22
INSTALLATION GUIDE Pentangle

Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

  • Upload
    letram

  • View
    217

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

INSTALLATION GUIDE

Pentangle

Page 2: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

1

MG135L4244×2

A06S0046×2

IRF6003-1x 4

MGCOVPLTx 4

MGCAPx 4

MGVC45Installation tool

×1MGVC19A

×2MGVC20A

×4

MGVC21L MGVC21R×1 ×1

×8 ×1MG8x51PLUG

x8MG6x30PLUG

x1

MGVC08AL MGVC08AR×1 ×1

MGST5X65 MGST4X30BH

Note:Extra components have been supplied to make this product suitable for left orright hand configuration and therefore some parts will be surplus to requirements.

MGCAP×8

Page 3: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

2

MGVC27×1

8S1300511×1

A06S0046x1

Ø6&8

x1

SP0GMHPRCH

Page 4: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

3

No. QTY Part No. Part No.

1

2

3

4

5

8

1

2

1

4

No. QTY

7

8

9 1

1

6

Part No.No. QTY

1

10

11

12

13

14

15

16

17

18

19

201

1

1

1

21

1

8

IRF6003-1

MG8x51PLUG

MGVC21L/R

GMPENTCSEAL1

MGVC08AL/R

GMGPH900

MGVC44LSET/RSET

Bottom track1

MGVC30A

MGST4X30BH

MGVC08AR/L

MGVC21R/L

MG6x30PLUG

MGST5X65

1 MGVC27

GMGPN

GMGPH900

MG135L4244

MGVCWPSET

12

3

4

5

6

7

9 1110

12

13

14

15

161820 1719

8

SPOGMHPRCH1

Page 5: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

4

Step 2

64mm

Mark 64 mm in from the edge of the tray.

100% level!

IMPORTANT!Whether fitting on a tray or on a tiled

Wetroom the tray or floor must be 100% level!

Page 6: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

5

Note the position of the labels on the wall profile.Make sure Label 'T' is to the topand 'B' is to the bottom. Line up the outside edge of the profile with the mark andplumb vertical. Mark the wall through the pre-drilled holes.

NOTE: Do not fix wall profile.

Step 3

B B

B B B

T

B

T

Page 7: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

Insert wall plugsDrill holes for hinge

8mm

Remove profile and drill holes for wall brackets with diameter 8mm masonery bit andinsert wall plugs.Ensure wall plugs are flush with tile.Repeat for each wall fixed panel.

MG8x51PLUG

Step 4

Insert wall plugs

Step 5Position brackets 8mm inwards from edge of tray Mark wall through slot. Drill6mm diameter hole centre of slot and fix bracket both sides.

8mm Wall Bracket

5A 5B

6mm

Drill 6mm diameter hole

6mm

5C 5D

Keep high side ofbracket facing outside

6

Add a dab of siliconeto the back of the wallbracket and fix with4x30 screws.

Page 8: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

Step 6

7

6A.Loosen both nuts enough to allow the nuts to slide into the grove in theside panel track.(Note:Do not remove nuts from bolt ). Ensure joint closesfully and tighten, silicone inside of joint.6B.Add a bead of silicone to both sides of the track, then insert the glassholding profiles.

Front Front

Front

6A

6B

Front

135°

Page 9: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

Step 8

8B

MGVC08AL

8

Slide caps into position.

MGVC08AR

8A

Insert completed track into brackets . Fit brackets to end of track.Step 7

Page 10: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

9

Step 9Before assembling the brackets make sure it is orientated the correct way.Measure hole centres from top and bottom to determine correct orientation ofpanel.Note the differences between the hinged fixed panel (has notch cuts for hinge)and the closing side fixed panel (no notch cuts).

Step 10

Push on wall profile completley ensuring end is flush with the top of theglass panel.

Top250mm

Bottom275mm

THIS WAY UP THIS WAY UP

Hinged fixed panel Closing sidefixed panel

Top250mm

Bottom275mm

Page 11: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

10

Step 11Fix wall brackets loosely ensuring fixing holes are to the inside of glass panel.

INSIDE

IRF6003-1

Step 12Take fixed wall panel and insert into bottom track keeping outside edge of glasspanel tight to end of angled profile in bottom track.

Make sure glass is tight toangled profile.

