Arnold 2000

Embed Size (px)

Citation preview

  • 7/30/2019 Arnold 2000

    1/27

    The economic consequences of regulatoryaccounting in the nuclear power industry:

    market reaction to plant abandonments

    Patricia J. Arnold 1, Rita Hartung Cheng *

    School of Business Administration, University of Wisconsin Milwaukee, P.O. Box 742, Milwaukee,

    WI 53201, USA

    Abstract

    Between 1972 and 1990, US electric utility companies cancelled orders for 117 nu-

    clear power plants (NEI, 1996, pp. 16). The regulatory accounting methods adopted by

    utility rate setting commissions determined whether utilities could recover the losses oncancelled plants through higher rates. In eect, the choice of accounting methods de-

    termined how billions of dollars invested in cancelled nuclear plants was allocated be-

    tween utility stockholders, ratepayers, and taxpayers (DOE/EIA, 1983, pp. ixx). Our

    paper examines the economic consequences to stockholders of capital project aban-

    donments in a regulated industry. The results show that while regulatory treatment of

    abandonment costs was generally favorable to investors, the market reacted negatively

    to nuclear project abandonment announcements indicating that investors did not expect

    to fully recoup abandonment losses. Two stage regression is used to investigate the

    determinants of the markets reaction to project cancellations. 2000 Elsevier Science

    Ltd. All rights reserved.

    1. Introduction

    The United States (US) nuclear power industry ran into great diculties in

    the late 1970s. Electric utilities ordered 231 nuclear plants before the end of

    1974, while only 15 construction orders were placed after 1974 (Campbell, 1988,

    Journal of Accounting and Public Policy 19 (2000) 161187

    *

    Corresponding author. Tel.: +1-414-229-4238; fax: +1-414-229-6957.E-mail addresses: [email protected] (P.J. Arnold), [email protected] (R.H. Cheng).

    1 Tel.: +1-414-229-3837; fax: +1-414-229-6957.

    0278-4254/00/$ - see front matter 2000 Elsevier Science Ltd. All rights reserved.

    PII: S 0 2 7 8 - 4 2 5 4 ( 0 0 ) 0 0 0 0 9 - 0

  • 7/30/2019 Arnold 2000

    2/27

    p. 3). No nuclear plants have been ordered since 1978 (Campbell, 1988, p. 3).

    Between 1972 and 1990, electric utilities in the US cancelled construction orders

    on 117 planned nuclear power plants (NEI, 1996, pp. 16), abandoning plans to

    construct approximately half of the countrys projected nuclear capacity (DOE/

    EIA, 1983, pp. ixx). From an accounting perspective, the diculties of the

    nuclear power industry is of interest because regulatory accounting policy was

    instrumental in determining who bore the costs of abandoned nuclear power

    projects. Accounting methods adopted by state utility rate setting commissions

    determined how billions of dollars (DOE/EIA, 1983, pp. ixx) invested in

    cancelled nuclear projects was allocated between nancial stakeholders,

    including utility stockholders, ratepayers and federal taxpayers. 2

    Our study examines the economic consequences of regulatory accountingpolicy with respect to the shareholders upon announcement of nuclear project

    cancellations. We extend the prior research by Chen et al. (1987). Chen et al.

    (1987, pp. 290291) found no signicant market reaction to nuclear project

    abandonment announcements in the period 19741982 consistent with the

    theory that regulated utilities expected to be compensated for abandonment

    losses in rate adjustments. A partitioning of the sample into two periods,

    however, found signicant negative excess returns associated with the an-

    nouncement of nuclear power project abandonments in the period (19741978)

    prior to the Three Mile Island (TMI) nuclear accident in 1979, while signicant

    positive excess returns were found in the post-TMI period (19791982) (Chenet al., 1987, pp. 291292). Chen et al. (1987, p. 293294) attribute this result to

    changing investor expectations concerning the regulatory treatment of aban-

    donment costs. Specically, Chen et al. (1987, pp. 293294) suggest that after

    1979 regulatory rulings allowing abandonment losses to be passed to, or at least

    shared by ratepayers, made ``abandonments more palatable to investors,'' and

    in conjunction with increased perceptions of risk resulting from the TMI acci-

    dent led investors to react positively to abandonment announcements. Chen

    et al. (1987) leaves several empirical questions unanswered regarding the in-

    teractions between regulatory accounting policies and the economic conse-

    quences to stockholders of nuclear project abandonments. To what extent didutility regulators compensate investors for abandonment losses by rate adjust-

    ments? Did investors expect to be fully compensated for abandonment losses?

    How did investors expectations about the regulatory treatment of abandon-

    ment losses aect the markets reaction to abandonment announcements?

    Our study addresses these questions by describing the regulatory accounting

    environment, analyzing how public service commissions treated the cost of

    cancelled nuclear projects for rate setting purposes, and examining how al-

    ternative regulatory accounting rulings allocated losses on abandoned nuclear

    2 The US Department of Energy (DOE/EIA, 1983, p. x) estimated that $10 billion was invested in

    the 100 nuclear power plants cancelled between 1972 and 1982 alone.

    162 P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187

  • 7/30/2019 Arnold 2000

    3/27

    projects and altered the distribution of cash ows among ratepayers, taxpayers

    and utility owners. Our review of regulatory commission decisions shows that

    although regulatory treatment of abandonment costs was generally favorable

    to investors, shareholders could not expect to be fully compensated for

    abandonment losses through rate adjustments. Accordingly, our study hy-

    pothesizes that investors will react negatively to abandonment announcements.

    This hypothesis is supported by empirical tests that indicate the stock market

    reacted negatively to nuclear project cancellation announcements over the

    period 19721987. Supplemental tests indicate that the negative market reac-

    tion is associated with investment size. Tests of the relationship between

    abandonment announcements and state-specic prior regulatory rulings yield

    mixed results.

    2. The regulatory environment

    Accounting choices are said to have economic consequences if the changes in

    the rules used to calculate accounting numbers alter the distribution of rms

    cash ows or the wealth of parties that use accounting numbers for contracting

    and decision making (Holthausen and Leftwich, 1983, p. 7). The cash ow

    consequences of accounting policy choices, in turn, explain interest group

    preferences for particular accounting policies and the intrusion of interest grouppolitics in the accounting standard setting process (Ze, 1978, pp. 5657). By

    calling attention to the conicts of economic interest inherent in the choice of

    accounting methods, the literature on the economic consequences of accounting

    has helped to dispel the idea that accounting choices are neutral or disinterested.

    A substantial body of economic consequences research (Ball and Smith,

    1992; Burgstahler and Dichev, 1997; DeAngelo et al., 1994; Hand and Skantz,

    1997; Healy, 1985, Muller, 1999; Soo, 1999) has focused on explaining dis-

    cretionary accruals and accounting policy choices adopted by rms. The lit-

    erature acknowledges that government regulation (Holthausen and Leftwich,

    1983, pp. 8586) and political costs (Watts and Zimmerman, 1978, pp. 115116) have cash ow consequences, and empirical studies (Han and Wang, 1998,

    p. 116; Key, 1997, p. 334) have found a relationship between rms choice of

    accounting policies and political costs. Recent accounting research on reg-

    ulated industries, has shown that the threat of regulatory costs aects rm

    value in the oil industry (Patten and Nance, 1998, pp. 426427) and that bank

    managers discretionary accruals are inuenced by regulatory changes (Kim

    and Kross, 1998, p. 97). With respect to the electric utilities industry, Johnson

    et al. (1998, p. 285) found that moves toward deregulation have had negative

    eects on utilities stock prices, particularly for utilities with heavy investments

    in nuclear power. DSouza (1998, p. 387) found that managers of rate-regulated

    rms that face greater uncertainties about further rate recoveries have greater

    P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187 163

  • 7/30/2019 Arnold 2000

    4/27

    incentives to use discretionary choices that intensify the impact of expense-

    increasing accounting changes. The economic consequences research, however,

    has focused primarily on managements discretionary policy choices or the

    impact of regulatory changes on stock prices. With the exception of tax re-

    search (Callihan, 1994), relatively little prior empirical research 3 has examined

    the economic consequences of accounting policies used by state regulators.

    The nuclear power industry provides a context for examining the cash ow

    consequences of regulatory accounting decisions made by public agencies, in

    this case by state electric utility rate setting commissions. Electricity rates in the

    US are regulated by public service commissions established within each of the

    fty states (Campbell, 1988, p. 94). The accounting methods adopted by public

    service commissions have direct cash ow consequences for utility investorssince regulatory accounting is the basis for determining the rates electric utilities

    can charge customers. Rates are set to cover allowable expenses and enable

    investors to earn a specied return on assets (Campbell, 1988, pp. 197198). For

    rate setting purposes, both allowable expenses and assets (i.e., the rate base) are

    measured on an accrual accounting basis with public service commissions pre-

    scribing allowable accounting methodologies (Otis, 1981, pp. 161163). Because

    utility rates are set by state commissions, the nuclear power industry represents a

    sector of the US economy where distributions of economic wealth depend ex-

    tensively on state actions and institutions, as well as market forces.

