April 2012 April 2012 April 2012 Program UpdateProgram UpdateProgram Update
OPSB & RSD Phase I ProjectsOPSB & RSD Phase I ProjectsOPSB & RSD Phase I Projects
Program Financial Status
Status Date: 30 April 2012
Note-The value in each phase represents the total of full project budgets.
The OPSB has $38.6 million in open contracts for the Phase 1 capital program projects after issuing no new contracts, change orders and amendments in April. In addition, the total change orders to date, $493 thousand, accounts for approximately two percent (1.87%) of the total open Phase 1 construction contracts. Finally, OPSB anticipates issuing $12 million in contracts in Phase 1 construction and $175 thousand in professional services contracts/amendments in May.
The RSD has $344 million in open contracts for the Phase 1 capital program projects after issuing no new contracts and $175 thousand in change orders and amendments in April. In addition, the total change orders to date, $7 million, accounts for approximately two percent (2.22%) of the total open Phase 1 construction contracts. Finally, RSD anticipates issuing no Phase 1 construction contracts and $6 thousand professional services contracts/amendments in May.
Program Schedule Status
Value of Projects by Phase
Design 132,172,141$
Procurement -$
Construction 228,835,275$
Complete 188,604,903$
Future Projects 25,958,218$
Group 1ProjectMahalia JacksonEdward Hynes School
Group 2ProjectAudubon SchoolLake Forest SchoolAlice Harte SchoolEleanor L. McMain SchoolMcDonogh 35 HS (Phillips/Waters)New PK-8 at North Kenilworth Park
Occupied (May 2010)
Procurement Construction Complete
Occupied (January 2012)
Design
OPSB Phase 1 Projects
Design Procurement Construction CompleteGroup 1
ProjectGuste ESLangston Hughes ESAndrew H. Wilson ESLake Area HSL.B. Landry HSJoseph A. Craig ESFannie C. Williams ESWilliam Frantz ESJean Batiste de Bienville ESParkview ESMildred Osborne ESCarter G. Woodson ESCharles J. Colton ESLawrence D. Crocker ES
Group 2ProjectBooker T. Washington HSPhillis Wheatley ESLittle Woods ESGeorge W. Carver HSEdward Livingston HSNew PK-8 Algiers
Complete
Occupied (August 2009)Occupied (January 2010)Occupied (January 2010)
Occupied (July 2010)
Procurement Construction Complete
Procurement Construction
RSD Phase 1 Projects
DesignOccupied (August 2008)
Design
Occupied (January 2010)
Value of Projects by Phase
Design 122,008,893$
Procurement 12,579,532$
Construction -$
Complete 41,531,174$
Future Projects 22,567,408$
Superintendents’ Report
April 2012
Mr. Darryl Kilbert
Orleans Parish School Board
Mr. John White
Louisiana Department of Education
Mr. Patrick Dobard
Recovery School District
Prepared by:
Status Date: April 30, 2012 1
Table of Contents
TABLE OF CONTENTS ....................................................... 1 OVERVIEW ............................................................................ 3 COMMUNITY MEETINGS ................................................. 4 BID OPENINGS...................................................................... 4 NEW & MAJOR RENOVATION – PROJECT STATUS . 5
Audubon School (OPSB)
.................................................. 5
Jean Batiste de Bienville School (RSD)
........................... 5 Stuart R. Bradley School
(RSD) ...................................... 5
George Washington Carver School (RSD)
...................... 6 Charles J. Colton School
(RSD) ....................................... 6
Lawrence D. Crocker School (RSD)
................................ 7
William Frantz School (RSD)
.......................................... 7
Alice Harte School (OPSB)
.............................................. 8 Edward Hynes School
(OPSB) ........................................ 8
New PK-8 School at North Kenilworth Park at Curran
Site (OPSB)
....................................................................... 9 Alfred Lawless School
(RSD) ......................................... 9
McDonogh #35 School (Phillip/Waters Site) (OPSB)
... 10 Eleanor L. McMain School
(OPSB) .............................. 11
Mildred Osborne School (RSD)
..................................... 12 Parkview School
(RSD) ................................................. 12
Booker T. Washington School (RSD)
............................ 13
Phillis Wheatley Elementary School (RSD)
.................. 13
Fannie C. Williams School (RSD)
................................. 14 Little Woods School
(RSD) ........................................... 14
Carter G. Woodson School (RSD)
................................. 15
OTHER PROJECTS ............................................................ 15 Arthur Ashe Elementary School
(OPSB) ........................ 15
Benjamin Franklin Senior High School (OPSB)
............ 16 Walter L. Cohen High School
(RSD) ............................. 16
A. D. Crossman Elementary School and Benjamin
Banneker Elementary School (RSD)
............................. 16 Warren Easton School
(OPSB) ...................................... 17
Frances Gaudet/Lake Forest Elementary School (RSD)
17 William J. Guste Elementary School
(RSD) ................. 18
Murray G. Henderson Elementary School (RSD)
......... 18
Langston Hughes School (RSD)
................................... 18
Andrew Jackson School (RSD)
..................................... 19 Mahalia Jackson Elementary School
(OPSB) ................. 19
Mahalia Jackson Elementary School Office Renovation (OPSB)
............................................................................ 20 John McDonogh High School
(RSD) ............................. 20
Dr. Martin Luther King Jr. Charter School (RSD)
........ 20
Status Date: April 30, 2012 2
Lafayette Elementary School (RSD)
.............................. 21
Live Oak Elementary School (RSD)
.............................. 21 McDonogh #15 Elementary School
(RSD) .................... 22
Sarah T. Reed High School (RSD)
................................. 22
Village de’Lest Elementary School (RSD)
.................. 22 Sylvanie Williams Elementary School
(RSD) ............... 23
Dwight D. Eisenhower Elmentary School (RSD)
......... 23 Andrew Jackson Elementary School
(RSD) ................. 23
Paul B. Habans Elementary School (RSD)
................... 23
Sylvanie F. Williams Elementary School (RSD)
.......... 23 Joseph S. Clark Senior High School
(RSD) ................... 23
Dr. Martin Luther King Charter School (RSD)
.............. 23 Albert Wicker Elementary School
(RSD) ..................... 23
A. P. Tureaud Elementary School (RSD)
................... 23 Edgar P. Harney Elementary School
(RSD) ................. 23
Harriet R. Tubman Elementary School (RSD)
.............. 23 Building Automation System Integration At Recovery
School District Central And Remote Offices (RSD)
..... 24
MOTHBALLING OF CLOSED SCHOOLS – SAFE &
SECURE ................................................................................ 24 Louis D. Armstrong Elementary School
(RSD)) ............ 24
Israel M. Augustine Middle School (RSD)
................... 25
Andrew J. Bell Junior High School (RSD)
................... 26 Oretha C. Haley Elementary School
(RSD) .................. 26
Lorraine Hansberry Elementary School (RSD)
............. 27
Morris F. X. Jeff Elementary School (RSD)
................. 27
Valena C. Jones Elementary School (RSD)
.................. 28 George Mondy Elementary School
(RSD) ..................... 28
John A. Shaw Elementary School (RSD)
....................... 28
DEMOLITION PROJECTS ................................................ 29 Greater St. Stephens School
(RSD) ................................ 29
Oretha C. Haley Elementary School (RSD)
.................. 29 L. B. Landry Annex Demolition
(RSD) ........................ 29
Mary Church Terrell Elementary School Demolition (RSD) )
............................................................................ 30 Booker T. Washington High School Demolition
(RSD)30
COMPREHENSIVE LIST - COMPLETED PROJECTS 30
Status Date: April 30, 2012 3
Overview
Recovery School District:
The RSD has $417 million in open contracts for the capital program
after issuing $81 thousand in new contracts and $8.7 million in
change orders and amendments in April. In addition, the total
change orders to date, $8.3 million, account for approximately two
percent (2.5%) of the total open construction contracts. RSD
anticipates issuing approximately $2.4 million in construction contracts
and $36 thousand in professional service contracts/amendments in
May.
Orleans Parish School Board:
The OPSB has $50.3 million in open contracts for the capital program
after issuing no new contracts, change orders or amendments in
April. In addition, the total change orders to date, $840 thousand,
account for approximately three percent (2.88%) of the total open
construction contracts. OPSB anticipates issuing approximately $16
million construction contracts and professional service contracts in
May.
Status Date: April 30, 2012 4
Community Meetings
April 5th:
McDonogh #35 School [#4], 1331 Kerlerec Street, New
Orleans, LA 70116, 6:00 – 8:00 p.m.
May 8th:
Fisk Howard Elementary [#3], 3401 Canal Street, New Orleans,
LA 70119, 6:00 – 8:00 p.m.
May 15th:
Paul L. Dunbar [#3], 3613 Cambronne Street, New Orleans, LA
70118, 6:00 – 8:00 p.m.
May 16th :
PreK-8 at North Kenilworth Park at Curran – TBD
May 17th:
Livingston Community Meeting [#1], 8358 Lake Forest
Boulevard, New Orleans, LA 70126, 6:00 – 8:00 p.m.
May 22nd:
Stuart R. Bradley [#3], 4128 Franklin Avenue, New Orleans, LA
70122, 6:00 – 8:00 p.m.
May 23rd:
McDonogh #35 [#5], 1331 Kerlerec Street, New Orleans, LA
70116, 6:00 – 8:00 p.m.
May 24th :
Dr. Charles R. Drew [#1] – 3819 St. Claude Avenue, New
Orleans, LA 70117, 6:00 – 8:00 p.m.
