Area 1 – Atascocita Shores Drive (Jan 22, 2020 to Feb 7, 2020)
Area 2 – Pine Shores Dr, Shoreview Lane, Shoreview Cir, Shady Cove Ln, Suncove Ln (Feb 10, 2020 to Feb 28, 2020)
Area 3 – Summit Pines Drive (Mar 2, 2020 to Mar 13, 2020) Area 4 – Pines Place Dr (From Pine Echo Dr to Atascocita Shore Dr)(Mar 16, 2020 to Mar 27, 2020) Area 5 – Pine Echo Dr (From FM 1960 to Nehoc Ln), Pine Shores Dr (Cul-de-sac), Pines Place Dr (From Pine Cluster Dr to Pine Echo Dr) (Mar 30, 2020 to Apr 10, 2020)
Area 6 – Timber View Dr, Nehoc Lane, Gamble Oak Dr, Autumn Creek Ln (Apr 13, 2020 to Jun 8, 2020)
Area 7 – Pines Place Dr (From Pine Cluster Dr to Dead End),Pine Cluster Dr, Pine Shores Dr (Jun 11, 2020 to Jun 29, 2020)
AREA 1
AREA 2
AREA 3
AREA 4
AREA 5
AREA 6
AREA 7
HCMUD 132- Waterline Replacement Phase 1 Phasing Plan