Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Armadale Road to North Lake Road Bridge Project
Consolidated Out of Hours Noise and Vibration Management Plan
Document details
Client Main Roads Western Australia (Main Roads)
Document Owner Armadale Access Alliance
Client Contract No. MRWA 237/16
Document Number ARNLR-AAA-MPL-0000-EN-0003
Revision 0
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page i
REVISION REGISTER
Rev Date Details Originator Reviewed Approved
0 11/11/2019 Issued for Review and Approval C. Ridley M. Bulmer A. Deurloo
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page ii
CONTENTS
1 PURPOSE 1
2 REFERENCES 2
3 ASSIGNED NOISE LEVELS 3
3.1 Influencing Factors 3
3.1.1 Influencing Factors – Land Zoning 3
3.1.2 Influencing Factors – Transport Factors 3
3.1.3 Influencing Factor calculation 4
3.2 Site Specific Assigned Noise Levels 5
4 SCOPE OF WORKS 6
4.1 Plant and Noise Sources 6
5 NOISE AND SENSITIVE RECIEVERS 9
5.1 Plant and Noise Generation 9
5.2 Intrusive Characteristics and Associated Penalties 13
5.3 Sensitive Receivers 13
6 VIBRATION AND SENSITIVE RECEIVERS 15
7 APPROVALS PROCESS 16
8 CONTROLS AND MITIGATIONS MEASURES 17
8.1 Management Controls 17
8.2 Source Controls 18
8.3 Path Controls 19
8.4 Monitoring 19
8.4.1 Noise Monitoring 19
8.4.2 Vibration Monitoring 20
9 COMMUNITY NOTIFICATION 21
10 COMPLAINTS 22
11 NON-CONFORMANCE, INCIDENT AND CORRECTIVE ACTION 23
12 REPORTING REQUIREMENTS 25
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page iii
Appendices
Appendix A Out of Hours Work Notification Form
Appendix B Transport Factors for Areas Surrounding Works
Appendix C Out of Hours Request Form
Appendix D Residential Notification Letter
Appendix E Timeline for Approvals
Appendix F Vibration Dissipation Distance
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page iv
Terms, Abbreviations and Definitions
Abbreviation Definition
AAA Armadale Access Alliance
Alliance The Alliance established to deliver the Project
ARNLR Armadale Road to North Lake Road Bride Project
CIC MRWA Customer Information Centre
CoC City of Cockburn
COHNVMP Consolidated Out of Hours Noise and Vibration Management Plan
CM Construction Manager
CNVMP Construction Noise and Vibration Management Plan
CSEM Community and Stakeholder Engagement Manager
CSET Community and Stakeholder Engagement Team
dB Decibel
DWER Department of Water and Environmental Regulation
EC Environmental Coordinator
EPA Environmental Protection Authority
EQSafe Main Roads Western Australia incident reporting portal
Hz Hertz
IMPACT LORA incident reporting portal
LGA Local Government Area
OOH Out-of-Hours
OOHW Out-of-Hours Works
PPV Peak Particle Velocity
Project Armadale Road to North Lake Road Bride Project, the Project
Main Roads Main Roads Western Australia
MRWA Main Roads Western Australia
RAP Representative Assessment Period
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 1
1 PURPOSE
This Consolidated Out of Hours Construction Noise and Vibration Management Plan (COHNVMP) has been produced to supplement Armadale Access Alliance’s (AAA) Environmental Management Plan (EMP) and the Construction Noise and Vibration Management Plan (CNVMP) for implementation by the Alliance throughout the Armadale Road to North Lake Road Bridge (ARNLR) Project.
The COHNVMP outlines AAA’s approach to the management of nuisance noise and vibration created from the Project. This Plan is an extension of the CNVMP and provides a detailed assessment of noise and vibration for works that are to be conducted outside of normal construction hours (i.e. between 1900 hours and 0700 hours). The COHNVMP has been developed with reference to the documents outlined in Section 2 below.
This is an overarching plan, applicable to a limited number of tasks which are expected to be regularly undertaken out-of-hours throughout the duration of the Project. The scope of works and associated tasks are outlined in Section 4 of this Plan. For works that are not covered within this Plan, or where significant changes are required, the normal Out-of-Hours Works (OOHW) approval process as described in the CNVMP must be followed. This includes a detailed assessment of noise levels, mapping of impacts, identification of sensitive receivers and submissions of approval request to Main Roads Western Australia (MRWA) and the Local Government Authority (LGA), the City of Cockburn.
This plan does not include the dates of any works to be undertaken. An ‘Out of Hours Works Notification Form’ shall be submitted to MRWA and the LGA which will set out the dates of works and the activities to be undertaken. A copy of the ‘Out of Hours Works Notification Form’ is provided in Appendix A.
This COHNVMP aims to satisfy the following objectives:
• Provide calculations for the assigned noise levels received by properties along the alignment • Identify expected noise (including sound penalties where required) generated by works using
sound power levels from plant and equipment • Where sound levels to be received by closest sensitive receivers exceed assigned levels, identify
and implement methods to decrease sound levels where possible • Minimise and manage noise generation from the project area during out of hours working • Mitigate potential impacts on the environmental values, and the health, amenity and welfare of
the community resulting from the OOHW • Ensure that noise generated from the construction works complies with the relevant statutory
requirements • Ensure that all reasonable and practical measures are undertaken during the works to minimise
noise and vibration emissions from site • Ensure that all works and activities within the scope are undertaken in a manner that will
minimise the noise and vibration impacts on sensitive receivers
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 2
2 REFERENCES
• Environmental Protection Act 1986 • Environmental Protection (Noise) Regulations 1997 • Environmental Protection Regulations 1987 • AS 2436-2010: Guide to noise control on construction, maintenance and demolition sites • AS 2670.2: Evaluation of Human Exposure to Whole Body Vibration • Environmental Protection Authority (EPA), 2007, EPA Guidance Statement No 8: Environmental
Noise (Draft). Environmental Protection Authority, Perth, WA • State Planning Policy 5.4: Road and Rail Transport Noise and Freight Considerations in Land Use
Planning (SPP 5.4) (Western Australian Planning Commission, 2009) • AAA Scope of Work and Technical Criteria • AAA Community and Stakeholder Engagement Management Plan (ARNLR-AAA-MPL-0000-CS-
0001).
