SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 CLIENT:
ALL SHEET
1 of 21
PROJECT: ALL -
AREA: GENERAL -
SBS
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
INDEX OF REVISIONS
REV. DESCRIPTION AND/OR ALTERED SHEETS
0 A B
C
Original Issue General Revision
Altered items 4.26, 8.1.1; 8.2.1.1 d); 8.2.2; 8.3.1 a) b) d); 8.3.3; 8.3.6; 9.1.3; 9.4.2; 9.6; 9.6.1; 9.6.4 d); 10.1 a); 11.2.4; 12.1.1; 12.2; 14.5.2.1 Removed items 6.2; 6.2.1, 8.2.1.1 e); 8.3.1 e); 11.2.4.2; 11.2.4.2 Included items 11.2.5; 11.3.2; ANNEX II II.6 Removed items 3.9; 4,5; 4.6; 6.1 NOTE; 6.1.3; 7.2; 7.2.1; 7.2.2; 7.2.3; 9.1.2 g); 9.2.2; 9.4.2; 9.6.4 NOTE; 13; 14.5.3; Altered items 2.2; 4.13; 6.1.1; 6.1.2; 7.1; 8.2.1.1 a) e d); 9.1.3; 9.2; 9.2.1; 9.4.1; 9.6.1; 9.6.2; 10.1 c) f); 11.3.5; Included items: 7.1.1; 7.1.1.1; 9.1.2.g) h) i) j); 9.1.3.1; 9.2.4; 10.1 NOTE 2; 13.5.3; ANNEX III; ANNEX IV.
REV. 0 REV. A REV. B REV. C REV. D REV. E REV. F
DATE 12/12/2018 29/03/2019 05/08/2019 26/05/2020
PROJECT QB QB QB GQB
EXECUTION CSM5 EM1E RNIU
CTNR CTMV CSM5 EM1E RNIU
CTNR CTMV A50O RNIU CTNR
MF84 UT6E
A50O CTNR BEJZ UT6E ES29 RC9D CQJ4 UPKG MF84
VERIFICATION UTE9 UTJ6 TW9O
SMS8 CTM5 UTE9 UTJ6 TW9O
SMS8 CTM5 TW9O UTE9 UTJ6 TW9O UTJ6
APPROVAL CXX6 CXX6 CXX6 CXX6
INFORMATION IN THIS DOCUMENT IS PROPERTY OF PETROBRAS, IT IS PROHIBITED TO USE OUT OF THIS PURPOSE.
THIS FORMULARY BELONGS TO PETROBRAS N-381 REV. L. 1
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
2 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
INDEX
1. PURPOSE 3
2. SCOPE 3
3. REFERENCES 3
4. DEFINITIONS, TERMINOLOGIES AND ACRONYMS 4
5. HIERARCHY OF DOCUMENTS 7
6. PERSONNEL QUALIFICATION AND CERTIFICATION 8
7. METROLOGY 8
8. MANUFACTURING INSPECTION 8
9. MANUFACTURING INSPECTION PLANNING 11
11. MANUFACTURING INSPECTION EXECUTION 15
12. RECORDS OF MANUFACTURING INSPECTION 17
13. QUALITY AUDIT 18
ANNEX I – GUIDELINE FOR ITP PREPARATION
ANNEX II – GUIDELINE FOR ISSUANCE OF MANUFACTURING INSPECTION RECORDS
ANNEX III – IMPARTIALITY AND INDEPENDENCE TERM
ANNEX IV – MODELS
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
3 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
1. PURPOSE
This Technical Specification aims to establish the minimum quality requirements to
be met in the supply of materials to PETROBRAS.
2. SCOPE
2.1. This document applies to the corporate materials of the Critical and Strategic
segments purchased directly by PETROBRAS, according to the USER GUIDE –
QUALITY REQUIREMENTS.
2.2. This document may be supplemented by Complementary Quality Requirement
to this technical specification.
NOTE 1: The USER GUIDE – QUALITY REQUIREMENTS is available for
consultation on the Petronect portal (www.petronect.com.br).
NOTE 2: The Complementary Quality Requirement applicable to each family of
material shall be consulted on the Petronect portal.
NOTE 3: The communication with PETROBRAS Quality of Materials Department
shall be via e-mail [email protected].
3. REFERENCES
3.1. ISO 9001 - Quality Management Systems – Requirements;
3.2. ISO 9712 - Non-Destructive Testing - Qualification and Certification of NDT
Personnel;
3.3. ABNT NBR 14842 - Criteria for the Qualification and Certification of Welding
Inspectors;
3.4. ABNT NBR 15218 - Criteria for Qualification and Certification of Industrial Paint
Inspectors;
3.5. ABNT NBR 15523 - Qualification and Certification of Inspector of Dimensional
Control;
3.6. ABNT NBR 15827 – Industrial valves for installation of exploration, production,
refining and transport of petrol production – Requirements for design and prototype
test;
3.7. ABNT NBR 16278 - Manufacturing Inspection - Personnel Qualification and
Certification for the Oil and Gas Sector;
3.8. ISO/IEC 17020 - Conformity Assessment - Requirements for the Operation of
Various Types of Bodies Performing Inspection;
3.9. ISO/IEC 17025 - General Requirements for the Competence of Testing and
Calibration Laboratories;
3.10. I-ET-0000.00-0000-970-PSQ-001 – Procedure and Personnel Qualification
and Certification.
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
4 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
NOTE 1: The edition/revision of the documents applicable to the PROJECT will be
that defined in the contractual documentation, if not specified, the current
edition/revision on the date of signature of the contract applies.
NOTE 2: PETROBRAS standards referenced above are available on PETROBRAS
website (www.petrobras.com.br / Business Channels / Supplier Channel / Technical
Standards).
NOTE 3: PETROBRAS technical specifications referenced above are available on
PETROBRAS website (www.petrobras.com.br / Business Channels / Supplier
Channel / Technical Specifications).
4. DEFINITIONS, TERMINOLOGIES AND ACRONYMS
The definitions adopted in this document are presented in ABNT NBR 16278. In
addition, the following terms are used in this document:
4.1. Document Approval – AD (Aprovação Documental)
Event in the manufacturing cycle where document approval (procedure) is required by
the Responsible for Manufacturing Inspection before the Execution of the respective
activity.
4.2. API
American Petroleum Institute.
4.3. API Source Inspector – API SI
Manufacturing Inspector certified by API.
4.4. Corporate Material
The materials used in PETROBRAS industrial process, whose failure or lack may
endanger the safety of people, facilities and/or the environment, influence the
operational performance and/or compromise the quality of PETROBRAS final product.
Corporate materials shall have Manufacturing Inspection.
4.5. Occurrence of Divergence Notice – COD (Comunicado de Ocorrência de
Divergência)
Record of technical or commercial divergences between the Supplier and
PETROBRAS, with the consequent notification of technical problems or poor
performance to the Supplier, based on the quality tools and the International Standard
of Quality ISO 9001. The main objectives of COD are eliminate such divergences and
prevent their recurrence. However, if the Supplier does not take the necessary
actions, it may result in the application of Administrative Sanction or Technical
Disqualification.
4.6. Untreated Technical COD
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
5 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
Occurrence of Divergence Notice without corrective action plan approved by
PETROBRAS.
4.7. Purchasing Company
Company that buys the material.
4.8. ET (Especificação Técnica)
Technical Specification
4.9. Family of Materials
A set of similar materials, which by their size, manufacturing process and technology
involved in their production, are manufactured and/or marketed by a certain set of
Suppliers.
4.10. Supplier
It is the company that will provide the material directly to PETROBRAS, according to
the Contractual Instrument.
4.11. Contract Manager
Employee of PETROBRAS, responsible for all contractual subjects.
4.12. International Association of Classification Societies – IACS
The International Association of Classification Societies’ (IACS) is a technically based
non-governmental organization.
4.13. Supplier Quality Indicator – IQF (Índice de Qualidade do Fornecedor)
Value, between 0 and 100%, resulting from the Supplier's performance after
PETROBRAS quality audit. This indicator is related to the family of material and the
audited plant.
4.14. Critical Item
A component, part of the scope of supply, which failure may cause interruption of
operation, damage to the environment or impairment to the safety of persons and
facilities, as defined by the Supplier Quality System or Design Standard.
4.15. Lot
Set of units of the same batch and the same product machining set-up (when
applicable) to be inspected to verify the compliance with acceptance requirements.
4.16. Monitoring Point (MP)
Follow-up of a continuous manufacturing or inspection process in the Supplier's
manufacturing cycle where there is no need to notify the Responsible of Inspector of
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
6 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
Manufacturing, who may witness it as often as it deems necessary in order to verify its
Execution in compliance with contractual procedures and requirements.
4.17. Accredited Inspection Body - AIB
Third party company accredited according to ISO 17020 Type A to provide
Manufacturing Inspection service.
4.18. Organization
Corporation involved in the supply chain of the material or service scope of the
contract and subject to contractual requirements, either as Supplier or Subsupplier.
4.19. Audit Body
PETROBRAS Quality of Material Department formally designated to perform the
quality audit of materials and the inspection service.
4.20. Purchase Order (PC – Pedido de Compras)
Document issued to supply materials and services associated with values, terms and
conditions.
4.21. Corrective Action Plan
A Plan elaborated by the Supplier, reporting the corrective actions related to
identification of the root cause of a nonconformity, to be implemented in its Quality
Management System.
4.22. Special Process
Process in which the conformity of the final product cannot be readily or economically
verified, e.g. welding, forging, casting etc.
4.23. Technical Qualification
Documental and/or presential technical evaluation process of a Supplier of materials
or services based on a set of requirements and indicators, aiming to demonstrate its
manufacturing and technical capacity, tradition of supply and eventual approvals and
certifications specific to a particular service or object evaluation.
4.24. Nonconformity Report – NCR (RNC - Relatório de Não Conformidade)
Inspection record issued by the Quality System of the Organization according to the
precepts of ISO 9001.
4.25. Informative Report - Registration of Nonconformity – IR-NCR (RI-RNC -
Relatório de Inspeção – Relatório de Não Conformidade)
Inspection record issued by the Responsible for Manufacturing Inspection to report
any deviation from the contractual requirements observed during the manufacturing
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
7 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
process not identified by the Supplier Quality Control. Shall be issued for rejection of
intermediate inspection events.
NOTE: This inspection record does not follow the provisions of ISO 9001. The
treatment of nonconformity shall be provided by the Organization to respond to the
contractor according to the Quality System implemented.
4.26. Complementary Quality Requirement
Document issued by PETROBRAS that complements and overlaps this General
Quality Requirement for the families of materials specified therein.
NOTE: Families of Materials and their Complementary Requirements are available
on the Petronect Portal.
