Upload
dangkiet
View
224
Download
0
Embed Size (px)
Citation preview
Memorial for the Claimant Team Code - Visscher
i
ARBITRATION INSTITUTE OF THE
STOCKHOLM CHAMBER OF COMMERCE
CALRISSIAN AND CO., INC. Claimant
v.
FEDERAL REPUBLIC OF DAGOBAH Respondent
___________________________
MEMORIAL ON BEHALF OF THE CLAIMANT
20 SEPTEMBER 2014
__________________________
Memorial for the Claimant Team Code - Visscher
ii
INDEX
TABLE OF ABBREVIATIONS IV
LIST OF AUTHORITIES VI
STATEMENT OF FACTS 1
ARGUMENTS ON JURISDICTION 3
Issue 1. The Tribunal has jurisdiction over the claims submitted by Calrissian and Co. 3
I. THE CLAIMANTS SUBMIT THAT THEY SATISFY THE CRITERIA OF RATIONE PERSONAE
AND RATIONE VOLUNTATIS 3
II. THE REQUIREMENT OF RATIONE MATERIAE IS SATISFIED AS SOVERIGN BONDS FULFIL
THE CRITERIA OF INVESTMENT UNDER ARTICLE 1 3
III. THE REQUIREMENTS IMPOSED BY THE BILATERAL INVESTMENT TREATY (‘BIT’)
ARE THE SOLE CRITERIA TO BE SATISFIED, AS THE REQUIREMENTS IMPOSED BY THE
INTERNATIONAL CONVENTION FOR SETTLEMENT OF INVESTMENT DISPUTES (‘ICSID’) ARE
INAPPLICABLE. 4
IV. IN ARGUENDO, THE BONDS COME UNDER THE AMBIT OF ‘INVESTMENT’ AS THEY
HAVE NOT BEEN EXPLICITLY EXCLUDED 5
V. THERE EXISTS A TERRITORIAL NEXUS WITH RESPECT TO THE INVESTMENT 5
ISSUE 2. That the Permanent Court of Arbitration’s interpretation is binding on this
tribunal 7
I. THE PRACTICAL EFFECT OF ARTICLE 7 OF THE BIT WAS TO ENSURE THE DECISION
BINDS THE TRIBUNALS UNDER ARTICLE 8 7
II. THE BIT EXPLICITLY PROVIDES FOR THIS AWARD TO BE BINDING ON THIS TRIBUNAL
8
III. IN ARGUENDO, THIS PROVIDES FOR AN AUTHORITATIVE INTERPRETATION OF THE
TREATY AND WOULD BE OF EXTREMELY HIGH PERSUASIVE VALUE TO THIS TRIBUNAL 8
ISSUE 3: The Tribunal should rule on the claim asserted despite of the forum selection
clause contained in the sovereign bonds 10
I. THE CLAIMS SUBMITTED AMOUNTS TO TREATY CLAIMS. 10
II. IN ARGUENDO, THE TRIBUNAL HAS JURISDICTION OVER CONTRACTUAL CLAIMS. 11
Memorial for the Claimant Team Code - Visscher
iii
III. THE FORUM SELECTION CLAUSE IS INEFFECTIVE. 12
ARGUMENTS ON MERITS 13
ISSUE 4. The measures of the Respondent State violate its obligations to accord Fair
and Equitable Treatment under Article 2(2) of the Corellia-Dagobah BIT. 13
I. THE RESPONDENT HAS VIOLATED THE LEGITIMATE EXPECTATIONS OF THE CLAIMANT.
13
II. THE RESPONDENT HAS BLOCKED ACCESS TO ANY EFFECTIVE REMEDY WITHIN ITS
JURISDICTION, WHICH CONSTITUTES DENIAL OF ACCESS TO JUSTICE. 14
III. THE RESPONDENT STATE HAS BREACHED ITS OBLIGATION TO ACCORD FULL
PROTECTION AND SECURITY TO THE BONDS. 15
ISSUE 5. The Respondent’s debt restructuring measures are not exempted under Article
6(2) of the BIT. 17
I. THE BURDEN TO PROVE THAT REQUIREMENTS OF ARTICLE 6(2) WERE MET LIES ON THE
RESPONDENT. 17
II. ARTICLE 25 OF THE INTERNATIONAL LAW COMMISSION’S ARTICLES ON STATE
RESPONSIBILITY (‘ARTICLE 25’) IS TO BE APPLIED TO INTERPRET THE TREATY DEFENSE
UNDER ARTICLE 6 OF THE BIT. 18
III. RESPONDENT’S ACTIONS DO NOT SATISFY ANY OF THE CONDITIONS STIPULATED FOR
THE APPLICATION OF ARTICLE 25. 18
IV. ARGUENDO, IN CASE THERE WAS A SITUATION OF NECESSITY THAT PRECLUDES
WRONGFULNESS, DAGOBAH WOULD STILL BE LIABLE TO PAY COMPENSATION. 21
RELIEF SOUGHT 22
Memorial for the Claimant Team Code - Visscher
iv
TABLE OF ABBREVIATIONS
Sl. No. Abbreviation Full Form
1. ¶ Para No.
2. Art. Article
3. BIT Bilateral Investment Treaty
4. Chap. Chapter
5. Ed. Edition
6. Eds. Editors
7. FET Fair and Equitable Treatment
8. FTC Free Trade Commission
9. HRI Human Health Research Institute
10. ICCPR International Covenant on Civil and Political Rights.
11. ICJ International Court of Justice
12. ICSID International Centre for Settlement of Investment Disputes
13. ILC International Law Commission
14. J.W.I.T. Journal of World Investment and Trade
15. NAFTA North American Free Trade Agreement
16. No. Number
17. O.U.P. Oxford University Press
18. p. Page No.
19. PCA Permanent Court of Arbitration
Memorial for the Claimant Team Code - Visscher
v
20. PCIJ Permanent Court of International Justice
21. Rep. Reports
22. SRA Sovereign Restructuring Act
23. U.S.A. United States of America
24. UDHR The Universal Declaration of Human Rights.
25. UN United Nations
26. UNCITRAL United Nations Commission on International Trade Law
27. UNCTAD United Nations Conference on Trade and Development
28. v. Versus
29. VCLT Vienna Convention on the Law of Treaties
30. Vol. Volume
31. WIPO World Intellectual Property Organization
32. YBIL Yearbook of International Law
Memorial for the Claimant Team Code - Visscher
vi
LIST OF AUTHORITIES
ARTICLES
Sl.
No.
Abbreviation Full Citation
1. Anthea Roberts Anthea Roberts, “State-to-State Investment Treaty Arbitration:
A Hybrid Theory of Interdependent Rights and Shared
Interpretive Authority", 55 HARVARD INTERNATIONAL
LAW JOURNAL, 1 (2014).
2. Anthea Roberts Anthea Roberts, “State-to-State Investment Treaty Arbitration:
A Hybrid Theory of Interdependent Rights and Shared
Interpretive Authority”, 55 HILJ 1 (2014).