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 3
3 ASSIGNED NOISE LEVELS
Assigned noise levels are the levels of noise allowed to be received at a premises at a particular time of the day. There are different assigned levels for noise sensitive, commercial and industrial premises. The assigned levels also depend on how close the noise sensitive premises are to industrial and commercial areas, and major and minor roads. These assigned noise levels always apply at the premises receiving the noise.
The assigned levels have been adopted on the Project as a noise target for construction works undertaken outside normal operating hours. The table of assigned levels, shown in Table 1 identifies three types of assigned levels: LAmax, LA1 and LA10.
Table 1 – Assigned noise levels
Type of premises receiving noise
Time of day Assigned Level (dB)
LA10 LA1 LAMAX
Noise sensitive premises 0700 to 1900 hours Monday to Saturday
45 + 55 + 65 +
0900 to 1900 hours Sunday and public holidays
40 + 50 + 65 +
1900 to 2200 hours all days 40 + 50 + 55 +
2200 hours on any day to 0700 hours Monday to Saturday and 0900 hours Sunday and public holidays
35 + 45 + 55 +
Commercial premises All hours 60 75 80
Industrial and utility premises All hours 65 80 90
+ = the addition of an influencing factor
3.1 Influencing Factors
As per Schedule 3 of the Environmental Protection (Noise) Regulations 1997, the assigned noise level that a sensitive receiver may be subject to can be modified by the surrounding land uses for the property. The influencing factor (IF) increases with the number of commercial and industrial premises in the vicinity of the receiver as well as the presence of major or minor roads. This is calculated by considering land use zoning and the volume of traffic that utilises the road infrastructure within 100m and 450m of the receiver.
3.1.1 Influencing Factors – Land Zoning
Influencing factors based on the surrounding land use within a set distance from the sensitive receiver are developed from local government zoning maps. Industrial and commercial land uses are likely to generate an increase in the volume of sound within a set area, and therefore any sensitive premises located within finite proximity to these areas are taken as being be more tolerant of higher volumes of sound. To calculate the influencing factor two concentric circles representing 100m and 450m radii are placed from the noise sensitive premises, any land within the circles that is classified as Type 1 land (industrial and utility) or Type 2 land (commercial) is calculated as a percentage of the full area of each circle. The percentage is then used to calculate the influencing factor to the nearest decibel.
3.1.2 Influencing Factors – Transport Factors
Sensitive premises that are located within a defined distance from a Primary Road (a road that takes in excess of 15000 vehicles per week day) or secondary road (a road that takes more than 6000 but less than 15000 vehicles per week day) are deemed to be influenced by transport. The transport factor can be a maximum of 6dB added to the influencing factor. The values to be added as transport factors are summarised in Table 2.
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 4
Table 2 – Influencing Factors for Primary and Secondary Roads
Encompassing Distance Primary Road
(15000+ vehicles per day)
Secondary Road
(6000 to 14999 vehicles per day)
100m 6dB 2dB
450m 2dB -
Transport factor assessment is provided in Table 3, with the affected properties provided in Appendix B.
Table 3 – Transport Factor Assessment
Nearby Roads Number of Vehicles Road Classification
Armadale Road (east of Kwinana Freeway)
45,268 Primary
North Lake Road 16,880 Primary
Kwinana Freeway (north bound, south of Berrigan Drive)
59,197 Primary
Kwinana Freeway (south bound, south of Berrigan Drive)
62,065 Primary
Kwinana Freeway (north bound, south of Armadale Road)
47,121 Primary
Kwinana Freeway (south bound, south of Armadale Road)
55,643 Primary
Berrigan Drive (east of Kwinana Freeway)
21,391 Primary
Berrigan Drive (west of Kwinana Freeway)
29,925 Primary
Beeliar Drive (west of Kwinana Freeway)
53,160 Primary
Midgegooroo Avenue 16,933 Primary
Ghostgum Ave No Data No Data
Verde Drive No Data No Data
Tapper Road No Data No Data
Solomon Road No Data No Data
Kentucky Court No Data No Data
Traffic data presented in Table 3 is based on the average number of vehicles recorded Monday to Friday between 2013 and 2019. This traffic count data was obtained from Main Roads Trafficmap website (https://trafficmap.mainroads.wa.gov.au/map).
3.1.3 Influencing Factor Calculation
Due to the limited area of the works impacted by industrial/commercial land zoning factors, AAA have opted not to utilise the influencing factor generated from land uses. Nearby industrial and commercial premises are also not expected to operate outside of normal construction hours. Transport Factors only shall be used to determine assigned noise levels for sensitive premises.
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 5
3.2 Site Specific Assigned Noise Levels
The assigned levels are statistical noise levels over a Representative Assessment Period (RAP); for this project the RAP 15 minutes has been chosen as an appropriate period for assessing noise from the project. The DWER Noise Regulations specify 15 minutes as the minimum assessment time and it is also the DWER’s preferred RAP for night time operations. As the sites will be operational for over 10% of the RAP, the LA10 statistical noise criteria is the relevant criteria for this project. The specific LA10 assigned levels for the predicted worst affected receivers (within 100m of the Project boundary) are outlined in Table 4. These assigned levels have been calculated by the addition of a Transport Factor. For simplicity, roads within 100m of the Project boundary have been identified and the periods have been split into day (0700 – 1900 Monday to Saturday and 0900 – 1900 Sundays and Public Holidays) evening (1900 – 2200 all days) and night (2200 – 0700 Monday to Saturday and 2200 - 0900 Sundays and Public Holidays).
Where a given task or set of works is calculated to exceed or significantly contribute to an exceedance of the assigned sound level for affected sensitive properties, AAA shall notify properties within 100m of the Project boundary relevant to the work area. A noise emission is generally understood to ‘significantly contribute’ to an exceedance if it is higher than a level which is 5.0 dBA below the assigned level at the point of reception.
Table 4 – Specific assigned noise levels
Construction Area Receiver Assigned level LA10 dB
Day Evening Night
Kwinana Freeway / Bridge
Residential: Muriel Court, Imlah Court, Verna Court, The Lakes Boulevard
N/A 46 41
Adjacent commercial N/A 66 66
Adjacent industrial N/A 71 71
Armadale Road Extension
Residential: Tylee Cove, Marie Court, Dreier Court, Hoult Mews, Mahogany Loop, Freshwater Drive, Veneta Circuit, Tapper Road, Ceadarleaf Entrance, Gutterridge Road
N/A 46 41
Adjacent commercial N/A 66 66
Adjacent industrial N/A 71 71
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 6
4 SCOPE OF WORKS
The ARNLR Project involves the construction of a bridge over the Kwinana Freeway connecting Armadale Road to North Lake Road and construction of free-flowing traffic lanes on Armadale Road through the Solomon Road and Tapper Road intersections. Full connectivity will be retained at the intersections of Solomon Road and Tapper Road through grade separated roundabouts.