4.27. Responsible for Manufacturing Inspection – RIF (Responsável pela
Inspeção de Fabricação)
Individual or legal entity designated and trained to coordinate, plan and execute the
Manufacturing Inspection.
For Suppliers required to hire an Inspection Body, RIF is the actual contracted
Inspection Body.
If the Supplier is dispensed from hiring the Inspection Body, the RIF function is
normally assigned to the Supplier's quality sector.
4.28. Material Requisition – RM (Requisição de Material)
PETROBRAS document describing the scope of supply.
4.29. Manufacturing Inspection Service
Service provided by Accredited Inspection Body in the Execution of Manufacturing
Inspection activities.
4.30. Subsupplier
It is the company chosen and qualified by the Supplier to provide the material or
components of the materials and/or services.
5. HIERARCHY OF DOCUMENTS
When not specified in contract, the documents follow the hierarchy below in
decrescent order:
1. Material Requisition (RM), Technical Specifications (ET), Data Sheet (FD),
Drawings (DE), Circular Letters, Technical Norms and other documents of the
bidding process;
2. Complementary Quality Requirements;
3. Materials Quality General Requirement.
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
8 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
In case of conflict among requirements of contractual documents, the Supplier shall
issue a request for clarification to PETROBRAS Contract Manager.
6. PERSONNEL QUALIFICATION AND CERTIFICATION
6.1. Certification of Inspectors (Not Mandatory)
6.1.1. The activities of Welding, Dimensional Control, Non-Destructive Testing and
Painting should be inspected by certified personnel by the National System of
Qualification and Certification of Personnel (SNQC), in compliance with the
Qualification and Certification Regulations listed below:
a) Welding Inspection: ABNT NBR 14842;
b) Inspection of Dimensional Control: ABNT NBR 15523;
c) Inspection by Non-Destructive Testing: ABNT NBR NM ISO 9712;
d) Painting Inspection: ABNT NBR 15218.
6.1.2. For Suppliers abroad, I-ET-0000.00-0000-970-PSQ-001 presents
certifications equivalent to describe in 6.1.1.
7. METROLOGY
7.1. The calibration of the test and measurement instruments used should be carried
out in laboratories accredited according to ISO/IEC 17025, in accordance with the
scope of the calibration service performed or using the standard traceable to
International Laboratory Calibration Network that participates in programs of
recognition of competence.
7.1.1.1. The instruments used can be calibrated in non-accredited laboratories (internal and external), if these laboratories have in accordance with the traceable standard to the Brazilian Calibration Network or accreditation systems in the origin country.
7.1.1.2. When non-accredited laboratories according by ABNT NBR ISO / IEC 17025 are used, the procedures must fully comply with the applicable standards to the performance of tests and / or calibration.
8. MANUFACTURING INSPECTION
8.1. General
8.1.1. The Supplier shall contract the a AIB, except when it is not required to contract
under item 8.3, in which case the Supplier shall maintain a RIF to perform and record
all required Manufacturing Inspection activities.
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
9 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
NOTE: Supplier assigned as Reseller or Distributor, the AIB may be contracted by
Manufacturer.
8.1.1.1. The AIB or RIF, as applicable, is responsible for the release of the
material, through the issuance/approval of the CLM (Comunicado de
Liberação de Material), which is equivalent to the MRN (Material Release
Notice). In case of rejection, a Rejection Notice, CRM (Comunicado de
Rejeição de Material), shall be issued. MRN will not be subject of approval by
PETROBRAS Quality of Materials Department.
8.1.2. The hiring of the Inspection Service does not release the responsibility of the
Supplier for the quality of the materials supplied, including items purchased from
Subsuppliers.
8.1.3. The responsibility for the Planning and Execution of the Manufacturing
Inspection is always attributed to an AIB, except when provided in item 8.3, that AIB
can be replaced by RIF.
8.1.4. The Supplier is responsible for transmitting all contractual technical
specifications to the Responsible for Manufacturing Inspection to perform the
necessary verifications in order to attest the conformity of the materials provided to
the one established in the contractual instrument.
8.1.5. This Materials Quality General Requirement and the Complementary Quality
Requirement, when applicable, shall form part of the scope of the contract between
the Supplier and the AIB/RIF.
8.2. Requirements of Manufacturing Inspection Service
8.2.1. The service of Manufacturing Inspection shall be performed by an Accredited
Inspection Body according with ISO/IEC 17020 Type A contracted by the Supplier.
8.2.1.1. In case of AIB according with ISO/IEC 17020 Type A is not available,
when hiring the Inspection Service, the Supplier shall guarantee the fulfillment
of the following premises:
a) Certification of the Inspection Body according to valid ISO 9001, whose
scope shall be Manufacturing Inspection or be quality system certifier
company, according to ABNT NBR ISO 9001, or naval classifier member of
IACS (International Association of Classification Societies);
b) Signature of a Impartiality and Independence term (ANNEX III) between
the Supplier and the Inspection Body under the premises of ISO/IEC 17020;
c) Availability of Inspector of Manufacturing certified according to ABNT NBR
16278 or API SI in the modalities and levels applicable to the scope of the
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
10 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
inspection. Other similar certifications, issued by independent bodies,
internationally recognized, shall be submitted to prior approval of
PETROBRAS Quality of Materials Department;
8.2.2. Supplier shall maintain the original inspection records, paper or electronic
files, for, at least, 5 years.
8.2.3. Inspection records issued by the Manufacturing Inspector shall be prepared
according to section 12, identified and signed.
8.2.3.1. The identification of the professional shall contain at least the full
name, certifications, registration number in the certifying entity and company
to which he is associated.
8.2.4. The Responsible for Manufacturing Inspection shall issue a CLM (MRN) to
attest the conformity of the material with the contractual requirements.
8.3. Dispensation of Hiring the AIB for a Family of Material 8.3.1. The Supplier may be dispensed of hiring an AIB, as required by items 8.1 and
8.2, if the following criteria are fully met:
a) IQF average of 97.0% or more in the last 3 complete audits or while the
supplier does not have the average, shall present:
i.Active API Monogram certificate for the material to be supplied, or if it does
not exist, active API Spec Q1 certificate, or;
ii.Naval Classification Society certificate, member of IACS (International
Association of Classification Societies), for the material to be supplied, or;
iii.Boiler and Pressure Vessel Code (BPVC) certificate according ASME for
the material to be supplied, or;
iv.ABNT NBR 15827 certificate for the material to be supplied.
b) Absence of untreated Technical COD;
c) Absence of IR-NCR or CRM (Material Rejection) reporting High or Severe
Nonconformities in the last 12 months;
d) Specific criteria can be provided in the Complementary Quality
Requirement applicable to the respective family of material.
8.3.2. The dispensation of hiring an AIB requires the maintenance of a RIF, which
shall carry out all required Manufacturing Inspection activities.
8.3.3. The RIF shall issue/approve the CLM (MRN) upon the release of the material
and other records of Manufacturing Inspection.
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
11 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
8.3.4. The dispensation of hiring an AIB applies to the family of material and plant
audited. It shall be formalized by PETROBRAS Quality of Materials Department
through previous request by the Supplier in the communication channel of Note 3,
item 2.2 of this document.
8.3.5. This exemption from the hiring of the AIB does not exempt the Supplier from
issuing the documents, executing and recording the inspections and meetings
required by this Quality Requirement, as well as the Complementary Quality
Requirement, which shall be included in the Quality System and be available for audit
at anytime.
8.3.6. Upon obtaining such waiving, the Supplier shall maintain the above premises
for its maintenance. In case of missing any premises, the Supplier shall hire an AIB
within 30 days at its own expenses, during this period any delivery shall be approved
by the contract manager of PETROBRAS.
8.3.7. If the Supplier obtains IQF less than 90.0% in subsequent audits to the
granting of the dispensation, Supplier shall hire an AIB within 30 days, at its exclusive
expenses, during this period any delivery shall be approved by the contract manager
of PETROBRAS.
8.3.8. If the Supplier obtains IQF between 90.0% and 96.9% in audits subsequent
to obtaining the release, the Supplier will have a period of 180 days to adjust its
Quality System, i.e., to obtain IQF equal or greater than to 97.0 % in the next quality
audit of materials. If IQF is not obtained above 97.0%, it shall contract AIB, at its
exclusive expense, within 30 days, without prejudice to contractual conditions, even
if the Supplier complies with items 8.3.1.a)i, 8.3.1.a)ii, 8.3.1.a)iii or 8.3.1.a)iv.
9. MANUFACTURING INSPECTION PLANNING
9.1. Inspection and Testing Plan - ITP
9.1.1. Inspection and Testing Plans (ITP) shall be issued by the Supplier and shall
comply with the Quality Requirements and other documents defined in the contract
and/or purchase order, including all the production processes, installation and
services associated with the supply. Annex I presents a Guidelines for the
preparation of the ITP in order to assist in its preparation.
9.1.2. Inspection and Test Plans shall be issued prior to commencement of
manufacturing activities to meet the following guidelines:
a) Description of the inspection and monitoring events throughout the
manufacturing process, including those performed in the Subsuppliers,
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
12 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
indicating the verifications to be carried out, the type and extent of the exams,
tests and verifications;
b) Identification of the type of participation (document approval, document
review, monitoring point, witness point and hold point) of the manufacturer and
of the Responsible for Manufacturing Inspection throughout the manufacturing
cycle;
c) Indication of the necessary qualification and certification for personnel
performing the inspection, exams, testing, checking and special production
processes;
d) Indication of procedures, technical specifications and standards applicable
to each activity and level of reference quality (API Q1 or API PSL2, for
example);
e) Indication of the documents to be approved by the Responsible for
Manufacturing Inspection, as defined in this Materials Quality General
Requirement and Complementary Quality Requirement, when applicable;
f) Indication of the acceptance criteria applicable to all characteristics and
quality requirements of each activity, as established in the procedures,
technical specifications and applicable standards;
g) Indication of critical components that are part of pressurized circuits. Also
include as critical components that interfere in operation, maintenance,
safety and useful life of the product;
h) Indication of the categorization and classification of the equipment
according to the project standard, Regulatory Standard (NR) and contractual
documentation. Equipment with special requirements is considered: service
with H2, H2S, lethal, toxic, clad, with heat treatment for stress relief and
toughness control;
i) Dimensional control of the critical dimensions of the components, including,
the dimensions of construction standard, manufacturer's design and the
specified by the customer;
j) Qualification and / or homologation approval of the material or its
components with by the responsible agencies and / or areas.
9.1.3. The Inspection and Testing Plan shall be approved by the Responsible for
Manufacturing Inspection.
9.1.3.1. The RIF will be dispensed from approving ITP for new purchase
orders when the PO have the same requirements and contractual documents
(except RM) as other approved ITP in previous evaluations by the same RIF.
