44
Armadale Road to North Lake Road Bridge Project Consolidated Out of Hours Noise and Vibration Management Plan Document details Client Main Roads Western Australia (Main Roads) Document Owner Armadale Access Alliance Client Contract No. MRWA 237/16 Document Number ARNLR-AAA-MPL-0000-EN-0003 Revision 0

Armadale Road to North Lake Road Bridge Project · 2020. 6. 25. · ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page ii

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

  • Armadale Road to North Lake Road Bridge Project

    Consolidated Out of Hours Noise and Vibration Management Plan

    Document details

    Client Main Roads Western Australia (Main Roads)

    Document Owner Armadale Access Alliance

    Client Contract No. MRWA 237/16

    Document Number ARNLR-AAA-MPL-0000-EN-0003

    Revision 0

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page i

    REVISION REGISTER

    Rev Date Details Originator Reviewed Approved

    0 11/11/2019 Issued for Review and Approval C. Ridley M. Bulmer A. Deurloo

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page ii

    CONTENTS

    1 PURPOSE 1

    2 REFERENCES 2

    3 ASSIGNED NOISE LEVELS 3

    3.1 Influencing Factors 3

    3.1.1 Influencing Factors – Land Zoning 3

    3.1.2 Influencing Factors – Transport Factors 3

    3.1.3 Influencing Factor calculation 4

    3.2 Site Specific Assigned Noise Levels 5

    4 SCOPE OF WORKS 6

    4.1 Plant and Noise Sources 6

    5 NOISE AND SENSITIVE RECIEVERS 9

    5.1 Plant and Noise Generation 9

    5.2 Intrusive Characteristics and Associated Penalties 13

    5.3 Sensitive Receivers 13

    6 VIBRATION AND SENSITIVE RECEIVERS 15

    7 APPROVALS PROCESS 16

    8 CONTROLS AND MITIGATIONS MEASURES 17

    8.1 Management Controls 17

    8.2 Source Controls 18

    8.3 Path Controls 19

    8.4 Monitoring 19

    8.4.1 Noise Monitoring 19

    8.4.2 Vibration Monitoring 20

    9 COMMUNITY NOTIFICATION 21

    10 COMPLAINTS 22

    11 NON-CONFORMANCE, INCIDENT AND CORRECTIVE ACTION 23

    12 REPORTING REQUIREMENTS 25

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page iii

    Appendices

    Appendix A Out of Hours Work Notification Form

    Appendix B Transport Factors for Areas Surrounding Works

    Appendix C Out of Hours Request Form

    Appendix D Residential Notification Letter

    Appendix E Timeline for Approvals

    Appendix F Vibration Dissipation Distance

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page iv

    Terms, Abbreviations and Definitions

    Abbreviation Definition

    AAA Armadale Access Alliance

    Alliance The Alliance established to deliver the Project

    ARNLR Armadale Road to North Lake Road Bride Project

    CIC MRWA Customer Information Centre

    CoC City of Cockburn

    COHNVMP Consolidated Out of Hours Noise and Vibration Management Plan

    CM Construction Manager

    CNVMP Construction Noise and Vibration Management Plan

    CSEM Community and Stakeholder Engagement Manager

    CSET Community and Stakeholder Engagement Team

    dB Decibel

    DWER Department of Water and Environmental Regulation

    EC Environmental Coordinator

    EPA Environmental Protection Authority

    EQSafe Main Roads Western Australia incident reporting portal

    Hz Hertz

    IMPACT LORA incident reporting portal

    LGA Local Government Area

    OOH Out-of-Hours

    OOHW Out-of-Hours Works

    PPV Peak Particle Velocity

    Project Armadale Road to North Lake Road Bride Project, the Project

    Main Roads Main Roads Western Australia

    MRWA Main Roads Western Australia

    RAP Representative Assessment Period

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 1

    1 PURPOSE

    This Consolidated Out of Hours Construction Noise and Vibration Management Plan (COHNVMP) has been produced to supplement Armadale Access Alliance’s (AAA) Environmental Management Plan (EMP) and the Construction Noise and Vibration Management Plan (CNVMP) for implementation by the Alliance throughout the Armadale Road to North Lake Road Bridge (ARNLR) Project.

    The COHNVMP outlines AAA’s approach to the management of nuisance noise and vibration created from the Project. This Plan is an extension of the CNVMP and provides a detailed assessment of noise and vibration for works that are to be conducted outside of normal construction hours (i.e. between 1900 hours and 0700 hours). The COHNVMP has been developed with reference to the documents outlined in Section 2 below.

    This is an overarching plan, applicable to a limited number of tasks which are expected to be regularly undertaken out-of-hours throughout the duration of the Project. The scope of works and associated tasks are outlined in Section 4 of this Plan. For works that are not covered within this Plan, or where significant changes are required, the normal Out-of-Hours Works (OOHW) approval process as described in the CNVMP must be followed. This includes a detailed assessment of noise levels, mapping of impacts, identification of sensitive receivers and submissions of approval request to Main Roads Western Australia (MRWA) and the Local Government Authority (LGA), the City of Cockburn.

    This plan does not include the dates of any works to be undertaken. An ‘Out of Hours Works Notification Form’ shall be submitted to MRWA and the LGA which will set out the dates of works and the activities to be undertaken. A copy of the ‘Out of Hours Works Notification Form’ is provided in Appendix A.

    This COHNVMP aims to satisfy the following objectives:

    • Provide calculations for the assigned noise levels received by properties along the alignment • Identify expected noise (including sound penalties where required) generated by works using

    sound power levels from plant and equipment • Where sound levels to be received by closest sensitive receivers exceed assigned levels, identify

    and implement methods to decrease sound levels where possible • Minimise and manage noise generation from the project area during out of hours working • Mitigate potential impacts on the environmental values, and the health, amenity and welfare of

    the community resulting from the OOHW • Ensure that noise generated from the construction works complies with the relevant statutory

    requirements • Ensure that all reasonable and practical measures are undertaken during the works to minimise

    noise and vibration emissions from site • Ensure that all works and activities within the scope are undertaken in a manner that will

    minimise the noise and vibration impacts on sensitive receivers

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 2

    2 REFERENCES

    • Environmental Protection Act 1986 • Environmental Protection (Noise) Regulations 1997 • Environmental Protection Regulations 1987 • AS 2436-2010: Guide to noise control on construction, maintenance and demolition sites • AS 2670.2: Evaluation of Human Exposure to Whole Body Vibration • Environmental Protection Authority (EPA), 2007, EPA Guidance Statement No 8: Environmental

    Noise (Draft). Environmental Protection Authority, Perth, WA • State Planning Policy 5.4: Road and Rail Transport Noise and Freight Considerations in Land Use

    Planning (SPP 5.4) (Western Australian Planning Commission, 2009) • AAA Scope of Work and Technical Criteria • AAA Community and Stakeholder Engagement Management Plan (ARNLR-AAA-MPL-0000-CS-

    0001).