This plan aims to identify all standard tasks required to occur out of hours and their corresponding noise levels. This will allow for a streamlined and standardised approach to the assessment of OOHW activities and the approvals process.
The standard tasks expected to be repeated throughout the duration of the ARNLR Project are detailed in Table 5 below.
Table 5 – List of standard tasks to be undertaken during the Project
Task
- Demolition- Clearing and arborist works - Foundation preparation - Embankment construction - Haulage and stockpiling - Deliveries of sand, subgrade and fill
material - Dust suppression including filling of water
carts - Under boring works for service installation - Trenching works for services installation - Trimming batters - Drainage installation and backfilling - Subgrade preparation
- Subbase installation- Base course installation - Seal and asphalt replacement - Profiling asphalt - Line marking - Kerbing - Hard landscaping - Steel and concrete traffic safety barrier
installation - Signage installation - Concrete pouring and pumping - Precast panel and beam installation - Light/signal pole removal - Gantry installation - Refuelling
4.1 Plant and Noise Sources
Plant required to complete the standard tasks outlined above are provided in Table 6. The sound generated from the normal use of an item of plant has been obtained from the plant specifications where available. Where plant specification does not include the sound power information, industry standard sound levels have been obtained from the Australian Standard 2436-2010 Appendix A. Where no standard sound levels are available, information has been sourced from onsite sound level monitoring of the plant.
Table 6 – Plant list and Sound Power Levels
Plant/Item Sound Power Level (dB)
Plant Specification
Industry Standard
In-Field Measurement
All Terrain Crane 25T 104 X
All Terrain Crane 500T 104 X
Auger 106 X
Bobcat/Positrack 104 X
Chainsaw 102 X
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 7
Plant/Item Sound Power Level (dB)
Plant Specification
Industry Standard
In-Field Measurement
Chip Truck 107 X
Compressor 109 X
Concrete Agi Truck 109 X
Concrete Pump Truck 108 X
Concrete Saw 117 X
Crawler Crane 400T 104 X
Delivery Trucks (>20 Tonnes) 107 X
Dozer 108 X
Dump Truck 107 X
Elevated Working Platform 105 X
Excavator 107 X
Extruded Barrier Machine 97 X
Franna 20T 104 X
Generators 99 X
Grader 110 X
Hand Tools (Electric) 102 X
Hand Tools (Manual) 82 X
Hand Tools (Pneumatic) 116 X
Hydraulic Crane 50T 104 X
Kerb extrusion machine 105 X
Light Vehicles 106 X
Lighting Towers 99 X
Linemarking Truck 107 X
Loader (Wheeled) 105 X
Pad Foot Roller 108 X
Paver Truck 108 X
Paver Truck 107 X
Plate compactor 108 X
Post Driver 72 X
Prime Mover (Truck with Trailer) 107 X
Profiling Machine 110 X
Rock Breaker (attachment) 118 X
Rough Terrain Crane 25T 104 X
Rubber Tyred Roller (Multi- tyred Roller)
101 X
Scraper 116 X
Screener 99 X
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 8
Plant/Item Sound Power Level (dB)
Plant Specification
Industry Standard
In-Field Measurement
Seal/Spray Truck 107 X
Self-Propelled Motorised Transporter
106 X
Service Truck 107 X
Skid Steer 85 X
Smooth Drum Roller 108 X
Stacker 99 X
Street Sweeper 96 X
Stump Grinder 106 X
Sucker Trucks 117 X
Telehandler 106 X
Tipper Truck 117 X
Vacuum Excavation Truck 92 X
Vacuum Excavation Trailer 93 X
Vermeer Directional Driller 106 X
Water Blaster 116 X
Water Cart 107 X
Water Pump 99 X
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 9
5 NOISE AND SENSITIVE RECIEVERS
5.1 Plant and Noise Generation
Construction activities often require multiple items of plant operating at the same time. The accumulation of sound power levels from multiple items of plant will result in a higher sound level than if one item was operating alone.
The plant described in Table 6 have been grouped according to the standard tasks required for the scope of works. In order to simplify calculations, assessments for all tasks have been calculated based on all plant operating simultaneously at the same location to provide a maximum sound level. However, this assumption will likely result in an overestimation of actual accumulative sound levels.
The calculation for the addition of various noise sources to be utilised is LTOT=10Log(10L1/10+10L2/ 10+10L3/10+………10Ln/10) where L1, L2, L3, Ln are individual noise sources.
The calculated sound levels generated from each task are provided in Table 7.