9.2. Execution, Inspection and Testing Procedures
9.2.1. Procedures considered critical by the Responsible for Manufacturing
Inspection shall be approved by RIF.
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
13 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
9.2.2. PETROBRAS Quality of Materials Department may request, at any time, the
submission of procedures considered critical.
9.2.3. The Responsible for Manufacturing Inspection shall ensure that the
procedures deemed critical to the supply comply with the Quality Requirements and
other contractual technical requirements. This verification shall appear as an activity
in the ITP and be recorded in the Inspection Report.
9.2.4. Shall be adopted procedures for handling, processing and storage of
materials, such as: stainless steel, nickel alloys, titanium and their alloys, to avoid
the risk of contamination.
9.3. Procedure Qualification
The required inspection, exams and testing procedures shall have the qualified
procedure, according to the contractual premises, with witnessing and approval of
certified professional when required for the activity.
9.4. Sampling Inspection
9.4.1. When not established in the Complementary Quality Requirement, technical
specifications or applicable standards, the sampling manufacturing inspection
shall be defined by the RIF at the PIM and has be described in the inspection
reports.
9.5. Pre Inspection Meeting (PIM)
9.5.1. Pre inspection meeting (PIM) shall be held with the participation of the
Responsible for Manufacturing Inspection and Supplier.
NOTE 1: It is recommended that PIM be performed before manufacture begins.
NOTE 2: The PIM can be held for one or more orders or purchase contracts.
9.5.1.1. The Supplier will be dispensed from PIM for new purchase orders
when the PO have the same requirements and contractual documents (except
RM) as other previous PIM with the same RIF. The scope shall be registered.
9.5.2. The participation of the Quality of Materials Department shall be at the
discretion of PETROBRAS and shall be notified at least 10 calendar days in advance
for national supplies and 30 calendar days for international supplies, with ITP and
production schedule of the material attached.
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
14 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
9.5.3. The agenda and draft minutes of the PIM shall be distributed for comment of
the participants in the act of notifying the meeting.
9.5.4. The PIM shall include at least the following objectives:
a) Presentation of the organizational chart, communication channels and
contacts and responsibilities of the parties involved;
b) Presentation of the Responsible for Manufacturing Inspection, including the
certification of the professionals involved;
c) Ratification of the scope of supply and technical requirements applicable;
d) Establishment of deadlines (notifications, inspection attending, issuance of
reports etc.), flow of communication and notification of inspection;
e) Clarification of doubts about technical requirements of manufacture and
possible deviations from technical documentation;
f) Planning of manufacturing, assembly and testing, including Subsuppliers;
g) Presentation of the Inspection and Test Plan (ITP) – establish the
participation of the parties in relation to the manufacturing stages, inform
Subsuppliers, certificates/reports and tests that shall be included in the ITP
and the types of interventions to be performed (AD, HP, WP, RD and MP) by
the Responsible for Manufacturing Inspection and Classification Society;
h) Define procedures to be analyzed for compliance with contractual
requirements;
i) Systematic for registration and treatment of Nonconformities;
j) Clarification of statutory and regulatory compliance requirements
(regulatory standards) and those of the organization;
k) Availability of quality records during manufacturing for the inspection team;
l) Presentation of HSE guidelines adopted at the plant;
m) Presentation of the Information Security guidelines adopted at the plant,
including restrictions on photographic registration (NOTE: the Responsible for
Manufacturing Inspection shall be authorized to photographically register the
inspected materials);
n) Presentation of all documents and records evidencing the acceptance of
deviations from the technical requirements and concessions signed between
PETROBRAS Contract Manager and the Supplier, for direct and indirect
purchases, from the proposal stage.
o) Sampling manufacturing inspection definition, if applicable.
10. MINIMUM MANUFACTURING INSPECTION ACTIVITIES
10.1. The minimum activities, to be carried out by the Responsible for
Manufacturing Inspection, are defined below, and shall be complemented according
to the respective Quality Requirements and approved ITP:
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
15 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
a) Analysis and approval of the Inspection and Testing Plan;
b) Approval of documents as provided in the Quality Requirements;
c) Verification of raw material certificates and quality records (product
compliance report with tests and inspections performed, etc.);
d) Verification during manufacturing (personnel qualification and certification,
methods and manufacturing processes, intermediate controls and tests);
e) Testimonial of hydrostatic and/or pneumatic, functional and/or performance
tests, when applicable;
f) Execution of the visual inspection, testimony of the final dimensional
examination and PMI, when applicable;
g) Verification of the data book and technical documentation;
h) Issuance of Inspection Records;
i) Identification, preservation and packaging.
NOTE 1: The AIB shall evaluate its participation during manufacture, (d), considering
the complexity of the material and the manufacturing process.
NOTE 2: The models in Annex IV include minimum inspection activities for the
manufacture of Pumps, Reciprocating Compressors, Centrifugal Compressors,
Screw Compressors, Gearboxes and Steam Turbines.
10.2. The AIB shall detail its participation in the manufacturing activities upon the
approval of the ITP in order to ensure the conformity of the material with respect to
the contractual documentation.
11. MANUFACTURING INSPECTION EXECUTION
11.1. All Manufacturing Inspection activities required in the approved ITP shall be
indicated in the Inspection Records issued by the RIF.
11.2. Nonconformity Treatment
11.2.1. When receiving an IR-NCR or CRM from RIF, the Supplier shall issue its
own NCR, according to the Implanted Quality System, to address deviations pointed
out in the IR-NCR or CRM.
11.2.2. When issuing IR-NCR or CRM, the RIF shall indicate the degree of
deviation in Light, Medium, High or Severe, according to the criteria established in
Table 1.
11.2.3. When issuing an NCR, the Supplier shall indicate the degree of deviation
in Light, Medium, High or Severe, according to the criteria established in Table 1.
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
16 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
11.2.4. All NCRs classified as High or Severe shall be immediately sent to Contract
Manager and Quality of Materials Department at PETROBRAS.
11.2.5. The Supplier shall send to PETROBRAS Quality of Materials Department
the corrective actions regarding to NCRs indicated in item 11.2.4 within 5 business
days of issuance and further results of corrective actions.
Table 1: Matrix to indicate the degree of the detected deviation.
Deviation
Degree Nonconformity Characteristic
Light
Nonconformity with the Supplier Quality System, whose implication does not
affect the performance of the equipment, which may affect the contractual
term, or generate reinspection.
Medium
Nonconformity observed in the Equipment, with the possibility of correction
through a Contractual Standard, which may imply in the term, or generate
reinspection.
High
Nonconformity in the Equipment, with compromise of the intrinsic quality,
performance of the equipment and without possibility of correction through a
Contractual Standard, which may affect the contractual term, or generate
reinspection.
Severe Nonconformity related to bad faith, adulteration of document or component
identification by Supplier or its supply chain.
11.3. Technical Documentation of Manufacture - Data Book
11.3.1. All the documents that make up the data book shall have the approval of
the Supplier evidenced by identification and signature. Supplier approval may be
evidenced by electronic systems that ensure traceability and reliability.
11.3.2. The Supplier shall provide a data book containing all documents mentioned
on ITP and applicable technical specification.
11.3.3. The section quality and manufacturing of the data book shall be verified
and approved, as a Hold Point in the ITP, by the Responsible for Manufacturing
Inspection before shipment of the equipment. The Responsible for Manufacturing
Inspection shall certify all the documents reviewed through identification and
signature or electronic systems that guarantee the traceability and reliability.
11.3.4. Throughout the manufacturing process, the Supplier shall keep available
for the Responsible for Manufacturing Inspection all quality and inspections records
performed in previous steps as required in the Inspection and Test Plans.
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
17 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
11.3.5. The raw material certificates shall be that of origin (factory, forge, foundry,
etc.). Certificates from resellers and distributors will be accepted if they are with origin
certificates. If these certificates are not available, material qualification tests are
acceptable upon testimony of the Responsible for the Manufacture Inspection and
issuance of a technical report of compatibility of the material by the supplier.
11.4. Access of the Inspector to Material Scope of Supply
11.4.1. The Supplier shall ensure free access of the Responsible for Manufacturing
Inspection to all components and manufacturing facilities related to the supply or
manufacture of the material upon request.
11.4.2. The RIF shall always have free access to all manufacturing areas where
manufacturing and inspection activities are performed on the material scope of
supply.
11.4.3. The Responsible for Manufacturing Inspection shall be authorized to obtain
a photographic record of the inspected materials. In case of restriction of the use of
cameras, by third parties, in the manufacturing plants, the Supplier shall provide the
required photographic record to the RIF.
12. RECORDS OF MANUFACTURING INSPECTION
12.1. The Responsible for Manufacturing Inspection shall issue the inspection
records (IR, IR-NCR, CLM or CRM) for all the events with its participation, as
indicated in the ITP, according to the type of intervention defined (AD, HP, WP, RD
and MP).
12.1.1. The inspection records CLM (MRN), CRM (Rejection), and IR-NCR shall
be issued within 7 days the inspection is completed.
12.2. Once all the steps of the Manufacturing Inspection have been completed with
satisfactory results, the RIF shall issue the CLM (MRN), according to model on
ANNEX II, attesting the conformity of the equipment with the contractual technical
documentation.
12.3. Inspection Records (IR, IR-NCR, CRM and CLM) shall contain at least the
following information:
a) Report number;
b) Order number or purchase order;
c) Item of the purchase order;
d) Quantity inspected;
e) Date or period of the inspection event;
f) Identification of the Supplier and manufacturer, in case of Subsupplier;
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
18 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
g) Purpose;
h) Description, identification and traceability of the property and its inspected
components (tag, serial number etc.);
i) Reference documents used in the inspection;
j) List of Annexes;
k) Stage (s) of ITP;
l) Description of the activities developed, and parameters evaluated;
m) Process stage (before, during or after manufacture);
n) Result of the inspection: satisfactory or unsatisfactory;
o) General notes, in the case of additional clarifications;
p) Identification of Manufacturing Inspector of RIF, including signature,
registration number in the certification body, level and modality of
certification;
q) Identification of the person responsible for Supplier Quality, including
signature, attesting to the receipt of the issued registration;
r) Distribution list of report;
s) Location of the activity;
t) Nonconformity Characteristics (only for IR-NCR and CRM);
u) Photographic records.
NOTE: Nonconformity Characteristic: When issuing an IR-NCR or CRM, the
Manufacturing Inspector shall indicate the degree of deviation detected in Light,
Medium, High or Severe, as established in Table 1.
12.3.1. ANNEX II provides a Guideline for Issuance of Manufacturing Inspection
records.
