efficiency Improvement Investment Program - Tranche 1

Invitation for Bids

1. The Democratic Socialist Republic of Sri Lanka has received financing from the Asian Development Bank (ADB) toward the cost of Green Power Development and Energy Efficiency Improvement Investment Program – Tranche 1. Part of this financing will be used for payments under the contract named above. No nationality restrictions apply, other than any restrictions arising from ITB 4.7.

2. The Ceylon Electricity Board (‘the Employer’) invites sealed bids from eligible bidders for the construction of Lot A2 – Main Civil Works consisting of construction of a dam, intake, headrace tunnel, surge tank, penstock, powerhouse, tailrace, switchyard, access roads and all other related works. Construction period is 1,338 days.

3. International Competitive Bidding will be conducted in accordance with ADB’s Single Stage: Two-Envelope bidding procedure and is open to all bidders without nationality restrictions.

4. Only eligible bidders with the following key qualifications should participate in this bidding:

• Participation in at least two (2) contracts that have been successfully or substantially completed within the last ten (10) years prior to the bid submission deadline and that are similar to the proposed works, where the value of the Bidder’s participation for each contract exceeds USD 43 Million. The similarity of the Bidder’s participation shall be based on the physical size, nature of works, complexity, methods, technology and other characteristics as described in Section 6; Employer’s Requirements.

19

Project ID No. CEB/PD/MOGL–LA2Project Name: Green Power Development and Energy Efficiency Improvement

Investment Program - Tranche 1Country: Sri Lanka Description: Procurement of Lot A2 – Main Civil Works

Funding agency: Asian Development Bank (ADB)Last date of bid submission: 22 August 2018, 10:00 hours local time

Address for bid submission: Project Director, Moragolla Hydropower Project, Ceylon Electricity Board, No. 6/1, T. B. Panabokke Mawatha, Gampola 20500, Sri Lanka. Tel: +94 81 3832043 Fax: +94 81 2353018 Email: [email protected] Website: www.ceb.lk

Page 21: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

• Minimum average annual turnover of at least USD 30 Million, calculated as total certified payments received for construction contracts in progress or completed, within the last five (5) years.

• All pending litigation and arbitration, if any, against the Bidder shall not in total represent more than fifty percent (50%) of the Bidder’s net worth.

• As a minimum, the Bidder’s net worth for last three (3) years, calculated as the difference between total assets and total liabilities, shall be positive.

• Minimum available financial resources shall be USD 4.9 Million.

• Bidders are required to have minimum construction experience in the following key activities:

o Main Civil Works for a concrete dam of height not less than 30 m with gated spillway or similar structure.

o Main Civil Works for pressure tunnel of minimum diameter 4.0 m and minimum length of 2,000 m excavated by drill and blast tunneling methodologies that include sequential excavation which provides support addressing the rock conditions encountered. o Main Civil Works for underground vertical or inclined shaft of minimum dimensions 4m diameter and 100m height / length.

o Main Civil Works for power house of volume not less than 40m L x 20m W x 35m H semi-underground structure or similar structure for the installation and housing of mechanical and electrical plant and control systems.

(Note: Only important eligibility criteria are mentioned above briefly. To know the complete eligibility criteria, intending bidders are advised to inspect the Bidding Document by visiting the website of Ceylon Electricity Board, www.ceb.lk.)

5. To obtain further information and to inspect the bidding documents, eligible bidders shall contact:

Project Director, Moragolla Hydropower Project, Ceylon Electricity Board, No. 6/1, T. B. Panabokke Mawatha, Gampola 20500, Sri Lanka. Tel: +94 81 3832043 Fax: +94 81 2353018 Email: [email protected] Website: www.ceb.lk

An information copy of the bidding document could be downloaded from the above CEB website.

