62
1 ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of the County of Annapolis August 17, 2016

ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

1

ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of the County of Annapolis

August 17, 2016

Page 2: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

2

SECTION A. MANDATE

This document has been prepared to allow the Municipality of the County of Annapolis to properly manage construction materials present within its buildings that contain asbestos. Currently, management of asbestos containing materials (ACMs) in Nova Scotia workplaces is addressed by the Nova Scotia Department of Labour and Advanced Education through a series of four Codes of Practice and Guidelines as follows:

A Guide to Assessment and Management of Asbestos in the Workplace – Code of Practice

A Guide to Removal of Friable Asbestos Containing Materials – Code of Practice

Guidelines for Maintenance Operation Involving Asbestos

Guidelines for Outdoor Work with Asbestos The Municipality of the County of Annapolis has expanded these documents into an Asbestos Management Plan (AMP). The intention of these documents is to:

Comply with the Codes of Practice and Guidelines noted above,

Establish Management’s intent to properly manage asbestos that is present in Municipality of the County of Annapolis buildings,

To provide instructions to permit management of asbestos in terms of: o sampling to determine locations, types, quantities and conditions of ACMs o information management o identify proper removal methods o provision of awareness training for management and custodial staff o provision of training in minor removal methods for maintenance staff o prequalification of outside contractors that will be retained for abatement work

To initiate an Operations and Maintenance Program to include: o Repair and/or removal of ACMs as needed o Maintain remaining ACMs in good condition o Minimise future exposure to asbestos by management of activities o Continued inspections and monitoring of activities that may impact ACMs

When asbestos has been identified as being present in a building, it is often not technically feasible, necessary or cost effective to remove all of it. In fact, in the absence of any renovation, maintenance or demolition work that has the potential for disrupting any asbestos, most owners elect to manage their asbestos in-place. This document that follows addresses each of these considerations.

Page 3: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

3

SECTION B. MANAGEMENT OF ASBESTOS Program Objectives In order that a uniform approach to the control and management of asbestos-containing materials (ACM) throughout all Municipality of the County of Annapolis facilities may be developed, the following program objectives have been established:

The program shall clearly establish management’s intent to manage any asbestos that remains in the buildings.

The program shall provide the criteria in which all asbestos-containing materials are to be identified and evaluated within the building and shall establish the means in which this information is to be passed on to all affected parties (i.e. management, planning staff, maintenance or custodial workers, outside contractors or building tenants, etc.).

The program shall establish the need for necessary training and education of all staff, maintenance or custodial workers or outside contractors.

The program shall contain the necessary work practices and procedures to affect asbestos work in a safe manner.

The program shall initiate the implementation of an Operations & Maintenance Program to address the following:

a. Repair and/or removal (as required) of any ACM identified as being in disrepair. b. Maintain all remaining ACM in good condition. c. Minimize future fibre releases by controlling activities that may disturb asbestos. d. Inspection and monitoring of all scheduled asbestos disturbances.

The following document provides information, procedures and work practices relevant to the management and control of asbestos-containing building materials known to be present. It has been commissioned in part, to fulfil obligations under Nova Scotia Labour and Advanced Education (NSLAE) Codes of Practice and Guidelines and to provide the means from which future exposures to asbestos may be prevented through the combined efforts of all parties (i.e. management, staff, maintenance or custodial workers, outside contractors, etc.). It also includes work procedures for the removal of friable asbestos-containing materials, glove bag work, outdoor work and maintenance work as performed by employees and/or an outside contractor. Types of Asbestos Asbestos is a generic term used to describe a family of naturally occurring fibrous minerals. These are divided into two groups; serpentines and amphiboles. The important property of asbestos as compared to non-asbestiform varieties of minerals is the presence of long, thin fibres that can be easily separated. Chrysotile (also known as white asbestos), which is by far the most abundant, is the only type that belongs to the serpentine group. Crocidolite (blue

Page 4: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

4

asbestos) and amosite (brown asbestos), the two other most commonly used fibres, together with anthophyllite, tremolite, and actinolite all belong to the amphibole group. Serpentine fibres differ from those of amphiboles in that they are more flexible, will become wet more easily and will tend to bend rather than splinter and thereby are far less dusty to work with. Health Effects of Asbestos For many years, asbestos has been recognized as a health hazard for workers employed in asbestos production, processing and use. Several serious, debilitating diseases that often end in death have been linked to the inhalation of fine asbestos fibres. It is not clear how asbestos fibres cause disease after they enter the lung. For each disease there is a period of latency, usually more than ten years, between first exposure to asbestos and the appearance of the disease. Each of the more common diseases linked to asbestos exposure are described below. Asbestosis: Asbestosis is characterized by a fibrosis (scarring) of the lung tissue, which makes breathing difficult. The most prominent symptom is breathlessness. Detection of asbestosis is possible by X-ray examination and lung function testing. Asbestosis will develop only with chronic exposure to high levels of airborne asbestos. Mesothelioma: This is a rare cancer arising from the cells of the pleura (lining of the chest cavity and lungs) and the peritoneum (lining of the abdominal cavity). The development of mesothelioma is characterized by a long latency period, usually at least 15 years and sometimes more than 40. There is no effective treatment for mesothelioma. Although asbestos was once thought to be responsible for all mesothelioma, other causes have now been identified. Still, the chance of getting mesothelioma in the absence of asbestos exposure is considered to be extremely remote. Lung Cancer: Unlike asbestosis and mesothelioma, lung cancer is not associated only with asbestos exposure. Furthermore, there is no basic difference between lung cancer caused by asbestos and that due to other causes. In general, the risk of getting lung cancer increases with the extent of asbestos exposure, in terms of both intensity and duration. This risk is also greatly enhanced by smoking; most asbestos workers who develop lung cancer are smokers. Other Asbestos-Related Cancers: The relationship between asbestos exposure and asbestosis, mesothelioma and lung cancer has been clearly established and is beyond argument. Several other cancers have also been associated with the inhalation of asbestos. Although the evidence is not as good as for the diseases discussed above, these cancers should be noted. They are gastrointestinal cancer affecting all sites in the gastrointestinal tract (oesophagus, stomach, colon and rectum) and cancer of the larynx.

Page 5: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

5

Other Asbestos-Related Conditions: A number of less serious effects have been associated with asbestos exposure, namely pleural plaques and asbestos warts. Pleural plaques are areas of scarring of the pleural surfaces. In general, they are not associated with any functional abnormality and are merely an indicator of asbestos exposure. Asbestos warts are harmless skin growths that occur when asbestos fibres penetrate the skin. Elements of the Asbestos Management Program The maintenance of a safe work environment depends on the establishment of an effective management program. Such a program shall incorporate and/or require the implementation of the following measures to ensure the safe and proper control of all suspected or confirmed ACM.

1. The development of a WRITTEN PLAN. 2. Establish PARAMETERS FOR THE EVALUATION of all suspected or confirmed ACM. 3. Create or otherwise establish an INVENTORY of all suspected or confirmed ACM. 4. Establish procedures for the NOTIFICATION of all workers, custodial or maintenance staff,

outside contractors, etc. whose work or use of the building will or may result in the disturbance of any suspect or confirmed ACM.

5. Provide direction for IDENTIFICATION of ACM. 6. Establish TRAINING protocol for all employees and any other personnel (i.e. outside

contractors, maintenance or renovation workers) required to work on or near any ACM or whose activities in the building may result in the disturbance of asbestos.

7. Establish direction pursuant to the periodic INSPECTION and re-evaluation of all materials known to contain asbestos.

8. Develop WORK PROCEDURES for the repair, clean-up or removal of minor amounts of ACM during routine maintenance, minor renovations or demolition.

9. Give consideration to the PRO-ACTIVE REMOVAL of asbestos during any renovation or demolition work performed on or near any known or suspect ACM. Such activities are normally performed by an outside contracting firm who specializes in asbestos work and will require the preparation of site-specific contract documents.

10. REMOVAL AND/OR REPAIR of any asbestos-containing materials that have been damaged and/or are otherwise in disrepair.

11. MINIMIZE FUTURE FIBRE RELEASES by controlling activities that may disturb asbestos and ensuring all affected ACM is removed prior to any major renovations, maintenance or demolition work.

12. Provide for the SCHEDULED RE-ASSESSMENT & UPDATING of the AMP document itself to ensure it remains a current and viable document.

13. Establish policy to ensure the INDEPENDENT INSPECTION AND MONITORING of all asbestos-related disturbances to ensure compliance with the requirements of the AMP document and governing authorities.

Page 6: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

6

Each of the above elements is discussed under the following sections and/or appendices and has been formulated so as to meet or exceed the requirements of current codes of practice and guidelines specific to asbestos control and management. Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or duties shall be the responsibility of Municipality of the County of Annapolis Management:

1. Implement the AMP. 2. Assign staff to be responsible for the overall administration and maintenance of the

AMP. 3. Provide necessary technical support and resources to effectively manage and

administrate his/her duties assigned under the AMP. 4. Ensure that appropriate staff are kept informed (in advance) of all maintenance,

renovation, or construction activities in sufficient time to assess their potential for asbestos disturbance.

5. Provide or arrange for awareness and procedural training of all maintenance or custodial workers and supervisory staff whose job descriptions require them to work on or near asbestos or may have occasion to respond to a spill or damage of asbestos.

6. Engage, as required, the services of an asbestos consulting firm to assist in the design, co-ordination, inspection and monitoring of all friable asbestos remedial work.

7. Engage, as required, a contracting firm specializing in asbestos abatement work for all friable asbestos removal projects. Ensure adequate information is contained in the Tender Package to satisfy provincial codes of practice and guidelines.

8. Engage, as required, the services of an asbestos consulting firm to assist in providing regular site inspection and air monitoring services during scheduled friable asbestos disturbances.

9. Ensure all asbestos-containing materials present throughout the buildings are maintained in good condition and/or are repaired or removed as deemed appropriate.

10. Commission or otherwise undertake a self-examination or review of the Asbestos Management Program every two years.

11. Ensure that general asbestos related information is provided to building occupants prior to all significant abatement projects.

Responsibilities Assigned by Management to Operations Staff Management will assign the following tasks and/or duties to designated staff:

1. Maintain documents required by the AMP including copies of any asbestos work reports, permits, correspondence with regulatory agencies, improvement orders, survey

Page 7: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

7

updates, worker training certificates, asbestos waste transportation manifests, site inspection reports, etc.

2. Arrange for copies of the completed Asbestos Inventory and Assessment Report to be held on file at location(s) readily accessible to all maintenance workers, custodial staff and/or outside contractors.

3. Evaluate on an annual basis or more frequently as the need may arise, and in consultation with management, the need to hold refresher training for any recently employed workers or to individual workers engaged in active asbestos work on a more regular basis.

4. Ensure all departmental supervisors, managers, maintenance and custodial staff are informed of the current location of all known asbestos-containing materials and are updated as conditions change or as these materials are removed.

5. Notify all outside contractors or service personnel (i.e. plumbers, custodial or maintenance firms, telephone service personnel, etc.), of the presence and approximate location of all known asbestos-containing materials if their work in the building may lead to the possible disturbance of known asbestos-containing materials.

6. Ensure all outside contractors or service personnel (i.e. plumbers, custodial or maintenance firms, telephone service personnel, etc.) are provided with and complete a Contractor’s Notification & Acknowledgement form.

7. Ensure that all building occupants and the Joint Occupational Health and Safety Committee (JOHSC) are notified prior to all asbestos projects that require enclosures in public areas.

8. Update the asbestos inspection reports, inventory reports and files to reflect ongoing asbestos abatement projects.

9. Ensure that all appropriate staff receive a copy of all site inspection reports and any corresponding air monitoring data as compiled in association with asbestos abatement activities undertaken on the premises.

Responsibilities Assigned to Supervisors and Client Service Managers/Coordinators The following tasks and/or duties shall be the responsibility of Maintenance and Custodial Supervisors:

1. Coordinate and/or otherwise effect the removal or repair of any asbestos-containing materials that have been damaged and/or are otherwise in disrepair.