13. QUALITY AUDIT
13.1. General
13.1.1. During the supply of the equipment, PETROBRAS Quality of Materials
Department may perform presential audits at the Suppliers and Subsuppliers
facilities or remote method at PETROBRAS premises, through the analysis of
technical documentation sent by the Supplier, with the Purpose to verify compliance
the quality management system, the manufacturing process, the product and the
records issued by the RIF.
13.1.1.1. PETROBRAS Quality of Materials Department shall communicate
the performance of the audit with 30 calendar days in advance, together with
the list of documents that shall be available within 10 calendar days of the
communication. Failure to comply with the aforementioned deadlines
constitutes a breach of contract, subject to the application of a fine.
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
19 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
13.1.1.2. During the audit, Organization shall provide an appropriate room
for the audit team, with an air-conditioned environment and data network.
13.1.2. PETROBRAS Quality of Materials Department reserves the right to audit,
at any time, the application and maintenance of the requirements defined in this
document at the Suppliers, Subsuppliers, Inspection Bodies and Manufacturing
Inspectors involved in the supply.
13.1.3. The periodicity of the audits will be defined by PETROBRAS Quality of
Materials Department, considering, among other aspects, the criticality of the
material for the operation, the complexity of the manufacturing process, the
Supplier's history and the market in which it operates, the occurrence of failures on
site, pioneering design and unprecedented supply.
13.1.4. Supplier's representative shall take part in Quality Audit at Subsuppliers.
13.1.5. The audit may be performed at the plant of the respective (s) manufacturer
(s) when the Supplier is classified as a Reseller or Distributor.
13.2. Responsibility for Quality Audits PETROBRAS Quality of Materials Department will be responsible for planning and
performing presential and/or remote audit, at the Supplier and Subsupplier, the
compliance checks regarding the contractual requirements during the supply of the
material.
13.3. Scope of the Quality Audit The Quality Audit in the Supplier and Subsupplier shall include the following aspects:
13.3.1. Quality Management System: verification of compliance with the
contractual requirements of the Organization's Quality Management System, as well
as the requirements of ISO 9001.
13.3.2. Material Manufacturing Process: verification of compliance with
contractual requirements in the manufacturing process of the material, such as
manufacturing procedures, inspection and testing, quality meeting minutes,
inspection and tests records generated during manufacturing, among other
documents required by the Quality Requirements.
13.3.3. Final Product: verification of conformity in relation to the contractual
requirements of the finished product.
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
20 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
13.3.4. Responsible for Manufacturing Inspection: verification of compliance
with the requirements of this Quality Requirement and the Complementary Quality
Requirement (when applicable), such as issuance of inspection records, participation
in manufacturing events and performance with independence and impartiality.
13.4. Execution of the Quality Audit 13.4.1. PETROBRAS Quality of Materials Department will carry out an opening
meeting on the first day of the audit, with the participation of the auditing team and
the Supplier Quality representatives.
13.4.2. During the audit, the audited organization shall designate a focal point to
provide all requested documentation, evidence the attendance of each item of
verification and make available the resources demanded by the audit team to verify
compliance with the contractual requirements.
13.4.3. PETROBRAS Quality of Materials Department will carry out a closing
meeting of the audit with the presence of the audit team and the representatives of
the Quality of the Organization, when they will be informed the points of improvement
and nonconformities observed in each phase.
13.5. Records of the Quality Audit 13.5.1. At the end of the closing meeting, minutes will be issued where the points
of improvement, observations and nonconformities identified in each phase will be
informed, for the signature of all participants.
13.5.2. The audit report, containing the findings of the audit team, including IQF,
with the respective evidence, will be forwarded to the Supplier within 15 calendar
days after the end of audit.
13.5.2.1. The Supplier, upon receipt of the audit report, may submit an
appeal to the findings of PETROBRAS Quality of Materials Department.
13.5.3. If Supplier obtains an IQF average less than 80.0% in the last 3 complete
audits, a procedure for requesting technical disqualification will be
established.
13.6. Control and Monitoring of Nonconformities 13.6.1. The Organization shall submit to PETROBRAS Quality of Materials
Department a Corrective Action Plan to mitigate all Nonconformities observed in the
audit within 15 calendar days of receipt of the final audit report.
SPECIFICATION Nº
I-ET-0000.00-0000-972-1AL-001 REV.
C
SHEET
21 of 21
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
13.6.2. The Corrective Action Plan shall contain the proposed actions, scope,
implementation deadlines and Supplier Quality Focal Points responsible for each
proposed action.
13.6.3. The Corrective Action Plan shall be submitted to PETROBRAS Quality of
Materials Department for review and approval, which will respond within 15 calendar
days.
13.6.4. PETROBRAS may verify the effectiveness of the Corrective Action Plan
implemented at any time.
2
SPECIFICATION Nº
ET-0000.00-0000-972-1AL-001 REV.
C
SHEET -
TITLE:
QUALITY OF MATERIALS GENERAL
REQUIREMENTS
PUBLIC
GQB
ANNEX IV
Models
The Models presented in this annex include the minimum manufacturing inspection activities for Pumps, Reciprocating Compressors, Centrifugal Compressors, Screw Compressors, Gearbox and Steam Turbine.
1 RD RD RD RD RD RD RD RD RD 3.1
2 RD RD RD RD RD RD RD RD RD 3.1
3 RD RD RD RD RD RD RD 3.1
4 RD RD RD RD RD RD RD RD RD 3.1
5 RD RD RD RD RD RD RD RD 3.1
6 RD RD RD RD RD
7 RD RD RD RD RD
8 RD RD RD RD 3.1
9 RD RD RD RD RD 3.1
10 RD RD 3.1
11 RD RD RD RD
12 RD RD RD RD
13 RD RD RD RD 2.1
14 RD RD RD RD
15 RD RD RD 3.1
16 RD RD RD RD
17 RD RD RD RD RD RD 3.1
18 RD RD RD 3.1
19 RD 3.1
20 RD 3.1
21 HP WP 3.2
22 HP 3.2
23 HP 3.2
24 HP 3.2
25 HP
26 HP 3.2
27 RD 3.2
28 HP 3.2
29 HP 3.2
30 RD
31 HP 3.2
32 HP HP 2.1
33 RD 3.1
34 RD 3.1
35 HP HP HP HP 2.1
36 RD 2.1
37 HP
REV. Nº DATE EXECUTION VERIFICATION APPROVED
VISUAL INSPECTION
PRESERVATION
FINAL INSPECTION (DIMENSIONAL AND VISUAL)
PERFORMANCE TEST
PERSONAL QUALIFICATION (NDT) (1)
PERSONAL QUALIFICATION (WELDING) (1)
PERSONAL QUALIFICATION (WELD INSPECTION) (1)
PERSONAL QUALIFICATION (DIMENSIONAL) (1)
PERSONAL QUALIFICATION (PAINTING) (1)
MECHANICAL TEST
ITP NUMBER:
REMARKS
ET(s):
WE
AR
RIN
GS
AU
XIA
LIR
Y P
IPIN
G
SE
AL
BE
AR
ING
HO
USE
SP
AR
E P
AR
TS (
2)
BA
R P
UM
P
SUPPLIER LOGO
HEAT TREATMENT
I
T
E
M
CRITICAL COMPONENTS
WPS/PQR/WQ (WELDING)
POSITIVE MATERIAL IDENTIFICATION (1)
INSPECTION AND TEST PLAN (ITP) FOR PUMP
ACCEPTANCE CRITERIA
PC:
BALANCING (1)
INCLUDE THE NAME OF THE SUPPLIER IN THIS CELL
FD(s):
SIGNATURE:
BA
SE
PLA
TE
REV.:
PAGE : 01 de 01
ST
UD
S,
SC
RE
WS A
ND
NU
TS
NA
ME
PLA
TE
DATE:
RUNOUT (MECHANICAL AND ELECTRICAL) (1)
REVIEW INDEX
RM:
CHEMICAL ANALYSIS
MECHANICAL PROPERTIES
INSPECTION AND TESTS
DESMAGNETIZATION (1)
CE
RT
IFIC
AT
E
(BS E
N 1
02
04
)
CONFORMITY CERTIFICATE
WP Witnesed Point) -It is the inspection event in the supplier's manufacturing cycle, in which the supplier will notify the Responsible for Manufacturing Inspection, within the contractual deadlines, for the analysis, verification or testimony of events agreed upon in the Inspection and Test Plan, without the
manufacturing process is interrupted.
HP (Hold Point) -It is the inspection event in the supplier's manufacturing cycle, in which the supplier will notify the Responsible for Manufacturing Inspection, within the contractual deadlines, for the analysis, verification or testimony of the same and without which the manufacturing process does not keep
going.
NSPH TEST (1)
MANUFACTURING INSPECTION ACTIVITIES
RO
TO
R
SH
AFT
DISASSEMBLY AFTER TEST (1)
NDT PROCEDURES (1)
PE
TR
OB
RA
S A
UD
IT
IMP
ELL
ER
CA
SIN
G
HARDNESS (1)
SU
PP
LIE
D I
NST
RU
ME
NT
S
PENETRANT TEST/MAGNETIC TEST (1)
MAP OF REPAIRS (Major repairs) (1)
DATE:
SIGNATURE:
PIPE-LOAD TEST (1)
PNEUMATIC TEST
DATA BOOK ANALYSIS
1 - ONLY WHEN APPLICABLE OR SPECIFIED
PAINTING (FINAL THICKNESS AND ADHERENCE) (1)
STRING TEST (1)
PRE-ALIGNMENT (1)
RD (Review Document) - It is the inspection event in the vendor's manufacturing cycle, in which documents (procedures, records, certificates, reports, etc.) will be generated to be presented to the inspection body as technical documentation in the final inspection.
4 - THE FITTING REPORT FOR THE FULL PUMP SHALL BE PROVIDED.
HYDROSTATIC TEST (3)
X RAY / ULTRASONIC (1)
WELD INSPECTION
CERTIFICATE OF CALIBRATION
CERTIFICATE FOR EXPLOSION AREA (1)
DIMENSIONAL INSPECTION (4)
PA
3 - THE EXTERNAL AND INTERNAL VISUAL INSPECTION AND THE DIMENSIONAL FLANGES SHALL BE PERFORMED AFTER THE HYDROSTATIC TEST.
2 - THE SPARE ROTORS SHALL HAVE THE SAME TESTS OF THE MAIN ROTOR, WHEN APPLICABLE.
TAG/MODEL/SERIAL NUMBER:GENERAL ARRANGEMENT DRAWING:
DESCRIPTION OF ITEMS:
PROCEDURES AND/OR TECHINICAL
INTRUCTIONS
CO
UP
LIN
G
CLIENT:
NOTES SUPPLIER APPROVAL RIF APPROVAL
PA (Audit Points) - Critical event in the manufacturing cycle where an audit by PETROBRAS is required during the execution of the respective activity. It is not characterized as a Hold Point. The supplier shall notify PETROBRAS Quality Department in advance of 10 (ten) calendar days for national contracts and
30 (thirty) consecutive days for international contracts. The notification shall be made by e-mail. Preferably, the definition of the audit points will be communicated by PETROBRAS. The Audit Point can be defined by PETROBRAS during the PMM.