    The history of nuclear power in the US has been highly volatile as the eco-nomic, technical and political feasibility of nuclear power generation was called

    into question in the 1970s (Campbell, 1988, pp. 310). A sharp decrease in de-

    mand in the mid-1970s coincided with rising concerns over nuclear safety dra-

    matized by the nuclear accident at TMI in 1979 (Campbell, 1988, pp. 5, 8).

    Increasingly stringent government safety standards and an active anti-nuclear

    movement combined to delay plant construction and increase costs (Campbell,

    1988, pp. 7391). By the end of the decade, utility bond ratings plummeted,

    capital market nancing for nuclear projects dissipated and the industry ran into

    great diculties (Campbell, 1988, pp. 92109). Against this background, public

    service commissions at the state level grappled with the decision of whether andto what extent the costs of abandoned nuclear projects should be passed on to

    utility ratepayers or absorbed by utility owners (DOE/EIA, 1983, pp. 3357).

    The outcomes to those decisions could not be easily predicted for three reasons.

    First, the institutional structure of utility rate setting in the US is fragmented

    and decentralized. Each of the fty states has its own rate setting commission

    with each commission facing a slightly dierent local constituency and array of

    organized interests including industry and consumer lobbies (Campbell, 1988,

    3

    For examples of prior research on regulatory accounting choices and the importance of the stateand regulatory accounting practices within capitalist economies see Arnold (1991), Burchell et al.

    (1980), Cooper and Sherer (1984) and Jarrell (1979).

    164 P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187

  • 7/30/2019 Arnold 2000

    5/27

    pp. 7391). To the extent that regulators act as self-interested utility maxi-

    mizers (Stigler, 1971, p. 11; Peltzman, 1976, p. 214) seeking re-appointment, re-

    election, and/or future employment in a regulated industry, the incentives

    facing commissioners vary according to state-specic organizational and en-

    vironmental variables such as whether commissions are appointed or elected,

    term length, state politics, anti-nuclear activism, and media attention.

    Second, the economics and politics of nuclear power, itself, was changing so

    that regulatory commissions faced a substantially dierent socio-economic

    climate in the late 1970s and 1980s. Anti-nuclear activism in the 1980s was

    increasingly directed at state public service commissions and economic issues

    (Campbell, 1988, pp. 7391). After 1976 anti-nuclear groups began pressuring

    state public service commissions not to approve new projects until the federalgovernment built a nuclear waste depository arguing that project costs could

    not be determined until the waste issue was resolved (Campbell, 1988. p. 86).

    As Campbell (1988, p. 76) indicates, a 1971 federal court ruling preventing

    state and local governments from superseding the rules and regulations of

    federal nuclear regulatory agencies prompted opponents of nuclear power to

    rephrase their arguments in economic, rather than safety terms, and to present

    them before state public service commissions. The intrusion of nuclear oppo-

    sition politics into the rate setting process further politicized the regulatory

    environment (Campbell, 1988, pp. 7391).

    Finally, the technical complexity of the rate setting process allows for de-viations between stated policies and practical consequences. Although rate

    setting commissions often adopted the policy objective of allocating costs eq-

    uitably between ratepayers, taxpayers, and utility owners, slight variations in

    elected accounting methods could skew the distributions of cash ows in favor

    of one group or another. Moreover, a ruling on nuclear abandonment costs

    that was favorable or unfavorable to a particular interest group could be oset

    by seemingly unrelated decisions such as an adjustment in the allowable rate of

    return. In sum, utility rate setting constitutes an arena where public policy is

    dicult to decipher because it is implemented through complex accounting

    technicalities that can obscure the cash ow consequences of rate rulings.Because of the complexity of government decision processes, the contra-

    dictory nature of the state, and the political volatility of the nuclear power

    industry, hypotheses about the economic consequences of regulatory ac-

    counting policy cannot be easily formulated on the basis of state theories

    alone. 4 Research in government accounting (Cheng, 1994) has shown that, as

    4 Contending state theories include economic theories of regulation (Stigler, 1971; Peltzman,

    1976), neo-Marxist state theories (Carnoy, 1984; Wright, 1978; Wood, 1995), public choice theories

    (Mueller, 1989), institutional theories (Hirst and Thompson, 1996; Skopol, 1985; March and Olsen,1989; Powell and DiMaggio, 1991; Zysman, 1983), and post-structural theories (Escobar, 1995;

    Miller and Rose, 1990).

    P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187 165

  • 7/30/2019 Arnold 2000

    6/27

    with other public policy decisions, public sector accounting choices are the

    outcome of complex political processes involving interactions between indi-

    vidual actors (e.g., elected ocials, agency administrators and sta, media,

    credit markets, taxpayers, and interest groups) constrained by socioeconomic

    conditions, technical capacity, and political and bureaucratic structures. As the

    following section demonstrates, hypotheses regarding the consequences of state

    interventions in the nuclear power industry require a concrete historical analysis

    of the regulatory rulings and the technical accounting choices that determined

    the cash ow consequences of nuclear plant abandonment decisions.

    3. The cash ow consequences of regulatory accounting policy

    To determine how public service commissions treated the cost of abandoned

    nuclear plants for rate setting purposes, we analyzed data on the major public

    utility commission and court rulings made between 1976 and 1987. 5 The re-

    sults are summarized in Table 1.

    Table 1 classies the accounting methods specied in 116 nal regulatory

    commission and appellate court rulings issued between 1976 and 1987 into

    three categories: no recovery; full recovery, and partial recovery. Similar cat-

    egories were used in prior research (DOE/EIA, 1983, p. 39) to classify regu-

    latory outcomes into three types of recovery methods. Each of the threerecovery methods results in a dierent allocation of costs 6 between stock-

    holders, ratepayers, and taxpayers. The frequency and cash ow eect of the

    three types of recovery methods are described below.

    5 Data on regulatory commission rulings on the treatment of cancelled plants was obtained from

    a Regulatory Research Associates, Inc. (RRA) report entitled Utility Composite Cancelled Plant

    Treatments (1988). This report was purchased for research purposes and is cited with permission

    from the Regulatory Research Associates, Inc. The report provides a tabular listing detailing

    regulatory decisions on treatment of cancelled nuclear plants issued by state commissions and/or

    state courts through 1987. While the listing attempts to be all-inclusive with respect to the state

    regulatory treatment of cancelled plant recovery, the report notes that some occurrences may have

    been omitted, particularly where plants were cancelled in the planning phase and only minor

    amounts of sunk costs were involved (RRA, 1988, p. 1).6 The major components of costs of abandoned nuclear projects, as dened for rate setting

    purposes, are capitalized Construction Work in Progress (CWIP) and Allowance for Funds Used

    During Construction (AFUDC). Other components of cost include contract cancellation penalties

    and site shutdown costs, less salvage value. CWIP includes cumulative cash expenditures to the date

    of cancellation (e.g., land acquisition; site improvements; construction labor, materials and

    equipment; engineering and environmental studies; and, costs to acquire licenses and permits).AFUDC is the carrying cost of capital on funds used during the construction period (DOE/EIA,

    1983, pp. 3338).

    166 P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187

  • 7/30/2019 Arnold 2000

    7/27

    3.1. No recovery

    In 25 cases (21.6%), regulatory commissions or the courts ruled that none of

    the costs of abandoned nuclear projects could be passed to ratepayers. When

    recovery is not allowed, losses on abandoned nuclear projects are shared be-

    tween utility stockholders and taxpayers. Taxpayers share part of the costs

    because utilities can write-o the cost of their investment in abandoned projectsas an extraordinary loss for income tax purposes in the year of the cancellation,

    thereby shifting part of their loss to taxpayers. Assuming a 50% tax rate, no

    recovery rulings allocate half the abandonment costs to utility owners and half

    to federal taxpayers (DOE/EIA, 1983, p. 40).

    3.2. Full recovery

    In 21 cases (18.1%), regulatory commissions allowed full recovery. Under

    the full recovery method, utility stockholders recover the full cost of prudent

    investments in cancelled nuclear projects (DOE/EIA, 1983, pp. 3940). Costsare amortized over a period of years, resulting in rate increases that gradually

    return the full amount of capital invested in cancelled projects to utility owners.

    In addition, rates are set to allow utilities to earn a return on the unamortized

    balance of their investment (i.e., the unamortized investment is included in the

    rate base). Utility owners, thus, recover their original capital investment, and

    earn a return on invested capital for the time it is committed (DOE/EIA, 1983,

    pp. 3940).