6. To purchase the Bidding Documents in English, eligible bidders shall;

• Visit the office of the Project Director, Moragolla Hydropower Project, No. 6/1, T. B Panabokke Mawatha, Gampola (20500), Sri Lanka on normal working days between 09:00 hours and 15:00 hours

20

Page 22: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

until 22 August 2018 and pay a non-refundable fee of LKR 160,000.00 or USD 1,000 by a bank draft drawn in favour of the General Manager, Ceylon Electricity Board, Sri Lanka. OR,

• Request for delivery by sending a written application to the address above requesting the bidding documents for Construction of Moragolla Hydropower Plant – Lot A2- Main Civil Works. The application must include a bank draft in favour of General Manager Ceylon Electricity Board, for the amount of LKR 160,000.00(domestic delivery) or USD 1,150 (overseas delivery). The document will be sent by courier. No liability will be accepted for loss or late delivery.

7. Bids must be delivered:

• To the address below: The Chairman, Standing Cabinet Appointed Procurement Committee (SCAPC) for Construction of Moragolla Hydropower Plant, c/o Additional General Manager (Projects) Ceylon Electricity Board, 385, 4th Floor, Landmark Building, Colombo 00300, Sri Lanka.

• On or before the deadline: 10:00 hours local time on 22 August 2018.

• Together with a Bid Security in the amount as described in the Bidding Document.

• Late Bids shall not be accepted.

8. Technical bids will be opened immediately in the presence of Bidders’ representatives who choose to attend at the office of the Additional General Manager (Projects), 385, 4th Floor, Landmark Building, Colombo 00300, Sri Lanka, whereas the Financial Bids shall remain sealed and unopened and shall be placed locked. The Financial Bids of only Technically Responsible and Qualified Bidders shall be opened after Technical Bid Evaluation, whereas, the Financial Bids of those Bidders whose Technical Bids are not responsive and qualified shall be returned unopened after the contract is awarded.

9. The Bidder shall bear all costs associated with the preparation, attending pre-bid meeting, site visits and submission of its bid and the Employer shall not be held responsible or liable for such costs, regardless of the conduct or outcome of the bidding process.

21

Page 23: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

Kostanay District Heating: Construction of DN 500 interconnection pipeline

INVITATION FOR TENDERS

Construction of DN 500 interconnection pipeline (Lermontova st.)

This Invitation for Tenders follows the General Procurement Notice for this project which was published inProcurement Opportunities on the EBRD website: 6 October 2016 and updated 16 October 2017.

State Communal Enterprise Kostanay Heat and Power Company, hereinafter referred to as the Employer, intends using part of the proceeds of a loan from the European Bank for Reconstruction and Development (the Bank) towards the cost of Kostanay District Heating Project.

The Purchaser now invites sealed tenders from the suppliers for the following contract KoDHP-9R, Construction of DN 500 interconnection pipeline (Lermontova st.).

The Project is implemented on the territory of Kostanay City of the Republic of Kazakhstan.

These contracts include works for Construction of DH Network according to the Requirements.

The estimated completion time under contract is 390 days.

Tendering for contracts to be financed with the proceeds of a loan from the Bank is open to firms from any country. The proceeds of the Bank's loan will not be used for the purpose of any payment to persons or entities, of for any import of goods, if such payment or import is prohibited by a decision of the United Nations Security Council taken under Chapter VII of the Charter of the United Nations.

To be qualified for the award of a contract, tenderers must satisfy the following requirements:

a. The Tenderer shall demonstrate that it has successful experience as prime contractor in the execution of at least 3 (three) successfully completed contracts of a nature and complexity comparable to the proposed contract, with at least one of them having a value of not less than KZT 340,000,000 (three hundred and forty million) equivalent, within the last 5 (five) years.

b. The Tenderer, partner of JVCA or their sub-contractors shall demonstrate successful experience in construction/reconstruction of DH networks of a nature and complexity comparable to the proposed contract.

22

Project ID No. 9169-IFT-47396Project Name: Kostanay District HeatingCountry: KazakhstanDescription: Construction of DN 500 interconnection pipeline (Lermontova st.).