3. Jan Paulsson Jan Paulsson, “Denial of Justice in International Law”,
Cambridge University press (2005).
4. Jeromin
Zettelmeyer
Jeromin Zettelmeyer, Christoph Trebesch, Mitu Gulati, “The
Greek Debt Restructuring: An Autopsy”, July 2013 available at
http://scholarship.law.duke.edu/cgi/viewcontent.cgi?article=534
3&context=faculty_scholarship.
5. Pauwelyn Joost Pauwelyn, “Role of Public International Law in the WTO:
How far can we go?”, 95 The American Journal of International
Law (2001).
6. Scheuer 2 Weiniger, Matthew and Scheuer, Conversations Across Cases -
Is there a Doctrine of Precedent in Investment Arbitration?
TDM 3 (2008).
7. Scheur 1 Christopher Scheuer, Towards Arbitral Path Coherence &
Judicial Borrowing: Persuasive Precedent in Investment
Memorial for the Claimant Team Code - Visscher
vii
Arbitration TDM 3 (2008).
8. Schreuer PIL Christoph Schreuer, The Relevance of Public International in
International Commercial Arbitration: Investment Disputes,
available at
http://www.univie.ac.at/intlaw/wordpress/pdf/81_csulpaper_1.p
df
9. Stanimir
Alexandrov
Stanimir Alexandrov, “Breaches of Contract and Breaches of
Treaty: The Jurisdiction of Treaty-based Arbitration Tribunals
to Decide Breach of Contract Claims in SGS v. Pakistan and
SGS v. Philippines”, 5 J. World Investment & Trade 555 (2004)
1
10.
Yuval Shany Yuval Shany, “Contract Claims vs. Treaty Claims: Mapping
Conflicts between ICSID Decisions on Multisourced Investment
Claims”, 99 The American Journal of International Law, No. 4
(2005)
BOOKS
Sl.
No.
Abbreviation Full Citation
1. - Brownlie, Brownlie's Principles of Public International Law,
Oxford University Press, (2012).
2. Muthucumaraswa
my
MUTHUCUMARASWAMY SORNARAJAH, THE
INTERNATIONAL LAW ON FOREIGN INVESTMENT, (3rd
ed. 2010).
3. - Villiger ME, Commentary on the 1969 Vienna Convention on
Memorial for the Claimant Team Code - Visscher
viii
the Law of Treaties (Martinus Ninjhof Publishers, 2009).
4. - Vienna Convention on the Law of Treaties a
Commentary (Oliver Dorr & Kirsten Schmalenbach eds.,
2012).
5. Crawford James Crawford, Brownlie’s Principles of Public International
Law, Oxford University Press (8th Ed. 2012)
6. Salacuse Jeswald W. Salacuse, The Law of Investment Treaties, (Oxford
University Press, 2010).
7. Sornarajah M. Sornarajah, International Law on Foreign Investment,
(Cambridge University Press, 2010).
8. James Crawford James Crawford, The International Law Commission’s Articles
on State Responsibility: Introduction, Text and Commentaries,
Cambridge University Press (2002).
9. Schreuer C Schreuer, The ICSID Convention: A Commentary
(Cambridge, Cambridge University Press, 2001)
ICSID CASES
Sl.
No.
Abbreviation Full Citation
1. AAPL v. Sri
Lanka
Asian Agricultural Products Limited v Sri Lanka, Final award
on merits and damages, ICSID Case No ARB/87/3 (21 June
1990).
2. Abaclat Abaclat and ors v Argentina, Decision on Jurisdiction and
Memorial for the Claimant Team Code - Visscher
ix
Jurisdiction Admissibility, ICSID Case No ARB/07/5 (04 August 2011)
3. ADF Group
Award
ADF Group Inc v. United States of America, ICSID Case No
ARB (AF)/00/1, Award, , (January 9, 2003).
4. Amco Asia
Jurisdiction
Amco Asia Corp Inc v The Republic of Indonesia , ICSID Case
No. ARB/81/1, Decision on Jurisdiction, 25 September 1983
5. Arif Award Arif v Moldova, Award, ICSID Case No ARB/11/23 (08 April
2013).
6. Azurix
Jurisdiction
Azurix Corp. v. The Argentine Republic, ICSID Case No.
ARB/01/12, Decision on Jurisdiction, (December 8, 2003)
7. CMS Annulment
committee
Decision
CMS Gas Transmission Company v Argentina, Decision on
Application for Annulment, ICSID Case No ARB/01/8 (25
September, 2007)
8. CMS award CMS Gas Transmission Company v. The Argentine Republic,
Award, ICSID Case No. ARB/01/8 (12 May, 2005)
9. Deutsche Bank
Award
Deutsche Bank AG v. Democratic Socialist Republic of Sri
Lanka, ICSID Case No. ARB/09/02, Award, (31 October 2012).
10. Duke Energy
Award
Duke Energy Electroquil Partners and Electroquil S.A. v.
Republic of Ecuador ICSID Case No. ARB/04/19, Award (18
August 2008).
11. Enron Award Enron Corporation Ponderosa Assets, L.P v. Argentine
Republic, Award, ICSID Case No. ARB/01/3 (22 March, 2007)
12. Impregilo
Jurisdiction
Impregilo S.P.A. v. Islamic Republic of Pakistan, Decision on
Jurisdiction, ICSID Case No. ARB/03/3 (22 April, 2005).
Memorial for the Claimant Team Code - Visscher
x
13. Lanco
Jurisdiction
Lanco International v. The Argentine Republic, Jurisdiction of
the Arbitral Tribunal, ICSID Case No. ARB/97/6 (8 December,
1998)
14. LG&E Award LG & E Energy Corp., LG & E Capital Corp., and LG & E
International, Inc. v. Argentine Republic, Award, ICSID Case
No. ARB/02/1 (25 July, 2007).
15. Lucchetti Award Empresas Lucchetti, S.A. v. Republic of Peru, ICSID Case No.
ARB/03/4, Award (Feb. 7, 2005)
16. National Grid
Award
National Grid Public Limited Company v Argentina, Award,
UNCITRAL, IIC 361 (2008) (03 November 2008).
17. Noble Ventures
Award
Noble Ventures, Inc. v. Romania, Award, ICSID Case No.
ARB/01/11 (12 October, 2005)
18. Pantechniki v.
Albania
Pantechniki SA Contractors and Engineers v Albania, Award,
ICSID Case No ARB/07/21 (28 July 2009).
19. Parkerings-
Compagniet
Award
Parkerings - Compagniet AS v. Republic of Lithuania, Award,
ICSID Case No. ARB/05/8 (11 September, 2007).
20. Saipem
Jurisdiction
Saipem S.p.A. v. The People’s Republic of Bangladesh (ICSID
Case No. ARB/05/07), Decision on Jurisdiction and
Recommendation on Provisional Measures of 21 March 2007.