Bid Openings
Over the next sixty days, bids will be received for the following projects:
Lorraine Hansberry Mothballing and Safe/Secure (RSD) – April 5th
Langston Hughes Dumpster Pad Demolition (RSD) – May 1st
Israel Augustine Mothballing and Safe/Secure (RSD) – June 5th
Eleanor McMain New Gym and Stabilization (OPSB) – June 14th
Sylvanie Williams AHU Replacement (RSD) – June 19th
Andrew Jackson Solar Panel Installation (RSD) – June 26th
George Washington Carver (RSD) – June 28th
Status Date: April 30, 2012 5
New & Major Renovation – Project Status
Audubon School (OPSB)
[428 Broadway Avenue, New Orleans, LA 70118]
Scope of work: Renovation & Addition of Existing Elementary School
Funding Source – FEMA
Architect – Blitch/Knevel Architects
Contractor – FHP Tectonics Corporation
Procurement Phase
The construction contract is being processed and OPSB is
expected to issue the Notice to Proceed in May
Anticipated Contractual Substantial Completion – Fall 2013
Forecasted Substantial Completion – Fall 2013
School Ready for Occupancy – Fall 2013
Jean Batiste de Bienville School (RSD)
[1456 Gardena Drive, New Orleans, LA 70122]
Scope of work: New Pre-K – 8 School
Funding Source – FEMA
Architect – Howard Performance Architecture
Contractor – Walton Construction – a CORE Company, LLC
Construction Phase
Flooring is 85% complete
Mechanical/Electrical/Plumbing punch work is in process
Millwork is 85% complete
Testing and Balancing is progressing
Contractual Substantial Completion – April 2012
Forecasted Substantial Completion – May 2012
School Ready for Occupancy – July 2012
Stuart R. Bradley School (RSD)
[ 2401 Humanity Street, New Orleans, LA 70122]
Scope of work: New 3-Section Elementary School
Funding Source – FEMA
Architect – Sizeler Thompson Brown Architects
Contractor – TBD
Status Date: April 30, 2012 6
Design Phase
Program Completion documents were approved on April 16th
Design Advisory Committee (DAC) Meeting – May 2nd
Community Meeting #3 – May 22nd
Anticipated Contractual Substantial Completion – August 2014
Forecasted Substantial Completion – August 2014
School Ready for Occupancy – November 2014
George Washington Carver School (RSD)
[3019 & 3059 Higgins Blvd., New Orleans, LA 70126]
Scope of work: New High School
Funding Source – FEMA
Architect – Trapolin Architects & VMDO Architects, A Joint- Venture
Contractor – TBD
Procurement Phase
100% Construction Documents were received on April 25th
1st Advertisement – May 24th
2nd Advertisement – May 31st
3rd Advertisement – June 7th
Pre-Bid Conference – 10:00 a.m. on June 12th at
Jacobs/CSRS Program Management, 909 Poydras Street,
Suite 1200, New Orleans, LA
Bid Opening – June 28th
Anticipated Contractual Substantial Completion – April 2014
Forecasted Substantial Completion – April 2014
School Ready for Occupancy – August 2014
Charles J. Colton School (RSD)
[2300 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Renovation of existing elementary school and new addition
Funding Source – FEMA
Architect – Waggonner & Ball Architects
Contractor – F.H. Paschen, S.N. Nielsen & Associates, LLC
Construction Phase
Interior block work is 95% complete
The new slab for the addition has been poured
Status Date: April 30, 2012 7
Installation of the roof fill on the existing building is complete
Roofing has commenced
Rear addition is enclosed with sheathing
Storm drain is tied into the City drain lines
Mechanical/Electrical/Plumbing rough-in work is ongoing
Building should be watertight in late May
Contractual Substantial Completion – November 2012
Forecasted Substantial Completion – December 2012
School Ready for Occupancy – January 2013
Lawrence D. Crocker School (RSD)
[2300 General Taylor Street, New Orleans, LA 70115]
Scope of work: New PK-8 School
Funding Source – FEMA
Architect – Chenevert Architects LLC
Contractor – Satterfield and Pontikes Construction Group, LLC
Construction Phase
Exterior brick continues on classroom wing
Window frame installation continues
Interior partition installation continues in the Classroom wing
Electrical and mechanical installation continues
Permanent utilities will be activated in May
Classroom wing will be dried-in in early May
Contractual Substantial Completion – March 2012
Forecasted Substantial Completion – July 2012
School Ready for Occupancy – August 2012
William Frantz School (RSD)
[3811 North Galvez Street, New Orleans, LA 70117]
Scope of work: Renovation of existing elementary school and new addition
Funding Source – FEMA
Architect – Billes Architecture, LLC
Contractor – The Lathan Company, Inc.
Construction Phase
Mechanical/Electrical/Plumbing rough-in continues in the new and existing building
Status Date: April 30, 2012 8
Installation of the storefront and curtain wall system is nearly complete
Window installation has commenced on all floors of the new building
Installation of the metal wall panel is ongoing
Acoustical tile grid installation has commenced in the existing building
Sheetrock installation continues in the new building
Tape and float work is ongoing
Painting of CMU and sheetrock is ongoing in both buildings
Ceramic tile installation in the new building restrooms continue
Contractual Substantial Completion – March 2012
Forecasted Substantial Completion – October 2012
School Ready for Occupancy – January 2013
Alice Harte School (OPSB)
[5300 Berkley Drive, New Orleans, La 70131]
Scope of work: New Pre-K – 8 School
Funding Source – CDBG & FEMA
Architect – WDG Architects Engineers
Contractor – TBD
Design Phase
Architect was issued the Notice to Proceed for the redesign
work on April 6th
The design is expected to be completed by June 4th
Anticipated 1st Advertisement – Mid June 2012
Anticipated Re-Bid – Late July 2012
Anticipated Contractual Substantial Completion – December 2013
School Ready for Occupancy – Spring 2014
Edward Hynes School (OPSB)
[900 Harrison Avenue, New Orleans, LA 70124]
Scope of work: New Pre-K – 8 School
Funding Source – FEMA
Architect – Imre Hegedus & Associates Architects
Contractor – Woodrow Wilson Construction Company, Inc.
Status Date: April 30, 2012 9
Close- Out Phase
Substantial Completion was executed
Punch list and close out work continues
Farnsworth building commissioning commenced in April
Contractual Final Completion – April 27, 2012
Forecasted Final Completion – April 27, 2012
New PK-8 School at North Kenilworth Park at Curran Site (OPSB)
[8500 Curran Boulevard, New Orleans, LA 70127]
Scope of work: New Pre-K– 8 School
Funding Source – FEMA
Architect – Mathes Brierre Architects
Contractor – TBD
Design Phase
100% Design Development documents were received on April
27th
Community meeting will be scheduled in May
Contract was awarded to Sea-level Construction for the
test pile program
Pre-construction meeting for the test pile program was
held on April 30th
Anticipated Contractual Substantial Completion – May 2014
School Ready for Occupancy – August 2014
Alfred Lawless School (RSD)
[5300 Law Street, New Orleans, LA 70117]
Scope of work: New High School
Funding Source – FEMA
Architect – Sizeler Thompson Brown Architects
Contractor – TBD
Design Phase
Architect was issued the Notice to Proceed on January 30th
Design was placed on hold on February 28th
Anticipated Contractual Substantial Completion – TBD
Forecasted Substantial Completion – TBD
School Ready for Occupancy – TBD
Status Date: April 30, 2012 10
McDonogh #35 School (Phillip/Waters Site) (OPSB)
[1200 Senate Street, New Orleans, LA 70122]
Scope of work: New 3-Story High School
Funding Source – FEMA
Architect – Sizeler, Thompson, Brown Architects
Contractor - TBD
Site Remediation Project
A Phase II environmental assessment revealed heavy metals
and PAHs exist in the fill
Scope of work is to remediate fly-ash materials found in the
soil
Contractor commenced preliminary work on April 28th
Contractor to commence excavation of haul work on
May 8th
Contractual Substantial Completion – August 2012
Forecasted Substantial Completion – August 2012
New Construction Project
Clear title of ownership of the varous parcels must be resolved
Ownership of the various parcels is in question, but is in favor of
OPSB
A legal opinion regarding ownership of property is required for
the surveyor to provide the re-subdivision request
Anticipated Contractual Substantial Completion – May 2014
School Ready for Occupancy – August 2014
Design Phase
The Design Phase is expected to be completed in mid-June
Community meeting was held on April 5th
Anticipated Bid Date – August 2012
Drain Lines Project
The Sewerage and Water Board of New Orleans has two large storm
drain lines running through the property that must be relocated
OPSB elected to relocate the drain lines back on property
Sewerage and Water Board approved the plan to
relocate the drain lines on OPSB’s property
Design is expected to be completed in June
Status Date: April 30, 2012 11
The drain line project will be integrated into the main
construction project
Anticipated Substantial Completion – May 2014
Eleanor L. McMain School (OPSB)
[5721 S. Claiborne Avenue, New Orleans, LA 70125]
Scope of work: The exterior of the existing building will be stabilized and a
new gym will be added to the site with a connecting breezeway to the main
building
Funding Source – FEMA
Architect – Jahncke & Burns Architects
Contractor – TBD
Procurement Phase
The design phase was completed on April 25th
1st Advertisement – May 10th
2nd Advertisement – May 17th
3rd Advertisement – May 24th
Pre-Bid Conference- 10:00 a.m. on May 30th at Jacobs/CSRS
Program Management, 909 Poydras Street, Suite 1200, New
Orleans, LA
Bid Opening – June 14th
Anticipated Contractual Substantial Completion – October 2013
School Ready for Occupancy – October 2013
School Based Health Clinic
Funding Source – HRSA Grant
Architect – Jahncke & Burns Architects
Contractor – TBD
Design Phase – School Based Health Clinic
Architect requested an enviornmental report for asbestos, lead, and mold
The environmental report was initiated based on the need to test
the windows and insulated piping in the area designated for the
clinic
Remediation will be included in the bid documents
100% Construction Documents were delayed due to the
environmental report
The design is expected to be completed in early May
Status Date: April 30, 2012 12
Anticipated 1st Advertisement – May 2012
Anticipated Contractual Substantial Completion – November 2012
Clinic Ready for Occupancy – January 2013
Mildred Osborne School (RSD)
[6701 Curran Blvd., New Orleans, LA 70126]
Scope of work: New Pre-K– 8 School
Funding Source – FEMA
Architect – Fauntleroy & Latham
Contractor – F.H. Paschen, S.N. Nielsen & Associates, LLC
Construction Phase
Metal roofing for the gymnasium is complete
Storefront glazing and windows are near completion
Kitchen equipment and hook-up connections are in progress
Installation of metal panels on the south classroom wing is underway
Epoxy flooring and ceramic tile walls in toilet rooms are ongoing
Finish trades are working in the north and south classroom wings
Contractual Substantial Completion – January 2012
Forecasted Substantial Completion – July 2012
School Ready for Occupancy – July 2012
Parkview School (RSD)
[4617 Mirabeau Avenue, New Orleans, LA 70126]
Scope of work: New Pre-K – 8 School
Funding Source – FEMA
Architect – Rozas-Ward
Contractor – Citadel Builders, LLC
Construction Phase
Exterior face brick, insulated metal panels, split face CMU and window installation are complete at the classroom and Administration Buildings
