FOUO – For Official Use Only Army Team C4ISR Army Team C4ISR BRAC Update BRAC Update Presented By: Sue Nevin, G3/5 CECOM Life Cycle Management Command 8 October 2009

Army Team C4ISR BRAC Update

  • Upload
    thu

  • View
    64

  • Download
    3

Embed Size (px)

DESCRIPTION

Army Team C4ISR BRAC Update. Presented By: Sue Nevin, G3/5 CECOM Life Cycle Management Command 8 October 2009. 1,131 “Boots on the Ground”. What We’ve Done. Phased Relocation Status and Timeline (FY07 – FY11). Groundbreaking For Permanent Facilities. - PowerPoint PPT Presentation

Citation preview

Page 1: Army Team C4ISR  BRAC Update

FOUO – For Official Use Only

Army Team C4ISR Army Team C4ISR BRAC UpdateBRAC Update

Presented By:Sue Nevin, G3/5CECOM Life Cycle Management Command8 October 2009

Page 2: Army Team C4ISR  BRAC Update

FOUO – For Official Use Only

Page 2 of 29

In accordance with Report to Congress and BRAC Strategic Plan: Developed Phased Early Relocation strategy using temporary

facilities at APG – combination of military, civilian volunteers, new hires and contractors

2007 2008 2009 2010 2011 2012

Phase 1Early Relocation

32 positions (11 Vol.) (11 Vol.)

GroundbreakingFor

PermanentFacilities

Phase 2Early Relocation

340 positions (140 Vol.)(140 Vol.)

Phase 3Early Relocation1317 positions

(542 Vol. Currently)(542 Vol. Currently) Main Moves Into

Permanent Facilities

What We’ve DoneWhat We’ve DonePhased Relocation Status and TimelinePhased Relocation Status and Timeline

(FY07 – FY11)(FY07 – FY11)

1,131 “Boots on

the Ground”Time Now

Page 3: Army Team C4ISR  BRAC Update

FOUO – For Official Use Only

Page 3 of 29

HQ BES WEST

MTF

GMS LAB

C2/CNT WEST

GMS TOWER

Phase 1 Estimated Move In Dates Domains

GMS Lab 1 Aug 10 Ground Based Radars, Multi-Intel,

Sensors, Force Protection (FP),

Night Vision (NVEO)GMS Tower 1 Aug 10

HQ East 1 Oct 10HQ, Business

Enterprise Systems, Operations Support

HQ West 1 Oct 10

Auditorium 1 Oct 10

C2/CNT West 1 Nov 10

Command & Control (C2), Navigation, Future Combat System (FCS)

Mission Training Facility

1 Nov 10 Mission Training Facility

HQ BES EASTAuditorium

Page 4: Army Team C4ISR  BRAC Update

FOUO – For Official Use Only

GMS Lab & GMS TowerEstimated Date that Moves will begin: 1 August 2010

Aug-Sep 10 Oct - Dec 10 Jan-Mar 11 TOTALCERDEC 75 107 33 215IEWS 73 104 32 209LRC 60 85 26 171SEC 41 58 18 117

249 354 109 712

Building Occupancy: 1,410

Page 5: Army Team C4ISR  BRAC Update

FOUO – For Official Use Only

HQ East & HQ WestEstimated Date that Moves will begin: 1 October 2010

Oct - Dec 10 Jan-Mar 11 Apr - Jun 11 TOTALC3T 8 11 4 23CCCE 68 96 29 193HQ CECOM 84 119 84 287CERDEC 18 26 8 52IEWS 3 4 2 9LRC 126 179 54 359SEC 72 103 21 196

379 538 202 1,119

Building Occupancy: 2,143

Page 6: Army Team C4ISR  BRAC Update

FOUO – For Official Use Only

C2/CNT West & Mission Training FacilityEstimated Date that Moves will begin: 1 November 2010

Nov - Dec 10 Jan-Mar 11 Apr - Jun 11 TOTALARL 5 12 3 20G2, G8, Safety 1 3 1 5CERDEC 28 66 17 111FCS 21 49 13 83LRC 26 62 16 104PEO C3T 116 278 70 464PEO IEW&S 7 17 5 29SEC 23 55 14 92

227 542 139 908

Building Occupancy: 1,800

Page 7: Army Team C4ISR  BRAC Update

FOUO – For Official Use Only

Army Team C4ISR Phase IIArmy Team C4ISR Phase II

Phase 2 Estimated Move In Dates Domains

C2/CNT East 1 Mar 11 Comm System Network Transport (CNT)

Consolidated North 1 Mar 11 C3T SPO, CECOM Safety

Power & Cooling (5100) 1 Mar 11 Power and Cooling (P&C)

JSEC 1 Mar 11 JSEC

C2 Integration 15 Jul 11 Fabrication

JSECConsolidated North C3/CNT EastPower & Cooling

Mar-11 Apr - Jun 11 Jul - Sep 11 TOTALCECOM Safety 3 14 2 19CERDEC 53 264 36 353LRC 41 204 28 273PEO C3T 42 210 28 280PM DCATS 9 43 6 58SEC 20 96 13 129

168 831 113 1,112

Building Occupancy:

2,213