Funding agency: EBRDLast date of bid submission: 21 Aug 2018   at  15:00   Local time

Address for bid submission: Mr. A. BekpaganbetovState Communal Enterprise "Kostanay Heat and Power Company"231 Borodina St. Kostanay City, KazakhstanFax: +7-7142-577024E-mail: [email protected]

Page 24: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

(c)   The Tenderer shall have an average annual turnover as prime contractor (defined as billing for works in progress and completed) over the last 3 (three) years of not less than KZT 630,000,000 (six hundred and thirty million) equivalent.

(d)  The Tenderer shall demonstrate that it has access to, or has available, liquid assets, unencumbered real assets, lines of credit, and other financial means sufficient to meet the construction cash flow for the contract for a period of 3 (three) months, estimated as not less than USD 1,300,000 (one million three hundred thousand) equivalent, taking into account the applicant's commitments for other contracts.

(e)   The Tenderer shall demonstrate that it has access to, or has available, liquid assets, unencumbered real assets, lines of credit, and other financial means sufficient to meet the construction cash flow for the contract for a period of 3 (three) months, estimated as not less than equivalent, taking into account the applicant's commitments for other contracts.

The tender documents may be obtained from the address below upon written request and payment of a non-refundable fee of KZT 100,000 (One hundred thousand) (VAT including) or equivalent in convertible currency.

In convertible currency payment shall be made by direct bank transfer to:

Beneficiary: State Communal Enterprise Kostanay Heat and Power Company                               

Beneficiary’s Bank: Halyk Bank Kazakhstan, 97 Rozybakiev str. 050046 Almaty Kazakhstan

Account No: KZ986010221000286607 USD

Account No: KZ426010221000315745 EUR

SWIFT BIC: HSBKKZKX

Correspondent account USD

No 8900372605

Correspondent Bank: THE BANK OF YORK MELLON NEW YORK, NY US

SWIFT BIC: IRVTUS3NXXX

Correspondent account EUR

No 100 9472176 1000

Correspondent Bank: DEUTSCHE BANK AG FRANKFURT AM MAIN DE

SWIFT BIC: DEUTDEFFXXX

Upon the written request and confirmation of payment of a non-refundable fee the tender documents may be collected from the office at the address given below or the documents will be promptly dispatched by e-mail to the address, indicated in the written request, but no liability can be accepted for loss or late delivery.

All tenders must be accompanied by a tender security in the amount not less than KZT 8,000,000 (eight million) or equivalent.

Tenders must be delivered to the office at the address below on or before or before 15:00 (local time) 21 August 2018, at which time they will be opened in the presence of those tenderers’ representatives who choose to attend.

23

Page 25: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

A register of potential tenderers who have purchased the tender documents may be inspected at the address below.

Prospective tenderers may obtain further information from, and inspect and acquire the tender documents at the following office:

Mr. A. BekpaganbetovState Communal Enterprise "Kostanay Heat and Power Company"

231 Borodina St. Kostanay City, KazakhstanFax: +7-7142-577024

E-mail: [email protected]

Consultancy

Enguri Hydro Power Plant Rehabilitation Project - Maintenance Audit

Govt. of the People's Republic of Bangladesh Ministry of PowJr, Energy and Mineral Resources Power Division Power Cell Biddyut Bhaban (l3n Floor) 1, Abdul Gani Road, Dhaka 1000, Bangladesh. (www.powercell.gov.bd, www.mpemr. gov.bd) REQUEST FOR EXPRESSTONS OF TNTERBST EEOr) FOR Appointment Of Consulting Firm For Preparation Of Open Standard And Interoperable Architecture For Smart Prepaid Metering System Date:02.07.2018

1. The vision of the Government of Bangladesh is to provide quality electricity to all by 2021. Govt. has rolled out a massive program to install pre-paid metering system in power sector and has already developed unified pre-paid metering system under a single umbrella. Now the unified prepayment metering system needs to be upgraded to smart pre-paid metering system to improve customer services.