    Taxpayers benet from the full recovery method because the initial write-

    o of abandonment costs is recovered over the amortization period via taxes

    paid on the incremental revenues resulting from rate increases imposed to

    recover abandonment costs (DOE/EIA, 1983, pp. 3940). Since income taxes

    Table 1

    Regulatory accounting for the cost of canceled nuclear power plants in 116 Final Commission and

    Court Rulings (19761987)a

    Recovery of investment Return on balance

    Yes No

    Yes Full Recovery Partial Recovery

    21 Cases (18.1%) 70 Cases (60.3%)

    No No Recovery

    25 Cases (21.6%)

    a Full Recovery allows utility owners to recover original capital invested and earn a return on the

    unamortized balance of their investment. Partial Recovery allows utilities a return of all or part of

    the capital invested, but no return on the unamortized balance of their investment. No Recovery

    allows none of the costs of abandoned projects to be recovered by rate increases. ( Source: Data onregulatory commission ruling on the treatment of cancelled plants was obtained from RRA (1988).

    See footnote 5.)

    P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187 167

  • 7/30/2019 Arnold 2000

    8/27

    are part of a utilitys service cost, they are built into rates and ultimately paid

    by ratepayers (DOE/EIA, 1983, pp. 3940). Taxpayers do, however, share

    part of the cost of abandonment due to the cash ow consequences of de-

    ferred tax revenues. Since tax revenues are lost in the year of the abandon-

    ment and only gradually recouped over the amortization period, taxpayers

    eectively pay the capital cost resulting from deferred revenues (DOE/EIA,

    1983, p. 41). In eect, the full recovery method allocates cost between rate-

    payers and taxpayers while utility stockholders bear no costs (DOE/EIA,

    1983, pp. 3940).

    3.3. Partial recovery

    Most state regulatory commissions allowed partial recovery of abandon-

    ment costs. The Federal Energy Regulatory Commission (FERC), the federal

    agency that regulates inter-state wholesale electricity rates also adopted a

    partial recovery policy in 1979. 7 Under partial recovery investors receive a

    return of, but no return on their investment. Although there are several variants

    of partial recovery methodologies (DOE/EIA, 1983, pp. 4041), partial re-

    covery, as it is used here, includes any method that returns all or part of the

    costs invested in abandoned nuclear projects to investors through periodic

    amortization charges which increase electricity rates, but does not allow in-vestors to earn a return on the unamortized balance (DOE/EIA, 1983, p. xiv).

    In other words, all prudently incurred costs invested in abandoned nuclear

    projects were returned to investors through periodic amortization charges

    which increased electricity rates (DOE/EIA, 1983, p. xiv). But, the unamortized

    investment in cancelled plants was excluded from the rate base (DOE/EIA,

    1983, p. xiv). Consequently, investors did not earn a return on their investment

    during the amortization period (DOE/EIA, 1983, p. xiv). The partial recovery

    method was adopted in 70 (60.3%) of the regulatory commission rulings and

    court cases between 1976 and 1987 (RRA, 1988, pp. 25). Amortization pe-

    riods ranged from 2 to 20 years with 10 years being most common (RRA, 1988,pp. 25).

    The Energy Information Administration conducted a simulation study for

    the Department of Energy (DOE/EIA, 1983, pp. xvxvii) to determine how the

    partial recovery methodology distributed costs between ratepayers, utility

    shareholders and taxpayers. The results of the DOE/EIA study comparing the

    7 The method described above was established by the FERC in Opinion No. 49 (8 FERC

    61,054) and remained in eect until 1988. On January 15, 1988 the FERC issued Opinion No. 295(42 FERC 61,016) which granted utility owners full recovery ofand on 50% of their investment in

    cancelled nuclear plants, and no recovery on the other 50% (42 FERC 61,016 at p. 61,068).

    168 P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187

  • 7/30/2019 Arnold 2000

    9/27

    present value of cash ows available to ratepayers, stockholders and taxpayers

    under the partial recovery method are summarized in Table 2. As Table 2shows, the distribution of cash ows to each of the three stakeholders is af-

    fected by the length of the amortization period. The DOE/EIA (1983, p. xvi)

    simulations reported that the partial recovery method, with an amortization

    period of 10 years, allocated 30% of the costs to ratepayers; 28% of the costs to

    utility owners; and 42% of the costs to federal taxpayers. The longer the am-

    ortization period, the greater the costs borne by utility investors who earned no

    return on the unamortized balance of their investment during the amortization

    period. For example, as Table 2 shows, the designation of a 5 versus a 20 year

    amortization period could double stockholders share of abandonment losses

    (from 19% to 38%).In addition to amortization periods, cash ows were also aected by pru-

    dence determinations (Teisberg, 1988, p. 9). Under the full recovery and partial

    recovery methods, investors were allowed to recover only the costs of prudent

    investments (DOE/EIA, 1983, p. 39). If a regulatory commission determined

    that a utility acted imprudently in making its nuclear investment decisions, the

    utility was not allowed to amortize the cost of its investment. Imprudence

    determinations resulted in partial denials of recovery (Teisberg, 1988, pp. 11

    12). Commissions sometimes ruled that the original investment decision was

    prudent, but that utilities had continued investing in the nuclear plants beyond

    the point when the prudent decision would have been to abandon the project

    (DOE/EIA, 1983, p. 39). Recovery was denied for some portion of the

    Table 2

    Cost distribution (% Share of costs borne by ratepayers, stockholders and taxpayers) for amorti-

    zation periods under the partial recovery method (full recovery of sunk costs; no return onbalance)a

    Amortization period (years)

    5 10 20

    Ratepayers 49% 30% 6%

    Stockholders 19 28 38

    Taxpayers 32 42 56

    100% 100% 100%

    a Source: Taken from DOE/EIA (1983, pp. xvi). The allocation of abandonment costs among the

    three payer groups was estimated by the Energy Information Administration, the statistical and

    analytical agency within the US Deparment of Energy, for a hypothetical nuclear plant cancellation.

    The percentages reported above indicate the relative distribution of costs under the most common

    partial recovery method where all costs invested in a cancelled plant are amortized over 5, 10 and 20

    year periods, but no return is earned on the unamoritized balance. The hypothetical plant was as-

    sumed to be cancelled in mid-1983 and the present values of the incrmental cash ows imposed on

    each payer group were calculated. The relative allocation of costs reported above assume a discount

    rate of 2 percentage points higher than the yield oered by US Treasury bonds that mature in the

    years in which the cash ows are received (DOE/EIA, 1983, pp. 5456 and pp. 87111).

    P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187 169

  • 7/30/2019 Arnold 2000

    10/27

    investment in 13 of the 21 full recovery rulings, and 26 of the 70 partial re-

    covery rulings reported in Table 1 (RRA, 1988, pp. 25).

    Although variations in accounting methods, amortization periods and

    partial cost denials could alter the distributions of cash ows among investors,

    taxpayers and ratepayers, overall the regulatory treatment of abandonment

    costs was favorable to utility owners. Assuming a 50% tax rate, stockholders

    never bore more than half of the cost of prudent investments in abandoned

    nuclear projects even in the worst case of a no recovery ruling. Under the most

    common recovery method, the partial recovery method with an amortization

    period of 10 years, investors bore less than a third of the losses on cancelled

    nuclear plants.

    In recognition of the fact that the partial recovery method disproportion-ately beneted stockholders, the FERC eventually changed its recovery policy

    in January of 1988 to a more equitable method (42 FERC 61,016 at

    p. 61,068). The new FERC policy allows utility owners full recovery of 50% of

    their investment in cancelled nuclear plants, and no recovery on the other 50%

    (42 FERC 61,016 at p. 61,068). In making the change the FERC rearmed

    its earlier policy objective of equitably balancing the interests of shareholders

    and ratepayers, but stated that in its implementation ``through tax benets,

    CWIP (Construction Work in Process), and accelerated capital recovery'', the

    original FERC partial recovery method had favored investors rather than

    producing an equal sharing of costs between stockholders and ratepayers (42FERC 61,016 at p. 61,081).

    Although the regulatory accounting treatment of nuclear plant abandon-

    ment costs was generally favorable to investors as opposed to other stake-

    holders, the above analysis suggests that stockholders would prefer completion

    to abandonment. If a planned nuclear project was completed, rates established

    once the plant was operative would provide investors with full recovery, i.e.,

    both a return on and a return of invested capital. In the case of abandonment,

    our data shows that state regulatory commissions issued full recovery rulings in

    only 18.1% of the cases (Table 1). Moreover, benets of full recovery rulings

    were frequently oset by imprudence ndings that disallowed recovery of aportion of the investment (Teisberg, 1988, p. 9). Despite considerable vari-

    ability in the amount of the losses allocated to stockholders by rate setting

    commissions, an analysis of the rate regulations and regulatory rulings on

    treatment of abandonment losses indicates investors could expect to bear some

    share of abandonment costs.