2. Respond to any report of asbestos debris, damage or disturbance. Evaluate the condition and provide or initiate the necessary clean-up, removal or repair as appropriate.

3. Evaluate the potential for asbestos disturbance in advance of any major maintenance renovation or construction activities planned. Ensure the appropriate risk classification is assigned to any asbestos removal required and that such work is completed safely.

4. Update the asbestos inspection report, asbestos inventory report, and files to reflect ongoing asbestos abatement projects.

Page 8: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

8

5. Coordinate and supervise all asbestos abatement activities whether undertaken internally by Municipality of the County of Annapolis employees or through an outside contractor.

6. Ensure that asbestos work is carried out in accordance with the AMP. Ensure that project signs are posted in locations that cover all access to the area. Ensure all persons in the area are informed prior to the commencement and when the work has been completed.

7. Ensure a duly signed and executed Asbestos Work Permit is issued and completed by all project supervisors and outside contractors, maintenance or custodial staff prior to commencing any scheduled friable asbestos abatement activities. Refer to the form provided for this purpose at the end of this document.

8. Ensure notification in advance to all appropriate personnel of any scheduled asbestos disturbances.

9. Ensure that work involving disturbance of ACM material is coordinated with and reviewed with the Supervisor or designate.

10. Ensure that contractors and employees are aware of the AMP and the location and type of asbestos-containing material.

11. Review and give Section 3 to contractor before start of contract work begins. 12. Commission and/or otherwise complete a regular review and evaluation of all remaining

asbestos-containing materials on an annual basis or more frequently as circumstances warrant.

13. Ensure that all persons in the area are informed when asbestos work procedures are being implemented.

14. Ensure that only authorized individuals trained in asbestos work procedures and equipped with the required protective equipment are assigned to work involving contact with asbestos containing material.

15. Ensure that specific AMP procedures are implemented as required by this program with staff for which the Supervisor has supervisory responsibilities.

16. Ensure that written procedures are available for work involving friable asbestos material or products containing asbestos and are implemented by staff and contractors carrying out work in buildings under the responsibility of the Supervisor.

17. Ensure that the requirements of the AMP are strictly enforced in properties for which the Supervisor has responsibility.

18. Ensure that current information for updating of the asbestos survey/inventory is available to staff responsible at all times (i.e. removal of asbestos containing materials, changes in conditions of ACM, etc.).

19. Ensure that the condition of ACM in buildings is inspected and re-assessed in compliance with this AMP.

20. Ensure that annual respirator fit-testing for all staff that may have occasion to make use of a respirator during the completion of any asbestos abatement activities has occurred.

21. Notify the JOHSC and the OHS Coordinators of workplace occupational health or safety monitoring or tests related to asbestos abatement.

22. Upon discovery of any unidentified asbestos-containing or suspect asbestos-containing materials, secure the area and suspend all activities that may disturb such materials. Do

Page 9: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

9

not proceed with work in the area until it has been determined if the material in questions contains asbestos and written authorization to proceed is obtained.

Responsibilities Assigned to Contractors The following responsibilities fall upon any contractor whose work may result in the disturbance of any asbestos-containing or contaminated materials or surfaces.

1. Before commencing work, ensure all contractors employees and supervisory staff have been informed as to the presence and approximate location of all asbestos-containing materials that may become subject to disturbance (whether intentional or not).

2. Only workers trained and authorized in friable asbestos work procedures are assigned to work involving exposure to material containing friable asbestos.

3. File with Municipality of the County of Annapolis a signed and executed copy of a Contractor’s Notification & Acknowledgement form as provided at the end of this document.

4. Perform work in such a manner as to avoid the disturbance of any asbestos-containing or contaminated surfaces or materials other than those materials intentionally contracted to remove, repair, encapsulate or enclose.

5. Upon discovery of any unidentified asbestos-containing or suspect asbestos-containing materials, secure the area, suspend all activities that may disturb such materials and do not proceed with work in the area until it has been determined if the material in question contains asbestos and written authorization to proceed is obtained from Universal.

6. Prior to proceeding with any asbestos disturbance for friable work (i.e. removal, clean-up or repair) ensure a signed and duly executed Asbestos Work Permit is obtained.

7. Ensure all work that may disturb any asbestos-containing or contaminated surfaces is completed in accordance with current regulatory requirements.

8. As required, provide a copy of all executed Asbestos Waste Transportation Manifests verifying the safe and proper disposal of asbestos waste generated.

Employee Responsibilities The following responsibilities shall be assigned to all Municipality of the County of Annapolis employees whose work will and/or may result in the disturbance of any asbestos-containing or contaminated materials or surfaces.

1. Be familiar with all duties and responsibilities assigned to him/her under the terms of the AMP.

2. Be knowledgeable as to the location of all known asbestos-containing materials and/or surfaces known to be contaminated with asbestos.

3. Upon discovery of any unidentified asbestos-containing or suspect asbestos-containing materials, secure the area, suspend all activities that may disturb such materials and immediately notify the supervisor/designate. Do not proceed with work in the area

Page 10: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

10

until it has been determined if the material in question contains asbestos and authorization to proceed is granted by Universal.

4. Report any damage to existing asbestos-containing materials to the supervisor upon discovery.

5. Execute all work in compliance with the AMP. 6. Follow all work and job procedures outlined in the AMP and use all protective

equipment as required by the procedures issued under the AMP.

Joint Occupational Health & Safety Committee Responsibilities

1. The JOHSC shall conduct scheduled reviews of the AMP on an annual basis. 2. The JOHSC shall incorporate the AMP as part of an annual workplace hazard inspection.

Regulatory Requirements Municipality of the County of Annapolis has varying responsibilities assigned to it as building managers and employers under the following acts, regulations and guidelines:

Occupational Health and Safety Act,

Workplace Hazardous Materials Information System (WHMIS),

Code of Practice for Managing Asbestos in Buildings, Nova Scotia Labour and Advanced Education (NSLAE) (attached as Appendix at the end of this document),

Code of Practice for Removal of Friable Asbestos Containing Materials, Nova Scotia Labour and Advanced Education (NSLAE) (attached as Appendix at the end of this document),

Guidelines for Maintenance Operation Involving Asbestos, Nova Scotia Labour and Advanced Education (NSLAE) (attached as Appendix at the end of this document),

Guidelines for Outdoor Work with Asbestos, Nova Scotia Labour and Advanced Education (NSLAE) (attached as Appendix at the end of this document).

Page 11: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

11

SECTION C. Identification of Asbestos Containing Materials Uses of Asbestos in Buildings The uses of asbestos are generally classed into two groups; friable and non-friable products. A friable material is a material that when dry can be crumbled, pulverized or powdered by hand pressure; this includes non-friable materials that have already been crumbled, pulverized or powdered. The use of friable materials in construction is banned today but due to the widespread use of friable materials in the past, these materials still are present in many buildings. In order to establish an effective control program, the possible uses of asbestos must be known. Asbestos-Cement (A/C) Products: The largest use of asbestos, in terms of the tonnage of fibres employed, is as a reinforcing agent in cement products. Asbestos-reinforced cement is strong, durable, rigid and resistant to both fire and weather. Portland cement, water and asbestos are mixed to form a slurry from which end-products can be fabricated by a process similar to that used in paper making. Such products can then be formed into sheets, pipes and a wide variety of other shapes. The asbestos fibre content of A/C products is usually about 15-50 percent. Asbestos-cement sheeting that is produced that comes in four basic forms: flat sheets, corrugated sheets, siding shingles or roofing shingles. The main use of A/C sheeting is for roofing and for cladding the exterior of buildings. Other uses are decorative panelling, electrical insulation and laboratory tabletops. Asbestos-cement piping is used for water supply, sewage, irrigation, drainage applications, the transport of corrosive chemical fluids, and electric and telephone conduits. Asbestos cement products are still in use and production today. Gaskets and Packings: The combination of long asbestos fibres and high temperature rubbers has provided some of the best gasket materials ever produced. The asbestos, in bulk fibre, woven, or plaited form, provides strength and temperature resistance, while the rubber acts as a binder and sealing material. Asbestos yarns have been commonly used in the manufacture of braided and woven packing materials. Many of these uses, particularly in sheet forms, are still in production and use today. Coatings and Sealants: Asbestos has been used in roof coatings, cements and to a lesser extent, in sealants and caulks. Roof coatings consist of asphalt that has been liquefied with solvents and then has had asbestos fibre added as filler. Roof cements are similar, but they are formulated to a thicker consistency so that they can be used to seal openings through which a liquid coating would flow. Some of these are still in production today. Paper Products: Asbestos paper products are used in a wide variety of applications. Among the most important in construction are roofing felts, gaskets, pipeline wrap, millboard and electrical insulation. Some uses (particularly where impregnated with tar or asphalt for roofing and pipeline wrap) are still in production today.

Page 12: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

12

Plastics: Asbestos has been used as a reinforcing agent in a wide range of asbestos/polymer composites. Applications include brake and transmission components, floor tiles, engine housings, bins and containers, and a variety of coatings, adhesives, caulks, sealants and patching compounds. Two areas have dominated asbestos use in plastics: phenolic moulding compounds and vinyl-asbestos tile. Few of these products remain in production today. Friction Materials: Asbestos has been used in the manufacture of brake and clutch linings and pads. The asbestos fibres may be embedded in a phenolic resin with various mixtures of fillers or a woven asbestos cloth may be impregnated with the resin. Friction products are primarily used in vehicles but may be used in any rotating machinery. They are still widely produced and used. Asbestos Textiles: Asbestos textile materials are predominantly manufactured from chrysotile fibres. Two types of yarn are produced: plain, possibly braced with organic fibres, and reinforced, which incorporates either wire or another yarn such as nylon, cotton or polyester. Major uses for asbestos textiles are gaskets, packings, friction materials, thermal and electrical insulation, and fire resistant applications, e.g. welding curtains, protective clothing, theatre curtains, hot conveyor belts and ironing board covers. These products may be considered or become friable in use. Asbestos textiles are no longer in widespread production. Acoustic Ceiling Tiles: Some types of mineral wool type acoustic ceiling tiles were formulated with asbestos from the early 1960's. The use of asbestos in ceiling tiles was discontinued in the early 1980’s. Analytical testing is required to distinguish the asbestos and non-asbestos ceiling tiles. The fire-rated tiles are more likely to contain asbestos. Amosite was the predominant fibre type used. Acoustic tile, particularly if splined or glued on, can release dust when removed. Prior to removal, all ceiling tiles must be checked against the asbestos inventory. Ceiling tiles containing asbestos may only be removed by persons trained and certified in asbestos work procedures. Damaged ceiling tile must be treated as a friable product that must be checked and handled by persons trained and certified in asbestos work procedures. Drywall Joint Compound: Drywall joint compound also contained asbestos until the early 1980’s. The concentration is quite low (less than 5%, often around 1% and always chrysotile). The product in place is quite hard and is treated as non-friable unless damaged. Potentially Friable Plaster: Asbestos was used in random fashion in the brown coat and surface coat of smooth plaster finishes. This has been used at a low level (less than 10% in most cases). In many instances the asbestos content is less than 1% or even less than 0.5%. This is often due to the presence of vermiculite in plaster. Vermiculite frequently contains actinolite or chrysotile as an impurity which contributes to the asbestos content. Plaster is non-friable in place but removal is impossible without causing it to become friable.