21. Salini Jurisdiction Salini Costruttori S.p.A. and Italstrade S.p.A. v. Morocco,
ICSID- Case-No. ARB/00/4, Decision on Jurisdiction, (July 23,
2001).
22. Sempra Award Sempra Energy International v. Argentine Republic, Award,
Memorial for the Claimant Team Code - Visscher
xi
ICSID Case No. ARB/02/16 (28 September, 2007)
23. SGS v. Pakistan
Jurisdiction
SGS Société Générale de Surveillance S.A. v. Islamic Republic
of Pakistan, Decision of the Tribunal on Objections to
Jurisdiction, ICSID Case No. ARB/01/13 (6 August, 2003)
24. SGS v.
Philippines
Dissent
SGS Société Générale de Surveillance S.A. v. Republic of the
Philippines, ICSID Case No. ARB/02/6, Dissenting Opinion of
Professor A. Crivellaro.
25. SGS v.
Philippines
Jurisdiction
SGS Société Générale de Surveillance S.A. v. Republic of the
Philippines, Decision of the Tribunal on Objections to
Jurisdiction, ICSID Case No. ARB/02/6 (29 January, 2004).
26. Siemens Award Siemens AG v Argentina, Award and Separate Opinion, ICSID
Case No ARB/02/8 (06 February 2007)
27. Southern Pacific
Properties
Jurisdiction
Southern Pacific Properties (Middle East) Ltd. V. Arab
Republic of Egypt, ICSID Case No. REP 131, Decision on
Jurisdiction, (April 14, 1988).
28. Suez Award Suez and ors v Argentina, Decision on Liability, ICSID Case No
ARB/03/17 (03 August 2006).
29. Vivendi I
Annulment
Compañia De Aguas Del Aconquija S.A. and Vivendi Universal
v. Argentine Republic, Decision on Annulment, ICSID Case No.
ARB/97/3 (3 July, 2002)
30. Vivendi I Award Compañia De Aguas Del Aconquija S.A. and Vivendi Universal
v. Argentine Republic, Award, ICSID Case No. ARB/97/3 (21
November, 2000)
31. Vivendi II Award Compañia De Aguas Del Aconquija S.A. and Vivendi Universal
Memorial for the Claimant Team Code - Visscher
xii
v. Argentine Republic, Award, ICSID Case No. ARB/97/3 (21
November, 2004)
32. Zaire Award American Manufacturing & Trading, Incorporated v Zaire,
Award and separate opinion, ICSID Case No ARB/93/1 (11
February 1997).
OTHER CASES
Sl.
No.
Abbreviation Full Citation
1. Alps Award Alps Finance and Trade AG v. Slovak Republic, UNCITRAL
Investor-State Claim, Award (March 5, 2011).
2. East Timor The case concerning East Timor I.C.J. Reports 1995
3. Gabchikovo-
Nagymyros Project
Case
GabcikovoNagymaros Project (Hungary v
Slovakia) [1997] ICJ Rep. 7.
4. Romak Award Romak S.A.(Switzerland) v . The Republic of Uzbekistan,
UNCITRAL, PCA Case No. AA280 (1976).
5. Saluka award Saluka Investments B.V. v. The Czech Republic, Partial Award,
UNCITRAL Arbitration Proceedings (17 March, 2006).
6. Soci n ale
Jurisdiction
Soci n ale v. ominican Republic, LCIA Case No. UN
7927, Decision on Jurisdiction (September 19, 2008).
7. Whaling case Whaling in the Antartic (Australia v. Japan) ICJ March 2014
available at http://www.icj-cij.org/docket/files/148/18136.pdf.
Memorial for the Claimant Team Code - Visscher
xiii
MISCELLANEOUS
Sl.
No.
Full Citation
1. Augustin Landier and Kenichi Ueda, “The Economics of Bank Restructuring:
Understanding the Options” available at
https://www.imf.org/external/np/seminars/eng/2012/fincrises/pdf/ch15.pdf.
2. Committee on Foreign & Comparative Law, New York Bar Association, “Governing
Law in Sovereign Debt –Lessons from the Greek Crisis and Argentina Dispute of
2012”, available at http://www2.nycbar.org/pdf/report/uploads/20072390-
GoverningLawinSovereignDebt.pdf.
3. IMF, “Collective Action Clauses in Sovereign Bond Contracts—Encouraging Greater
Use”, available at https://www.imf.org/external/np/psi/2002/eng/060602a.pdf.
Memorial for the Claimant Team Code - Visscher
1
STATEMENT OF FACTS
I. The Bilateral Investment Treaty
1. The Federal Republic of Dagobah (“Dagobah”) and the Corellian Republic (“Corellia”)
entered into the Agreement in 1992 for the Promotion and Protection of Investments
(“BIT”). The BIT provided for a definition of protected investments and contained
standard clauses of protection such as national treatment, fair and equitable treatment, full
protection and security and protection against expropriation
II. 2001 Financial Crisis and Proposed Sovereign Debt Restructuring
2. In 2001 Dagobah was faced with an unsustainable debt burden and descended into a two-
and-a-half year long economic crisis. Dagobah’s inability to meet its debt obligations led
its government to restructure its sovereign debt and launch an offer according to which
bondholders would be able to exchange their bonds for new ones which woul reduce the
bonds’ face value by 43%. Such proposed restructuring could cause losses to
bondholders, among which were several investors from Corellia. The IMF presented
certain recommendations for Dagobah to appropriately implement the sovereign debt
restructuring process.
III. The Permanent Court of Arbitration’s Award
3. Corellia decided to ensure the protection of Corellian bondholders by trying to clarify the
language of the BIT, which did not include an express reference to sovereign bonds under
the definition of investments. Despite Diplomatic relations the parties were not able to
agree on whether the treaty covered sovereign bonds or not. Pursuant to Article 7 of the
BIT, Corellia commenced arbitral proceedings against Dagobah, administered by the
Permanent Court of Arbitration (“PCA”), providing for State-to-State dispute settlement,
requesting a decision on the interpretation issue.
4. On 29 April 2003, the PCA Arbitral Tribunal finally decided, by majority, that sovereign
bonds were investments within the definition of the BIT and that bondholders of both
countries were entitled to its standards of protection and to resort to the investor-State
dispute settlement provision included therein. On 19 May 2003, the dissenting arbitrator
presented his opinion, in which he held that sovereign bonds could not constitute an
Memorial for the Claimant Team Code - Visscher
2
investment in accordance with the wording of the BIT. By then, Corellian bondholders
had already accepted a restructuring offer made by Dagobah, which only represented
losses of less than 20% of the net present value.
