Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
Strategic Study
Utility Scale – Brazilian PV Market 2017 / 2018
Revision: January 2018 Brazil
Introduction
This Strategic Study developed by Greener aims to evaluate the current market development regarding the
contracted Large Scale PV Projects in Brazil. This Study also creates references for current and future
entrepreneurs according to the Market dynamics and the impact on the projects’ profitability.
Main points of the Study:
STATUS OF THE CONTRACTED
PROJECTS
OPPORTUNITIES IN UTILITY SCALE
PHOTOVOLTAIC MARKET
THE MACROECONOMIC DYNAMICS AND ITS
IMPACTS
KEY DRIVERS
VS.
ENERGY PRICING
Highlights
1 Evolution of Projects contracted in the Auctions of 2014 and 2015
2 Utility Scale PV Market Opportunities
3 Contracted Projects’ Profile
4 Market Share and Equipment Ranking (PV Modules, Inverters, Structures, EPC)
5 Hypothetical Case: 90 MW PV Power Plant
6 CAPEX structure for a 90 MW PV Power Plant
7 PV Modules: How may the future prices impact the projects profitability?
8 Imported Modules vs. Local Modules, how does it affect the IRR?
9 Scenarios of 2017, 2018, 2019 and 2020 for deployment of PV Power Plants
10 PPA Pricing vs Key Drivers for a hypothetical 90 MW Power Plant
ANEEL'S AUCTIONSStatus of the Contracted Projects
Auctions Timeline
2014 2015 2016 2017
6th LER* 7th LER 8th LER25th LEN A-4/2017 **
First ANEEL’s Auction for
solar source. 1,048 MWp
were contracted.
2,159 MWp were
contracted in two Reserve
Energy Auctions.
The 2 Reserve Energy
Auctions announced for
2016 were cancelled. No
new projects of solar
source were contracted.
New Energy Auction A-4 in
December/2017. 790,6 MWp of
PV were contracted.
* LER – Leilão de Energia de Reserva ( Reserve Energy Auction ) **LEN – Leilão de Energia Nova ( New Energy Auction )
Summary of ANEEL Auctions
6th Reserve Energy Auction
(2014/Oct-31)LER 2014
7th Reserve Energy Auction
(2015/Aug-28)1th LER 2015
8th Reserve Energy Auction
(2015/Nov-13)2th LER 2015
25th New Energy Auction
(2017/-Dez-18)LEN A-4
Contracted Power (MWp) 1,048.2 1,043.7 1,115.9 790.6
Contracted Power (MWac) 889.7 833.8 929.3 574
Average Sale Price(R$/MWh)
R$ 215.12/MWh R$ 301.79/MWh R$ 297.75/MWh R$ 145.60/MWh
Average Sale Price(US$/MWh)
US$ 87.80/MWh US$ 85.98/MWh US$ 78.77/MWh US$ 44.25/MWh
Exchange Rate R$ 2.45/US$ R$ 3.51/US$ R$ 3.78/US$ R$ 3.29/US$
Start of Energy Supply 01/10/2017 01/08/2017 01/11/2018 01/01/2021
Capex* Average (R$/MWp)
R$ 3,953,660.56 R$ 4,162,392.44 R$ 3,940,245.77 R$ 4,874,861.17
Capex* Average (US$/MWp)
US$ 1,613,739.00 US$ 1,185,866.79 US$ 1,042,393.06 US$ 1,481,720.72
*CAPEX reported in auctions registration at EPE, not the execution price. Source: EPE.
Probability of Project Completion
*MWac, correspondent to the inverters output power. **data brought up to date in November, 2017.
Completion Probability
High • Investor-backed• EPC contracted• Equipment Suppliers Contracted
Medium• Investor-backed• Contract with Suppliers (not
necessarily)
Low • Nothing set570
828,8
350
1748,8
544,3
544,3
70
5 35
110
249,7
249,7
6 TH R E SE R VE E N E R G Y AU CTIO N O CT/ 2 0 1 4
7 TH R E SE R VE E N E R G Y AU CTIO N AU G / 2 0 1 5
8 TH R E SE R VE E N E R G Y AU CTIO N N O V/ 2 0 1 5
CU MU LATIVE
MW
AC
High Medium Low De-contracted
Projects Completion Expectation
*MWac, correspondent to the inverters output power. **data brought up to date in November, 2017.
Classification of Enterprises
High Probability
Medium Probability• Investor-backed• Contract with Suppliers (not
necessarily)
Low Probability• Nothing set
• Investor-backed• EPC contracted• Equipment Suppliers Contracted
880 868,8
424,3
120
5
105
2 0 1 7 2 0 1 8 2 0 1 9 2 0 2 0 2 0 2 1
MW
AC
High Probability Medium Probability2 Low Probability3
New Auctions are key to keep the pipeline of future projects!
???
Regarding PV Projects contracted in 2014 and 2015.
Projects in Operation,Test or Construction
Completion Expected for 2018 Projects under Construction
30 MW
270 MW
430 MW
150 MW
80 MW
90 MW
89.7 MW
300 MW
150 MW
Completion Expected in 2017 Projects in Operation, under test or
Construction
*data brought up to date in November, 2017.
Regarding PV Projects contracted in 2014 and 2015.
Project Overload %
En
terp
ris
es
Overload (%) [MWp/MWac]
Overload
Relation between DC power and AC powerof the Power Plant.
UsageIncrease the power generation with low CAPEX raise.
Ideal OverloadThere is no ideal Overload. Each project must seek the best balance between DC and AC power according to its IRR. It is observed that a significant portion of the contracted projects obtained an Overload between 20% and 25%.
Overload Histogram of the Contracted Projects
Capacity Factor %
Proje
cts
CF (%)
Capacity Factor (%)
Relationship between the amount of power generated by the power plant according to its potential of generation (if the power plant operates 100% of the time under maximum capacity).
UsageComparison between power plants in different locations and/or with different technologies.
Ideal CFThere is no ideal CF, but the higher CF, the greater is the power generated (often without a high increase in CAPEX). Evaluate sites of greater productivity and use technologies that increase the generation and/or reduce losses in the power plant. Those measures are key to achieve more profitable projects.
CF (Capacity Factor) Histogramof the Contracted Projects
BUSINESSOpportunities in the Brazilian Utility Scale PV Market
Introduction
High
Probability
The first solar power plants in Brazil are being constructed, creating many opportunities for various sectors of the PV chain.
This report points out business opportunities for projects contracted in the 3 auctions in 2014 and 2015 considering its development stages.
PV Plants in Operation
PV Plants under Test
PV Plants under Construction
PV Plants which has Not Started Construction
Opportunities to buy assets. Opportunities forOperation & Maintenanceservices.
Opportunities for
Owner's Engineering and
Certificationservices.
Opportunities forsecondary suppliers andoutsourced services.
PV Projectswithout EPC contract andSuppliers*
PV Projects with medium probability have not contracted the EPC andthere may be opportunities for various services and equipment suppliers.
PV Projects with no Investors, EPC or
Suppliers
Low probability PV Projects have not defined their suppliers, not contracted EPC and, inparticular, have not yet signed an investment agreement/contract for the plant construction.
Medium
Probability
Low
Probability
Project Status
360
60
460
709,7
424,3
159,1
120
5
105
2017 2018 2019
MW
ac
Operation Testing Construction High Probability – Not Initiated Medium Probability Low Probability
Regarding PV Projects contracted in 2014 and 2015.
Opportunities
High
Probability
PV Projects status and its financial impact in the chain.
In Operation
Under Test
Under Construction
Construction Not Started
360 MW
R$ 1.495 Billion
Projects without EPC contract and
Suppliers*
Projects with no Investors, EPC or
Suppliers
Medium
Probability
Low
Probability
60 MW
R$ 249 Million
1,169.7 MW
R$ 4.858 Billion
159.1 MW
R$ 661 Million
544.3 MW
R$ 2.261 Billion
110 MW
R$ 457 Million
Financials based on the average CAPEX (local and imported modules) set in R$ 3,436/Wp
and Average Overload of 20,87% (excluding de-contracted). Such a assumption was set
based on the proportion of PV Plants in operation and/or under construction using Local or
imported modules and on the basis of the CAPEX structure presented in the next chapter of
this study.