Page 13: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

13

Vermiculite Insulation: Some vermiculite insulation may contain amphibole asbestos fibres as a contaminant. These products can cause health risks if disturbed during maintenance, renovation or demolition. However, there is currently no evidence of risk to your health if the insulation is sealed behind wallboards and floorboards, isolated in an attic, or otherwise kept from exposure to the interior environment. Spray or Trowel Applied Fireproofing or Sprayed Insulation: Several types of fireproofing or insulation were used in the period encompassing the mid 1930's through to about 1974. Fibrous products were spray applied after being blown as a dry mix through an application gun. These products may contain up to 90% asbestos and any of the three major types (chrysotile, amosite or crocidolite). Cementitious products were trowel applied or sprayed as a wet slurry. These were harder products which did not contain more than 25% asbestos. Only chrysotile asbestos was used in the cementitious type materials. Sprayed or Trowel Applied Texture or Acoustic Plasters: The use of asbestos was widespread in trowel applied or sprayed texture coats, stipple coats or acoustic plasters commencing in the 1950's through to the late 1970's (at least as late as 1977). These products always contained less than 25% chrysotile. Some of these products may be considered non-friable in place and only become friable when disturbed by construction or demolition. Other products in this group can be very soft and extremely friable. Mechanical System Insulation: This is the most widespread use of friable asbestos in buildings. Their use dates from the late 1800's to the late 1970s. The material can have a number of appearances and asbestos contents.

white, brown, pink or grey block

white or grey corrugated paper

white, grey or brown layered paper

grey trowel or hand applied material (with the appearance of hard grey dry mud) It is possible to find all asbestos types in mechanical insulation although chrysotile is predominant and amosite the next most common. SECTION D. Sampling and Maintenance of Inventory In order to reduce risk of accidental exposure to asbestos fibres resulting from damage to asbestos containing materials (ACMs) that results in fibre release, an inventory will be maintained for each building identifying the location of all asbestos containing materials or, where that is not immediately practical, a list of materials that could potentially contain asbestos. The following guideline identifies materials that often contain asbestos and that will be helpful in determining the types of materials to sample or, where samples are not yet

Page 14: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

14

available, the types of materials that are apt to contain asbestos in buildings constructed before 1986:

• exterior siding and shingles, sometimes under vinyl siding • some exterior paint, typically thick consistency • boiler and flue stack insulation • cement insulation on pipes, fittings, tees, valves, etc • gaskets on furnaces and valves • drywall joint-filling compound • plaster scratch coat • acoustical and decorative texture coats (stuccos) • floor tiles and adhesives, especially 9 inch tiles • suspended and glued-in-place ceiling tiles, including the glue • fireproofing, typically on structural components or concrete ceiling decks • fire resistant cement panels, often in boiler and electrical rooms • paper under hardwood floors and around air ducts • corrugated cardboard products on water pipes • old wiring • concrete conduits • chalkboards • lab bench tops • fume hood liners • caulking on windows and doors • seamless flooring, especially on the back • fire doors • vermiculite

Sampling of materials has already been completed. These data follow at the end of this report, tabulated individually for each building. Note that data complied in the report were collected in a way to minimise obvious damage – these data may NOT be suitable to support extensive renovations or demolitions as ACM may be present in wall/ceiling cavities, under upper layers of flooring, or between exterior sheathing components. The number of samples needed to be collected depends upon the type of material to be sampled, its quantity and homogeneity. Some materials, such as floor tiles, are consistent in terms of asbestos content and can be reliably sampled based simply on color and size, whereas materials such as plaster, texture coats and drywall filler can vary in asbestos content due to both differences within the same material as well as difference between materials, neither of which is visible to the naked eye. Accordingly, the following table should be consulted to determine minimum numbers of samples to be collected for various materials should additional testing be required.

Page 15: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

15

Table 1. Bulk Material Sample Guidelines

Type of material Size of area of homogeneous material1

Minimum number of bulk material samples to be collected

Surfacing material, including without limitation material that is applied to surfaces by spraying, by towelling or otherwise, such as acoustical plaster on ceilings and fireproofing materials on structural members

Less than 90 square metres 90 or more square metres, but less than 450 square metres 450 or more square metres

3

5

7

Thermal insulation, except patch any size 3

Thermal insulation patch Less than 2 linear metres or 0.5 square metres

1

Other material Any size 3

Note 1. Homogeneous material is one that looks to the eye to be uniform in terms of colour, texture and application. Buildings with asbestos containing materials must be inspected not less often than annually to determine current condition of the ACMs, reprioritize any necessary actions regarding the materials, and update the inventory as needed.

Page 16: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

16

SECTION E. Maintenance, Renovation or Demolition of Asbestos Containing Materials This section describes the procedures to be followed for various levels of abatement and also the criteria to be used to select the appropriate procedure to follow for the work to be done. In Nova Scotia, as per the Code of Practice, use of enclosures is recommended for all friable asbestos removal. The “Type 2” and “Type 3” procedures notes above should be followed for all friable asbestos removal. “Type 2” methods will be suitable only for circumstances in which only small quantities of friable materials require removal – “Type 3” methods should be used otherwise. “Type 1” procedures are suitable for non-friable asbestos removal. Definitions In this description, “asbestos-containing material” means friable material that contains 0.5 per cent or more asbestos by dry weight; “building” means any structure, vault, chamber or tunnel including, without limitation, the electrical, plumbing, heating and air handling equipment (including rigid duct work) of the structure, vault, chamber or tunnel; “competent worker”, in relation to specific work, means a worker who,

(a) is qualified because of knowledge, training and experience to perform the work, (b) has knowledge of all potential or actual danger to health or safety in the work;

“demolition” includes dismantling and breaking up; “friable material” means material that,

(a) when dry, can be crumbled, pulverized or powdered by hand pressure, or (b) is already crumbled, pulverized or powdered;

“HEPA filter” means a high efficiency particulate aerosol filter that is at least 99.97 per cent efficient in collecting a 0.3 micrometre aerosol; “homogeneous material” means material that is uniform in colour and texture; “Type 1 operation” means an operation described in section 2 following, “Type 2 operation” means an operation described in section 2 following, “Type 3 operation” means an operation described in section 2 following.

Page 17: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

17

Procedures Type 1, Type 2 and Type 3 operations are described below. All asbestos removal, whether done by outside contractors or in-house, shall follow these methods. Additional requirements are noted in the “Guide to Removal of Friable Asbestos Containing Material” as published by the Department of Labour and Advanced Education and attached to this document. Currently, this latter document is provided for guidance purposes but can be enforced as a regulation should no other suitable prescribed method be available or should a regulator inspector be unsatisfied with a removal method either being used or planned for use. These requirements should also be considered with the most stringent being followed in case of conflict. 1. For the purposes of this description, operations are classified as Type 1, Type 2 and Type 3 operations. 2. The following are Type 1 operations:

Removing non-friable asbestos-containing material, other than ceiling tiles, if the material is installed or removed without being broken, cut, drilled, abraded, ground, sanded or vibrated.

Breaking, cutting, drilling, abrading, grinding, sanding or vibrating non-friable asbestos-containing material if, i. the material is wetted to control the spread of dust or fibres, and ii. the work is done only by means of non-powered hand-held tools.

3. The following are Type 2 operations:

Removing all or part of a false ceiling to obtain access to a work area, if asbestos-containing material is likely to be lying on the surface of the false ceiling.

Applying tape or a sealant or other covering to pipe or boiler insulation that is asbestos-containing material.

Breaking, cutting, drilling, abrading, grinding, sanding or vibrating non-friable asbestos-containing material if, i. the material is not wetted to control the spread of dust or fibres, and ii. the work is done only by means of non-powered hand-held tools.

Breaking, cutting, drilling, abrading, grinding, sanding or vibrating non-friable asbestos-containing material if the work is done by means of power tools that are attached to dust-collecting devices equipped with HEPA filters.

Removing insulation that is asbestos-containing material from a pipe, duct or similar structure using a glove bag.

An operation that is not mentioned above or is not classified as a Type 1 or Type 3 operation.

Page 18: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

18

4. The following are Type 3 operations:

The removal or disturbance of friable asbestos-containing material during repair, alteration, maintenance or demolition.

The spray application of a sealant to friable asbestos-containing material.

Repairing, altering or demolishing all or part of a furnace or similar structure that is made in part of refractory materials that are asbestos-containing materials.

Breaking, cutting, drilling, abrading, grinding, sanding or vibrating non-friable asbestos-containing material, if the work is done by means of power tools that are not attached to dust-collecting devices equipped with HEPA filters.

Respirators A respirator provided by an employer and used by a worker in a Type 1, Type 2 or Type 3 operation, 1. Shall be fitted so that there is an effective seal between the respirator and the worker’s face, unless the respirator is equipped with a hood or helmet; 2. Shall be assigned to a worker for his or her exclusive use; 3. Shall be used and maintained in accordance with written procedures that are established by the employer and are consistent with the manufacturer’s specifications; 4. Shall be cleaned, disinfected and inspected after use on each shift, or more often if necessary; 5. Shall have damaged or deteriorated parts replaced prior to being used by a worker; and 6. When not in use, shall be stored in a convenient, clean and sanitary location. 7. If respirators are used in the workplace,

The employer shall establish written procedures regarding the selection, use and care of respirators; and

A copy of the procedures shall be provided to and reviewed with each worker who is required to wear a respirator.

A worker shall not be assigned to an operation requiring the use of a respirator unless he or she is physically able to perform the operation while using the respirator.

Page 19: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

19

Table 2 - Respirators

Work Category Required respirator

Type 1 Operations, Glove Bag Air purifying half-mask respirator with N-100, R-100 or P-100 particulate filter

Type 2 Operations Powered air purifying respirator equipped with a tight-fitting facepiece and a high efficiency filter or N-100, P-100 or R-100 particulate filter

Type 3 Operations Airborne fibre levels maintained below 100 fibres/cc as determined by air monitoring

Powered air purifying respirator equipped with a tight-fitting facepiece and a high efficiency filter or N-100, P-100 or R-100 particulate filter

Type 3 Operations Airborne fibre levels not maintained below 100 fibres/cc as determined by air monitoring

Pressure demand supplied air respirator equipped with a full facepiece and assigned protection factor of 10,000

Type 1 Operations The following measures and procedures apply to Type 1 operations: 1. Before beginning work, visible dust shall be removed with a damp cloth or a vacuum equipped with a HEPA filter from any surface in the work area, including the thing to be worked on, if the dust on that surface is likely to be disturbed. 2. The spread of dust from the work area shall be controlled by measures appropriate to the work to be done including the use of drop sheets of polyethylene or other suitable material that is impervious to asbestos. 3. The material shall be wetted before and kept wet during the work to control the spread of dust or fibres, unless wetting would create a hazard or cause damage. 4. A wetting agent shall be added to water that is to be used to control the spread of dust and fibres.

Page 20: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

20

5. Frequently and at regular intervals during the doing of the work and immediately on completion of the work,

dust and waste shall be cleaned up and removed using a vacuum equipped with a HEPA filter, or by damp mopping or wet sweeping, and placed in a suitable container, and

drop sheets shall be wetted and placed in the suitable container as soon as practicable after the item above been complied with.

6. Drop sheets shall not be reused. 7. After the work is completed, polyethylene sheeting and similar materials used for barriers and enclosures shall not be reused, but shall be wetted and placed in a suitable container as soon as practicable. 8. After the work is completed, barriers and portable enclosures that will be reused shall be cleaned, by using a vacuum equipped with a HEPA filter or by damp wiping, as soon as practicable. 9. Barriers and portable enclosures shall not be reused unless they are rigid and can be cleaned thoroughly. 10. Compressed air shall not be used to clean up and remove dust from any surface. 11. Eating, drinking, chewing or smoking shall not be permitted in the work area. 12. The employer shall provide the worker with a CSA approved respirator in accordance with the attached Table, and the worker shall wear and use the respirator. 13. The employer shall provide the worker with protective clothing that

shall be made of a material that does not readily retain nor permit penetration of asbestos fibres,

shall consist of head covering and full body covering that fits snugly at the ankles, wrists and neck, in order to prevent asbestos fibres from reaching the garments and skin under the protective clothing,

shall include suitable footwear, and

shall be repaired or replaced if torn.

the worker shall wear the protective clothing. 14. Facilities for the washing of hands and face shall be made available to workers and shall be used by every worker when leaving the work area.

Page 21: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

21

Type 2 and Type 3 Operations, Common Requirements The following measures and procedures apply to both Type 2 operations and to Type 3 operations: 1. The work area shall be identified by clearly visible signs warning of an asbestos dust hazard. 2. Signs shall be posted in sufficient numbers to warn of the hazard and shall clearly state that,

there is an asbestos dust hazard, and

access to the work area is restricted to persons wearing protective clothing and equipment.

