  • February 1993 - Construction Safety Manual: Table of Contents Page 1

    SAUDI ARAMCO CONSTRUCTION SAFETY MANUAL

    PREFACE Dhahran, Saudi Arabia

    February, 1993

    The purpose of the Saudi Aramco Construction Safety Manual (CSM) is to prevent injury, loss of life, and damage to assets. This is the fourth revision of the CSM. Since its 1974 introduction, the Construction Safety Manual has provided safety criteria for all construction work performed by Saudi Aramco and its contractors.

    Many of the requirements in this manual detail the need for Saudi Aramco services or equipment. Where references indicate that certain equipment (fall protection, safety shoes, etc.) should be provided or services rendered (bio-monitoring, etc.), the intent is that contractors must provide equivalent equipment or services (as approved by Saudi Aramco) from their own resources.

    The construction industry functions in a dynamically changing work environment in which updating of equipment and standards is a continuous process resulting from changes in operating variables, regulatory requirements, and safety practices. Although this manual has been updated to reflect the latest Saudi Aramco and construction industry practices, as time goes on there may be a need to consider new procedures, standards, or operating conditions. Such new developments, including potential conflicts with existing provisions, should be referred to the Loss Prevention Department for resolution. The Loss Prevention Department will issue interim revisions or updates where appropriate.

    Good loss prevention is an integral part of good project management. For our projects and maintenance programs to proceed safely, all Saudi Aramco and contractor personnel involved in construction activities, whether management or line employees, need to understand and follow the provisions in this Manual. Only with the active commitment of everyone can we ensure that Saudi Aramco maintains the safest possible work environment.

    Senior Vice President, Engineering and Project Management

  • February 1993 - Table Of Contents Page 2

    I. Administration.................................................................................30

    1.0 SAUDI ARAMCO LOSS PREVENTION POLICY AND PROGRAM......................................31 1.1 Loss Prevention Policy Implementation.................................................................31

    1.1.1 Compliance With Construction Requirements .......................................31 1.1.2 Operating Standards and Instructions.....................................................31 1.1.3 Personal Protection.....................................................................................31 1.1.4 Inspection ....................................................................................................31 1.1.5 Education and Training..............................................................................32 1.1.6 Motivation and Recognition .....................................................................32 1.1.7 Job Placement ..............................................................................................32 1.1.8 Response to Accidental Occurrences......................................................32 1.1.9 Contractor Safety ........................................................................................32 1.1.10 Off-The-Job Safety......................................................................................32 1.1.11 Traffic Safety................................................................................................32 1.1.12 Accountability.............................................................................................33 1.1.13 Compliance Reviews ...................................................................................33

    1.2 Saudi Aramco Loss Preve ntion Requirements For Contractors.......................33 1.2.1 Non-Compliance..........................................................................................33 1.2.2 Assistance....................................................................................................33 1.2.3 Standards and Instructions .......................................................................34

    1.3 Contractor's Loss Prevention Program.................................................................34 1.3.1 Written Program..........................................................................................34 1.3.2 Hazard Identification Plan..........................................................................35 1.3.3 Safety Supervisor........................................................................................35 1.3.4 Safety Discussion .......................................................................................35

    2.0 SAUDI ARAMCO LOSS PREVENTION DEPARTMENT SERVICES ....................................36 2.1 Loss Prevention Program.........................................................................................36 2.2 Program Management Services ..............................................................................37 2.3 Program Maintenance Services ..............................................................................38

    3.0 ACCIDENT INVESTIGATION, ANALYSIS AND REPORTING..............................................39 3.1 Reports Required by Saudi Aramco........................................................................39 3.2 Accident Investigation ...............................................................................................40

    3.2.1 Responsibilities for Investigation.............................................................40 3.2.1.1 Supervisor/Safety Representative............................................40 3.2.1.2 Project Manager..........................................................................40

    3.3 Cases to be Investigated.............................................................................................41 3.4 Accident Investigation Guidelines...........................................................................41 3.5 Accident Analysis ....................................................................................................41

    3.5.1 Classification................................................................................................41

    4.0 RESPONSIBILITIES FOR SAFETY...............................................................................................45 4.1 Contractor Senior Management..............................................................................45 4.2 Design Engineer.........................................................................................................45 4.3 Contractor's Safety Officer......................................................................................45 4.4 Construction Manager/Superintendent.................................................................46 4.5 Site Safety Supervisor ...............................................................................................47 4.6 Equipment Manager/Supervisor ..............................................................................47 4.7 Engineer/Supervisor..................................................................................................47

  • February 1993 - Table Of Contents Page 3

    4.8 Foreman........................................................................................................................47 4.9 Worker.........................................................................................................................48

    5.0 EMERGENCY PROCEDURES .........................................................................................................49 5.1 Action to be Taken......................................................................................................49 5.2 Contact After Office Hours ......................................................................................49 5.3 Help in an Emergency................................................................................................49

    6.0 SAFETY TRAINING...........................................................................................................................51 6.1 Safety Training for Supervisors..............................................................................51 6.2 Safety Training for Workmen.................................................................................51

    6.2.1 Integrated Practices ....................................................................................51 6.2.2 Specialized Training....................................................................................52 6.2.3 Use of Persuasion .......................................................................................52 6.2.4 Course Requirements..................................................................................52

    6.3 Scope of Training .......................................................................................................53 6.3.1 Safety Training Topics For Supervisors ..................................................54 6.3.2 Induction Safety Topics For Workmen ...................................................55

    7.0 SITE PLANNING AND HOUSEKEEPING.....................................................................................57 7.1 Initial Planning ...........................................................................................................57

    7.1.1 Hazard Identification Plan..........................................................................57 7.1.2 Loss Prevention Program...........................................................................58 7.1.3 Protection of Emplo