2. To convert pre-paid metering system into smart pre-paid metering system preparation of Head End System (HES), Meter Data Management system (MDMs), specification of communication devices with

24

Project ID No.Project Name: Enguri Hydro Power Plant Rehabilitation Project - Maintenance AuditCountry: BangladeshDescription: Appointment Of Consulting Firm For Preparation Of Open Standard

And Interoperable Architecture For Smart Prepaid Metering System

Funding agency:Last date of bid submission: 2nd August,2018, 17:00 hrs (BST

Address for bid submission: Director General Tel: 88 (02) 9556040, 9555962, 9566099 Fax: 88 (02) 9572097, 9 554664 Email : dg@powercell. gov.bdEnguri Hydro Power Plant Rehabilitation Project - Maintenance Audit

Page 26: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

standard API and other associated softwares are essential. Government has assigned power Cell to appoint a consulting firm to carry out the above mentioned tasks.

3. Power cell, Power Division now invites proposals from potential consulting firms with the following team composition for the titled study. Detailed qualification and the required eligibility are given in the Terms of Reference (TOR).

o Power Sector Specialist . Computer Programmer/Software Expert

o Computer Hardware & Network Specialist

o Smart/Pre-Paid Metering Expert . Communication Expert . Security/Risk Analyst

4. The consulting firm will be selected based on the following evaluation criteria: . Age of the firm

o Experience of the firm in Bangladesh power Sector . Experience of firm in similar works . Qualification of Key Professionals . Work Methodology and plan

5. Detail Scope of Work will be available in the TOR which can be downloaded from the website of power Cell (www.powercell.gov.bd) from the date of publishing of EOI.

6. Applicants are requested to submit their' f.OI (2 copies) to the above mentioned address within the submission deadline. The submission deadline is 2nd August,2018, 17:00 hrs (BST). Any submission received after the confirmed submission date and time will not be accepted.

(Mohammad Hossain) Director General Tel: 88 (02) 9556040, 9555962, 9566099 Fax: 88 (02) 9572097, 9 554664 Email : dg@powercell. gov.bdEnguri Hydro Power Plant Rehabilitation Project - Maintenance Audit

25

Page 27: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

Annual maintenance audit on the Enguri and Vardnili hydropower scheme                      

Executing Agency (Client):

ENGURHESI Ltd The Client Contact Persons:Mr Malkhaz TskvitishviliProject Manager8, Politkovskaya str. Tbilisi, GeorgiaEmail: [email protected].: (995 32) 218 80 11 

Project Description:

The Enguri hydropower scheme is located at the Enguri River in west Georgia. The hydro-power cascade of the Enguri and Vardnili Hydropower Plants (“HPPs”) was commissioned in late 1970s. Their share of electricity generation reaches 40% of the country’s electricity production and represents the largest hydropower scheme in the national power system.

EBRD became involved in financing of the Enguri and Vardnili HPP Rehabilitation Project (the “Project”) in 2000. The project involved a full-scale rehabilitation of the hydro cascade. A new loan financing provided by EBRD in 2018 aims to resolve a number of safety issues.

Assignment Description:

On the basis of the Consultancy Procurement Document the Client intends to select and contract a consulting company (the Consultant) to perform the annual maintenance audit on the Enguri and Vardnili hydropower scheme and to produce an annual operation and maintenance (“O&M”) program for the years 2018 to 2021 (the Assignment).

The expected outcome of the Assignment is improvement of safety and sustainability of operations of the power plants for greater self-reliance.