Assumptions
Regarding PV Projects contracted in 2014 and 2015.
Financial Activity
Financial projections of the Utility Scale PV market according to the pipeline presented previously. It was considered that the enterprises concluded
during the year will handle the financial activity of the photovoltaic chain of that year.
R$3.654,72
R$5.391,13
R$934,45
2017 2018 2019
MIL
LIO
NS
R$
Regarding PV Projects contracted in 2014 and 2015.
Financial Activity
R$1,495.11
R$1,910.42
R$249.19
R$2,449.08
R$1,159.13
R$1,762.16
R$498.37
R$20.77
R$436.07
2017 2018 2019
MIL
LIO
NS
R$
Operation Testing Construction High Probability - Not Yet Initiated Medium Probability Low Probability
Regarding PV Projects contracted in 2014 and 2015.
PV Plants in Operation, Testing or under Construction.The following analysis refers to the operational, under testing or construction PV Projects, addressing some themes regarding the total capacity
contracted (excluding the rescinded contracts) and the market share of the main equipment and services.
9,41%
59,93%
Contracted Capacity
De-contracted(249.7 MW)
30,66%
Operation, Testing, or Construction (1,589.7 MW)
Construction Not Started (813.4 MW)
6º RPA
53.95% of the contracted capacity inthe Auction are in Operation, Testing, orunder Construction.
7º RPA
91.11% of the contracted enterprisesin the Auction are in Operation, Testing,or under Construction.
8º RPA
37.66% of the contracted enterprisesin the Auction are in Operation, Testing,or under Construction.*
* The deadline for the enterprises completion of the 8º LER has not yet expired, which implies a low enterprises completion rate.
Photovoltaic ModulesRegarding PV Plants in Operation, Testing or under Construction.
32,85%
67,15%
PV Modules Manufacturing
Local
Imported
Price The Local assembled Modules aresubstantially more expensive. Ingeneral the price is between 35%and 45% more expensive thanthe imported module in samecomparison basis.
Among the main modules suppliersfor utility scale enterprises, only 2have local manufacturing.
Manufacturers
Local
Availability The national production capacitylimits the supply of modules forthe contracted PV Projects, one ofthe main bottlenecks nowadays isthe delivery time, for both localand international delivery.
Note.: Enterprises with signed contracts, but that are not under construction, were not accounted for.
25.59%
21.29%
12.99%
Trina
3.80% 1.30%5.64% 1º Jinko
29.40% 2º Canadian Solar
3º
4º
BYD
JA Solar
5º GCL
6º First Solar
7º
PV ModulesRegarding Projects in Operation, under test or Construction, 2017.
PV Modules Supply (1,955.4 MWp)
Note.: Projects with signed Modules supply contracts, but that are not constructed or under construction, were not accounted.
25.79%
9.44%
5.66%3.77% 1.89%
GE
Fimer
1º
2º
40.24% 3º
4º
SMA
Ingeteam
13.21% 5º WEG
6º Power Eletronics
7º Siemens
PV InvertersRegarding Projects in Operation, under test or Construction, 2017.
Inverters Supply(1,589.7 MWac)
Note.: Projects with signed Inverter supply contracts, but that are not constructed or under construction, were not accounted.
8,75%
91,25%
Structure Type
Fixed
Single Axis Tracker
Advantages • The use of single axis trackersimproves the power generation,even in conditions of lowlatitude (most enterprises inBrazil).
• Reduce the accumulation of dirton the modules.
Disadvantages • Greater complexity to assembly.
• Increase mechanical assembly cost.
• They occupy greater area due tothe greater spacing between thetables (shading).
StructuresRegarding Projects in Operation, under test or Construction, 2017.
Note.: Projects with signed Structure supply contracts, but that are not constructed or under construction, were not accounted.
42.17%
21.62%
16.36%
7.52%
4.37%
4.37%
3.59%
Soltec
NEXTracker
Convert Italia
STI Norland
Brafer
Nclave
PVH
1º
2º
3º
4º
5º
6º
7º
Note.: Projects with signed Structure supply contracts, but that are not constructed or under construction, were not accounted.
.
PV Structures / TrackingRegarding Projects in Operation, under test or Construction, 2017.
Structure Supply(1.955,4 MWp)
25.64%
21.62%
15.06%
12.54%
8.75%
3.37%
3.59%
5.64%
1.92% 1.88%
Prodiel
Biosar
Enerray
SNEF
Grupo Cobra
WEG
GRS
ATP
Quebec
Araxá Solar
1º
2º
3º
4º
5º
6º
7º
8º
9º
10º
Note.: Enterprises with signed contracts, but that are not under construction, were not accounted for.
EPC (Engineering, Procurement and Construction)
Regarding Projects in Operation, under test or Construction, 2017.
EPC(1,955.4 MWp)
DRIVERSHow Macroeconomic and other key drivers can affect the PV Projects
Introduction
This chapter shows the impact of the main drivers on the viability and profitability of a PV Plant. A proper balance of CAPEX/OPEX, an optimal capital
structure and a realistic vision of the macroeconomic conditions have a direct impact on the project profitability. A proper evaluation of the scenarios
and the market trends can make a difference in a safe bid in the auctions.
Macroeconomics
Scenarios2017, 2018,
2019 and 2020Plant Location Local Modules
Technical
Characteristics
CAPEX Composition
Productivity, Grid
Connection
Price
Scenarios
Brazilian Economics
Selic Rate,
Inflation,
Exchange
Technologies
Modules,
Inverters,
Structure
FinancingDevelopment
Banks, Private
Funding
Operation & Maintenance of
OPEX,
Exchange
Inverters
Imported Modules
Price
Scenarios
Cost StructureCAPEX:
Local Modules &
Int’l Modudles
MacroeconomicsMain Drivers
Understanding the impact of each driver:
Selic Rate
The Selic rate (basic interest rate in Brazil) is an important reference
for the definition of the PV Project capital cost. Lower reference rates
tend to make the return on infrastructure investment more
attractive.
Inflation
(IPCA)
Inflation is directly linked to the consumption balance with the
productive capacity of the country. When the inflation grows and the
interests rate remains stable, the real capital gain is reduced.
In general, with a booming economy the inflation is higher, but
in our scenarios, we considered a inflation target set for 2019 and 2020. As
the economy activity is expected accelerate again, we considered a higher
Selic rate to contain the excessive consumption and do not reduce the real
capital gain.
Exchange Rate(R$/USD)
A significant part of the CAPEX is directly impacted by the
exchange rate. For this reason, the currency fluctuation is
often one of the main risks in the project modeling and
pricing strategy .
Understanding the macroeconomic dynamics is fundamental for future projects, as well as knowing the correct “timing” to come up with the project.
Four scenarios will be evaluated throughout the study considering different moments for the power plants construction.
Scenarios 2017 2018 2019 2020
Selic( interest rate reference)
7.50%(Boletim Focus Oct/2017)
7.00%(Boletim Focus Oct/2017)
8.00%(Greener Estimation)
8.50%(Greener Estimation)
Inflation (IPCA)
4.50%(Boletim Focus
Oct/2017, inflation target)
4.25%(Boletim Focus
Oct/2017, inflation target)
4.00%(Inflation target)
4.00%(Inflation target)
Exchange Rate (R$/US$)
R$ 3.19(Boletim Focus Oct/2017)
R$ 3.30(Boletim Focus Oct/2017)
R$ 3.30(Greener Scenario)
R$ 3.30(Greener Scenario)
PV Plant Construction
Start and conclusion in2017
Start and conclusion in2018
Start and conclusion in2019
Start and conclusion in2020
Note.: It was considered that all the disbursement of the enterprise is made in its year of construction.