Interior finishes including drywall, acoustical ceilings, terrazzo and ceramic tile flooring, and finish painting continue throughout the classroom and Administration Buildings
Overhead Mechanical/Electrical/Plumbing rough-in continues
Status Date: April 30, 2012 13
Permanent power and conditioned air are expected in the coming month
Installation of temperature sensitive finishes will commence
Contractual Substantial Completion – June 2012
Forecasted Substantial Completion – July 2012
School Ready for Occupancy – August 2012
Booker T. Washington School (RSD)
[1201 South Roman Street, New Orleans, LA 70125]
Scope of work: The auditorium and entry will be renovated and the
remainder of the facility will be demolished and constructed new
Funding Source – FEMA
Architect – Hewitt-Washington & Associates
Contractor – TBD
Design Phase
The Design Advisory Committee (DAC) rejected the
documents on April 4th
100% Design Development documents were received on April
9th
Design documents will be resubmitted to the Design Advisory
Committee (DAC) for approval on May 4th
Anticipated Contractual Substantial Completion – July 2014
Forecasted Substantial Completion – June 2014
School Ready for Occupancy – August 2014
Phillis Wheatley Elementary School (RSD)
[2300 Dumaine Street, New Orleans, LA 70119]
Scope of work: New Elementary School
Funding Source – FEMA
Architect – Holly & Smith Architects
Contractor – TBD
Design Phase
Conditional Use Permit was approved with provisos
100% Construction Documents are due on May 9th
Anticipated 1st Advertisement – June 12th
Anticipated Bid Date – July 17th
Anticipated Contractual Substantial Completion – December 2013
Status Date: April 30, 2012 14
Forecasted Substantial Completion – December 2013
School Ready for Occupancy – January 2014
Fannie C. Williams School (RSD)
[11755 Dwyer Road, New Orleans, LA 70128]
Scope of work: New Pre-K – 8 School
Funding Source – FEMA
Architect – Yeates & Yeates Architects
Contractor – Brice Building Company, LLC
Construction Phase
Installed framework for the storefront windows
Masonry brick commenced in the kitchen/cafeteria
Terrazzo flooring is 30% complete
Overhead rough-in is 95% complete
Contractual Substantial Completion – April 2012
Forecasted Substantial Completion – November 2012
School Ready for Occupancy – December 2012
Little Woods School (RSD)
[10200 Curran Blvd., New Orleans, LA 70127]
Scope of work: New Pre-K – 8 School
Funding Source – FEMA
Architect – Group Novak, LLC
Contractor – MAPP Construction
Construction Phase
Structural steel erection of sequence #3 continues and is
expected to be completed in May
Joists and deck installation is ongoing and is expected to be
completed in May
Slab on deck pours in Areas “A&B” are complete
CMU installation is ongoing on the 2nd and 3rd floors in Areas
“A&B”
Fireproofing is ongoing in Areas “A&B” and will continue to
follow steel erection
Mechanical/Electrical/Plumbing rough-in has commenced on
all floors of Sequence #1
Contractual Substantial Completion – November 2012
Status Date: April 30, 2012 15
Forecasted Substantial Completion – November 2012
School Ready for Occupancy – February 2013
Carter G. Woodson School (RSD)
[2514 Third Street, New Orleans, LA 70113]
Scope of work: New Pre-K – 8 School
Funding Source – FEMA
Architect – Byron J. Stewart & Associates
Contractor – Brice Building Company, LLC
Construction Phase
Exterior face brick is nearing completion on all facades of the building
Exterior window installation is progressing
Overhead Mechanical/Electrical/Plumbing rough-ins continue in areas “A-C”
Interior CMU partition work is near completion
Lightweight concrete roof deck and membrane roofing work continues
Contractual Substantial Completion – June 2012
Forecasted Substantial Completion – July 2012
School Ready for Occupancy – August 2012
OTHER PROJECTS
Arthur Ashe Elementary School (OPSB)
Scope of work: Renovation of the kitchen
Funding Source – OPSB
Architect – OPSB/Moses Engineers
Contractor – Crescent Commercial Construction
Construction Phase
All plumbing rough-ins are complete
Floor tile in the kitchen is complete
The hood has been installed
Painting in the kitchen area is complete
Contractual Substantial Completion – May 2012
School Ready for Occupancy – May 2012
Status Date: April 30, 2012 16
Benjamin Franklin Senior High School (OPSB)
Scope of work: Renovation and Repairs to the existing courtyard, exterior
lighting, metal roof panels, interior lighting, curtain wall, exterior doors
(frames), fencing, scoreboard and goal post
Funding Source – FEMA
Architect – Perez, APC
Contractor – W. L. Wyman Construction Company Inc.
Procurement Phase
The Recommendation letter was prepared and delivered to
OPSB for review and approval on April 26th
OPSB is expected to issue the Notice of Intent to Award in
early May
The construction contract will be processed thereafter, and
OPSB is expected to issue the Notice to Proceed in late May
Anticipated Contractual Substantial Completion – January 2013
School Ready for Occupancy – February 2013
Walter L. Cohen High School (RSD)
Scope of work: Correct the HVAC Return Air/Ventilation problems and replace
eight (8) chilled water pumps
Funding Source – FEMA
Architect – Infinity Engineering Consultants, LLC
Contractor – TBD
Design Phase
Start-up meeting was held with the Engineer to review the
scope of work
A site visit is scheduled in early May
Design is forecasted for completion in August
Anticipated Contractual Substantial Completion – TBD
Forecasted Substantial Completion – TBD
School Ready for Occupancy – TBD
A. D. Crossman Elementary School and Benjamin Banneker Elementary School (RSD)
Scope of work: Implementation of Energy Conservation Measures at A.D.
Crossman Elementary School and Benjamin Banneker Elementary School
Funding Source – Harrah’s
Architect – Integrated Management Services, Inc.
Status Date: April 30, 2012 17
Contractor – W. L. Wyman Construction Company, Inc.
Construction Phase
The Contractor is completing punch list items
Contractor will test, balance and perform commissioning in
April
Contractual Substantial Completion – April 2012
Forecasted Substantial Completion – April 2012
School Ready for Occupancy – April 2012
Warren Easton School (OPSB)
Scope of work: Removal and replacement of existing exterior windows and
waterproofing of the courtyard masonry
Funding Source – Harrah’s
Architect – VergesRome Architects, apc
Contractor – Barbara Enterprises, Inc.
Construction Phase
The final two windows have been installed
Additional window trim has been ordered and is
expected in May
Miscellaneous window trim, sill painting and punch list items
must be completed
Contractual Substantial Completion – March 19, 2010
Forecasted Substantial Completion – May 2012
Frances Gaudet/Lake Forest Elementary School (RSD)
Scope of work: Roof Repairs
Funding Source – FEMA
Architect – HMS Architects, LLC
Contractor – Chatmon Construction, LLC
Construction Phase
Project is approximately 80% complete
Contractor requested 21 days due to weather, voting and LEAP
testing
Contractor is on schedule to complete all work by April 30th
Contractual Substantial Completion – April 2012
Forecasted Substantial Completion – April 2012
Status Date: April 30, 2012 18
William J. Guste Elementary School (RSD)
Scope of work – Roof Replacement & Elevator Installation
Funding Source – FEMA
Architect – Richard C. Lambert Consultants, LLC
Contractor – CAMCO, LLC
Construction Phase
Project is 80% complete
Contractor is 90% complete with the placement of the granular
top sheet
The new elevator is approximately 90% complete
Contractor is accruing liquidated damages as work requested
by the Architect has not been corrected
Contractual Substantial Completion – March 2012
Forecasted Substantial Completion – May 2012
Murray G. Henderson Elementary School (RSD)
Scope of work – Roof Replacement
Funding Source – FEMA
Architect – HMS Architects, Inc.
Contractor – Crown Architectural Metal Company, LLC
Procurement Phase
Contractor turned in submittals on April 3rd
Contractor mobilized on April 23rd
Contractual Substantial Completion – June 2012
Forecasted Substantial Completion – June 2012
Langston Hughes School (RSD)
Scope of work: Remove abandoned dumpster pad and grease trap; replace
on classroom door/hardware; correct duct system in the IT room; install
fencing in place of the dumpster pad; provide and install a fence around the
backflow preventer
Funding Source – FEMA
Architect – Lachin Oubre & Associates
Contractor – TBD
Procurement Phase
1st Advertisement – March 27th
Status Date: April 30, 2012 19
2nd Advertisement – April 3rd
3rd Advertisement – April 10th
Pre-Bid Conference was held on April 11th
Bid Opening – May 1st
Anticipated Contractual Substantial Completion – September 2012
Forecasted Substantial Completion – September 2012
Andrew Jackson School (RSD)
Scope of work: To install solar panels at Andrew Jackson School. This will
save energy for the school and serve as a teaching aide for students to learn
about solar energy
Funding Source – Greater New Orleans Foundation/ Entergy Grant
Architect – Perez, APC
Contractor – TBD
Procurement Phase
1st Advertisement – May 22nd
2nd Advertisement – May 29th
3rd Advertisement – June 5th
Pre-Bid Conference – 10:00 a.m. on June 6th at Jacobs/CSRS
Program Management, 909 Poydras Street, Suite 1200, New
Orleans, LA
Bid Opening – June 26th
Anticipated Contractual Substantial Completion – October 2012
Forecasted Substantial Completion – October 2012
Mahalia Jackson Elementary School (OPSB)
Scope of work: New dumpster pad and various improvements
Funding Source – General Fund
Architect – N-Y Associates
Contractor – C.D.W. Services, LLC
Close-Out Phase
Project is complete
Contractual Substantial Completion – March 2012
Actual Substantial Completion – March 2012
Status Date: April 30, 2012 20
Mahalia Jackson Elementary School Office Renovation (OPSB)
Scope of work: Convert the office space on the second floor of Building C into four classrooms
Funding Source – New Orleans Parish School Board General Fund
Architect – VergesRome Architects, APAC
Contractor – TBD
Design Phase
Notice to Proceed was issued to the Architect on April 17th
Contractual Substantial Completion – TBD
Forecasted Substantial Completion – TBD
John McDonogh High School (RSD)
Scope of work – Replacement of Bleachers
Funding Source – Harrah’s
Architect – Trapolin Peer Architects, LLC
Contractor – TBD
Design Phase
The State Fire Marshal confirmed that with the addition of the
new bleachers, a fire sprinkler system will be required in the
gymnasium
Architect submitted two recommendations to the Owner
Anticipated 1st Advertisement – Early May
Anticipated Contractual Substantial Completion – September 2012
Forecasted Substantial Completion – September 2012
Dr. Martin Luther King Jr. Charter School (RSD)
Scope of work: Modular building, deck and canopy system installation
Funding Source – Harrah’s
Architect – Perez, APC
Contractor – T&D Contractors, LLC
Procurement Phase
RSD approved the contract for T&D Contractors on April 16th
Pre-construction meeting was held on April 17th
Awaiting correct insurance documents from the Contractor
Upon receipt, the contract will be sent to LDOE for
approval and the Notice to Proceed
Status Date: April 30, 2012 21
Anticipated Contractual Substantial Completion – TBD
Forecasted Substantial Completion – July 2012
Lafayette Elementary School (RSD)
Scope of work – Roof Replacement and Masonry Repairs
Funding Source – FEMA
Architect – Montgomery Roth Architecture, LLC
Contractor – The Lathan Company, Inc.