    4. Stock market reaction to abandonment announcements

    Since investors could expect to bear at least some portion of the costs

    of cancelled projects, they will prefer project completion to abandonment.

    170 P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187

  • 7/30/2019 Arnold 2000

    11/27

    Consequently, we hypothesize that the market will react negatively to

    announcements of nuclear project abandonment decisions. Our paper employs

    a standard event-study methodology to test this hypothesis. We extend the

    work of Chen et al. (1987) by employing a larger sample size than Chen et al.

    (1987) to examine the stock market reaction to nuclear power plant cancella-

    tion announcements. Our sample was obtained by extending the time period of

    the study through 1987 and by including observations of the stock returns of

    partial owners in cases where a cancelled nuclear plant was jointly owned by

    more than one utility.

    4.1. Sample selection

    Over the history of the nuclear power industry from 1972 (the year of the

    rst nuclear project cancellation) through 1990, construction plans have been

    cancelled for 117 nuclear reactors (NEI, 1996, pp. 16). In many cases a de-

    cision to abandon a nuclear project involved the cancellation of two or more

    reactors, and eight cancelled reactors were government owned. (NEI, 1996, pp.

    16). Several of the cancelled plants were partially owned by two or more

    utilities (RRA, 1988, pp. 25).

    Our sample consists of rms that announced nuclear plant abandonments in

    the period 19721987 for which (1) an announcement date can be identiedthrough The Wall Street Journal, (2) daily return data for the investor-owned

    utilities are available on the Center for Research in Security Prices (CRSP) data

    base, and (3) no other signicant events concerning the utility are evident from

    a search of The Wall Street Journal in the period surrounding the announce-

    ment date. The nal sample includes 107 observations of rms who were full or

    partial owners of abandoned nuclear projects. 8

    To assess the stock market reaction to nuclear project abandonment an-

    nouncements, an event-study methodology was employed to consider abnor-

    mal performance over the event period relative to a model-generated normal

    return using 200 days of return observations for each utility security, beginning250 days prior to the announcement date. The announcement date is dened as

    the day on which the announcement of the nuclear project abandonment ap-

    peared in The Wall Street Journal. Abnormal returns (ARs) were calculated as

    follows:

    ARit Rit ai biRmtY

    8 A listing of the utilities, cancelled plants and abandonment dates included in the sample is

    available from the authors on request.

    P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187 171

  • 7/30/2019 Arnold 2000

    12/27

    where Rit is the actual return for rm ion day t and ai biRmt is the predictedreturn from the market model. 9 To control for information leakage or late

    arrival of information to the market, a cumulative abnormal return (CARin) is

    computed for each sample utility during each of four periods (n) around the

    announcement by summing estimated ARs over four announcements periods

    (capturing 2, 4, 13, and 26 days):

    CARin

    ARitX

    Finally, cross-sectional average ARs for all utilities in the sample are also

    calculated for each day. The estimated average abnormal return for Nrms on

    day t, ARNt, is the simple average of the estimated AR itS, calculated by sum-

    ming ARit across the N rms and dividing this sum by N.

    4.2. Results

    Tables 3 and 4 present the cross-utility average residuals (abnormal returns)

    from the market model for each day in the 26-day announcement period: 10

    days prior to the abandonment announcement to 15 days after the an-

    nouncement, with the announcement date dened as 0. Consistent with our

    hypothesis, the results presented in Table 3 show that announcements of nu-

    clear abandonment decisions are associated with signicant negative ARs.

    Negative ARs are found both before the TMI Accident (19721978) and afterTMI (19801987).

    To compare the results with Chen et al. (1987), Table 4 shows the results of

    partitioning the post-TMI sample into two time periods: (1) the years imme-

    diately following TMI (19801981), and the subsequent period (19821987).

    The results are consistent with Chen et al. (1987, pp. 290291) in that we nd

    some evidence of a positive market reaction on day t 0 in the period im-mediately following TMI (19801981). After 1981, however, the market reac-

    tion to abandonment announcements was strongly negative. As Chen et al.

    (1987, pp. 293294) suggest the TMI nuclear accident may have initially

    9 The CRSP value-weighted market index return was used for Rmt. The parameters ai and bi are

    estimated by ordinary-least-squares regression using the 200 two-day return pairs (RitYRmt) over the

    interval from 250 to 51 trading days before the project abandonment announcement. ARit (the

    forecast error) provides an estimate of utility i's abnormal stock return over the tth two-day

    interval. The market model was run with and without making the ScholesWilliams (Scholes and

    Williams, 1977, pp. 315316) adjustment and the results were not signicantly dierent. Use of a

    100 day estimation period also yielded similar results. This is consistent with Brown and Warner

    (1985, pp. 1619) who show that straightforward ordinary least squares procedures for estimatingthe market model and standard parametric tests are as powerful as more elaborate tests in

    determining abnormal returns.

    172 P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187

  • 7/30/2019 Arnold 2000

    13/27

    aected the market's reaction to abandonment announcements by increasing

    investors' awareness of the risks of nuclear power, including the risk that

    regulators would not allow utilities to recoup clean up costs by rate increases.

    However, the eect was short lived. Over the long term, investors reacted

    negatively to abandonment announcements in both the pre- and post-TMI

    periods (see Table 3).

    The results of our expanded sample are not consistent with the Chen et al.

    (1987, p. 291) nding that the market viewed abandonments of nuclear pro-

    jects favorably after 1979. Nor, are they consistent with McConnell and

    Table 3

    Average abnormal returns (ARNt) around the abandonment announcement datea

    Day Total sample (19721987) Before TMI (19721978) After TMI (19791987)

    n 107 n 37 n 70

    ARNt t-Statistic ARNt t-Statistic ARNt t-Statistic

    )10 )0.00040 )1.02 0.10237 0.06 )0.00114 )1.30

    )9 0.00137 0.73 0.25877 1.09 0.00072 0.10

    )8 0.00230 1.56 0.32566 1.48 0.00180 0.82

    )7 )0.00144 )1.62 )0.07120 )1.19 )0.00182 )1.11

    )6 0.00151 0.73 0.48949 1.24 )0.00028 )0.02

    )5 0.00057 )0.19 0.13118 )0.02 0.00018 )0.22

    )4 )0.00004 )0.20 0.24382 0.44 )0.00135 )0.57

    )

    3 0.00220)

    1.21)

    0.11537)

    0.32)

    0.00275)

    1.24)2 )0.00062 )0.31 )0.18634 )0.95 0.00004 0.31

    )1 )0.00062 )0.94 0.21485 0.69 )0.00208 )1.65

    0 )0.00778 )5.39 )0.64467 )2.16 )0.00848 )4.99

    1 )0.00268 )2.39 )0.24193 )0.94 )0.00282 )2.23

    2 )0.00418 )4.28 0.14523 0.17 )0.00716 )5.34

    3 )0.00093 )1.14 0.11319 0.55 )0.00202 )1.79

    4 0.00262 2.03 )0.04931 )0.19 0.00427 2.62

    5 0.00027 0.48 0.28989 1.44 )0.00111 )0.46

    6 )0.00031 )0.68 0.10551 0.30 )0.00103 )1.05

    7 0.00030 0.97 0.07064 0.43 0.00008 0.87

    8 0.00114 1.27 0.00878 0.11 0.00170 1.47

    9 0.00244 1.47 0.30454 0.81 0.00213 1.2010 0.00122 0.85 0.40273 1.16 )0.00026 0.19

    11 0.00216 0.97 0.08582 )0.02 0.00285 1.20

    12 )0.00254 )2.24 0.06546 )0.27 )0.00423 )2.53

    13 )0.00128 )1.77 )0.09018 )0.72 )0.00147 )1.64

    14 )0.00113 )0.70 )0.27965 )1.33 )0.00025 0.11

    15 )0.00153 )1.20 0.26125 1.04 )0.00371 )2.22

    a ARNt is the simple average of the estimated individual (i) utility's abnormal returns, ARit, for N

    rms on day t.* Signicant at 0.10 in a two-tailed test.** Signicant at 0.05 in a two-tailed test.*** Signicant at 0.01 in a two-tailed test.

    P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187 173

  • 7/30/2019 Arnold 2000

    14/27

    Muscarella's (1985, p. 399) nding that stockholders of public utilities and

    industrial rms react dierently to decreases in planned capital expenditures.

