LEAD TIME & INVENTORY REDUCTIONIN APPAREL SUPPLY CHAIN
Team Synergy
Abhishek KumarMangala MRashmi RaoJisna P Gopi
ABOUT THE COMPANY
• Manufacturing arm of Madura Garments having brands like Louis Philippe , Van Heusen , Allen Solly and Peter England
• It comprises of 4 factories located in Bangalore , with a total employee strength close to 3000.
• The product range offered is men’s and women’s formal –Shirts , Trousers and Suits with annual volumes of 43.6 Lakh garments.
Aditya Birla Group
AB Nuvo
Madura Garments
Madura Clothing
Vision: “To be a global benchmark for apparel industry in manufacturing and innovation providing competitive advantage to stake holders”
Note:-To understand the apparel supply chain in brief which will help to understand the project better
APPAREL SUPPLY CHAIN
NEED FOR PROJECTNo well defined and scientific replenishment model and stocking policyStagnating sales growth year-on-year basisHigh finished goods inventoryIncrease in discounted sales year on year leading to profit erosion
0100200300400500600
APR
20
08
MA
Y 2
00
8
JUN
20
08
JUL
20
08
AU
G 2
00
8
SEP
20
08
OC
T 2
00
8
NO
V 2
00
8
DEC
20
08
JAN
20
09
FEB 2
00
9
MA
R 2
00
9
APR
20
09
MA
Y 2
00
9
JUN
20
09
JUL
20
09
AU
G 2
00
9
SEP
20
09
OC
T 2
00
9
NO
V 2
00
9
DEC
20
09
JAN
20
10
FEB 2
01
0
MA
R 2
01
0Qty
(in
pcs
)
LP Core FG Sales : FY08-10
0
2000
4000
6000
8000
APR
20
08
MA
Y 2
00
8
JUN
20
08
JUL
20
08
AU
G 2
00
8SE
P 2
00
8
OC
T 2
00
8N
OV
20
08
DEC
20
08
JAN
20
09
FEB 2
00
9
MA
R 2
00
9A
PR 2
00
9
MA
Y 2
00
9JU
N 2
00
9
JUL
20
09
AU
G 2
00
9
SEP
20
09
OC
T 2
00
9
NO
V 2
00
9
DEC
20
09
JAN
20
10
FEB 2
01
0M
AR
20
10Q
ty (in
pcs
)
LP Core FG Inventory : FY08-10
FG inventory in the range of 5000pcs while Retail sales in
400pcs per month, hence carrying 10 months more
inventory
Due to such high FG inventory level, cash flow for business is blocked and discounted sales
increasing to improve it
PROJECT CHARTER
Business Case : Total Lead time ofApparel supply chain was 130 daysand there has been noreplenishment leading to high out-of-stock rate. The inventory levelwas very high carrying 9 monthsinventory.
This threw up tremendous potentialfor improving the lead time andinventory reduction
Scope: Fabric procurement toRetail Sales
Relation with business case , approach , scope , CTQ’s and benefits were finalized in the charter
SIPOC
Fabric procurement
from mill
Fabric procurement
from mill
Fabric storage at
factory
Fabric storage at
factory
Garment mfg at factory
Garment mfg at factory
FG storage at
WH
FG storage at
WH
Retail store
replenish
Retail store
replenishRetail salesRetail sales
Core
CORE REPLENISHMENT SYSTEM
Factory
Warehouse
Retail Store
Consumer
CRS ( Pull Strategy)
Fabric Mills
Core products would be managed using continuous replenishment at FG as well as fabric stages …
CORE REPLENISHMENT SYSTEM
Core products would be managed using continuous replenishment at FG as well as fabric stages …
Orders are Aggregated Order
Garment Production
PO Preparation
Sends the order
WO is generated
WO
Supplies Fabric PO
FabricOrderDetails
FabricStatus
Garments
Pending Order File
Warehouse Factory
Purchase
Supplier
Customer
FG Stocks,WIP
Levels
Fabric StocksIn-Transit, Fabric
RoP Levels
FabricAvb.