IV. Terms of the Sovereign Restructuring Act
5. At the beginning of 2010, a new recession hit Dagobah and on 14 September 2011, the
IMF issued a recommendation stating that “although Dagobah has for the most part
followed the IMF’s recommendations after the crisis of 2001, its debt, now estimated at
more than U$ 400 billion, is unsustainable”, and suggesting several measures which
included the implementation of a new sovereign debt restructuring
6. On 28 May 2012, Dagobah enacted the Sovereign Restructuring Act (“SRA”) applicable
to all bonds governed by Dagobah’s law, which provided that if a qualified majority of
the owners of 75% of the aggregate nominal value of all outstanding bonds governed by
domestic law agreed to modify the terms of the bonds, that decision would bind all the
remaining bondholders. Before the adoption of the SRA, the affected bonds did not allow
for amendment unless all bondholders agreed to it.
7. In contrast to the old bonds, which were governed by Dagobah’s law and contained a
forum selection clause granting exclusive jurisdiction to Dagobah’s courts over any
disputes arising therefrom, the new bonds were governed by the law of the Kingdom of
Yavin. The new bonds also included provisions regulating collective action (Collective
Action Clauses, ‘CACs’), which related both to the collective change of the bond terms as
well as to the enforcement of any of the current bonds’ contractual obligations. The CACs
provided that if bondholders wanted to initiate any legal action, they would need to gather
at least 20% of the nominal value of the issue in order to sue. Such a clause was absent in
the old bonds.
V. Submission before the tribunal constituted under the rules of the Arbitration
Institute of the Stockholm Chamber of Commerce
8. On 30 August 2013, Calrissian & Co., a Corellian hedge fund that holds a number of
sovereign bond, was among the holdout minority under the SRA, commenced arbitral
proceedings before the SCC pursuant Article 8 of the BIT on issues relating to
interpretation of “investments” and breach of Fair and Equitable Treatment.
Memorial for the Claimant Team Code - Visscher
3
ARGUMENTS ON JURISDICTION
ISSUE 1. THE TRIBUNAL HAS JURISDICTION OVER THE CLAIMS SUBMITTED BY CALRISSIAN
AND CO.
9. The Claimant submits that
a. The claimant satisfy the criteria of ratione personae and ratione voluntatis.
b. The requirement of ratione materiae is satisfied as soverign bonds fulfil the criteria of
investment under Article 1.
c. The requirements imposed by the BIT are the sole criteria to be satisfied, as the
requirements imposed by the ICSID are inapplicable.
d. In arguendo, The bonds come under the ambit of ‘investment’ as they have not been
explicitly excluded.
e. There exists a territorial nexus with respect to the investment.
I. THE CLAIMANTS SUBMIT THAT THEY SATISFY THE CRITERIA OF RATIONE PERSONAE AND
RATIONE VOLUNTATIS
10. An ‘investor’ includes “a national of a Party” which is defined as any legal person
established in the Territory of one of the Parties in accordance with the respective
national legislation.1 The Claimant is a hedge fund incorporated in and in accordance with
the laws of, the Corellian Republic.2 Thus, the Claimants satisfy the criteria of ratione
personae. ‘Ratione voluntatis’ has been satisfied upon the submission of a request for
arbitration by the Claimant.3 This request was voluntarily done, satisfying the second
jurisdictional requirement.
II. THE REQUIREMENT OF RATIONE MATERIAE IS SATISFIED AS SOVERIGN BONDS FULFIL
THE CRITERIA OF INVESTMENT UNDER ARTICLE 1
11. Soverign Bonds are an investment as the three indicative requirements present in the
chapeau of the BIT has been fulfilled. There is the commitment of capital or other
1 Article 1, BIT.
2 Appendix 6, Para 2.
3 Appendix 6, Para 1.
Memorial for the Claimant Team Code - Visscher
4
resources, the expectation of gain or profit, or the assumption of risk.4 While this risk has
been quantified to be of a higher threshold for an investment, and the dissenting opinion
of the PCA Award stated that this ‘risk’ must have more than the risk of default,5 it is
submitted that Article 1 does not require that standard to be met. The laundry list includes
“mortgages, pledges and liens”6 where the only risk is that of default. In fact in
investments such as mortgages, there is the property as security which reduces the
quantum of risk. Thus the standard of risk contemplated within Article 1 is not a high
standard envisaged but a lower standard that must be read in light of the “context” of the
treaty, which is indicative in the laundry list.7
12. Further, it cannot be argued that “typical characteristics” such as ‘duration’ which have
been a requirement in general standard is applicable under Article 1. Portfolio
investments, which have a small duration such as “shares, stock”8, are included within the
ambit of the laundry list. Thus, it is indicative that the treaty does not seek to exclude
portfolio investments.
III. THE REQUIREMENTS IMPOSED BY THE BILATERAL INVESTMENT TREATY (‘BIT’) ARE
THE SOLE CRITERIA TO BE SATISFIED, AS THE REQUIREMENTS IMPOSED BY THE
INTERNATIONAL CONVENTION FOR SETTLEMENT OF INVESTMENT DISPUTES (‘ICSID’)
ARE INAPPLICABLE.
13. When the treaty elucidates a standard for an ‘investment’ that must be followed and not
the general standard which has laid down. This is due to treaty standards prevailing over
the general standard laid down for any definition.9 A requirement to conform to general
objective standards laid down while interpreting the scope of an ‘investment’ would
render the necessary of defining an ‘investment’ a nullity.10
Further, the decisions which
4 Article 1, BIT.
5 Appendix 3, ¶ 92-93.
6 Article 1, Illustration (vi).
7 Article 31, VCLT.
8 Article 1, Illustration (ii).
9 Brownlie, Brownlie's Principles of Public International Law, Oxford University Press, (2012).
10 Article 31, VCLT.
Memorial for the Claimant Team Code - Visscher
5
lay down these objective standards11
are requirements by tribunals under ICSID and
cannot bind this Tribunal12
which has been constituted under the SCC.
IV. IN ARGUENDO, THE BONDS COME UNDER THE AMBIT OF ‘INVESTMENT’ AS THEY HAVE
NOT BEEN EXPLICITLY EXCLUDED
14. Occidental v. Equador has laid down the principle that when a term requires to be
interpreted in favour of either party, it must be interpreted in the favour of the investor. In
that case, the held that unless the State had particularly exempted a certain item from the
protection of the treaty, it will be considered within the ambit of protection, if the
protection is uncertain and if it is in favour of the investor.13
There are many BITs which
have explicitly excluded sovereign bonds from the ambit of “investment” as defined
under their treaty.14
Further the broad principle of a treatment favourable to an investor
has been codified in the treaty, most notably under Article 10, where if any rule or
obligation provides a treatment more favourable to an investor, such a rule supersedes the
BIT.15
V. THERE EXISTS A TERRITORIAL NEXUS WITH RESPECT TO THE INVESTMENT
15. The bonds are governed under Dagobah’s laws and hence, Dagobah exercises requisite
control over them.16
This control can be seen by enacting the SRA17
or by the Haircut
offered after the first financial crisis.18
Further, the bonds were utilized for the benefit of
the Dagobah and their place of transfer is immaterial.19
The capital from bondholders is
indirectly made available within the territory of the host state as part of a larger economic
11
Salini Award; Romak Award.