    McConnell and Muscarella (1985, p. 416) found that decreases in planned

    capital expenditures by public utilities, unlike industrial rms, are not ac-

    companied by signicant negative excess returns. Our results however, are

    consistent with results of studies (Bowen et al., 1993, p. 106; Fuller et al., 1990,

    pp. 128131) which examine utility stock price behavior over time and con-

    clude that investors appear to believe that they will not be fully compensatedfor losses to utilities engaged in providing nuclear energy.

    Table 4

    Average abnormal returns (ARNt) around abandonment announcement date partitioned post-TMI

    samplea

    Day After TMI (19801981) After TMI (19821987)

    n 34 n 36

    ARNt t-Statistic ARNt t-Statistic

    )10 0.00028 )0.22 )0.00249 )1.59

    )9 0.00157 0.36 )0.00008 )0.21

    )8 0.00105 0.49 0.00250 0.67

    )7 )0.00231 )0.83 )0.00136 )0.74

    )6 )0.00107 )0.70 0.00046 0.66

    )5 0.00068 )0.10 )0.00029 )0.21

    )

    4 0.00006 0.19)

    0.00269)

    0.98)3 )0.00159 )0.29 )0.00384 )1.44

    )2 )0.00030 0.52 0.00037 )0.07

    )1 0.00135 0.36 )0.00532 )2.66

    0 0.00383 2.18 )0.02011 )9.08

    1 0.00180 0.11 )0.00719 )3.22

    2 )0.00124 )0.92 )0.01275 )6.55

    3 0.00014 )0.55 )0.00407 )1.97

    4 )0.00006 )0.06 0.00835 3.70

    5 )0.00342 )1.43 0.00107 0.74

    6 )0.00028 )0.34 )0.00173 )1.13

    7 0.00032 0.88 )0.00014 0.36

    8 0.00134 1.32 0.00204 0.789 0.00233 0.87 0.00193 0.84

    10 )0.00062 )0.08 0.00008 0.34

    11 0.00263 1.28 0.00306 0.43

    12 )0.00551 )1.81 )0.00302 )1.76

    13 0.00180 0.04 )0.00457 )2.32

    14 0.00160 )0.44 )0.00200 )0.27

    15 )0.00251 )0.97 )0.00485 )2.15

    a ARNt is the simple average of the estimated individual (i) utility's abnormal returns, ARit, for N

    rms on day t.* Signicant at 0.10 in a two-tailed test.** Signicant at 0.05 in a two-tailed test.*** Signicant at 0.01 in a two-tailed test.

    174 P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187

  • 7/30/2019 Arnold 2000

    15/27

    5. Determinants of the market reaction

    Additional tests using two-stage regression methods were performed to

    identify the determinants the abnormal negative returns found in our study.

    The objective of the tests is to determine whether stock market reactions to

    nuclear plant cancellation announcements are associated with either (1) the size

    of the investment, and/or (2) prior state-specic regulatory decisions.

    5.1. Model 1: investment costs

    The cost of building nuclear power plants escalated dramatically over time,

    increasing by 500900% between 1970 and 1983 (Campbell, 1988, p. 4), as aresult of design changes, construction delays, and stricter safety regulatory

    standards (Campbell, 1988, p. 7). The amounts invested in cancelled nuclear

    projects increased accordingly. Prior to 1980, most cancelled plants were in

    early stages of planning and construction with investments of less than $50

    million (DOE/EIA, 1983, p. 36). After 1980, most abandonments involved

    investments in excess of $50 million (DOE/EIA, 1983, p. 36).

    The rst regression model tests for an association between market returns

    and the costs invested in cancelled nuclear projects. The dependent variable is

    the estimated utility-specic cumulative abnormal return (CARin). In mea-

    suring the CARin values, four alternative window lengths (n) surrounding theannouncement date t 0 are employed. The event windows are: (1) a two-daywindow (t1 to t0); (2) a four-day window (t1 to t2); (3) 13-day window (t6 to

    t6); and (4) a 26-day window (t10 to t15). The utility-specic independent

    variable (COST) is the amount invested in the abandoned plant scaled by rm

    total assets. The cost variable is normalized by total assets in order to capture

    the importance of the investment relative to rm size.

    Model 1 is specied as:

    CARin a b1COSTiY

    where CARin is the cumulative abnormal return over an n-day period around

    the announcement of a nuclear project cancellation for utility i and COSTi is

    the investment/total assets for utility i.

    The null hypothesis: b1 0 is tested against the alternative hypothesis:b1 ` 0. Since investors' risk of loss increases with the size of the investment, we

    expect the market reaction to nuclear project cancellations to be negatively

    associated with the costs.

    To be included in the sample the following data must be available: (1)

    cumulative abnormal returns (CARin) for the four event windows; (2)

    The amount of investment in the cancelled projects obtained from Regulatory

    Research Associates, Moody's, or The Wall Street Journal, and (3) Total

    P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187 175

  • 7/30/2019 Arnold 2000

    16/27

    assets obtained from the Compusat data le. The selection yielded a sample of

    75. 10

    The results are presented in Table 5. The results show a signicant negative

    association between the relative size of a utility's investment in a nuclear

    project (COSTi) and stock market returns around the announcement of a

    decision to cancel the project. Costs are associated with negative returns in all

    four event windows.

    5.2. Model 2: state-specic regulatory environment

    Although national trends indicate that investors could expect to bear some

    portion of cancellation losses, rate setting is a decentralized process withconsiderable variability between rulings by public service commissions at the

    state level (DOE/EIA, 1983, pp. ixxxii). Therefore, market reaction to

    abandonment announcements may be aected by the state-specic regulatory

    environment in which utilities operate, as well as overall national trends. Based

    on our analysis of the cash ow consequences of regulatory accounting policies

    noted earlier in our paper, we can derive the following expectations regarding

    investor behavior. Investors anticipating a full recovery ruling from a state

    regulatory commission would not be expected to react negatively to aban-

    donment announcements since the cash ow consequences of abandonment

    and non-abandonment are identical. Investors anticipating a state-specicruling of no recovery or partial recovery, however, would be expected to react

    negatively to abandonment announcements since both these rulings have

    negative cash ow consequences in comparison to the alternative of bringing

    the project to completion. We use prior regulatory rulings on abandonment

    costs as a proxy variable for the state-specic regulatory environment in order

    to examine the association between the state regulatory environment and the

    stock market's reaction to abandonment decisions.

    A sub-sample comprised of the 33 cases where state commissions had issued

    prior regulatory decisions on the treatment of nuclear plant abandonment costs

    is used to examine the association between the content of prior state-specicregulatory accounting rulings and the market's reaction to cancellation an-

    nouncements. Model 2 controls for the size of the utility's investment and

    10 Sample statistics are:

    Variable Mean S.D. Max Med. Min.

    Investment (in millions) 125.8 204.9 1298 62 0.98

    Total assets (in millions) 2933.0 2145.2 8723.2 2451.6 65.1COST (Investment/total assets) 0.0431 0.0462 0.2666 0.0266 0.0002

    176 P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187

  • 7/30/2019 Arnold 2000

    17/27

    Table

    5

    Ordina

    ryleastsquaresregressionresults

    fortheinuenceofcostsinvested

    incancellednuclearprojectsoncumulativeabnormalreturns,CAR

    in

    ,for

    2-day,

    4-day,

    13-day,and26-dayeventp

    eriods(n

    75)a

    Independent

    variables(predicted

    sign)

    2-dayperiod(

    )1to0)

    4-dayperiod()1

    to+2)

    13-dayperiod()6to

    +6)

    26-dayperiod()10to+1

    5)

    Estimated

    coecient

    t-Statistic

    Estimated

    coecient

    t-S

    tatistic

    Estimated

    coecient

    t-Statistic

    Estimated

    coecient

    t-Statistic

    Intercept

    0.0040

    0.831

    0.0076

    0.8

    85

    0.0163

    1.705

    0.0119

    0.831

    Cost

    ())

    )0.2797

    )3.696

    )0.5548

    )4.0

    58

    0.8084

    )5.317

    )0.8353

    )3.670

    Modelestimates

    AdjustedR2

    0.1461

    0.1729

    0.2693

    0.1442

    F-statistic

    13.6

    61

    16.4

    67

    28.2

    73

    13.4

    71

    Probabilityof

    F-statistic

    0.0004

    0.0001

    0.0001

    0.0005

    a

    Mode

    l1:CAR

    in

    a

    b1COST

    i,where

    CAR

    in

    istheutilityspeciccumulativeabnormalreturnmeasured

    bysummingtheindividualutility

    'ses-

    timatedabnormalreturnsoverfourevent

    periods(CAR

    in

    AR

    it

    )andCO

    ST

    i

    isthetotalinvestmentinthen

    uclearprojectdividedbythetotalassets

    oftheutility.