yes
no
Fulfill
CTQ TREE DIAGRAM
Reduction ofLead time andinventory inApparel Supplychain for CoreReplenishmentSystem
Garment Manufacturing
REWORK%
RECUTTING%
MANUFACTURING LEAD TIME
Finished Goods INVENTORY (DAYS)
Fabric LEAD TIME (DAYS)
Retail RETAIL SALES (PCS)
Critical To Quality Characteristics (CTQ)
Operational Definition Measure
Current Status
CTQ Specification
Defect Definition
KANO Status
1. FABRIC PROCUREMENT LEAD TIME (DAYS)
FABRIC LEAD TIME FROM PO CREATION TO DELIVERY AT FACORY STORES
105 Days <15 Days > 15 Days MUST BE
2. MANUFACTURING LEAD TIME (DAYS)
TIME FROM WO CREATION TO DELIERY AT FACTORY WAREHOUSE
18 Days <12 Days > 12 Days MUST BE
3. FINISHED GOODS INVENTORY IN WH (DAYS)
FINISHED GOODS INVENTORY IN DAYS
271Days < 60 Days > 60 Days MUST BE
4. RETAIL SALES (PCS) RETAIL SALES IN PIECES
400 Pcs >500 Pcs < 500 PCS MUST BE
5. RECUTTING (%) PANELSRECUTTING
4% <3% >3% LOWER THE BETTER
BATCH RECUTTING 3% <1% >1%
6. REWORK (%) END OF LINE 7.83% < 7% >7% LOWER THE BETTER
FQC 1.73% <5% >5%
The project objective (Y) is addressed by focusing on the Must Be” CTQ’s (y’s) identified as shown above
CTQ TABLE
MILESTONE
GANTT CHART
Jun’10 Jul’10 Aug’10 Sep’10 Oct’10 Nov’10 Dec’10 Jan’11
DEFINEProject CharterSIPOCCTQ Tree Diagram
MEASUREAs-is CTQ Status
APPROACH/ ANALYSISCause & Effect DiagramFMEA
DEPLOYMENT/ IMPROVENVA Identification & stratificationSetting up section wise WIP NormsSingle piece clearance on daily basisDeveloping system to monitor online
ASSESSMENT & REVIEW/ CONTROLImplementing control mechanismSustenance (Review & Assessment)Replication
CTQ 1: FABRIC LEAD TIME REDUCTION AT FABRIC MILL
The Strategic supplier relationship management is required to
Ensure the strategic partnership with fabric millsEnsure reduced fabric lead time by Vendor managed inventoryEnsure improved service levels for fabric lead time and qualityEnsure building base stock to service peak season demand
ANALYZE
An internal brainstorming session, helped to narrow down the Focus area for
Deployment in spoke from “12 Spoke solution design”
with strong core
IMPROVE
• SATISFACTIONSURVEY• HALF YEARLY FEEDBACK REPORT
Supplier Segmentation
(Supplier wise strategy )
Vendor Connect
(IT Enablement)
Supplier Forums
(Relationship Mapping)
Supplier Feedback
CONTROL After establishing Strategic supplier
relationship, critical vendors identified based on following parameters for rationalization: Geographic Location Delivery, Quality, Cost
VMI has been adopted for critical vendors by providing them Quarterly projections to deliver stock on-demand
After implementing VMI, due to reduction in Fabric lead time and improved service levels, base stock was built to service
ESCALATION MATRIXLEAD TIME
DELAYVENDOR/ INCHARGE
PURCHASE MANAGER
SOURCING HEAD
BRANDHEAD
14 Days10 Days7 Days2 Days
Safety Stock
Reorder Point
CTQ 2 : GMT MFG LEAD TIME REDUCTION AT FACTORY
The reduction in Garment manufacturing lead time is done by
Ensure timely delivery of finished goods at warehouse against SLAIdentifying potential causes for high manufacturing lead timeIdentifying root causes by using FMEA Implementing improvement solutions for those root causesImplementing controls to ensure that implemented solutions sustain
DIAGNOSING POTENTIAL ROOT CAUSES
An internal brainstorming session, helped to narrow down from 52 x’s to more
likely root causes for further analysis
Single pc clearanceFurther, FMEA was carried out to help in prioritizing the potential root causes
FMEA FOR PRIORITIZING POTENTIAL ROOT CAUSES
Cause
Probability of
Occurrence
Severity Of Conseque
nce
Difficulty of
Detection
(A) Probability
of Occurrenc
e
(B) Consequen
ce(C)
Detection
Risk Priority
No. (RPN)
(High / Medium / Low)Rating (1-6-9) 1 = lowest, 6 =
medium, 9 = highest A x B x C
Lack of work aid Low Medium Medium 1 6 6 36Mismatching of material Medium Medium Low 6 6 1 36Fabric Defect & Shade variation Medium High Low 6 9 1 54Improper method due to lack of adherance to SOP Low High Medium 1 9 6 54Planning procedure leading to improperrelease of work orders Medium High Medium 6 9 6 324High sectional WIP due to lack of adherance to WIP Norms High High Medium 9 9 6 486Delay in single piece clearance due to lack ofsupervision High High High 9 9 9 729
