ECRBMINUTESMay24,2017
TO: AllEngineeringCriteriaReviewBoardMembers
FROM: LawrenceJ.Goldzband,ExecutiveDirector(415/352-3653;[email protected])RafaelMontes,SeniorStaffEngineer(415/352-3670;[email protected])
SUBJECT:ApprovedMinutesofMay24,2017,BCDCEngineeringCriteriaReviewBoardMeeting
1. CalltoOrder.ThemeetingwascalledtoorderbytheChair,Dr.RogerBorcherdtat1:00p.m.,intheBeniciaConferenceRoomat455GoldenGateAvenue,SanFrancisco,California.
ThefollowingBoardMemberswerepresent:Dr.RogerBorcherdt,BoardChair,Robert“Bob”Battalio,PE,ProfessorMaryCatherineComerio,RichardB.Dornhelm,PE,LouGilpin,PhD,CEG,andWilliamHolmes,SE.
ThefollowingBoardMemberswerenotpresent:ProfessorMartinFischer,James“Jim”French,PE,GE,ProfessorJackMoehle,FrankRollo,PE,GE.
BCDCStaffMemberspresentwere:Mr.BradMcCrea,RegulatoryDirector,Ms.JaimeMichaels,ChiefofPermits,RafaelMontes,SeniorStaffEngineerandBoardSecretaryandElenaPerez,PermitAnalyst.
Theaudienceincludedthefollowing:CleveLivingston,LaconiaDevelopmentLLC,SamYao(SimpsonGumpertz&Heger-SGH),JeffFippin(ENGEO),PedroEspinosa(ENGEO),ToddBradford(ENGEO),JasonWhite(BKFEngineers),JustinAff(CMGLandscapeArchitecture),MaximoArgo(SGH),LutherGreene(RYC),C.MichaelLederer(BrickyardCove)
Mr.Montesaddressedthemeeting'sagendaaswellassomehousekeepingitemsatthestartofthemeeting;thoseincludedlocationofrestrooms,exitsandseveralotheritems.
ChairBorcherdtcalledforintroductions.
DuringintroductionsBoardMemberBattaliostatedthatEnvironmentalScienceAssociateshaddoneworkfortheCityofRichmond.Heaskedtheapplicantiftheyfeltheshouldrecusehimselffromtheprojectreviewanddiscussion.
Mr.Livingston,theprojectrepresentative,statedtheywouldhavenoobjectiontogettingMr.Battalio'sinputonthisprojectandwouldappreciateit.
2
ECRBMINUTESMay24,2017
2. ApprovalofDraftMinutesforMarch21,2017,EngineeringCriteriaReviewBoard(ECRB)Meeting.
MOTION:BoardMemberComeriomovedapprovaloftheminutes,secondedbyBoardMemberHolmes.
BoardMemberDornhelmnotedonpage2,thesecondparagraphfromthebottommentionedtheAlamedaNavalWeaponsStation.HestateditwastheAlamedaNavalAirStationorNavalAviationDepot,notaWeaponsStation.
BoardChairBorcherdtcorrectedpage15asfollows:
Strikethelastparagraphbeginningwith"HerequestedtheBoard'scomments..."andreplaceitwithtwoshortsentencessaying:"TheBoardunanimouslyrecommendedthataletterbedraftedtoacknowledgethecontributionsoftheCSMIPprogram.TheChairvolunteeredtodraftaletterforreviewbytheBoardthatwouldbesenttotheExecutiveDirectorofBCDCforconsideration."
Inthesecondparagraphchange"TheChairacknowledged"to"TheBoardacknowledged"becausetherewasquiteabitofdiscussionamongtheBoardMembersastothatitem.Alsomovethelastsentenceinthatparagraphbeginningwith"Hementionedbrieflytheongoingwork..."totheprecedingparagraph.
Inthefirstparagraphstrikeoutthewords"disclosedhisintervention"andreplacethatwith"indicatedhisparticipationattheinvitationofBCDC."
Attheendofthatsentencealsoaddthephrase"asdocumentedinthetechnicalspecificationlettersprovidedbyCSMIPandtheapplicant."
VOTE:Themotioncarriedunanimously.
3. ApprovalofLetterofAcknowledgementforOutstandingContributionsofCSMIP.
MOTION:BoardMemberDornhelmmovedapprovaloftheletter,secondedbyBoardMemberGilpin.
VOTE:Themotioncarriedunanimously.
4. BoardDiscussion:LatitudeProject(formerlyreferredtoastheTerminalOneProject)(Pre-Application).BoardChairBorcherdtannounced:WehadanovervieworintroductiontothisprojectatameetingonJune7,2016,whichwasajointmeetingbetweentheECRBandtheDesignCriteriaReviewBoard.SowiththatsaidIwillturnitovertotheApplicant.