MacroeconomicsScenarios
Boletim Focus: Monthly Report published by Brazilian Central Bank.
Another crucial issue is to understand the possible ways to compose the capital structure. We will evaluate 2 possible scenarios: Financing provided by
development banks and private funding.
Equity
(Own Capital)
20%
Financing
(Private source)
80%
Private
Financing
Invested Capital (100%)
Equity
(Own Capital)
40%
Financing(Development bank
Funding)
60%
Development
Bank
Invested Capital (100%)
MacroeconomicsCapital Structure
What is the difference between the two capital structures and what are they for?
Private Funding Development Bank
The capital structure with private resources (banks, funds, etc) is an
alternative for those investors who do not wish to make 100% of the contribution in
order to reduce the contribution of capital. A financing operation generally increases the Cost of Capital (WACC) of the project and does not offers flexible
conditions for payment if compared to a development bank. However the financing operation reduces the contribution of the
investor.
The capital structure with development banks aims to reduce the Weighted
Average Cost of Capital (WACC), leveraging the operation with a cheaper
capital and with an extended amortization period. Development
banks have requirements regarding the project's documentation. Also, the amount borrowed must meet the
minimum percentage of local content.
MacroeconomicsCapital Structure
Scenarios 2017 2018 2019 2020
Opportunity Cost(%/y)
(Selic+2,5%)10.19% 9.68% 10.70% 11.21%
Equity (%) 20% 20% 20% 20%
Financed (%) 80% 80% 80% 80%
Interest Rate (%/y)(Selic+4.5%) 12.34% 11.82% 12.86% 13.38%
Period 10 years 10 years 10 years 10 years
Grace Period 0 years 0 years 0 years 0 years
MacroeconomicsPrivate Funding
Scenarios 2017 2018 2019 2020
Opportunity Cost (%a year)
(Selic+2,5%)
10.19% 9.68% 10.70% 11.21%
Equity (%) 40% 40% 40% 40%
Financed (%)60% 60% 60% 60%
Interest Rate(% a year)(Selic+1.0%)
8.58% 8.07% 9.08% 9.58%
Period 19 years 19 years 19 years 19 years
Grace Period 1 year 1 year 1 year 1 year
MacroeconomicsDevelopment Bank
Technical Characteristics
Understanding the impact of each driver:
Plant Location
The choice of the power plant location should be associated with
some fundamental factors to ensure the success of the project. Among the
main considerations, a good PV Project should be located in an area
with good solar radiation and favorable grid connection (preferably
a few kilometers away from the substation and at the lowest possible
voltage level) and the area should have environmental approval.
Technologies
The selection of power plant technologies will affect the project
competitiveness.
A proper choice of the modules technology (crystalline or thin film), as well as the inverters (central or string)
and the structure (fixed or with tracker) will influence the project CAPEX,
productivity, required land and O&Mcost.
Operation and Maintenance
Beyond the impact of the choice of technologies in the Operation &
Maintenance cost, other factors are crucial to guarantee an efficient and
low O&M cost. The frequency of cleaning should be considered, as well as the availability of hydric
resources, scale of the power plant for dilution of the fixed costs and
concerns about the plant security .
Technical CharacteristicsPlant Location
The location where the PV Plant is developed and installed is one of the key factors for the viability and attractiveness of the Project.
Productivity
Locations with high productivity are always preferred for deployment of PV
plants, however the availability of grid connection must be first evaluated,
followed by the potential environmental restrictions.
Grid Connection
The Grid access has been a major bottleneck for the development of projects in
Brazil. Significant part of the distribution and transmission networks of the
northeast regions are overloaded (region with high solar irradiation), with no
availability of energy transmission, which often makes the project unfeasible.
Environmental Licensing
Environmental licenses can take a long time in a bureaucratic process, if not
properly prepared its can be easily denied by State organs.
The choice of a technology for an enterprise must take into account not only its initial investment, but also its secondary gains and long term costs.
Remember that the technology adopted in the project will remain for more than 20 years.
Crystalline Tracker
Crystalline modules in
general provide greater
efficiency and lower Wp-
cost. However this
technology has major
losses due to warmer
local temperatures, its
choice must be
evaluated.
Thin Film
Thin Film modules in
general provide lower
efficiency and take up
more area, raising the
costs with structure
wiring system and
workforce. On the other
hand, this technology
presents loss reduction in
high temperature
conditions.
Central
Central inverters have
been the most used
topology in Utility Scale PV
plants as they’re cost
competitive at the moment
of the initial investment.
String
String Inverters are
becoming a competitive
technology and important
option for large size plants.
Its great advantage are the
low operational costs, as
they allow a fast
replacement in case of
failure, requiring less
specialized technicians.
Fixed
The fixed structure is the
option with lower initial
costs as well as during
the operational period.
Although the higher costs
(initial and operational), the
energy production increase
can be significant even in
low-latitude regions.
Technical CharacteristicsTechnology
Operation and maintenance is crucial to the profitability of the enterprise. Its improper sizing can create risks to assets or jeopardize the power plant
productivity.
It is essential to evaluate the availability of water resource at the power plant location. An PV
Plant uses a significant amount of water for cleaning the modules, specially in dry areas where
the resource is scarce.
The PV plant are usually located in remote places and have fragile and vulnerable equipment
which may be vandalized. An adequate monitoring and security are important and can increase
the operation and maintenance costs significantly.
Production loss by dirt/dust can be significant, especially in arid regions. An efficient plan for
cleaning the modules is important.
Technical CharacteristicsOperation and Maintenance
CAPEX Composition
Understanding the impact of each driver:
Local Modules Imported Modules Cost Structure
Local produced modules are an option for the current and future entrepreneurs in the sector. As
the costs are 35% to 45% higher than the imported modules, the PV projects using local modules
requires favorable financing conditions provided by
development banks.
Used by most Utility Scale Projects, imported modules feature
substantially lower costs than the local modules, however they limit or
prevent access to resources of development banks.
The strong rise in current market prices draws special attention, as well as limitations on availability reported by some entrepreneurs.
The modules represent the main component in the range of CAPEX costs. The recent volatility as well
as the uncertainties in the international PV chain makes the cost projection of this component
an important risk factor. The CAPEX is mostly exposed to Exchange Rate
variations. This, in turn, heavily influenced by the political and
economic scenario.It is worth remembering that 2018, year of elections in the
country, and 2019, beginning of a new government, the scenarios
become even more complex.
Composition of CAPEXLocal Modules
Although locally assembled, the local modules depend on imported parts which is subject to the direct impact of the exchange rate.
Scenarios 2017 2018 2019 2020
LocalModules
(US$/Wp)
US$ 0.660/Wp(include taxes)
US$ 0.633/Wp(include taxes)
US$ 0.624/Wp(include taxes)
US$ 0.614/Wp(include taxes)
LocalModules (R$/Wp)
R$ 2.106/Wp(dollar base R$3.19)
R$ 2.088/Wp(dollar base R$3.30)
R$ 2.058/Wp(dollar base R$3.30)
R$ 2.027/Wp(dollar base R$3.30)
Note. 1: polycrystalline
modules were evaluated, due to
the fact of being the only
nationally produced module on
a large scale.
Note. 2: the prices already include taxes.
There was a module price
increase in 2017 due to high
demand and raw material
supply deficit.
The expectation is that the module prices will decrease
in the following years, but it's hard to foresee when it
will reach the same prices as in the beginning of 2017.
What is the prices expectation for imported modules in the evaluated scenarios?
Scenarios 2017 2018 2019 2020
Imported Modules
(US$/Wp)
US$ 0.472/Wp(include taxes)
US$ 0.452/Wp(include taxes)
US$ 0.445/Wp(include taxes)
US$ 0.439/Wp(include taxes)
Imported Modules (R$/Wp)
R$ 1.504/Wp(dollar base R$3.19)
R$ 1.491/Wp(dollar base R$3.30)
R$ 1.470/Wp(dollar base R$3.30)
R$ 1.448/Wp(dollar base R$3.30)
Note. 1: polycrystalline
modules were evaluated, due to
the fact of being the only
nationally produced module on
a large scale.