26

Project ID No. 9167-RFP-15857Project Name: Annual maintenance audit on the Enguri and Vardnili hydropower

scheme

Country: GeorgiaDescription: ConsultancyFunding agency: EBRDLast date of bid submission: 04 September 2018

Address for bid submission: The Client Contact Persons:Mr Malkhaz TskvitishviliProject Manager8, Politkovskaya str. Tbilisi, GeorgiaEmail: [email protected].: (995 32) 218 80 11

Page 28: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

The selected Consultant will identify opportunities to strengthen the management control framework of the O&M program, as well as the management of the capital investment projects and O&M funding. The Consultant will also propose a Management Action Plan.

Consultant Selection Procedure: Single stage open competitive selection

Interested firms of groups of firms are invited to submit a Technical and Financial Proposal.

Assignment Start Date and Duration: The Assignment is expected to start in September 2018 and has an estimated overall duration of about 10 man/months over a 4-year period.

Cost Estimate: EUR 100,000.00. Subject to availability of funding, the performance of the selected Consultant and the specific needs of the Client the Assignment may be extended beyond the current scope and duration.

The Consultant must determine whether any indirect taxes/VAT are chargeable on the proposed services and state the basis for such. If any indirect taxes/VAT are payable, the Client will have to pay indirect taxes/VAT element to the services directly to the Consultant unless otherwise agreed.

Funding Source: EBRD loan proceeds.

Eligibility:  There are no eligibility restrictions based on the consultant's country of origin.

Submission Requirements: In order to determine the capability and experience of Consultants seeking to be selected, the consultant shall submit a Response in accordance with the Consultancy Procurement Document (CPD). Click here: CPD

  Important Notes:

1. The selection will normally be made from the Proposals received in response to this notification only, on the basis of the selection criteria set out in the CPD. The highest-ranked Consultant will be selected and be invited to negotiate the contract, subject to availability of funding.

2. Any updates of and clarifications on this procurement notice and/or the CPD shall be announced as updates on this notice, without any other notification. In the event of changes to the CPD, consultants will need to download the updated version of the CPD. Consultants are required to periodically check the notice for updates. Failure to take the updates into account while preparing the Proposal may result in disqualification or penalties to the scores in the evaluation.

27

Page 29: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

ENGURI HYDRO POWER PLANT REHABILITATION PROJECT – CLIMATE RESILIENCE UPGRADE

Invitation for Prequalification

Enguri Hydro Power Plant Rehabilitation Project –Climate Resilience Upgrade

 Electromechanical Works on Switchyard &

Hydro-mechanical Works on Penstocks and Gates at Enguri Dam 

This Invitation for Prequalification follows the General Procurement Notice for this project which was published on the EBRD website, Project Procurement Notices (http://www.ebrd.com/pages/workingwithus/procurement/project.shtml) on 5 January 2017.

Engurhesi Ltd, hereinafter referred to as “the Client”, intends using part of the proceeds of a Loan from European Bank for Reconstruction and Development, hereinafter referred to as “the Bank” towards the cost of Enguri Hydro Power Plant Rehabilitation Project.

The Client intends prequalifying firms and consortia to tender for the following contract(s), hereinafter referred to as “the Contract”, to be funded from part of the proceeds of the Loan.

The aim of the Contract is to carry out the refurbishment and moderinzation of the electrical and hydromechanical equipment of Enguri HPP facilities.

The Enguri Dam is located in west Georgia, Tsalenjikha Region, 35 kilometers from the regional center city – Zugdidi, while the Enguri HPP is located in Gali region, 16 kilometers from the temporary Abkhazian border.  The dam and the power plant are connected with the 15km, Ø9.5m pressure tunnel.