ACTIVITIES OF RESPONSIBLE FOR MANUFACTURING INSPECTION
SU
RV
EY
OR
STANDARDS: PC ITEMS:
1 RD RD RD RD RD RD RD RD RD RD RD RD RD RD RD RD 3.1
2 RD RD RD RD RD RD RD RD RD RD RD RD RD RD RD RD 3.1
3 RD RD RD RD RD RD RD RD RD RD RD RD RD 3.1
4 RD RD RD RD RD RD RD RD RD RD RD RD RD RD RD RD 3.1
5 RD RD RD RD RD RD RD RD RD RD RD RD RD RD 3.1
6 RD RD RD RD
7 RD RD RD RD
8 RD RD RD RD 3.1
9 RD RD RD RD 3.1
10 RD 3.1
11 RD RD RD
12 RD RD RD
13 RD RD RD RD RD RD RD RD RD RD RD RD 2.1
14 RD RD RD
15 RD RD RD 3.1
16 RD
17 RD 3.1
18 RD RD 3.1
19 HP WP 3.2
20 HP 3.2
21 HP 3.2
22 HP 3.2
23 HP 3.2
24 HP 3.2
25 HP 3.2
26 HP
27 WP HP 3.2
28 HP 3.2
29 RD
30 HP 3.2
31 HP HP 2.1
32 RD 3.1
33 RD 3.1
34 HP HP HP 2.1
35 RD 2.1
36 HP
REV. Nº DATE EXECUTION VERIFICATION APPROVED
DATE:
ET(s): STANDARDS: PC ITEMS:
HP (Hold Point) -It is the inspection event in the supplier's manufacturing cycle, in which the supplier will notify the Responsible for Manufacturing Inspection, within the contractual deadlines, for the analysis, verification or testimony of the same and without which the manufacturing process does not keep
going.
WP Witnesed Point) -It is the inspection event in the supplier's manufacturing cycle, in which the supplier will notify the Responsible for Manufacturing Inspection, within the contractual deadlines, for the analysis, verification or testimony of events agreed upon in the Inspection and Test Plan, without the
manufacturing process is interrupted.
RD (Review Document) - It is the inspection event in the vendor's manufacturing cycle, in which documents (procedures, records, certificates, reports, etc.) will be generated to be presented to the inspection body as technical documentation in the final inspection.
PA (Audit Points) - Critical event in the manufacturing cycle where an audit by PETROBRAS is required during the execution of the respective activity. It is not characterized as a Hold Point. The supplier shall notify PETROBRAS Quality Department in advance of 10 (ten) calendar days for national contracts and
30 (thirty) consecutive days for international contracts. The notification shall be made by e-mail. Preferably, the definition of the audit points will be communicated by PETROBRAS. The Audit Point can be defined by PETROBRAS during the PMM.
NOTES
REMARKS
DATE:
2 - THE SPARE ROTORS SHALL HAVE THE SAME TESTS OF THE MAIN ROTOR, WHEN APPLICABLE.
3 - THE EXTERNAL AND INTERNAL VISUAL INSPECTION AND THE DIMENSIONAL FLANGES SHALL BE PERFORMED AFTER THE HYDROSTATIC TEST.
4 - THE FITTING REPORT FOR THE FULL RECIPROCATING COMPRESSOR SHALL BE PROVIDED.
REVIEW INDEX
1 - ONLY WHEN APPLICABLE OR SPECIFIED SIGNATURE: SIGNATURE:
SUPPLIER APPROVAL RIF APPROVAL
SUPPLIER LOGOINCLUDE THE NAME OF THE SUPPLIER IN THIS CELL
ITP NUMBER: REV.:
INSPECTION AND TEST PLAN (ITP) FOR RECIPROCATING COMPRESSOR PAGE : 01 de 01
TAG/MODEL/SERIAL NUMBER:
FD(s):
I
T
E
M
CRITICAL COMPONENTS
CIL
IND
ER
DESCRIPTION OF ITEMS:
RM:
AU
XIA
LIR
Y P
IPIN
G
CE
RT
IFIC
AT
E
(BS E
N 1
02
04
)
PROCEDURES AND/OR TECHINICAL
INTRUCTIONS
PC: CLIENT: GENERAL ARRANGEMENT DRAWING:
PE
TR
OB
RA
S A
UD
IT
SU
RV
EY
OR
SP
AR
E P
AR
TS (
2)
BA
R C
OM
PR
ESSO
R
BA
SE
PLA
TE
FLY
WH
EE
L
ACCEPTANCE CRITERIA
MANUFACTURING INSPECTION ACTIVITIES ACTIVITIES OF RESPONSIBLE FOR MANUFACTURING INSPECTION
ST
UD
S,
SC
RE
WS A
ND
NU
TS
NA
ME
PLA
TE
S
SU
PP
LIE
D I
NST
RU
ME
NT
S
INSPECTION AND TESTS
CHEMICAL ANALYSIS
MECHANICAL PROPERTIES
BE
AR
ING
HO
USIN
G
CR
OSSH
EA
D
CR
OSSH
EA
D P
IN
LIN
ER
HARDNESS (1)
HEAT TREATMENT
POSITIVE MATERIAL IDENTIFICATION (1)
NDT PROCEDURES (1)
PERSONAL QUALIFICATION (NDT) (1)
PENETRANT TEST/MAGNETIC TEST (1)
X RAY / ULTRASONIC (1)
MAP OF REPAIRS (Major repairs) (1)
WPS/PQR/WQ (WELDING)
PERSONAL QUALIFICATION (WELDING) (1)
VISUAL INSPECTION
PERSONAL QUALIFICATION (WELD INSPECTION) (1)
WELD INSPECTION
PERSONAL QUALIFICATION (DIMENSIONAL) (1)
DIMENSIONAL INSPECTION (4)
DISASSEMBLY AFTER TEST (1)
TIGHTNESS TEST
BALANCING (1)
HYDROSTATIC TEST (3)
WEB DEFLECTION
MECHANICAL TEST
PRE-ALIGNMENT (1)
PERSONAL QUALIFICATION (PAINTING) (1)
PAINTING (FINAL THICKNESS AND ADHERENCE) (1)
PRESERVATION
CERTIFICATE OF CALIBRATION
CERTIFICATE FOR EXPLOSION AREA (1)
FINAL INSPECTION (DIMENSIONAL AND VISUAL)
CONFORMITY CERTIFICATE
DATA BOOK ANALYSIS
PIS
TO
N R
OD
CO
NN
EC
TIN
G R
OD
CR
AN
KSH
AFT
VA
LVE
RUNOUT CHECK
CLEARANCE VOLUME CHECK
CR
AN
KSH
AFT
CA
SIN
G
DIS
TA
NC
E P
IEC
E
PIS
TO
N
WE
AR
RIN
GS
GAS LEAK TEST
BAR-OVER TEST
1 RD RD RD RD RD RD RD RD RD RD RD 3.1
2 RD RD RD RD RD RD RD RD RD RD RD 3.1
3 RD RD RD RD RD RD RD RD RD 3.1
4 RD RD RD RD RD RD RD RD RD RD RD 3.1
5 RD RD RD RD RD RD RD RD RD 3.1
6 RD RD RD RD RD RD
7 RD RD RD RD RD RD
8 RD RD RD RD RD RD 3.1
9 RD RD RD RD RD RD 3.1
10 RD RD RD 3.1
11 RD RD RD RD RD
12 RD RD RD RD RD
13 RD RD RD 2.1
14 RD RD RD RD RD
15 RD RD RD RD RD 3.1
16 RD RD RD
17 RD RD RD RD 3.1
18 RD RD RD 3.1
19 RD 3.1
20 RD 3.1
21 HP 3.2
22 HP 3.2
23 HP HP WP 3.2
24 HP 3.2
25 HP HP 3.2
26 HP 3.2
27 HP 3.2
28 HP 3.2
29 HP 3.2
30 HP
31 HP 3.2
32 HP 3.2
33 HP 3.2
34 HP
35 HP 3.2
36 HP HP
37 RD 3.1
38 RD 3.1
39 HP HP HP HP 3.2
40 HP 3.2
41 HP
REV. Nº DATE EXECUTION VERIFICATION APPROVED
4 - THE FITTING REPORT FOR THE FULL CENTRIFUGAL COMPRESSOR SHALL BE PROVIDED.
DATE: DATE:
RD (Review Document) - It is the inspection event in the vendor's manufacturing cycle, in which documents (procedures, records, certificates, reports, etc.) will be generated to be presented to the inspection body as technical documentation in the final inspection.
PA (Audit Points) - Critical event in the manufacturing cycle where an audit by PETROBRAS is required during the execution of the respective activity. It is not characterized as a Hold Point. The supplier shall notify PETROBRAS Quality Department in advance of 10 (ten) calendar days for national contracts
and 30 (thirty) consecutive days for international contracts. The notification shall be made by e-mail. Preferably, the definition of the audit points will be communicated by PETROBRAS. The Audit Point can be defined by PETROBRAS during the PMM.
NOTES SUPPLIER APPROVAL RIF APPROVAL
1 - ONLY WHEN APPLICABLE OR SPECIFIED SIGNATURE: SIGNATURE:
2 - THE SPARE ROTORS SHALL HAVE THE SAME TESTS OF THE MAIN ROTOR, WHEN APPLICABLE.
3 - THE EXTERNAL AND INTERNAL VISUAL INSPECTION AND THE DIMENSIONAL FLANGES SHALL BE PERFORMED AFTER THE HYDROSTATIC TEST.
HP (Hold Point) -It is the inspection event in the supplier's manufacturing cycle, in which the supplier will notify the Responsible for Manufacturing Inspection, within the contractual deadlines, for the analysis, verification or testimony of the same and without which the manufacturing process does not keep
going.
REVIEW INDEX
WP Witnesed Point) -It is the inspection event in the supplier's manufacturing cycle, in which the supplier will notify the Responsible for Manufacturing Inspection, within the contractual deadlines, for the analysis, verification or testimony of events agreed upon in the Inspection and Test Plan, without the
manufacturing process is interrupted.