Note. 2: the prices already include
taxes.
There was a module price
increase in 2017 due to high
demand and supply deficit.
The expectation is that the module prices will decrease
in the following years, but it's hard to foresee when it
will reach the same prices as in the beginning of 2017.
Composition of CAPEXImported Modules
To understand the impact of module costs in a PV Plant, a CAPEX composition for a hypothetical project will be presented.
DC Power: 106.2 MWp
AC Power: 90 MW
Modules: Polycrystalline 330 Wp
Inverters: Central 2 MW
Structure: Single Axis Tracker +50°/-50°
Connection: 10 km Line at 69kV, connection to 69 kV Bay
Substation: 3 smaller substations and a central,
with central power transformer.
Power plant: 3 solar fields of 30 MW.
CAPEX CompositionHypothetical Case Study: 90 MW PV Power Plant
Values in R$/Wp Imported Module % Local Module %
Modules R$ 1.504 47.10% R$ 2.106 55.51%
Inverters R$ 0.287 8.99% R$ 0.287 7.57%
Structure R$ 0.383 11.99% R$ 0.383 10.09%
Substations(3 smaller and one central, without
transformer)
R$ 0.287 8.99% R$ 0.287 7.57%
Central Transformer R$ 0.026 0,81% R$ 0.026 0,67%
Transmission Line R$ 0.200 6.26% R$ 0.200 5.27%
Works and Engineering R$ 0.300 9,40% R$ 0.300 7.91%
Management R$ 0.080 2.51% R$ 0.080 2.11%
Development R$ 0.006 0,19% R$ 0.006 0,14%
Others R$ 0.120 3.76% R$ 0.120 3.16%
TOTAL( R$/Wp) R$ 3.193 R$ 3.794
Composition of CAPEXCAPEX Structure 90 MW PV Plant (106.2 MWp) - 2017 Scenario
Scenarios 2017 2018 2019 2020
CAPEXLocal
Modules (R$/Wp)
R$ 3.79/Wp R$ 3.81/Wp R$ 3.78/Wp R$ 3.75/Wp
CAPEXImported Modules (R$/Wp)
R$ 3.19/Wp R$ 3.21/Wp R$ 3.19/Wp R$ 3.17/Wp
Exchange (R$/US$)
R$ 3.19 R$ 3.30 R$ 3.30 R$ 3.30
Note. 1: Not only the modules were considered influenced by US Dollar and affected by the exchange rate.
Note. 2: it was considered that all items, except the modules, had their prices stable in the 4 scenarios, varying only according to the exchange rate.
CAPEX CompositionCAPEX 90 MW Power Plant (106.2 MWp) - All Scenarios
Energy PricingScenarios for a hypothetical 90 MW PV Plant
Introduction
This chapter aims to demonstrate the scenarios for 2017, 2018 and 2019 (for the PV Projects already contracted) and the 2018, 2019 and 2020
scenarios for new PV Projects demanded by future Auctions , in different CAPEX conditions and funding sources.
The energy prices are hypothetical as they can vary significantly according the project Capital Structure and the investor return and risk
profile.
Scenarios 2017 2018 2019 2020
Power plants already contracted, with adjusted PPA.
Power plants already contracted, with adjusted PPA.
Power plants already contracted, with adjusted PPA.
New power plants from LEN A-4 / 2017.
New power plants from LEN A-4 / 2017, with adjusted PPA.
New power plants from LEN A-4 / 2017, with adjusted PPA.
6th, 7th and 8th LER
LENA-4/2017 & 2018
Boundary Conditions:
As presented previously, some premises will be reopened to compose the scenarios of the study. The macroeconomic conditions for the scenarios of
2017, 2018, 2019 and 2020 will be kept. The funding conditions presented will be addressed in 2 Cases (one with Private Funding and another with
Development Bank), as well as the initial cost composition (CAPEX) considering use of local modules and imported modules.
Assumptions
Economic Scenarios
2017, 2018,
2019 and 2020
Costs Composition
CAPEXLocal Modules
Imported Modules
FinancialFundraising
Development
Banks, Private
Funding
The 90 MW PV Plant
The 90 MW Power Plant
The following PV Plant configuration will be used in Study Case for the pricing models.
Technical Characteristics
• Modules: Polycrystalline 330 Wp
• Inverters: Central 2 MW
• Structure: Single Axis Trackers of -50°/+50°
• Grid Connection: 69 kV
• Transmission Line: 10 km in 69 kV
• Power plant: 3 solar fields of 30 MW
• DC Power: 106.2 MWp
• AC Power: 90 MW
• Overload: 18%
• Inverters exchange: year 10 and year 20 (20 and 10
Million R$ respectively)
35.2 MWp
30 MW
106.2 MWp
90 MW35.2 MWp
30 MW
35.2 MWp
30 MW
The 90 MW Power Plant
Generation Characteristics
• Productivity :2.200 kWh/kW /year
(considered the tracker gain)
• Capacity Factor: 25.11%
• Generated power/year: 233,640 MWh/year
• Electrical Loss: 3,5%
• Modules degradation year 1: 2,5%
• Modules degradation coming years: 0.85%/year
35.2 MWp
30 MW
106.2 MWp
90 MW35.2 MWp
30 MW
35.2 MWp
30 MW
Other Features
• Operation and Maintenance: 1.50% of CAPEX a year.
• Administration costs: 0.10% of CAPEX /year.
• Insurance costs: 0.10% of CAPEX /year.
• Taxes: Assumed Profit
• Contract Duration: 20 years
Cases
In the next pages the impact of main investment drivers on the 90MW Plant will be presented, considering that it could be constructed in different years
between 2017 and 2020. The pros and cons among the possible strategies adopted in a PV Project and the impact in the IRR (Internal Rate of Return)
were highlighted.
2017 2018 2019 2020
Scenarios
Pre-established macroeconomic conditions.
Case 1
• 90 MW PV Plant• Imported
Modules• Private
Funding
• 90 MW PV Plant• Local
Modules• Develop
ment Bank
Case 2
• 90 MW PV Plant• Imported
Modules• Private
Funding
• 90 MW PV Plant• Local
Modules• Develop
ment Bank
• 90 MW PV Plant• Imported
Modules• Private
Funding
• 90 MW PV Plant• Local
Modules• Develop
ment Bank
• 90 MW PV Plant• Imported
Modules• Private
Funding
• 90 MW PV Plant• Local
Modules• Develop
ment Bank
Case 1 - 90 MW - Imported Modules
90 MW PV Plant using imported modules and financed by private funding, according to the assumptions presented previously.
Macroeconomic Assumptions
Scenarios 2017 2018 2019 2020
Selic 7.50% 7.00% 8.00% 8.50%
Inflation (IPCA) 4.50% 4.25% 4.00% 4.00%
Exchange Rate (R$/US$)
R$ 3.19 R$ 3.30 R$ 3.30 R$ 3.30
Construction & Startup
Start and conclusion in 2017 Start and conclusion in 2018 Start and conclusion in 2019 Start and conclusion in 2020
CAPEX Assumptions
Scenarios 2017 2018 2019 2020
CAPEXLocal Modules
(R$/Wp)R$ 3.79/Wp R$ 3.81/Wp R$ 3.78/Wp R$ 3.75/Wp
CAPEXImported Modules (R$/Wp)
R$ 3.19/Wp R$ 3.21/Wp R$ 3.19/Wp R$ 3.17/Wp
Exchange Rate (R$/US$) R$ 3.19 R$ 3.30 R$ 3.30 R$ 3.30
Case 1 - 90 MW Imported Modules
Private Funding Assumptions
Scenarios 2017 2018 2019 2020
Opportunity Cost (% a year)(Selic+2,5%)
10.19% 9.68% 10.70% 11.21%
Equity (%) 20% 20% 20% 20%
Financing (%) 80% 80% 80% 80%
Interest Rate(% a year)(Selic+4.5%)
12.34% 11.82% 12.86% 13.38%
Period 10 years 10 years 10 years 10 years
Grace Period 0 years 0 years 0 years 0 years
Case 1 - 90 MW Imported Modules
PPA Prices (R$/MWh)
R$ 170/MWh R$ 180/MWh R$ 190/MWh
R$ 200/MWh R$ 210/MWh R$ 220/MWh
R$ 230/MWh R$ 240/MWh R$ 250/MWh
R$ 260/MWh R$ 270/MWh R$ 280/MWh
R$ 290/MWh R$ 300/MWh R$ 310/MWh
R$ 320/MWh R$ 330/MWh R$ 340/MWh
We analyze how energy price (R$/MWh) and CAPEX impact the PV Project IRR (Internal Rate of Return).