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 3

    3 ASSIGNED NOISE LEVELS

    Assigned noise levels are the levels of noise allowed to be received at a premises at a particular time of the day. There are different assigned levels for noise sensitive, commercial and industrial premises. The assigned levels also depend on how close the noise sensitive premises are to industrial and commercial areas, and major and minor roads. These assigned noise levels always apply at the premises receiving the noise.

    The assigned levels have been adopted on the Project as a noise target for construction works undertaken outside normal operating hours. The table of assigned levels, shown in Table 1 identifies three types of assigned levels: LAmax, LA1 and LA10.

    Table 1 – Assigned noise levels

    Type of premises receiving noise

    Time of day Assigned Level (dB)

    LA10 LA1 LAMAX

    Noise sensitive premises 0700 to 1900 hours Monday to Saturday

    45 + 55 + 65 +

    0900 to 1900 hours Sunday and public holidays

    40 + 50 + 65 +

    1900 to 2200 hours all days 40 + 50 + 55 +

    2200 hours on any day to 0700 hours Monday to Saturday and 0900 hours Sunday and public holidays

    35 + 45 + 55 +

    Commercial premises All hours 60 75 80

    Industrial and utility premises All hours 65 80 90

    + = the addition of an influencing factor

    3.1 Influencing Factors

    As per Schedule 3 of the Environmental Protection (Noise) Regulations 1997, the assigned noise level that a sensitive receiver may be subject to can be modified by the surrounding land uses for the property. The influencing factor (IF) increases with the number of commercial and industrial premises in the vicinity of the receiver as well as the presence of major or minor roads. This is calculated by considering land use zoning and the volume of traffic that utilises the road infrastructure within 100m and 450m of the receiver.

    3.1.1 Influencing Factors – Land Zoning

    Influencing factors based on the surrounding land use within a set distance from the sensitive receiver are developed from local government zoning maps. Industrial and commercial land uses are likely to generate an increase in the volume of sound within a set area, and therefore any sensitive premises located within finite proximity to these areas are taken as being be more tolerant of higher volumes of sound. To calculate the influencing factor two concentric circles representing 100m and 450m radii are placed from the noise sensitive premises, any land within the circles that is classified as Type 1 land (industrial and utility) or Type 2 land (commercial) is calculated as a percentage of the full area of each circle. The percentage is then used to calculate the influencing factor to the nearest decibel.

    3.1.2 Influencing Factors – Transport Factors

    Sensitive premises that are located within a defined distance from a Primary Road (a road that takes in excess of 15000 vehicles per week day) or secondary road (a road that takes more than 6000 but less than 15000 vehicles per week day) are deemed to be influenced by transport. The transport factor can be a maximum of 6dB added to the influencing factor. The values to be added as transport factors are summarised in Table 2.

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 4

    Table 2 – Influencing Factors for Primary and Secondary Roads

    Encompassing Distance Primary Road

    (15000+ vehicles per day)

    Secondary Road

    (6000 to 14999 vehicles per day)

    100m 6dB 2dB

    450m 2dB -

    Transport factor assessment is provided in Table 3, with the affected properties provided in Appendix B.

    Table 3 – Transport Factor Assessment

    Nearby Roads Number of Vehicles Road Classification

    Armadale Road (east of Kwinana Freeway)

    45,268 Primary

    North Lake Road 16,880 Primary

    Kwinana Freeway (north bound, south of Berrigan Drive)

    59,197 Primary

    Kwinana Freeway (south bound, south of Berrigan Drive)

    62,065 Primary

    Kwinana Freeway (north bound, south of Armadale Road)

    47,121 Primary

    Kwinana Freeway (south bound, south of Armadale Road)

    55,643 Primary

    Berrigan Drive (east of Kwinana Freeway)

    21,391 Primary

    Berrigan Drive (west of Kwinana Freeway)

    29,925 Primary

    Beeliar Drive (west of Kwinana Freeway)

    53,160 Primary

    Midgegooroo Avenue 16,933 Primary

    Ghostgum Ave No Data No Data

    Verde Drive No Data No Data

    Tapper Road No Data No Data

    Solomon Road No Data No Data

    Kentucky Court No Data No Data

    Traffic data presented in Table 3 is based on the average number of vehicles recorded Monday to Friday between 2013 and 2019. This traffic count data was obtained from Main Roads Trafficmap website (https://trafficmap.mainroads.wa.gov.au/map).

    3.1.3 Influencing Factor Calculation

    Due to the limited area of the works impacted by industrial/commercial land zoning factors, AAA have opted not to utilise the influencing factor generated from land uses. Nearby industrial and commercial premises are also not expected to operate outside of normal construction hours. Transport Factors only shall be used to determine assigned noise levels for sensitive premises.

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 5

    3.2 Site Specific Assigned Noise Levels

    The assigned levels are statistical noise levels over a Representative Assessment Period (RAP); for this project the RAP 15 minutes has been chosen as an appropriate period for assessing noise from the project. The DWER Noise Regulations specify 15 minutes as the minimum assessment time and it is also the DWER’s preferred RAP for night time operations. As the sites will be operational for over 10% of the RAP, the LA10 statistical noise criteria is the relevant criteria for this project. The specific LA10 assigned levels for the predicted worst affected receivers (within 100m of the Project boundary) are outlined in Table 4. These assigned levels have been calculated by the addition of a Transport Factor. For simplicity, roads within 100m of the Project boundary have been identified and the periods have been split into day (0700 – 1900 Monday to Saturday and 0900 – 1900 Sundays and Public Holidays) evening (1900 – 2200 all days) and night (2200 – 0700 Monday to Saturday and 2200 - 0900 Sundays and Public Holidays).

    Where a given task or set of works is calculated to exceed or significantly contribute to an exceedance of the assigned sound level for affected sensitive properties, AAA shall notify properties within 100m of the Project boundary relevant to the work area. A noise emission is generally understood to ‘significantly contribute’ to an exceedance if it is higher than a level which is 5.0 dBA below the assigned level at the point of reception.

    Table 4 – Specific assigned noise levels

    Construction Area Receiver Assigned level LA10 dB

    Day Evening Night

    Kwinana Freeway / Bridge

    Residential: Muriel Court, Imlah Court, Verna Court, The Lakes Boulevard

    N/A 46 41

    Adjacent commercial N/A 66 66

    Adjacent industrial N/A 71 71

    Armadale Road Extension

    Residential: Tylee Cove, Marie Court, Dreier Court, Hoult Mews, Mahogany Loop, Freshwater Drive, Veneta Circuit, Tapper Road, Ceadarleaf Entrance, Gutterridge Road

    N/A 46 41

    Adjacent commercial N/A 66 66

    Adjacent industrial N/A 71 71

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 6

    4 SCOPE OF WORKS

    The ARNLR Project involves the construction of a bridge over the Kwinana Freeway connecting Armadale Road to North Lake Road and construction of free-flowing traffic lanes on Armadale Road through the Solomon Road and Tapper Road intersections. Full connectivity will be retained at the intersections of Solomon Road and Tapper Road through grade separated roundabouts.

