hrm std tstASEHRM Standard Process Test
CUSTOMER: . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . SERIAL NO: . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PROCESS TYPE: . . . …. . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . WAFER CLAMP TYPE: . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . WAFER/ CARRIER SIZE: . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . ASE OPTIONS: LOW
FREQUENCY
FIELD TESTS (see note 2 below)
Note 1: This Test phase should not be started until Test
Specification C4 document has been completed.
Note 2: For Field tests, please perform sections 1 till 5, 9a &
9b only.
Signed
Date
Checked (Process Test Technician)
Base pressure = …………..T
Pass criteria: <5 x 10-6 Torr Chamber leak-up rate = ………..mT/min
(heaters off)
Pass criteria: <0.2 mTorr/min (ideal), <0.5 mTorr/min
(target), <1.0 mTorr/min (maximum limit)
Chamber leak-up rate = ………..mT/min (heaters on) Pass criteria:
<0.5 mTorr/min (ideal), <0.6 mTorr/min (target), <1.5
mTorr/min (maximum limit)
He leak-up rate = ………..mT/min Pass criteria: <15 mT/min ESC,
<15 mT/min WTC, <20 mT/min 200 mm WTC (maximum limit) <10
mT/min ESC, <5 mT/min WTC, <15 mT/min 200 mm WTC (ideal) 95
mm ASE spacers fitted? 20T He backcooling baratron fitted? Foreline
heater temperature setpoint = 65°C Chamber block wall heater
temperature (HCU3) setpoint = 120°C Confinement chamber heater
temperature (HCU7) setpoint = 130°C Gas diffuser heater temperature
(HCU7) setpoint = 150°C Self tune on all HCU7 controllers turned
off. ALM1 function on all HCU7 controllers = ± 20°C Run O2 clean
process on a blank Si wafer for 30 minutes: (40 sccm O2, 40 mT,
MSource 800W, Platen 0W, 10°C platen, 10T He backcooling)
Signature: . . . . . . . . . . . . . . . . Dat e: . . . . . . .
.
ASEHRM Standard Process Test 1. Plasma stability Test
Objective: To demonstrate stable transition between etch and
deposition phases without plasma blinks: 1.1 Load blank silicon
wafer into the chamber. 1.2 Save the following process as “stab”
and run for 14 minutes 59 seconds (62 cycles) , using the
following
tables to record process conditions and whether plasma was
stable.
Stab Process 1 Etch Step Expected Value Pass. Step Expected
Value
Flow: SF6=260sccm , O2=26scc m (9.5s on time + 0s over-run
time)
260, 26 sccm 0 sccm
Flow: C4F8= 80sccm (5s on time + 0s over-run time)
0 sccm 80 sccm
Pressure Ranges 3 ~32mT ~13mT
MSource Power = 2.0KW (etch)/300W (deposition) 4
(forward/reflected) ~2000 - 0W ~300 -0W
Load Position / Tune Position - -
30 W
5 W
He flow = . . . . . . sccm , He pressure (set 9.9T) = . . . . T, He
LUR = ……………..….mT/min, Wall temperature = 120/130/150ºC (set);
Start value:……………………………. End value:…………………….., Platen temperature =
10ºC, Datalog Number: …………………
1 Select passivation step first in recipe 2 Fix APC angle at value
which gives ~ 32 mT at end of etch cycle on blank Si wafer 3 Record
pressure swings during etch and dep steps i.e. max and min
pressures. 4 Record forward and reflected power from screen i.e. if
fwd power = 1995W and reflected is 12W then write “1995-12” 5 NOTE.
Systems with electrostatic clamping should not display a Vdc
reading. Check that the limit in the software is set to 200W.
ASEHRM Standard Process Test 1.3 Plasma stability Record: Was
plasma stable or flashing on and off in following steps?
Step Plasma Behaviour 6
Pass/ etch transition
Checks to be performed at generator display/output, not at VDU. For
AE 3 KW generators, checks may be performed at the operator station
VDU. Note down the minimum value of the reflected power. Examine
the datalog files for any discrepancies.
Etch Step Target Pass Step Target Plasma blink time at start of
step (<1 s) (<1 s) Number of blinks ( ≤1) ( ≤1) Minimum
reflected MSource Power (<20 W) (<40 W)
If the system fails to meet the pass criteria and you change
settings and/or perform hardware modifications, return and repeat
all previous plasma stability checks (standard tests section C4),
to ensure they still meet the targets. Signature: . . . . . . . . .
. . . . . . . Dat e: . . . . . . . .
6 E.g. Record stable if plasma shows no evidence of flickering or
flashing on/off during each etch or passivation cycle, record
blinks if plasma goes off completely and record slight flicker if
the plasma flickers during steps or during transitions between
steps.