12 Muthucumaraswamy, p. 306.
13 Occidental v. Equador
14 Mexico-India BIT; US-Baharain BIT; Croatia-Azerbaijan BIT; NAFTA.
15 Article 10, BIT.
16 Abaclat Jurisdiction.
17 Facts of the Case, ¶ 17.
18 Facts of the Case, ¶ 4.
19 Ambient Officio v. Argentina.
Memorial for the Claimant Team Code - Visscher
6
transaction.20
The identity of a bond holder is immaterial, as the bondholder, upon
maturity of the bond, would have to redeem the investment from Dagobah, hence
providing sufficient territorial link. Further, an investment need not be connected to a
specific enterprise or a specific economic venture located in the territory of either state to
quantify as an investment.21
Thus, the lack of a connection with a specific enterprise does
not bar a sovereign bond from being an investment made in the territory of the Republic
of Dagobah.
20
Abaclat Jurisdiction.
21 Deutsche Bank Award.
Memorial for the Claimant Team Code - Visscher
7
ISSUE 2. THAT THE PERMANENT COURT OF ARBITRATION’S INTERPRETATION IS BINDING
ON THIS TRIBUNAL
16. The Claimant submits that
a. The practical effect of Article 7 of the BIT was to ensure this decision binds the
tribunals under Article 8.
b. The BIT explicitly provides for this award to be binding on this tribunal
c. In arguendo, this provides for an authoritative interpretation of the treaty and would
be of extremely high persuasive value to this Tribunal
I. THE PRACTICAL EFFECT OF ARTICLE 7 OF THE BIT WAS TO ENSURE THE DECISION BINDS
THE TRIBUNALS UNDER ARTICLE 8
17. In the regime of Investment Arbitration, disputes between two States have been a rarity,
and have never been successfully pursued.22 Standard dispute resolution clauses in BITs
are to address issues that arise between an investor and a State. In this context, Article 7
of the BIT was purely for the interpretation of the BIT and not for a concrete legal
dispute. The effect of the 2003 PCA decision was that “that sovereign bonds were
investments within the definition of the Corellia-Dagobah BIT and that bondholders of
both countries were entitled to its standards of protection and to resort to the investor-
State dispute settlement provision included therein”.
18. Thus, the effect in that case would be to ensure that there is an entitlement to the terms of
this treaty as investors and the right to access the forum for dispute resolution incase of a
breach. If this award not binding on any Tribunal constituted under Article 8, the purpose
of Article 7 would be nullified. The effect of discarding the PCA judgment would render
the purpose of inserting Article 7 useless in the bilateral investment treaty, if all the
arbitrations for interpretation are not of any use in the Investor-State treaty tribunal,
where the rights investors derive from treaty would be realised.
19. While this Tribunal can exercise mandate over “any legal dispute”23, the tribunal would
have to exercise its powers in accordance with this agreement and any relevant rules of
international law.24 The VCLT to which both states are parties too requires an agreement
22
Anthea Roberts. 23
Article 8 (1), BIT.
24 Article 8 (3), BIT.
Memorial for the Claimant Team Code - Visscher
8
to be interpreted in good faith25, and thus neither party would have intended to have a
useless provision, which they have undertaken as binding, in accordance with the
applicable rules of international law.26
II. THE BIT EXPLICITLY PROVIDES FOR THIS AWARD TO BE BINDING ON THIS TRIBUNAL
20. While there is no hierarchy between Tribunals and one Tribunal would not normally be
bound by the decision of the other, the BIT can restrict the scope of an arbitral tribunal.
Article 10 of the BIT allows for “obligations under international law” which are
“established hereafter between the Parties in addition to the present Agreement”,
“entitling investments by investors of the other Party to a treatment more favourable than
is provided for by the present Agreement, such rules shall to the extent that they are more
favourable prevail over the present Agreement.”27 An arbitration award, which the parties
have declared to be binding, is an ‘obligation under international law which has been
established between the Parties in addition to this Agreement’ and the obligation, as long
as it is favourable to investors will prevail over this agreement. Thus, this tribunal, which
is bound to decide based on the BIT would have to consider the Award binding on a
reading of Article 7(2), Article 8(3) and Article 10.
III. IN ARGUENDO, THIS PROVIDES FOR AN AUTHORITATIVE INTERPRETATION OF THE TREATY
AND WOULD BE OF EXTREMELY HIGH PERSUASIVE VALUE TO THIS TRIBUNAL
21. It is submitted that the decision of the Permanent Court of Arbitration, which is
considered the forum to resolve disputes regarding interpretation, is an authoritative
interpretation of the BIT.28 An authoritative interpretation can be by the Parties that
drafted the treaty, or can be authorized to interpret the treaty by the Parties.29 This
interpretation given by the PCA is an obligation by the Parties,30 and the authorization for
25
Article 31, VCLT.
26 Article 7 (2), BIT.
27 Article 10, BIT.
28 Article 31 (3) (b), VCLT.
29 Villiger ME, COMMENTARY ON THE 1969 VIENNA CONVENTION ON THE LAW OF TREATIES (Martinus Ninjhof
Publishers, 2009).
30 Article 7 (2), BIT.
Memorial for the Claimant Team Code - Visscher
9
the PCA to interpret arose from the provisions of the treaty itself.31 An authoritative
interpretation is considered to reflect the intent, context, purpose and meaning of the
treaty,32 and must be used to interpret the treaty.33
31
Article 7 (1), BIT.
32 VIENNA CONVENTION ON THE LAW OF TREATIES A COMMENTARY (Oliver Dorr & Kirsten Schmalenbach eds.,
2012).
33 ADF
Group Award, ¶177.
Memorial for the Claimant Team Code - Visscher
10
ISSUE 3: THE TRIBUNAL SHOULD RULE ON THE CLAIM ASSERTED DESPITE OF THE FORUM
SELECTION CLAUSE CONTAINED IN THE SOVEREIGN BONDS
22. The Claimant submits that
a. That the claims submitted before this tribunal amounts to treaty claim.
b. In arguendo, this tribunal can exercise jurisdiction over contractual claims.
c. The contractual forum selection clause in ineffective.
I. THE CLAIMS SUBMITTED AMOUNTS TO TREATY CLAIMS.
23. Article 8 (2) (c) of the BIT vests ‘any legal dispute between an investor of one Party and
the other Party in connection with an investment’ in case of failure of negotiations to the
binding jurisdiction of this tribunal.
24. In the instant case, the existence of a legal dispute which is defined as ‘a disagreement on
a point of law or fact, a conflict of legal views or interests between parties’34 as well as
the status of nationality of claimants is not disputed. What is disputed is whether the
existence of a contractual forum selection clause could affect the jurisdiction over or the
admissibility of the claims presented.