Table 7 – Accumulative Sound Levels
Task Work Activity Plant / Equipment Required
dB Accumulative Sound Level (dB)
1 Application of Anti-graffiti Paint Generators 99 117
Compressor 109
Handtools (pneumatic) 116
2 Base Course Installation Grader 110 116
Smooth Drum Roller 108
Water Cart 107
Rubber Tyred Roller (Multi- tyred Roller)
101
Excavator 107
Loader (Wheeled) 105
Delivery Trucks (>20 Tonnes) 107
3 Clearing and Arborist Works Elevated Working Platform 105 109
Chain Saw 102
Stump Grinder 106
4 Concrete pouring and pumping Concrete Agi Truck 109 112
Concrete Pump Truck 108
5 Construction of Limestone Retaining Walls
Excavator 107 107
6 Deliveries of Sand, Subgrade and Fill Material
Dump Truck 107 111
Delivery Trucks (>20 Tonnes) 107
Loader (Wheeled) 105
7 Demolition Excavator 107 122
Rock Breaker 118
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 10
Task Work Activity Plant / Equipment Required
dB Accumulative Sound Level (dB)
Concrete Saw 117
Water Cart 107
Delivery trucks (>20 T) 107
Concrete Agi Truck 109
Smooth Drum Roller 108
Profiling Machine 110
Plate Compactor 108
8 Drainage Installation and Backfilling
Excavator 107 115
Smooth Drum Roller 108
Plate Compactor 108
Concrete Agi Truck 109
Delivery Trucks (>20 Tonnes) 107
Loader (Wheeled) 105
9 Dust Suppression Including Filling of Water Carts
Generators 99 108
Water Pump 99
Water Cart 107
10 Embankment Construction Grader 110 116
Smooth Drum Roller 108
Water Cart 107
Dump Truck 107
Loader (wheeled) 105
Excavator 107
Delivery trucks (>20 T) 107
11 Extruded Concrete Barrier Installation
Concrete Agi Trucks 109 109
Extruded Barrier Machine 97
12 Formwork installation Handtools (pneumatic) 116 117
50T to 75T Hydraulic Crane 104
Telehandler 106
13 Foundation Preparation Grader 110 114
Smooth Drum Roller 108
Water Cart 107
Excavator 107
14 Gantry Installation All Terrain Crane/HiAb Truck 104 116
Hand Tools (pneumatic) 116
15 Hard Landscaping Concrete Agi Truck 109 116
Plate Compactor 108
Excavator 107
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 11
Task Work Activity Plant / Equipment Required
dB Accumulative Sound Level (dB)
Auger (attachment) 106
Bobcat/Pozitrack 104
Loader (Wheeled) 105
Delivery Trucks (>20 Tonnes) 107
Water Cart 107
Street Sweeper 96
16 Haulage and Stockpiling Delivery Trucks (>20 Tonnes) 107 111
Loader (Wheeled) 105
Dump Truck 107
17 Installation and Modification of Overhead Line Equipment
Excavator 107 109
50T Hydraulic Crane 104
18 Kerbing Concrete Agi Truck 109 110
Kerb Extrusion Machine 105
Hand Tools (Manual) 82
19 Light/Signal Pole Removal Excavator 107 110
Hi-ab Truck 107
20 Line Marking Linemarking Truck 107 117
Water Blaster 116
Hand Tools (Manual) 82
21 Precast Panel and Beam Installation/ Construction of Noise Walls
25T Franna / 750 T Hydraulic Crane
104 104
22 Profiling Asphalt Profiling Machine 110 112
Prime Mover (Truck with Trailer)
107
23 Refuelling Service truck 107 107
24 Seal and Asphalt Replacement Seal/Spray Truck 107 116
Chip Truck 107
Paver Truck 108
Smooth Drum Roller 108
Water Cart 107
Profiling Machine 110
Rubber Tyred Roller (Multi- tyred Roller)
101
Delivery Trucks (>20 Tonnes) 107
25 Service Installation and Potholing Vacuum Excavation Truck 92 106
Vacuum Excavation Trailer 93
Light Vehicle 106
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 12
Task Work Activity Plant / Equipment Required
dB Accumulative Sound Level (dB)
26 Signage Installation Excavator 107 115
Auger (attachment) 106
Loader (Wheeled) 105
Concrete Agi Truck 109
Delivery Trucks (>20 Tonnes) 107
Loader (Wheeled) 105
27 Subbase Installation Smooth Drum Roller 108 114
Water Cart 107
Rubber Tyred Roller (Multi- tyred Roller)
101
Excavator 107
Loader (Wheeled) 105
Delivery Trucks (>20 Tonnes) 107
28 Subgrade Preparation Grader 110 114
Smooth Drum Roller 108
Water Cart 107
Rubber Tyred Roller (Multi-tyred roller)
101
Excavator 107
29 Traffic Safety Barrier Installation Post Driver 72 106
Light Vehicle 106
30 Trenching Works for Service Installation
Excavator 107 119
Loader (Wheeled) 105
Skid Steer 85
10 Wheel Tipper 20 Tonnes) 107
Where multiple tasks are completed in an area simultaneously, the total sound levels per task shall be used to calculate the total sound levels for the area. Where penalties are applied to multiple tasks, they shall not be duplicated. Therefore, the total penalty cannot exceed 15dB as stated in Section 5.2 below.
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 13
5.2 Intrusive Characteristics and Associated Penalties
Intrusive or dominant noise characteristics namely; modulation, impulsiveness and tonality have the potential to impact on a receiver’s perception of sound. If noise emitted from any premises when received at any other premises cannot reasonably be free of intrusive characteristics, then a series of adjustments must be added to the emitted levels (measured or calculated) and the adjusted level must then be compared to the assigned level. These adjustments are detailed in Table 8.
Table 8 - Table of Adjustments
Adjustment where noise emission is not music. These adjustments are cumulative to a maximum of 15 dB.
Where tonality is present Where modulation is present Where impulsiveness is present
+5dB +5dB +10dB
A total penalty of up to 15dB can be applied to any given sound with all or one of these characteristics.
Where a task is expected to generate noise with any of the characteristics listed above, the relevant penalties will be applied to the overall sound level for the given task. The addition of the applicable penalties is identified in Table 9. Table 9 also provides a total sound calculation and the dissipation distances to achieve the various assigned noise levels (relevant to the appropriate Transport Factor).
5.3 Sensitive Receivers
Sound levels expected to be received at residential properties from construction activities shall be calculated using the formula LpA= LWA-20log10 x R - 8 (where R = distance in metres) in accordance with AS 2436-2010 (point source in a free field calculation). Dissipation of sound shall be calculated at a loss of 6dB for every doubling of distance. The total distance for sound to dissipate to the assigned sound levels for residential properties shall be used to identify all properties potentially impacted by the works.
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 14
Table 9 – Calculated sound levels vs distance for sound to dissipate to assigned levels with and without penalties. The distance to dissipate is based on assigned levels with varying Transport Factors including no Transport Factor applied, +2dB (for minor roads) is applied and +6dB (for primary roads) is applied.