ASEHRM Standard Process Test 2. Wafer Temperature Test
(Only complete if not already carried out in Test Procedure C. If
not performed, please copy results from part C into table
2.3.2)
Objective: Ensure correct operation of substrate temperature
control system and wafer temperature ≤77°C. 2.1 Standard wafer
temperature test. You will need 1 blank Si wafer and temperature
dots, ranges 1 till 4. 2.2 Mount temperature dots in the range 40ºC
to 110ºC (ranges 1 till 4) at 5 positions on the wafers. The 5
positions are the centre and 4 edges - major flat, opposite major
flat, left and right sides. The dots at the edges should be 7 mm
from the edge of the wafer. Cover the dots with polyimide tape. The
polyimide tape should cover 6 ±±±± 1 mm around the edges of each
label. Then pierce the tape with a scalpel/blade to allow trapped
air to escape. 2.3.1 Run the following process called ‘temp’ for 15
minutes 8 seconds (79 cycles) and use the following table to
record process conditions:
Temp Process 7 Etch Step Expected Value Pass. Step Expected
Value
Flow: SF6=450sccm , O2=45sccm (8.5s on time + 0s over-run
time)
450, 45 sccm 0 sccm
Flow: C4F8=200sccm (3s on time + 0s over-run time)
0 sccm 200 sccm
Pressure Ranges 9 ~32-28mT ~14-13mT
MSource Power = 2.2KW (etch)/1.5KW (deposition) 10
(forward/reflected) ~2200 - 0W ~1500 -0W
Load Position / Tune Position - -
40 W
20 W
2.5s/2A/………V 0
He flow = . . . . . . sccm , He pressure (set 9.9T) = . . . . T, He
LUR = ……………..….mT/min, Wall temperature = 120/130/150ºC (set);
Start value:……………………………. End value:…………………….., Platen temperature =
10ºC, Datalog Number: …………………
2.3.2 Record the dots, which have turned black (corresponding to
the temperature reached), in the table below: Centre Left Right
Major Flat Opposite
Major Flat
7 Select passivation step first in recipe 8 Fix APC angle at value
which gives ~ 30 mT at end of etch cycle on blank Si wafer 9 Record
pressure swings during etch and dep steps i.e. max and min
pressures. 10 Record forward and reflected power from screen i.e.
if fwd power = 2199W and reflected is 12W then write “2199-12” 11
NOTE. Systems with electrostatic clamping should not display a Vdc
reading. Check that the limit in the software is set to 200W.
ASEHRM Standard Process Test Blank Si wafer
Final temperature
For pass criteria, please see ASE-HRM specification quality
document. 2.3.3 Plasma stability Record: Checks to be performed at
generator display/output, not at VDU. For AE 3 KW generators,
checks may be performed at the operator station VDU. Note down the
minimum value of the reflected power. Examine the datalog files for
any discrepancies.
Etch Step Target Pass Step Target Plasma blink time at start of
step (<1 s) (<1 s) Number of blinks ( ≤1) ( ≤1) Minimum
reflected MSource Power (<20 W) (<40 W)
If the system fails to meet the pass criteria and you change
settings and/or perform hardware modifications, return and repeat
all previous plasma stability checks (standard tests section C4),
to ensure they still meet the targets.
ASEHRM Standard Process Test 3. Low Temperature Chiller Test
(Only complete if not already carried out in Test P rocedure
C)
Objective: Check performance of systems running at sub-zero platen
temperatures and to confirm that low temperature operation does not
affect He seal. 3.1 To test He leak-up rate (LUR) without RF. Load
a blank silicon wafer into the chamber and set He pressure to
9.9 Torr. Record the leak-up rate (LUR) values at the various
temperatures shown below. 3.2 Note that chamber LUR tests to be
done without a wafer in the chamber and He LUR tests with a wafer
in the
chamber. 3.3 When reducing temperature, use a temperature ramp rate
of -1°C/min on Huber chillers. On other chillers
change the setpoint as required. After changing chiller
temperature, leave time for system to stabilise. On Huber chillers,
to reduce temperature press “RAMP” and then “TEMP”. Enter the
required temperature and press “ENTER.” Then set the ramping rate
by pressing “TIME” and entering the time, which the chiller should
take to get to this temperature, followed again, by “ENTER.”
3.4 Please record data in the table below:
Temperature °C He LUR (mT/min) Chamber LUR (mT/min) 20 0
-10 -20
Pass criteria:
Chamber LUR: ≤≤≤≤ 1.5 mT/min (maximum limit - hot) HeLUR: <15
mT/min ESC, <15 mT/min WTC, <20 mT/min 200 mm WTC (maximum
limit) <10 mT/min ESC, <5 mT/min WTC, <15 mT/min 200 mm
WTC (ideal)
Signature: . . . . . . . . . . . . . . . . Dat e: . . . . . . .
.
Objective: To achieve uniform polymer deposition at the expected
deposition rate.
4.1 Save the following process as “dep”, and determine fixed APC
position by loading blank silicon wafer into
chamber and adjusting APC to get desired pressure with RF on. APC
Angle: ……….. °°°°
4.2 With these process parameters run one blank silicon wafer for 3
minutes, using the following tables to record
process conditions. 4.3 As an alternative to scratching the polymer
off to measure the step height (as in section 4.5), please
place
squares of polyimide tape (1cm square) at 5 positions on the wafer
(centre and 4 edges- major flat, opposite major flat, left and
right sides).
Note: Major wafer flat must be towards load lock.
Dep Process Recorded process parameters
Flow: C4F8=130sccm (unswitched)
MSource Power = 300W (Auto match): (forward/reflected)
Load
Tune
Load
Tune
Vpp
Vdc
He LUR
Datalog number
4.4 Please record below whether the deposited polymer looks
uniform:
ASEHRM Standard Process Test 4.5 Plasma stability Pass Criteria:
Checks to be performed at generator display/output, not at VDU. For
AE 3 KW generators, checks may be performed at the operator station
VDU. Note down the minimum value of the reflected power. Examine
the datalog files for any discrepancies.
Value Target Minimum reflected MSource Power (<20 W )
If the system fails to meet the pass criteria and you change
settings and/or perform hardware modifications, return and repeat
all previous plasma stability checks (standard tests section C4),
to ensure they still meet the targets. 4.6 Measure the wafer and
record in the table below. Write on the back, the process name,
platen power and
system serial number and store in a disposable wafer box. 4.6.1
Note: (a) Edge measurements should be made 5 mm in from the wafer
edge. (i.e. 5 mm edge exclusion).
(b) Scratch surface with tweezers and remove debris, to provide
step for measurement. Or remove the squares of polyimide
tape.
(c) If possible use Tencor P2 profilometer program recipe “Leedep”
or P10 profilometer. 4.6.2 Results:
Position Polymer thickness (Å)
For pass criteria, please see ASE-HRM specification quality
document.