3. A wetting agent shall be added to water that is to be used to control the spread of dust and fibres. 4. Eating, drinking, chewing or smoking shall not be permitted in the work area. 5. Containers for dust and waste shall be

dust tight,

suitable for the type of waste,

impervious to asbestos,

identified as asbestos waste,

cleaned with a damp cloth or a vacuum equipped with a HEPA filter immediately before being removed from the work area, and

removed from the workplace frequently and at regular intervals. 6. Frequently and at regular intervals during the doing of the work and immediately on completion of the work, dust and waste shall be cleaned up and removed using a vacuum equipped with a HEPA filter, or by damp mopping or wet sweeping, and placed in a suitable container, and drop sheets shall be wetted and placed in suitable container. 7. Drop sheets shall not be reused. 8. After the work is completed, polyethylene sheeting and similar materials used for barriers and enclosures shall not be reused, but shall be wetted and placed in a suitable container as soon as practicable. 9. After the work is completed, barriers and portable enclosures that will be reused shall be cleaned, by using a vacuum equipped with a HEPA filter or by damp wiping, as soon as practicable. 10. Barriers and portable enclosures shall not be reused unless they are rigid and can be cleaned thoroughly.

Page 22: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

22

11. The employer shall provide every worker who will enter the work area with a CSA approved respirator in accordance with the attached Table and the worker shall wear and use the respirator. 12. Protective clothing shall be provided by the employer and worn by every worker who enters the work area, and the protective clothing,

shall be made of a material that does not readily retain nor permit penetration of asbestos fibres,

shall consist of head covering and full body covering that fits snugly at the ankles, wrists and neck, in order to prevent asbestos fibres from reaching the garments and skin under the protective clothing,

shall include suitable footwear, and

shall be repaired or replaced if torn. 13. Compressed air shall not be used to clean up and remove dust from any surface. 14. Only persons wearing protective clothing and equipment shall enter a work area where there is an asbestos dust hazard. Additional Procedures, Type 2 Operations In addition to the measures and procedures prescribed previously, the following measures and procedures apply to Type 2 operations: 1. Before commencing work that is likely to disturb friable asbestos-containing material that is crumbled, pulverized or powdered and that is lying on any surface, the friable material shall be cleaned up and removed by damp wiping or by using a vacuum equipped with a HEPA filter. 2. Friable asbestos-containing material that is not crumbled, pulverized or powdered and that may be disturbed or removed during the work shall be thoroughly wetted before the work and kept wet during the work, unless wetting would create a hazard or cause damage. 3. The spread of dust from a work area shall be prevented by

using an enclosure of polyethylene or other suitable material that is impervious to asbestos (including, if the enclosure is opaque, one or more transparent window areas to allow observation of the entire work area from outside the enclosure), if the work area is not enclosed by walls, and kept under negative air pressure relative to non-work areas by use of HEPA filtered equipment,

disabling the mechanical ventilation system serving the work area, and

sealing the ventilation ducts to and from the work area.

Page 23: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

23

4. Before leaving the work area, a worker shall,

decontaminate his or her protective clothing by using a vacuum equipped with a HEPA filter, or by damp wiping, before removing the protective clothing, and

if the protective clothing will not be reused, place it in a suitable container. 5. Facilities for the washing of hands and face shall be made available to workers and shall be used by every worker when leaving the work area. Additional Type 2 Procedures, Glove Bag Operations In addition to the measures and procedures prescribed previously, the following measures and procedures apply to Type 2 operations referred to as glove bag operations. 1. The work area shall be separated from the rest of the workplace by walls, barricades, fencing or other suitable means. 2. The spread of asbestos-containing material from the work area shall be prevented by disabling the mechanical ventilation system serving the work area and sealing all openings or voids, including ventilation ducts to and from the working area. 3. Surfaces below the work area shall be covered with drop sheets of polyethylene or other suitable material that is impervious to asbestos. 4. The glove bag shall be made of material that is impervious to asbestos and sufficiently strong to support the weight of material the bag will hold. 5. The glove bag shall be equipped with,

sleeves and gloves that are permanently sealed to the body of the bag to allow the worker to access and deal with the insulation and maintain a sealed enclosure throughout the work period,

valves or openings to allow insertion of a vacuum hose and the nozzle of a water sprayer while maintaining the seal to the pipe, duct or similar structure,

a tool pouch with a drain,

a seamless bottom, and

a high strength double throw zipper and removable straps, if the bag is to be moved during the removal operation.

6. A glove bag shall not be used to remove insulation from a pipe, duct or similar structure if,

it may not be possible to maintain a proper seal for any reason including, without limitation,

o the condition of the insulation, or o the temperature of the pipe, duct or similar structure, or

Page 24: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

24

the bag could become damaged for any reason including, without limitation, o the type of jacketing, or o the temperature of the pipe, duct or similar structure.

7. Immediately before the glove bag is attached, the insulation jacketing or coating shall be inspected for damage or defects, and if any damage or defect is present, it shall be repaired. 8. The glove bag shall be inspected for damage or defects,

immediately before it is attached to the pipe, duct or other similar structure, and

at regular intervals during its use. 9. If damage or defects are observed when the glove bag is inspected the glove bag shall not be used and shall be disposed of. 10. If damage or defects are observed when the glove bag is inspected at any other time,

the use of the glove bag shall be discontinued,

the inner surface of the glove bag and the contents, if any, shall be thoroughly wetted,

the glove bag and the contents, if any, shall be removed and placed in a suitable container, and

the work area shall be cleaned by vacuuming with a vacuum equipped with a HEPA filter before removal work is resumed.

11. When the removal work is completed,

the inner surface of the glove bag and the waste inside shall be thoroughly wetted and the air inside the bag shall be removed through an elasticized valve, by means of a vacuum equipped with a HEPA filter,

the pipe, duct or similar structure shall be wiped down and sealed with a suitable encapsulant,

the glove bag, with the waste inside, shall be placed in a container, and

the work area shall be cleaned by damp wiping or by cleaning with a vacuum equipped with a HEPA filter.

Additional Procedures, Type 3 Operations In addition to the measures and procedures prescribed previously, the following measures and procedures apply to Type 3 operations: 1. Friable asbestos-containing material that is crumbled, pulverized or powdered and that is lying on any surface in the work area shall be cleaned up and removed using a vacuum equipped with a HEPA filter or by damp wiping and everything shall be removed from the work area or covered with polyethylene sheeting or other suitable material that is impervious to asbestos.

Page 25: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

25

2. The spread of dust from the work area shall be prevented by an enclosure of polyethylene or other suitable material that is impervious to asbestos, if the work area is not enclosed by walls, and by a decontamination facility consisting of a series of interconnecting rooms including,

a room suitable for changing into protective clothing and for storing contaminated protective clothing and equipment,

a shower room as described in paragraph 7,

a room suitable for changing into street clothes and for storing clean clothing and equipment, and

curtains of polyethylene sheeting or other suitable material that is impervious to asbestos, fitted to each side of the entrance or exit to each room.

3. The rooms described above shall be arranged in sequence and constructed so that any person entering or leaving the work area must pass through each room. 4. The mechanical ventilation system serving the work area shall be disabled and all openings or voids, including ventilation ducts to or from the work area, shall be sealed by tape or other appropriate means. 5. The spread of dust from the work area shall also be prevented by,

creating and maintaining within the enclosed area, by installing a ventilation system equipped with a HEPA filtered exhaust unit, a negative air pressure of 0.02 inches of water, relative to the area outside the enclosed area. Specific requirements for integrity-testing of the filtration system of any HEPA filtered equipment (negative air units, vacuums) are noted in the Code of Practice attached to this document. Different requirements are in place for systems venting exhausted air to the building exterior versus systems vented exhausted air back into the building.

ensuring that replacement air is taken from outside the enclosed area and is free from contamination with any hazardous dust, vapour, smoke, fume, mist or gas, and

using a device, at regular intervals, to measure the difference in air pressure between the enclosed area and the area outside it.

The ventilation system noted above must be left in operation until completion and acceptance of final air monitoring within the enclosed space.

Where exhausted air is discharged into non work areas on the building rather than outside, air testing will be conducted daily outside of the enclosure to ensure that airborne fibre levels do not exceed 0.01 fibres/cc.

6. The ventilation system referred to above shall be inspected and maintained by a competent worker before each use to ensure that there is no air leakage, and if the filter is found to be damaged or defective, it shall be replaced before the ventilation system is used. 7. The shower room in the decontamination facility shall,

Page 26: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

26

be provided with hot and cold water or water of a constant temperature that is not less than 40° Celsius or more than 50° Celsius,

have individual controls inside the room to regulate water flow and, if there is hot and cold water, individual controls inside the room to regulate temperature,

be capable of providing adequate supplies of hot water to maintain a water temperature of at least 40° Celsius, and

be provided with clean towels. 8. When leaving the work area, a worker shall enter the decontamination facility and shall, in the following order,

decontaminate his or her protective clothing by using a vacuum equipped with a HEPA filter, or by damp wiping, before removing the protective clothing,

place protective clothing it in a suitable waste container,

shower, and

remove and clean the respirator. 9. If practicable, existing electrical power distribution systems that are not water-tight shall be de-energized and locked out where wet removal operations are to be carried out. 10. Temporary electrical power distribution systems for tools and equipment involved in wet removal operations shall be equipped with ground fault circuit interrupters. 11. Friable asbestos-containing material shall be thoroughly wetted before and during removal, unless wetting would create a hazard or cause damage. Amosite and crocidolite cannot be removed by dry procedures. 12. The work area shall be inspected by a competent worker for defects in the enclosure, barriers and decontamination facility,

at the beginning of each shift,

at the end of a shift if there is no shift that begins immediately after the first-named shift, and

at least once each day on days when there are no shifts. 13. Defects observed during an inspection shall be repaired immediately and no other work shall be carried out in the work area until the repair work is completed. 14. If practicable, dust and waste shall be kept wet. 15. On completion of the work,

negative air pressure shall be maintained until air testing is complete,

the inner surface of the enclosure and the work area inside the enclosure shall be cleaned by a thorough washing or by vacuuming with a vacuum equipped with a HEPA filter,

Page 27: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

27

equipment, tools and other items used in the work shall be cleaned with a damp cloth or by vacuuming with a vacuum equipped with a HEPA filter or they shall be placed in a suitable waste container before being removed from the enclosure, and

a visual inspection shall be conducted by a competent worker to ensure that the enclosure and the work area inside the enclosure are free from visible dust, debris or residue that may contain asbestos.

16. Once the work area inside the enclosure is dry after the steps set out above have been completed, clearance air testing shall be conducted by a competent worker. 17. The barriers, enclosure and decontamination facility shall not be removed or dismantled until,

cleaning has been done as described above, and

if clearance air testing is required, it has been completed and the work area inside the enclosure has passed the clearance air test.

Additional Procedures, Emergency Operations 1. Emergency work, defined as an immediate response required to address an unexpected possible release of asbestos-containing materials, may be required if

building materials not known to be asbestos-free are damaged or otherwise disturbed,

known ACMs are damaged or otherwise disturbed by accident,

known ACMs are damaged or otherwise disturbed intentionally,

known ACMs may be impacted or must be removed immediately to permit proper responses to other emergency circumstances to be addressed.

2. All emergency work will be conducted following Type 1, 2 and 3 procedures (including Glove Bag) as noted in the sections.

3. Immediately stop work (if the asbestos has been damaged from a work-related activity) in the area and notify the supervisor or designate or competent asbestos consulting firm should any unexpected materials or materials suspect of containing asbestos be encountered. Do not clean-up, cover, move or otherwise disturb the suspect asbestos-containing material in question.

4. Have the supervisor or designate, or others in his/her absence, advise occupants to vacate the area.

5. Where practical, or where such actions will not interfere with established emergency or fire routes, isolate the area in question by closing and locking all perimeter exists. In the alternative, workers shall establish a tape or rope barricade complete with necessary signage at all points of entry.

Page 28: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

28

6. The supervisor or designate or others in his/her absence shall make arrangements to shut down ventilation systems to or from the affected area where the materials concerned are friable or may contain amphibole asbestos.