28

Project ID No. 9166-PRE-49649Project Name: Enguri Hydro Power Plant Rehabilitation Project –

Climate Resilience Upgrade

Country: GeorgiaDescription: Electromechanical Works on Switchyard &

Hydro-mechanical Works on Penstocks and Gates at Enguri Dam

Funding agency: EBRDLast date of bid submission: 14 Aug 2018   at  16:00   Local time

Address for bid submission: Contact person:        Mr. Malkhaz TskvitishviliExecuting Agency:   Engurhesi Ltd, Project Implementation UnitStreet Address:           8, Politkovskaya Str.Floor/Room number: 3rd floorCity:                               TbilisiPostal Code:                 0186Country:                        GeorgiaPhone number:            (995 32) 2 18 80 11Facsimile number:       (995 32) 2 18 80 22E-mail address:             [email protected]    

Page 30: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

The scope of the Contract includes the rehabilitation of the following equipment:

Hydro-mechanical part:

Enguri bottom outlet gates

Maintenance and service gates rehabilitation with replacement of hydraulic cylinders The “upstream guiding strips” and “lateral guiding blocks” need to be fully replaced by UHME-

PE (Ultra-Hoch-Molecular - Polyethylene) plates Provision and installation of all sealings between the maintenance gate bonnet covers and new

by-pass valves 

Additional service butterfly valves - Ø5000 mm for turbine penstocks

Rehabilitation (complete) of the electrical overhead travelling (EOT) crane 800 kN / 200 kN Rehabilitation of the by-pass system of the present valves and the aeration valve Replacement of all hydraulic cylinders of the present valves Design and installation of one new butterfly valves with all their auxiliaries as a pilot (optional) 

Additional butterfly bypass (Ø6000) or redesign of existing bypass in pressure tunnel valve chamber

Complete rehabilitation of electrical overhead travelling (EOT) crane 1000 kN / 200 kN Provision and installation of four (2x2) manually operated spherical valves (DN 400, PN25),

incl. all necessary piping Provision and installation of extra eight (4x2) manually operated spherical valves (DN 400,

PN25) Provision and installation of 4 new servomotors (Ø800 x Ø160 x 2122 mm) for the butterfly

valve Ø6000 including valve drifting monitoring system. 

New gates and hoists for Vardnili 2 HPP

Cleaning, repair (both concrete and mechanical parts) and painting of all 4 spillway maintenance and service gate embedded parts to receive the new spillway gates

After structural calculations, repair the remaining hoist structures and complete it to receive the 2 winch hoisting units of capacity of 2x320 kN

Provide and install 2 winch hosting units of the capacity of 2x320 kN in two (2) spillway structures with new roof construction

Provide and install local and remote-control equipment (electrical cabinets) for two (2) hoisting winches with a capacity of 2x320 kN;

Provide and install 2 fixed wheel roller gates as spillway service gate in the 2 spillway structures

Provide and install one fixed wheel roller gate as spillway maintenance gate common for both spillway structures

Provide and install necessary gate dogging devices on all spillway gate slots

Rehabilitation of existing gates, sealings and hoists for Enguri diversion weir to Gali reservoir

Provide and install the new steel construction to support the hoists with new foundation bolts on all 5 spillway gates etc.

Install new hoisting system of sufficient capacity (or install hydraulic strand jack) Rehabilitation of all 5 spillway gates Provide a mobile electric generator of required capacity to lift one spillway gate at a time.

Electro-mechanical part:

29

Page 31: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

Partially replacement of complete auxiliary power supply system including transformers, distribution and sub distributions 0.4 kV, 50 Hz, Direct current system;

Partially replacement of power supply and control cables in dam galleries, including arrangement of cable trays and channels;

Replacement of 6.3 kV Main distribution board including control and protection system; installation of Step-Up transformer for existing low voltage emergency diesel generator set to

feed the emergency consumer via 6.3 kV line; replacement of lighting system in selected galleries. replacement of equipment in 35/6.3 kV switchyard, including circuit breaker disconnectors,

instrument transformers, protection system, surge arresters, isolators, connections, lightning system etc.,

Installation of redundant 35/6.3 kV power line with circuit breaker disconnectors, step-down transformer, instrument transformers, protection system, lighting system and auxiliary power supply 6.3/0,4 kV for yard supply.

Reconstruction and refurbishment of the existing 6.3 kV Overhead line with the dedicated towers, isolators and conductors.