Note: Uniformity (±…%) = ± {(max – min)/(2 × average)} × 100
Signature: . . . . . . . . . . . . . . . . Dat e: . . . . . . .
.
5. Standard SF 6 Etch Rate Tests Objective: To attain Si etch rate
of the expected value. 5.1 Using a resist pen or poly tape pattern
three new blank silicon wafers as shown below. Note: (a) ~1cm x 1cm
squares with edge exclusion of 5 mm LR
ASEHRM Standard Process Test (b) Leave to dry for 10 minutes 5.2
Save the following process as “etch1”, and carry out a 3 minute
conditioning run prior to the main test on a
blank silicon wafer. Determine fixed APC position by adjusting APC
to get desired pressure with RF on. APC Angle: ……….°°°°
Recipe etch 1; EM1 = 0A Recipe etch 2; EM1 = 2.5A Recipe etch 3;
EM1 = 3.4A
ASEHRM Standard Process Test 5.3 With the same process parameters
then run the new patterned silicon wafers for 3 minutes each. Use
the
following table to record process conditions:
etch1 Process 12 EM1=0A EM1=2.5A EM1=3.4A
Flow: SF6=260sccm (unswitched)
MSource Power = 2000W (Auto match): (forward/reflected)
Load
Tune
Load
Tune
Vpp
Vdc
Platen 10°C
He LUR
Datalog number
5.4 Plasma Stability Record: Checks to be performed at generator
display/output, not at VDU. For AE 3 KW generators, checks may be
performed at the operator station VDU. Note down the minimum value
of the reflected power. Examine the datalog files for any
discrepancies.
Value Target Minimum reflected MSource Power (EM1=0A) (<20 W )
Minimum reflected MSource Power (EM1=2.5A) (<20 W ) Minimum
reflected MSource Power (EM1=3.4A) (<20 W )
If the system fails to meet the pass criteria and you change
settings and/or perform hardware modifications, return and repeat
all previous plasma stability checks (standard tests section C4),
to ensure they still meet the targets. 5.5 Measure the wafer and
record in the table below. Mark on the back, the process name,
platen power and
system serial number and store in a disposable wafer box. 5.5.1
Note: (a) Remove resist using acetone soaked wipe.
ASEHRM Standard Process Test (b) Tencor P2 profilometer. Recipe
“LeeEtch” or P10 profilometer. (c) Measure etch step 5 mm from
wafer edge (i.e. 5 mm edge exclusion).
5.5.2 Record Etch Step in µm:
Position EM1=0A EM1=2.5A EM1=3.4A
Centre
Left
Right
Uniformity (±…%)
Note: Uniformity (±…%) = ± {(max – min)/(2 × average)} × 100 5.5.3
Pass criteria 1: SF6 etch rate at with current on (2.5 A and 3.4 A)
should be less than etch rate with no current (0A) i.e. [etch rate
(2.5A and 3.4 A) < etch rate (0A)].
Yes No Pass criteria 2: Etch rate difference (2.5 A and 0A) should
fall within this margin:
0.2 µm/min ≤ [etch rate (0A)-etch rate (2.5A)] ≤ 0.8 µm/min Does
etch rate difference fall within this margin? Yes No For further
pass criteria, please see ASE-HRM speci fication quality document.
Signature: . . . . . . . . . . . . . . . . Dat e: . . . . . . .
.
ASEHRM Standard Process Test 6. Standard Silicon Trench Profile
Tests
Objective: To confirm basic switched ASE process meets expected
performance level in ‘cold’ or ‘hot’ state. Note: These tests are
only carried out on systems before shipment from STS. You will
need:
100 mm platen: 2 whole 100 mm STS patterned test wafers 150 mm
platen: 2 whole 150 mm STS patterned test wafers + 1x ¼ piece of a
100 mm STS patterned test
wafer (see appendix A) 125 mm and 200 mm platens: 2 whole 100 mm
STS patterned test wafers respectively
cool-grease mounted onto photoresist coated silicon wafers.
Note: Use whole STS patterned test wafers with ~4 µµµµm thick
mask.
ASEHRM Standard Process Test 6(a): Switched COLD TEST
Ensure chamber is in a cold” state 13 Please tick box if using a
quarter piece (e.g. for fault investigation)
6a.1 Measure the resist thickness on the Nanospec before etching,
recording the results in the table overleaf. 6a.2 Run the following
switch process for 15 minutes 8 seconds (79 cycles) and record the
process parameters
in following table:
Switch Process 14 Etch Step Expected Value Pass. Step Expected
Value
Flow: SF6=450sccm , O2=45sccm (8.5s on time + 0s over-run
time)
450, 45 sccm 0 sccm
Flow: C4F8=200sccm (3s on time + 0s over-run time)
0 sccm 200 sccm
Pressure Ranges 16 ~32-28mT ~14-13mT
MSource Power = 2.2KW (etch)/1.5KW (deposition) 17
(forward/reflected) ~2200 - 0W ~1500 -0W
Load Position / Tune Position - -
40 W
20 W
2.5s/2A/……….V 0
He flow = . . . . . . sccm , He pressure (set 9.9T) = . . . . T, He
LUR = ……………..….mT/min, Wall temperature = 120/130/150ºC (set);
Start value:……………………………. End value:…………………….., Platen temperature =
10ºC, Datalog Number: …………………
13 No RF. should have been run on the system in the previous 2
hours.
14 Select passivation step first in recipe 15 Fix APC angle at
value which gives ~ 30 mT at end of etch cycle on blank Si wafer 16
Record pressure swings during etch and dep steps i.e. max and min
pressures. 17 Record forward and reflected power from screen i.e.
if fwd power = 2199W and reflected is 12W then write “2199-12” 18
NOTE. Systems with electrostatic clamping should not display a Vdc
reading. Check that the limit in the software is set to 200W.