Mr.LivingstonaddressedtheBoard:Welookforwardtogettingyourinputandguidanceontheengineeringcriteriaissuesthatwearedealingwithonthisproject.
ThisisaprojectthatwillinvolvetherepurposingoftheTerminalOnewharfthatisover100yearsold.ThatrepurposedwharfwillserveasthecenterpieceforawaterfrontparkthatwillextendthelengthoftheshorelineoftheTerminalOneProject.
3
ECRBMINUTESMay24,2017
ThestructuralengineeringissuesthatwillberaisedbythisrepurposingofthewharfwillbeaddressedbySimpsonGumpertz&HegerandwehavetworepresentativesfromSGHheretoday,SamYaoandMaxArgo.Theywillbepresentingadiscussionabouttheconditionassessmentthattheyperformedonthewharfandtheshorelineprotectionandinadditiontheywillbesharingtheirthoughtsregardingtheresultsofthestructuralanalysisthattheyhaveperformedonthewharf.
TheyhavebeenworkingverycloselywithourgeotechengineerENGEO.HeretodayfromENGEOwehaveJeffFippin,PedroEspinosaandToddBradford.Jeffwillbesharingwithyousomethoughtsaboutthegeotechnicalanalysisthattheyperformedonthesiteandwillalsobediscussingthedeep-soilmixingtechnologythatwewillbeusingtostabilizetheshoreline.
Inaddition,ENGEOandSGHhavebeenworkingwithourcivilengineeringteamthatisfromBKFtodotheanalysisthatisgoingtobecriticaltotheimprovementofthesite.WehaveheretodayfromBKFJasonWhitewhowillbesharingwithyousomethoughtsthatwehaveregardinghowwearegoingtobedealingwiththefloodriskthatisassociatedwiththedevelopmentofthesiteaswellaswithsealevelrise.
AndthenfinallywehavewithustodayJustinAfffromCMG.CMGisthelandscapearchitectontheprojectandIthinkitisfairtosaythatthesuccessofthisprojectwilllargelydependuponthecreativityofCMGintermsofcomingupwithimprovementsthatwillsignificantlyanddramaticallyenhancethepublicaccesstotheshoreline.
Iwouldliketorunthroughsomeslidesthatwillgiveyousomehistoricalcontextforthisprojectandalsowillsetthelanduseplanningstageforthediscussionofengineeringcriteriathatwillfollow.
ThisfirstimageisarepresentationanditshowsthelocationoftheprojectsiteinRichmond.Thesiteislocatedona13-acreportionoflandthatextendsintotheBay.Itisaveryunusualsite,auniquesite,becauseitprovidesnotonlypanoramicviewsoftheentiretheBaybutitalsoprovidesdirectandintimateopportunityforconnectingwiththeshorelineenvironment.
ThisistheRichmondBridge.OverontheeastoftheprojectsiteistheRosietheRivetermuseumandthereconditionedFordplant.Thisiswherethenewferryterminalwillgo.Sothepropertyisextremelywell-situatedintermsoftheregionaltransportationgrid.
Thisisanaerialviewwiththelandplanthatweareproposingsuperimposedupontheadjacentpropertyareas.Again,thisprojectsiteishighlyunusualinthesensethatitissurroundedonthreesidesbynaturalelements.
Theportfacilitythatexistedonthesitewasoriginallyconstructedin1915.Thereisa94,000-square-footwarehousethatstillexistsonthesite.ThispropertyisallbuiltonfillandthereweresomeadditionalindustrialrelatedusesalongtheshorelinebutBrickyardCovewasundevelopedatthetime.
4
ECRBMINUTESMay24,2017
TheYachtClubhasbeenbuiltimmediatelyadjacenttotheTerminalOnesiteandthentheCovehasbeendevelopedintoaresidentialenclavetotheeastoftheRichmondYachtClub.
ThisisapictureofthesiteaftertheRichmondRedevelopmentAgencytookstepstopreparethesiteforredevelopment.In2002theRichmondRedevelopmentAgencyremovedthestoragetanksyousawinthepriorpictureandtheytookstepstoremediatetheexistingcontaminationonthesite.Thoseactivitiescontinueduntil2008andthesitehasremainedrelativelyunchangedfrom2008.
Althoughthestoragetankshavebeenremovedthesiteislargelystillcoveredbyhardscapeelements,foundationsforthetanksandothermaterialsthatwillneedtoberemovedasthepropertyisredeveloped.
Therearereallytwomajorelementsofthisproject.Oneisaresidentialdevelopmentthatconsistsof316residentialunits.