 

The Client will provide basic design for the rehabilitation activities.

The rehabilitation activities can be implemented concurrently. The expected construction period is 18-20 months, according to the operational conditions of the plant.

Prequalification and tendering for contracts to be financed with the proceeds of a Loan from the Bank is open to firms and joint ventures of firms from any country.

Prequalification documents may be obtained from the office at the address below or in electronic format free of charge.

The prequalification documents must be duly completed and delivered to the address below, on or before 14 August 2018, by 16:00 hrs local time. Documents which are received late may be rejected and returned unopened.

Interested firms may obtain further information from, and inspect and acquire the prequalification documents at the following office:

Contact person:        Mr. Malkhaz TskvitishviliExecuting Agency:   Engurhesi Ltd, Project Implementation UnitStreet Address:           8, Politkovskaya Str.Floor/Room number: 3rd floorCity:                               TbilisiPostal Code:                 0186Country:                        GeorgiaPhone number:            (995 32) 2 18 80 11Facsimile number:       (995 32) 2 18 80 22E-mail address:             [email protected]    

30

Page 32: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

News Items

Malaysia seeks 'drastic' price cut in $20 bn China backed rail link projectMalaysia's new government has axed a high-speed rail line to Singapore because it is too costly and is reviewing other large infrastructure projects financed by ChinaAP/PTI  |  Kuala Lumpur Last Updated at July 3, 2018 13:11 IST

Malaysia's government has said a major China-backed rail link project can only be viable with a "drastic" price reduction by the Chinese contractor as the actual cost of the venture is 81 billion ringgit ($20 billion).

The 688 kilometre (430 miles) East Coast Rail Link is a key part of China's regional Belt and Road infrastructure initiative. It would connect Malaysia's west coast to rural eastern states. It is largely financed by China and the main contract was awarded in 2016 to the China Communication Construction Company, or CCCC, by former Prime Minister Najib Razak, who was defeated in May 9 elections.

Finance Minister Lim Guan Eng said the project final cost, which is nearly 50 per cent higher than that estimated by the previous government, includes land acquisition, interest, fees and other operational costs. The 81 billion ringgit doesn't include operating costs, he said.

343 infra projects show cost overrun of Rs 2.16 trn over delays: Report

Of the 1,304 projects, 343 reported cost overrun and 262 times escalationPress Trust of India  |  New Delhi Last Updated at July 1, 2018 14:01 IST

As many as 343 infrastructure projects, each worth Rs 1.5 billion or above, have shown cost overrun of Rs 2.16 trillion owing to delays and other reasons, a report said.

It has also been observed that "project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are underreported", according to the report.

The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 1.5 billion and above.

"Total original cost of implementation of the 1,304 projects was Rs 16.21 trillion and their anticipated completion cost is likely to be Rs 18.38 trillion, which reflects overall cost overruns of Rs 2.16 trillion (13.36% of original cost)," The ministry's latest report for February 2018 said.

Of the 1,304 projects, 343 reported cost overrun and 262 times escalation.

According to the report, the expenditure incurred on these projects till February 2018 is Rs 6.36 trillion, which is 34.60 per cent of the anticipated cost of the projects.

While 14 projects are ahead of schedule, 307 are on schedule, 262 are delayed, 343 projects are showing cost overrun and 100 projects are showing both time and cost overrun with respect to original implementation schedules, the report said.

31

Page 33: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

However, it said the number of delayed projects decreased to 222 if the delay is calculated with reference to latest revised schedules of completion.

"For 721 projects, where original/anticipated commissioning date has not been reported, all concerned have been requested to provide the original/anticipated commissioning date so that these projects can be monitored for completion vis-a-vis the targeted dates," the report said.

Of the 262 delayed projects, 53 projects have an overall delay in the range of 1 to 12 months, 55 projects (13-24 months), 83 projects (25-60 months) and 71 projects (61 months and above).