ASEHRM Standard Process Test 6a.3 Plasma Stability Record: Checks
to be performed at generator display/output, not at VDU. For AE 3
KW generators, checks may be performed at the operator station VDU.
Note down the minimum value of the reflected power. Examine the
datalog files for any discrepancies.
Etch Step Target Pass Step Target Plasma blink time at start of
step (<1 s) (<1 s) Number of blinks ( ≤1) ( ≤1) Minimum
reflected MSource Power (<20 W) (<40 W)
If the system fails to meet the pass criteria and you change
settings and/or perform hardware modifications, return and repeat
all previous plasma stability checks (standard tests section C4),
to ensure they still meet the targets. Resist Measurements. 6a.4
Re-measure resist thickness after etching and calculate selectivity
from the measured depth (below).
Position Pre-etch thickness
C L R MF OMF
6a.5 Cleave wafer through centre and major flat and measure, on a
SEM, the dimensions of the cross-section of
two different sized trenches. Please record the results below:
Results - switch process on STS test wafer
Feature Size
Depth (µm)
Profile Angle (°)
Undercut (Å/edge)
Scallops (Å)
Centre 40 µm 5 µm Major 40 µm flat 5 µm
Profile angle = 90 – tan-1{(top width – bottom width)/(2 × depth)}
RIE lag = (5 µm feature depth)/(40 µm feature depth) 40 µm: Average
etch rate =……………µm/min ±……….% 5 µm: Average etch rate =……………µm/min
±……….% RIE lag (5/40) = ………………… For pass criteria, please see
ASE-HRM specification quality document. Attach SEMs here.
Signature: . . . . . . . . . . . . . . . . Dat e: . . . . . . .
.
ASEHRM Standard Process Test 6(b): Switched HOT TEST
Ensure chamber is in a “hot” state 6b.1 Measure the resist
thickness on the Nanospec before etching, recording the results in
the table overleaf.
Please tick box if using a quarter piece (e.g. for fault
investigation) 6b.2 Heating the chamber: Run the following process
with 600W power during th e etch and deposition
steps, for 90 minutes on a 2 separate blank Si wafe rs (45 minutes
each). 6b.3 Immediately run the following switch process for 15
minutes 8 seconds (79 cycles) and record the process
parameters in following table:
Switch Process 19 Etch Step Expected Value Pass. Step Expected
Value
Flow: SF6=450sccm , O2=45sccm (8.5s on time + 0s over-run
time)
450, 45 sccm 0 sccm
Flow: C4F8=200sccm (3s on time + 0s over-run time)
0 sccm 200 sccm
Pressure Ranges 21 ~32-28mT ~14-13mT
MSource Power = 2.2KW (etch)/1.5KW (deposition) 22
(forward/reflected) ~2200 - 0W ~1500 -0W
Load Position / Tune Position - -
40 W
20 W
2.5s/2A/……….V 0
He flow = . . . . . . sccm , He pressure (set 9.9T) = . . . . T, He
LUR = ……………..….mT/min, Wall temperature = 120/130/150ºC (set);
Start value:……………………………. End value:…………………….., Platen temperature =
10ºC, Datalog Number: …………………
6b.4 Plasma Stability Record: Checks to be performed at generator
display/output, not at VDU. For AE 3 KW generators, checks may be
performed at the operator station VDU. Note down the minimum value
of the reflected power. Examine the datalog files for any
discrepancies.
Etch Step Target Pass Step Target
19 Select passivation step first in recipe 20 Fix APC angle at
value which gives ~ 30 mT at end of etch cycle on blank Si wafer 21
Record pressure swings during etch and dep steps i.e. max and min
pressures. 22 Record forward and reflected power from screen i.e.
if fwd power = 2199W and reflected is 12W then write “2199-12” 23
NOTE. Systems with electrostatic clamping should not display a Vdc
reading. Check that the limit in the software is set to 200W.
ASEHRM Standard Process Test Plasma blink time at start of step
(<1 s) (<1 s) Number of blinks ( ≤1) ( ≤1) Minimum reflected
MSource Power (<20 W) (<40 W)
If the system fails to meet the pass criteria and you change
settings and/or perform hardware modifications, return and repeat
all previous plasma stability checks (standard tests section C4),
to ensure they still meet the targets. Resist Measurements. 6b.5
Re-measure resist thickness after etching and calculate selectivity
from the measured depth (below).
Position Pre-etch thickness
C L R MF OMF
6b.6 Cleave wafer through centre and major flat and measure, on a
SEM, the dimensions of the cross-section of
two different sized trenches. Please record the results below:
Results - switch process on STS test wafer
Feature Size
Depth (µm)
Profile Angle (°)
Undercut (Å/edge)
Scallops (Å)
Centre 40 µm 5 µm Major 40 µm flat 5 µm
Profile angle = 90 – tan-1{(top width – bottom width)/(2 × depth)}
RIE lag = (5 µm feature depth)/(40 µm feature depth) 40 µm: Average
etch rate =……………µm/min ±……….% 5 µm: Average etch rate =……………µm/min
±……….% RIE lag (5/40) = ………………… Hot-cold wafer-wafer uniformity: 40
µm = ±……….%
5 µm = ±…….….% For pass criteria, please see ASE-HRM specification
quality document. Attach SEMs here. Signature: . . . . . . . . . .
. . . . . . Dat e: . . . . . . . .
ASEHRM Standard Process Test 7. Deep Silicon Trench Profile
Tests
Objective: To confirm that deep switched ASE process meets expected
performance level.
Note: Use whole STS patterned test wafers with ~8 µµµµm thick mask.
