Upload
jam
View
27
Download
1
Tags:
Embed Size (px)
DESCRIPTION
Arklow - GEWE 3.6 MW Offshore Project Lessons Learned. John Stephens Global Development Manager GE Energy. Offshore Europe Americas Onshore. Installed MW. Global Offshore Update. A $ Multi-B industry over the next 10 years. Remarkable growth 15 – 20 % CAGR - PowerPoint PPT Presentation
Citation preview
Arklow - GEWE 3.6 MW Offshore ProjectLessons Learned
John Stephens
Global Development Manager
GE Energy
Global Offshore Update A $ Multi-B industry over the next 10 years. Remarkable growth 15 – 20 % CAGR Can be sited closer to urban populations Proximity of local grid connection to urban centers. Less turbulence and WTG Fatigue Higher capacity factors – 50% Cost of electricity approaching 6¢/kWh Favourable regulatory support.
Global Growth
US 2003 Installed <100 MW Planned >8 GW
Europe 2003 Installed base 260 MW Planned >11 GW.
Inst
alle
d M
W
Offshore Europe Americas
Onshore
Installed base for Wind Power
GE Wind Energy – Arklow ProjectSite Specifics
• 8.5 m/s wind speed at 73,5 m
• 10 km from shore
• 3.5 – 6.4 m water depth
• Breaking waves & high currents
• Dense sand & gravel
• Co-Development project of Airtricity & GE Wind Energy
Arklow Background 25.2 MW Demonstration project of GE Wind
Energy’s 3.6 MW Offshore Wind Turbine Generator
Project located 10 kms off the coast of Arklow, Ireland in the Irish Sea
7 x 3.6 MW WTGs constructed by GEWE in 2003 GEWE co-developed project with Irish Green
energy company, Airtricity GEWE has built and will own and operate turbines
for approximately 2 years, then transfer (BOOT)
During Ownership period GEWE will ensure acceptance of: Basic reliability of design Necessary operating hours to prove new
technology Warranty provisions and weather
exclusions adequate for financing Optimization of O&M – Cost effective and
safe
45 miles south of Dublin
Arklow Update
Asset Management team in place Develop World class O&M Document lessons learned and implement solutions
Completing evaluation of how to optimize access Completing comprehensive maintenance plan with major EHS focus Validating plan to jump to 4 MW Wind Turbine
All 7 Wind turbines Pre-Commissioned 3 Wind turbines commissioned & under final testing - expect to generate electricity by 8th March 2004 Remaining turbines 50% commissioned All undersea cabling connected & tested Land-based switch house commissioned Meteorological mast foundation and tower fully installed, monitoring & measurement equipment being installed
Arklow Lessons LearnedConstruction Complete detailed logistics planning early in
execution phase Complete geo-technical analysis early Develop design sufficiently to minimize changes Coordinate order placement w/ legal, accounting
& tax constraints Acknowledge EHS risk & convert to competitive
advantage Access…access…access
Contractual Partner with offshore contractors having skills
to take installation risk Engineering & Supply Chain must be
completed ahead of construction window Manage undersea cable like a separate project New major components should be managed in
a similar fashion to product NPI
Arklow EHSGrid Connection GEWE personnel closely liased with ESB to
ensure Arklow Safety Management system interfaced with local Electricity Grid safety boundary documents.
Leverage GE Safe Systems of Work from other GE Energy businesses to suite local legislative requirements
Environment & Safety Management Systems
GE’s global EHS systems recognized as world leaders.
Risk management approach from Corporate level through to a Site’s business plan.
Developing access systems to maximise availability and to suite local conditions.
All offshore personnel are required to attend the BOSIET course(Basic Offshore Survival).
Arklow – Objectives and Plans
Environment, Health & Safety GEWE will be a leader in the Offshore Wind
Industry for EHS programs Active involvement and assessment of all
activities from construction to access to O&M Established environmental monitoring and
reporting program
Operations & Maintenance (O&M) Using 2 year ownership period to develop
expertise Asset Management, Services & Engineering
organizations working closely to optimize
Arklow – Objectives and Plans
Availability Tiger Team Multi-discipline team formed to drive reliability Manage Arklow turbines with high availability objective Establishing remote monitoring of Arklow turbines through monitoring center in Germany Assess design and develop redundancy to allow long maintenance intervals. Long term goal is once per year
Access Evaluating options to optimize access methods considering EHS, availability impact and cost Recognize EHS risks and looking to set standards Looking to leverage best practices from other offshore industries
Thank you!