7. The supervisor or designate shall then determine if the material in question contains any asbestos, the extent of any contamination (if any) to surrounding areas and the desired course of action. If necessary, the supervisor or designate shall collect a representative sample of the material (debris) in question and have it submitted for analysis.

8. Should the material (debris) in question be determined or assumed to be asbestos, the affected area shall be cleaned-up while following the appropriate asbestos precautions.

9. Do not resume work in the area until it has been determined if the material in question contains asbestos, the required clean-up (if necessary) has been completed, and that authorization to return to the area has been given.

Clearance Air Testing 1. Sample collection and analysis shall be done,

using the phase contrast microscopy method, or

using the transmission electron microscopy method. 2. If the work area inside the enclosure fails the clearance air test, the area shall be recleaned and retested. 3. Clearance air testing using the phase contrast microscopy method shall be carried out in accordance with NIOSH Method 7400, using the asbestos fibre “A” counting rules, and shall comply with the following requirements:

Testing shall be based on samples taken inside the enclosure.

Forced air shall be used, both before and during the sampling process, to ensure that fibres are dislodged from all surfaces inside the enclosure before sampling begins and are kept airborne throughout the sampling process. Agitation of air must last for 5 minutes for each 90 m3 of enclosed volume being tested.

The number of air samples to be collected is noted the attached Table.

The work area inside the enclosure passes the clearance air test only if every air sample collected has a concentration of fibres that does not exceed 0.01 fibres/cm3 of air.

When a second analysis is done if needed, the work area inside the enclosure passes the clearance air test only if every air sample collected has a concentration of asbestos fibres that does not exceed 0.01 fibres per cubic centimetre of air.

Page 29: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

29

Table 3 - Air Samples

Minimum number of air samples to be taken from each enclosure

Number of Tests

For every 270 m3 of enclosed volume 1 test per 270 m3

SECTION F. Training of Staff All Municipality of the County of Annapolis staff whose job may require working with asbestos containing materials will receive asbestos awareness training. This training is not intended to be sufficient to permit asbestos removal to be undertaken, but is instead intended to ensure that employees are aware of:

What asbestos is

What type of products can contain asbestos

The risks of working with asbestos

Personal protective measures

Sampling protocols

Guidelines and Codes of Practice

Introduction to the various removal protocols

Protocols for determination if asbestos may be present

Protocols for addressing planned and unplanned disturbances This training can be provided by outside consultants or in-house personnel as necessary. All training will be conducted not less than annually and prior to any employee working with ACMs. A copy of a “checklist” for respirator care, fitting and inspection as well as a copy of a certificate to acknowledge basic worker awareness training are attached in Appendices 1 and 2.

Page 30: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

30

Appendix 1. Respirator Care

The following applies to the use of a Half-faced Negative Pressure Air Purifying Respirator equipped with P100 filters.

WARNING: Such respirators do not generate or have their own supply of oxygen. They must not be used in oxygen deficient atmospheres (less than 19.5%) and must not be worn for removal of friable asbestos unless using a glove bag.

Respirators filters must be approved for protection against asbestos.

RESPIRATOR FITTING

Persons required to wear a respirator must first pass a qualitative fit-test administered in accordance with the most current version of CSA standard Z-94.4. The fit-test should be repeated yearly with the records maintained on file.

The respirator wearer must be clean-shaven along all the seal points for proper protection to be obtained. Even stubble growth may be sufficient to reduce the seal of the face-piece and, therefore, the protection. The respirator approval is voided for users with facial hair that may interfere with the seal.

CHECK PRIOR TO EACH USE

Examine facepiece for any: o dirt (clean if necessary); o cracks, tears or holes (obtain new face-piece); o distortion and inflexibility (stretch and knead to restore shape and flexibility or

obtain new face-piece); o cracks, or breaks in filter holders, worn threads and missing gaskets (replace or

obtain new face-piece).

Examine head straps for any: o breaks or tears (replace if discovered); o loss of elasticity (replace if discovered); o broken or malfunctioning buckles and attachments (replace if discovered).

Examine valves for signs of any: o detergent residue, dust or other material on valves or valve seats (clean before

use); o cracks, tears or distortion in the valve material (replace if discovered); o missing or defective valves or valve covers (replace if discovered).

Examine filter for: o proper filter for protection against asbestos (High Efficiency Particulate) o incorrect installation, loose connections, missing or worn gaskets or cross

threading (remove and re-install); o cracks or dents in filter housing (replace if discovered).

Perform the following tests for leaks on each donning of the respirator:

Page 31: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

31

o negative pressure test: cover inlets to filters, breathe in and hold breath; respirator should be drawn to face for minimum of 10 seconds (if not, check exhalation valve and fit);

o positive pressure test: cover exhalation valve cover and puff out slightly and hold breath; respirator should slightly pressurize and still hold seal (if not, check inhalation valves and fit).

RESPIRATOR CLEANING AND DISINFECTION

Remove filters and disassemble face-piece. Discard or repair defective parts.

Wash components in warm water (50oC - 60oC) with mild detergent, using a brush. Respirator suppliers can provide ready-made cleaning and disinfectant solutions and instructions for use.

Thoroughly rinse components in clean, warm water.

Air dry or hand dry components with a clean, lint-free cloth.

Reassemble respirator and test to ensure that all components are working properly (see above). Be careful to check that valves are not lost in cleaning.

Use of positive pressure respiratory protection will not be required by employees of the Municipality of the County of Annapolis.

Page 32: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

32

Appendix 2. Training Acknowledgement

WORKING WITH ASBESTOS CAN BE DANGEROUS. INHALING ASBESTOS FIBRES CAN CAUSE VARIOUS TYPES OF LUNG DISEASE INCLUDING CANCER. SMOKING INCREASES THE RISK OF LUNG CANCER FROM ASBESTOS EXPOSURE.

RESPIRATOR PROTECTION: I have been supplied with a respirator and received training for its proper use including qualitative fit testing (irritant smoke). I understand that I must be free of any facial hair that may interfere with the seal of the respirator with my face.

TRAINING COURSE: I have been trained in the dangers inherent in handling asbestos and breathing asbestos dust and in proper work procedures and personal and area protective measures. The topics covered in the course included the following:

Awareness Training:

Physical characteristics and use of asbestos

Health hazards associated with asbestos

Sampling and analytical methods

Regulations concerning work with asbestos

Assessment of asbestos containing materials

Respiratory protection

Use of protective equipment

General practices for asbestos removal

By signing this certificate, I acknowledge that I have received the above training and agree to follow these procedures for all work assigned to me.

EMPLOYEE NAME:

DATE OF TRAINING:

RESPIRATOR MANUFACTURER: SIZE:

SIGNATURE: DATE:

TRAINER: DATE:

Page 33: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

33

Appendix 3. Contractor’s Notification and Acknowledgement

Municipality of the County of Annapolis has identified the presence of various friable and non-friable asbestos-containing materials as being present throughout properties under its control and administration. For a complete listing of any asbestos-containing or suspect asbestos materials known to be present, refer to the inventory attached to this document.

Contractors other than abatement contractors must ensure their workers, at a minimum, are provided with asbestos awareness training. Proof of training must be presented to Municipality of the County of Annapolis before commencing work at a site.

The Asbestos Management Plan prepared by Municipality of the County of Annapolis applies to all maintenance and renovation work that may disturb asbestos or suspect asbestos-containing materials in the workplace. This document states that any disturbance of asbestos-containing materials may only be performed by workers or by an outside contractor who have first received the required training in asbestos-related precautions.

The following is a partial listing of typical activities that will or may disturb known asbestos-containing materials and hence requiring the implementation of Type 1, 2 or 3 asbestos precautions. Any Contractor required to perform any of the following activities and/or similar tasks that may result in the disturbance of known or suspect asbestos-containing materials must first obtain a signed and authorized Asbestos Work Permit from the Supervisor or designate.

Access above a suspended or enclosed ceiling system at a location where known asbestos-containing spray or trowel applied fireproofing, thermal or acoustic insulation is present.

Access within a crawlspace, pipe chase, service area or tunnel where damaged asbestos-containing materials are known to be present.

Work that may disturb any spray or trowel applied fireproofing, thermal or acoustic insulation known to contain asbestos.

Work that may disturb any asbestos-containing spray or trowel applied texture coats.

Work that may disturb any asbestos mechanical insulation (i.e. pipes, ducts, vessels, boiler, etc.).

Removal, clean-up or repair of any asbestos mechanical insulation (i.e. pipes, ducts, vessels, boilers, etc.).

Removal of asbestos-containing ceiling tiles.

Removal of asbestos-containing sheet flooring products.

Removal, cutting, drilling or other such disturbance of any non-friable asbestos materials (i.e. vinyl composite tile, asbestos hardboard, transite panelling, asbestos cement pipes, etc.).

Page 34: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

34

Demolition, cutting, drilling or other such disturbance of any plaster finishes/drywall compound (i.e. wall or ceiling) known to contain asbestos and/or listed as a suspect material in the above mentioned asbestos survey report.

Other materials, as informed by subsequent notices.

As a condition of our contract to provide services and materials to Municipality of the County of Annapolis, we, the undersigned company hereby agree to perform our work in such a manner so as NOT to disturb any asbestos-containing materials without prior authorization and notification of the Municipality of the County of Annapolis supervisor or designate. We further acknowledge that this firm and its employees, as referenced in the AMP, will conduct our work in accordance with such requirements and in compliance with all provincial regulation or guidelines pertaining to asbestos; and that all asbestos waste will be packaged and disposed of at a licensed landfill.

COMPANY NAME:

SIGNATURE: DATE:

NAME & TITLE:

Page 35: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

35

Appendix 4. Asbestos Work Permit

NOTICE: All work shall conform to Federal, Provincial, Municipal standards, codes and guidelines and the requirements set forth in the Asbestos Management Program for Municipality of the County of Annapolis or any project specifications prepared. In the case of a conflict in any of the above noted documents, the most stringent shall apply.

PERMIT NO.

Asbestos Work Request Originator

Contact Telephone No.

Date of Request Anticipated Start Date Anticipated Completion date day month year day month year day month year

Work Site Location Project Description

Work will be completed by:

Municipality of the County of Annapolis Employees

Pre-Qualified Contractor

Specify Contractor:

ASBESTOS PROCEDURES Check all applicable

Material Comments

Ceiling Tiles

Contaminated Space Entry (ceiling, crawlspace, shaft, chase, etc.)

Sheet Flooring

Floor Tiles

Asbestos Cement Panels

Mechanical Insulation

Asbestos Containing pipe elbows

Page 36: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

36

Asbestos Debris Clean-up

Electrical

ACM Drywall joint compound

OTHER CONTROL FACTORS

Evening Work Specify Hours:

Day Work Specify Hours:

Weekend Work Specify Hours:

Restricted Access to Work Area by Occupants

Specify Areas:

Re-location of occupants required Specify Area to be Relocated:

Inspection and Air Monitoring Required Arrangements Made for Inspections

HVAC Shut Down Specify Hours and Zones:

Other System Shut Down Specify:

NOTIFICATION

Notification Sent to: Site Supervisor or designate

Building Services Director

Municipality of the County of Annapolis Approval

SIGNATURE: DATE:

NAME & TITLE:

Page 37: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

37

Appendix 5. Codes of Practice

A Guide to the Assessment and Management of Asbestos in the Workplace – Code of Practice

A guide to the Removal of Friable Asbestos Containing Material – Code of Practice

Maintenance Operation Involving Asbestos Guidelines

Outdoor Work with Asbestos Guidelines

Page 38: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

38

Appendix 6. Asbestos Survey Results Samples were collected in each of the following buildings of every material that could be reasonably expected to contain asbestos. Both friable and non-friable products were tested. Materials known not to contain asbestos, such as fibreglass insulations on pipes, cellulose ceiling tiles, etc were not sampled and are not otherwise specifically referenced. Surveys were generally conducted to be non-intrusive and cause minimal damage, meaning that test holes were not advanced into wall/ceiling/floor cavities nor through roofing structures to collect samples. The reader is advised that, should demolition or extensive renovation be required, additional testing may be needed to address these issues. Please note the following specific limitations of these survey data:

Vermiculite insulation might be present between brick veneers and exterior structural components on in cavities in hollow concrete block walls. It may also be present in attic cavities that could not be inspected. Vermiculite can contain amphibole asbestos in low concentrations as a contaminant.