Please tick box if using a quarter piece (e.g. for fault
investigation)
7.1 Measure the resist thickness on the Nanospec before etching,
recording the results in the table overleaf. 7.2 Run the following
deep process for 45 minutes 2 seconds (235 cycles) and record the
process parameters
in following table:
Deep Process 24 Etch Step Expected Value Pass. Step Expected
Value
Flow: SF6=450sccm, O 2=45sccm (8.5s on time + 0s over-run
time)
450, 45 sccm 0 sccm
Flow: C4F8=200sccm (3s on time + 0s over-run time)
0 sccm 200 sccm
Pressure Ranges 26 ~32-28mT ~14-13mT
MSource Power = 2.2KW (etch)/1 .5KW (deposition) 27
(forward/reflected) ~2200 - 0W ~1500 -0W
Load Position / Tune Position - -
40 W
20 W
2.5s/2A/……….V 0
He flow = . . . . . . sccm , He pressure (set 9.9T) = . . . . T, He
LUR = ……………..….mT/min, Wall temperature = 120/130/150ºC (set);
Start value:……………………………. End value:…………………….., Platen temperature =
10ºC, Datalog Number: …………………
24 Select passivation step first in recipe 25 Fix APC angle at
value which gives ~ 30 mT at end of etch cycle on blank Si wafer 26
Record pressure swings during etch and dep steps i.e. max and min
pressures. 27 Record forward and reflected power from screen i.e.
if fwd power = 2199W and reflected is 12W then write “2199-12” 28
NOTE. Systems with electrostatic clamping should not display a Vdc
reading. Check that the limit in the software is set to 200W.
ASEHRM Standard Process Test 7.3 Plasma Stability Record: Checks to
be performed at generator display/output, not at VDU. For AE 3 KW
generators, checks may be performed at the operator station VDU.
Note down the minimum value of the reflected power. Examine the
datalog files for any discrepancies.
Etch Step Target Pass Step Target Plasma blink time at start of
step (<1 s) (<1 s) Number of blinks ( ≤1) ( ≤1) Minimum
reflected MSource Power (<20 W) (<40 W)
If the system fails to meet the pass criteria and you change
settings and/or perform hardware modifications, return and repeat
all previous plasma stability checks (standard tests section C4),
to ensure they still meet the targets. Resist Measurements. 7.4
Re-measure resist thickness after etching and calculate selectivity
from the measured depth (below).
Position Pre-etch thickness
C L R MF OMF
7.5 Cleave wafer through centre and major flat and measure, on a
SEM, the dimensions of the cross-section of
two different sized trenches. Please record the results below:
Results -Deep process on STS test wafer
Feature Size
Depth (µm)
5 µm Major flat
80 µm 50 µm
5 µm Profile angle = 90 – tan-1{(top width – bottom width)/(2 ×
depth)} RIE lag = (5 um feature depth)/(80 um feature depth) 80 µm:
Average etch rate =……………µm/min ±……….% 50 µm: Average etch rate
=……………µm/min ±……….% 5 µm: Average etch rate =……………µm/min ±……….% RIE
lag (5/80) = ………………… For pass criteria, please see ASE-HRM
specification quality document. If there is grass at the bottom or
notching at the top of any trenches, then please perform the altern
ative deep etch test in appendix B. Otherwise proceed to sect ion
8. Attach SEMs here. Signature: . . . . . . . . . . . . . . . . Dat
e: . . . . . . . .
ASEHRM Standard Process Test 8. Smooth etch process test
Objective: To confirm that smooth switched ASE process meets
expected performance level.
Note: Use whole STS patterned test wafers with ~4 µµµµm thick mask.
Please tick box if using a quarter piece (e.g. for fault
investigation)
8.1 Measure the resist thickness on the Nanospec before etching,
recording the results in the table overleaf. 8.2 Run the following
smooth process for 5 minutes 15 seconds (63 cycles) and record the
process parameters
in following table:
smooth Process 29 Etch Step Expected Value Pass. Step Expected
Value
Flow: SF6=450sccm , O2=45sccm (3s on time + 0s over-run time)
450, 45 sccm 0 sccm
Flow: C4F8=200sccm (2s on time + 0s over-run time)
0 sccm 200 sccm
MSource Power = 3.0KW (etch)/1.0KW (deposition) 32
(forward/reflected) ~3000 - 0W ~1000 -0W
Load Position / Tune Position - -
45 W
0 W
0s/1A/……….V 0
He flow = . . . . . . sccm , He pressure (set 9.9T) = . . . . T, He
LUR = ……………..….mT/min, Wall temperature = 120/130/150ºC (set);
Start value:……………………………. End value:…………………….., Platen temperature =
0ºC, Datalog Number: …………………
8.3 Plasma Stability Record: Checks to be performed at generator
display/output, not at VDU. For AE 3 KW generators, checks may be
performed at the operator station VDU. Note down the minimum value
of the reflected power. Examine the datalog files for any
discrepancies.
Etch Step Target Pass Step Target
29 Select passivation step first in recipe 30 Fix APC angle at
value which gives ~ 41 mT at end of etch cycle on blank Si wafer 31
Record pressure swings during etch and dep steps i.e. max and min
pressures. 32 Record forward and reflected power from screen i.e.
if fwd power = 2997W and reflected is 12W then write “2997-12” 33
NOTE. Systems with electrostatic clamping should not display a Vdc
reading. Check that the limit in the software is set to 200W.
ASEHRM Standard Process Test Plasma blink time at start of step
(<1 s) (<1 s) Number of blinks ( ≤1) ( ≤1) Minimum reflected
MSource Power (<20 W) (<40 W)
If the system fails to meet the pass criteria and you change
settings and/or perform hardware modifications, return and repeat
all previous plasma stability checks (standard tests section C4),
to ensure they still meet the targets. Resist Measurements. 8.4
Re-measure resist thickness after etching and calculate selectivity
from the measured depth (below).