    *

    Signicantat0.10inaone-tailedtest.

    ***

    Sign

    icantat0.01inaone-tailedtest.

    P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187 177

  • 7/30/2019 Arnold 2000

    18/27

    examines the relationship between estimated CARs around the announcement

    of a plant cancellation and the accounting method (i.e., full recovery, partial

    recovery, or no recovery) adopted in the most recent ruling by a public utility

    commission with jurisdiction over the cancelling utility. The sample size is

    limited by the number of observations for which prior regulatory accounting

    rulings existed at the time of the abandonment announcement. Of the 33 rms

    in the sub-sample, state regulatory commissions issued full recovery rulings in

    three cases (9.1% of the sample), partial recovery rulings in 20 cases (60.6% of

    the sample), and no recovery rulings in 10 cases (30.3% of the sample). By

    comparison, Table 1 shows that state regulators issued full recovery rulings

    in18.1% of cases, partial recovery rulings in 60.3% of cases, and no recovery

    rulings in 21.6% of cases.The dependent variable is the estimated utility specic CARs (CAR in) cal-

    culated over four event windows surrounding the announcement of a nuclear

    project cancellation. The independent variables are (1) the amount of invest-

    ment in cancelled projects scaled by total assets, and (2) dummy variables in-

    dicating the recovery method adopted in the most recent rulings by a state

    commission with jurisdiction over the cancelling utility. 11

    Model 2 is specied as:

    CARin a b1COSTi b2 Partial Recoveryi b3 No RecoveryiY

    where CARin is the cumulative abnormal returns over a n-day period aroundthe announcement of a nuclear project cancellation for utility i. COSTi is in-

    vestment/total assets for utility i. Partial Recoveryi

    is 1 if the prior state ruling

    allowed amortization of the investment, but no return on the unamortized

    balance, and 0 otherwise. No Recoveryi

    is 1 if the prior state ruling disallowed

    all recovery, and 0 otherwise.

    As specied, the eect of a prior full recovery ruling is captured in the in-

    tercept term, and the parameters on the dummy variables indicate the marginal

    eect of the prior decision to adopt the partial recovery method or disallow all

    recovery. Since our analysis of cash ow consequences shows that full recovery

    generates the same cash ow as non-abandonment, while both partial recoveryand the no recovery have negative cash ow consequences, we hypothesize that

    the coecients b2 and b3 will be signicantly negative. Formally, we test the

    null hypothesis: b2 and b3 0; against the alternative hypothesis: b2 andb3 ` 0.

    The results of the ordinary least squares regression analysis are presented in

    Table 6. Consistent with previous results, the ndings indicate that the relative

    11

    For utilities operating in multiple state jurisdictions, observations were included if at least onestate had issued a prior ruling. If a utility operated in more than one state and these states had

    issued conicting prior rulings, the observation was omitted.

    178 P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187

  • 7/30/2019 Arnold 2000

    19/27

    Table

    6

    Ordina

    ryleastsquaresregressionresults

    fortheinuenceofcostsinvested

    incancelednuclearprojectsandstate-specicregulatoryenvironme

    nton

    cumula

    tiveabnormalreturns,CAR

    in

    ,Fo

    r2-day,

    4-day,

    13-dayand26-day

    eventperiods(n

    33)a

    Independentvariables

    (pred

    ictedsign)

    2-dayperio

    d()1to0)

    4-dayperiod()1to+2)

    13-dayperiod()6to

    +6)

    26-dayperiod()10to+15

    )

    Estimated

    coecient

    t-Statistic

    Estimated

    coecient

    t-Statistic

    Estimated

    coecient

    t-Statistic

    Estimated

    coecient

    t-Statis

    tic

    Intercept

    0.0303

    1.581

    0.0321

    0.780

    0.0297

    0.73

    8

    0.0054

    0.079

    Cost

    ())

    )0.4088

    )3.560

    )0.6282

    )2.550

    0.9681

    )4.01

    5

    )0.7767

    )1.879

    PartialRecovery())

    )0.0361

    )1.728

    )0.4330

    )0.967

    )0.0340

    )0.77

    5

    )0.0055

    )0.073

    NoR

    ecovery())

    )0.0127

    )0.537

    )0.0398

    )0.786

    )0.0124

    )0.25

    1

    )0.0480

    )0.565

    Modelestimates

    AdjustedR2

    0.3259

    0.1826

    0.3447

    0.1110

    F-statistic

    6.156

    3.382

    6.61

    2.332

    ProbabilityofF-statistic

    0.0023

    0.0314

    0.0015

    0.0949

    a

    Mode

    l2:CAR

    in

    a

    b1COST

    i

    b2PartialRecovery

    i

    b3NoRecovery

    i,whereCAR

    in

    istheutilityspeciccumulativeabnormalreturnmea

    sured

    bysum

    mingtheindividualutility'sestima

    tedabnormalreturnsoverfoureventperiods(CAR

    in

    AR

    it

    ).CO

    ST

    i

    isthetotalinvestmentinthenuclear

    project

    dividedbythetotalassetsofthe

    utility.

    PartialRecoveryi

    isthepolicyallowingutilitiesareturnof,

    butnoreturnontheirinvestmen

    t.No

    Recoveryiisdenedasnoreturnoforonthecostsofabandonedprojects.

    TheinterceptinthismodelrepresentsFullRecoverywhereutilityowners

    recoverthefullcostofprudentinvestmentsandearnareturntheunamortizedbalanceoftheirinvestment.

    *

    Signicantat0.10inaone-tailedtest.

    **

    Signicantat0.05inaone-tailedtest.

    ***

    Sign

    icantat0.01inaone-tailedtest.

    P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187 179

  • 7/30/2019 Arnold 2000

    20/27

    investment size is a signicant predictor of negative excess return. Our tests did

    not conrm the hypothesis that the existence of a prior state-specic regulation

    mandating no recovery of costs invested in cancelled nuclear plants or the

    partial recovery method would negatively aect the stock market's reaction to

    announcements of subsequent plant cancellations. 12

    Due to sample size limitations, further nonparametric tests were con-

    ducted (Siegel, 1956). Tables 7 and 8 summarized the results of the

    nonparametric analysis. These tables contain 38 observations, including ve

    observations that were excluded from the parametric analysis due to the

    unavailability of cost data. Table 7 shows the frequency distributions

    12

    A Chow test (Kennedy, 1987, pp. 229230) for dierences in regression coecients for dierentgroups similarly detected no dierences between CARs for the three types of regulatory decisions

    (Full Recovery, Partial Recovery, No Recovery) after controlling for the amount of investment.

    Table 7

    Frequency distributions of sign of cumulative abnormal returns, CARin vs. prior regulatory ruling

    over 2-day, 4-day, 13-day and 26-day event periods (n 38)a

    CARin (sign) Prior rulings

    Full Recovery Partial Recovery No Recovery

    26-day period

    CARin (+) 1 10 4

    25% 48% 31%

    CARin ()) 3 11 9

    75% 52% 69%

    13-day period

    CARin (+) 3 6 4

    75% 29% 31%CARin ()) 1 15 9

    25% 71% 69%

    4-day period

    CARin (+) 4 6 0

    100% 29% 0%

    CARin ()) 0 15 13

    0% 71% 100%

    2-day period

    CARin (+) 4 8 1

    100% 38% 8%CARin ()) 0 13 12

    0% 62% 92%

    a All variables are dened in Table 6.

    180 P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187

  • 7/30/2019 Arnold 2000

    21/27

    obtained by cross tabulating the sign of the CARins (positive or negative)

    against prior regulatory decisions (Full Recovery, Partial Recovery, No

    Recovery) for our four event periods. Table 8 shows the results of a

    nonparametric tests that consider the magnitude as well as the sign of the

    CARs. KruskalWallis tests for dierences between the three groups of prior

    regulatory decisions yield signicant chi squares for the four-day and two-

    day event periods. Pairwise comparisons using MannWhitney procedures

    nd signicant dierences between Full Recovery and Partial Recovery rul-

    ings, and between Full Recovery and No Recovery rulings for the 13-day,

    four-day and two-day event windows. No signicant dierences are detectedbetween Partial Recovery and No Recovery rulings. While the nonpara-

    metric results lend support to the hypothesis that state-specic prior regu-

    latory rulings inuence the market's reaction to cancellation announcements,

    the tests are inconclusive since they do not control for the relative size of

    investment in cancelled nuclear projects.