Test data may be of insufficient detail to support major renovations or demolitions.

Asbestos containing flooring materials may be covered by newer non-asbestos containing materials. Efforts were made during survey work to identify such possibilities but not all may have been identified.

In general, roofing materials were not sampled to avoid creating leaks.

Some buildings have been renovated in part with asbestos containing plasters, drywall joint fillers and flooring materials remaining in the older sections and non-asbestos containing products being present in the newer sections. In some cases, particularly with drywall joint filler, the “cross over” points are not necessarily obvious, and can be a problem when only portions of older buildings were renovated (i.e. one wall in an office or one office in an area).

As a visual guide, drywall joint fillers that are of a “tan” or “straw yellow” colour contain asbestos. This material was found in some buildings together with “grey” or “white” materials that were of newer construction and did not contain asbestos. It is not practical during survey work to attempt to categorise these materials on each wall to the level where uncertainty can be reduced to near zero. Additional testing on a specific “case-by-case” basis may be required where generalities are insufficient to provide the needed guidance.

Test data describing various types of floor and ceiling tiles in specific rooms should be interpreted to imply that all similar materials in other rooms meeting the same

Page 39: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

39

description should be considered to be the same composition. For example, if brown 9x9 inch floor tiles in Room A contain asbestos then all other similar tiles in the building should be presumed to also contain asbestos.

Fires doors were not samples but older ones may contain asbestos insulation as a filler.

Although concrete mortars and grouts were sampled, note that these materials are extremely non-homogenous in nature. If used, asbestos content would be expected to be very low and potentially not detectable by routine light microscopical methods. Overall, if these materials must be pulverised, drilled or otherwise damaged such that airborne concrete dust is created, additional larger samples might need to be collected. As well, not that most concrete materials have crystalline silica, and protection needed to address exposure to this would also be suitable to protect from asbestos.

The following buildings were surveyed with results following:

Administration Buildings o Annapolis Royal Administration Building o Lawrencetown Office o Bridgetown Office o Granville Ferry Public Works Building

Wastewater Treatment Plants o Cornwallis Park o Bridgetown (full survey not needed, plaster samples collected from one building)

Water Treatment Plants o Margaretsville o Cornwallis Park

Other o Bridgetown Arena o Bridgetown Pool o Raven Haven o Jubilee Park (full survey not needed, floor tile samples collected from one

building) The following Buildings were not surveyed due to construction dates after 1990:

o Nictaux wastewater treatment plant o Granville Ferry water treatment plant o Bridgetown water treatment plant

Page 40: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

40

Sample Analysis Results and Summary, Annapolis Royal Administration Building.

Building Description.

Building is constructed in two sections – one built in 1940s-1950s and the other built in the 1970s.

Both sections have concrete floors covered with combinations of seamless flooring, ceramic tiles, carpets, 9x9 and 12x12 inch floor tiles.

Walls are composed of combinations of unfinished concrete and concrete covered in drywall and plaster.

Ceilings are composed of combinations of unfinished concrete and concrete covered in texture coat (only 1940s-1950s section, not 1970s section), drywall and plaster.

Pipe runs are insulated with fibreglass on straight sections and fibreglass and/or cementitious materials on fittings. Some of both materials are also covered in texture coat.

The boiler room is located in the 1940s-1950s section – insulation was upgraded recently and none is original. Walls in boiler room have transite panels.

Test Data.

Here are test data for sample that were collected from the Annapolis Royal Administration Building on 18 June, 2016, and then analysed asbestos content testing by light microscopy method EPA 600/R-93/116.

Sample Label Description Friable Asbestos Content

1940s-1950s Section

Sample 1 Room 201/202 blue seamless flooring no none

Sample 2 Room 201/202 skim coat on concrete floor no none

Sample 3 Room 201/202 Beige seamless flooring no none

Sample 4 Room 201/202 Texture coat yes 5% chrysotile asbestos

Sample 5 Room 201/202 Adhesive blue baseboard no none

Sample 6 Stairs near Room 201 12x12 beige/green floor tile

no none

Sample 7 Stairs near Room 201 white skim coat on exterior wall

no none

Sample 8 Stairs near Room 201 rubber baseboard adhesive

no none

Sample 9 Hallway near Room 209 drywall joint filler interior wall

yes 5% chrysotile asbestos

Sample 10 Room 208 hardwood floor style seamless no none

Sample 11 Room 204/205 drywall joint filler interior wall yes 5% chrysotile asbestos

Sample 12 Room 209 texture coat ceiling/column yes 5% chrysotile asbestos

Sample 13 Room 210 drywall joint compound interior wall

yes 5% chrysotile asbestos

Sample 14 Room 211 texture coat exterior wall yes 5% chrysotile asbestos

Sample 15 Room 212 white baseboard adhesive no none

Sample 16 Room 207 12x12 grey floor tiles no 2% chrysotile asbestos

Page 41: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

41

Sample 17 Rear stairwell near Room 218 pipe fitting insulation

yes 50% chrysotile asbestos

Sample 18 Rear stairwell near Room 218 concrete block mortar

no none

Sample 19 Rooms 215-218 texture coat yes 5% chrysotile asbestos

Sample 20 Room 219 12x12 grey floor tiles under new seamless flooring

no 2% chrysotile asbestos

Sample 21 Room 219 white skim coat plaster on concrete yes 1-2% chrysotile asbestos

Sample 22 Room 203 texture coat yes 5% chrysotile asbestos

Sample 23 Room 203 drywall joint filler interior wall yes none

Sample 24 Room 214 texture coat yes 5% chrysotile asbestos

Sample 25 Room 214 drywall joint filler exterior wall yes none

Sample 26 Room 111/112 small diameter pipe fitting insulation

yes 50% chrysotile asbestos

Sample 27 Room 111/112 large diameter pipe fitting insulation

yes 50% chrysotile asbestos

Sample 28 Room 111/112 texture coat on pipes yes 5% chrysotile asbestos

Sample 29 Room 114/115 White skim coat on plaster exterior wall

yes none

Sample 30 Room 114/115 drywall joint filler yes 5% chrysotile asbestos

Sample 31 Hallway next to Room 114 ceiling tiles yes none

Sample 32 Room 110 texture coat yes 5% chrysotile asbestos

Sample 33 Room 109 texture coat on pipes yes 5% chrysotile asbestos

Sample 34 Room 105 small diameter pipe fitting insulation

yes 50% chrysotile asbestos

Sample 35 Room 105 large diameter pipe fitting insulation

yes 50% chrysotile asbestos

Sample 36 Room 109 drywall joint filler yes 5% chrysotile asbestos

Sample 37 Room 104 brown baseboard adhesive no none

Sample 38 Room 103 small diameter pipe fitting insulation

yes 50% chrysotile asbestos

Sample 39 Room 103 drywall joint filler yes 5% chrysotile asbestos

Sample 40 Room 102 straight pipe insulation with parging beneath

yes none

Sample 41 Hallway near Room 108 texture coat yes 5% chrysotile asbestos

Sample 42 Room 106 drywall joint filler yes 5% chrysotile asbestos

Sample 43 Room 117 skim coat on plaster exterior wall yes none

Sample 44 Room 116 skim coat on plaster exterior wall yes none

Sample 45 Room 116 12x12 vinyl floor tiles no none

Sample 46 Room 116 9x9 vinyl floor tiles no 2% chrysotile asbestos

1970s Section

Sample 47 Hallway by Room 119 drywall joint filler yes none

Sample 48 Hallway by Room 119 leveling compound no none

Sample 49 Rooms 136-138 drywall joint filler yes none

Page 42: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

42

Sample 50 Room 138 incandescent light heat shield yes 75% chrysotile asbestos

Sample 51 Stairs near open area drywall joint filler yes 5% chrysotile asbestos

Sample 52 Hallway next to Room 229 drywall joint filler interior walls

yes none

Sample 53 Hallway next to Room 229 ceiling tiles yes none

Sample 54 Hallway next to Room 229 seamless flooring no none

Sample 55 Room 233 drywall joint filler exterior wall yes none

Sample 56 Room 228 drywall joint filler exterior walls yes none

Sample 57 Room 234 drywall joint filler exterior walls yes none

Sample 58 Hallway near Room 235 ceiling tiles yes none

Sample 59 Hallway near Room 235 drywall joint filler yes none

Sample 60 Room 220 drywall joint filler yes none

Boiler Room, 1940s -1950s Section

Sample 61 Panelling on wall no 35% chrysotile asbestos

Exterior

Sample 62 Near main entrance brick mortar no none

Sample 63 Pinkish brick mortar no none

Sample 64 Black window caulking no none

Sample 65 White/beige window caulking no none

Sample 66 Brick mortar no none

Sample 67 Brick mortar no none

Sample 68 Grey window caulking against brick mortar 1950s section

no 10% chrysotile asbestos

Sample 69 Brick mortar no none

Sample 70 Brick mortar no none

Summary. Based upon these data, the following materials should be presumed to contain asbestos at this location.

All texture coat in 1940s-1950s section

All drywall joint filler in 1940s-1950s section

All insulating cement on pipe fittings 1940s-1950s section

Grey 12x12 inch floor tiles in Room 207 under carpets and all similar

All 9x9 inch floor tiles

All plaster materials in 1940s-1950s section should be presumed to contain asbestos

All incandescent light shield insulation in 1970s section

Drywall joint filler near stairs in open area 1970s section

Panelling on boiler room wall

Grey exterior window caulking in 1950s section

Fire doors not sampled, all should be presumed to contain asbestos

Page 43: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

43

Sample Analysis Results and Summary, Bridgetown Pool.

Building Description.

Built in 1967

Flooring is concrete

Walls are concrete block

Ceiling is wooden plank

No insulation on pipes other than fibreglass and foam Test Data.

Here are test data for samples that were collected from the Bridgetown Pool Building on 22 June, 2016, and then analysed asbestos content testing by light microscopy method EPA 600/R-93/116.

Sample Label Description Friable Asbestos Content

Sample 1 Chlorine Mechanical room concrete block mortar

no none

Sample 2 Training Room concrete block mortar

no none

Sample 3 Girls Area concrete block mortar no none

Sample 4 Boys Area concrete block mortar

no none

Sample 5 Concrete floor coating no none

Sample 6 Caulking from building to pool deck

no none

Sample 7 Caulking concrete seams pool deck

no none

Sample 8 Exterior concrete block mortar no none

Sample 9 Exterior concrete block mortar no none

Sample 10 Caulking on concrete block seam

no none

Summary.

No asbestos containing materials were identified at this location.

Page 44: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

44

Sample Analysis Results and Summary, Raven Haven Park.

Building Description.

Series of Cabins

No water-based or forced air heating

Vinyl siding on exterior walls

Back section of canteen with shower built in 1997 not surveyed

Part of Manager’s cabin renovated in 2007 not surveyed

Drywall walls and ceilings in canteen, ceiling tiles in some cabins

Seamless flooring and vinyl tiles

No vermiculite in attics

No insulated pipes

Test Data.

Here are test data for samples that were collected from the Raven Haven Park buildings on 16 June, 2016, and then analysed asbestos content testing by light microscopy method EPA 600/R-93/116.