25. It is submitted that the distinction between treaty and contract claims is well established.35
The breach of an investment contract can simultaneously give rise to independent claims
under a treaty as well as a contract as both claims requires different inquiries.36 Rights
asserted under a contract and those under a treaty are essentially different37 and both can
be claimed under their respective dispute resolution clause.38
26. If a breach of contract at the same time violates a treaty provision applicable between an
investor and the host state, it will give rise to the international responsibility of the host
state.39 The present claims are against the Republic of Dagobah for violation of BIT and
not for the violation of rights under the Sovereign bonds.
27. It is submitted that the task of the Tribunal at this stage consists only in determining
whether the facts alleged by the claimant, if established, are capable of constituting a
34
East Timor, pp. 89, 99.
35 SGS v. Uruguay Jurisdiction ¶ 128.
36Impregilo Jurisdiction, ¶ 258.
37 Azurix Award, ¶54.
38 Vivendi I Award, ¶ 102; Lanco Jurisdiction, ¶ 28; Azurix Award, ¶ 79.
39 Noble Ventures Award, ¶ 53.
Memorial for the Claimant Team Code - Visscher
11
breach of the provisions of the BIT which have been invoked,40 as for this tribunal to
assume jurisdiction, there has to be a breach of a substantive treaty provision,41 which in
the present case is Article 2 (2) of the BIT.
28. A prima facie violation of Article 2 (2) is established by the failure of Republic of
Dagobah in providing fair and equitable treatment to its investors by ignoring any concept
of proportionality in responding to its temporary financial crisis and imposing arbitrary
regulatory and legislative measures and therefore the claims in the instant case constitute
treaty claims.42
29. Moreover, when in exercise of sovereign power, the equilibrium of the contract and the
provisions contained therein are unilaterally altered by a Host State; the origin and nature
of such power are totally foreign to the contract.43 In other words, the present dispute does
not derive from the mere fact that Dagobah failed to perform its payment obligations
under the bonds but from the fact that it intervened as a sovereign by virtue of its State
power44 to modify its payment obligations towards its creditors in general, encompassing
but not limited to the Claimants and therefore this dispute cannot be considered a mere
contractual dispute.
II. IN ARGUENDO, THE TRIBUNAL HAS JURISDICTION OVER CONTRACTUAL CLAIMS.
30. It is submitted that the wording of Article 8 of BIT i.e. ‘any dispute’ is wide enough to
include both treaty claims as well as contractual claims with respect to an investment
under its ambit and therefore even if the tribunal holds that the present dispute represent a
contractual claim, the tribunal still possess the jurisdiction.45 Interpreting the said phrase
in light of Article 31 of VCLT also justifies such an interpretation.46
31. Moreover, the difference between respective wording of Article 7 and Article 8 of BIT
also justifies a broader interpretation of Article 8. Article 7 restricts the nature of disputes
40
Saipem Jurisdiction §§ 84.
41 SGS v. Pakistan Jurisdiction, ¶ 162.
42 Abaclat Jurisdiction ¶ 314.
43 Abaclat Jurisdiction ¶ 321.
44 SGS v. Pakistan Jurisdiction, ¶ 260.
45 SGS v. Philippines Jurisdiction.
46 Stanimir Alexandrov pp. 573
Memorial for the Claimant Team Code - Visscher
12
to ‘issues concerning the interpretation or application of this Agreement’ whereas Article
8 includes ‘any legal dispute in connection with an investment’. Such difference in
wording clearly indicates the intent of the Parties to the BIT to include disputes not based
on treaty within the ambit of Article 8.
III. THE FORUM SELECTION CLAUSE IS INEFFECTIVE.
32. When there exist a possibility of treaty claim based on treaty violation, then the treaty
tribunal will have exclusive jurisdiction over such claims regardless of the existence of a
contractual forum selection clause or simultaneous contract claim.47 The contractual
forum cannot oust the jurisdiction of this tribunal over treaty claims.48
33. Moreover, mere incorporation of an exclusive forum selection clause in a contract
without an express waiver of the rights of remedy under the treaty is insufficient to
amount as an implied waiver and cannot prevent this tribunal from exercising its
jurisdiction.49
34. Alternatively, the remedy under Article 8 and the forum selection clause in sovereign
bonds ‘survive and coexist’. They function as simultaneous remedies available to an
investor and thus the forum selection clause ceases to be an “exclusive” forum from the
investor’s perspective.50
47
SGS v. Pakistan Jurisdiction; SGS v. Philippines Jurisdiction; Yuval Shany pp. 842
48 Azurix Jurisdiction ¶262.
49 Aguas del Tunari v. Bolivia Jurisdiction ¶ 119, SGS v. Uruguay Jurisdiction ¶ 179.
50 SGS v. Philippines Dissent ¶ 2.
Memorial for the Claimant Team Code - Visscher
13
ARGUMENTS ON MERITS
ISSUE 4. THE MEASURES OF THE RESPONDENT STATE VIOLATE ITS OBLIGATIONS TO
ACCORD FAIR AND EQUITABLE TREATMENT UNDER ARTICLE 2(2) OF THE CORELLIA-
DAGOBAH BIT.
35. The Claimant submits that
a. The debt restructuring measures of the Respondent violated the legitimate
expectations of the Claimant.
b. The Respondent State had blocked access to any effective remedy within this
jurisdiction, which constitutes denial of access to justice.
c. The Respondent State has breached its obligation to accord full protection and
security to the bonds.
I. THE RESPONDENT HAS VIOLATED THE LEGITIMATE EXPECTATIONS OF THE CLAIMANT.
36. The protection of a foreign investor’s legitimate expectations has been repeatedly
identified as the dominant element of the FET standard51. To be protected, the investor’s
expectations must be reasonable and justified based on the conditions and representations
offered by the host State. The concept includes not just explicit affirmations given by the
government but also the reasonable and basic expectations taken into account by the
investor52.
37. The arbitral tribunal in Suez stated it is the aggregate of the existence of expectations
created in a foreign investor by host country’s laws, coupled with the act of investing
capital in reliance on them and a subsequent, sudden change in that legislative framework
that constitutes a violation of the FET standard53.
38. It is in light of these views that the Claimant submits that the actions of the Respondent
have not adhered to the legitimate expectations requirement on two occasions:
i. The Respondent’s restructuring measures and subsequent partial default on the
sovereign bonds;
51
Saluka Award; Bayindir v. Pakistan Award.
52 Azurix Award; Parkerings-Compagniet Award.
53 Suez Award.
Memorial for the Claimant Team Code - Visscher
14
ii. Retrofit application of the Collective Action Mechanism [CAM] contained in the
SRA.
39. The investment by the Claimant into sovereign bonds, thus entering into a long-term
contractual relationship with the Respondent State, shows that it was acting upon the
basic premise of a stable legal investment environment. Stability and predictability of the
regulatory framework is quintessential to the FET standard54, and has also been
recognized as an important objective by the State parties in the Preamble of the Corellia-
Dagobah BIT55.