The high volatility of PV Modules in the coming years brings uncertainty over the project CAPEX. We considered modules price variation by +10%,
+20%, -10% and -20%.
CAPEX Variation
( all scenarios)
Imported Module Price
2017 R$/Wp*
Price VariationImported Module
Project CAPEX
R$ 1.504 /Wp 0% R$ 3,19 /Wp
R$ 1.654 /Wp +10% R$ 3.34 /Wp
R$ 1.805 /Wp +20% R$ 3.49 /Wp
R$ 1.354 /Wp -10% R$ 3.04/Wp
R$ 1.203 /Wp -20% R$ 2.89/Wp
* Values include taxes and nationalization costs.
WACC CAPEX -20% module CAPEX -10% module Nominal CAPEX CAPEX +10% module CAPEX +20% module
10,24% R$ 2.89/Wp R$ 3.04/Wp R$ 3.19/Wp R$ 3.34/Wp R$ 3.49/Wp
Investment R$ 306.9 Millions R$ 323.1 Millions R$ 339.0 Millions R$ 355.0 Millions R$ 371.0 Millions
R$ 170/MWh 7.89% 6.68% 5.58% 4.57% 3.64%
R$ 180/MWh 9.36% 8.08% 6.92% 5.87% 4.89%
R$ 190/MWh 10.84% 9.48% 8.26% 7.14% 6.13%
R$ 200/MWh 12.32% 10.88% 9.59% 8.42% 7.35%
R$ 210/MWh 13.83% 12.30% 10.92% 9.69% 8.56%
R$ 220/MWh 15.37% 13.73% 12.27% 10.96% 9.78%
R$ 230/MWh 16.93% 15.18% 13.63% 12.25% 11.00%
R$ 240/MWh 18.54% 16.66% 15.01% 13.54% 12.22%
R$ 250/MWh 20.19% 18.18% 16.42% 14.86% 13.47%
R$ 260/MWh 21.89% 19.74% 17.86% 16.20% 14.72%
R$ 270/MWh 23.64% 21.34% 19.33% 17.57% 16.00%
R$ 280/MWh 25.45% 22.98% 20.84% 18.97% 17.30%
R$ 290/MWh 27.32% 24.68% 22.39% 20.40% 18.63%
R$ 300/MWh 29.26% 26.43% 23.99% 21.86% 19.99%
R$ 310/MWh 31.26% 28.24% 25.63% 23.37% 21.39%
R$ 320/MWh 33.34% 30.11% 27.33% 24.92% 22.81%
R$ 330/MWh 35.48% 32.03% 29.08% 26.52% 24.28%
R$ 340/MWh 37.69% 34.03% 30.88% 28.16% 25.79%
How to read the results table?
The WACC represents the capital cost of the project, comprising the equity cost and the funding capital cost. The WACC is the reference rate to which the project has a minimal expected outcome in line with the rate of risk adopted on own capital.
IRR of the project obtained under the conditions of energy sales price and evaluated CAPEX condition.
Green cells are those conditions where the IRR of the project exceeds the WACC of the project, presenting a
positive gain (NPV > 0).
Energy Prices are illustrative, as it varies according the each projectdrivers and assumptions
WACC CAPEX -20% module CAPEX -10% module Nominal CAPEX CAPEX +10% module CAPEX +20% module
11.91% R$ 2.89/Wp R$ 3.04/Wp R$ 3.19/Wp R$ 3.34/Wp R$ 3.49/Wp
Investment R$ 307.1 Millions R$ 323.1 Millions R$ 339.0 Millions R$ 355.0 Millions R$ 371.0 Millions
R$ 170/MWh 7.89% 6.68% 5.58% 4.57% 3.64%
R$ 180/MWh 9.36% 8.08% 6.92% 5.87% 4.89%
R$ 190/MWh 10.84% 9.48% 8.26% 7.14% 6.13%
R$ 200/MWh 12.32% 10.88% 9.59% 8.42% 7.35%
R$ 210/MWh 13.83% 12.30% 10.92% 9.69% 8.56%
R$ 220/MWh 15.37% 13.73% 12.27% 10.96% 9.78%
R$ 230/MWh 16.93% 15.18% 13.63% 12.25% 11.00%
R$ 240/MWh 18.54% 16.66% 15.01% 13.54% 12.22%
R$ 250/MWh 20.19% 18.18% 16.42% 14.86% 13.47%
R$ 260/MWh 21.89% 19.74% 17.86% 16.20% 14.72%
R$ 270/MWh 23.64% 21.34% 19.33% 17.57% 16.00%
R$ 280/MWh 25.45% 22.98% 20.84% 18.97% 17.30%
R$ 290/MWh 27.32% 24.68% 22.39% 20.40% 18.63%
R$ 300/MWh 29.26% 26.43% 23.99% 21.86% 19.99%
R$ 310/MWh 31.26% 28.24% 25.63% 23.37% 21.39%
R$ 320/MWh 33.34% 30.11% 27.33% 24.92% 22.81%
R$ 330/MWh 35.48% 32.03% 29.08% 26.52% 24.28%
R$ 340/MWh 37.69% 34.03% 30.88% 28.16% 25.79%
Case 1 - Scenario 2017 Imported Module
WACC CAPEX -20% module CAPEX -10% module Nominal CAPEX CAPEX +10% module CAPEX +20% module
11.39% R$ 2.91/Wp R$ 3.06/Wp R$ 3.21/Wp R$ 3.36/Wp R$ 3.51/Wp
Investment R$ 309.6 Millions R$ 325.4 Millions R$ 341.3 Millions R$ 357.1 Millions R$ 372.9 Millions
R$ 170/MWh 7.91% 6.72% 5.63% 4.63% 3.71%
R$ 180/MWh 9.39% 8.12% 6.98% 5.93% 4.97%
R$ 190/MWh 10.87% 9.53% 8.32% 7.22% 6.21%
R$ 200/MWh 12.36% 10.94% 9.66% 8.50% 7.43%
R$ 210/MWh 13.88% 12.36% 11.00% 9.77% 8.66%
R$ 220/MWh 15.42% 13.80% 12.35% 11.06% 9.88%
R$ 230/MWh 16.99% 15.26% 13.72% 12.35% 11.11%
R$ 240/MWh 18.60% 16.75% 15.12% 13.66% 12.35%
R$ 250/MWh 20.26% 18.28% 16.53% 14.99% 13.60%
R$ 260/MWh 21.97% 19.84% 17.98% 16.34% 14.87%
R$ 270/MWh 23.73% 21.45% 19.46% 17.71% 16.16%
R$ 280/MWh 25.54% 23.10% 20.98% 19.12% 17.47%
R$ 290/MWh 27.42% 24.81% 22.55% 20.56% 18.81%
R$ 300/MWh 29.37% 26.57% 24.15% 22.04% 20.18%
R$ 310/MWh 31.38% 28.39% 25.81% 23.56% 21.59%
R$ 320/MWh 33.46% 30.27% 27.52% 25.13% 23.03%