Therewillbe295condominiumflatsandthoseflatswillbelocatedinfivefour-andfive-storybuildingsthatarespreadacrossthesite.
ThesecondmajorcomponentoftheprojectisthewaterfrontparkandthatparkwillextendfromtheintersectionofDornanDriveandBrickyardCoveRoaddowntothesouthandwraparoundtheresidentialportionofthesiteandcomebackinandreconnectwithBrickyardCoveRoad.
Itincludesacoupleofveryimportantfeatures:
One,anextensionoftheBayTrail,whichwillpickupBrickyardCoveRoadhereandrunalongtheoutsideofthelooproadwaythatwewillbeconstructingtoprovideautomobileaccesstothewaterfront.TheBayTrailwillrunalongtheoutsideofthatlooproadrepurposingthewharfintoapublicparkfeaturethatwillbethecenterpieceofthiswaterfrontpark.
Allofthedevelopmentwithinthe100-footshorelinezoneisintendedtoaccommodatethepublicandpublicaccess.
Wearecurrentlyworkingonimprovementsforthewharf.Wewouldliketohaveawooddeckhereanditwillprovideanelevatedplatformforviewingandperhapssomepicnicactivities.
Wewillhavealittle,informalamphitheaterhere.Itisjustasmall,informalareawhereyoucouldhaveaweddingorsomethingofthatnature.
Wewillhaveaturfareawhichwillsupportsomeinformalactivitiesandagardensectionofthedeckthatwillprovidesomealmost-nativehabitatforviewingandsitting.
SowiththatwhatIwouldliketodoisturnthepodiumovertoSamYao.Samwillintroducethevariouselementsoftheprojectthatweareheretodaytodiscuss.
Mr.Yaomadethefollowingpresentation:Clevejustgaveanoverviewoftheproject,heisfromLaconia.
5
ECRBMINUTESMay24,2017
CMGisgoingtotalkalittleaboutthelandscaping,that'saworkinprogress.
ThenthegeotechENGEOisgoingtopresentthegeotechnicalexplorationfindingsandIwilltalkaboutthestructuralconditionofthewharf.
ThenJasonWhiteisgoingtodiscussthefloodingandsealevelriseissues.
Iwillthenpickitupwiththeshorelineprotectionassessment.
Justin,doyouwanttosaysomethingaboutit?
Mr.Affreplied:ThelandscapedesignforthewharfisagreatamenityforprovidingpublicaccesstothewaterfrontaswellasavarietyofotheramenitiesthatClevedescribed.
Themainprogramspacessitwithinthehistoricfootprintofthewarehouseanditisplannedtoraisethatupbetween18and24inchestoacceptsoil,structuralelementsforthedeckanddrainage.ThisdesignwaspresentedtotheBCDCDRBapproximatelyoneyearagoandwearecurrentlyrevisingthedesignaswecoordinatewiththestructuralandgeotechnicalengineersandwewillbecomingbacktotheBCDCDesignReviewBoardwithinthenextfewmonthstopresentthereviseddesign.
Mr.Fippincommented:IamJeffwithENGEOandIwilltalkaboutthegeotechnicalaspectsoftheproject.
ENGEOhascompletedreportsatthesitein2003,2014and2016andanothergeotechnicalengineerworkedonthesiteinthelate'90s.
Somostrecentlyweperformedthreedeepborings,onebehindthewharf,oneinthemiddleofthewharfthrougharockdikeandoneoutnearthewater'sedgeaswellassomeCPTstobetterinformtheshorelineconditionsfromageotechperspective.
Sobasedonallthatdatawecreatedthiscross-section,whichisveryrepresentativeofwhatweseeacrossthesite.Thesitewasbuiltabout1915;sowhentheyfirstdevelopedthesitetheyreclaimedtheland.Allofthesiteatthewharfandthebacklandsareallreclaimedland;filloverwhatusedtobetheBay.
Tofirstreclaimthesiteadredgingprocesswasperformed;aslotcutwasmadeandthenitwasbackfilledwitharockdike.Thereisanas-builtthatshowsyoungBaymudbelowthebottomoftherockdike.Toconfirmthatwedrilledthroughtherockdikeandconfirmedthattherewas10feetofsoilbelowtherockdike,whichmatchesverywellwithwhattheas-builtdocumentsshow.Sotheyplacedtherockdikeandthenputfillbehindit,whichisamixreallyclosetotherockdike,itisamixofBaymuddredgedfromhereandrockfromthehillsidecut.Asyoumovefurtherinlanditismostlyrockcut.