    5.3. Discussion

    Several factors could explain the failure to nd the expected association

    between the state-specic regulatory environment and the market reaction

    Table 8

    Dierence in cumulative abnormal returns, CARin, between types of prior regulatory rulings (Full

    Recovery, Partial Recovery, No Recovery) over 2-day, 4-day, 13-day and 26-day event periods(n 38)

    2-day period

    ()1 to 0)

    4-day period

    ()1 to +2)

    13-day peri-

    od ()6 to +6)

    26-day period

    ()10 to +15)

    KruskalWallis test

    v2 Statistica 12.011 10.779 4.983 1.967

    df 2 2 2 2

    Prob> v2 (0.003) (0.005) (0.083) (0.374)

    MannWhitney zb

    Full Recovery vs. 3.002 2.928 2.038 0.000

    Partial Recovery (0.001) (0.002) (0.021) (0.500)Full Recovery vs. 2.887 2.887 1.981 0.962

    No Recovery (0.002) (0.002) (0.024) (0.168)

    Partial Recovery vs. 1.488 1.028 0.461 1.276

    No Recovery (0.068) (0.152) (0.323) (0.101)

    a KruskalWallis one-way analysis of variance tests dierences in cumulative abnormal returns,

    CARin (magnitude and sign) between the three groups of prior regulatory decisions (Full Recovery,

    Partial Recovery, No Recovery).b MannWhitney pairwise comparisons p-values (shown in parentheses) are based on a one-tailed

    test.

    P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187 181

  • 7/30/2019 Arnold 2000

    22/27

    to abandonment announcements in the parametric tests. First, the power of

    the tests is limited by the small sample size. Second, state-specic prior

    regulatory rulings may be an inadequate proxy for state regulatory envi-

    ronment. Further research might develop a more accurate measure of state

    regulatory environment by creating an index that factors in regulatory

    commissions rulings on a number of issues, rather than considering only

    prior rulings on abandonment costs. Third, the market may have im-

    pounded the eect of expected regulatory rulings at a time other than the

    announcement date.

    Alternatively, it is possible that the market discounted prior state-specic

    regulatory decisions, because of uncertainty as to whether further regulatory

    rulings would be consistent with prior rulings. The decentralized, volatile,and litigious regulatory environment undoubtedly increased uncertainty as to

    what portion of the losses investors would ultimately bear. It was not un-

    common for state regulatory commissions to reverse previous rulings on

    nuclear plant abandonment costs (RRA, 1988, pp. 25). Nor, was it unusual

    for utilities to operate under more than one state jurisdiction, and thus be

    subject to sometimes contradictory regulatory rulings in dierent states

    (RRA, 1988, pp. 25). On the legal front, utilities and/or consumer groups

    frequently appealed unfavorable commission decisions through the courts,

    particularly in cases of no recovery or full recovery rulings (RRA, 1988,

    pp. 222). In some cases, appellate courts overtuned commission's rulings(RRA, 1988, pp. 222). The legal environment remained highly uncertain

    until 1989 when the US Supreme Court upheld the authority of states to

    disallow recovery of capital invested in abandoned nuclear plants (Duquesne

    Light Co. v. Barasch, 1989).

    In sum, rulings on nuclear power abandonment costs varied over time even

    within a given state as a result of litigation, changing state laws, and/or the

    intrusion of nuclear politics on the rate setting process. Such uncertainty

    combined with the political volatility of nuclear power may have caused in-

    vestors to discount information about state-specic prior rulings in pricing

    utilities securities. The results of our study, however, indicate that investors didconsider information about broader national regulatory trends, i.e., the high

    probability that investors would bear some portion of abandonment losses, in

    pricing securities.

    6. Conclusions

    Barring a revival of the US nuclear power industry, future losses on nuclear

    project abandonments will not be consequential. Nonetheless, regulatory ac-

    counting for the nuclear industry will continue to have signicant cash ow

    consequences, most immediately in the area of accounting for the cost of

    182 P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187

  • 7/30/2019 Arnold 2000

    23/27

    stranded assets (Blacconiere et al., 1997, p. 199). Recent trends toward dere-

    gulation of the electric utilities industry are opening the way for consumer

    choice and rate competition (Parker and Grove, 1998, p. 67). As competition is

    phased in, state regulators and legislatures will decide the extent to which

    previously regulated utilities will be allowed to recover the cost of so-called

    stranded costs through levies on consumers. Stranded costs are the portion of a

    utilities' existing assets that would have been recovered under regulation, but

    cannot be recovered through rates set in a competitive market (Parker and

    Grove, 1998, pp. 6769). They include high-cost (non-competitive) generating

    plants such as nuclear facilities, and the cost of decommissioning nuclear

    plants at the end of their lives. Nationally, stranded costs are estimated the

    range between $100 and $200 billion (Parker and Grove, 1998, pp. 6769). Theissue of how state regulators employ accounting choices and estimates to

    allocate the cost of stranded investments in nuclear technologies among

    stockholders, ratepayers, and taxpayers remains politically salient in the era of

    deregulation.

    Our review of public utility commissions' decisions on nuclear plant

    abandonment costs shows that, in the past, regulatory accounting treatment

    was generally favorable to investors. As the classication of regulatory de-

    cisions in Table 1 shows, full recovery rulings were issued in approximately

    18.1% of the rate cases; no recovery rulings were issued in approximately

    21.6% of the cases; and, partial recovery rulings in approximately 60.3% ofthe cases. Under full recovery investors both recouped their costs and

    earned a return on their investment in failed nuclear projects. Because of

    tax savings, stockholders never bore the full cost of investments in aban-

    doned nuclear projects even in the worst case of a no recovery ruling (DOE/

    EIA, 1983, p. 36). Under the most common recovery method, the partial

    method with an amortization period of 10 years, investors bore an esti-

    mated 1938% of the losses on cancelled nuclear plants (DOE/EIA, 1983,

    pp. 3940).

    While a substantial share of the abandonment losses were transferred to

    ratepayers and taxpayers, investors bore some portion of the losses in mostcases. Indeed, our review of the regulatory accounting decisions concludes that

    regulatory incentives would lead investors to prefer project completion over

    abandonment. If a nuclear plant could be brought to completion, investors

    would earn both a return on and a return of their investment whereas, in the

    case of abandonment, investors received similar returns only in 18.1% of cases

    where regulators ruled in favor of full recovery. Thus, our review of rate reg-

    ulations led to the hypothesis that the stock market would react negatively to

    nuclear project cancellation announcements.

    Consistent with this expectation, our empirical results indicate that overall

    the stock market reacted negatively to announcements of nuclear power project

    cancellations by regulated public utilities. The nding is signicant in two

    P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187 183

  • 7/30/2019 Arnold 2000

    24/27

    respects. First, our results conrm prior research studies (Bowen et al., 1983,

    p. 106; Fuller et al., 1990, pp. 128131) that suggest investors in nuclear utilities

    do not expect to be fully compensated for losses through regulatory rate in-

    creases. Our nding is not consistent with theoretical speculations that utility

    stockholders will either react positively or be neutral with respect to capital

    project abandonment decisions because of expectations for favorable rate

    rulings (Chen et al., 1987, pp. 293, 294; McConnell and Mascarella, 1985,

    p. 416). To the contrary, our study nds that notwithstanding favorable reg-

    ulatory treatment, investors bore some risk from investment in nuclear tech-

    nology given the institutionally decentralized US regulatory environment and

    the political volatility of nuclear power.

    Second, the nding of a negative reaction to nuclear abandonment an-nouncements has implications for theory development. Recent trends in the

    theoretical literature (for example, see Cheng, 1994; Mueller, 1989; March and

    Olsen, 1989; Powell and DiMaggio, 1991) on state interventions in the econ-

    omy suggest models of regulation that view regulators simply as pro-producer

    or pro-consumer provide inadequate grounds on which to theorize the con-

    sequences of regulatory accounting policies. To the contrary, the literature

    indicates that public sector accounting choices are the outcome of complex

    political processes the outcome of which is not easily predicted. These processes

    involve interactions between elected ocials, agency administrators and sta,

    media, credit markets, taxpayers, and interest groups within an environmentconstrained by socioeconomic conditions, technical capacity, and political and

    bureaucratic structures.

    In the absence of a simple predictive theory, hypotheses concerning the

    economic consequences of regulatory accounting policy choices cannot be

    formulated in the absence of concrete and detailed analyses of regulatory

    rulings. In the case of our study, such an historical analysis of the regula-

    tory treatment of abandonment losses formed the basis for the empirically

    grounded hypothesis that the market would react negatively to abandon-

    ment decisions; a hypothesis that was conrmed by empirical tests. We hope

    that our article will encourage others to ground theoretical propositionsabout the eects of state interventions in the economy within the context of

    concrete analyses of incentives created by regulatory accounting and taxing

    regimes that govern wealth transfers and resource allocations within in-

    dustries.

    Acknowledgements

    We wish to thank two anonymous reviewers and seminar participants at the

    London School of Economics and Political Science for helpful comments and

    suggestions.