Task
Calculated Sound Level (dB)
Sound Characteristics
Total Sound from Works Including Penalties (dB)
Total Sound Level with Penalties and 25dB Deduction
applied (dB)
Distance (m) to dissipate to the Assigned Noise Levels of:
Distance (m) to dissipate to the Assigned Noise Levels of:
(Table 7)
Impulsiveness (I) (Without Penalties) (With Penalties)
Tonality (T)
Modulation (M) 35dB 37dB 41dB 35dB 37dB 41dB
1 117 I 127 102 267 212 134 842 669 422
2 116 I + M 131 106 238 189 118 1334 1060 669
3 109 I + T + M 124 99 112 89 56 625 495 313
4 112 N/A 112 97 150 117 75 N/A N/A N/A
5 107 N/A 107 82 85 67 43 N/A N/A N/A
6 111 M 116 91 134 106 67 238 189 119
7 122 I + M 137 112 474 376 238 2661 2114 1334
8 115 I + M 130 105 212 168 106 1189 945 596
9 108 N/A 108 83 95 75 48 N/A N/A N/A
10 116 I + M 131 106 238 189 118 1334 1060 669
11 109 M 114 89 106 85 54 189 150 95
12 117 I + T 132 107 267 212 134 1497 1189 750
13 114 M 119 94 189 150 95 335 267 168
14 116 I + T 131 106 238 189 119 1334 1060 669
15 116 I 126 101 238 189 119 750 596 376
16 111 M 116 91 134 106 67 238 189 119
17 109 I + T + M 124 99 112 89 56 625 495 313
18 110 M 115 90 119 95 60 212 168 106
19 110 I + T 125 100 119 95 60 669 531 335
20 117 M 122 97 267 212 134 474 376 238
21 104 I + T 119 94 60 48 30 335 267 168
22 112 M 117 92 150 119 75 267 212 134
23 107 N/A 107 82 85 67 43 N/A N/A N/A
24 116 M 121 96 238 189 118 422 335 212
25 106 I + T 121 96 79 63 40 441 350 221
26 115 I + M 130 105 212 168 106 1189 945 596
27 114 I + M 129 104 191 152 96 1073 853 538
28 114 M 119 94 189 150 95 335 267 168
29 106 I + T 121 96 75 60 38 422 335 212
30 119 I + T + M 134 109 317 252 159 1781 1415 893
31 111 N/A 111 86 134 106 67 N/A N/A N/A
32 118 I + T 133 108 189 150 95 1060 842 531
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 15
6 VIBRATION AND SENSITIVE RECEIVERS
AAA identifies that any vibration above 1 mm/s-1 peak particle velocity (PPV) received at a sensitive receiver has the potential to cause disturbance to the occupier during OOHW.
Tasks that have potential to generate vibration above 1mm/s-1 include the following:
• Task 2 – Base Course Installation • Task 7 – Demolition • Task 8 – Drainage Installation and Backfilling • Task 10 – Embankment Construction • Task 13 – Foundation Preparation • Task 24 – Seal and Asphalt Replacement • Task 27 – Subbase Installation • Task 28 – Subgrade Preparation • Task 30 – Trenching Works for Service Installation
AAA shall manage works to minimise the impact of vibration on residential properties between non-standard construction hours by conducting vibration assessments of works, modelling the potential vibration, and monitoring.
Plant and equipment that is most likely to generate vibration includes plate compactors, tracked plant, smooth drum rollers and pad-foot rollers. The rollers are expected to generate vibration that dissipates furthest from its source, and therefore shall be used to model expected vibration from works.
Vibration data from previous onsite measurements have been used to calculate the distance required for vibration to dissipate to below 1mm/s. The dissipation curves for the smooth drum roller and the pad foot roller are provided in Appendix F.
The distance required for the vibration to dissipate to beneath 1mm/s are provided in Table 10 for the various settings on the padfoot roller and the smooth drum roller.
Table 10 – Vibration Dissipation Distances calculated from on-site trials
Plant Setting Distance to dissipate beneath
1mm/s (m)
Smooth Drum Roller Low Vibration 70
High Vibration N/A
Padfoot Roller Low Vibration (20hz) 40
Low Vibration (30hz) 40
High Vibration (20hz) 37
High Vibration (30hz) N/A
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 16
7 APPROVALS PROCESS
The approvals process described below applies to tasks included within this Plan only. If other significant works are planned to occur out of hours, a separate, more detailed plan will be prepared and submitted to MRWA and the City of Cockburn for approval.
The approvals process is summarised in Appendix E.
STEP 1
•Engineer responsible for works to be undertaken will complete an Out of Hours Request form (Appendix C) and submit the completed form together with the required mapping files to the AAA Environmental Coordinator a minimum of 12 working days prior to works commencing.
STEP 2
•The AAA Environmental Coordinator will review the information provided to develop sound dissipation mapping and complete an Out of Hours Notification of Works form (Appendix A).
•The completed form will then be provided to the AAA Community & Stakeholder Engagement Team (CSET) 10 working days prior to works.
STEP 3
•AAA CSET will develop a notification letter (example provided in Appendix D) for distribution to the impacted sensitive receivers (if required).
• The Out of Hours Notification form and the notification letter will then be submitted to the City of Cockburn (Coc).
STEP 4
•The CoC will be asked to review the Out of Hours works application and provide any feedback before issuing approval at least 3 days prior to the proposed OOHW.
•Upon receipt of CoC approval, the notification letter will be distributed no later than 48 hours prior to the commencement of works.
•If CoC objects to the works being undertaken, AAA shall amend the plan (via addemdum) to address CoC concerns and re-submit the Out of Hours Notification form. Should this occur, the described process and timeframe for approval is reset unless otherwise agreed with CoC.
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 17
8 CONTROLS AND MITIGATIONS MEASURES
The construction works will be carried out in accordance with control of environmental noises practices set out in AS2436-2010 Guide to Noise Control on Construction, Maintenance and Demolition Sites. Controls to be implemented have been divided into three categories; management controls, source controls and path controls. All relevant controls are detailed in the following sections.
8.1 Management Controls
The noise mitigation management measures outlined in Table 11 will be implemented in order to reduce disturbance to nearby receivers during the project.
Table 11 - Management Controls
Action Required Applies Details
Working hours Noise
Vibration
Construction activities are to be only undertaken between 7.00 am and 7.00 pm Monday to Saturday unless otherwise approved. Information regarding working hours is to be included in Project Induction and Pre Start Briefings, Toolbox Talks etc.
Out of hours works Noise
Vibration
All requests for Out of Hours Works are to be assessed by the Environmental Coordinator using processes outlined in the CNVMP and COHNVMP.
Respite periods Noise
Vibration
Restricting time when noisy and vibration intensive works are carried out. Works will be scheduled in order to reduce the impact of noise and vibration on sensitive receivers where practicable.
Implement community consultation measures
Noise
Vibration
• Periodic notification (monthly letterbox drop or equivalent)
• Website • Project info line • Email distribution list • Community Based Forums
Site inductions Noise
Vibration
All AAA employees, contractors and subcontractors are to receive an environmental induction. The induction must at least include:
• All relevant project specific and standard noise and vibration mitigation measures
• Relevant licence and approval conditions • Permissible hours of work • Any limitations on high noise generating activities • Location of nearest sensitive receivers • Construction employee parking areas • Designated loading/ unloading areas and processes • Site opening/closing times (including deliveries) • Environmental incident response processes
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 18
Action Required Applies Details
Behavioural practices Noise No swearing or unnecessary shouting or loud stereos/radios on site.
No dropping of materials from height, throwing of metals items and slamming of doors.