2 main causes having highest RPNs were selected to work on
High RPN root causes 486 and 729 respectively are identified and
action taken to reduce it
IMPROVEMENT Delay in single piece clearance due to lack of supervision
Tracking format implemented for tracking down the single piece in the section
Operators and supervisors were educated to clear single piece
Daily review for deviations
Results Statistical Validation
SINGLE PIECE CLEARANCE TRACKING
2-Variance test was done and since p-value (0.498) is greater than 0.05, there is no significant change in the variation
2-sample t-test was done and since the p-value (0.002) is less than 0.05, there is significant reduction in single piece clearance time.
IMPROVEMENT
High Net WIP due to lack of adherance to WIP norms
Section wise norms were fixed based on the daily productionof section
Implementation of pull system inWIP based WO release
Daily review for deviations
2-Variance test was done and since p-value (0.587) is greater than 0.05, there is no significant change in the variation
2-sample t-test was done and since the p-value (0.006) is less than 0.05, there is significant reduction in Net WIP (pcs)
Results Statistical Validation
FMEA FOR RESULT VALIDATIONFailure Mode Effect Analysis (FMEA) for Validating the solutions.
Cause Probability
Severity Of
Consequence
Difficulty of
Detection
(A) Poten
tial
(B) Consequenc
e
(C) Detect
ion
Risk Priority
No. (RPN)
Implemented Preventive Action
(A1) Probability
(B1) Severi
ty
(C1) Detection
Residual No.
(High / Medium / Low) Rating (1-6-9) 1 = lowest, 6 = medium, 9 =
highest
A x B x C
Rating (1-6-9) 1 = lowest, 6 = medium, 9
= highest
A1 x B1 x C1
Lack of work aid
Low Medium High 1 6 9 54 1 6 9 54
Mismatching of material
Medium Medium Low 6 6 1 36 6 6 1 36
Fabric Defect & Shade variation
Medium High Low 6 9 1 54 6 9 1 54
Improper method due to lack of adherance to SOP
Low High Medium 1 9 6 54 1 9 6 54
Planning procedure leading to improper release of work orders
Medium High Medium 6 9 6 324 Implementation of pull system, WIP based work
order release system
6 1 6 36
High sectionalWIP due to lack of adherance to WIP Norms
High High Medium 9 9 6 486 Establishing section wise WIP norms and ensuring
adherance to it
1 9 6 54
Delay in single piece clearance due to lack ofsupervision
High High High 9 9 9 729 Establishing single piece clearance tracking sheet
and ensuring adherance to it
1 9 6 54
With the implemented solution RPN of root causes came down from 486 and 729 to
54 respectively which validates the
effectiveness of solution
Sheet to record details of all alterations of same product,
different batches
Single piece clearance of monitoring on a day to day basisRegular training to operators on clearing single pieces on top-priorityOn-site board for supervisors to keep tracking single pieces and Section wise WIPHolding dispatch till 100% single pc clearanceWeekly reviews by Production Manager for ensuring adherance to Section wise WIP norm and single pc clearance
CONTROL
On-site board for production monitoring , style description
and daily wo clearance
Standard operating procedures in all sections to
ensure the process adherence
BENEFITS : MFG LEAD TIME REDUCTION
Two-Sample T-Test and CI: After Tpt time, Before Tpt timeTwo-sample T for After vs Before
N Mean StDev SE MeanAfter 4 12.50 2.65 1.3Before 9 29.44 6.37 2.1Difference = mu (After) - mu (Before)Estimate for difference: -16.944495% upper bound for difference: -12.4122T-Test of difference = 0 (vs <): T-Value = -6.78 P-Value = 0.000 DF = 10
2-Variance test was done and since p-value is greater than 0.05, there is no significant change in the variation
2-sample t-test was done and since the p-value is less than 0.05, there is significant reduction in throughput time.