Sample Label Description Friable Asbestos Content

Canteen

Sample 1 Hallway entrance white seamless flooring

no none

Sample 2 Hallway entrance floor tiles under white seamless flooring

no 5% chrysotile asbestos

Sample 3 Life jacket room drywall joint filler

yes 5% chrysotile asbestos

Sample 4 Staff washroom drywall joint filler

yes 5% chrysotile asbestos

Sample 5 Staff washroom seamless flooring

no none

Sample 6 Staff washroom 9x9 floor tiles stored next to water heater

no 5% chrysotile asbestos

Sample 7 Canteen brown seamless flooring

no none

Sample 8 Canteen white seamless flooring under brown seamless flooring

no none

Sample 9 Canteen drywall joint filler yes 5% chrysotile asbestos

Sample 10 Canteen blue/grey seamless flooring

no none

Sample 11 Canteen drywall joint filler yes 5% chrysotile asbestos

Sample 12 Staff room peel and stick flooring

no none

Sample 13 Staff room drywall joint filler yes 5% chrysotile asbestos

Sample 14 Hallway drywall joint filler yes 5% chrysotile asbestos

Sample 15 Storage room 9x9 flooring no none

Page 45: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

45

Sample 16 Storage room drywall joint filler yes 5% chrysotile asbestos

Cabin 1

Sample 1 Waterfront Bedroom white seamless flooring

no none

Sample 2 Waterfront Bedroom drywall joint filler

yes 2% chrysotile asbestos

Sample 3 Rear Bedroom drywall joint filler yes 2% chrysotile asbestos

Cabin 2

Sample 1 Waterfront Bedroom, drywall joint filler

yes 2% chrysotile asbestos

Sample 2 Bunk Bedroom drywall joint filler

yes 2% chrysotile asbestos

Sample 3 Main area white/blue seamless flooring

no none

Manager’s Cabin

Sample 1 Main area seamless flooring, 2 layers

no none in either

Sample 2 Spare bedroom seamless flooring, 2 layers

no none in either

Sample 3 Bedroom drywall joint filler yes 2% chrysotile asbestos

Hostel Cabins 1/2

Sample 1 Ceiling drywall joint filler yes 2% chrysotile asbestos

Sample 2 Wall drywall joint filler yes 2% chrysotile asbestos

Sample 3 Wall drywall joint filler yes 2% chrysotile asbestos

Summary. Based upon these data, the following materials should be presumed to contain asbestos at this location.

All drywall joint filler in all buildings

Page 46: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

46

Sample Analysis Results and Summary, Granville Ferry Public Works Building.

Building Description.

Concrete stone and mortar foundation walls

Vinyl siding, windows are new

Floors are bare concrete or concrete with floor tiles, plywood and new seamless flooring, combination of new and old materials

Walls and ceilings are plywood or drywall, combination of new and old materials

Forced hot air furnace, no insulated ducts

Furnace room has plaster ceiling

Test Data.

Here are test data for sample(s) that we collected from the Granville Ferry Public Works Building on 16 June, 2016, and then analysed asbestos content testing by light microscopy method EPA 600/R-93/116.

Sample Label Description Friable Asbestos Content

Sample 1 Garage loading area, drywall joint filler

yes none

Sample 2 Garage loading area, drywall joint filler

yes none

Sample 3 Garage loading area, concrete block mortar

no none

Sample 4 Lunchroom, wall drywall joint filler

yes none

Sample 5 Lunchroom, ceiling drywall joint filler

yes 5% chrysotile asbestos

Sample 6 Office area, wall drywall joint filler

yes 5% chrysotile asbestos

Sample 7 Locker room, wall drywall joint filler

yes 5% chrysotile asbestos

Sample 8 Locker room, ceiling drywall joint filler

yes 5% chrysotile asbestos

Sample 9 Locker room, chimney concrete no none

Sample 10 Attic, plaster ceiling yes none

Sample 11 Attic, plaster ceiling yes none

Sample 12 Attic, chimney concrete yes none

Sample 13 Storage room near washroom, drywall joint filler

yes 5% chrysotile asbestos

Sample 14 Tool storage, 9x9 brown floor tiles

no 15% chrysotile asbestos

Sample 15 Tool storage, 9x9 beige floor tiles

no 15% chrysotile asbestos

Sample 16 Workshop, wall drywall joint filler

yes 5% chrysotile asbestos

Page 47: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

47

Sample 17 Workshop, ceiling drywall joint filler

yes 5% chrysotile asbestos

Sample 18 Basement/furnace room, plaster ceiling

yes none

Sample 19 Basement, concrete block mortar

no none

Sample 20 Basement, foundation mortar no none

Sample 21 Basement, foundation mortar no none

Sample 22 Basement, foundation mortar no none

Summary. Based upon these data, the following materials should be presumed to contain asbestos at this location.

This building has been renovated and both original and newer materials are present; asbestos is present in original construction materials as noted below.

All original drywall joint filler contains asbestos

All original floor tiles contain asbestos

Page 48: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

48

Sample Analysis Results and Summary, Bridgetown Fire Hall.

Building Description.

Brick exterior walls

Floors are bare concrete or concrete with seamless flooring

Walls and ceilings are drywall and suspended ceiling tiles

Forced hot air furnace, no insulated ducts

Furnace room has plaster ceiling

Fibreglass insulation above ceiling tiles

No insulation on pipe fittings

Plaster in vault only

Test Data.

Here are test data for sample that were collected from the Bridgetown Fire Hall on 22 June, 2016, and then analysed asbestos content testing by light microscopy method EPA 600/R-93/116.

Sample Label Description Friable Asbestos Content

Sample 1 Main bay area, Exterior wall brick mortar near bay door

no none

Sample 2 Main bay area, Grey brick parging cement

no none

Sample 3 Main bay area, Exterior wall brick mortar

no none

Sample 4 Main bay area, Ceiling in bay area, drywall joint filler

yes 5% chrysotile asbestos

Sample 5 Main bay area, New canteen area, interior wall drywall joint filler

yes none

Sample 6 Back area near kitchen, Blue seamless vinyl flooring

no none

Sample 7 Back area near kitchen, Acoustic ceiling tiles

yes none

Sample 8 Back area near kitchen, Ceiling above ceiling tiles, drywall joint filler

yes 5% chrysotile asbestos

Sample 9 Kitchen, Exterior wall drywall joint filler

yes none

Sample 10 Kitchen, Brown seamless flooring under blue seamless noted in Sample 6

no 75% chrysotile asbestos

Sample 11 Washroom, Brown and blue seamless flooring as in samples 6 and 10

no none in blue 75% chrysotile asbestos in brown

Page 49: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

49

Sample 12 Washroom, Interior wall drywall joint filler

yes none

Sample 13 Main bay area, Exterior wall black mortar

no none

Sample 14 Main bay area, Ceiling drywall joint filler

yes 5% chrysotile asbestos

Sample 15 Back area near vault, Interior wall drywall joint filler

yes none

Sample 16 Vault, plaster wall yes 1-2% chrysotile asbestos

Sample 17 Main bay area, brick mortar interior wall

no none

Sample 18 Furnace room, parging around old coal chute

no none

Sample 19 Brick mortar no none

Sample 20 Exterior, rear exterior brick mortar

no none

Sample 21 White/beige caulking around windows

no none

Sample 22 Side, brick mortar no none

Sample 23 White window caulking no none

Sample 24 White caulking around bay doors

no none

Sample 25 Front, brick mortar no none

Sample 26 Grey patch parging cement around brick holes

no none

Summary. Based upon these data, the following materials should be presumed to contain asbestos at this location.

This building has been renovated and both original and newer materials are present.

All original drywall joint filler contains asbestos, newer drywall filler does not. If the distinction between the two types is not clear, then all should be presumed to contain asbestos.

Original brown seamless flooring, at least some of which lies under blue seamless floor, contains asbestos.

Plaster in the vault contain asbestos.

Page 50: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

50

Sample Analysis Results and Summary, Cornwallis Park Wastewater Treatment Plant.

Building Description.

Concrete exterior walls

Metal window frames with caulking

Floors are bare concrete or concrete with floor tiles

Walls and ceilings are concrete, drywall and suspended ceiling tiles

Hot water furnace, no pipes insulated with fibreglass on straight sections and parging cement on fittings

Test Data.

Here are test data for sample that were collected from the Cornwallis Park Wastewater Treatment Plant on 28 June, 2016, and then analysed asbestos content testing by light microscopy method EPA 600/R-93/116.

Sample Label Description Friable Asbestos Content

Sample 1 Office/bathroom area, 12x12 white/grey inch floor tiles

no none

Sample 2 Office/bathroom area, ceiling tile 1

yes none

Sample 3 Office/bathroom area, ceiling tile 2

yes none

Sample 4 Office/bathroom area, black baseboard adhesive

no none

Sample 5 Office/bathroom area, concrete block mortar

no none

Sample 6 Office/bathroom area, concrete block mortar

no none

Sample 7 Lab/storage/entryway area, brownish with light brown streaks 12x12 floor tiles

no 5% chrysotile asbestos

Sample 8 Lab/storage/entryway area, brownish with thick brown streaks 12x12 floor tiles

no 2% chrysotile asbestos

Sample 9 Lab/storage/entryway area, ceiling titles with small lines

Yes none

Sample 10 Lab/storage/entryway area, ceiling tiles with thick lines

yes none

Sample 11 Lab/storage/entryway area, black tar on block wall

no 10% chrysotile asbestos

Sample 12 Lab/storage/entryway area, parging cement on pipe fitting

yes none

Sample 13 Chlorinator, concrete block mortar

no none

Page 51: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

51

Sample 14 Chlorinator, mortar on wall patch

no none

Sample 15 Hot water heater area/stairwell, parging cement on pipe fitting

yes none

Sample 16 Filter room, concrete patch on floor

no none

Sample 17 Filter room, parging cement on yellow pipe fitting

yes none

Sample 18 Filter room, Concrete block mortar

no none

Sample 19 Filter room, parging cement on green pipe fitting

yes none

Sample 20 Alum storage, parging cement on yellow pipe fitting

yes none

Sample 21 Alum storage, parging cement on green pipe fitting

yes none

Sample 22 Alum storage, block wall separating blower room

no none

Sample 23 Blower room, parging cement on green pipe fitting

yes none

Sample 24 Storage/workshop, drywall joint filler

yes none

Sample 25 Storage/workshop, drywall joint filler

yes none

Sample 26 Storage/workshop, drywall joint filler

yes none

Sample 27 Storage/workshop, brown adhesive on black baseboard

no none

Sample 28 Rinse room, parging cement on yellow pipe fitting

yes none

Sample 29 Rinse room, block mortar no none

Sample 30 Exterior, concrete wall mortar no none

Sample 31 Exterior, concrete wall mortar no none

Sample 32 Exterior, concrete wall mortar no none

Sample 33 Exterior, caulking around door frame

no 5% chrysotile asbestos

Summary. Based upon these data, the following materials should be presumed to contain asbestos at this location.

Both types of brown floor tiles in lab/storage/entrance area

Black tar on block wall in lab/storage/entrance area

Caulking around exterior door frame

Page 52: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

52

Sample Analysis Results and Summary, Cornwallis Park Water Treatment Plant.

Building Description.

Newly renovated with new addition on back

Walls and ceilings are concrete, drywall and suspended ceiling tiles

Pipes insulated with fibreglass and parging cement

Test Data.

Here are test data for sample that were collected from the Cornwallis Park Water Treatment Plant on 28 June, 2016, and then analysed asbestos content testing by light microscopy method EPA 600/R-93/116.

Sample Label Description Friable Asbestos Content

Sample 1 Lab/entryway/office, ceiling tiles

yes none

Sample 2 Lab/entryway/office, 12x12 blue/white floor tiles

no none

Sample 3 Lab/entryway/office, concrete block mortar

no none

Sample 4 Lab/entryway/office, elbow parging on pipe

yes none

Sample 5 Lab/entryway/office, baseboard adhesive

no none

Sample 6 Lab/entryway/office, drywall joint filler

yes none

Sample 7 Lab/entryway/office, grey caulking around window interior

no none

Sample 8 Alum storage, concrete block mortar

no none

Sample 9 Alum storage, elbow parging on pipe

yes none

Sample 10 Tank room, floor grout no none

Sample 11 Tank room, concrete block mortar

no none

Sample 12 Tank room, large diameter pipe elbow parging

Yes none

Sample 13 Tank room, small diameter pipe elbow parging

yes none

Sample 14 Tank room, concrete brick mortar

no none

Sample 15 Tank room, concrete brick mortar

no none

Sample 16 Chemical storage, block mortar no none

Sample 17 Chemical storage, small diameter pipe elbow parging

no none

Page 53: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

53

Sample 18 Locker room, drywall joint filler yes none

Sample 19 Chlorine room, drywall joint filler

yes none

Sample 20 Exterior, block mortar no none

Sample 21 Exterior, grey caulking on window sill,

no none

Sample 22 Exterior, grey caulking on block wall seam

no none

Sample 23 Exterior, block mortar no none

Sample 24 Exterior, block mortar no none

Summary. Based upon these data, the following materials should be presumed to contain asbestos at this location.

