Upload
karan-avad
View
233
Download
1
Embed Size (px)
Citation preview
8/3/2019 Approximate Estimate - tendering and contract estimation
1/16
Presented by-Karan Avad
Vinayak KendreRohan Desarda
Apurv VaidyaGaurang Malviya
8/3/2019 Approximate Estimate - tendering and contract estimation
2/16
Introduction The only safe and secure way of estimating construction
costs is to take out the quantities of works under thedifferent items and multiply these quantities by the
prevailing unit rates as per the DSR issued by the PWD. However, this can be done only when drawing,
specifications and bill of quantities have been preparedand made available to the contractor.
When accurate cost of construction is not yet required anda rough idea is sought at some stage to help decisionmakers decide whether to proceed or not, approximateestimates of construction cost are used.
8/3/2019 Approximate Estimate - tendering and contract estimation
3/16
Purposes served by Approximate Estimation
To Give a rough idea of the probable expenditure- A rough idea of the probable expenditure has to be
obtained and if this appears feasible, then further detailsmay be considered.
Administrative Approval
In case of government and public works, proper sanctionhas to be obtained for allocating the expenditurerequired for detailed investigations, which is given based
on approximate cost estimating methodValuation and rent fixation
Sometimes it is required to estimate the cost of existingstructure for one or more reasons, in these cases theapproximate methods are adopted
8/3/2019 Approximate Estimate - tendering and contract estimation
4/16
Methods of Approximate
Estimating Service Unit Method
Square meter of floor area
Cubic meter of the building Rough grouped quantities
Comparison of costs at relative dates
8/3/2019 Approximate Estimate - tendering and contract estimation
5/16
The service unit method Buildings are constructed to serve a specific purpose.
For example, hospitals are designed to accommodatecertain number of beds. Each bed is then considered asa Service Unit.
Whenever a building is constructed, the Engineer orArchitect keeps record of the place, actual cost,number of service units and year of construction etc.
From this record it is possible to work out per service
unit. This cost is then adjusted to present day considering
inflation and peculiarities of project and multiplied bynumber of units
8/3/2019 Approximate Estimate - tendering and contract estimation
6/16
Service Unit Method (Total Cost)
Total cost = cost per unit x number of units
8/3/2019 Approximate Estimate - tendering and contract estimation
7/16
Floor Area Method The floor area of the proposed structure is worked out
and then multiplied by a suitable rate.
This rate of construction per square meter of floor area
is worked out by dividing the known cost ofconstruction of a similar building by the floor area ofthat building
The building must be first measured by its internal
dimensions at each floor level and no deductions aremade for internal walls, ducts, lifts or stair cases.
There are some variations of this method asmentioned in the next slide
8/3/2019 Approximate Estimate - tendering and contract estimation
8/16
Floor Area method (Variations) One way is to add all the usable f loor areas and exclude
basement and roof
Another way is to use certain rate for each floor,including roof and basement
Using different rate for basement floor, other floorsand roof
Another way is to have the unit rate of the lower floorinclude basement and foundations and that for the topfloor include roof
8/3/2019 Approximate Estimate - tendering and contract estimation
9/16
Floor area method (Total Cost)
Total cost = cost per square meter x totalproject area.
8/3/2019 Approximate Estimate - tendering and contract estimation
10/16
The Cube rate method This method is more accurate than the square meter
method because the depth of foundations and the height ofthe structure above the ground level are the additionaldimensions taken into consideration.
In order to use the method, the building volume must befirst assessed
Buildings with distinct types of occupation should havecorresponding volumes assessed separately, for example,car park areas, shopping areas and office areas in a
commercial building This method depends on a number of variables, like
building types, proportion of wall area per floor area,quality of finishes and so on
8/3/2019 Approximate Estimate - tendering and contract estimation
11/16
Cube rate method (Total Cost)
Total cost = cost per cubic meter x totalproject volume.
8/3/2019 Approximate Estimate - tendering and contract estimation
12/16
Rough grouped quantities This method aims at overcoming the problems detected in
other single-rate estimating methods, by taking intoaccount variations in plan shape and storey height.
Though, this method was never totally adopted by
construction professionals because it requires much morecalculations than other single-rate methods and becausethe rates needed cannot be directly extracted fromhistorical data.
Basically, the utilisation of the method starts with themeasurement of the building enclosure (comprising floors,external walls and roof areas). Each area is then multipliedby an appropriate weighing factor, thereby resulting the
number of storey enclosure units
8/3/2019 Approximate Estimate - tendering and contract estimation
13/16
Rough Grouped quantities
(weighting factors) Floor areas, measured from the internal face of
external walls: basements x 3;
Ground floor x 2; first floor x 2.15; second floor x 2,30and add 0,15 for each successive floor.
Roof areas, measured in its plan projection, to theextremities of eaves: roof x 1.
External wall areas, measured on the external face ofthe walls: basement wall area x 2;
Above ground level (without any deduction foropenings x1.
8/3/2019 Approximate Estimate - tendering and contract estimation
14/16
Rough grouped quantities (Total
Cost)
Total cost = unit cost rate x number ofstorey enclosure units
8/3/2019 Approximate Estimate - tendering and contract estimation
15/16
Comparison of Costs Method The approximate cost of the proposed structure is
found out by modifying the known cost of similarexisting structure with due consideration to pricefluctuation between the dates of construction of theold and proposed structure.
This method gives best results but it is applicable tostructures which are repetition of similar works.
8/3/2019 Approximate Estimate - tendering and contract estimation
16/16
THANK YOU !