Page 12: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

11

Step 13

INSIDE

Screw 5×65

Fix wall brackets to the pre drilled holes.Do not fully tighten,leaveenough slack for adjustment.Secure top bracket first.Note: Hold glass panel and gently tap profile back tight against wallusing MDF tool provided, working from bottom to top.

Step 14Check panel for level and fully tighten screws to wall.Do not fully tighten bracket toglass, leave enough slack for adjustment.

MGVC45

INSIDE

INSIDE

Page 13: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

12

Step 15Fit hinges ensuring that the part of the hinge which has a cut out is fitted to the door.

Fixed Panel

MovingPanel

135°

Step 16The side of the hinge that has the fixing bolts must be to the inside of the movingpanel. Hinge should be fitted in centre of cutout for maximum adjustment later.Fully tighten bolts.Step 17Step 18Step 19 The moving panel is fitted from inside the enclosure so make sure allhinge parts and tools are placed inside before the door is lifted into place.

Tip:Use MDF tool for squaring hingesRemove back plates from hinges on fixed panel side.

Hinge plate with bevellededge goes on the fixed panel

Page 14: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

13

Step 20Check door opening at bottom and make sure that the distance at the top is thesame.

Step 21 Fit the support rail to fixed panels.

21A Loosen both grub screws.

21B Fit the support rail to fixed panels.

Page 15: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

14

21C Step in the clamp equal distance from the edge of the glass on both sides.

21D Check gap between both panels is equal top and bottom, then tighten bothclamps.

Page 16: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

15

Step 22 Place locating aids and spacers on threshold, one eachside of opening.Fit closing seal to edge of inline panel.Make sure to keep fin to the inside.

Tip! Hold both locating aids inposition with masking tape.

locating aids

Step 23The door should be lifted onto the locating aids standing inside the enclosure. Makesure you have all the fixings and tools required inside the enclosure.

Page 17: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

16

Step 24Loosely fix back plate to hinges ensuring washers are in position and hinges arelevel.

Step 25Ensure gap between both glass panels is equal top and bottom,and that the gapbetween the seal and the edge of the moving panel is approx 5mm,then fully tightenhinge bolts.

gap is equal

gap is equal

25A 25B

5mm

Page 18: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

17

To remove door positioning aids open door outwards.When positioning aidshave been removed check gap beneath door is even.

Step 26

26A

26B

Step 27Left and right hand seal kits are provided, determine handing and use appropriateseal kit. Left hand model shown below.Push on longest seal between hinges ontoback edge of moving panel. Take shortest seal and fit to top keeping notch tohinge.Repeat with longer bottom seal.

Page 19: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

18

Fit bottom door seal keeping longest fin to inside.Notch fin where it meets the closing seal to ensuredoor closes fully .

INSIDE

28B

INSIDE

28A

28C

INSIDE

Step 28

Step 29 Fit the handle to the door.

MGVC27

29

Page 20: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

19

Step 30If after fitting doors and fixed panels and you still need adjustment to align doorsetc ,you can achieve this by loosening the screws fixing the plate/hinge to the walland the bolts clamping the bracket/hinge to the glass.Adjust the panels until the desired fit is achieved.Fully tighten all fixings.Note: If not further adjustment is needed make sure all fixings have been tightenedsecurely.

INSIDE

Fitting cover caps.Step 31

INSIDE

Fitting cover caps. Peel off protective strip to adhesive tape to back of cap andfirmly press in position .Tip:We recommend that you place a dab of silicone to the back of the covercaps at each end of the tape.

fit wall bracketcaps

Page 21: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

20

Step 34

Only seal the outside of the enclosure(red line). Do not seal the inside.Seal vertically along the wall, along the outside edge of the bottom profile and anyjoins in the profile, including where the bottom track meets the end brackets

Sealing your enclosure.Make sure all surfaces are thoroughly cleaned and dry before applying sealant.

24 h.

Page 22: Arysto instruction GM100.200.300.400 Pentangle · PDF file1 MG135L4244 ×2 A06S0046 ×2 IRF6003-1 x 4 MGCOVPLT x 4 MGCAP x 4 MGVC45 Installation tool ×1 MGVC19A ×2 MGVC20A ×4 MGVC21L

Merlyn ShoweringUnit 8, Purcellsinch Industrial Park,Dublin Road, Kilkenny, Ireland.Tel: 00353 56 779 1555Fax: 00353 56 779 1576www.merlynshowering.com

MERLYN