2 X 363.3 Combined Cycle Gas Power Project Palatana, Tripura Presentation at Ministry of Development of North Eastern Region, Government of India. April 25, 2011 www.otpcindia.in New Delhi. Contents. Background Project Highlight Power Allocation - PowerPoint PPT Presentation
Citation preview
2 X 363.3 Combined Cycle Gas Power Project
Palatana, Tripura
Presentation
atMinistry of Development of
North Eastern Region,Government of India
April 25, 2011 www.otpcindia.inNew Delhi
Contents
Background Project Highlight Power Allocation Project Location Gas Supply Network of ONGC Project Status : Clearances & Permits Project Status : Supply and Construction Project Status : Erection Logistics Status of Inputs Areas of Concern Assistance Required
October 29, 2005
LAYING OF FOUNDATION STONE
Source of Inspiration
Project Highlight
Capacity: 2 x 363.3 MW
Type: Gas Based Combined Cycle
Location: Palatana, Tripura
Project Cost: Rs 3,429 Crore
Source of Fuel: ONGC’s Gas Field in Tripura
Type of Fuel: Natural Gas
Quantity of Fuel: 2.65 MMSCMD
Source of Water: River Gumti
Quantity of Water: 125 MLD
Promoters: ONGC (50%), IL&FS (26%), GOT (0.5%).
Project Highlight …… Contd
EPC Contractor: Bharat Heavy Electricals Limited (BHEL)
Award of Contract: 23-Jun-08
Commissioning: Unit-1: 22-Dec-11,
Unit-2: 22-Mar-12
Evacuation: 650 KM 400 KV D/C Palatana – Bongaigaon Line
Power Allocation
Power Allocation by MoP
Beneficiary State Pro-rata allocation in MW based on actual capacity of 726.6 MW
Tripura 196
Assam 240
Arunachal Pradesh 22
Nagaland 27
Mizoram 22
Manipur 42
Meghalaya 79
Power allocated to OTPC 98
Project Location
650 kms 400 kV D/C line
Byrnihat S/S
Ajara S/S
Silchar S/S
Konaban GGSKunjaban Manifold
Nimbutali
Sonamura GGS
Agartala Dome GGS(ADB)
Palatana
Sundalbari Manifold
16” 12km Pipeline
(Sector–II)
8” 19.5km Pipeline
(Sector-IV)
6” 19.5km Pipeline
(Sector-V)
20” 41km Pipeline (Sector-I)
20” 12km Pipeline
(Sector –I)
8” 12.5km Pipeline
(Sector –VI)6” 12.5km
Pipeline(Sector-VII)
16” 22km Pipeline
(Sector – III)
BagabasaSectionalizing Valve Station
F1A : Facility F1 (Early)F1B : Facility F1 (as per NOA)F 2 : Facility F2
Gas Supply from ONGC – Tripura Asset
F1A
F1A
F1B
F2F2
F2
Project Status: Clearances and Agreements
Clearance received from MOEF, TSPCB, AAI, MOD
State Support Agreement Signed
206 Acres of Land Acquired for the project
Shareholders Agreement, Gas Sale & Purchase Agreement and Power
Purchase Agreement signed.
Long Term Service Agreement signed with OEM (GE) for Gas Turbine
Project Status : Supply & Construction
SUPPLIES
All ODC to be transported through Bangladesh dispatched from BHEL works. Transportation of ODC from Kolkata to Ashuganj in Bangladesh started in February’11 and last consignment expected to reach Bangladesh in May’11.
Supplies of non-ODCs to be transported via Gauhati started in Mar-10 and last dispatch from BHEL works for Unit-1 & Unit-2 is expected by Jun-11 and Sep-11 respectively.
CIVIL CONSTRUCTION
Piling and foundation of major buildings for Unit-1 completed and main plant equipment erection started in Jan-11.
Major structures for Unit-2 are likely to be ready for erection by Jun-11.