Position Pre-etch thickness
C L R MF OMF
8.5 Cleave wafer through centre and major flat and measure, on a
SEM, the dimensions of the cross-section of
two different sized trenches. Please record the results below:
Results - smooth process on 'Cronos' wafer
Feature Size
Depth (µm)
Grass? (any trench)
Centre 5 µm 2 µm Major 5 µm flat 2 µm
Profile angle = 90 – tan-1{(top width – bottom width)/(2 × depth)}
RIE lag = (2 um feature depth)/(5 um feature depth) 5 µm: Average
etch rate =……………µm/min ±……….% 2 µm: Average etch rate =……………µm/min
±……….% RIE lag (2/5) = ………………… For pass criteria, please see
ASE-HRM specification quality document. Attach SEMs here.
Signature: . . . . . . . . . . . . . . . . Dat e: . . . . . . .
.
ASEHRM Standard Process Test 9 (a). Pulsing compensation
Objective: To set up pulse generator to achieve required pulse duty
cycle. N/A 9a.1 Connect a RF sniffer in series with the RF output
(J1) of the LF5 generator and view the signal on an oscilloscope.
9a.2 Run a LF process such as lfhrm (see section 9c) and freeze the
signal during the etch cycle. 9a.3 Note down the delay times for
various duty cycles and increase the pulse width using the pulse
generator as necessary in order to achieve the correct duty cycle.
Fill out the table below. Then use these compensated values, if
necessary, for all LF pulsed standard tests. Consult a process
engineer for clarification if required.
Duty cycle required Compensated on-time required (ms)
Compensated off-time required (ms)
15% (5 ms on, 25 ms off) 20% (5 ms on, 20 ms off) 25% (5 ms on, 15
ms off) 33% (5 ms on, 10 ms off) 50% (5 ms on, 5 ms off)
9 (b) For systems with capability to run platen at low frequency
9b.1 Using lfhrm conditions (see section 9c). Please select low
380KHz option in recipe editor and ensure remote switching enabled
on hardware. 9b.2 Unpulsed
Run for 30 minutes and obtain datalog file. Pass criteria: Load and
Tune positions are stable and within 20% and 80% limits. OK?
Plasma stability Record: Checks to be performed at generator
display/output, not at VDU. For AE 3 KW generators, checks may be
performed at the operator station VDU. Etch Step Target Pass Step
Target Plasma blink time at start of step (<1 s) (<1 s)
Number of blinks (≤ 1) ( ≤ 1) Minimum reflected MSource Power
(<5 W) (<15 W)
Datalog file details: 9b.3 Pulsed at 5ms pulse width and 33%
duty-cycle Run for 30 minutes and obtain datalog file. Use
compensated pulse set-up if necessary, according to section
3(a). Pass criteria: Load and Tune positions are stable and within
20% and 80% limits. OK?
Plasma stability Record: Checks to be performed at generator
display/output, not at VDU. For AE 3 KW generators, checks may be
performed at the operator station VDU. Etch Step Target Pass Step
Target Plasma blink time at start of step (<1 s) (<1 s)
Number of blinks (≤ 1) ( ≤ 1) Minimum reflected MSource Power
(<20 W) (<40 W)
Datalog file details: Signature: . . . . . . . . . . . . . . . .
Dat e: . . . . . . . .
ASEHRM Standard Process Test 9 (c). SOI test
Objective: To confirm that SOI feature controls notching at
Si/oxide interface. N/A Note: Use 1/8 piece of SOI wafer (20 µm
thick SOI, 150 mm diameter test wafers) mounted onto a resist
coated oxide carrier with cool-grease.
Please tick box if using a 1/16 piece (e.g. for fau lt
investigation)
9c.1 Measure the resist thickness on the Nanospec before etching,
recording the results in the table overleaf. 9c.2 Run the following
lfhrm process for 5 minutes 40 seconds = 68 cycles (estimated ~20%
overetch) and
record the process parameters in following table:
lfhrm Process 34 Etch Step Expected Value Pass. Step Expected
Value
Flow: SF6=450sccm , O2=45sccm (3s on time + 0s over-run time)
450, 45 sccm 0 sccm
Flow: C4F8=100sccm (2s on time + 0s over-run time)
0 sccm 100 sccm
Pressure Ranges 36 ~37mT ~11mT
MSource Power = 3.0KW (etch)/1.0W (deposition) 37
(forward/reflected) ~3000 - 0W ~1000 -0W
Load Position / Tune Position - -
(LF 5 ms 20% duty cycle)
45 W
0 W
1A 0
He flow = . . . . . . sccm , He pressure (set 9.9T) = . . . . T, He
LUR = ……………..….mT/min, Wall temperature = 120/130/150ºC(set); Start
value:……………………………. End value:…………………….., Platen temperature = 10ºC,
Datalog Number: …………………
9c.3 Plasma Stability Record: Checks to be performed at generator
display/output, not at VDU. For AE 3 KW generators, checks may be
performed at the operator station VDU. Note down the minimum value
of the reflected power. Examine the datalog files for any
discrepancies.
34 Select passivation step first in recipe 35 Fix APC angle at
value which gives ~ 41 mT at end of etch cycle on blank Si wafer 36
Record pressure swings during etch and dep steps i.e. max and min
pressures. 37 Record forward and reflected power from screen i.e.
if fwd power = 2997W and reflected is 12W then write “2997-12” 38
NOTE. Systems with electrostatic clamping should not display a Vdc
reading. Check that the limit in the software is set to 200W.
ASEHRM Standard Process Test Etch Step Target Pass Step Target
Plasma blink time at start of step (<1 s) (<1 s) Number of
blinks ( ≤1) ( ≤1) Minimum reflected MSource Power (<20 W)
(<40 W)
If the system fails to meet the pass criteria and you change
settings and/or perform hardware modifications, return and repeat
all previous plasma stability checks (standard tests section C4),
to ensure they still meet the targets. Resist Measurements. 9c.4
Re-measure resist thickness after etching and calculate selectivity
from the measured depth (below).