No asbestos containing materials were identified at this location.

Page 54: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

54

Sample Analysis Results and Summary, Margaretsville Water Treatment Plant.

Building Description.

Concrete exterior walls

Floors are bare concrete or concrete with seamless flooring

Walls and ceilings are concrete, plywood, plaster

Fibreglass insulation in ceiling

Test Data.

Here are test data for sample that we collected from the Margaretsville Water Treatment Plant on 24 June, 2016, and then analysed asbestos content testing by light microscopy method EPA 600/R-93/116.

Sample Label Description Friable Asbestos Content

Sample 1 Exterior, concrete block mortar, grey wall

no none

Sample 2 Exterior, caulking around side vent

no none

Sample 3 Exterior, concrete block mortar, rear side

no none

Sample 4 Exterior, roof, thin tarpaper lowest layer

no none

Sample 5 Exterior, roof, thick tarpaper, second layer

no none

Sample 6 Exterior, roof, asphalt shingles no none

Sample 7 Exterior, concrete block no none

Sample 8 Exterior, concrete foundation upper

no none

Sample 9 Exterior, concrete foundation lower

no none

Sample 10 Interior, upper level, wall block mortar

no none

Sample 11 Interior, upper level, plaster interior wall

yes none

Sample 12 Basement, parging cement around tap

no none

Sample 13 Lining undo exterior wall wood yes none

Sample 14 Side storage, parging cement no none

Sample 15 Water tower parging cement no none

Summary. Based upon these data, the following materials should be presumed to contain asbestos at this location.

No asbestos containing materials were identified at this location.

Page 55: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

55

Sample Analysis Results and Summary, Lawrencetown Administration Building.

Building Description.

Concrete walls

Floors are bare concrete or concrete with seamless flooring, floor tiles, small porcelain tiles and carpets. In many areas carpets cover other flooring.

Walls and ceilings are drywall

Hot water furnace, newly abated pipes, all fibreglass

Basement level recently completely renovated

Test Data.

Here are test data for sample that were collected from the Lawrencetown Administration Building on 25 June, 2016, and then analysed asbestos content testing by light microscopy method EPA 600/R-93/116.

Sample Label Description Friable Asbestos Content

Main Level

Sample 1 Server room, drywall joint filler interior wall

yes none

Sample 2 Server room, 9x9 inch grey floor tile

no 5% chrysotile asbestos

Sample 3 Manager Protective Services, 9x9 inch brown floor tiles

no 5% chrysotile asbestos

Sample 4 Manager Protective Services, drywall joint filler office partition wall

yes 5% chrysotile asbestos

Sample 5 Manager Protective Services, ceiling tiles

yes none

Sample 6 Kitchen, drywall joint filler interior wall

yes 5% chrysotile asbestos

Sample 7 Kitchen, 9x9 inch brown floor tiles

no 10% chrysotile asbestos

Sample 8 Staff room, 9x9 inch brown floor tiles

no 5% chrysotile asbestos

Sample 9 Staff room, drywall joint filler yes 5% chrysotile asbestos

Sample 10 Fire Inspector, drywall joint filler interior wall

yes none

Sample 11 Vacant 1, drywall joint filler interior wall

yes none

Sample 12 Vacant wall, caulking on block wall seam

no none

Sample 13 Director of Planning, drywall joint filler interior wall

no none

Sample 14 Building official, grey tiles no none

Sample 15 Building official, ceiling tiles yes none

Page 56: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

56

Sample 16 Open office space, concrete block mortar

no none

Sample 17 Washroom areas, 9x9 inch green floor tiles

no 15% chrysotile asbestos

Sample 18 Washroom areas, 9x9 inch brown floor tiles

no 5% chrysotile asbestos

Sample 19 Washroom areas, drywall joint filler

yes none

Sample 20 Lobby, drywall joint filler yes none

Sample 21 Law library, ceiling tiles yes none

Sample 22 Law library, 9x9 inch grey floor tiles

no 10% chrysotile asbestos

Sample 23 Law library, drywall joint filler interior wall

yes 5% chrysotile asbestos

Sample 24 Corridor, drywall joint filler yes 5% chrysotile asbestos

Sample 25 GIS, ceiling tiles yes none

Sample 26 GIS, drywall joint filler yes 5% chrysotile asbestos

Basement

Sample 27 Janitor closet, 9x9 grey inch floor tiles

no 15% chrysotile asbestos

Sample 28 Stairwell, concrete block no none

Sample 29 Hallway, 12x12 inch green floor tiles

no none

Sample 30 Kitchen, tile pattern seamless floor

no none

Sample 31 Kitchen, grey floor tiles no 5% chrysotile asbestos

Sample 32 Kitchen, drywall joint filler yes none

Sample 33 Furnace room office, brick mortar

no none

Sample 34 Open office area, textured ceiling tile

yes none

Sample 35 Open office area, drywall joint filler

yes none

Sample 36 Garage, white caulking no none

Exterior

Sample 37 White caulking around side entrance next to furnace room

no 5% chrysotile asbestos

Sample 38 Grey patch caulking near oil tank

no none

Sample 39 Brick mortar no none

Sample 40 Brick mortar no none

Sample 41 Parging coating on foundation no none

Sample 42 Brick mortar no none

Sample 43 Brick mortar no none

Page 57: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

57

Sample 44 Black tar above garage no none

Summary. Based upon these data, the following materials should be presumed to contain asbestos at this location.

All 9x9 inch floor tiles contain asbestos

All original drywall joint filler (tan coloured) contains asbestos

White caulking around the side entrance next to the furnace room contains asbestos

Page 58: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

58

Sample Analysis Results and Summary, Bridgetown Arena.

Building Description.

Metal clad exterior on concrete

Most room concrete block, some drywall and plywood

No insulated pipes, electric heat

Test Data.

Here are test data for sample that were collected from the Bridgetown Arena on 29 June, 2016, and then analysed asbestos content testing by light microscopy method EPA 600/R-93/116.

Sample Label Description Friable Asbestos Content

Sample 1 Entrance, concrete block mortar exterior wall

no none

Sample 2 Canteen, seamless flooring beige/blue

no none

Sample 3 Canteen, stove area, beige seamless flooring

no none

Sample 4 Canteen, 12x12 inch beige floor tiles

no none

Sample 5 Heritage room, concrete block mortar

no none

Sample 6 Room 2, washroom, concrete block mortar

no none

Sample 7 Men’s washroom, exterior concrete block mortar

no none

Sample 8 Hall from canteen, concrete block mortar

no none

Sample 9 Girl’s room concrete block mortar

no none

Sample 10 Zamboni room, concrete block mortar

no none

Sample 11 Officials’ room, concrete block mortar

no none

Sample 12 Viewing room, concrete block mortar

no none

Sample 13 Stairway to viewing room, drywall joint filler

yes none

Sample 14 Viewing room, wall drywall joint filler

yes none

Sample 15 Viewing room, ceiling drywall joint filler

yes none

Page 59: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

59

Sample 16 Upper washroom, wall drywall joint filler

yes none

Sample 17 Concrete foundation no none

Sample 18 Exterior red brick mortar no none

Sample 19 Exterior beige brick mortar no none

Sample 20 Exterior, Grey caulking, left side of building on metal

no 10% chrysotile asbestos

Sample 21 Exterior, Black tar caulking, left side of building on metal

no 5% chrysotile asbestos

Sample 22 Exterior, caulking on gutters no none

Summary. Based upon these data, the following materials should be presumed to contain asbestos at this location.

Exterior caulking on metal seams contains asbestos.

Page 60: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

60

Sample Analysis Results and Summary, Bridgetown Administration Building.

Building Description.

Hardwood flooring throughout except bathroom/kitchen and Room 208/209

Walls and ceilings are drywall and suspended ceiling tiles

Hot water furnace

Test Data.

Here are test data for samples that were collected from the Bridgetown Administration Building on 25 June, 2016, and then analysed asbestos content testing by light microscopy method EPA 600/R-93/116.

Sample Label Description Friable Asbestos Content

Main Level

Sample 1 Rear exit, 12x12 inch beige floor tiles

no none

Sample 2 Rear exit, green seamless flooring

no none

Sample 3 Entry by kitchen, tan drywall joint filler interior wall

yes 5% chrysotile asbestos

Sample 4 Interior wall by kitchen, plaster yes 1-2% chrysotile asbestos

Sample 5 Room 104 hallway, paper above wooden brace ceiling

no none

Sample 6 Side exit, interior wall plaster yes 1-2% chrysotile asbestos

Sample 7 Room 106, 12x12 inch green floor tiles

no none

Sample 8 Room 106, drywall joint filler exterior wall

yes none

Sample 9 Wheelchair exit hall, ceiling plaster

yes none

Sample 10 Room 107, drywall joint filler interior wall

yes none

Sample 11 Room 105, exterior wall plaster yes 1-2% chrysotile asbestos

Sample 12 Bathroom ceiling tiles yes none

Sample 13 Hardwood floor underlay paper no none

Sample 14 Room 101, ceiling tiles yes none

Sample 15 Room 101, exterior wall plaster yes none

Sample 16 Room 101, ceiling plaster yes none

Sample 17 Room 107, ceiling drywall joint filler

yes none

Upper Level

Sample 18 Hardwood floor underlay paper no none

Sample 19 Room 206, exterior wall plaster yes 1-2% chrysotile asbestos

Sample 20 Room 209, ceiling plaster yes 1-2% chrysotile asbestos

Page 61: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

61

Sample 21 Room 207 closet, ceiling plaster yes 1-2% chrysotile asbestos

Sample 22 Room 205, interior wall plaster yes 1-2% chrysotile asbestos

Sample 23 Room 202, exterior wall drywall joint filler

yes none

Sample 24 Room 209, incandescent lamp heat shield

yes 75% chrysotile asbestos

Sample 25 Room 201 wall plaster yes 1-2% chrysotile asbestos

Basement

Sample 26 Main area, Acoustic tile adhesive

no none

Sample 27 Furnace room, drywall joint filler exterior wall

yes 5% chrysotile asbestos

Sample 28 Storage room, drywall joint filler exterior wall

yes none

Sample 29 Concrete mortar around windows

no none

Sample 30 Concrete foundation no none

Sample 31 Furnace room, parging cement on exterior wall

yes 5% chrysotile asbestos

Sample 32 Furnace room, brick mortar no none

Exterior

Sample 33 Brick mortar, rear side no none

Sample 34 Brick mortar, front side no none

Sample 35 Brick mortar, front left of entrance

no none

Sample 36 Lower roof, asphalt shingle no none

Sample 37 Black/grey caulking, lower roof no none

Summary. Based upon these data, the following materials should be presumed to contain asbestos at this location.

All plaster

All original drywall joint filler

All incandescent lamp heat shields

Parging cement in furnace room

Page 62: ASBESTOS SURVEYS AND MANAGEMENT PLAN Municipality of … · Responsibilities under the Asbestos Management Program Responsibilities Assigned to Management The following tasks and/or

62

Sample Analysis Results and Summary, Other Buildings.

Test Data.

Here are test data for sample(s) that we collected from the several other buildings on 20 June, 2016, and then analysed asbestos content testing by light microscopy method EPA 600/R-93/116. These buildings were either new, newly renovated or were of a construction type that use of asbestos was deemed to be very unlikely other than in the few applications that were tested and reported here. Accordingly, general surveys were not conducted and only the materials noted below were tested.

Sample Label Description Friable Asbestos Content

Sample 1 Bridgetown wastewater treatment plant, plaster walls in chlorine room

no none

Sample 2 Bridgetown Jubilee Park, brown floor tiles

no none