Reduction in Suits average manufacturing lead time from 18 days to 12 days (0.4 times improvement)
CTQ 3: FG INVENTORY REDUCTION AT WAREHOUSE
The Warehouse replenishment system for finished goods to warehouse required to
Ensure work orders are created to fill the inventory gap at warehouseEnsure that replenishment is aligned to sales as per pull modelEnsure that inventory carrying cost of finished goods is reduced
Warehouse replenishment approach to provide the brands with a competitive advantage of Replenishment Model, which characterizes
Planning Horizon of fortnight with Weekly Wave Model of Work Ordering and Delivery cycle
IMPROVEFactory
Warehouse
Wo Creation
Pre-production activity (1 Days)
11 Days against SLA
Wo Release
Forecasting/ WH Stock Gap against Norm
Every Monday
Production Plan for filling Gap Fabrics &
Trims in-stockEvery
Tuesday
1 Day Every Tuesday
Entoma Warehouse
(Retail)2 DaysRetail
Store1 Day
IMPROVE (Contd) Work ordering cycle : Weekly (on every Tuesday),Delivery cycle : 12 working days from day of work order creation for blazers/
SuitsMOQ per style code : 10 pcs (based on cutting and marker laying efficiency)Fabric Norm: 1 month of salesWarehouse Norm: 1 month of sales
Assessment Mechanism (Daily)OTIFLead Time
Review Mechanism (Quarterly)WH InventoryFabric Inventory
Service level Agreement0
50
100
150
200
250
300
May Jun Jul Aug Sep Oct
Jun
+ Ju
l Req
uire
men
tBui
ldin
g
Safe
ty S
tock
Bui
ldin
g
MF&L INVENTORY REPLENISHMENT MODEL (MONTH ON MONTH) - AW
GAP REPLENISHMENT
CONTROL
Based on the Scenarios, work order were created to
replenish the gap in warehouse inventory
Daily Status of Work orders were sent to brands for
ensuring the transparency in work order execution
ESCALATION MATRIXLEAD TIME
DELAYSUPERVISOR PRODUCTION
MANAGERFACTORY
MANAGERHEAD OF
MFG4 Days3 Days2 Days1 Day
For process, Smart Transactional Excel Macros were developed for: Monitoring Retail Sales Monitoring Retail Inventory Monitoring WH Inventory Monitoring Gap in WH inventory
against Norm due to retail sales Work order need to be created
based on gaps on weekly basis
To improve the transparency in work order execution as control sheet, Daily status is sent to all stakeholders
Escalation matrix established for handling lead time delays
BENEFITS : FG INVENTORY REDUCTION
Two-Sample T-Test and CI: After Inventory, Before Inventory Two-sample T for After Inventory vs Before Inventory
SEN Mean StDev Mean
After Inventory 7 72.4 28.4 11Before Inventory 5 208.6 68.8 31Difference = mu (After Inventory) - mu (Before Inventory)Estimate for difference: -136.17195% upper bound for difference: -66.697T-Test of difference = 0 (vs <): T-Value = -4.18 P-Value = 0.007 DF = 4
2-Variance test was done and since p-value is greater than 0.05, there is no significant change in the variation
2-sample t-test was done and since the p-value is less than 0.05, there is significant reduction in inventory
Reduction in Suits inventory from 9 months to 2 months (4.5 times improvement)
CTQ 4: SALES IMPROVEMENT AT RETAIL STORE
The Retail replenishment system for finished goods to retail stores is required to
Ensure timely delivery of finished goods at retail store against SLAEnsure STO are created to fill the inventory gap at retail storesEnsure that replenishment is aligned to sales as per pull modelEnsure that sale of finished goods is improved
Retail replenishment approach would ensure that local customer preferences as well as brand’s targeted sales is maintained...