    184 P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187

  • 7/30/2019 Arnold 2000

    25/27

    References

    Arnold, P.J., 1991. Accounting and the state: consequences of merger and acquisition accounting in

    the US hospital industry. Accounting Organizations and Society 16 (2), 121140.

    Ball, R.J., Smith, C.W., 1992. The Economics of Accounting Policy Choice. McGraw-Hill, New

    York.

    Blacconiere, W.G., Johnson, M.F., Johnson, M.S., White, L.J., 1997. Stranded costs and

    competitive forces in the electric utility industry. Journal of Accounting Auditing and Finance

    12 (3), 199221.

    Bowen, R., Castainas, R., Daley, L., 1983. Intra-industry eects of the accident at Three Mile

    Island. Journal of Financial and Quantitative Analysis 18 (1), 87110.

    Brown, S.J., Warner, J.B., 1985. Using daily stock returns: the case of event studies. Journal of

    Financial Economics 14 (1), 331.

    Burchell, S., Clubb, C., Hopwood, A., Hughes, J., Nahapiet, J., 1980. The role of accounting inorganizations and society. Accounting, Organizations and Society 5 (1), 527.

    Burgstahler, D, Dichev, I., 1997. Earnings management to avoid earnings decreases and losses.

    Journal of Accounting and Economics 24 (1), 99126.

    Callihan, D., 1994. Corporate eective tax rates: a synthesis of the literature. Journal of Accounting

    Literature 13, 143.

    Campbell, J., 1988. Collapse of an Industry. Cornell University Press, Ithaca, NY.

    Carnoy, M., 1984. The State and Political Theory. Princeton University Press, Princeton, NJ.

    Chen, C., Fanara, P., Gorman, R., 1987. Abandonment decisions and the market value of the rm:

    the case of nuclear power project abandonment. Journal of Accounting and Public Policy 6 (4),

    285297.

    Cheng, R.H., 1994. A politico-economic model of government accounting policy choice. In:

    Copley, P. (Ed.), Research in Government and Nonprot Accounting 8. JAI Press, New York,pp. 3968.

    Cooper, D.J., Sherer, M.J., 1984. The value of corporate accounting reports. Accounting,

    Organizations and Society 9 (3/4), 207232.

    D'Souza, J.M., 1998. Rate-regulated enterprises and mandated accounting changes: the case of the

    electric utilities and post-retirement benets other than pensions (SFAS No. 106). The

    Accounting Review 73 (3), 387410.

    DeAngelo, H., DeAngelo, L., Skinner, D.J., 1994. Accounting choice in troubled companies.

    Journal of Accounting Economics 17 (1/2), 113143.

    Department of Energy/Energy Information Administration (DOE/EIA), 1983. Nuclear plant

    cancellations: causes, costs and consequences. A report prepared by the Energy Information

    Administration, the Independent Statistical and Analytical Agency within the Department of

    Energy. DOE/EIA-0382. US Department of Energy, Washington, DC.

    Duquesne Light Co v. Barasch, 1989. 488 US 299.

    Escobar, A., 1995. Encountering Development. Princeton University Press, Princeton, NJ.

    Federal Energy Regulatory Commission (FERC) 1979. New England Power Company, 8 FERC

    61, 054 at pp. 61,06161,192.

    Federal Energy Regulatory Commission (FERC) 1988. New England Power Company, 42 FERC

    61,016 at pp. 61,06861,085.

    Fuller, R., Hinman, G., Lowinger, T., 1990. The impact of nuclear power on the systematic risk

    and market value of electric utility common stock. The Energy Journal 11 (2), 117133.

    Han, J.C.Y., Wang, S., 1998. Political costs and earnings management of oil companies during the

    1990 Persian Gulf crisis. The Accounting Review 73 (1), 103118.

    Hand, J.R.M., Skantz, T.R., 1997. The economic determinants of accounting choices: theunique case of equity carve-outs under SAB 51. Journal of Accounting and Economics 24 (2),

    175204.

    P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187 185

  • 7/30/2019 Arnold 2000

    26/27

    Healy, P., 1985. The eect of bonus schemes on accounting decisions. Journal of Accounting and

    Economics 7 (13), 85107.

    Holthausen, R.W., Leftwich, R., 1983. The economic consequences of accounting choice:implications of costly contracting and monitoring. Journal of Accounting and Economics 5

    (2), 77117.

    Hirst, P., Thompson, G., 1998. Globalization in Question. Polity Press, Cambridge.

    Jarrell, G.A., 1979. Pro-producer regulation and accounting for assets: the case of electric utilities.

    Journal of Accounting and Economics 1 (2), 93116.

    Johnson, M.S., Niles, M.S, Suydam, S.L., 1998. Regulatory changes in the electric utility industry:

    investigation of eects on shareholder wealth. Journal of Accounting and Public Policy 17 (4,5),

    285309.

    Kennedy, P., 1998. A Guide to Econometrics, 4th ed. MIT Press, Cambridge, MA.

    Key, K.G., 1997. Political cost incentives for earnings management in the cable television industry.

    Journal of Accounting and Economics 23 (3), 309337.

    Kim, M.S., Kross, W., 1998. The impact of the 1989 change in bank capital standards on loan loss

    provisions and loan write-os. Journal of Accounting and Economics 25 (1), 6999.

    March, J.G., Olsen, J.P., 1989. Rediscovering Institutions: The Organizational Basis of Politics.

    The Free Press, New York.

    McConnell, J.J., Mascarella, C.J., 1985. Corporate capital expenditure decisions and the market

    value of the rm. Journal of Financial Economics 14 (3), 399422.

    Miller, P., Rose, N., 1990. Governing economic life. Economy and Society 19 (1), 131.

    Mueller, D., 1989. Public Choice II. Cambridge University Press, New York.

    Muller, K.A., 1999. An examination of the voluntary recognition of acquired brand names in the

    United Kingdom. Journal of Accounting and Economics 26 (1-3), 179191.

    Nuclear Energy Institute (NEI). Historical Prole of US Nuclear Power Development, 1996

    edition. Nuclear Energy Institute, Washington, DC.Otis, T.H., 1981. A Review of Nuclear Energy in the US. Praeger, New York.

    Parker, R.P, Grove, C.B., 1998. The statistics producers' corner. Business Economics 33 (4),

    6769.

    Patten, D.M., Nance, J.R., 1998. Regulatory cost eects in a good news environment: the intra-

    industry reaction to the Alaskan oil spill. Journal of Accounting and Public Policy 17 (4/5), 409

    429.

    Peltzman, S., 1976. Toward a more general theory of regulation. Journal of Law and Economics 19

    (2), 211240.

    Powell, W., DiMaggio, J., 1991. The New Institutionalism in Organizational Analysis. The

    University of Chicago Press, Chicago.

    Regulatory Research Associates, Inc. (RRA), 1988. Utility Composite Cancelled Plant

    Treatment. Regulatory Study. Regulatory Study. Regulatory Research Associates, Inc., JerseyCity, NJ.

    Scholes, M., Williams, J., 1977. Estimating betas from non-synchronous data. Journal of Financial

    Economics 5 (3), 309328.

    Siegel, S., 1956. Nonparametric Statistics. McGraw-Hill, New York.

    Skopol, T., 1985. Bringing the State Back in: strategies of analysis in current research. In: Evans,

    R., Rueschemeyer, D., Skopol, T. (Eds.), Bringing the States Back in. Cambridge University

    Press, Cambridge, pp. 137.

    Soo, B.S., 1999. Accrual response to mandated accounting principles: the case of SFAS Nos. 2 and

    34. Journal of Accounting and Public Policy 18 (1), 5984.

    Stigler, G.J., 1971. The theory of regulation. Bell Journal of Economics and Managerial Science 2

    (1), 321.

    Teisberg, E.O., 1988. Investment cost recovery and incentives for power plant construction. PublicUtilities Fortnightly 121 (5), 914.

    186 P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187

  • 7/30/2019 Arnold 2000

    27/27

    Watts, R.L., Zimmerman, J.L., 1978. Towards a positive theory of the determination of accounting

    standards. The Accounting Review 53 (1), 112134.

    Wood, E.M., 1995. Democracy Against Capitalism. Cambridge University Press, Cambridge.Wright, E.O., 1978. Class Crisis and the State. New Left Books, London.

    Ze, S., 1978. The rise of economic consequences. The Journal of Accountancy 146 (6), 5663.

    Zysman, J., 1983. Government, Markets and Growth: Financial Systems and the Politics of

    Industrial Change. Cornell University Press, Ithaca, NY.

    P.J. Arnold, R.H. Cheng / Journal of Accounting and Public Policy 19 (2000) 161187 187