Monitoring Noise A monitoring program as specified in Section 8.4 is to be carried out for the duration of the works
Cease work Noise
Vibration
In the event of exceedance of action targets, impacts can be controlled by ceasing the activity until received noise/vibration levels can be reduced to within acceptable levels.
8.2 Source Controls
The source noise mitigation measures outlined in Table 12 will be implemented in order to reduce the disturbance to nearby receivers during the project.
Table 12 - Source controls
Action Required Applies Details
Equipment selection Noise All fixed plant at the work sites are to be selected to be as quiet as practicable and where required, fitted with silencers, acoustical enclosures and other noise attenuation measures.
Equipment selection Vibration Quieter and less vibration emitting construction methods will be used where feasible and reasonable.
Rental plant and equipment
Noise The noise levels of plant and equipment items are to be considered in rental decisions.
Maintenance of plant Noise
Vibration
Vehicle, plant and equipment maintenance schedules and lubrication will be maintained as per manufacturers’ specifications.
Regular checks are to be undertaken to ensure all equipment and vehicles are in good working order and are operated correctly.
Use and siting of plant
Noise Simultaneous operation of noisy plant within discernible range of a sensitive receiver is to be avoided.
The offset distance between noisy plant and adjacent sensitive receivers is to be maximised.
Plant used intermittently to be throttled down or shut down when not in use.
Noise-emitting plant to be directed away from sensitive receivers.
Plant inspection Noise
Vibration
All plant and equipment is to be inspected for use on site to ensure it is compliant prior to use on site.
Plan worksites and activities to minimise noise and vibration
Noise
Vibration
Plan traffic flow, parking and loading / unloading areas to minimise reversing movements within the site.
Prevent vehicles and plant queuing to access site.
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 19
Action Required Applies Details
Non-tonal reversing alarms
Noise Non-tonal reversing beepers (or an equivalent mechanism) will be fitted and used on all construction vehicles and mobile plant used on site.
Minimise disturbance arising from delivery of goods to construction sites
Noise Loading and unloading of materials/deliveries is to occur as far as possible from sensitive receivers.
Site access points and roads as far as possible away from sensitive receivers will be used.
Dedicated loading/unloading areas to be shielded if close to sensitive receivers.
Delivery vehicles to be fitted with straps rather than chains for unloading, wherever possible.
Hand tools Noise As much as practical the use of hand tools such as grinders, impact wrenches, hammers etc. will be used in specifically designated areas as far as possible from sensitive receivers and preferably separated by a barrier. Metal on metal contact will be avoided where possible.
8.3 Path Controls
The noise mitigation path control outlined in Table 13 will be implemented in order to reduce the disturbance to the nearby receivers during the project.
Table 13 - Path controls
Action Required Applies Details
Shield stationary noise sources such as pumps, compressors, fans etc.
Noise Stationary noise sources will be enclosed or shielded whilst ensuring that the occupational health and safety of workers is maintained.
Shield sensitive receivers from noisy activities
Noise Use structures to shield residential receivers from noise such as site shed placement; fencing; erection of operational stage noise barriers (where practicable) and consideration of site topography when situating plant.
Should a permanent acoustic barrier for operational noise control be erected consideration will be given to building it prior to the rest of the construction works (i.e. noise walls).
Acoustic barriers Noise Erecting barriers on site at source where practical will be considered to reduce the impact of noise at receivers. AS2436 identifies the options for barriers to reduce noise emissions from construction sites.
8.4 Monitoring
8.4.1 Noise Monitoring
Monitoring will be undertaken to assess the noise generated by AAA construction activities and will be carried out in accordance to the Environmental Protection (Noise) Regulations 1997. A number of monitoring
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 20
stations will be established along the alignment in proximity to sensitive receptors. The AAA Team proposes to maintain up to seven (7) Casella C633C noise monitors. The locations of these monitors will likely be influenced by the location of works, particularly those undertaken out of hours.
Noise monitors shall be set up to send alerts if the calculated maximum sound level (Table 9) is breached. Should an alert be received, the supervisor of the works shall be informed for suitable action to be taken. All data collected by the noise monitoring units will be reviewed regularly by a suitably qualified person to ensure the Project is not contributing to excessive / unnecessary levels of noise.
8.4.2 Vibration Monitoring
Vibration monitoring using Instantel’s MicroMate sensors shall be conducted continually during out of hours’ construction activities. Vibration monitoring will likely occur alongside noise monitoring. The location of these monitoring stations will be dependent upon the location of out of hours works and corresponding sensitive receivers. These monitors will have telemetry capabilities to enable notification should the set triggers be exceeded.
If the set trigger levels are exceeded, the work activity at the time shall be investigated and if possible the method altered to remove the vibration generating tasks.
Vibration trials may also be conducted prior to out of hours’ vibration-intensive activities that may have significant impact on receptors to gauge potential setback distances or start-up locations.
All data collected by the vibration monitoring units will be reviewed regularly by a suitably qualified person to ensure the Project is not contributing to excessive / unnecessary levels of vibration.
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 21
9 COMMUNITY NOTIFICATION
The Community and Stakeholder Engagement Team will conduct designated night works updates prior to all out of hours works commencing. These resident notifications will be communicated to sensitive receivers via email. Sensitive receivers are identified as properties within 100m of the Project boundary. Email notifications will be sent at least 48 hours prior to the works commencing.
In the case of excessively noisy works, where setback distances are greater than 200m (assuming a 37dB assigned level without penalties- see Table 9), residents receiving noise greater than the assigned level will receive notification via letter drop. This is applicable to Task 1, 7, 12, 20 and 30. This notification will be a hard copy of the electronic format provided via email to residents within 100m of the Project boundary. An example notification letter is provided in Appendix D.
Should the City of Cockburn receive more than two complaints within 24 hours from a stakeholder, local community member or business, the notification range will be extended to that identified in Table 9 and additional resident notifications will be issued via letter drop.
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 22
10 COMPLAINTS
All complaints shall be handled in accordance with the AAA Community and Stakeholder Engagement Management Plan. Where a noise or vibration complaint is received, AAA shall respond to the complaint and notify MRWA within 24 hours of receipt of complaint. The complaint will also be recorded in the MRWA customer relationship management database, Connect (refer to Table 14 below regarding noise and vibration complaints and contingency actions).
Stakeholders can contact the MRWA Customer Information Centre (CIC) on 138 138 with complaints. The CIC operates 24 hours a day. All complaints will be entered into Connect and be responded to by the AAA Community and Stakeholder Engagement Team (CSET).