    This plan aims to identify all standard tasks required to occur out of hours and their corresponding noise levels. This will allow for a streamlined and standardised approach to the assessment of OOHW activities and the approvals process.

    The standard tasks expected to be repeated throughout the duration of the ARNLR Project are detailed in Table 5 below.

    Table 5 – List of standard tasks to be undertaken during the Project

    Task

    - Demolition- Clearing and arborist works - Foundation preparation - Embankment construction - Haulage and stockpiling - Deliveries of sand, subgrade and fill

    material - Dust suppression including filling of water

    carts - Under boring works for service installation - Trenching works for services installation - Trimming batters - Drainage installation and backfilling - Subgrade preparation

    - Subbase installation- Base course installation - Seal and asphalt replacement - Profiling asphalt - Line marking - Kerbing - Hard landscaping - Steel and concrete traffic safety barrier

    installation - Signage installation - Concrete pouring and pumping - Precast panel and beam installation - Light/signal pole removal - Gantry installation - Refuelling

    4.1 Plant and Noise Sources

    Plant required to complete the standard tasks outlined above are provided in Table 6. The sound generated from the normal use of an item of plant has been obtained from the plant specifications where available. Where plant specification does not include the sound power information, industry standard sound levels have been obtained from the Australian Standard 2436-2010 Appendix A. Where no standard sound levels are available, information has been sourced from onsite sound level monitoring of the plant.

    Table 6 – Plant list and Sound Power Levels

    Plant/Item Sound Power Level (dB)

    Plant Specification

    Industry Standard

    In-Field Measurement

    All Terrain Crane 25T 104 X

    All Terrain Crane 500T 104 X

    Auger 106 X

    Bobcat/Positrack 104 X

    Chainsaw 102 X

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 7

    Plant/Item Sound Power Level (dB)

    Plant Specification

    Industry Standard

    In-Field Measurement

    Chip Truck 107 X

    Compressor 109 X

    Concrete Agi Truck 109 X

    Concrete Pump Truck 108 X

    Concrete Saw 117 X

    Crawler Crane 400T 104 X

    Delivery Trucks (>20 Tonnes) 107 X

    Dozer 108 X

    Dump Truck 107 X

    Elevated Working Platform 105 X

    Excavator 107 X

    Extruded Barrier Machine 97 X

    Franna 20T 104 X

    Generators 99 X

    Grader 110 X

    Hand Tools (Electric) 102 X

    Hand Tools (Manual) 82 X

    Hand Tools (Pneumatic) 116 X

    Hydraulic Crane 50T 104 X

    Kerb extrusion machine 105 X

    Light Vehicles 106 X

    Lighting Towers 99 X

    Linemarking Truck 107 X

    Loader (Wheeled) 105 X

    Pad Foot Roller 108 X

    Paver Truck 108 X

    Paver Truck 107 X

    Plate compactor 108 X

    Post Driver 72 X

    Prime Mover (Truck with Trailer) 107 X

    Profiling Machine 110 X

    Rock Breaker (attachment) 118 X

    Rough Terrain Crane 25T 104 X

    Rubber Tyred Roller (Multi- tyred Roller)

    101 X

    Scraper 116 X

    Screener 99 X

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 8

    Plant/Item Sound Power Level (dB)

    Plant Specification

    Industry Standard

    In-Field Measurement

    Seal/Spray Truck 107 X

    Self-Propelled Motorised Transporter

    106 X

    Service Truck 107 X

    Skid Steer 85 X

    Smooth Drum Roller 108 X

    Stacker 99 X

    Street Sweeper 96 X

    Stump Grinder 106 X

    Sucker Trucks 117 X

    Telehandler 106 X

    Tipper Truck 117 X

    Vacuum Excavation Truck 92 X

    Vacuum Excavation Trailer 93 X

    Vermeer Directional Driller 106 X

    Water Blaster 116 X

    Water Cart 107 X

    Water Pump 99 X

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 9

    5 NOISE AND SENSITIVE RECIEVERS

    5.1 Plant and Noise Generation

    Construction activities often require multiple items of plant operating at the same time. The accumulation of sound power levels from multiple items of plant will result in a higher sound level than if one item was operating alone.

    The plant described in Table 6 have been grouped according to the standard tasks required for the scope of works. In order to simplify calculations, assessments for all tasks have been calculated based on all plant operating simultaneously at the same location to provide a maximum sound level. However, this assumption will likely result in an overestimation of actual accumulative sound levels.

    The calculation for the addition of various noise sources to be utilised is LTOT=10Log(10L1/10+10L2/ 10+10L3/10+………10Ln/10) where L1, L2, L3, Ln are individual noise sources.

    The calculated sound levels generated from each task are provided in Table 7.

    Table 7 – Accumulative Sound Levels

    Task Work Activity Plant / Equipment Required

    dB Accumulative Sound Level (dB)

    1 Application of Anti-graffiti Paint Generators 99 117

    Compressor 109

    Handtools (pneumatic) 116

    2 Base Course Installation Grader 110 116

    Smooth Drum Roller 108

    Water Cart 107

    Rubber Tyred Roller (Multi- tyred Roller)

    101

    Excavator 107

    Loader (Wheeled) 105

    Delivery Trucks (>20 Tonnes) 107

    3 Clearing and Arborist Works Elevated Working Platform 105 109

    Chain Saw 102

    Stump Grinder 106

    4 Concrete pouring and pumping Concrete Agi Truck 109 112

    Concrete Pump Truck 108

    5 Construction of Limestone Retaining Walls

    Excavator 107 107

    6 Deliveries of Sand, Subgrade and Fill Material

    Dump Truck 107 111

    Delivery Trucks (>20 Tonnes) 107

    Loader (Wheeled) 105

    7 Demolition Excavator 107 122

    Rock Breaker 118

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 10

    Task Work Activity Plant / Equipment Required

    dB Accumulative Sound Level (dB)