Inthiscrosssectiontheoriginalshorelineis1,000feetbeyondtheedgetotheright.BedrockatthesiteisprimarilyrocksassociatedwiththeFranciscancomplex.
6
ECRBMINUTESMay24,2017
Wedidsomeslopestabilityanalysis.Underastaticconditionthisslopeisplentystablebutunderseismicloading,underthedesignearthquakeunderthecurrentCaliforniaBuildingCodeweidentifiedbothwithcircularandnon-circularfailuresurfacesafailuresurfacethatwantstotravelalongtheyoungBaymudandgowellbackintothesitehundredsoffeetandcouldperhapsdisplaceontheorderoffeet,whichwouldbeunacceptableforboththewharfaswellasthestructuresthatwewanttobuildbehind;soourmitigationforthatistobuildabuttressinthegroundbydoingdeep-soilmixingbehindtherockdike.Therockdikeessentiallywrapsaroundtheentireshoreline.
Itisrelativelyofsimilarconfiguration.Soitessentiallyformstheentireshorelineandthenriprapwasplacedatopit.Sotherockdikeitselfisamix.Itisamixofsandandgravel.
Weknowfromtheas-builtthattheycutaslotthatlookedlikethis.Thebathymetryshowsthatthereissoiltheresowehavejustputinsoilthathasverylowstrengthandatinybitofweightinourmodelingbecauseweknowthatitwasin-filledprobablythroughaccretion.Inourstrengthmodelingthathasverylowstrength.Andwedrovethroughittoo;wehaveaboringthatwasoverhereandencounteredverylowstrength,verylowdensitysoil.
Sobecauseoftheextremelysoftsoilatthesiteandthecomplexityofhavingrelativelyshallow,relativelyhardbedrock,wedidasiteresponseanalysistodetermineifthesoftsoilwouldaffectthegroundshakingatthesiteforstructuralanalysis.
WefollowedASCE7-10procedureswherewecameupwithatargetspectrumthatrepresentedbedrockbasedonthedesignspectrumfromtheBuildingCode,selectedfiverepresentativegroundmotionsthatarecommonlyusedinthearea,matchedthemtothetargetspectrumandthendidone-dimensionallinearequivalentsiteresponseanalysisandcameupwithdifferenttimehistoriesatthegroundsurfaceastheytraveledthroughthesoilcolumn;andthencomparedthoseperthebuildingCodetothe80percentmappeddesignresponsespectrumandcameupwiththeenvelopingcurvethatdoesn'tgobelowthe80percent.
SowhatweseeisthatifyouweretocomparethesiteclassE;atthereallylowperiodsthepeakgroundaccelerationisslightlybelowthetargetspectrum.Intheperiodsofinterestofthestructure,somewherearound0.75ofasecondouttoabout2secondstheaveragespectrumisgreaterthantheCode.ThenatreallylongperiodsitwantstobelowerthantheCodeandwejustmatchittotheCode.
Ithinkitissoftsoiloverstiffrock.ItcomesupwithsomethingthatintheperiodofinterestofthisstructureishigherthanwhattheBuildingCodewouldtellyou.WethinkwegotthespectrumdialedinreallywellandthenSGHusedthatfortheirstructuralanalysis.
Mr.Livingstoncommented:IthinkwhatwesaidattheJune7thpresentationswerethatwehadnotfoundtheas-builts.BKFwentthroughtheirfilesandfoundas-builtplans.
Mr.Yaocontinued:Iwilldiscussourassessmentoftheexistingstructuralconditions.
7
ECRBMINUTESMay24,2017
Thewharfifabout550feetby91feetandrightnowthereisawarehouseontopofthat.
Thestructureisaverythinconcretedeck,about5inches,supportedonbeamsandgirdersandsupportedbyover500piles.
Thisisageneraloverviewcross-sectionofthewharf.Thosepilesareessentiallyona10feetgrid.Therearesometimberpiles,batteredtimberpiles.Essentiallyit'smeanttobedesignedfortakingtheberthingloads.Itusedtobeberthingalotofshipsandbarges.
Thebackofthestructureseismicdesignisacolumnsupportingapilecapandsupportingatimberpile.
Onthelandsideofthewharfthereisabulkheadwall,aconcretebulkheadwalldividedbythe20inchby20inchsquarecolumns.
Thisisthetypicalbandsinthemiddle.Thosebeamsarerunningtransverseandlongitudinalandhaveacoverconnectedwiththepileunderneathandthatisthepilecaprunning.
Ifyoulookatthespiralsonthosepiles;thoseareverymuchclosetoourmoderndesigns100yearslater.Backthentherewasnoconceptofhinge.
Sowehaveallthedetails.Weknowthewharfverywell.