R$ 330/MWh 35.61% 32.21% 29.28% 26.74% 24.51%
R$ 340/MWh 37.83% 34.21% 31.10% 28.39% 26.03%
Case 1 - Scenario 2018 Imported Module
WACC CAPEX -20% module CAPEX -10% module Nominal CAPEX CAPEX +10% module CAPEX +20% module
12.43% R$ 2.90/Wp R$ 3.04/Wp R$ 3.19/Wp R$ 3.34/Wp R$ 3.49/Wp
Investment R$ 307.7 Million R$ 323.4 Millions R$ 339.0 Millions R$ 354.6 Millions R$ 370.2 Millions
R$ 170/MWh 7,40% 6.25% 5.20% 4.23% 3.33%
R$ 180/MWh 8.84% 7.62% 6.51% 5.50% 4.56%
R$ 190/MWh 10.28% 8.99% 7.82% 6.75% 5.77%
R$ 200/MWh 11.73% 10.36% 9.12% 8.00% 6.97%
R$ 210/MWh 13.20% 11.74% 10.43% 9.25% 8.17%
R$ 220/MWh 14.69% 13.13% 11.75% 10.50% 9.36%
R$ 230/MWh 16.21% 14.55% 13.08% 11.75% 10.56%
R$ 240/MWh 17.76% 15.99% 14.42% 13.02% 11.76%
R$ 250/MWh 19.36% 17.46% 15.79% 14.31% 12.97%
R$ 260/MWh 21.00% 18.97% 17.19% 15.61% 14.20%
R$ 270/MWh 22.69% 20.52% 18.62% 16.95% 15.45%
R$ 280/MWh 24.43% 22.11% 20.09% 18.30% 16.72%
R$ 290/MWh 26.24% 23.75% 21.59% 19.70% 18.02%
R$ 300/MWh 28.10% 25.44% 23.14% 21.12% 19.34%
R$ 310/MWh 30.03% 27.19% 24.73% 22.59% 20.70%
R$ 320/MWh 32.03% 28.99% 26.37% 24.09% 22.09%
R$ 330/MWh 34.10% 30.86% 28.06% 25.64% 23.51%
R$ 340/MWh 36.24% 32.78% 29.81% 27.23% 24.98%
Case 1 - Scenario 2019 Imported Module
WACC CAPEX -20% module CAPEX -10% module Nominal CAPEX CAPEX +10% module CAPEX +20% module
12.95% R$ 2.88/Wp R$ 3.03/Wp R$ 3.17/Wp R$ 3.31/Wp R$ 3.46/Wp
Investment R$ 305.9 Millions R$ 321.3 Millions R$ 336.7 Millions R$ 352.0 Millions R$ 367.4 Millions
R$ 170/MWh 7.25% 6.12% 5.08% 4.13% 3.24%
R$ 180/MWh 8.68% 7.48% 6.39% 5.39% 4.47%
R$ 190/MWh 10.11% 8.84% 7.69% 6.64% 5.67%
R$ 200/MWh 11.54% 10.20% 8.98% 7.88% 6.86%
R$ 210/MWh 12.99% 11.56% 10.28% 9.11% 8.05%
R$ 220/MWh 14.47% 12.94% 11.58% 10.35% 9.23%
R$ 230/MWh 15.97% 14.34% 12.90% 11.60% 10.42%
R$ 240/MWh 17.51% 15.77% 14.23% 12.85% 11.61%
R$ 250/MWh 19.08% 17.23% 15.59% 14.13% 12.82%
R$ 260/MWh 20.70% 18.72% 16.97% 15.42% 14.04%
R$ 270/MWh 22.37% 20.25% 18.39% 16.74% 15.27%
R$ 280/MWh 24.09% 21.82% 19.84% 18.09% 16.53%
R$ 290/MWh 25.88% 23.44% 21.32% 19.46% 17.82%
R$ 300/MWh 27.72% 25.11% 22.85% 20.88% 19.13%
R$ 310/MWh 29.63% 26.84% 24.43% 22.32% 20.47%
R$ 320/MWh 31.60% 28.62% 26.05% 23.81% 21.84%
R$ 330/MWh 33.64% 30.47% 27.73% 25.35% 23.26%
R$ 340/MWh 35.76% 32.37% 29.45% 26.92% 24.71%
Case 1 - Scenario 2020 Imported Module
Case 2 - 90 MW Local Modules
90 MW PV plant using Local modules and financed by development bank, according to the premises presented previously.
Macroeconomic Assumptions
Scenarios 2017 2018 2019 2020
Selic 7.50% 7.00% 8.00% 8.50%
Inflation (IPCA) 4.50% 4.25% 4.00% 4.00%
Exchange Rate (R$/US$)
R$ 3.19 R$ 3.30 R$ 3.30 R$ 3.30
Construction & Startup
Start and conclusion in 2017 Start and conclusion in 2018 Start and conclusion in 2019 Start and conclusion in 2020
CAPEX Assumptions
Scenarios 2017 2018 2019 2020
CAPEXLocal Modules
(R$/Wp)R$ 3.79/Wp R$ 3.81/Wp R$ 3.78/Wp R$ 3.75/Wp
CAPEXImported Modules (R$/Wp)
R$ 3.19/Wp R$ 3.21/Wp R$ 3.19/Wp R$ 3.17/Wp
Exchange Rate (R$/US$) R$ 3.19 R$ 3.30 R$ 3.30 R$ 3.30
Case 2 - 90 MW Local Modules
Development Bank Funding Assumptions
Scenarios 2017 2018 2019 2020
Opportunity Cost (% a year)(Selic+2,5%)
10.19% 9.68% 10.70% 11.21%
Equity (%) 40% 40% 40% 40%
Financed (%) 60% 60% 60% 60%
Interest Rate(% a year)(Selic+1.0%)
8.58% 8.07% 9.08% 9.58%
Period 19 years 19 years 19 years 19 years
Grace Period 1 year 1 year 1 year 1 year
Case 2 - 90 MW Local Modules
PPA Price (R$/MWh)
R$ 170/MWh R$ 180/MWh R$ 190/MWh
R$ 200/MWh R$ 210/MWh R$ 220/MWh
R$ 230/MWh R$ 240/MWh R$ 250/MWh
R$ 260/MWh R$ 270/MWh R$ 280/MWh
R$ 290/MWh R$ 300/MWh R$ 310/MWh
R$ 320/MWh R$ 330/MWh R$ 340/MWh
We analyze how energy price (R$/MWh) and CAPEX impact the PV Project IRR (Internal Rate of Return).
The high volatility of PV Modules in the coming years brings uncertainty over the project CAPEX. We considered modules price variation by +10%,
+20%, -10% and -20%.
CAPEX Variation
(all scenarios)
Local Module Price 2017 R$/Wp*
Price VariationImported Module
Total CAPEX
R$ 2.106/Wp 0% R$ 3.79/Wp
R$ 2.317 /Wp +10% R$ 4.00 /Wp
R$ 2.527 /Wp +20% R$ 4.22 /Wp
R$ 1.895 /Wp -10% R$ 3.58 /Wp
R$ 1.685 /Wp -20% R$ 3.37 /Wp
* Values include taxes.