    Concrete Saw 117

    Water Cart 107

    Delivery trucks (>20 T) 107

    Concrete Agi Truck 109

    Smooth Drum Roller 108

    Profiling Machine 110

    Plate Compactor 108

    8 Drainage Installation and Backfilling

    Excavator 107 115

    Smooth Drum Roller 108

    Plate Compactor 108

    Concrete Agi Truck 109

    Delivery Trucks (>20 Tonnes) 107

    Loader (Wheeled) 105

    9 Dust Suppression Including Filling of Water Carts

    Generators 99 108

    Water Pump 99

    Water Cart 107

    10 Embankment Construction Grader 110 116

    Smooth Drum Roller 108

    Water Cart 107

    Dump Truck 107

    Loader (wheeled) 105

    Excavator 107

    Delivery trucks (>20 T) 107

    11 Extruded Concrete Barrier Installation

    Concrete Agi Trucks 109 109

    Extruded Barrier Machine 97

    12 Formwork installation Handtools (pneumatic) 116 117

    50T to 75T Hydraulic Crane 104

    Telehandler 106

    13 Foundation Preparation Grader 110 114

    Smooth Drum Roller 108

    Water Cart 107

    Excavator 107

    14 Gantry Installation All Terrain Crane/HiAb Truck 104 116

    Hand Tools (pneumatic) 116

    15 Hard Landscaping Concrete Agi Truck 109 116

    Plate Compactor 108

    Excavator 107

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 11

    Task Work Activity Plant / Equipment Required

    dB Accumulative Sound Level (dB)

    Auger (attachment) 106

    Bobcat/Pozitrack 104

    Loader (Wheeled) 105

    Delivery Trucks (>20 Tonnes) 107

    Water Cart 107

    Street Sweeper 96

    16 Haulage and Stockpiling Delivery Trucks (>20 Tonnes) 107 111

    Loader (Wheeled) 105

    Dump Truck 107

    17 Installation and Modification of Overhead Line Equipment

    Excavator 107 109

    50T Hydraulic Crane 104

    18 Kerbing Concrete Agi Truck 109 110

    Kerb Extrusion Machine 105

    Hand Tools (Manual) 82

    19 Light/Signal Pole Removal Excavator 107 110

    Hi-ab Truck 107

    20 Line Marking Linemarking Truck 107 117

    Water Blaster 116

    Hand Tools (Manual) 82

    21 Precast Panel and Beam Installation/ Construction of Noise Walls

    25T Franna / 750 T Hydraulic Crane

    104 104

    22 Profiling Asphalt Profiling Machine 110 112

    Prime Mover (Truck with Trailer)

    107

    23 Refuelling Service truck 107 107

    24 Seal and Asphalt Replacement Seal/Spray Truck 107 116

    Chip Truck 107

    Paver Truck 108

    Smooth Drum Roller 108

    Water Cart 107

    Profiling Machine 110

    Rubber Tyred Roller (Multi- tyred Roller)

    101

    Delivery Trucks (>20 Tonnes) 107

    25 Service Installation and Potholing Vacuum Excavation Truck 92 106

    Vacuum Excavation Trailer 93

    Light Vehicle 106

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 12

    Task Work Activity Plant / Equipment Required

    dB Accumulative Sound Level (dB)

    26 Signage Installation Excavator 107 115

    Auger (attachment) 106

    Loader (Wheeled) 105

    Concrete Agi Truck 109

    Delivery Trucks (>20 Tonnes) 107

    Loader (Wheeled) 105

    27 Subbase Installation Smooth Drum Roller 108 114

    Water Cart 107

    Rubber Tyred Roller (Multi- tyred Roller)

    101

    Excavator 107

    Loader (Wheeled) 105

    Delivery Trucks (>20 Tonnes) 107

    28 Subgrade Preparation Grader 110 114

    Smooth Drum Roller 108

    Water Cart 107

    Rubber Tyred Roller (Multi-tyred roller)

    101

    Excavator 107

    29 Traffic Safety Barrier Installation Post Driver 72 106

    Light Vehicle 106

    30 Trenching Works for Service Installation

    Excavator 107 119

    Loader (Wheeled) 105

    Skid Steer 85

    10 Wheel Tipper 20 Tonnes) 107

    Where multiple tasks are completed in an area simultaneously, the total sound levels per task shall be used to calculate the total sound levels for the area. Where penalties are applied to multiple tasks, they shall not be duplicated. Therefore, the total penalty cannot exceed 15dB as stated in Section 5.2 below.

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 13

    5.2 Intrusive Characteristics and Associated Penalties

    Intrusive or dominant noise characteristics namely; modulation, impulsiveness and tonality have the potential to impact on a receiver’s perception of sound. If noise emitted from any premises when received at any other premises cannot reasonably be free of intrusive characteristics, then a series of adjustments must be added to the emitted levels (measured or calculated) and the adjusted level must then be compared to the assigned level. These adjustments are detailed in Table 8.

    Table 8 - Table of Adjustments

    Adjustment where noise emission is not music. These adjustments are cumulative to a maximum of 15 dB.

    Where tonality is present Where modulation is present Where impulsiveness is present

    +5dB +5dB +10dB

    A total penalty of up to 15dB can be applied to any given sound with all or one of these characteristics.

    Where a task is expected to generate noise with any of the characteristics listed above, the relevant penalties will be applied to the overall sound level for the given task. The addition of the applicable penalties is identified in Table 9. Table 9 also provides a total sound calculation and the dissipation distances to achieve the various assigned noise levels (relevant to the appropriate Transport Factor).

    5.3 Sensitive Receivers

    Sound levels expected to be received at residential properties from construction activities shall be calculated using the formula LpA= LWA-20log10 x R - 8 (where R = distance in metres) in accordance with AS 2436-2010 (point source in a free field calculation). Dissipation of sound shall be calculated at a loss of 6dB for every doubling of distance. The total distance for sound to dissipate to the assigned sound levels for residential properties shall be used to identify all properties potentially impacted by the works.

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 14

    Table 9 – Calculated sound levels vs distance for sound to dissipate to assigned levels with and without penalties. The distance to dissipate is based on assigned levels with varying Transport Factors including no Transport Factor applied, +2dB (for minor roads) is applied and +6dB (for primary roads) is applied.