MANUFACTURING INSPECTION ACTIVITIES ACTIVITIES OF RESPONSIBLE FOR MANUFACTURING INSPECTION
PE
TR
OB
RA
S A
UD
IT
SUR
VE
YO
R
RO
TO
R
SEA
L
BE
AR
ING
HO
USE
SUPPLIER LOGOINCLUDE THE NAME OF THE SUPPLIER IN THIS CELL
ITP NUMBER: REV.:
INSPECTION AND TEST PLAN (ITP) FOR CENTRIFUGAL COMPRESSOR PAGE : 01 de 01
PC: CLIENT: GENERAL ARRANGEMENT DRAWING: TAG/MODEL/SERIAL NUMBER:
FD(s): DESCRIPTION OF ITEMS:
RM:
ET(s): STANDARDS: PC ITEMS:
STU
DS,
SC
RE
WS
AN
D
NU
TS
BA
SEP
LAT
E
BA
R C
OM
PR
ESS
ORI
T
E
M
CRITICAL COMPONENTS
CA
SIN
G
IMP
ELL
ER
SHA
FT
DIF
USO
R
HY
DR
OD
INA
MIC
BE
AR
ING
S
NA
ME
PLA
TE
SUP
PLI
ED
IN
STR
UM
EN
TS
INSPECTION AND TESTS
CHEMICAL ANALYSIS
SLE
EV
E
TA
MB
OR
DE
BA
LAN
CE
AM
EN
TO
SPA
RE
PA
RT
S (2
)
CO
UP
LIN
G
ACCEPTANCE CRITERIA
CE
RT
IFIC
AT
E
(BS
EN
10
20
4)
(BS
EM
10
20
4)
PROCEDURES AND/OR TECHINICAL
INTRUCTIONS
HARDNESS (1)
MECHANICAL PROPERTIES
POSITIVE MATERIAL IDENTIFICATION (1)
NDT PROCEDURES (1)
HEAT TREATMENT
PERSONAL QUALIFICATION (NDT) (1)
PENETRANT TEST/MAGNETIC TEST (1)
MAP OF REPAIRS (Major repairs) (1)
X RAY / ULTRASONIC (1)
PERSONAL QUALIFICATION (WELD INSPECTION) (1)
WPS/PQR/WQ (WELDING)
PERSONAL QUALIFICATION (WELDING) (1)
VISUAL INSPECTION
WELD INSPECTION
PERSONAL QUALIFICATION (DIMENSIONAL) (1)
BALANCING (1) (High and low speed)
DIMENSIONAL INSPECTION (4)
CONTACT TEST (PRUSSIAN BLUE)
HYDROSTATIC TEST (3)
PERFORMANCE TEST (1)
UNBALANCED RESPONSE TEST (1)
PRE-ALIGNMENT (1)
DESASSEMBLY AFTER TEST
STRING TEST PA
PERSONAL QUALIFICATION (PAINTING) (1)
PAINTING (FINAL THICKNESS AND ADHERENCE) (1)
DATA BOOK ANALYSIS
PRESERVATION
CERTIFICATE OF CALIBRATION
CERTIFICATE FOR EXPLOSION AREA (1)
FINAL INSPECTION (DIMENSIONAL AND VISUAL)
CONFORMITY CERTIFICATE
STABILITY TEST (1)
AU
XIL
IAR
Y P
IPIN
G
GAS LEAK TEST (1)
HELIUM TEST (1)
DEMAGNETIZATION (1)
MECHANICAL TEST
RUNOUT (mechanical and electrical) (1)
OVERSPEED TEST
OPTIONAL TESTS
REMARKS
1 RD RD RD RD RD RD RD RD RD 3.1
2 RD RD RD RD RD RD RD RD RD 3.1
3 RD RD RD RD RD RD RD RD RD 3.1
4 RD RD RD RD RD RD RD 3.1
5 RD RD RD RD RD
6 RD RD RD RD RD
7 RD RD RD RD RD 3.1
8 RD RD RD RD RD 3.1
9 RD RD RD 3.1
10 RD RD RD RD RD
11 RD RD RD RD RD
12 RD RD RD RD 2.1
13 RD RD RD RD RD
14 RD RD RD 3.1
15 RD RD RD
16 RD RD RD RD 3.1
17 RD RD RD 3.1
18 RD 3.1
19 RD 3.1
20 HP 3.2
21 HP WP 3.2
22 HP 3.2
23 HP 3.2
24 HP 3.2
25 HP 3.2
26 HP
27 HP 3.2
28 HP 3.2
29 HP 3.2
30 HP 3.2
31 HP 3.2
32 HP
33 HP 3.2
34 HP HP
35 RD 3.1
36 RD 3.1
37 HP HP HP HP 3.2
38 HP 3.2
39 HP
REV. Nº DATE EXECUTION VERIFICATION APPROVED
DATE: DATE:
RIF APPROVAL
1 - ONLY WHEN APPLICABLE OR SPECIFIED SIGNATURE: SIGNATURE:
2 - THE SPARE ROTORS SHALL HAVE THE SAME TESTS OF THE MAIN ROTOR, WHEN APPLICABLE.
3 - THE EXTERNAL AND INTERNAL VISUAL INSPECTION AND THE DIMENSIONAL FLANGES SHALL BE PERFORMED AFTER THE HYDROSTATIC TEST.
4 - THE FITTING REPORT FOR THE FULL STEAM TURBINE SHALL BE PROVIDED.
STANDARDS: PC ITEMS:
MANUFACTURING INSPECTION ACTIVITIES ACTIVITIES OF RESPONSIBLE FOR MANUFACTURING INSPECTION
HP (Hold Point) -It is the inspection event in the supplier's manufacturing cycle, in which the supplier will notify the Responsible for Manufacturing Inspection, within the contractual deadlines, for the analysis, verification or testimony of the same and without which the manufacturing process does not keep going.
AU
XIL
IAR
Y P
IPIN
G
ST
UD
S,
SC
RE
WS
AN
D
NU
TS
REVIEW INDEX
WP Witnesed Point) -It is the inspection event in the supplier's manufacturing cycle, in which the supplier will notify the Responsible for Manufacturing Inspection, within the contractual deadlines, for the analysis, verification or testimony of events agreed upon in the Inspection and Test Plan, without the
manufacturing process is interrupted.
RD (Review Document) - It is the inspection event in the vendor's manufacturing cycle, in which documents (procedures, records, certificates, reports, etc.) will be generated to be presented to the inspection body as technical documentation in the final inspection.
SUPPLIER LOGOINCLUDE THE NAME OF THE SUPPLIER IN THIS CELL
ITP NUMBER: REV.:
INSPECTION AND TEST PLAN (ITP) FOR STEAM TURBINE PAGE : 01 de 01
PC: CLIENT: GENERAL ARRANGEMENT DRAWING: TAG/MODEL/SERIAL NUMBER:
FD(s): ET(s): DESCRIPTION OF ITEMS:
RM:
HY
DR
OD
INA
MIC
BE
AR
ING
S
NA
ME
PLA
TE
ACCEPTANCE CRITERIA
I
T
E
M
CRITICAL COMPONENTS
CA
SIN
G
VA
LVE
BO
DY
WH
EE
L
BLA
DE
S
SH
AF
T
PROCEDURES AND/OR TECHINICAL
INTRUCTIONS
RO
TO
RINSPECTION AND TESTS
BE
AR
IN H
OU
SE
BA
SE
PLA
TE
BA
R T
UR
NIN
E
SP
AR
EP
AR
TS
(2
)
CO
UP
LIN
G
CHEMICAL ANALYSIS
PE
TR
OB
RA
S A
UD
IT
SU
RV
EY
OR
CE
RT
IFIC
AT
E
(BS
EN
10
20
4)
(BS
EM
10
20
4)
REMARKS
SU
PP
LIE
D I
NS
TR
UM
EN
TS
HEAT TREATMENT
MECHANICAL PROPERTIES
POSITIVE MATERIAL IDENTIFICATION (1)
NDT PROCEDURES (1)
PERSONAL QUALIFICATION (NDT) (1)
PENETRANT TEST/MAGNETIC TEST (1)
MAP OF REPAIRS (Major repairs) (1)
X RAY / ULTRASONIC (1)
PERSONAL QUALIFICATION (WELD INSPECTION) (1)
WPS/PQR/WQ (WELDING)
PERSONAL QUALIFICATION (WELDING) (1)
VISUAL INSPECTION
WELD INSPECTION
PERSONAL QUALIFICATION (DIMENSIONAL) (1)
DIMENSIONAL INSPECTION (4)
BALANCING (1) (High and low speed)
DEMAGNETIZATION (1)
HYDROSTATIC TEST (3)
JOINT LEAK TEST (1)
PA
RUNOUT (mechanical and electrical) (1)
CONTACT TEST (PRUSSIAN BLUE) (1)
PERFORMANCE TEST (1)
OVERSPEED TEST
MECHANICAL TEST
OPTIONAL TEST
STRING TEST
CERTIFICATE FOR EXPLOSION AREA (1)
FINAL INSPECTION (DIMENSIONAL AND VISUAL)
PRE-ALIGNMENT (1)
UNBALANCED RESPONSE TEST (1)
DISASSEMBLY AFTER TEST (1)
GOVERNATOR TEST
PERSONAL QUALIFICATION (PAINTING) (1)
PAINTING (FINAL THICKNESS AND ADHERENCE) (1)
PRESERVATION
CERTIFICATE OF CALIBRATION
CONFORMITY CERTIFICATE
DATA BOOK ANALYSIS
PA (Audit Points) - Critical event in the manufacturing cycle where an audit by PETROBRAS is required during the execution of the respective activity. It is not characterized as a Hold Point. The supplier shall notify PETROBRAS Quality Department in advance of 10 (ten) calendar days for national contracts and 30
(thirty) consecutive days for international contracts. The notification shall be made by e-mail. Preferably, the definition of the audit points will be communicated by PETROBRAS. The Audit Point can be defined by PETROBRAS during the PMM.
NOTES SUPPLIER APPROVAL
1 RD RD RD RD RD RD 3.1
2 RD RD RD RD RD RD 3.1
3 RD RD RD RD 3.1
4 RD RD RD RD RD RD 3.1
5 RD RD RD RD RD 3.1
6 RD RD RD RD
7 RD RD RD RD
8 RD RD RD RD 3.1
9 RD RD RD RD 3.1
10 RD 3.1
11 RD RD RD
12 RD RD RD
13 RD RD 2.1
14 RD RD RD
15 RD RD RD 3.1
16 RD RD
17 RD RD RD 3.1
18 RD RD 3.1
19 HP WP 3.2
20 HP 3.2
21 HP 3.2
22 HP 3.2
23 HP 3.2
24 HP 3.2
25 HP 3.2
26 HP
27 HP 3.2
28 HP 3.2
29 RD
30 HP 3.2
31 HP HP 2.1
32 RD 3.1
33 RD 3.1
34 HP HP HP HP 2.1
35 RD 2.1
36 HP
REV. Nº DATE EXECUTION VERIFICATION APPROVED
HP (Hold Point) -It is the inspection event in the supplier's manufacturing cycle, in which the supplier will notify the Responsible for Manufacturing Inspection, within the contractual deadlines, for the analysis, verification or testimony of the same and without which the manufacturing process does not keep
going.