The report attributes the time overrun to a host of issues, including delay in land acquisition, forest clearance, supply of equipment, fund constraint, Maoist incursion, legal cases and law and order situation.

The brief reasons for time overruns as reported by various project implementing agencies are delay in land acquisition, delay in forest clearance, delay in supply of equipment, fund constraints and geological surprises, among others.

Asian Infra Investment Bank to pump in $1.9 bn into various Indian projects"We have another $ 1.9 billion for Indian projects in the pipeline," vice-president and corporate secretary Danny Alexander told.Press Trust of India  |  Mumbai Last Updated at June 20, 2018 22:01 IST

Ahead of the annual meeting of its board of governors here next week, a senior official from the Asian Infrastructure Investment Bank (AIIB) on Wednesday said it will pump $1.9 billion into various Indian projects.

The country, the second largest shareholder in the Beijing-headquartered lender, is already the largest borrower accounting for commitments to the tune of $ 1.2 billion of the overall $ 4.5-billion committed so far.

"We have another $ 1.9 billion for Indian projects in the pipeline," vice-president and corporate secretary Danny Alexander told PTI here.

He said the project pipeline includes an investment in the National Investment and Infrastructure Fund (NIIF), the Mumbai Metro, major irrigation and flood management projects in Bengal, making of Andhra's new capital city Amravathi, and two more projects in Andhra focused on rural roads and urban water supply.

The projects to which the $ 1.2 billion have been committed include a rural connectivity project in MP, Bengaluru Metro, power transmission in Tamil Nadu, rural roads in Gujarat, the power-for-all project in Andhra and a $ 150 -million investment in an infrastructure fund floated by Morgan Stanley, Alexander said.

When asked if the any of these projects will get finalised at the next week's annual meeting, he replied in the negative, saying the bank's directors take a call on the lending proposals and not the governors, which include the finance ministers of all shareholder states.

Alexander said the forthcoming annual meeting, which is the third in its history and the first being held in the country, will concentrate on getting the private sector to play a more active role in funding the infrastructure needs of their respective nations, adding the resources available at AIIB's command may not be sufficient to address such needs.

32

Page 34: Tenders asia july 2018.docx · Web view1. The People’s Republic of Bangladesh has received financing from the toward the cost of Coastal Towns Environmental Infrastructure Project

Global Project News (Asia): July’ 2018

"Infrastructure needs in India and the whole of Asia are so huge that they cannot be only met by the AIIB and by other multilateral agencies and governments," Alexander said.

To achieve the same objective, the summit will be having an Asian Infrastructure Forum, where the member governments will present projects to financiers and other experts for possible deals in the future.

Prime Minister Narendra Modi will be attending the meet being held on June 25-26 in the Nariman Point business district. Over 2,000 delegates from member- countries are expected to attend the two-day summit, which will have 22 seminars on dedicated topics.

A minister from the Chinese finance ministry is expected to represent the largest shareholder of the AIIB, while others attending the meet will include the British Chancellor of the Exchequer Philip Hammond and other ministers from member countries, he said.

The next annual meet of the body is set to be held in Luxemburg, Alexander said, adding non-Asian members have grown to 30, taking the overall memberships to 86 now.

Seeking to dispel misperceptions that is an alternative to the Bretton Woods Institutions like the World Bank and International Monetary Fund, he said the AIIB believes in collaborating with them and working together and not replacing or competing with them.

"We are a partner with the existing institutions and not trying to compete with them," Alexander said, adding a majority of its projects have World Bank or Asian Development Bank as co-financiers.

The AIIB is also interested in eventually taking equity in infra projects, he said, adding the investment in the Morgan Stanley fund is a precursor to the same.

With sovereign wealth funds and pension funds taking an increased interest in the country, he said the infra needs of the country are so high that it requires for infrastructure and the AIIB would like to "crowd-in" investments from other investors in projects.

33