    Task

    Calculated Sound Level (dB)

    Sound Characteristics

    Total Sound from Works Including Penalties (dB)

    Total Sound Level with Penalties and 25dB Deduction

    applied (dB)

    Distance (m) to dissipate to the Assigned Noise Levels of:

    Distance (m) to dissipate to the Assigned Noise Levels of:

    (Table 7)

    Impulsiveness (I) (Without Penalties) (With Penalties)

    Tonality (T)

    Modulation (M) 35dB 37dB 41dB 35dB 37dB 41dB

    1 117 I 127 102 267 212 134 842 669 422

    2 116 I + M 131 106 238 189 118 1334 1060 669

    3 109 I + T + M 124 99 112 89 56 625 495 313

    4 112 N/A 112 97 150 117 75 N/A N/A N/A

    5 107 N/A 107 82 85 67 43 N/A N/A N/A

    6 111 M 116 91 134 106 67 238 189 119

    7 122 I + M 137 112 474 376 238 2661 2114 1334

    8 115 I + M 130 105 212 168 106 1189 945 596

    9 108 N/A 108 83 95 75 48 N/A N/A N/A

    10 116 I + M 131 106 238 189 118 1334 1060 669

    11 109 M 114 89 106 85 54 189 150 95

    12 117 I + T 132 107 267 212 134 1497 1189 750

    13 114 M 119 94 189 150 95 335 267 168

    14 116 I + T 131 106 238 189 119 1334 1060 669

    15 116 I 126 101 238 189 119 750 596 376

    16 111 M 116 91 134 106 67 238 189 119

    17 109 I + T + M 124 99 112 89 56 625 495 313

    18 110 M 115 90 119 95 60 212 168 106

    19 110 I + T 125 100 119 95 60 669 531 335

    20 117 M 122 97 267 212 134 474 376 238

    21 104 I + T 119 94 60 48 30 335 267 168

    22 112 M 117 92 150 119 75 267 212 134

    23 107 N/A 107 82 85 67 43 N/A N/A N/A

    24 116 M 121 96 238 189 118 422 335 212

    25 106 I + T 121 96 79 63 40 441 350 221

    26 115 I + M 130 105 212 168 106 1189 945 596

    27 114 I + M 129 104 191 152 96 1073 853 538

    28 114 M 119 94 189 150 95 335 267 168

    29 106 I + T 121 96 75 60 38 422 335 212

    30 119 I + T + M 134 109 317 252 159 1781 1415 893

    31 111 N/A 111 86 134 106 67 N/A N/A N/A

    32 118 I + T 133 108 189 150 95 1060 842 531

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 15

    6 VIBRATION AND SENSITIVE RECEIVERS

    AAA identifies that any vibration above 1 mm/s-1 peak particle velocity (PPV) received at a sensitive receiver has the potential to cause disturbance to the occupier during OOHW.

    Tasks that have potential to generate vibration above 1mm/s-1 include the following:

    • Task 2 – Base Course Installation • Task 7 – Demolition • Task 8 – Drainage Installation and Backfilling • Task 10 – Embankment Construction • Task 13 – Foundation Preparation • Task 24 – Seal and Asphalt Replacement • Task 27 – Subbase Installation • Task 28 – Subgrade Preparation • Task 30 – Trenching Works for Service Installation

    AAA shall manage works to minimise the impact of vibration on residential properties between non-standard construction hours by conducting vibration assessments of works, modelling the potential vibration, and monitoring.

    Plant and equipment that is most likely to generate vibration includes plate compactors, tracked plant, smooth drum rollers and pad-foot rollers. The rollers are expected to generate vibration that dissipates furthest from its source, and therefore shall be used to model expected vibration from works.

    Vibration data from previous onsite measurements have been used to calculate the distance required for vibration to dissipate to below 1mm/s. The dissipation curves for the smooth drum roller and the pad foot roller are provided in Appendix F.

    The distance required for the vibration to dissipate to beneath 1mm/s are provided in Table 10 for the various settings on the padfoot roller and the smooth drum roller.

    Table 10 – Vibration Dissipation Distances calculated from on-site trials

    Plant Setting Distance to dissipate beneath

    1mm/s (m)

    Smooth Drum Roller Low Vibration 70

    High Vibration N/A

    Padfoot Roller Low Vibration (20hz) 40

    Low Vibration (30hz) 40

    High Vibration (20hz) 37

    High Vibration (30hz) N/A

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 16

    7 APPROVALS PROCESS

    The approvals process described below applies to tasks included within this Plan only. If other significant works are planned to occur out of hours, a separate, more detailed plan will be prepared and submitted to MRWA and the City of Cockburn for approval.

    The approvals process is summarised in Appendix E.

    STEP 1

    •Engineer responsible for works to be undertaken will complete an Out of Hours Request form (Appendix C) and submit the completed form together with the required mapping files to the AAA Environmental Coordinator a minimum of 12 working days prior to works commencing.

    STEP 2

    •The AAA Environmental Coordinator will review the information provided to develop sound dissipation mapping and complete an Out of Hours Notification of Works form (Appendix A).

    •The completed form will then be provided to the AAA Community & Stakeholder Engagement Team (CSET) 10 working days prior to works.

    STEP 3

    •AAA CSET will develop a notification letter (example provided in Appendix D) for distribution to the impacted sensitive receivers (if required).

    • The Out of Hours Notification form and the notification letter will then be submitted to the City of Cockburn (Coc).

    STEP 4

    •The CoC will be asked to review the Out of Hours works application and provide any feedback before issuing approval at least 3 days prior to the proposed OOHW.

    •Upon receipt of CoC approval, the notification letter will be distributed no later than 48 hours prior to the commencement of works.

    •If CoC objects to the works being undertaken, AAA shall amend the plan (via addemdum) to address CoC concerns and re-submit the Out of Hours Notification form. Should this occur, the described process and timeframe for approval is reset unless otherwise agreed with CoC.

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 17

    8 CONTROLS AND MITIGATIONS MEASURES

    The construction works will be carried out in accordance with control of environmental noises practices set out in AS2436-2010 Guide to Noise Control on Construction, Maintenance and Demolition Sites. Controls to be implemented have been divided into three categories; management controls, source controls and path controls. All relevant controls are detailed in the following sections.

    8.1 Management Controls

    The noise mitigation management measures outlined in Table 11 will be implemented in order to reduce disturbance to nearby receivers during the project.

    Table 11 - Management Controls

    Action Required Applies Details

    Working hours Noise

    Vibration

    Construction activities are to be only undertaken between 7.00 am and 7.00 pm Monday to Saturday unless otherwise approved. Information regarding working hours is to be included in Project Induction and Pre Start Briefings, Toolbox Talks etc.

    Out of hours works Noise

    Vibration

    All requests for Out of Hours Works are to be assessed by the Environmental Coordinator using processes outlined in the CNVMP and COHNVMP.

    Respite periods Noise

    Vibration

    Restricting time when noisy and vibration intensive works are carried out. Works will be scheduled in order to reduce the impact of noise and vibration on sensitive receivers where practicable.

    Implement community consultation measures

    Noise

    Vibration

    • Periodic notification (monthly letterbox drop or equivalent)

    • Website • Project info line • Email distribution list • Community Based Forums

    Site inductions Noise

    Vibration

    All AAA employees, contractors and subcontractors are to receive an environmental induction. The induction must at least include:

    • All relevant project specific and standard noise and vibration mitigation measures

    • Relevant licence and approval conditions • Permissible hours of work • Any limitations on high noise generating activities • Location of nearest sensitive receivers • Construction employee parking areas • Designated loading/ unloading areas and processes • Site opening/closing times (including deliveries) • Environmental incident response processes

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 18

    Action Required Applies Details

    Behavioural practices Noise No swearing or unnecessary shouting or loud stereos/radios on site.