REVIEW INDEX
WP Witnesed Point) -It is the inspection event in the supplier's manufacturing cycle, in which the supplier will notify the Responsible for Manufacturing Inspection, within the contractual deadlines, for the analysis, verification or testimony of events agreed upon in the Inspection and Test Plan, without the
manufacturing process is interrupted.
STRING TEST PA
MANUFACTURING INSPECTION ACTIVITIES ACTIVITIES OF RESPONSIBLE FOR MANUFACTURING INSPECTION
PE
TR
OB
RA
S A
UD
IT
SU
RV
EY
OR
CE
RT
IFIC
AT
E
(BS E
N 1
02
04
)
SUPPLIER LOGOINCLUDE THE NAME OF THE SUPPLIER IN THIS CELL
ITP NUMBER: REV.:
INSPECTION AND TEST PLAN (ITP) FOR SCREW COMPRESSOR PAGE : 01 de 01
GENERAL ARRANGEMENT DRAWING: TAG/MODEL/SERIAL NUMBER:
FD(s): DESCRIPTION OF ITEMS:
RM:
ET(s): STANDARDS: PC ITEMS:
CO
UP
LIN
G
PC: CLIENT:
I
T
E
M
CRITICAL COMPONENTS
CA
SIN
G
SH
AFT
AN
D R
OT
OR
S
BE
AR
ING
HO
USIN
G
AU
XIL
IAR
Y P
IPIN
G
INSPECTION AND TESTS
CHEMICAL ANALYSIS
ST
UD
S,
SC
RE
W A
ND
NU
TS
BA
SE
PLA
TE
BA
R C
OM
PR
ESSO
R
NA
ME
PLA
TE
SU
PP
LIE
D I
NST
RU
ME
NT
S
SP
AR
E P
AR
TS (
2)
ACCEPTANCE CRITERIA PROCEDURES AND/OR TECHINICAL
INTRUCTIONS
HARDNESS (1)
MECHANICAL PROPERTIES
POSITIVE MATERIAL IDENTIFICATION (1)
NDT PROCEDURES (1)
HEAT TREATMENT
PERSONAL QUALIFICATION (NDT) (1)
PENETRANT TEST/MAGNETIC TEST (1)
MAP OF REPAIRS (Major repairs) (1)
X RAY / ULTRASONIC (1)
PERSONAL QUALIFICATION (WELD INSPECTION) (1)
WPS/PQR/WQ (WELDING)
PERSONAL QUALIFICATION (WELDING) (1)
VISUAL INSPECTION
WELD INSPECTION
PERSONAL QUALIFICATION (DIMENSIONAL) (1)
DIMENSIONAL INSPECTION (4)
HYDROSTATIC TEST (3)
BALANCING
HELIUM TEST (1)
PERFORMANCE TEST (1)
MECHANICAL TEST
DISASSEMBLY AFTER TEST (1)
GAS LEAK TEST
OPTIONAL TESTS
HEAT TEST
PERSONAL QUALIFICATION (PAINTING) (1)
PAINTING (FINAL THICKNESS AND ADHERENCE) (1)
PRE-ALIGNMENT (1)
DATA BOOK ANALYSIS
PRESERVATION
CERTIFICATE OF CALIBRATION
CERTIFICATE FOR EXPLOSION AREA (1)
FINAL INSPECTION (DIMENSIONAL AND VISUAL)
CONFORMITY CERTIFICATE
RD (Review Document) - It is the inspection event in the vendor's manufacturing cycle, in which documents (procedures, records, certificates, reports, etc.) will be generated to be presented to the inspection body as technical documentation in the final inspection.
PA (Audit Points) - Critical event in the manufacturing cycle where an audit by PETROBRAS is required during the execution of the respective activity. It is not characterized as a Hold Point. The supplier shall notify PETROBRAS Quality Department in advance of 10 (ten) calendar days for national contracts and
30 (thirty) consecutive days for international contracts. The notification shall be made by e-mail. Preferably, the definition of the audit points will be communicated by PETROBRAS. The Audit Point can be defined by PETROBRAS during the PMM.
NOTES SUPPLIER APPROVAL RIF APPROVAL
1 - ONLY WHEN APPLICABLE OR SPECIFIED SIGNATURE: SIGNATURE:
2 - THE SPARE ROTORS SHALL HAVE THE SAME TESTS OF THE MAIN ROTOR, WHEN APPLICABLE.
3 - THE EXTERNAL AND INTERNAL VISUAL INSPECTION AND THE DIMENSIONAL FLANGES SHALL BE PERFORMED AFTER THE HYDROSTATIC TEST.
4 - THE FITTING REPORT FOR THE FULL SCREW COMPRESSOR SHALL BE PROVIDED.
DATE: DATE:
REMARKS
1 RD RD RD RD RD RD 3.1
2 RD RD RD RD RD RD 3.1
3 RD RD RD 3.1
4 RD RD RD RD RD RD 3.1
5 RD RD RD RD RD 3.1
6 RD RD RD RD
7 RD RD RD RD
8 RD RD RD RD 3.1
9 RD RD RD RD 3.1
10 RD 3.1
11 RD RD RD
12 RD RD RD
13 RD RD RD 2.1
14 RD RD RD
15 RD RD RD 3.1
16 RD RD
17 RD RD RD 3.1
18 RD RD 3.1
19 RD 3.2
20 WP 3.2
21 WP 3.2
22 HP HP 3.2
23 HP 3.2
24 HP 3.2
25 HP 3.2
26 HP 3.2
27 HP 3.2
28 RD
29 HP 3.2
30 HP HP 2.1
31 RD 3.1
32 RD 3.1
33 HP HP HP HP 2.1
34 RD 2.1
35 HP
REV. Nº DATE EXECUTION VERIFICATION APPROVED
3 - THE EXTERNAL AND INTERNAL VISUAL INSPECTION AND THE DIMENSIONAL FLANGES SHALL BE PERFORMED AFTER THE HYDROSTATIC TEST.
NA
ME
PLA
TE
DATE: DATE:
RIF APPROVAL
1 - ONLY WHEN APPLICABLE OR SPECIFIED SIGNATURE: SIGNATURE:
2 - THE SPARE ROTORS SHALL HAVE THE SAME TESTS OF THE MAIN ROTOR, WHEN APPLICABLE.
CLIENT:
4 - THE FITTING REPORT FOR THE FULL GEARBOX SHALL BE PROVIDED.
ET(s): STANDARDS: PC ITEMS:
HP (Hold Point) -It is the inspection event in the supplier's manufacturing cycle, in which the supplier will notify the Responsible for Manufacturing Inspection, within the contractual deadlines, for the analysis, verification or testimony of the same and without which the manufacturing process does not keep
going.
PROCEDURES AND/OR TECHINICAL
INTRUCTIONS
BA
SE
PLA
TE
REVIEW INDEX
WP Witnesed Point) -It is the inspection event in the supplier's manufacturing cycle, in which the supplier will notify the Responsible for Manufacturing Inspection, within the contractual deadlines, for the analysis, verification or testimony of events agreed upon in the Inspection and Test Plan, without the
manufacturing process is interrupted.
SUPPLIER LOGOINCLUDE THE NAME OF THE SUPPLIER IN THIS CELL
ITP NUMBER: REV.:
INSPECTION AND TEST PLAN (ITP) FOR GEAR BOX PAGE : 01 de 01
GENERAL ARRANGEMENT DRAWING: TAG/MODEL/SERIAL NUMBER:
FD(s): DESCRIPTION OF ITEMS:
RM:
MANUFACTURING INSPECTION ACTIVITIES ACTIVITIES OF RESPONSIBLE FOR MANUFACTURING INSPECTION
PE
TR
OB
RA
S A
UD
IT
BA
R G
EA
R B
OX
CE
RT
IFIC
AT
E
(BS E
N 1
02
04
)
HY
DR
OD
INA
MIC
BE
AR
ING
S
INSPECTION AND TESTS
PC:
ST
UD
S,
SC
RE
WS A
ND
NU
TS
CO
UP
PLI
NG
BE
AR
ING
HO
USE
SU
RV
EY
OR
I
T
E
M
CRITICAL COMPONENTS
CR
AC
KSH
AFT
CA
SIN
G
GE
AR
, P
INIO
AN
D S
HA
FT
AU
XIL
IAR
ES P
IPIN
G
REMARKS
SU
PP
LIE
D I
NST
RU
ME
NT
S
ACCEPTANCE CRITERIA
SP
AR
E P
AR
TS (
2)
MECHANICAL PROPERTIES
CHEMICAL ANALYSIS
HEAT TREATMENT
HARDNESS (1)
POSITIVE MATERIAL IDENTIFICATION (1)
NDT PROCEDURES (1)
PERSONAL QUALIFICATION (NDT) (1)
PENETRANT TEST/MAGNETIC TEST (1)
MAP OF REPAIRS (Major repairs) (1)
X RAY / ULTRASONIC (1)
PERSONAL QUALIFICATION (WELD INSPECTION) (1)
WPS/PQR/WQ (WELDING)
PERSONAL QUALIFICATION (WELDING) (1)
VISUAL INSPECTION
WELD INSPECTION
PERSONAL QUALIFICATION (DIMENSIONAL) (1)
DIMENSIONAL INSPECTION (4)
HYDROSTATIC TEST (3)
BALANCING
MECHANICAL TEST
TIGHTNESS TEST
CONTACT TEST (PRUSSIAN BLUE)
FITTING CHECK (AXIAL E BACKLASH)
DISASSEMBLY AFTER TEST (1)
RD (Review Document) - It is the inspection event in the vendor's manufacturing cycle, in which documents (procedures, records, certificates, reports, etc.) will be generated to be presented to the inspection body as technical documentation in the final inspection.
PA (Audit Points) - Critical event in the manufacturing cycle where an audit by PETROBRAS is required during the execution of the respective activity. It is not characterized as a Hold Point. The supplier shall notify PETROBRAS Quality Department in advance of 10 (ten) calendar days for national contracts and
30 (thirty) consecutive days for international contracts. The notification shall be made by e-mail. Preferably, the definition of the audit points will be communicated by PETROBRAS. The Audit Point can be defined by PETROBRAS during the PMM.