Construction Phase
The new roof and parapet coping are 95% complete
Contractor is 99% finished with filling the joint cracks in the
concrete quoins, banding, sills, water tablets and parapets
Contractor is raking masonry joints and installing mortar
The Contractor hired an historic specialist to develop a
plan of action for the exterior of the building
Alternate #1 is 100% complete for removing specific areas of
brick and reinstalling to a plum tolerance
Contractor is scheduled to complete all punch work by May
10th
Contractual Substantial Completion – April 2012
Forecasted Substantial Completion – May 2012
Live Oak Elementary School (RSD)
Scope of work: Repair of auditorium floor and school roof
Funding Source – FEMA for Design & CDBG for Construction
Architect – HMS Architects, APC
Contractor – CMR Construction & Roofing LLC
Construction Phase
A change order was approved for new stained concrete flooring
in the auditorium after substantial completion was achieved
The change order added 100 days construction time
The concrete floors cured in April
Stain work commenced on April 27th
The floors will be sealed in mid-May
Contractual Substantial Completion – June 2012
Forecasted Substantial Completion – June 2012
Status Date: April 30, 2012 22
McDonogh #15 Elementary School (RSD)
Scope of work: Remaining Exterior Masonry Repairs According to SOI
Standards
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – Hamp’s Construction LLC
Half of the exterior masonry work was completed in the initial contract
Additional scope was discovered and the decision was made
to rebid the remaining work
Construction Phase
Contractor continues exterior masonry repairs
Contractual Substantial Completion – May 2012
Forecasted Substantial Completion – May 2012
Sarah T. Reed High School (RSD)
Scope of work: Replacement of Bleachers
Funding Source – Harrah’s
Architect – Trapolin Peer Architects, LLC
Contractor – Hamp’s Construction, LLC
Construction Phase
Project is substantially complete
Contractor is scheduled to complete all punch work by May 4th
Contractual Substantial Completion – March 2012
Forecasted Substantial Completion – April 2012
Village de’Lest Elementary School (RSD)
Scope of work: New Roof & Subsidence
Funding Source – FEMA
Architect – Richard C. Lambert Consultants, LLC
Contractor – TBD
Roof
Procurement Phase
The bids were rejected for “just cause” on April 27th
The RSD will reevaluate the project
Anticipated Contractual Substantial Completion – August 2012
Status Date: April 30, 2012 23
Forecasted Substantial Completion – August 2012
Subsidence
Construction Phase
Contractor – Owen Construction Company
Charter has requested the Notice to Proceed on May 20th
Anticipated Contractual Substantial Completion – August 2012
Forecasted Substantial Completion – August 2012
Sylvanie Williams Elementary School (RSD)
Scope of work: HVAC and Chiller Replacement
Funding Source – FEMA
Architect – Integrated Management Services, Inc.
Contractor – Towers Construction, LLC
Construction Phase
Project is 100% complete
Training and demonstrations will be conducted on May 2nd
Contractual Substantial Completion – March 2012
Forecasted Substantial Completion – April 2012
Dwight D. Eisenhower Elmentary School (RSD) Andrew Jackson Elementary School (RSD) Paul B. Habans Elementary School (RSD) Sylvanie F. Williams Elementary School (RSD) Joseph S. Clark Senior High School (RSD)
Scope of work: Roof Repairs and Replacement
Funding Source – FEMA
Architect – HMS Architects, Inc.
Contractor – Hamp’s Construction, LLC
Construction Phase
Work is progressing at Joseph S. Clark Senior High School
Contractual Substantial Completion – July 2012
Forecasted Substantial Completion – July 2012
Dr. Martin Luther King Charter School (RSD) Albert Wicker Elementary School (RSD) A. P. Tureaud Elementary School (RSD) Edgar P. Harney Elementary School (RSD) Harriet R. Tubman Elementary School (RSD)
Scope of work: Roof Repairs
Status Date: April 30, 2012 24
Funding Source – FEMA
Architect – Richard C. Lambert Consultants, LLC
Contractor – Hamp’s Construction LLC
Construction Phase
Contractor mobilized and work is progressing at Harriett R.
Tubman and A.P. Tureaud Elementary Schools
Contractual Substantial Completion – April 2012
Forecasted Substantial Completion – May 2012
Building Automation System Integration At Recovery School District Central And Remote Offices (RSD)
Scope of work: Implementation of a Central Remote Building Automation
System that integrates the existing Building Automation Systems of the 4
Quick Start Schools (Andrew H. Wilson ES, Langston Hughes ES, L.B.
Landry HS, and Lake Area HS) and Joseph A. Craig ES into a central
remote monitoring workstation that will include Fannie C. Williams ES,
Lawrence D. Crocker ES, Mildred Osborne ES, William Frantz ES, Bienville
ES, Charles J. Colton ES, Carter G. Woodson ES and Parkview ES
Funding Source – FEMA
Architect – Moses Engineers
Contractor – Synergy Building Solutions, Inc.
Construction Phase
Work continues on the five Quick Start Schools
Integration of the five Quick Start Schools is ongoing
Substantial completion for the Quick Start Schools is
expected in May 2012
The remaining integration for schools currently under
construction will occur as each school is completed
Contractual Substantial Completion – 3rd Quarter 2014
Forecasted Substantial Completion – 3rd Quarter 2014
MOTHBALLING OF CLOSED SCHOOLS – SAFE & SECURE
Louis D. Armstrong Elementary School (RSD))
Scope of work: Document Existing Conditions of the Interior and Exterior of
each school, Determine what amount and methods need to be used to
stabilize each school; Develop a plan for securing the exterior envelope from
moisture, vandals and natural disasters; Develop a ventilation plan
Status Date: April 30, 2012 25
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – TBD
Mothballing of Closed Schools – Safe & Secure
100% Construction Documents were received on April 19th
Anticipated 1st Advertisement – May 15th
Forecasted Bid Date – June 2012
Anticipated Contractual Substantial Completion – August 2012
Forecasted Substantial Completion – September 2012
Israel M. Augustine Middle School (RSD)
Scope of work: Document Existing Conditions of the Interior and Exterior of
school, Determine what amount and methods need to be used to stabilize
school; Develop a plan for securing the exterior envelope from moisture,
vandals and natural disasters; Develop a ventilation plan
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – CAMCO LLC
Construction Phase
Roof Replacement
The TPO roofing is complete
Installation of the clay tile roof is complete
Architect completed a walk through and punch list on April 13th
Contractual Substantial Completion – April 2012
Forecasted Substantial Completion – April 2012
Mothballing of Closed Schools – Safe & Secure
1st Advertisement – April 26th
2nd Advertisement – May 3rd
3rd Advertisement – May 10th
Pre-Bid Conference – 10:00 a.m. on May 11th at Jacobs/CSRS
Program Management, 909 Poydras Street, Suite 1200, New
Orleans, LA 70112
Bid Opening – June 5th
Anticipated Contractual Substantial Completion – November 2012
Forecasted Substantial Completion – November 2012
Status Date: April 30, 2012 26
Andrew J. Bell Junior High School (RSD)
Scope of work: Document Existing Conditions of the Interior and Exterior of
each school, Determine what amount and methods need to be used to
stabilize each school; Develop a plan for securing the exterior envelope from
moisture, vandals and natural disasters; Develop a ventilation plan
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – TBD
Emergency Shoring – 100% complete
Temporary Roofing and Roof Structure Replacement
Redesign of replacement of trusses has been completed
Material changed from wood to steel
The legal matter has been resolved
The final judgement agreement was issued
Anticipate 1st Advertisement in early June
Annex Building Demolition
Facility, Planning & Control (FP&C) approval has been