    No dropping of materials from height, throwing of metals items and slamming of doors.

    Monitoring Noise A monitoring program as specified in Section 8.4 is to be carried out for the duration of the works

    Cease work Noise

    Vibration

    In the event of exceedance of action targets, impacts can be controlled by ceasing the activity until received noise/vibration levels can be reduced to within acceptable levels.

    8.2 Source Controls

    The source noise mitigation measures outlined in Table 12 will be implemented in order to reduce the disturbance to nearby receivers during the project.

    Table 12 - Source controls

    Action Required Applies Details

    Equipment selection Noise All fixed plant at the work sites are to be selected to be as quiet as practicable and where required, fitted with silencers, acoustical enclosures and other noise attenuation measures.

    Equipment selection Vibration Quieter and less vibration emitting construction methods will be used where feasible and reasonable.

    Rental plant and equipment

    Noise The noise levels of plant and equipment items are to be considered in rental decisions.

    Maintenance of plant Noise

    Vibration

    Vehicle, plant and equipment maintenance schedules and lubrication will be maintained as per manufacturers’ specifications.

    Regular checks are to be undertaken to ensure all equipment and vehicles are in good working order and are operated correctly.

    Use and siting of plant

    Noise Simultaneous operation of noisy plant within discernible range of a sensitive receiver is to be avoided.

    The offset distance between noisy plant and adjacent sensitive receivers is to be maximised.

    Plant used intermittently to be throttled down or shut down when not in use.

    Noise-emitting plant to be directed away from sensitive receivers.

    Plant inspection Noise

    Vibration

    All plant and equipment is to be inspected for use on site to ensure it is compliant prior to use on site.

    Plan worksites and activities to minimise noise and vibration

    Noise

    Vibration

    Plan traffic flow, parking and loading / unloading areas to minimise reversing movements within the site.

    Prevent vehicles and plant queuing to access site.

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 19

    Action Required Applies Details

    Non-tonal reversing alarms

    Noise Non-tonal reversing beepers (or an equivalent mechanism) will be fitted and used on all construction vehicles and mobile plant used on site.

    Minimise disturbance arising from delivery of goods to construction sites

    Noise Loading and unloading of materials/deliveries is to occur as far as possible from sensitive receivers.

    Site access points and roads as far as possible away from sensitive receivers will be used.

    Dedicated loading/unloading areas to be shielded if close to sensitive receivers.

    Delivery vehicles to be fitted with straps rather than chains for unloading, wherever possible.

    Hand tools Noise As much as practical the use of hand tools such as grinders, impact wrenches, hammers etc. will be used in specifically designated areas as far as possible from sensitive receivers and preferably separated by a barrier. Metal on metal contact will be avoided where possible.

    8.3 Path Controls

    The noise mitigation path control outlined in Table 13 will be implemented in order to reduce the disturbance to the nearby receivers during the project.

    Table 13 - Path controls

    Action Required Applies Details

    Shield stationary noise sources such as pumps, compressors, fans etc.

    Noise Stationary noise sources will be enclosed or shielded whilst ensuring that the occupational health and safety of workers is maintained.

    Shield sensitive receivers from noisy activities

    Noise Use structures to shield residential receivers from noise such as site shed placement; fencing; erection of operational stage noise barriers (where practicable) and consideration of site topography when situating plant.

    Should a permanent acoustic barrier for operational noise control be erected consideration will be given to building it prior to the rest of the construction works (i.e. noise walls).

    Acoustic barriers Noise Erecting barriers on site at source where practical will be considered to reduce the impact of noise at receivers. AS2436 identifies the options for barriers to reduce noise emissions from construction sites.

    8.4 Monitoring

    8.4.1 Noise Monitoring

    Monitoring will be undertaken to assess the noise generated by AAA construction activities and will be carried out in accordance to the Environmental Protection (Noise) Regulations 1997. A number of monitoring

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 20

    stations will be established along the alignment in proximity to sensitive receptors. The AAA Team proposes to maintain up to seven (7) Casella C633C noise monitors. The locations of these monitors will likely be influenced by the location of works, particularly those undertaken out of hours.

    Noise monitors shall be set up to send alerts if the calculated maximum sound level (Table 9) is breached. Should an alert be received, the supervisor of the works shall be informed for suitable action to be taken. All data collected by the noise monitoring units will be reviewed regularly by a suitably qualified person to ensure the Project is not contributing to excessive / unnecessary levels of noise.

    8.4.2 Vibration Monitoring

    Vibration monitoring using Instantel’s MicroMate sensors shall be conducted continually during out of hours’ construction activities. Vibration monitoring will likely occur alongside noise monitoring. The location of these monitoring stations will be dependent upon the location of out of hours works and corresponding sensitive receivers. These monitors will have telemetry capabilities to enable notification should the set triggers be exceeded.

    If the set trigger levels are exceeded, the work activity at the time shall be investigated and if possible the method altered to remove the vibration generating tasks.

    Vibration trials may also be conducted prior to out of hours’ vibration-intensive activities that may have significant impact on receptors to gauge potential setback distances or start-up locations.

    All data collected by the vibration monitoring units will be reviewed regularly by a suitably qualified person to ensure the Project is not contributing to excessive / unnecessary levels of vibration.

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 21

    9 COMMUNITY NOTIFICATION

    The Community and Stakeholder Engagement Team will conduct designated night works updates prior to all out of hours works commencing. These resident notifications will be communicated to sensitive receivers via email. Sensitive receivers are identified as properties within 100m of the Project boundary. Email notifications will be sent at least 48 hours prior to the works commencing.

    In the case of excessively noisy works, where setback distances are greater than 200m (assuming a 37dB assigned level without penalties- see Table 9), residents receiving noise greater than the assigned level will receive notification via letter drop. This is applicable to Task 1, 7, 12, 20 and 30. This notification will be a hard copy of the electronic format provided via email to residents within 100m of the Project boundary. An example notification letter is provided in Appendix D.

    Should the City of Cockburn receive more than two complaints within 24 hours from a stakeholder, local community member or business, the notification range will be extended to that identified in Table 9 and additional resident notifications will be issued via letter drop.

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 22

    10 COMPLAINTS

    All complaints shall be handled in accordance with the AAA Community and Stakeholder Engagement Management Plan. Where a noise or vibration complaint is received, AAA shall respond to the complaint and notify MRWA within 24 hours of receipt of complaint. The complaint will also be recorded in the MRWA customer relationship management database, Connect (refer to Table 14 below regarding noise and vibration complaints and contingency actions).