For complex or intrusive works, the contact phone number of the rostered site supervisor will be provided to the CIC if urgent information is required. All other enquiries and complaints will be handled via the process outlined above. Enquiries and complaints may also be received via the [email protected] address and directed to the AAA CSET via Connect.
Should a complaint be received as a result of the out of hours works, the cause of the complaint and compliance with the predicted noise and/or vibration levels as defined within this plan shall be investigated. The methodology of works shall also be reviewed to determine any necessary corrective actions and to limit the potential for the works to cause further disturbance.
Where a complaint is identified as being a direct result of a non-conformance or incident, the procedure outlined in Section 11 of this Plan will be followed to allow AAA to identify and amend existing procedures and implement appropriate actions.
Potential contingencies include but are not limited to the actions outlined in Table 14. Where the contingency actions do not resolve the issue, MRWA are to be notified as per section 11.
Table 14 – Noise and vibration complaint contingency actions
Complaint Type Contingency Actions
Noise complaint is received
• Complaint received by CIC and recorded in Connect
• AAA to investigate the source of the noise levels
• Assess the location of monitoring equipment and the need for additional monitoring near origin of complaint
• Respond to complaint and report to MRWA within 24 hours (and to CoC if 2 or more complaints are received)
• Modify the methodology, employ controls i.e. screens, substitute the source of the noise, or stage the works at less disruptive hours of work
Vibration complaint is received
• Complaint received by CIC and recorded in Connect
• AAA to investigate the source of the vibration levels
• Assess the location of monitoring equipment
• Respond to complaint and report to MRWA within 24 hours (and to CoC if 2 or more complaints are received)
• Request vibration monitoring with the landowner at complaint origin
• Modify the methodology, employ controls i.e. dampeners/buffers, substitute the source of the vibration i.e. higher hertz or smaller machinery, or stage the works at less disruptive hours of work
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 23
11 NON-CONFORMANCE, INCIDENT AND CORRECTIVE ACTION
Where monitoring confirms the predicted noise or vibration levels (as defined in Table 9 and Section 6) have been met, AAA shall investigate the cause of the exceedance. Where vibration limits are reached, AAA will complete a record of an incident on IMPACT, Laing O'Rourke’s Online Incident Investigation and Reporting Tool. The incident will also be reported through the MRWA electronic incident reporting system, EQSafe. If predicted noise levels are exceeded at a monitoring location this will be recorded as a non-conformance. Where confirmation is possible using additional monitoring as per Table 14 above or reasonably extrapolated to within a residential dwelling or business premise, the exceedance will be recorded as an incident.
All contingency actions taken will be recorded in IMPACT (incidents) and the corrective action register (non-conformances).
Incidents/complaints involving noise and vibration typically involve a complaint from the community, notification by a regulatory authority or non-compliance with an approval or licence condition. These and other typical noise and vibration incidents and appropriate responses are detailed in Table 15 below.
Table 15 – Incident planning and response
Situation Response Responsibility
Works occurring outside standard work hours without approval or appropriate notification to community/ authorities
Immediately cease work where safe to do so. Notify authorities required under licence/approval condition and enter details in compliance register as required.
Undertake investigation of incident to determine corrective/preventative actions.
Apply for approval if works are still required.
AAA Construction Manager (CM), Environmental Coordinator (EC), Community and Stakeholder Engagement Manager (CSEM)
Malfunction of equipment used for tasks causing excessive noise / vibration emissions
Cease activities under direction of the EC and / or CM. Notify relevant staff, and organise use of appropriate equipment to complete task.
CM
EC
Noise or vibration causing community complaint and/or exceedance of action level
Investigate, identify and review the source of the noise and/or vibration levels
Respond to the complaint and notify MRWA within 24 hours of receipt
Record the complaint / incident in IMPACT and EQSafe
Assess the location of monitoring equipment and potential for additional or specific monitoring requirements
Modify the methodology, employ controls, or stage the works at less disruptive hours of work
CSEM
CM
EC
Vibration causing structural damage
In the case where monitoring shows excessive vibration levels, cease activities causing vibration under direction of the CM. If appropriate, evacuate any occupants of buildings with due consideration to
CM
CSEM
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 24
Situation Response Responsibility
safety, and secure the area to prevent unauthorised access.
Undertake a structural assessment and compare results with any previous condition survey. If any damage is associated with construction, implement rectification works or agree compensation.
Noise causing disturbance for site workers
Cease activities causing disturbance under direction of the CM. Conduct assessment of noise exposure in accordance with worksite Health and Safety Regulations. Implement buffer zones for hearing protection where necessary.
CM
WHS Manager
In addition to the Project induction, information regarding noise and vibration compliance will be included in daily pre-starts and environmental Toolboxes to raise awareness and educate the Project team.
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 25
12 REPORTING REQUIREMENTS
Results from noise and vibration monitoring will be reviewed by AAA for compliance and, if required, analysed by a suitably qualified specialist. The results will be recorded and provided to MRWA (monthly) and City of Cockburn (upon request).
The AAA Environmental Coordinator will conduct daily observations of noise and vibration monitoring and complete weekly environmental inspections on Project work areas to assess environmental site conditions, ensuring environmental controls are implemented and legislative requirements are adhered to.
ARMADALE ROAD TO NORTH LAKE ROAD BRIDGE PROJECT ARNLR-AAA-MPL-0000-EN-0003 / Rev 0 / Date 30/10/2019 / Page 26
APPENDIX A
Out of Hours Work Notification Form
Out of Hours Works Notification Form Reference Number: OOHWNF_01
1
1. Works to be Undertaken:
Task(s)1
Task 1 ☐ Task 7 ☐ Task 13 ☐ Task 19 ☐
Task 2 ☐ Task 8 ☐ Task 14 ☐ Task 20 ☐
Task 3 ☐ Task 9 ☐ Task 15 ☐ Task 21 ☐
Task 4 ☐ Task 10 ☐ Task 16 ☐ Task 22 ☐
Task 5 ☐ Task 11 ☐ Task 17 ☐ Task 23 ☐
Task 6 ☐ Task 12 ☐ Task 18 ☐ Task 24 ☐
Task 25 ☐ Task 26 ☐ Task 27 ☐ Task 28 ☐
Task 29 ☐ Task 30 ☐ Task 31 ☐ Task 32 ☐1Plant and task descriptions are provided in the COHNVMP and are attached to this notification form
2. Planned program and duration of works
Task(s) Hours of Work Target Period Start
Target Period End
Planned Duration of Works
Notes:
3. Cumulative Sound Levels from Task
Task(s) Sound Levels Cumulative Sound Level (with penalties)
Cumulative Sound Level (without penalties)
4. Assigned Noise Levels
Noise Level and Sound Dissipation from Task m / dB
Distance to closest sensitive receiver
Sound expected from works at closest sensitive receiver (with penalty)
Sound expected from works at closest sensitive receiver (without penalty)
Out of Hours Works Notification Form Reference Number: OOHWNF_01
2
Noise Level and Sound Dissipation from Task m / dB
Lowest Assigned Sound levels of Property to be impacted by works
Distances required to dissipate to within assigned sound levels with penalty
Distances required to dissipate to within assigned sound levels with penalty
5. Reason why works are required to be undertaken out of hours
6. Residential Notification Required
Notification Requirement
Yes ☐ See attached notification draft
No ☐Justification as to why residential notification is not required to be provided
Impacted Sensitive Receivers
Affected residents are classed as those who will receive sound levels in excess of the assigned noise
level.