received
Cottage Demolition
FEMA is reviewing all documentation for this project
Mothballing of Closed Schools – Safe & Secure
Additional site security is being procured, including Vandal
Protection System (VPS) panels and new perimeter fencing
Anticipated 1st Advertisement – Late June
Forecasted Bid Date – Late July
Anticipated Contractual Substantial Completion – TBD
Forecasted Substantial Completion – TBD
Oretha C. Haley Elementary School (RSD)
Scope of work: Document Existing Conditions of the Interior and Exterior of
school, Determine what amount and methods need to be used to stabilize
school; Develop a plan for securing the exterior envelope from moisture,
vandals and natural disasters; Develop a ventilation plan
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – TBD
Status Date: April 30, 2012 27
Mothballing of Closed Schools – Safe & Secure
The Notice of Intent to Award was received on April 9th
The construction contract is being processed and LDOE is
expected to issue the Notice to Proceed in May
Anticipated Contractual Substantial Completion – September 2012
Forecasted Substantial Completion – September 2012
Lorraine Hansberry Elementary School (RSD)
Scope of work: Document Existing Conditions of the Interior and Exterior of
school, Determine what amount and methods need to be used to stabilize
school; Develop a plan for securing the exterior envelope from moisture,
vandals and natural disasters; Develop a ventilation plan
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – Tuna Construction LLC
Mothballing of Closed Schools – Safe & Secure
Three (3) general contractors submitted bids at the
construction bid opening on April 5th
LDOE is expected to issue the Notice of Intent to Award in May
Anticipated Contractual Substantial Completion – September 2012
Forecasted Substantial Completion – September 2012
Morris F. X. Jeff Elementary School (RSD)
Scope of work: Document Existing Conditions of the Interior and Exterior of
school, Determine what amount and methods need to be used to stabilize
school; Develop a plan for securing the exterior envelope from moisture,
vandals and natural disasters; Develop a ventilation plan
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – TBD
Mothballing of Closed Schools – Safe & Secure
100% Construction Documents were received on April 6th
Anticipated 1st Advertisement – May 8th
Anticipated Contractual Substantial Completion – October 2012
Forecasted Substantial Completion – October 2012
Status Date: April 30, 2012 28
Valena C. Jones Elementary School (RSD)
Scope of work: Document Existing Conditions of the Interior and Exterior of
school, Determine what amount and methods need to be used to stabilize
school; Develop a plan for securing the exterior envelope from moisture,
vandals and natural disasters; Develop a ventilation plan
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – TBD
Mothballing of Closed Schools – Safe & Secure
Anticipated 1st Advertisement – May 10th
Anticipated Contractual Substantial Completion – November 2012
Forecasted Substantial Completion – November 2012
George Mondy Elementary School (RSD)
Scope of work: Document Existing Conditions of the Interior and Exterior of
school, Determine what amount and methods need to be used to stabilize
school; Develop a plan for securing the exterior envelope from moisture,
vandals and natural disasters; Develop a ventilation plan
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – TBD
Demolition of the Modular Classrooms
Project has been placed on hold
Mothballing of Closed Schools – Safe & Secure
Anticipated 1st Advertisement – May 10th
Anticipated Contractual Substantial Completion – November 2012
Forecasted Substantial Completion – November 2012
John A. Shaw Elementary School (RSD)
Scope of work: Document Existing Conditions of the Interior and Exterior of
school, Determine what amount and methods need to be used to stabilize
school; Develop a plan for securing the exterior envelope from moisture,
vandals and natural disasters; Develop a ventilation plan
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – Zimmer-Eschette Services II, LLC
Mothballing of Closed Schools – Safe & Secure
The Notice of Intent to Award was issued on April 2nd
Status Date: April 30, 2012 29
The construction contract is being processed and LDOE is
expected to issue the Notice to Proceed in early May
Anticipated Contractual Substantial Completion – August 2012
Forecasted Substantial Completion – September 2012
Demolition Projects
Greater St. Stephens School (RSD)
Funding Source – FEMA
Architect – Chenevert Architects LLC
Contractor – TBD
Design Phase
The Notice to Proceed is expected to be issued to the Architect
on May 9th
Anticipated Contractual Completion – TBD
Forecasted Substantial Completion - TBD
Oretha C. Haley Elementary School (RSD)
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Annex Building Demolition
Contractor – Ram J. Construction
Demolition is complete
Substantial completion documentation will be processed in
May
Anticipated Contractual Substantial Completion – June 2012
Forecasted Substantial Completion – June 2012
L. B. Landry Annex Demolition (RSD)
Funding Source – FEMA
Architect – Perez Architects
Contractor – TBD
Design Phase
Notice to Proceed was issued to the Architect on April 23rd
Anticipated Contractual Substantial Completion – TBD
Forecasted Substantial Completion – TBD
Status Date: April 30, 2012 30
Mary Church Terrell Elementary School Demolition (RSD) )
Funding Source – FEMA
Architect – SCNZ Architects
Contractor – TBD
Design Phase
Notice to Proceed was issued to the Architect on April 9th
Anticipated Contractual Substantial Completion – TBD
Forecasted Substantial Completion – TBD
Booker T. Washington High School Demolition (RSD)
Funding Source – FEMA
Architect – Hewitt-Washington & Associates
Contractor – Gulfcon LLC
Procurement Phase
Phase II RCRA8 environmental analysis was conducted at the
site
Contaminants were discovered and will be addressed
when the building has been demolished
LDOE is expected to issue the Notice to Proceed in mid May
Contractual Substantial Completion – October 2012
Forecasted Substantial Completion – October 2012
Comprehensive List - Completed Projects
Abrams | Morial | Abramson | Coghill Demolition (RSD)
A. D. Cross Elementary School Energy Conservation (RSD)
Agnes Bauduit Elementary School Boiler (RSD)
Alfred Lawless Senior High Security Fencing (RSD)
Alice M. Harte Elementary School Demolition (OPSB)
Andrew H. Wilson Elementary School Cottage (RSD)
Avery-Alexander Elementary School Demolition (RSD)
Barbara C. Jordan Elementary School Demolition (RSD)
Benjamin Banneker Elementary School Energy Conservation (RSD)
Bienville Elementary School Demolition (RSD)
Status Date: April 30, 2012 31
Carter G. Woodson Middle School Demolition (RSD)
Central Services Warehouse Demolition (OPSB)
Charles J. Colton Elementary Selective Demolition (RSD)
Charles R. Drew Elementary Roof & Installation of Kitchen Hood (RSD)
Cohen High School Health Clinic (RSD)
East BankSwing Space for Audubon Charter School (OPSB)
Edward Livingston Middle School Demolition(RSD)
Edward Henry Phillips Junior High School Demolition (RSD)
Edwards | Hardin | Lockett | Lawless Demolition (RSD)
Eleanor L. McMain School Replacement of Existing Chillers (OPSB)
Ernest N. Morial Elementary Security Fencing (RSD)
Fannie C. Williams Elementary School Demolition (RSD)
Fisk-Howard Elementary School Demolition (RSD)
Florence J. Chester Elementary School Demolition (RSD)
Francis W. Gregory Demolition (RSD)
Frederick A. Douglass High Switchgear (RSD)
Frederick A. Douglass High Emergency Boiler Roof Repairs (RSD)
George Washington Carver High School Demolition (RSD)
Henry Allen Elementary School Roof (RSD)
Henry C. Schaumburg – Window/Door, Air Condition, Water
Fountain/Sink Installation (RSD)
Holy Cross Modular Relocation (RSD)
Israel M. Augustine Middle School Roof Replacement (RSD)
James Derham Demolition (RSD)