NOTES SUPPLIER APPROVAL
OPTIONAL TESTS
PRE-ALIGNMENT (1)
CONFORMITY CERTIFICATE
DATA BOOK ANALYSIS
PERSONAL QUALIFICATION (PAINTING) (1)
PAINTING (FINAL THICKNESS AND ADHERENCE) (1)
RUNOUT (MECHANICAL AND ELECTRICAL)
PRESERVATION
CERTIFICATE OF CALIBRATION
CERTIFICATE FOR EXPLOSION AREA (1)
FINAL INSPECTION (DIMENSIONAL AND VISUAL)
SPECIFICATION Nº
ET-0000.00-0000-972-1AL-001 REV.
C
SHEET -
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
ANNEX II
Guideline for Issuance of Manufacturing Inspection Records
The content proposed below applies to issue any type of Manufacturing Inspection record. NOTE: The itemization and assigned titles are merely exemplary and may be replaced by others that best represent reality in each inspected process. Report Topics
II.1 - Inspected Material: Identify, with as much information as possible, the actual inspected material. It is essential to refer information that is marked on the material in an indelible form. If this is not possible, the material shall be punctured with the seal of the inspector. Here are some examples: - Name of the equipment/material inspected (mainly when referring to a part or component of an item of the order); - Identification with low stress puncture; - TAG and Dimensions (diameter, length, thickness, width etc.); - PROJECT reference; - Other references (serial number, process fluid, etc.). NOTE: In case of documentation review, the Inspected Material will be considered the one to which this documentation refers. II.2 - Activities Developed: Describe all the activities developed during the period in which the inspection was performed and the participants of the event. Here are some examples: - Analysis of documentation; - Testimony of Tests and Assays; - Monitoring of manufacturing; - Other analyzes and checks. II.3 - Results: Describe the result obtained in relation to "Item II.2 - Developed Activities". NOTE1: In the case of an IR (Informative Inspection Report), describe as satisfactory the inspections performed and in the case of IR-NCR describe the deviations observed with the appropriate contractual references. NOTE2: This item may be deleted if the result of each activity developed is described in "Item II.2 - Developed Activities".
SPECIFICATION Nº
ET-0000.00-0000-972-1AL-001 REV.
C
SHEET -
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
II.4 - Conclusion: Report the conclusion regarding the acceptance of the inspection event based on the results found and the impact of these results in relation to the Manufacturing Inspection process, when applicable. In addition to the results found, information on the impact of this result on the manufacturing process shall be included, such as: - In the case of IR, report that the material will go to further phase and a new notification of inspection shall be made for next inspection step, when applicable. - In the case of IR-NCR, inform the deviation issues that shall be treated before a new notification of inspection, or other pertinent information, is issued. II.5 - Notes: Present, where applicable, other information regarding the inspection performed, for example: - Supplier's NCR closing or any type of pending event from previous reports; - The monitoring of inspection by a 3rd party, Classification Society, User of the equipment, among others; - User requests for equipment serviced by the Inspection Service; - Other remarks.
II.6 Model of Inspection Report: The Supplier may use the following model of inspection report to be issued by RIF (RI, RI-RNC, CLM and CRM).
SPECIFICATION Nº
ET-0000.00-0000-972-1AL-001 REV.
C
SHEET -
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
MODEL OF INSPECTION REPORT (RI, RI-RNC, CLM and CRM)
SUPPLIER PETROBRAS PURCHASE ORDER
ABCDEFGH 450243295
SUB-SUPPLIER REFERENCES
XXXXXX Nº OF CONTRACT 123
INTERNAL ORDER 456
INSPECTION LOCATION INSPECTION NOTICE
ABD12345678 ABD1234
CONTACT OF SUPPLIER
NAME XXXX
SECTOR XXXX
PETROBRAS UNIT INSPECTION PERIOD
REFINERY ABC, UO XYZ XX/XX/XXXX a XX/XX/XXXX
PARTY DELIVERY ALLOWED YES/NO
MATERIAL / EQUIPAMENT
ITEM QUANTITY TYPE DESCRIPTION
10 20 Q VALVE, PUMP, VESSEL XYZK
REFERENCE DOCUMENTS ANNEX
ITP PO XXXXX STANDARD 1 STANDARD 2
DOCUMENT ANALYZED 1 DOCUMENT ANALYZED 2 TEST RECORD 1 PICTURE 1 CERTIFICATE OF CONFORMITY
SUBJECT
ITP ANALYZE WPS ANALYZE HYDROSTATIC TEST RECEIVEMENT DIMENSIONAL INSPECTION VISUAL INSPECTION NCR TREATMENT nº ABCD-00000000111222333/2013 FINAL INSPECTION PERFORMANCE TEST
REPORT
1 OBJECTIVE : Detail the objective of inspection (final, intermediate, Tests, ITP analyze, document analyze, etc.). 2 MATERIAL: Detail the material or equipment characteristic, traceability, number, TAG, etc. 3 ACTIVITIES DEVELOPED: ACTIVITY 1: XXXXXX REFERENCE DOCUMENTS: XXXXXXX ITP ITEM (s) REFERENCE EVENT(s): XXXXXX RESULT: XXXX (APPROVED OR REPROVED) INSTRUMENTS: XXXXXX OBSERVATION: XXXXX ACTIVITY 2: XXXXXX REFERENCE DOCUMENTS: XXXXXXX ITP ITEM (s) REFERENCE EVENT(s): XXXXXX RESULT: XXXX (APPROVED OR REPROVED) INSTRUMENTS: XXXXXX OBSERVATION: XXXXX 4 CONCLUSION Detail the results, if the material is approved or reproved.
RESPONSIBLE FOR PROVISIONS SOLUTION DEADLINE
SSSSSSSSS MMMMMMM XX/XX/XXXX
INSPECTION STAGE
FINAL, INTERMADIATE, BEFORE MANUFACTURING
INSPECTOR
AAAAAAAAAAA BBBBBBB
SPECIFICATION Nº
ET-0000.00-0000-972-1AL-001 REV.
C
SHEET -
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
QUALIFICATION TYPE REGISTER NUMBER
API SOURCE INSPECTON XYZ 456
DISTRIBUTION
[email protected] [email protected]
SUPPLIER ISSUER APPROVER CLIENT
SPECIFICATION Nº
ET-0000.00-0000-972-1AL-001 REV.
C
SHEET -
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
ANNEX III
IMPARTIALITY AND INDEPENDENCE TERM
Ref.: ABNT NBR ISO/IEC 17020:2012
1. OBJECTIVE
This document has the objective to affirm that the service of Manufacturing Inspection defined throughout the scope below will be performed with impartiality and independence
2. SCOPE
Accredited Inspection Body data:
Company Name: [Insert the Company Name]
ITIN: [Insert Individual Tax Payer Identification Number]
ISO 9001 Certificate: [Insert the certificate number and the certifying body]
Supplier data:
Company Name: [Insert the Company Name]
ITIN: [Insert Individual Tax Payer Identification Number]
Address: [Insert the plant address]
Manufacturing Inspection Execution Information:
Contracts/Purchase Order and/or Service execution period:
[Insert the Contracts/Purchase Order and/or Service execution period]
Goods Description: [Insert briefly the types of materials and equipment and scope of the manufacturing inspection activity]
Applicable Disciplines: [Insert the applicable disciplines inspection, according defined in ABNT NBR 16278]
Performed Activities: [Insert the manufacturing process stages that will be the scope of the Inspection Body's performance]
3. Description
The inspection body and its personnel will not engage in any activities that may conflict with their independence of judgment and integrity in relation to their inspection activities. In particular, they will not be engaged in the design, manufacture, supply, installation, purchase, ownership, use or maintenance of the items inspected.
SPECIFICATION Nº
ET-0000.00-0000-972-1AL-001 REV.
C
SHEET -
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
The inspection body will not be a part of a legal entity that is engaged in design, manufacture, supply, installation, purchase, ownership, use or maintenance of the items inspected. The inspection body will not be a part of contractual commitments, or other means that may have an ability to influence the outcome of an inspection. Issues arising from activities and the relationship between the Inspection Body and the Supplier – example: commercial and financial pressures, personnel management, resources sharing, marketing, etc. – will not compromise the impartiality and independence of the service performed. [Local and Date]
____________________________________ [Inspection Body Name]
[Legal Representative of Inspection Body]
SPECIFICATION Nº
ET-0000.00-0000-972-1AL-001 REV.
C
SHEET -
TITLE:
QUALITY OF MATERIALS GENERAL REQUIREMENTS
PUBLIC
GQB
ANNEX I
Guideline for ITP Preparation
STAGE ITEM DESCRIPTION RECORD REFERENCE
DOCUMENT
ACCEPTANCE
CRITERIA
INTERVENTIONS NOTES
FA MI
Documentation
Insert
sequentia
l num
berin
g o
f in
spectio
n a
ctivitie
s in t
he o
rder
of
executio
n
Drawings,
procedures,
welding plans,
personnel
qualification, etc.
Defin
e t
he type o
f re
cord
to b
e issued b
y the m
anufa
ctu
rer
for
the r
espective a
ctivity
Lis
t sta
ndard
s, pro
cedure
s, te
chnic
al spe
cific
atio
ns a
pplic
able
to t
heir a
ctivity.
Report
editio
n a
nd r
evis
ion o
f docum
ents
.
Info
rm t
he ite
ms o
f th
e s
tandard
s, pro
cedure
s, te
chnic
al specific
atio
ns a
pplic
able
to their a
ctivity.
Indic
ate
the p
art
icip
atio
n o
f th
e m
anufa
ctu
rer's Q
ualit
y C
ontr
ol (d
ocum
ent
appro
val, d
ocum
ent
revie
w, m
onitorin
g
poin
t, w
itness p
oin
t and h
old
poin
t).
Indic
ate
the p
art
icip
atio
n o
f th
e R
IF o
r A
IB in t
he a
ctivitie
s o
f in
spection a
nd t
ests
(docum
ent appro
val, d
ocum
ent
revie
w, m
onitorin
g p
oin
t, w
itness p
oin
t and h
old
poin
t).
Inclu
de a
ny a
dditio
nal in
form
atio
n r
equired
Raw material
and Qualification
of welding
procedures,
NDE, tests etc.
Receiving
Inspection for
plates, forgings,
tubes,
consumables etc.
Inspections,
exams, tests
during
manufacturing
Relate inspections,
examinations, tests
and tests
throughout
manufacturing
Heat treatment
for stress relief
Full or partial
Equipment, oven or
located
Factory
Acceptance
Tests
Production,
hydrostatic, leak,
functional,
performance, etc.
Post-test
Inspection
Relate inspections
and exams after
final tests
Painting and
Coating
Surface
preparation,
controls during the
application and
inspections, tests
and assays
Final inspection
PMI, Visual,
Dimensional and
Inspection Records
Material Release
Spare parts,
packaging,
conditioning, data
book etc.
Subtitles:
FA (Fabricator): Manufacturer
MI (Manufacturing Inspection): RIF or AIB