APPENDIX B
Transport Factors for Areas Surrounding Works
Transport Factors for Areas Surrounding Works
Legend
Meters
18009000
SCALE: 1:30,000
Traffic Mapping
Primary Road 100m Buffer 6dB
Primary Road 450m Buffer 2dB
Armadale Road to NorthLake Road Bridge Project
Contract No. 237/16
Revision: A
Date: 28/10/19
Drawn By: RW
APPENDIX C
Out of Hours Request Form
Out of Hours Works Request Form Reference Number: OOHWRF_01
1
Normal hours of construction are Monday to Saturday 07:00 – 19:00 (excluding public holidays). Any
works scheduled to occur outside of these hours need to be assessed and approved by MRWA and
the LGA. Engineers are required to complete this form and provide it to the Project Environmental
Coordinator at least 12 working days prior to the proposed out of hours works commencing.
1. Tasks to be undertaken and their durations (refer to COHNVMP for standard list of tasks)
Task(s) Hours of Work Target Period Start
Target Period End
Planned Duration of Works
Notes:
2. Tasks not included in the COHNVMP standard list
If the works to be undertaken differ from the standard tasks outlined in the COHNVMP, please
describe the works below and break into tasks. A list of plant that will be used and the
corresponding Sound Power Levels is also required.
Task Description
Task Plant Required Number of Plant Sound Power Levels
Notes:
3. Reason why works cannot be completed within normal construction hours
In order to obtain approval from the LGA, it must be reasonably necessary for the work to be done
out of hours (e.g. worker or traffic safety).
Out of Hours Works Request Form Reference Number: OOHWRF_01
2
4. Location(s)
Location(s) of work areas are to be provided to the Project’s Environmental Coordinator as either a
.KMZ or .DWG file.
File provided:
KMZ ☐ DWG ☐
All works are to be undertaken in accordance will the Armadale Access Alliance Construction Noise
and Vibration Management Plan and the Consolidated Out of Hours Noise and Vibration
Management Plan.
Name:
Signature: Date:
APPENDIX D
Residential Notification Letter
Night works along Armadale Road
The Armadale Road to North Lake Road Bridge project is a $237 million jointly funded Federal and State Government initiative being delivered by Main Roads Western Australia. Armadale Access Alliance (AAA), an alliance between Main Roads WA, Laing O’Rourke and BG&E will deliver the project. The project involves construction of a bridge over Kwinana Freeway that connects Armadale Road to North Lake Road, and construction of free flowing regional traffic lanes on Armadale Road through the Solomon Road and Tapper Road intersections. The project will address congestion at the Kwinana Freeway, Armadale Road and Beeliar Drive interchange, Perth’s fifth most congested intersection.
What work is happening?
We wish to notify you that we will soon start early work activities. This will include some night works to
locate existing underground services and undertake geotechnical investigations.
When will works take place?
Night work will begin during the week commencing Monday 9 September and take approximately two weeks. The project team have approval to conduct work between 7pm and 6am, Monday to Friday during this period. Residents in the area may experience construction-related noise and as a result of works being undertaken.
What will be done to reduce any impacts in the area?
We wish to assure residents that all efforts will be taken to minimise impacts during the works. This includes ensuring quiet reverse alarms are used, lighting towers are positioned away from residential areas where possible, machinery is turned off when not in use and workers are respectful of residents nearby.
Contact us
If you have any questions or concerns, please phone 138 138 or email [email protected].
More project information is also available at https://project.mainroads.wa.gov.au/home
SEPTEMBER 2019
Armadale Road to North Lake Road Bridge
Construction update
APPENDIX E
Timeline for Approvals
Step 1Engineer completes Out of Hours Works Request Form
(Appendix C)
-11 Days
Step 4Community Team review provided information and if required,
develop a residential notification letter
Step 5 Notification Form is submitted to LGA for review
-9 Days
-8 Days
-7 Days
-6 Days
-5 Days
-4 Days
-3 Days Step 6 LGA to provide response to AAA Community Team
-2 Days Step 7Residents notified (if required) at least 2 days prior to works
commencing
-1 Day Step 8Noise and/or vibration monitoring equipment set up in
appropriate locations with notifications enabled according to
set trigger levels
Not approvaed by LGA - timeline resets
Approved by LGA
Note: Days are minimum timeframes which must be met to ensure that
approvals are received prior to the planned commencment of works
Step 2
-12 Days
Environmental Coordinator uses information provided to
populate Out of Hours Work Notification Form (Appendix A)
-10 Days
LGA to review Out of Hours Request Form
Works Commence
Rev
iew
Per
iod
APPENDIX F
Vibration Dissipation Distance
Vibration Dissipation Distances
Legend
Meters
18009000
SCALE: 1:30,000
Project Footprint
40m Vibration Buffer(Low vibration roller setting - 20hz)
Armadale Road to NorthLake Road Bridge Project
Contract No. 237/16
Revision: A
Date: 28/10/19
Drawn By: RW
ARNLR COHNVMP (003).pdfARNLR-AAA-MPL-0000-EN-0003.pdfARNLR COHNVMP (003).pdfARNLR-AAA-MPL-0000-EN-0003.pdfARNLR COHNVMP (002).pdfApproval Timeline.pdfARNLR - Transport Factors.pdfVibration Dissipation Distances Layout2 (1).pdfOut of Hours Notification Form.pdfOut of Hours Request Form.pdfExtractPage3