    Stakeholders can contact the MRWA Customer Information Centre (CIC) on 138 138 with complaints. The CIC operates 24 hours a day. All complaints will be entered into Connect and be responded to by the AAA Community and Stakeholder Engagement Team (CSET).

    For complex or intrusive works, the contact phone number of the rostered site supervisor will be provided to the CIC if urgent information is required. All other enquiries and complaints will be handled via the process outlined above. Enquiries and complaints may also be received via the [email protected] address and directed to the AAA CSET via Connect.

    Should a complaint be received as a result of the out of hours works, the cause of the complaint and compliance with the predicted noise and/or vibration levels as defined within this plan shall be investigated. The methodology of works shall also be reviewed to determine any necessary corrective actions and to limit the potential for the works to cause further disturbance.

    Where a complaint is identified as being a direct result of a non-conformance or incident, the procedure outlined in Section 11 of this Plan will be followed to allow AAA to identify and amend existing procedures and implement appropriate actions.

    Potential contingencies include but are not limited to the actions outlined in Table 14. Where the contingency actions do not resolve the issue, MRWA are to be notified as per section 11.

    Table 14 – Noise and vibration complaint contingency actions

    Complaint Type Contingency Actions

    Noise complaint is received

    • Complaint received by CIC and recorded in Connect

    • AAA to investigate the source of the noise levels

    • Assess the location of monitoring equipment and the need for additional monitoring near origin of complaint

    • Respond to complaint and report to MRWA within 24 hours (and to CoC if 2 or more complaints are received)

    • Modify the methodology, employ controls i.e. screens, substitute the source of the noise, or stage the works at less disruptive hours of work

    Vibration complaint is received

    • Complaint received by CIC and recorded in Connect

    • AAA to investigate the source of the vibration levels

    • Assess the location of monitoring equipment

    • Respond to complaint and report to MRWA within 24 hours (and to CoC if 2 or more complaints are received)

    • Request vibration monitoring with the landowner at complaint origin

    • Modify the methodology, employ controls i.e. dampeners/buffers, substitute the source of the vibration i.e. higher hertz or smaller machinery, or stage the works at less disruptive hours of work

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 23

    11 NON-CONFORMANCE, INCIDENT AND CORRECTIVE ACTION

    Where monitoring confirms the predicted noise or vibration levels (as defined in Table 9 and Section 6) have been met, AAA shall investigate the cause of the exceedance. Where vibration limits are reached, AAA will complete a record of an incident on IMPACT, Laing O'Rourke’s Online Incident Investigation and Reporting Tool. The incident will also be reported through the MRWA electronic incident reporting system, EQSafe. If predicted noise levels are exceeded at a monitoring location this will be recorded as a non-conformance. Where confirmation is possible using additional monitoring as per Table 14 above or reasonably extrapolated to within a residential dwelling or business premise, the exceedance will be recorded as an incident.

    All contingency actions taken will be recorded in IMPACT (incidents) and the corrective action register (non-conformances).

    Incidents/complaints involving noise and vibration typically involve a complaint from the community, notification by a regulatory authority or non-compliance with an approval or licence condition. These and other typical noise and vibration incidents and appropriate responses are detailed in Table 15 below.

    Table 15 – Incident planning and response

    Situation Response Responsibility

    Works occurring outside standard work hours without approval or appropriate notification to community/ authorities

    Immediately cease work where safe to do so. Notify authorities required under licence/approval condition and enter details in compliance register as required.

    Undertake investigation of incident to determine corrective/preventative actions.

    Apply for approval if works are still required.

    AAA Construction Manager (CM), Environmental Coordinator (EC), Community and Stakeholder Engagement Manager (CSEM)

    Malfunction of equipment used for tasks causing excessive noise / vibration emissions

    Cease activities under direction of the EC and / or CM. Notify relevant staff, and organise use of appropriate equipment to complete task.

    CM

    EC

    Noise or vibration causing community complaint and/or exceedance of action level

    Investigate, identify and review the source of the noise and/or vibration levels

    Respond to the complaint and notify MRWA within 24 hours of receipt

    Record the complaint / incident in IMPACT and EQSafe

    Assess the location of monitoring equipment and potential for additional or specific monitoring requirements

    Modify the methodology, employ controls, or stage the works at less disruptive hours of work

    CSEM

    CM

    EC

    Vibration causing structural damage

    In the case where monitoring shows excessive vibration levels, cease activities causing vibration under direction of the CM. If appropriate, evacuate any occupants of buildings with due consideration to

    CM

    CSEM

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 24

    Situation Response Responsibility

    safety, and secure the area to prevent unauthorised access.

    Undertake a structural assessment and compare results with any previous condition survey. If any damage is associated with construction, implement rectification works or agree compensation.

    Noise causing disturbance for site workers

    Cease activities causing disturbance under direction of the CM. Conduct assessment of noise exposure in accordance with worksite Health and Safety Regulations. Implement buffer zones for hearing protection where necessary.

    CM

    WHS Manager

    In addition to the Project induction, information regarding noise and vibration compliance will be included in daily pre-starts and environmental Toolboxes to raise awareness and educate the Project team.

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 25

    12 REPORTING REQUIREMENTS

    Results from noise and vibration monitoring will be reviewed by AAA for compliance and, if required, analysed by a suitably qualified specialist. The results will be recorded and provided to MRWA (monthly) and City of Cockburn (upon request).

    The AAA Environmental Coordinator will conduct daily observations of noise and vibration monitoring and complete weekly environmental inspections on Project work areas to assess environmental site conditions, ensuring environmental controls are implemented and legislative requirements are adhered to.

  • ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 26

    APPENDIX A

    Out of Hours Work Notification Form

  • Out of Hours Works Notification Form Reference Number: OOHWNF_01

    1

    1. Works to be Undertaken:

    Task(s)1

    Task 1 ☐ Task 7 ☐ Task 13 ☐ Task 19 ☐

    Task 2 ☐ Task 8 ☐ Task 14 ☐ Task 20 ☐

    Task 3 ☐ Task 9 ☐ Task 15 ☐ Task 21 ☐

    Task 4 ☐ Task 10 ☐ Task 16 ☐ Task 22 ☐

    Task 5 ☐ Task 11 ☐ Task 17 ☐ Task 23 ☐

    Task 6 ☐ Task 12 ☐ Task 18 ☐ Task 24 ☐

    Task 25 ☐ Task 26 ☐ Task 27 ☐ Task 28 ☐

    Task 29 ☐ Task 30 ☐ Task 31 ☐ Task 32 ☐1Plant and task descriptions are provided in the COHNVMP and are attached to this notification form

    2. Planned program and duration of works

    Task(s) Hours of Work Target Period Start

    Target Period End

    Planned Duration of Works

    Notes:

    3. Cumulative Sound Levels from Task

    Task(s) Sound Levels Cumulative Sound Level (with penalties)

    Cumulative Sound Level (without penalties)

    4. Assigned Noise Levels

    Noise Level and Sound Dissipation from Task m / dB

    Distance to closest sensitive receiver

    Sound expected from works at closest sensitive receiver (with penalty)

    Sound expected from works at closest sensitive receiver (without penalty)

  • Out of Hours Works Notification Form Reference Number: OOHWNF_01

    2

    Noise Level and Sound Dissipation from Task m / dB

    Lowest Assigned Sound levels of Property to be impacted by works

    Distances required to dissipate to within assigned sound levels with penalty

    Distances required to dissipate to within assigned sound levels with penalty

    5. Reason why works are required to be undertaken out of hours

    6. Residential Notification Required

    Notification Requirement

    Yes ☐ See attached notification draft

    No ☐Justification as to why residential notification is not required to be provided

    Impacted Sensitive Receivers

    Affected residents are classed as those who will receive sound levels in excess of the assigned noise

    level.

  • APPENDIX B

    Transport Factors for Areas Surrounding Works

  • Transport Factors for Areas Surrounding Works

    Legend

    Meters

    18009000

    SCALE: 1:30,000

    Traffic Mapping

    Primary Road 100m Buffer 6dB

    Primary Road 450m Buffer 2dB

    Armadale Road to NorthLake Road Bridge Project

    Contract No. 237/16

    Revision: A

    Date: 28/10/19

    Drawn By: RW

  • APPENDIX C

    Out of Hours Request Form

  • Out of Hours Works Request Form Reference Number: OOHWRF_01

    1

    Normal hours of construction are Monday to Saturday 07:00 – 19:00 (excluding public holidays). Any

    works scheduled to occur outside of these hours need to be assessed and approved by MRWA and

    the LGA. Engineers are required to complete this form and provide it to the Project Environmental

    Coordinator at least 12 working days prior to the proposed out of hours works commencing.

    1. Tasks to be undertaken and their durations (refer to COHNVMP for standard list of tasks)

    Task(s) Hours of Work Target Period Start

    Target Period End

    Planned Duration of Works

    Notes:

    2. Tasks not included in the COHNVMP standard list

    If the works to be undertaken differ from the standard tasks outlined in the COHNVMP, please

    describe the works below and break into tasks. A list of plant that will be used and the

    corresponding Sound Power Levels is also required.

    Task Description

    Task Plant Required Number of Plant Sound Power Levels

    Notes:

    3. Reason why works cannot be completed within normal construction hours

    In order to obtain approval from the LGA, it must be reasonably necessary for the work to be done

    out of hours (e.g. worker or traffic safety).

  • Out of Hours Works Request Form Reference Number: OOHWRF_01

    2

    4. Location(s)

    Location(s) of work areas are to be provided to the Project’s Environmental Coordinator as either a

    .KMZ or .DWG file.

    File provided:

    KMZ ☐ DWG ☐

    All works are to be undertaken in accordance will the Armadale Access Alliance Construction Noise

    and Vibration Management Plan and the Consolidated Out of Hours Noise and Vibration

    Management Plan.

    Name:

    Signature: Date:

  • APPENDIX D

    Residential Notification Letter

  • Night works along Armadale Road

    The Armadale Road to North Lake Road Bridge project is a $237 million jointly funded Federal and State Government initiative being delivered by Main Roads Western Australia. Armadale Access Alliance (AAA), an alliance between Main Roads WA, Laing O’Rourke and BG&E will deliver the project. The project involves construction of a bridge over Kwinana Freeway that connects Armadale Road to North Lake Road, and construction of free flowing regional traffic lanes on Armadale Road through the Solomon Road and Tapper Road intersections. The project will address congestion at the Kwinana Freeway, Armadale Road and Beeliar Drive interchange, Perth’s fifth most congested intersection.

    What work is happening?

    We wish to notify you that we will soon start early work activities. This will include some night works to

    locate existing underground services and undertake geotechnical investigations.

    When will works take place?

    Night work will begin during the week commencing Monday 9 September and take approximately two weeks. The project team have approval to conduct work between 7pm and 6am, Monday to Friday during this period. Residents in the area may experience construction-related noise and as a result of works being undertaken.

    What will be done to reduce any impacts in the area?

    We wish to assure residents that all efforts will be taken to minimise impacts during the works. This includes ensuring quiet reverse alarms are used, lighting towers are positioned away from residential areas where possible, machinery is turned off when not in use and workers are respectful of residents nearby.

    Contact us

    If you have any questions or concerns, please phone 138 138 or email [email protected].

    More project information is also available at https://project.mainroads.wa.gov.au/home

    SEPTEMBER 2019

    Armadale Road to North Lake Road Bridge

    Construction update

  • APPENDIX E

    Timeline for Approvals

  • Step 1Engineer completes Out of Hours Works Request Form

    (Appendix C)

    -11 Days

    Step 4Community Team review provided information and if required,

    develop a residential notification letter

    Step 5 Notification Form is submitted to LGA for review

    -9 Days

    -8 Days

    -7 Days

    -6 Days

    -5 Days

    -4 Days

    -3 Days Step 6 LGA to provide response to AAA Community Team

    -2 Days Step 7Residents notified (if required) at least 2 days prior to works

    commencing

    -1 Day Step 8Noise and/or vibration monitoring equipment set up in

    appropriate locations with notifications enabled according to

    set trigger levels

    Not approvaed by LGA - timeline resets

    Approved by LGA

    Note: Days are minimum timeframes which must be met to ensure that

    approvals are received prior to the planned commencment of works

    Step 2

    -12 Days

    Environmental Coordinator uses information provided to

    populate Out of Hours Work Notification Form (Appendix A)

    -10 Days

    LGA to review Out of Hours Request Form

    Works Commence

    Rev

    iew

    Per

    iod

  • APPENDIX F

    Vibration Dissipation Distance

  • Vibration Dissipation Distances

    Legend

    Meters

    18009000

    SCALE: 1:30,000

    Project Footprint

    40m Vibration Buffer(Low vibration roller setting - 20hz)

    Armadale Road to NorthLake Road Bridge Project

    Contract No. 237/16

    Revision: A

    Date: 28/10/19

    Drawn By: RW

    ARNLR COHNVMP (003).pdfARNLR-AAA-MPL-0000-EN-0003.pdfARNLR COHNVMP (003).pdfARNLR-AAA-MPL-0000-EN-0003.pdfARNLR COHNVMP (002).pdfApproval Timeline.pdfARNLR - Transport Factors.pdfVibration Dissipation Distances Layout2 (1).pdfOut of Hours Notification Form.pdfOut of Hours Request Form.pdfExtractPage3