James W. Johnson Elementary School Roof (RSD)
John Dibert Elementary School Roof (RSD)
Jean Gordon Elementary School Demolition (RSD)
John W. Hoffman Elementary School Demolition (RSD)
John F. Kennedy Modular Relocation (Schwarz Campus) (RSD)
John F. Kennedy Modular Relocation (Coghill Modular Campus) (RSD)
John F. Kennedy High School Demolition (RSD)
John McDonogh Senior High School Roof (RSD)
Status Date: April 30, 2012 32
Joseph A. Craig Elementary Canopies (RSD)
Joseph A. Craig Elementary Elevator Installation (RSD)
Joseph A. Hardin Elementary Security Fencing (RSD)
Lake Area | Landry Demolition (RSD)
Langston Hughes Elementary School (Phase I) (RSD)
Langston Hughes Elementary School – New Gymnasium (Phase II) (RSD)
Lawrence D. Crocker Elementary School Demolition (RSD)
Little Woods Elementary School Demolition (RSD)
Live Oak Elementary School Exterior Door Replacement (RSD)
Live Oak Elementary School Roof Repair (RSD)
Mahalia Jackson Elementary School (OPSB)
Mahalia Jackson Elementary School Dumpster/Other
Improvements (OPSB)
Martin Behrman Elementary School Roof (RSD)
Martin Luther King Jr. Elementary Canopy System (RSD)
Mary M. Bethune Elementary 1st Floor Replacement (RSD)
Mary M. Bethune Elementary Rear Yard Repair/Resurfacing (RSD)
McDonogh #15 Elementary Exterior Masonry to SOI Standards (RSD)
McDonogh #28 Elementary School Roof (RSD)
McDonogh #32 Roof Replacement (RSD)
McDonogh #35 ADA Upgrades to Public Restrooms, Exterior Ramp &
Handicap Seating in the Auditorium (OPSB)
McDonogh #42 Elementary School Roof (RSD)
McDonogh #42 Elementary School HVAC Replacement (RSD)
Mildred C. Osborne Elementary School Demolition (RSD)
Modular Campuses Close Outs (RSD)
Modular Structures at Langston Hughes Elementary School (RSD)
Morris F.X. Jeff Elementary School Demolition (RSD)
New Andrew H. Wilson Elementary School (RSD)
New Joseph A. Craig Elementary School (RSD)
New Lake Area High School (RSD)
New L.B. Landry High School (RSD)
New Equipment & Upgrades at 8 Central & 25 Satellite Kitchens (RSD)
Status Date: April 30, 2012 33
Oretha C. Haley Demo (RSD)
Parkview Elementary School Demolition (RSD)
Paul L. Dunbar Elementary School Demolition (RSD)
Phillis Wheatley Elementary School Demolition (RSD)
Robert M. Lusher Elementary Roof Removal & Replacement (OPSB)
Sarah T. Reed High School Bleachers (RSD)
Sarah T. Reed High School Auditorium Wall (RSD)
Seabrook Computer Training Center Demolition (OPSB)
Schaumburg Chillers (RSD)
Schwarz Alternative (RSD)
Schwarz Alternative Modulars Demolition (RSD)
Sherwood Forest Elementary School Demolition (RSD)
Sophie B. Wright Various Repairs/Restroom Renovations (OPSB)
Stuart R. Bradley Elementary School Demolition (RSD)
Sylvanie Williams Elementary School Play Yard (RSD)
Sylvanie Williams Elementary School HVAC/Chiller Replacement (RSD)
Temporary Campus for McDonogh #11 Expropriation (OPSB)
Thomas A. Edison Elementary School Demolition (RSD)
Thomy Lafon Elementary School Demolition (RSD)
Timbers Park Office Building #1 & #2 Demolition (OPSB)
Vorice J. Waters Elementary School Demolition (RSD)
West Bank Swing Space for Alice Harte Elementary School (OPSB)
William J. Guste Elementary School (RSD)
William J. Guste Elementary School Science Lab (RSD)
William Frantz Elementary School Environmental Remediation &
Selective Demolition (RSD)
William Frantz Elementary School Roof (RSD)
BESE MONTHLY REPORT
OPEN CONTRACTS as of 05/03/12
SCHOOLFUNDING SOURCE CONTRACTOR/ARCHITECT
ORIGINAL CONTRACT AMOUNTS
CHANGE ORDERS/ AMENDMENTS
CURRENT CONTRACT AMOUNTS TOTAL CONTRACT
QUICK STARTLake Area HS Construction FEMA Verges & Rome/Fanning Howey 1,878,159.00$ 971,537.10$ 2,849,696.10$
Roy Anderson 35,580,000.00$ 1,001,860.00$ 36,581,860.00$ LAKE AREA TOTAL 39,431,556.10$
Langston Hughes ES Construction FEMA Roy Anderson 26,430,000.00$ 1,219,581.15$ 27,649,581.15$
LANGSTON HUGHES TOTAL 27,649,581.15$ L B Landry HS Construction FEMA
Satterfield & Pontikes 52,723,000.00$ 3,109,470.06$ 55,832,470.06$ LANDRY TOTAL 55,832,470.06$
FC Williams ES Construction FEMA Yeates&Yeates 522,693.00$ 1,967,267.01$ 2,489,960.01$ Brice Building Company 21,997,000.00$ 62,140.19$ 22,059,140.19$
FANNY C WILLIAMS TOTAL 24,549,100.20$
OTHER RENOVATION / CONSTRUCTIONCrocker ES Construction FEMA Chenervert Architects 860,139.00$ 1,382,327.93$ 2,242,466.93$
Demolition P&J Contracting of LA LLC 437,000.00$ 6,000.00$ 443,000.00$ Satterfield & Pontikes Construction Group, LL 18,598,500.00$ 352,567.33$ 18,951,067.33$
CROCKER TOTAL 21,636,534.26$ Frantz ES Renovation/Addition FEMA Billes Architects 1,034,991.00$ 1,087,492.20$ 2,122,483.20$
The Lathan Company 19,537,000.00$ 460,643.84$ 19,997,643.84$ FRANTZ TOTAL 22,120,127.04$
DEMOLITIONSWoodson MS Demo FEMA
Hamp's Enterprises, Inc 456,000.00$ 20,790.93$ 476,790.93$ WOODSON MS DEMO 476,790.93$
Gregory Junior High School Demo FEMA M3A Architecture, PLLC 98,793.50$ (28,390.00)$ 70,403.50$ Bayou Sheet Metal & Roofing, Inc. 342,000.00$ -$ 342,000.00$
GREGORY DEMO 412,403.50$ Jordan ES Demo FEMA M3A Architecture, PLLC 62,795.00$ (15,203.90)$ 47,591.10$
Louisiana Demolition, Inc. 180,299.65$ 7,931.00$ 188,230.65$ JORDAN DEMO 235,821.75$
Fisk-Howard ES Demo FEMA M3A Architecture, PLLC 55,426.00$ 9,800.00$ 65,226.00$ Hamp's Enterprises LLC 230,500.00$ 174,873.29$ 405,373.29$
FISK-HOWARD DEMO 470,599.29$ Kennedy HS Demo FEMA Shaw Environmental & Infrastructure 186,028.68$ 45,960.17$ 231,988.85$
Contaminant Control 549,500.00$ 3,500.00$ 553,000.00$ KENNEDY DEMO 784,988.85$
James Derham JHS Demo (NOHSSC) FEMA SRF Group Consulting, LLC 94,759.50$ (23,306.00)$ 71,453.50$ Concrete Busters of LA 538,000.00$ 287,157.53$ 825,157.53$
DERHAM DEMO 896,611.03$ Lafon ES Demo FEMA Shaw Environmental & Infrastructure 101,450.00$ (26,119.00)$ 75,331.00$
Hamp's Enterprises, LLC 199,500.00$ -$ 199,500.00$ LAFON DEMO 274,831.00$
Wheatley ES Demo FEMA SRF Group Consulting, LLC 42,323.00$ (899.20)$ 41,423.80$ Zimmer-Eschette Service II, LLC 199,500.00$ 37,210.68$ 236,710.68$
WHEATLEY DEMO 278,134.48$ Terrell ES Abatement & Demo FEMA SCNZ Architects, LLC 27,777.00$ 23,166.00$ 50,943.00$
Contingency -$ -$ -$ TERRELL DEMO 50,943.00$
Andrew Bell JH Demo FEMA VergesRome Architects, APAC -$ 10,147.00$ 10,147.00$ CONSTRUCTION - TBD -$ -$ -$
BELL DEMO 10,147.00$ Oretha Haley ES Demo FEMA VergesRome Architects, APAC -$ 10,169.00$ 10,169.00$
Contingency 79,000.00$ -$ 79,000.00$ HALEY DEMO 89,169.00$
George Mondy Demo FEMA VergesRome Architects, APAC -$ 2,633.00$ 2,633.00$ CONSTRUCTION - TBD -$ -$ -$
MONDY DEMO 2,633.00$ Booker T Washington HS Demo - Annex & FEMA Hewitt-Washington & Associates Architects a 80,385.00$ 5,796.60$ 86,181.60$
CONSTRUCTION - TBD -$ -$ -$ BTW DEMO 86,181.60$
L.B. Landry Annnex Building Demo FEMA Perez, APC 26,533.50$ -$ 26,533.50$ CONSTRUCTION - TBD -$ -$ -$
LANDRY ANNEX DEMO 26,533.50$
Page 1
BESE MONTHLY REPORT
OPEN CONTRACTS as of 05/03/12
SCHOOLFUNDING SOURCE CONTRACTOR/ARCHITECT
ORIGINAL CONTRACT AMOUNTS
CHANGE ORDERS/ AMENDMENTS
CURRENT CONTRACT AMOUNTS TOTAL CONTRACT
STABILIZATION Reed High School Wall Repair FEMA
Precision Construction & Maintenance, LLC 10,850.00$ -$ 10,850.00$ REED HS REPAIR TOTAL 10,850.00$
McDonogh 15 ES Waterproofing Exterior M FEMA VergesRome Architects 21,646.00$ (286.00)$ 21,360.00$
McDONOGH 15 TOTAL 21,360.00$ Live Oak ES Repair of Auditorium Floor/Ro FEMA HMS Architects 65,736.00$ 13,883.43$ 79,619.43$
CDBG CMR Construction & Roofing LLC 759,625.00$ 143,882.47$ 903,507.47$ LIVE OAK ES TOTAL 983,126.90$
Dibert ES Roof FEMAHamp's Construction 41,900.00$ -$ 41,900.00$
DIBERT ES TOTAL 41,900.00$ Gentilly Terrace ES Roof FEMA VergesRome Architects 6,198.00$ 1,957.00$ 8,155.00$
Hamp's Construction 67,900.00$ -$ 67,900.00$ GENTILLY TERRACE ES TOTAL 76,055.00$
Drew ES Roof FEMA VergesRome Architects 38,378.00$ (2,397.00)$ 35,981.00$
DREW ES TOTAL 35,981.00$ Live Oak ES (Door Replacement) FEMA HMS Architects, APC 37,529.00$ 6,717.00$ 44,246.00$
CDBG M. Slayton Construction, Inc. 319,500.00$ -$ 319,500.00$ LIVE OAK ES TOTAL 363,746.00$