40. The enactment of the SRA was an abuse of sovereign power by the Respondent to
exercise coercion and unilaterally modify its contractual obligations, which could not
have been reasonably anticipated by the Claimant. Furthermore, the Claimant contends
that the incorporation of the retroactive Collective Action Mechanism [CAM] through the
SRA, unilaterally modified not only the contractual terms of the bonds by way of
legislation but also the legal framework governing the contractual obligations of the
parties56.
41. The bonds were issued in 2003, after the Respondent has already encountered a sovereign
debt crisis. During the bond issuance or any period before or after it, the Respondent had
not shown the slightest inclination to consider the incorporation of CAMs in its bonds.
Since a CAM did not originally exist in the bond terms, the Claimant had a legitimate
expectation that its investment will not be subject to a debt restructuring process unless it
had expressly consented to it.
42. The Arif tribunal reached the conclusion that over time, legitimate expectations grow and
strengthen insofar as the investment is cultivated57. Thus, the acts of the Respondent have
frustrated the legitimate expectations of the Claimant and this in itself constitutes a
violation of the FET standard.
II. THE RESPONDENT HAS BLOCKED ACCESS TO ANY EFFECTIVE REMEDY WITHIN ITS
JURISDICTION, WHICH CONSTITUTES DENIAL OF ACCESS TO JUSTICE.
54
Enron Award, ¶260, 267- 268.
55 Preamble, the BIT
56 SRA, Article 2 (8).
57 Arif Award.
Memorial for the Claimant Team Code - Visscher
15
43. Within the Preamble of the BIT, the State parties have been careful to recognize the
“importance of providing effective means of asserting claims and enforcing rights with
respect to investment under national law as well as through international arbitration”58.
44. The bonds that had been purchased by the Claimant were governed by Dagobahian law
and were subject to the exclusive jurisdiction of the courts of Dagobah59. But the SRA
provides that in the event of a successful bond exchange, all rights and obligations under
the old bonds will be extinguished60. Moreover, as the SRA has already been deemed
constitutional in a review prior to its enactment, there are no means available under
national law to challenge the validity of the SRA within the jurisdiction of Dagobah61.
45. Therefore, there is no effective remedy available to the Claimant under national law to
enforce its contractual rights derived from the old bonds or challenge the validity of the
SRA.
III. THE RESPONDENT STATE HAS BREACHED ITS OBLIGATION TO ACCORD FULL PROTECTION
AND SECURITY TO THE BONDS.
46. It is emphasized that the terms “protection” and “security” are qualified by the term “full”
in Article 2(2) of the BIT. It cannot be reasonably construed to be limited to merely
physical security of an investment because the term “investment” as defined in Article 1
includes not only tangible assets but also intangible assets such as intellectual property
rights62.
47. While interpreting a similar provision as Article 2(2), the arbitral tribunal in Biwater
Gauff opined that the clause implies “a State’s guarantee of stability in a secure
environment, both physical, commercial and legal”, a view that has been accepted by
several arbitral tribunals63. The content of the obligation incumbent on the host State
extends to ensuring that the agreed and approved security of the foreign investor’s
58
Preamble, the BIT.
59 Facts of the Case, ¶ 20.
60 SRA, Article 2 (8).
61 Procedural Order No. 2, ¶ 22.
62 Article 1, the BIT.
63 Siemens Award; Vivendi Award, National Grid Award.
Memorial for the Claimant Team Code - Visscher
16
investment is withdrawn or devalued by the amendment of its laws or the actions of its
administrative bodies64.
48. The Claimant contends that first, by the retrofit application of CAM through the SRA, the
Respondent has withdrawn the previously agreed security of the Unanimous Action
Clause [UAC] in the bonds bought by the Claimant. Before the SRA, any amendment of
the bonds, even a restructuring process, required the express consent of all the
bondholders65. Second, the bond exchange offer on 29 November 2012 issued by the
Ministerial Council, an administrative authority under the SRA, devalued the value of the
bonds held by the Claimant. The offer is the sine qua non for the devaluation of the bonds
as all the terms and conditions of the bond exchange were fixed by the Ministerial
Council and the participation of the investors was restricted to “whether they accept…”
the offer66.
49. In light of these circumstances, it is submitted the Respondent’s actions have breached the
obligation to accord full protection and security to the investment of the Claimant.
64
CME Award.
65 Facts of the Case, ¶ 17.
66 Article 2(1), SRA.
Memorial for the Claimant Team Code - Visscher
17
ISSUE 5. THE RESPONDENT’S DEBT RESTRUCTURING MEASURES ARE NOT EXEMPTED
UNDER ARTICLE 6(2) OF THE BIT.
50. The Claimant submits that
a. The burden to prove that requirements of Article 6(2) were met lies on the
Respondent.
b. Article 25 of the International Law Commission’s Articles on State Responsibility
(‘Article 25’) is to be applied to interpret the treaty defense under Article 6 of the
BIT.
c. Respondent’s actions do not satisfy any of the conditions stipulated for the application
of Article 25.
d. Arguendo, in case there was a situation of necessity that precludes wrongfulness,
Dagobah would still be liable to pay compensation.
I. THE BURDEN TO PROVE THAT REQUIREMENTS OF ARTICLE 6(2) WERE MET LIES ON THE
RESPONDENT.
51. Article 6 (2) of the BIT reads as follows:
52. “Nothing in this Treaty shall be construed: (2) to preclude a Party from applying measures
that are necessary for the fulfilment of its obligations with respect to the maintenance or
restoration of international peace or security, or the protection of its own essential
security interests.”67
Article 6(2) is a Not-Precluded Measures (NPM) clause which, if
applicable, would preclude liability of the host State for breach of substantive obligations
under the BIT. The intention behind such a provision in the BIT is to preserve some legal
flexibility for the State to able to take the necessary measures in exceptional
circumstances.
53. Since Article 6(2) operates as an exception to the other provisions and obligations
contained in the BIT, the burden to prove that all the requirements of Article 6(2) are
satisfied and it is applicable in the present case rests on the Respondent.
67
Article 6 (2), BIT.
Memorial for the Claimant Team Code - Visscher
18
II. ARTICLE 25 OF THE INTERNATIONAL LAW COMMISSION’S ARTICLES ON STATE
RESPONSIBILITY (‘ARTICLE 25’) IS TO BE APPLIED TO INTERPRET THE TREATY DEFENSE
UNDER ARTICLE 6 OF THE BIT.
54. A plain reading of Article 6 of the BIT shows that the provision does not lay down any
standards or criteria to adjudge the necessity of measures or what constitutes ‘essential
security interests’. Therefore, since the BIT itself does not offer any guidance, the content
of this exceptional provision must be found in customary international law. This approach
has been favoured by arbitral tribunals68, especially while interpreting Article XI of the
U.S.-Argentina BIT which is couched in similar language as Article 6 of the Corellia-
Dagobah. Further, Article 8(2) mandates that the arbitral tribunal shall decide the disputes
in accordance with any ‘ elevan ules of in e na ional law’69.