WACC CAPEX -20% module CAPEX -10% module Nominal CAPEX CAPEX +10% module CAPEX +20% module
9.22% R$ 3.37/Wp R$ 3.58/Wp R$ 3.79/Wp R$ 4.00 /Wp R$ 4.22 /Wp
Investment R$ 358.2 Millions R$ 380.6 Millions R$ 402.9 Millions R$ 425.3 Millions R$ 447.7 Millions
R$ 170/MWh 6.05% 4.30% 2.66% 1.09% -0.42%
R$ 180/MWh 7.75% 5.99% 4.35% 2.80% 1.32%
R$ 190/MWh 9.39% 7,60% 5.95% 4.39% 2.92%
R$ 200/MWh 10.97% 9.15% 7.47% 5.90% 4.43%
R$ 210/MWh 12.51% 10.64% 8.93% 7.35% 5.86%
R$ 220/MWh 14.01% 12.10% 10.35% 8.74% 7.24%
R$ 230/MWh 15.49% 13.52% 11.73% 10.08% 8.56%
R$ 240/MWh 16.95% 14.92% 13.08% 11.40% 9.85%
R$ 250/MWh 18.39% 16.30% 14.41% 12.68% 11.10%
R$ 260/MWh 19.82% 17.66% 15.71% 13.95% 12.33%
R$ 270/MWh 21.25% 19.01% 17.01% 15.19% 13.53%
R$ 280/MWh 22.66% 20.35% 18.29% 16.42% 14.72%
R$ 290/MWh 24.07% 21.69% 19.56% 17.64% 15.89%
R$ 300/MWh 25.48% 23.02% 20.82% 18.85% 17.05%
R$ 310/MWh 26.88% 24.34% 22.08% 20.05% 18.20%
R$ 320/MWh 28.28% 25.66% 23.33% 21.24% 19.35%
R$ 330/MWh 29.68% 26.98% 24.58% 22.43% 20.48%
R$ 340/MWh 31.09% 28.30% 25.83% 23.61% 21.61%
Case 2 - Scenario 2017 Local Modules
WACC CAPEX -20% module CAPEX -10% module Nominal CAPEX CAPEX +10% module CAPEX +20% module
8.71% R$ 3.39/Wp R$ 3.60/Wp R$ 3.81/Wp R$ 4.02/Wp R$ 4.23/Wp
Investment R$ 360.3 Millions R$ 382.4 Millions R$ 404.6 Millions R$ 426.8 Millions R$ 449.0 Millions
R$ 170/MWh 6.25% 4.53% 2.91% 1.36% -0.13%
R$ 180/MWh 7.96% 6.22% 4,60% 3.07% 1,60%
R$ 190/MWh 9.59% 7.83% 6.20% 4.66% 3.21%
R$ 200/MWh 11.17% 9.37% 7.72% 6.17% 4.72%
R$ 210/MWh 12.71% 10.87% 9.18% 7.62% 6.15%
R$ 220/MWh 14.21% 12.32% 10.60% 9.01% 7.52%
R$ 230/MWh 15.69% 13.75% 11.98% 10.36% 8.85%
R$ 240/MWh 17.15% 15.15% 13.33% 11.67% 10.14%
R$ 250/MWh 18.59% 16.53% 14.66% 12.96% 11.39%
R$ 260/MWh 20.02% 17.89% 15.97% 14.22% 12.62%
R$ 270/MWh 21.44% 19.24% 17.26% 15.47% 13.82%
R$ 280/MWh 22.85% 20.58% 18.54% 16.70% 15.01%
R$ 290/MWh 24.26% 21.91% 19.81% 17.92% 16.19%
R$ 300/MWh 25.67% 23.24% 21.08% 19.12% 17.35%
R$ 310/MWh 27.07% 24.57% 22.33% 20.33% 18.50%
R$ 320/MWh 28.47% 25.89% 23.59% 21.52% 19.65%
R$ 330/MWh 29.86% 27.20% 24.84% 22.71% 20.78%
R$ 340/MWh 31.26% 28.52% 26.08% 23.90% 21.92%
Case 2 - Scenario 2018 Local Modules
WACC CAPEX -20% module CAPEX -10% module Nominal CAPEX CAPEX +10% module CAPEX +20% module
9.73% R$ 3.37/Wp R$ 3.57/Wp R$ 3.78/Wp R$ 3.99/Wp R$ 4.19/Wp
Investment R$ 357.7 Millions R$ 379.5 Millions R$ 401.4 Millions R$ 423.3 Millions R$ 445.1 Millions
R$ 170/MWh 5.46% 3.76% 2.15% 0.61% -0.88%
R$ 180/MWh 7.17% 5.45% 3.84% 2.32% 0.86%
R$ 190/MWh 8.79% 7.05% 5.43% 3.91% 2.47%
R$ 200/MWh 10.37% 8.59% 6.95% 5.42% 3.98%
R$ 210/MWh 11.90% 10.08% 8.41% 6.86% 5.41%
R$ 220/MWh 13.39% 11.53% 9.82% 8.25% 6.78%
R$ 230/MWh 14.86% 12.94% 11.20% 9.59% 8.10%
R$ 240/MWh 16.31% 14.34% 12.54% 10.90% 9.38%
R$ 250/MWh 17.74% 15.71% 13.86% 12.18% 10.63%
R$ 260/MWh 19.16% 17.06% 15.16% 13.44% 11.86%
R$ 270/MWh 20.57% 18.40% 16.45% 14.68% 13.06%
R$ 280/MWh 21.98% 19.74% 17.72% 15.90% 14.24%
R$ 290/MWh 23.38% 21.06% 18.99% 17.11% 15.41%
R$ 300/MWh 24.77% 22.38% 20.24% 18.32% 16.56%
R$ 310/MWh 26.16% 23.70% 21.49% 19.51% 17.71%
R$ 320/MWh 27.56% 25.01% 22.74% 20.70% 18.85%
R$ 330/MWh 28.95% 26.32% 23.98% 21.88% 19.98%
R$ 340/MWh 30.34% 27.63% 25.22% 23.06% 21.10%
Case 2 – Scenario 2019 Local Modules
WACC CAPEX -20% module CAPEX -10% module Nominal CAPEX CAPEX +10% module CAPEX +20% module
10.24% R$ 3.34/Wp R$ 3.55/Wp R$ 3.75/Wp R$ 3.95/Wp R$ 4.15/Wp
Investment R$ 355.1 Millions R$ 376.7 Millions R$ 398.2 Millions R$ 419.7 Millions R$ 441.2 Millions
R$ 170/MWh 5.21% 3.52% 1.92% 0.39% -1.09%
R$ 180/MWh 6.91% 5.21% 3.61% 2.10% 0.65%
R$ 190/MWh 8.54% 6.81% 5.21% 3.70% 2.26%
R$ 200/MWh 10.12% 8.35% 6.73% 5.20% 3.77%
R$ 210/MWh 11.64% 9.84% 8.18% 6.65% 5.20%
R$ 220/MWh 13.14% 11.29% 9.60% 8.03% 6.57%
R$ 230/MWh 14.61% 12.70% 10.97% 9.38% 7.90%
R$ 240/MWh 16.06% 14.10% 12.32% 10.69% 9.18%
R$ 250/MWh 17.49% 15.47% 13.64% 11.97% 10.43%
R$ 260/MWh 18.91% 16.82% 14.94% 13.22% 11.65%
R$ 270/MWh 20.32% 18.16% 16.22% 14.46% 12.85%
R$ 280/MWh 21.72% 19.50% 17.50% 15.69% 14.03%
R$ 290/MWh 23.12% 20.82% 18.76% 16.90% 15.20%
R$ 300/MWh 24.52% 22.14% 20.02% 18.10% 16.36%
R$ 310/MWh 25.91% 23.46% 21.27% 19.30% 17.51%
R$ 320/MWh 27.31% 24.78% 22.52% 20.49% 18.65%
R$ 330/MWh 28.70% 26.09% 23.76% 21.67% 19.78%
R$ 340/MWh 30.10% 27.40% 25.01% 22.85% 20.91%
Case 2 – Scenario 2020 Local Modules
Using the Tables
The tables simulate various scenarios for current and future entrepreneurs who wish to structure centralized generation photovoltaic Projects. With the
tables it is possible to check the advantages and disadvantages of some strategic enterprises, in addition to simulate the best timing for construction of
the power plants.
Then we will use an example of power plant simulation to predict the highest bid for an auction, in addition to the strategies that could be adopted to
reduce the bid for energy sale.
Example: Hypothetical 90 MW Power Plant to bid for LEN A-4 2017.
We will consider a power plant identical to the previously presented for construction of scenarios and find out which would be a good bid to energy sale
to the enterprise and the possible strategies.