Schaumburg ES Window Replacement FEMA N-Y Associates, Inc. 76,481.00$ 46,438.88$ 122,919.88$ ICON Construction Group, Inc 891,000.00$ 5,269.64$ 896,269.64$
SCHAUMBURG ES TOTAL 1,019,189.52$
STABILIZATION (2)Roof Repairs Various Sites (MLK Charter, W FEMA Richard C. Lambert Consultants, LLC 11,693.00$ (4,004.01)$ 7,688.99$
Hamp's Construction, LLC 105,700.00$ -$ 105,700.00$ ROOF REPAIR VARIOUS SITES TOTAL 113,388.99$
McDonogh #42 ES Roof, Stabilization, FEMA Richard C. Lambert Consultants, LLC 36,334.00$ 11,549.80$ 47,883.80$ Roofing Solutions, LLC 370,200.00$ -$ 370,200.00$
MCDONOGH 42 TOTAL 418,083.80$ McDonogh #28 ES Roof FEMA Richard C. Lambert Consultants, LLC 325.00$ 7,932.60$ 8,257.60$
Roofing Solutions, LLC 46,000.00$ -$ 46,000.00$ McDONOGH 28 TOTAL 54,257.60$
McDonogh #32 ES Roof FEMA Richard C. Lambert Consultants, LLC 905.00$ 40,650.00$ 41,555.00$ The Ellis Company, LLC 417,600.00$ -$ 417,600.00$
McDONOGH 32 TOTAL 459,155.00$ Village de L'est Roof Repairs (Einstein Cha FEMA Richard C. Lambert Consultants, LLC 9,269.00$ 20,418.01$ 29,687.01$
CONSTRUCTION - TBD -$ -$ -$ VILLAGE DE LEST TOTAL 29,687.01$
Roof Repairs Various Sites (Eisenhower ES FEMA HMS Architects, Inc. 15,823.00$ 1,177.00$ 17,000.00$ CONSTRUCTION - TBD -$ -$ -$
ROOF REPAIRS VARIOUS TOTAL 17,000.00$ Gaudet/Lake Forest Charter Roof FEMA HMS Architects, Inc. 37,967.00$ -$ 37,967.00$
Chatmon Construction, LLC 281,370.00$ -$ 281,370.00$ GAUDET/LAKE FOREST ROOF TOTAL 319,337.00$
Murray Henderson ES Roof FEMA HMS Architects, Inc. 666.00$ 39,574.40$ 40,240.40$ Crown Architectural Metal Co, LLC 55,834.00$ -$ 55,834.00$
HENDERSON TOTAL 96,074.40$
Page 2
BESE MONTHLY REPORT
OPEN CONTRACTS as of 05/03/12
SCHOOLFUNDING SOURCE CONTRACTOR/ARCHITECT
ORIGINAL CONTRACT AMOUNTS
CHANGE ORDERS/ AMENDMENTS
CURRENT CONTRACT AMOUNTS TOTAL CONTRACT
STABILIZATION (3)Marquis de Lafayette - Roof & Masonry Rep FEMA Montgomery Roth Architecture & Interior Des 99,152.00$ (10,797.00)$ 88,355.00$
The Lathan Company 857,020.00$ -$ 857,020.00$ de LAFAYETTE ROOF TOTAL 945,375.00$
Sarah T Reed - Bleachers FEMA Trapolin-Peer Architects, APC - VMDO Archit 11,822.50$ -$ 11,822.50$ Hamp's Construction, LLC 67,700.00$ -$ 67,700.00$
REED BLEACHERS TOTAL 79,522.50$ John McDonogh HS - Bleachers Harrah's Trapolin-Peer Architects, APC - VMDO Archit 11,822.50$ -$ 11,822.50$
CONSTRUCTION - TBD -$ -$ -$ J MCDONOGH BLEACHERS TOTAL 11,822.50$
Martin Luther King - Canopy System Harrah's Perez, APC 12,565.00$ (845.00)$ 11,720.00$ Gulf States Contractors, LLC 99,995.00$ 3,700.41$ 103,695.41$
MLK CANOPY TOTAL 115,415.41$ Andrew J Bell Roof Replacement Harrah's VergesRome Architects, APAC -$ 35,523.00$ 35,523.00$
CONSTRUCTION - TBD -$ -$ -$ BELL ROOF TOTAL 35,523.00$
Fredrick Douglass HS Room #214 Remodeurance ProceedMontgomery Roth Architecture & Interior Des 10,942.00$ -$ 10,942.00$
DOUGLASS TOTAL 10,942.00$ Guste ES Roof Replacement & Elevator Ins FEMA N-Y Associates, Inc. 70,624.00$ 24,854.00$ 95,478.00$
Crown Architectural Metal Co 1,105,000.00$ -$ 1,105,000.00$ GUSTE ROOF TOTAL 1,200,478.00$
Carbon Credit - AD Crossman (aka Espera Harrah's Integrated Management Services, P.A., Inc. 16,329.19$ 22,528.19$ 38,857.38$ W.L. Wyman Construction Company, Inc 199,850.00$ -$ 199,850.00$
CARBON CREDIT CROSSMAN TOTAL 238,707.38$ Carbon Credit - Banneker ES Harrah's Integrated Management Services, P.A., Inc. 5,749.00$ 15,143.81$ 20,892.81$
W.L. Wyman Construction Company, Inc 143,350.00$ -$ 143,350.00$ CARBON CREDIT BANNEKER TOTAL 164,242.81$
Sylvanie Williams HVAC & Chiller Replacem FEMA Integrated Management Services, P.A., Inc. -$ 49,802.00$ 49,802.00$ Towers Construction LLC 398,000.00$ -$ 398,000.00$
S WILLIAMS HVAC TOTAL 447,802.00$ Douglass HS - Replace under floor utilities FEMA Infinity Engineering Consultants, LLC 32,529.00$ -$ 32,529.00$
DOUGLASS TOTAL 32,529.00$ Langston Hughes ES - Dumpster Pad FEMA Lachin Oubre & Associates, APC 6,000.00$ -$ 6,000.00$
CONSTRUCTION - TBD -$ -$ -$ HUGHES TOTAL 6,000.00$
McDonogh 15 ES - Exterior Masonry Repai FEMA VergesRome Architects -$ 21,975.50$ 21,975.50$ CONSTRUCTION - TBD -$ -$ -$
McDONOGH 15 TOTAL 21,975.50$ Craig ES Elevator FEMA SCNZ Architects 8,914.00$ -$ 8,914.00$
Harrah's Battco Construction & Maintenance Inc 138,950.00$ -$ 138,950.00$ CRAIG ES TOTAL 138,950.00$
Andrew Jackson ES Solar Panels GNOF - Perez, APC 22,578.00$ -$ 22,578.00$ Entergy CONSTRUCTION - TBD
Jackson ES TOTAL 22,578.00$ Martin Luther King - Modular Buildings Harrah's Perez, APC -$ 15,433.00$ 15,433.00$
CONSTRUCTION - TBDKING MODULAR ES TOTAL 15,433.00$
Sylvanie Williams ES AHU FEMA Integrated Management Services, P.A., Inc. -$ 39,757.00$ 39,757.00$ CONSTRUCTION - TBD
WILLIAMS ES AHU TOTAL 39,757.00$ Village de L'est ES Subsidence FEMA Richard C. Lambert Consultants, LLC -$ 18,198.00$ 18,198.00$
CONSTRUCTION - TBDDe Lest Subsidence TOTAL 18,198.00$
Environmental Testing @ 13 Schools FEMA Three Fold Consultants, Inc 52,130.25$ 46,632.00$ 98,762.25$ ENVIRONMENTAL TESTING TOTAL 98,762.25$
NOHSSC Feasibility Study (Derham) FEMA Evans-Graves Engineers, Inc 32,000.00$ -$ 32,000.00$ NOHSSC STUDY TOTAL 32,000.00$
MECHANICAL Building Automation System Integration at R FEMA Moses Engineers, Inc. 54,368.80$ 26,229.01$ 80,597.81$
Synergy Building Solutions 398,375.50$ -$ 398,375.50$ BAS TOTAL 478,973.31$
MODULAR RELOCATIONS Kennedy Modular Relocation (Coghill Camp FEMA Burk-Kleinpeter, Inc -$ 80,889.00$ 80,889.00$
Gulf States Contractors, LLC 519,000.00$ 286,273.74$ 805,273.74$ KENNEDY (COGHILL) TOTAL 886,162.74$
Page 3
BESE MONTHLY REPORT
OPEN CONTRACTS as of 05/03/12
SCHOOLFUNDING SOURCE CONTRACTOR/ARCHITECT
ORIGINAL CONTRACT AMOUNTS
CHANGE ORDERS/ AMENDMENTS
CURRENT CONTRACT AMOUNTS TOTAL CONTRACT
MOTHBALLING FACILITIES
Israel Augustine Safe & Secure FEMA VergesRome Architects, APAC -$ 38,523.00$ 38,523.00$ Crown Architectural Metal Co 301,000.00$ 27,535.00$ 328,535.00$
AUGUSTINE MOTHBALLING TOTAL 367,058.00$ Louis Armstrong Mothballing FEMA VergesRome Architects, APAC 26,023.00$ 11,880.00$ 37,903.00$ CONSTRUCTION - TBD
ARMSTRONG MOTHBALLING TOTAL 37,903.00$ Andrew J Bell Safe & Secure - Mothballing FEMA VergesRome Architects, APAC 92,568.00$ 3,131.00$ 95,699.00$ CONSTRUCTION - TBD
BELL MOTHBALLING TOTAL 95,699.00$ Oretha Haley ES Mothballing FEMA VergesRome Architects, APAC 26,023.00$ 12,100.00$ 38,123.00$ CONSTRUCTION - TBD
HALEY MOTHBALLING TOTAL 38,123.00$ Lorraine Hansberry Mothballing FEMA VergesRome Architects, APAC 26,023.00$ 13,200.00$ 39,223.00$ CONSTRUCTION - TBD
HANSBERRY MOTHBALLING TOTAL 39,223.00$ Morris Jeff Mothballing FEMA VergesRome Architects, APAC 26,023.00$ 11,220.00$ 37,243.00$ CONSTRUCTION - TBD
JEFF MOTHBALLING TOTAL 37,243.00$ Valena Jones Mothballing FEMA VergesRome Architects, APAC 26,023.00$ 12,430.00$ 38,453.00$ CONSTRUCTION - TBD
JONES MOTHBALLING TOTAL 38,453.00$ George Mondy ES Mothballing FEMA VergesRome Architects, APAC 26,023.00$ 11,220.00$ 37,243.00$ CONSTRUCTION - TBD
MONDY MOTHBALLING TOTAL 37,243.00$ John Shaw Mothballing FEMA VergesRome Architects, APAC 26,023.00$ 11,770.00$ 37,793.00$ CONSTRUCTION - TBD
SHAW MOTHBALLING TOTAL 37,793.00$ Andrew J Bell Shoring Main Classroom Bui FEMA VergesRome Architects, APAC -$ 106,095.00$ 106,095.00$
Abry Brothers, Inc. 910,000.00$ 133,425.00$ 1,043,425.00$ BELL SHORING TOTAL 1,149,520.00$
Page 4
BESE MONTHLY REPORT
OPEN CONTRACTS as of 05/03/12
SCHOOLFUNDING SOURCE CONTRACTOR/ARCHITECT
ORIGINAL CONTRACT AMOUNTS
CHANGE ORDERS/ AMENDMENTS
CURRENT CONTRACT AMOUNTS TOTAL CONTRACT
PHASE 1 GROUP 1 Bienville ES Construction FEMA Howard Performance Architecture, LLC 1,336,822.00$ 300,589.29$ 1,637,411.29$
Walton Construction Company, a CORE Com 18,880,000.00$ 87,846.09$ 18,967,846.09$ BIENVILLE ES TOTAL 20,605,257.38$
Colton ES Renovation FEMA Waggoner & Ball Architects, APC 1,208,475.00$ 1,702,211.26$ 2,910,686.26$ F.H. Paschen, S.N. Nielsen & Associates, LL 26,173,000.00$ 153,873.02$ 26,326,873.02$