Position Pre-etch thickness
Centre Edge
9c.5 Cleave wafer through centre and major flat and measure, on a
SEM, the dimensions of the cross-section of
the 3 µm sized trenches. Please record the results below: Results
-lfhrm process
Feature Size
Depth (µm)
3 µm
Profile angle = 90 – tan-1{(top width – bottom width)/(2 × depth)}
Average etch rate (including overetch) =……………µm/min For pass
criteria, please see ASE-HRM specification quality document. Notch
width/edge should be ≤≤≤≤0.35 µµµµm. If notch width/edge > 0.35
µm, is depth <20 µm?
Yes then proceed to section 10.
No then perform test in appendix C before proceeding to section
10.
Attach SEMs here. Signature: . . . . . . . . . . . . . . . . Dat e:
. . . . . . . .
ASEHRM Standard Process Test 10. Final Checks
10.1 Final Chamber Vacuum Check: 10.2 Chamber base pressure (<5
x 10-6 Torr) . . . . . . . . . . Torr 10.3 Chamber leak-up rate
(<1.0 mTorr/min) . . . . . . . . . mTorr/ min (with heaters on)
[from base pressure averaged over a minimum of 3 minutes]
Signature: . . . . . . . . . . . . . . . . Dat e: . . . . . . . .
10.4 Is ECN Activity Sheet up to date (i.e. all ECNs affecting
machine listed & signed off if completed on machine). YES 10.5
List all outstanding ECNs that have yet to be actioned: . . . . . .
. . . . . . . . . . . . . . . . . . . . . . Signature: . . . . . .
. . . . . . . . . . Dat e: . . . . . . . .
10.6 Please record all faults on the process fault sheet or in a
notepad document and attach a hard-copy to this document on
handover. 10.7 Please summarise the results in the table provided
in the ASE-HRM summary quality document QD000118.
Specifications for 100mm and 150 mm systems can be found in the
ASE-HRM specification quality document TS000012.
10.8 Provided all sections of this document & the Safety
Certificate have been completed the machine may be handed over to
the Process Department. Signature: . . . . . . . . . . . . . . . .
Dat e: . . . . . . . .
ASEHRM Standard Process Test APPENDIX A: Switched COLD TEST
This test is only to be performed on 150 mm systems . Please use a
¼ piece of a 100 mm STS patterned test wafer mounted on a 150 mm
resist coated carrier. Ensure chamber is in a cold” state 39.
A.1 Measure the resist thickness on the Nanospec before etching,
recording the results in the table overleaf. A.2 Run the following
switch process for 15 minutes 8 seconds (79 cycles) and record the
process parameters
in following table:
Switch Process 40 Etch Step Expected Value Pass. Step Expected
Value
Flow: SF6=450sccm , O2=45sccm (8.5s on time + 0s over-run
time)
450, 45 sccm 0 sccm
Flow: C4F8=200sccm (3s on time + 0s over-run time)
0 sccm 200 sccm
Pressure Ranges 42 ~32-28mT ~14-13mT
MSource Power = 2.2KW (etch)/1.5KW (deposition) 43
(forward/reflected) ~2200 - 0W ~1500 -0W
Load Position / Tune Position - -
40 W
20 W
2.5s/2A/……….V 0
He flow = . . . . . . sccm , He pressure (set 9.9T) = . . . . T, He
LUR = ……………..….mT/min, Wall temperature = 120/130/150ºC (set);
Start value:……………………………. End value:…………………….., Platen temperature =
10ºC, Datalog Number: …………………
39 No RF. should have been run on the system in the previous 2
hours.
40 Select passivation step first in recipe 41 Fix APC angle at
value which gives ~ 30 mT at end of etch cycle on blank Si wafer 42
Record pressure swings during etch and dep steps i.e. max and min
pressures. 43 Record forward and reflected power from screen i.e.
if fwd power = 2199W and reflected is 12W then write “2199-12” 44
NOTE. Systems with electrostatic clamping should not display a Vdc
reading. Check that the limit in the software is set to 200W.
ASEHRM Standard Process Test A.3 Plasma Stability Record: Checks to
be performed at generator display/output, not at VDU. For AE 3 KW
generators, checks may be performed at the operator station VDU.
Note down the minimum value of the reflected power. Examine the
datalog files for any discrepancies.
Etch Step Target Pass Step Target Plasma blink time at start of
step (<1 s) (<1 s) Number of blinks ( ≤1) ( ≤1) Minimum
reflected MSource Power (<20 W) (<40 W)
If the system fails to meet the pass criteria and you change
settings and/or perform hardware modifications, return and repeat
all previous plasma stability checks (standard tests section C4),
to ensure they still meet the targets. Resist Measurements. A.4
Re-measure resist thickness after etching and calculate selectivity
from the measured depth (below).
Position Pre-etch thickness
C L R MF OMF
A.5 Cleave wafer through centre and major flat and measure, on a
SEM, the dimensions of the cross-section of
two different sized trenches. Please record the results below:
Results - switch process on STS test wafer
Feature Size
Depth (µm)
Profile Angle (°)
Undercut (Å/edge)
Scallops (Å)
Centre 40 µm 5 µm Major 40 µm flat 5 µm
Profile angle = 90 – tan-1{(top width – bottom width)/(2 × depth)}
RIE lag = (5 µm feature depth)/(40 µm feature depth) 40 µm: Average
etch rate =……………µm/min ±……….% 5 µm: Average etch rate =……………µm/min
±……….% RIE lag (5/40) = ………………… For pass criteria, please see
ASE-HRM specification quality document. Attach SEMs here.
ASEHRM Standard Process Test Signature: . . . . . . . . . . . . . .
. . Dat e: . . . . . . . .