2017 2018 2019
Condition 1
Condition 2
Auction
Auction
2020
Power Plant Construction
2021
Regulated Market Operation
Power Plant Construction
Free Market Regulated Market Operation
Energy Prices are illustrative, as itvaries according the each projectdrivers and assumptions
Using the Tables
2017 2018 2019 2020
Condition 1
Condition 2
Auction
Auction
2021
Power Plant Construction
Regulated Market Operation
Power Plant Construction
Free Market Regulated Market Operation
For a power plant that will be built in 2020, we have to use the 2020 scenario and stipulate the CAPEX return and scenario to be adopted. A
comparison must be done between the two cases in order to see the advantages and disadvantages of local modules funding and purchasing.
Case 1 Imported Module and Case 2 Local Module
Scenario 2020
Case 1 Imported Module and Case 2 Local Module
Scenario 2019
Using the Tables
2017 2018 2019 2020
Condition 1
Condition 2
Auction
Auction
2021
Power Plant Construction Regulated Market Operation
Power Plant Construction
Free Market Regulated Market Operation
Case 1 - Scenario 2020 Imported Module
Nominal CAPEX: $3.17/Wp
IRR Required: WACC+2%
WACC 2020: 12.95%
IRR in the Table: >15.21%
Case 2 - Scenario 2020 Local Module
Nominal CAPEX: $3.75/Wp IRR
Required: WACC+2% WACC
2020: 10.24%
IRR in the Table: >12.44%
Energy Sales Price in 2020:
250 R$/MWh
Energy Sales Price in 2020:
~240 R$/MWh
Energy Value in
2017 *:
230.58 R$/MWh
Energy Value in
2017 *:
~221.36 R$/MWh
*The corrected energy value for 2017 - auction date - recede the IPCA of 2019 and 2018. The IPCA of 2020 shall not be considered because the disbursement is made at the
beginning of the year and the model already considers the delivery of the corrected energy for 2021.
Using the Tables
2017 2018 2019
Condition 1
Condition 2
Auction
Auction
2020
Power Plant Construction
2021
Regulated Market Operation
Power Plant Construction Free Market Regulated Market Operation
*The approach to the scenario was made to facilitate the demonstration of the impact of 1 year of the power plant in the free market in order to amortize part of the initial
investment, so is considered a lower CAPEX and the current scenario of the table is used only for a estimate.
Power Plant in the Free
market 1 year, energy sales
price: 120 R$/MWh
Revenue R$ 28 Million
Power Plant in the Free market 1 year,
energy sales price: 120
R$/MWh
Revenue R$ 28 Million
Close to the scenario with CAPEX of R$ 2.90/Wp*
Close to the scenario with CAPEX
of R$ 3,57/Wp*
Case 1 - Scenario 2020 Imported Module
Nominal CAPEX: R$ 3.19/Wp
TIR Required: WACC+2%
WACC 2019: 12.43%
IRR in the Table: >14.68%
Case 2 - Scenario 2020 Local Module
Nominal CAPEX: R$ 3.78/Wp
TIR Required: WACC+2%
WACC 2019: 9.73%
IRR in the Table: >11.92%
Using the Tables
2017 2018 2019
Condition 1
Condition 2
Auction
Auction
2020
Power Plant Construction
2021
Regulated Market Operation
Power Plant Construction
Free Market Regulated Market Operation
Energy Sales Price in 2019:
220 R$/MWh
Energy Sales Price in 2019:
~220 R$/MWh
Energy Value in
2017 *:
211.03 R$/MWh
Energy Value in
2017 *:
~211.03 R$/MWh
* The corrected energy value for 2017 - auction date - recede the IPCA of 2018 The IPCA of 2019 shall not be considered because the disbursement is made at the beginning of
the year and the model already considers the delivery of the corrected energy for 2021.
Case 1 - Scenario 2020 Imported Module
Nominal CAPEX: R$ 2.90/Wp
TIR Required: WACC+2%
WACC 2019: 12.43%
IRR in the Table: >14.68%
Case 2 - Scenario 2020 Local Module
Nominal CAPEX: R$ 3.57/Wp
TIR Required: WACC+2% WACC
2019: 9.73%
IRR in the Table: >11.92%
Using the Tables
Conclusions
It is noted that some strategies can help to reduce the energy sales price at the actions, considering some estimates. The intention of these analyses is
to compare the presented scenarios and evaluate the pros and cons of constructing and starting up the power plant before the delivery deadline, so it
can anticipate the energy generation, creating additional revenues to the project , in case it is allowed.
Other exercises can be made with the spread sheet. The worse CAPEX condition for private funding are similar to the best CAPEX conditions for funding
by development bank, which shows the advantages of the development bank.
Some points to be noted about some strategies:
• Constructing power plants before the deadline can be a good strategy to reduce the energy sales price at the auction, but should be consider the
feasibility of providing modules and EPC companies available to conduct the work within the time limit set.
• Consider the participation of development banks to guarantee a lower bid is also a risk, due to great uncertainty of approval
and availability of the resource.
• In our scenarios with funding provided by development bank was not considered the delay for credit concession, which often leads to a bridge loan
in order to cover the cash flow of the project. That implies a financial cost which was not considered in our scenarios.
GREENER INSIGHTSOur vision for cost-effective projects
!
Scenarios !
Although they reflect the current conditions, the considered scenarios for implementation of the power plants have high degree of uncertainty, especially in the period from 2019 to 2020.
The 2018 presidential elections in the country can significantly impact the macroeconomic conditions in 2019 and 2020.
Amongst the main Drivers, the exchange rate and the capital cost are the ones which present greater impact in the projects profitability and generates greater uncertainty to the projects.
Modules !
Due to large price volatility of the PV modules on the international market during 2017, there is still great uncertainty about future prices and availability of supply.
The prices variation reached, in 2017, up to +20%. The international market still presents a scenario of great uncertainties for the next years. The risk of eventual impacts in the CAPEX must be adequately priced according to the energy value.
Although a significant portion of the enterprises have used local modules so far, the financing conditions and the availability of resources through development banks are key items for the development of local production.
An important factor to be considered with respect to the modules supply is connected to the delivery availability, both in the local and international market. Price may not be the main driver in a short term scenario.
Funding !
With a great fall in the Selic Index throughout 2017, the conditions of financing and capital structure hadchanged significantly. Debentures issuance for capitalization was a solution found by entrepreneurs.
Although the development banks present competitive financial cost, an investor should consider therequirements for access and the uncertainty about the resources availability, which can limit the volume ofbenefited projects.
The lines practiced for the development banks finance a significant part - though not all - of the project.Therefore they are not adequately fulfilling their role to “foster” the local modules market in the currentmacroeconomic conditions. Since the local modules could represent around 55% of CAPEX of an PVProject, it is critical that the banks cover at least 80% of projects CAPEX, otherwise, the entrepreneursmay choose to raise less funds and finance all items of the power plant with local equipment, except themodules, because they increase the CAPEX by at least 18%, reducing the profitability of the project. If thebanks aim to promote the local PV Modules production chain, it is essential that they create favorableconditions for the purchase of the local modules.
Pricing !Various scenarios were presented to aid in the understanding of a PPA pricing, however it is emphasized thatin any way we consider the presented values as a "milestone" for the 90 MW projects.
It is crucial that entrepreneurs take a higher risk for a competitive pricing, guaranteeing a minimum expected profitability.
The scale of the projects is essential for an efficient cost structure and therefore a competitive pricing. Thescenarios presented to a 90 MW power plant provide just an order of magnitude, and should not be taken asa reference for the ideal size of a project.
If allowed, the construction of power plants prior to the auction delivery deadline, and the energy supply onthe free market, could be a good strategy to increase the amortization period of the enterprise and toguarantee a more competitive energy in the auction. It should be noted that to have the guarantee of sale ofthat energy on the free market, the energy generated must be considered cheap and low-risk.
January, 2018
Strategic StudyUtility Scale Brazilian PV Market 2017/2018
All rights reserved.Enova Solar Energia LTDA
+55 11 3586-9466
www.greener.com.br
Brazil