COLTON ES TOTAL 29,237,559.28$ Osborne ES Construction FEMA Fauntleroy Latham Weldon Barre Architects, 1,336,822.00$ 325,682.28$ 1,662,504.28$
F.H. Paschen, S.N. Nielsen & Associates, LL 21,375,000.00$ 43,445.39$ 21,418,445.39$ OSBORNE ES TOTAL 23,080,949.67$
Woodson ES Construction FEMA Byron J. Stewart & Associates 1,336,822.00$ 283,630.93$ 1,620,452.93$ Brice Building Company 19,500,000.00$ 181,152.67$ 19,681,152.67$
WOODSON ES TOTAL 21,301,605.60$ Parkview ES Construction FEMA Rozas-Ward/a.i.a. architects, inc. 1,336,822.00$ 316,937.06$ 1,653,759.06$
Citadel Builders, LLC 21,137,000.00$ 230,942.00$ 21,367,942.00$ PARKVIEW ES TOTAL 23,021,701.06$
New Booker T Washington HS & Auditorium FEMA Hewitt-Washington & Associates Architects 3,854,210.00$ 271,691.00$ 4,125,901.00$ CONSTRUCTION - TBD -$ -$ -$
BOOKER T WASHINGTON TOTAL 4,125,901.00$ PHASE 1 GROUP 2Little Woods ES Construction FEMA Group Novak, LLC 1,498,299.00$ 171,294.84$ 1,669,593.84$
MAPP Construction, LLC 21,980,000.00$ -$ 21,980,000.00$ LITTLE WOODS ES TOTAL 23,649,593.84$
Wheatley ES New Construction FEMA Holly & Smith Architects, APAC 1,749,900.00$ 193,204.58$ 1,943,104.58$ Test Pile Sealevel Construction, Inc. 52,990.00$ -$ 52,990.00$
RENOVATION - TBD -$ -$ -$ WHEATLEY ES TOTAL 1,996,094.58$
George W. Carver HS FEMA Trapolin-Peer Architects, APC - VMDO Archit 2,267,824.80$ 848,339.50$ 3,116,164.30$ CONSTRUCTION - TBD -$ -$ -$
CARVER HS TOTAL 3,116,164.30$ Livingston HS Construction FEMA Perez, APC 3,237,677.00$ 155,132.49$ 3,392,809.49$
Test Pile Sealevel Construction, Inc. 56,725.00$ -$ 56,725.00$ CONSTRUCTION - TBD -$ -$ -$
EDWARD LIVINGSTON HS TOTAL 3,449,534.49$
PHASE 2Fisk-Howard ES Construction FEMA VergesRome Architects + Fanning Howey, A 1,582,878.00$ -$ 1,582,878.00$
Construction - TBD -$ -$ -$ FISK ES TOTAL 1,582,878.00$
New HS @ Alfred Lawless - HS Constructio FEMA Sizeler Thompson Brown Architects Project D 1,981,345.00$ -$ 1,981,345.00$ Construction - TBD -$ -$ -$
NEW HS TOTAL 1,981,345.00$ Dunbar ES Construction FEMA Chenevert Architects, LLC 1,437,088.00$ 32,945.00$ 1,470,033.00$
Construction - TBD -$ -$ -$ DUNBAR ES TOTAL 1,470,033.00$
Bradley ES Renovation/Construction FEMA Sizeler Thompson Brown Architects Project D 1,582,878.00$ -$ 1,582,878.00$ Renovation - TBD -$ -$ -$
BRADLEY ES TOTAL 1,582,878.00$ Edward Livingston HS Construction FEMA Rozas-Ward/a.i.a. architects, inc. 1,058,410.78$ -$ 1,058,410.78$
Construction - TBD -$ -$ -$ LIVINGSTON HS TOTAL 1,058,410.78$
McDonogh 42 ES Renovation FEMA Eskew+Dumez+Ripple, APC 1,371,659.00$ -$ 1,371,659.00$ Renovation - TBD -$ -$ -$
MCDONOGH 42 TOTAL 1,371,659.00$ Drew ES Renovation FEMA Blitch/Knevel Architects, Inc. 1,456,546.00$ -$ 1,456,546.00$
Renovation - TBD -$ -$ -$ DREW TOTAL 1,456,546.00$
Sophie B Wright MS Renovation FEMA Waggonner & Ball Architects, APC 1,847,676.00$ -$ 1,847,676.00$ Renovation - TBD -$ -$ -$
WRIGHT HS TOTAL 1,847,676.00$ Frederick A Douglass HS Renovation FEMA VergesRome Architects, APAC 2,618,653.00$ -$ 2,618,653.00$
Renovation - TBD -$ -$ -$ DOUGLASS HS TOTAL 2,618,653.00$
Refurbishments Exterior and Structural Assessments FEMA Perez, APC 62,491.00$ -$ 62,491.00$
BlitchKnevel Architects 41,985.00$ -$ 41,985.00$ Chenevert Architects, LLC 29,528.45$ -$ 29,528.45$
Waggoner & Ball Architects, APC 29,032.00$ -$ 29,032.00$ ASSESSMENTS TOTAL 163,036.45$
Other Professional ServicesBuilding Commissioning
Quickstarts FEMA Farnsworth Group 825,958.00$ 333,694.14$ 1,159,652.14$ 7 New & Renovated Schools FEMA Farnsworth Group 1,192,800.00$ 379,663.13$ 1,572,463.13$
5 plus 2 FEMA Farnsworth Group 1,856,608.00$ 83,625.52$ 1,940,233.52$ BUILDING COMMISSIONING TOTAL 4,672,348.79$
Program/Construction Management FEMAJacobs Project Management/CSRS Consortiu 26,994,177.00$ 9,102,290.45$ 36,096,467.45$
PM/CM TOTAL 36,096,467.45$
GRAND TOTAL 415,780,049.03$
Page 5
OPSB OPEN CONTRACTSas of
05/03/12
SCHOOL CONTRACTOR/ARCHITECT CURRENT CONTRACT
AMOUNTS TOTAL CONTRACT SCHOOL CONTRACTOR/ARCHITECT TOTAL CONTRACT
Building Commissioning Farnsworth Group, Inc 1,277,713.75$ Building Commissioning Total 1,277,713.75$
Demolition of Timbers Bldg #1 and #2 Hamp's Construction, LLC 795,225.40$ M3A Architects, PLLC 176,035.75$
Demolition of Timbers Bldg #1 and #2 Total 971,261.15$ Demolition of Central Services Warehouse Shaw Environmental & Infrastructure, Inc 183,609.26$
J.C.C. Environmental, Inc 989,528.50$ Demolition of Central Services Warehouse Total 1,173,137.76$
Alice Harte Demolition M3A Architects, PLLC 60,510.50$ Zimmer-Eschette Services II 309,062.74$
Alice Harte Demolition Total 369,573.24$ Hynes Elementary Construction Hegedus & Associates 1,486,424.55$
Woodrow Wilson Construction 21,550,672.33$ Hynes Elementary Construction Total 23,037,096.88$
New McDonogh 35 High School (Phillips Waters Site) Sizeler Thompson Brown Architects Project Design Group, LLC 3,376,149.00$ New McDonogh 35 High School (Phillips Waters Site) Total 3,376,149.00$
New McDonogh 35 High School (Phillips Waters Site) Site Remediation Hamp's Construction, LLC 4,529,536.65$ Sizeler Thompson Brown Architects Project Design Group, LLC 370,222.00$
New McDonogh 35 High School (Phillips Waters Site) Site Remediation Total 4,899,758.65$ New McDonogh 35 High School (Phillips Waters Site) Test Pile Brice Building Company 97,700.00$
Sizeler Thompson Brown Architects Project Design Group, LLC 11,107.00$ New McDonogh 35 High School (Phillips Waters Site) Test Pile Total 108,807.00$
Audubon School Reno/Addition Blitch Knevel Architects 1,182,110.90$ Audubon School Reno/Addition Total 1,182,110.90$
Alice Harte Elementary WDG Architects Engineers 1,770,734.00$ Alice Harte Elementary Total 1,770,734.00$
Alice Harte Elementary Test Pile Sealevel Construction, Inc 72,275.00$ WDG Architects Engineers 8,467.00$
Alice Harte Elementary Test Pile Total 80,742.00$ McMain HS Gym/Exterior Stabilization Jahncke & Burns Architects, LLC 1,022,635.04$
McMain HS Gym/Exterior Stabilization Total 1,022,635.04$ New PK-8 at Kenilworth Park (Curran Site) Mathes Brierre Architects 1,587,671.03$
New PK-8 at Kenilworth Park (Curran Site) Total 1,587,671.03$ Program Management/Construction Management Jacobs Project Management Company/CSRS Consortium 8,397,444.00$
Program Management/Construction Management Total 8,397,444.00$ Benjamin Franklin SHS (Renovations & Repairs) Perez, APC 137,715.00$
Benjamin Franklin SHS (Renovations & Repairs) Total 137,715.00$ Lusher Elementary (Roof) Harry Baker Smith II 21,625.00$
Lusher Elementary (Roof) Total 21,625.00$ McMain (Chiller) ARC Mechanical Contractors Inc. 511,022.85$
McMain (Chiller) Total 511,022.85$ McDonogh 35 (ADA Upgrades) True Wall Enterprises, LLC 182,756.87$
McDonogh 35 (ADA Upgrades) Total 182,756.87$ Mahalia Jackson (Dumpster) N-Y Associates, Inc 8,190.00$
C.D.W. Services, LLC 69,739.41$ Mahalia Jackson (Dumpster) Total 77,929.41$
Lusher Charter ES (Robert Mills) Stabilization Chenevert Architects 32,372.00$ Lusher Charter ES (Robert Mills) Stabilization Total 32,372.00$
Mary McLeod Bethune ES Stabilization Chenevert Architects 32,372.00$ Mary McLeod Bethune ES Stabilization Total 32,372.00$
McDonogh 35 HS Stabilization Chenevert Architects 32,372.00$ McDonogh 35 HS Stabilization Total 32,372.00$
Warren Easton HS Stabilization Chenevert Architects 32,372.00$ Warren Easton HS Stabilization Total 32,372.00$
Audobon Charter School (Extension ES & MS) Stabilization Chenevert Architects 32,372.00$ Audobon Charter School (Extension ES & MS) Stabilization Total 32,372.00$
Lusher Charter Middle & HS (Extension - Fortier) Stabilization Chenevert Architects 32,372.00$ Lusher Charter Middle & HS (Extension - Fortier) Stabilization Total 32,372.00$
Karr High Stabilization Chenevert Architects 46,962.00$ Karr High Stabilization Total 46,962.00$
Arthur Ashe Kitchen Reno Crescent Commercial Construction 545,929.00$ Moses Engineers, Inc. 43,224.35$
Arthur Ashe Kitchen Reno Total 589,153.35$
GRAND TOTAL 51,016,230.88$