Wedidacorethroughthedeck,throughthepileandthroughthebeam.Thepilesstartingfromthemeanlowwateruptotheundersideofthedeck,includingsomeofthebeams,hadshotcreteforprotection.
Youseesomeofthecoreswehavetakenarefromtheconcretepiles.Herewefoundtherebarandwearecoringbetweentherebar.Thatistherealconcretepile.
Thisisthecorethroughtheback.Wehaveasphaltonthetopandtheconcreteonthedeck.
Thestrengthisnotrealhighbutitisprettycommonbythestandardof1915,3,000/4,000psi.
WeratedeachpileaccordingtotheAmericanSocietyofCivilEngineersManualofPracticeforratingthepiles.Asyoulookatthis,thosearethestandardsoftheindustry.
Ifweratedthepileasmoderatedeteriorationitmeansthatyouwouldseecracksoverit.
Butifitismajoritmeansthatyouseespalls,youhaveverylargecrackscomingupbutitdoesnotshowtherebar.
Onceyouhaveamajorspallexposingtherebarwecallitsevere.Severeisawiderange.Youcanshowthattheconcretespallexposedtheoldrebaruptothewholesection.Asweshowherethewholesectionofconcreteisgone.
8
ECRBMINUTESMay24,2017
Soitisaverywiderangebuttheratingsfollowthestandard.Thisisthesummaryofthepileratingswefound.
Thisistheshotcrete,hereistheshotcrete.Butrightinthefrontthereisnoshotcrete.Myguessisbythetimetheydidtheshotcreteitwasalreadybroken,essentiallybroken.Butthispartisvery,veryneartothewharf,therewasnotshotcrete.Iwouldsay60to70percentofthepilesinthetidalzonewereshotcretedtoprotecttheconcretebecausethetidewentupanddown.Butthisiswayabovethetide.
Wedidnotcuttherebar.Butbasedonthecoreswehavetaken,passingthroughtheshotcretetogettothereinforcedconcrete,thestrengthisgood,theconcretewasnotdeteriorated.Wedidnotlookattherebar.Butatthispointthemajorityofthepileshad4to7inchesofshotcreteprotectingthem.Iftheshotcretestayedaroundfor10,15yearsthereisasignificantcorrosionoftherebar,thatshotcreteisnotgoingtobeabletocontainexpansionofthecorrosion,itisgoingtocrack.
Wecannotsaythatpartiallycorrodedrebarwasprotectedfromfurthercorrosiononcetheyputtheshotcretein.However,theconcretetestingshowsthatthechlorides,thesaltintrudingintothepilesexceededthethresholdforthestartingofcorrosionwithinthosepiles.
Thetestingreportwegotbacksaidthatthereisnothingirregularintheoriginalconcretepile.
SoIwanttogiveasummaryoftherating:33pilesareMinor.ThemajorityofthepilesareinModeratecondition.ThenwehavegotMajordeteriorationofabout20percentofthepiles.ThentheSeveredeteriorationislessthan5percent,about30pilesareinSeverecondition.
Itisveryhardtotelltheconditionsofthetimberpiles.Butingeneralouranalysisdoesnotnecessarilydependonthetimberpiles.Weunderstandthosetimberpilesstayaroundfor100years.Wearenotintentionallyassigningasignificantvariancetothosetimberpiles.
Thetimberpileswereputinfortheberthingloads.
WelookedattheSevereconditionofcertainpiles.AmongtheSevereratingofpilesthereisawiderangeofconditions.Aswemoveaheadtofinalizeourdesignwewanttokeepthisinmind.
Wewilldeterminelaterhowmanyneedtobereplaced.Rightnowwearejustpresentingtheconditions.Itwillverymuchdependonwhatwedowiththewharf,howmuchlandscapingisontopofthis.ButingeneralwewouldliketorepairtheSeveredamagedpilestomeetthesafetyrequirementsoftheCaliforniaBuildingCode.
Fromastructuralperspective,withoutinformationfromthegeotech,fromastructuralperspectiveweareworkingwiththelandscapingarchitecttotrytocomeupwitha35percentdesignbutwearenotthereyet.
9
ECRBMINUTESMay24,2017
Mr.Montescommented:MyassessmentisthatitwillcomebacktotheECRBforafullassessmentofthegeotechnicalandstructuralaspects.
Mr.Yaoadded:IwouldsaythatwhatwepresenttotheDesignCriteriaReviewBoardtodayiswhatwearegoingtostickwithfora35percentdesign,75percentdesignanda100percentdesign.Iwillcomebackandpresenttheseismiccriteriaandjustthedesigncriteria.Wearegoingtostickwiththataslongasyouapproveit.Butthe35percentresults,typicallyyouarelookingforacceptance,approval.Wearenotquitethereyetbutwearealmostthere.