Work for Cooling Tower and Water Treatment System has commenced. CT-1 is likely to be commissioned in Sep-11 and Water Treatment System is likely to be commissioned in Jul-11
Construction of River Water Intake Pump house and pipeline has commenced and likely to be commissioned by Jul-11.
Project Status : Erection
ERECTION
Main Plant equipment erection started in Jan-11
Milestone Target Date
UNIT-1
Mechanical Completion Sep-11
Hydro test Completion Nov-11
Readiness for commissioning Dec-11
UNIT-2
Mechanical Completion Dec-11
Hydro test Completion Feb-12
Readiness for commissioning Mar-12
Routes: Kolkata – Ashuganj – Palatana Kolkata – Karimgunj - Palatana
Routes for transportation of ODCs from Kolkata: There are two routes available for transportation of ODCs to Palatana site:
Via Karimganj: 1318 KM (river) + 320 KM (road - India)
Via Ashuganj (Bangladesh): 856 KM (river) + 115 KM (road – India + B’dsh)
Ashuganj route has been selected because river route is navigable through out the year and road route passes through generally plain land leading to less risk in transportation.
Hon’ble Prime Minister of Bangladesh during her visit to India in Jan-10 agreed to allow movement of ODC through Ashuganj in Bangladesh. Since then, Ashuganj has been included in Indo-Bangla Water Transport Proto-call and MOU has been signed with GOB on 29th November 2010 formally allowing movement of ODCs through Bangladesh territory.
90 ODCs shall be transported through Bangladesh. Construction of bypasses in between Ashuganj (Bangladesh) and Palatana (Tripura) has breen completed.
13 ODCs have reached site, 2 are likely to reach site within 2-3 days and balance ODCs are expected to reach site progressively by Jun-11.
Logistics – Overview
PROJECT – STATUS OF INPUTS
Commissioning Gas Start-up Power Evacuation System
Responsible agency ONGC TSECLNETCL / POWERGRID /
NER STATES
Latest required – to meet commissioning schedule
August ’11 May’11 November’11
Current StatusConstruction has
started
Contract for line construction awarded
Slow progress
Construction started but moving at tardy
pace.
OTPC assessment No delay Delay of 3 Months
Delay of 3 months (up to Silchar)
Delay of 6-9 months (up to Bongaigaon)
Impact on unit#1 No impact Delay of 3 monthsLikely delay of 3
months
Impact on Unit#2 No impact No impactLikely delay of 6/9
months
SILCHAR – BONGAIGAON TRANSMISSION LINE
Delay in Forest Clearance in Meghalaya (25 KM) and Assam (22 KM) – NETCL
EVACUATION CONSTRAINT: PALATANA – BONGAIGAON
Delay in construction of Azara, Byrnihat and Surajmaninangar sub-station – Assam / Meghalaya / Tripura
Delay in construction of 400 kV Silchar sub-station – POWERGRID
Delay in construction of Palatana – Silchar Line – NETCL / POWERGRID
DOWNSTREAM NETWORK BY BENEFICIARY STATES
Work yet to commence by States i.e. Assam, Tripura, Mizoram etc for absorption of power. Unit-1 commissioning may be delayed on this account. – NER States
States to absorb Unit-1 power:
Assam : 120 MW Meghalaya: 40 MW
Tripura: 98 MW Manipur: 21 MW
Mizoram: 11 MW Nagaland: 14 MW
Arunachal: 11 MW
AREAS OF CONCERN
Immediate Forest Clearance in Assam (22 KM), Meghalaya (25 KM) and Tripura (4 KM) required.
State governments to expedite development of Azara (Assam), Byrnihat (Meghalaya) and Surajmaninagar (Tripura) sub-station and downstream network to match Unit-1 commissioning in Dec-11
States to advise POWERGRID to install series-compensation facility at Bongaigaon sub-station.
Government of Tripura to expedite construction of 132 KV line and provide startup power by May-11
POWERGRID to expedite construction of 400 kV Silchar substation to match with Unit-1 commissioning in Dec-11.
NETC and POWERGRID to expedite construction of 400 kV D/C Palatana – Silchar Line