IMPROVEProvide information on store traffic, demand patterns, gaps in merchandise
Provide with weekly control reports to monitor inventory and store look
IMPROVE
Retail management system -Micro strategy and Business warehouse was implemented in year 2009 to provide transparency across the 68 retail stores of LP Store Sales Store Inventory In-transit inventory
To replenish retail stock in northern and western region, couriers are used to reduce replenishment time within 3 days
All India One Stock (AIOS) system deployed for cross-docking, one retail store to another retail store
Micro strategy software to monitor store sales,
inventory
Business warehouse software to monitor in-transit inventory and AIOS system
CONTROL
ESCALATION MATRIXOUT OF STOCK
VENDOR/ INCHARGE
RETAIL MERCHANT
RETAIL HEAD
BRANDHEAD
4 Days3 Days2 Days1 Day
For process, Out-of-stock and Transit time is monitored and reviewed on daily basis based on: Retail Sales Retail Inventory Retail inventory norm Monitoring gap in Retail inventory
against Norm Stock transfer order need to be
created based on gaps
Escalation matrix established for handling transit time delays
Store Transit Time (Days) Before After
% Improvement
APK 2.56 1.38 46.09%TN/ KERALA 2.45 1.28 47.76%
WEST 6.28 2.96 52.87%NORTH 7.43 3.21 56.80%
AVERAGE 4.68 2.21 52.83%
(IN PCS)
Month NormActual Stock
Out-of-stock
Sales Loss %
Jul 1367 932 435 32%Aug 1367 830 537 39%Sep 1367 1067 300 22%Oct 2734 2568 166 6%Nov 2734 2876 0 0%Dec 2734 2754 0 0%
BENEFITS : SALES IMPROVEMENT
Two-Sample T-Test and CI: Before Sale, After Sale Two-sample T for Before Sale vs After Sale
SEN Mean StDev Mean
Before Sale 12 174.7 43.0 12After Sale 3 717.7 38.7 22Difference = mu (Before Sale) - mu (After Sale)Estimate for difference: -543.00095% upper bound for difference: -482.904T-Test of difference = 0 (vs <): T-Value = -21.26 P-Value = 0.000 DF = 3
2-Variance test was done and since p-value is greater than 0.05, there is no significant change in the variation
2-sample t-test was done and since the p-value is less than 0.05, there is significant improvement in sales
Increase in Suits retail sales from avg 400 pcs sales to avg 785pcs in peak season (2 times improvement)
OVERALL BENEFIT
FINANCIAL BENEFIT FOR SUITS & BLAZER IN RETAIL CHANNELBUDGETED SALES PROJECTION (JAN’11-DEC’11) – 3375 pcs (Rs. 1.68 crores/ Annum)
DUE TO RETAIL REPLENISHMENT, 40% REDUCTION IN BUDGETED SALES LOSSNOV’10- JAN’11 ACTUAL SALES IMPROVEMENT – 800 PCS, ACTUAL EXTRA REVENUE – Rs20 Lacs
EXPECTED SALES IMPROVEMENT DUE TO RETAIL REPLENISHMENT – 1350 pcs/ AnnumEXPECTED PROFIT DUE TO SALES IMPROVEMENT– Rs33.6 Lacs/ Annum (Profit@Rs 2500/pc)
NET LEAD TIME REDUCTION(FABRIC + MANUFACTURING + RETAIL REPLENISHMENT) LEAD TIMEBEFORE, 105 + 18 + 7 (Max in case of Delhi) – 130 DaysAFTER, 15+12+3 (Max in case of Delhi) – 30 DaysIMPROVEMENT IN LEAD TIME – 4 TIMES
FUTURE ROADMAPAutomating the mechanism for forecasting Channel wise sales trend by identifying the best tool among the several tools by Q1
Automating the process of setting the inventory norm across the supply chain quarterly by Q1
Automating the transaction, which triggers the stock transfer order, work order for style codes and purchase order for fabric codes by Q2
Increasing the Scope of this project to different products and channels
BRAND CHANNEL PRODUCT EXP TIMELP RETAIL S&BLP TRADE S&B Q1LP RETAIL SHIRT Q2LP TRADE SHIRT Q2LP RETAIL TROUSER Q1LP TRADE TROUSER Q1VH RETAIL S&B Q1VH TRADE S&B Q1VH RETAIL SHIRT Q1VH TRADE SHIRT Q1VH RETAIL TROUSER Q2VH TRADE TROUSER Q2