Power Plant & TransmissionSiting Summary

ACC Staff Presentation

October 30, 20019

Page 2: Arizona Corporation Commission Power Plant & Transmission Siting Summary ACC Staff Presentation October 30, 20019

10/30/01 ACC Siting Summary 2

A.R.S. §40-360-07.BACC Balance Test

Adequacy

Economics

Reliability

Public InterestPublic Interest

Environment

Ecology

Page 3: Arizona Corporation Commission Power Plant & Transmission Siting Summary ACC Staff Presentation October 30, 20019

10/30/01 ACC Siting Summary 3

House Bill 2040

Effective 8/9/01:

Power Plants shall file a plan with the Commission 90 days prior to filing an application for a CEC

Filed Power Plant plan is confidential

All Plans filed with the Commission must now be accompanied by a power flow and stability analysis report showing the effect on the current Arizona transmission system

Page 4: Arizona Corporation Commission Power Plant & Transmission Siting Summary ACC Staff Presentation October 30, 20019

10/30/01 ACC Siting Summary 4

GenerationAdequacy Determination

Existing Loads with Reserve Margins

Projected Loads with Reserve Margins

Replace Older, Less Efficient Plants

Competitive Margin

Ancillary Services

Page 5: Arizona Corporation Commission Power Plant & Transmission Siting Summary ACC Staff Presentation October 30, 20019

10/30/01 ACC Siting Summary 5

Proposed Plants in Arizona

TotalStatus 2001 2002 2003 2004 2005 2006 2007 MWs

Commercial Operation

1,830 - - - - - 1,830

Under Construction

- 2,370 3,365 - - 5,735

Regulatory Approval Received

- 450 1,040 1,605 825 620 530 5,070

Application Under Review

- 500 2,340 540 1,540 4,920

Application Filed

- - - 500 500 - 1,000

Announced - - 520 580 - - 2,720 3,820 Total MWs 1,830 3,320 7,265 3,225 2,865 620 3,250 22,375

Year

Page 6: Arizona Corporation Commission Power Plant & Transmission Siting Summary ACC Staff Presentation October 30, 20019

10/30/01 ACC Siting Summary 6

Water / Gas UsageAll Filed Power Plants

Year

No. Power Plants Units

Output (MW)

Water Usage

(Acre-ft/Yr)

Gas Usage (B Btu/Yr)

2001 11 1,830 12,843 110,986 2002 28 3,320 24,102 195,554 2003 40 6,745 39,773 408,223 2004 17 2,645 26,000 130,887 2005 28 2,865 17,500 189,437 2006 5 620 3,465 37,230 2007 3 530 3,325 33,830

132 18,555 127,008 1,106,147

Page 7: Arizona Corporation Commission Power Plant & Transmission Siting Summary ACC Staff Presentation October 30, 20019

New AZ Power Plants, Gas Supply BasinsAnd Pipelines

Approved Plants Pending Plants Future Plants

Page 8: Arizona Corporation Commission Power Plant & Transmission Siting Summary ACC Staff Presentation October 30, 20019

10/30/01 ACC Siting Summary 8Source: Presentation to East of California parties by El Paso Natural Gas Company on April 26, 2001

Page 9: Arizona Corporation Commission Power Plant & Transmission Siting Summary ACC Staff Presentation October 30, 20019

Projected Gas Consumption of New Electric Generation in Arizona

0

500

1000

1500

2000

2500

3000

MM

cf/d

ay

El Paso Southern System El Paso Northern System

Page 10: Arizona Corporation Commission Power Plant & Transmission Siting Summary ACC Staff Presentation October 30, 20019

10/30/01 ACC Siting Summary 10

Staff Proposed Measures of Adequacy & Security

There should be sufficient transmission import capacity to reliably serve all loads in a utility’s service area without limiting access to more economical or less polluting remote generation

New power plants must have sufficient interconnected transmission capacity to reliably deliver its full output without use of remedial action schemes or displacing apriori generation at the same interconnection for single contingency (N-1) outages

Page 11: Arizona Corporation Commission Power Plant & Transmission Siting Summary ACC Staff Presentation October 30, 20019

10/30/01 ACC Siting Summary 11

Arizona EHV TransmissionSan Juan

NavajoGlenCanyon

North Gila

PaloVerde

SilverKingKyreneLiberty

South

Saguaro

Vail

Greenlee

ChollaMohave

MeadFour Corners

Springerville

McKinley

Tortolita

Phoenix

Tucson

Yuma

Westwing Coronado

PinnaclePeak

Transmission ImportConstrained Areas

Page 12: Arizona Corporation Commission Power Plant & Transmission Siting Summary ACC Staff Presentation October 30, 20019

10/30/01 ACC Siting Summary 12

Comparison of Proposed Generation &Transmission

Generation Transmission DifferenceStatus MWs MWs MWs

Commercial Operation

1,830 - 1,830

Under Construction 5,735 - 5,735 Regulatory Approval

Received5,070 - 5,070

Application Under Review (1)

4,920 1,950 2,970

Application Filed 1,000 1,000 Announced (2) 3,820 2,850 970

Total MWs 22,375 4,800 17,575

(1) Palo Verde to Southwest Valley & South Sub to Nogales(2) PNM's Palo Verde to Mexico & NRG's Palo Verde to Yuma West & SRP's Palo Verde to Souteast Valley

Page 13: Arizona Corporation Commission Power Plant & Transmission Siting Summary ACC Staff Presentation October 30, 20019

10/30/01 ACC Siting Summary 13

When is Enough ENOUGH?

Water Resources Over Utilized

Gas Supply or Delivery Capability Exceeded

Transmission System Deliverability Exceeded

Market Saturated

Page 14: Arizona Corporation Commission Power Plant & Transmission Siting Summary ACC Staff Presentation October 30, 20019

10/30/01 ACC Siting Summary 14

Questions ?