55. The very object of conclusion of the BIT was to apply in situations of economic difficulty
to guarantee the rights of investors of both States70. Since Article 6 allows a State to
override all of the substantive protections guaranteed to investors, it must be subject to a
stringent threshold, which the Claimant submits, may be found in Article 25.
56. Article 25 reflects the defense of necessity as it exists in customary international law71. It
has been held to be a “most exceptional remedy subject to very strict conditions because
otherwise it would open the door to elude any international obligation”72. Therefore,
Article 25 must be used to interpret the treaty defense under Article 6 of the BIT.
III. RESPONDENT’S ACTIONS DO NOT SATISFY ANY OF THE CONDITIONS STIPULATED FOR
THE APPLICATION OF ARTICLE 25.
57. Article 25 lays down the following conditions for the operation of the defense of
necessity:
i. The measure adopted by the State must be to protect itself from a grave and
imminent peril;
68
Sempra Award; Enron award; CMS Award.
69 Article 8(2), BIT.
70 Suez Award.
71 Gabchikovo- Nagymyros Project Case.
72 Ibid.
Memorial for the Claimant Team Code - Visscher
19
ii. It must be the only way available to the State;
iii. The State must not have contributed to the situation of necessity.
58. It is emphasized that for successful invocation of the defense of necessity, the Respondent
must prove that all of these conditions are met. The Claimant only needs to show that any
one of these is not satisfied.
i. Grave and imminent peril
59. The only ‘peril’ that the Respondent may claim in the present case is the debt burden that
the IMF has recognized as “unsustainable”73. But the threshold requires the peril to be
‘grave and imminent’, that is, gravity of the peril must be such that it will lead to
complete political and social collapse and compromise the very existence of the State74.
60. There is no evidence that the political and social framework of the State was on the brink
of collapse. The demonstrations and social unrest was triggered by the impact of the 2008
financial crisis on the economy of Dagobah75 and had not acquired such proportions that
the Respondent could not have reasonably controlled the state of affairs through the
exercise of its legitimate police powers and adequate structural reforms.
61. The arbitral tribunals in Enron and Sempra, when faced with similar circumstances of
economic distress cited by the Argentine Republic, acknowledged the severity of the
crisis but determined that it had not compromised “the very existence of the State and its
independence.”76 They further noted that the dangers presented by social unrest and
political stability could be, and in fact were, handled under the constitutional
arrangements in force77.
62. Thus, it is submitted that the economic distress of the Respondent does not meet the
threshold of ‘grave and imminent peril’.
ii. Only way available to the State
73
Facts of the Case, ¶ 15.
74 CMS Award.
75 Procedural Order no. 3, ¶ 38.
76 Enron award, ¶ 306.
77 Enron Award, ¶ 306; Sempra Award, ¶ 348.
Memorial for the Claimant Team Code - Visscher
20
63. According to Article 25, a State, in order to invoke the necessity doctrine, must have no
means to guard its vital interest other than breaching its international obligation. If it was
possible for the State to take recourse to other alternative measures, even if they were
more difficult or costly, could safeguard the interest of the State, those alternative steps
should be taken78.
64. The Claimant submits that debt restructuring and partial default on the bonds cannot be
reasonably presumed as the only means open to the Respondent. The State of Dagobah
could have taken recourse to options such as privatization of public services to reduce the
unsustainable debt burden79. Other States such as Chile have used debt-for-equity swaps
for privatization of government assets and simultaneous reduction of debt80.
65. It is not the intention of the Claimant to substitute its judgment for the judgment of the
government of the Respondent. The only burden incumbent on the Claimant is to show
that alternative measures were available to the Respondent, which is satisfied in the
present case.
iii. No contribution of the State to the situation of necessity
66. Article 25 prohibits the invocation of the necessity defense by a State if the State has
contributed to the situation of necessity, in a way that is “sufficiently substantial and not
merely incidental or peripheral”81.
67. The Claimant contends that the Respondent has substantially contributed to the financial
crisis. Flawed government policies and shortcomings exacerbated the impact of the 2008
financial crisis on the economy of Dagobah. The government of Dagobah has had a long
history of negligent policies; in 2001, it had already encountered a state of financial crisis
because of its heavy borrowing from international markets and a conscious failure on its
part to check massive tax evasion. Even subsequently, it chose to not change its expansive
borrowing policy or adopt structural reforms to increase revenue82. The government of
78
James Crawford, pp. 160–86.
79 Augustin Landier and Kenichi Ueda, “The Economics of Bank Restructuring: Understanding the Options”
available at https://www.imf.org/external/np/seminars/eng/2012/fincrises/pdf/ch15.pdf.
80 Ibid.
81 James Crawford, pp. 160–86.
82 Appendix 4.
Memorial for the Claimant Team Code - Visscher
21
Dagobah continued to ignore the prevalence of massive tax evasion within the country
even asit adopted austerity measures after the 2008 crisis but the combination of the two
only led to the crisis becoming “even more pronounced and amplified the government’s
revenue crisis”83.
68. Thus, the Respondent has contributed to the financial crisis and should not be allowed to
take advantage of its own wrong.
IV. ARGUENDO, IN CASE THERE WAS A SITUATION OF NECESSITY THAT PRECLUDES
WRONGFULNESS, DAGOBAH WOULD STILL BE LIABLE TO PAY COMPENSATION.
69. Article 27 of the Articles on State Responsibility reads:
70. “The invocation of a circumstance precluding wrongfulness in accordance with this
chapter is without prejudice to:
(a) Compliance with the obligation in question, if and to the extent that the circumstance
precluding wrongfulness no longer exists;
(b) The question of compensation for any material loss caused by the act in question.”
71. In the event that the Respondent prevails and is able to successfully invoke the defense of
necessity, the Claimant contends that that does not mean that the Claimant is not entitled
to compensation for the material loss that it has suffered to its investment. Therefore, the
defense of necessity in itself does not negate the claim for compensation.
72. In the instant case, the Claimant contends that the Respondent must compensate it for the
thirty percent haircut on the net value of the sovereign bonds that it holds. Thus, the State
of Dagobah may not have incurred responsibility for violation of an international
obligation but it is still liable for compensation.
83
Ibid.
Memorial for the Claimant Team Code - Visscher
22
RELIEF SOUGHT
The Claimant respectfully prays to the Tribunal for the following relief-
Declare that the Tribunal has jurisdiction over this dispute.
Declare that the retroactive effects of Respondent’s Sovereign Restructuring Act, as
well as other measures conducted by that state as part of its sovereign debt
restructuring, violated Respondent’s obligations under Art. 2 of the Corellia-Dagobah
BIT.
Declare that Claimant is entitled to full compensation for the losses it incurred as a
result of Dagobah’s violations, including interest.
Declare that Claimant is entitled to the restitution by Respondent of all costs related to
these proceedings.
Counsels for the Respondent
Team Visscher
20 September 2014