Arterial Street Rehabilitation for Riverside Drive24th Street to 35th Street
Public Informational Meeting
July 22, 2014
Introductions
• Doug Helt, P.E. City of Tulsa
Transportation Lead
• Brooke Caviness, P.E.City of Tulsa
Senior Engineer / Project Manager
• Tim Morgan, P.E.HNTB Corporation
Project Manager
Project Location Map
Overview
• Roadway Improvements
• Stormwater Improvements
• Water Main Improvements
• Sanitary Sewer Improvements
• Anticipated Project Schedule
• Questions
Roadway Improvements
Roadway Geometry Improved = Safer Drive
Roadway Improvements
• 35 mph Speed Limit
• Median Separation Through Park
• Lane Widths Increased
• New Lighting (LED)
Roadway Improvements
Stormwater Improvements
• Travis Park RCB System
• Swan Creek RCB System
• Crow Creek Bridge Replaced
• Riverside Drive Storm System Upgraded
Stormwater Improvements
Pre-Project Storm Conveyance System
Stormwater Improvements
Post-Project Storm Conveyance System
Water Main Improvements
• Riverside Drive 12” Water Main
• Gathering Place 8” Water Main
• Creating Looped Water Main Systems
• Improved Function and Flow in Neighborhoods
Water Main Improvements
Pre Project Water Main Network
Water Main Improvements
Post Project Water Main Network
Sanitary Sewer Improvements
• Existing Systems are 60-100 years old
• Reconstruction of Major Sanitary Mains
• High Strength Fiberglass for New Systems
• No Impact to Users
Sanitary Sewer Improvements
Pre-Project Sanitary Sewer Network
Sanitary Sewer Improvements
Sanitary Sewer Replacements
Anticipated Project Schedule
• Fall 2014 - Construction Contract Award
• Winter 2014/2015 - Construction Begins
• Spring 2015 - Riverside Drive Closure
• 2016 - Riverside Drive Pavement Construction
• 2017 - Project Completed
Questions?