Wearelookingforyourinputnowatour35percentdesignstage.
BoardMemberBattalioasked:Forthosepilesthataremoderatelydamagedwouldyouanticipatethattheymayprogresstoamoreseverelevelofdamagethroughspallingorotheractionduringthelifeoftheproject?
Mr.Yaoreplied:Laconiahiredustofinishthedesign.Iwillserveasthestructuralengineerofrecord.IwouldmakeaformalrecommendationtoLaconiathatyouneedtohaveperiodicalinspectionstomonitorthedeteriorationofthepiles.Ofcourseallthepilesdeteriorate,someofthemfaster,someofthemslower.EventheCaliforniaBuildingCode,Chapter31F,doeshavearecommendationbasedontheconditionofthepile,howoftenyouneedtodoapileinspection.SowewillaspartofourdesignpackagegivearecommendationtoLaconiaforinspectionandgivethemallthepileinspectionrecordswemadesoeitherwedoitorsomebodyelsecandoit;that'sthebase.
BoardMemberBattalioclarified:Sotheassumptionthenisthatthemoderatelydeterioratedpileswouldhaveacapacityorwhatever,exceedingwhateverdesignlevelisrequired?
Mr.Yaoagreed:Thatiscorrect.Wethinkthattheshotcrete,thestrengthisreasonablyhigh.Theshotcretecontainedawiremesh.Butourstructuralassessmentignoredtheshotcrete,justassumedtheoriginalconcretepileswith4,000psistrength,sothatisourbase.Buthoweveryoudohaveshotcreteinacertainportionofthepiles;thatisagivenfact.Ithinkthatingeneralthatthepilesthatdonothavesectionloss,theyprobablyhavethecapacitytocarrytheloads.Butyouhaveacertainamountofsectionloss.Youaregoingtoreducethepilecapacity.Thatisthewaywewouldapproachit.
All30pilesoverhereonthistableareratedSevere.ButwithintheSevereratingthereisadegreeofdeteriorationsowedivideditintothreecategorieswithintheSevererating,the30piles.Only3pileshavesectionlossofover50percent,another3pileswithsectionlossof25to50percent,andtherestofthemarelessthan25percent.
BoardMemberHolmescommented:IamjustlookingatthedescriptionofMajor.Itincludesmultiplecracksanddisintegrationduetochemicaldeterioration.Thatsoundslikesomethingthatmaybeshouldnotwaitforinspection,itsoundslikethatshouldbefixedordeteriorationstoppedimmediately.
10
ECRBMINUTESMay24,2017
Mr.Yaoagreed:Iagreewithyou,Mr.Holmes.Ithinkthatwhenweapproachthepilerepairweworkwiththeowner.Youstudynotjustthestrengthrepairbutstartwithyourpreventativemeasuresearly.Actuallylong-termyouaresavingmoney.Buttheirapproach,peoplejustsay,"Ionlyrepairwhatisnecessary."Sowewillworkouttheoptions.Aslongasitismeetingthesafetyrequirementwehavemultipleoptionsforthemtochoose.Butmypersonalexperienceisthatifwetakethepreventativemeasuresearly,actuallylong-termyousavemoney,yousavemoneybymaintaining.
BoardMemberHolmesasked:WhatdoestheASCEguidethatyouaretakingthisfromsuggestaboutMajor?
Mr.Yaoexplained:TheASCEguidedoesnotrecommendasetmeasurefortheMajorcategory.ASCEisjusttohaveapples-to-applescomparison,everybodyisgoingtorateitthesameway,haveveryspecificcriteria,youratethisMajor,youratethisSevere,youratethisModeratesowehaveacommonlanguage.
In2005thatinspectionwasverybrief,wasnotratedaccordingtostandardindustrypracticetodaysoitisveryhardtomakeacomparison.Butingeneralwedoseethatthestructuredoesunderstandablydeteriorateoverthelast11years.
BoardMemberHolmescontinued:Butjustlookingatthesedescriptions,IcanseeModeratebeingputoffandinspected,thatmakesalotofsense,butthedescriptionofMajordidnotappealtomethatway.
Mr.Yaoadded:Well,thestructuralassessment,itisdebatableiftheMajordeteriorationconstitutesamajordefectonthestructuralcapacity.ButingeneralweliketoaddressthisbeforeitbecomesSevere.Sothatismyexperience.Thefirstoptionissomeownersdonotwanttodothat,theywanttodelay.Thatisanoption,stillmeetingtheBuildingCode.