APPENDIX B - ALTERNATIVE DEEP ETCH TEST This test is only to be run
if deep etch test 7a fa ils. N/A
B.1 Run the following deep process for 45 minutes 2 seconds (235
cycles) and record the process parameters
in following table:
Deep Process 45 Etch Step Expected Value Pass. Step Expected
Value
Flow: SF6=450sccm (8.5s on time + 0s over-run time)
450 sccm 0 sccm
0 sccm 200 sccm
Pressure Ranges 47 ~32-28mT ~14-13mT
MSource Power = 2.2KW (etch)/1.5KW (deposition) 48
(forward/reflected) ~2200 - 0W ~1500 -0W
Load Position / Tune Position - -
(forward/reflected)
2.5s/2A/……….V 0
He flow = . . . . . . sccm , He pressure (set 9.9T) = . . . . T, He
LUR = ……………..….mT/min, Wall temperature = 120/130/150ºC (set);
Start value:……………………………. End value:…………………….., Platen temperature =
0ºC, Datalog Number: …………………
45 Select passivation step first in recipe 46 Fix APC angle at
value which gives ~ 30 mT at end of etch cycle on blank Si wafer 47
Record pressure swings during etch and dep steps i.e. max and min
pressures. 48 Record forward and reflected power from screen i.e.
if fwd power = 2199W and reflected is 12W then write “2199-12” 49
NOTE. Systems with electrostatic clamping should not display a Vdc
reading. Check that the limit in the software is set to 200W.
ASEHRM Standard Process Test B.2 Plasma Stability Record: Checks to
be performed at generator display/output, not at VDU. For AE 3 KW
generators, checks may be performed at the operator station VDU.
Note down the minimum value of the reflected power. Examine the
datalog files for any discrepancies.
Etch Step Target Pass Step Target Plasma blink time at start of
step (<1 s) (<1 s) Number of blinks ( ≤1) ( ≤1) Minimum
reflected MSource Power (<20 W) (<40 W)
If the system fails to meet the pass criteria and you change
settings and/or perform hardware modifications, return and repeat
all previous plasma stability checks (standard tests section C4),
to ensure they still meet the targets. Resist Measurements. B.3
Re-measure resist thickness after etching and calculate selectivity
from the measured depth (below).
Position Pre-etch thickness
C L R MF OMF
B.4 Cleave wafer through centre and major flat and measure, on a
SEM, the dimensions of the cross-section of
two different sized trenches. Please record the results below:
Results -Deep process on STS test wafer
Feature Size
Depth (µm)
5 µm Major flat
80 µm 50 µm
5 µm Profile angle = 90 – tan-1{(top width – bottom width)/(2 ×
depth)} RIE lag = (5 um feature depth)/(80 um feature depth) 80 µm:
Average etch rate =……………µm/min ±……….% 50 µm: Average etch rate
=……………µm/min ±……….% 5 µm: Average etch rate =……………µm/min ±……….% RIE
lag (5/80) = ………………… Attach SEMs here. Signature: . . . . . . . . .
. . . . . . . Dat e: . . . . . . . .
APPENDIX C: CHECK FOR LF ETCH RATE This test is only to be
performed if test 9c fails (i.e. notch width/edge > 0.35 µµµµm
and SOI depth >20 µµµµm)
N/A
C.1 Run the following lfhrm process for 5 minutes 40 seconds on an
STS patterned test wafer (not SOI) and
record the process parameters in following table:
ASEHRM Standard Process Test lfhrm Process 50 Etch Step Expected
Value Pass. Step Expected
Value Flow: SF6=450sccm , O2=45sccm (3s on time + 0s over-run
time)
450, 45 sccm 0 sccm
Flow: C4F8=100sccm (2s on time + 0s over-run time)
0 sccm 100 sccm
Pressure Ranges 52 ~37mT ~11mT
MSource Power = 3.0KW (etch)/1.0W (deposition) 53
(forward/reflected) ~3000 - 0W ~1000 -0W
Load Position / Tune Position - -
(LF 5 ms 20% duty cycle)
45 W
0 W
1A 0
He flow = . . . . . . sccm , He pressure (set 9.9T) = . . . . T, He
LUR = ……………..….mT/min, Wall temperature = 120/130/150ºC(set); Start
value:……………………………. End value:…………………….., Platen temperature = 10ºC,
Datalog Number: …………………
50 Select passivation step first in recipe 51 Fix APC angle at
value which gives ~ 41 mT at end of etch cycle on blank Si wafer 52
Record pressure swings during etch and dep steps i.e. max and min
pressures. 53 Record forward and reflected power from screen i.e.
if fwd power = 2997W and reflected is 12W then write “2997-12” 54
NOTE. Systems with electrostatic clamping should not display a Vdc
reading. Check that the limit in the software is set to 200W.
ASEHRM Standard Process Test C.2 Plasma Stability Record: Checks to
be performed at generator display/output, not at VDU. For AE 3 KW
generators, checks may be performed at the operator station VDU.
Note down the minimum value of the reflected power. Examine the
datalog files for any discrepancies.
Etch Step Target Pass Step Target Plasma blink time at start of
step (<1 s) (<1 s) Number of blinks ( ≤1) ( ≤1) Minimum
reflected MSource Power (<20 W) (<40 W)
If the system fails to meet the pass criteria and you change
settings and/or perform hardware modifications, return and repeat
all previous plasma stability checks (standard tests section C4),
to ensure they still meet the targets. Resist Measurements. C.3
Re-measure resist thickness after etching and calculate selectivity
from the measured depth (below).
Position Pre-etch thickness
Centre Edge
C.4 Cleave wafer through centre and major flat and measure, on a
SEM, the dimensions of the cross-section of
the 3 µm sized trenches. Please record the results below: Results
-lfhrm process
Feature Size
Depth (µm)
3 µm