Weareintheprocessofdoingacapacityanalysiswithseismicload.
BoardMemberBattaliostated:Iguessthequestionwaswhetherornottheproposedloadingislessthanthewharfloading.IguessitmightbeverticallybutIdonotknowaboutthelateral.
Mr.Yaoreplied:Well,thisisaveryimportantpointIhadplannedtoaddresslaterbutsinceyoubroughtitupIwilljustsaythis:Thiswharfwasdesignedforvery,veryheavyindustryloads.Forthefuturepublicaccesswewillneverseesuchhighloads.
Butsayingthat,thepublicsafetyshouldnotbeputindanger,westillneedtomeettheBuildingCode;butthewharfisverysturdy.Itwasdesignedforloadsseveraltimeshigherthanwhatweplanfor.Sotheloadswearegoingtoputonthewharfaremuchlighter.
WetakethewholethingintoconsiderationbutwearegoingtoprovethatwearemeetingtheBuildingCode.Wewillstillkeepthewharfhealthy,atleastforseveralyearsforthenextinspection.Thatisthegoal.
Iwillpresentdatarelatingtoseismicloadabitlater.
11
ECRBMINUTESMay24,2017
BoardMemberDornhelmcommented:SoIinferfromthisthatthedevelopmentremainsresponsibleforthemaintenancewhichincludesthefutureinspectionsofthewharfsothatweknowthatwhatwearecountingonbeingdonetoprotectthepublicspaces,ratherthanjusttheprivatespaces,willbeaddressedintheplanthatyouprepare.
Mr.Livingstonstated:Thatiscorrect.
Mr.JasonWhiteofBKFEngineeringaddressedtheBoard:Iwilltalkalittlebitaboutsealevelriseandfloodingatthesite.
WeperformedananalysisaspartoftheEIRfortheprojectfordesigningthesiteelevationsrelativetofuturesealevelrise.
ThebasisforanalysiswasanupdatedFEMAFIRMpanelissuedin2015whichsettheworst-casebasefloodelevationforthesiteat11feetforZoneVE,whichisazonethatissubjecttoinducedvelocityactionbya3-footorhigherwave.Sothat11-footbasefloodelevationisthestartingpointforoursiteelevation.
ThenwhatwedidiswetookalookatdatafromBCDCandNOAAforpredictedsealevelrise.Thatreportindicatedthatsealevelrisewaspredictedtoriseby16inchesby2050and55inchesby2100.
Sowhatwehavedoneiswehavedesignedthesitetothemid-centuryandwewouldintendtoemployadaptivemeasuresaftermid-centuryifsealevelriseoccurredbeyondthatorwhenitbecomesanissue.
Sothat16inchesby2050plusthebaseloadelevationof11feetgivesusastartingpointof12.3feet.ThenwewentwiththeBuildingCoderecommendationfor2feetabovethatsoourminimumfinishedfloorelevationforthesiteis14.3feet;so3.3feetabovethebasefloorelevationof11feet.Weareactuallyacoupleoftenthshigherthanthat,weareat14.5feet.
InadditionwehavetheBayTrailaroundtheperimeterofthesite,whichwearealsosettingat14.5feet;theBayTrailwhichconnectstothewharfpark.TheBayTrailwillbeat14.5feet.Currentlythewharfsitsatanelevationofapproximately13feet.WiththelandscapingimprovementsthatJustinmentionedwearegoingtobeplusanother18inchesto24inches,whichwillputus14.5feetto15feet.
Mr.Affadded:Exceptforatthewatersidepart.
Mr.Whiteagreed:Correct.Thepublicimprovements,BayTrail,themajorityoftheparkarealsoatthe14.5footelevation.
BoardMemberComeriohadaquestion:IsthereareasonwhythatpieceattheBaysideislower?I'mconfused.Whyisthat?
Idon'tknowhowdeepitis.Whyisthatprominent?Iamcurious,whyisitatalowerlevel.
12
ECRBMINUTESMay24,2017
Mr.Affexplained:Theideaistokeepthis15footwidepromenadeattheBaysideatthatlowerlevel.Ithinkwearegoingtohaveaspartoftheimprovements,intherangeofimprovementswearegoingtohaveanadditional6inchesofconcretetoppingslabontopofthat,soitwillgetraisedupalittlebit.
Partofthedesignideafortheparkwastohavethisraisedsectionsitatthehistoricfootprintofthewharfwarehouse.Oneelementofthatisitmarkingthehistoricaluseofthesite.
Mr.Fippinadded:Thepromenadekindofmimicstheexistingwalkwaybetweenthewharfandthebuilding.
Mr.Affcontinued:Idon'tknowfromthepointofviewofsealevelriseifthereisaproblemifweget55inchesofsealevelrisein50yearstherewillbesomeovertoppingofthatslabonthatedge.
Mr.Livingstoncontinued:Ithinkthemainideawastocreatesortofanactivepromenadealongthewaterfrontwherepeoplecouldwalkandstrollandbasicallytakeadvantageofaccessdirectlytothewaterandbehindthatcreatethesesortofdifferentelementsthatwouldfocusondifferentusesoftheland,againwithinthebuildingfootprintoftheexistingwarehouse.Soitwastotryandcreateapromenadethatwouldbecomplementedbywhatwecommonlyrefertoasroomsthatarebuiltwithinthefootprintthatwouldbemorepassiveuse.
BoardMemberBattaliocommented:Idohavesomequestionsorcomments.Letmejustgiveyouaheads-uponacoupleofmythoughtsandwecanaddressthemwheneveryouwant.
Firstofall,the16inchesandthemid-centurytimehorizonareconsistentandmaybealittlehigher,the16inchesisalittlehigherthansomeofthemorerecentguidelinesandsothatisfinebutthemid-centurytimehorizonseemsalittleshortforadevelopmentthatwillprobablybetheremuchlongerthanthat.
SoIguessfromthatperspective,giventhat16inchesisalittlehighformid-centurywithrecentguidance,theactualamountisprobablylowbecauseyoureallyshouldbelookingfartherintothefuture.Alotofwhatweareseeingnowispeopleusingsomewherearounda3footvalueofsealevelrise,whichissomewhereinthe2070to2100ormaybeevenalittlelaterthan2100timeframe.Maybeitishighbyalittlebitbutthatisthewaytheseaisgoing.
Sothatconcernsmealittlebitthatyouareusing16inchesandjustifyingthatas2050,whichIthinkisbothlowandsoon,inmyview.
Mr.Whiteclarified:Weareusingthe16inchesplus2feet.
BoardMemberBattalioreplied:Yes.Idonotknowwhereyougotthe2feetbutthegoodthingaboutaddingthose2feet,whichisprobablysomethingyoudidearlyonwhichisgreat,asanengineerIthinkthatwassmart,butyouarestillacoupleoftenthsofafootorhalfafootshyofadding3feetplussomesortoffreeboard.
13
ECRBMINUTESMay24,2017
Youknow,it'sfunny,whenwedesignbeamsandthelikeweusuallyfigureoutwhatweneedandover-designalittlebit.Ithinkfreeboardisnotabadidea,evenifweareaddinginsealevelrise.ThereisnotsuperclarityinthepracticeonallthatbutIwouldassumefromwhatIhaveseenthata3footsealevelriseasadesigncriteriawouldbeconsistentwithwhatIamseeingelsewhereintheBayandthensomeleveloffreeboardabovethat,whichmeansthatyour14.3isalittlelowbecause11+3+1wouldbe15.Nothingisthatprescriptivebutthatismyfirstthought.
Thesecondthoughtistheshoreelevationawayfromthewharfisat8feet.IguessthatisNAVDormeanoverthewater,whichiskindofclose.Sothatmeansthatpartoftheshoreisover-toppedwitha100yeardesignoraFEMAfloodeventrun-upof11feet.Sothatmeansyouhavewaterrushinglandward,sothatneedstobeaddressed.
Mr.Whiteanswered:Right.AndIthinkSGHhassomeimprovementsthattheyareproposing.Theycanspeaktothatinamoment.
BoardMemberBattaliocontinued:OntheadaptationwearereallylookingforalittlemoredetailthanwhatIhaveseensofar.Maybewewillhearaboutthatintermsofhowyouadapt.Ithinkthereisareferencetoawallontheedge,whichisoneadaptationstrategy.Butaproblemwithawall,especiallytheedge,isthatitisovertoppedandthenyouhavewaterontheothersideofthewall.
Whatsomepeoplearedoingishavingaplacewherethewatercanovertopandrunback.Theadaptationstrategyshouldactuallylooklikeitfitsandhavesomesortofconventiontoitsothatitlooksfeasible.Nottosayitisnotbutwedonotknowwhatitis.Justsayingthereisawall,inmyminditisawall,block,drainageone-way;ifitisovertoppeditcannotgetout.Anditismorelikelytobeovertoppedifitisseaward.Andithastobehigher,whichobstructstheviews,whichinmymindmeansthat50yearsfromnowitmightnothappen.
Mr.Livingstoninquired:Whenyousuggestthatweusethe3footcriteriaasadesigncriteria;areyoutyingthattoanyparticularperiodoftime?
BoardMemberBattalioexplained:Yes,Iwouldsaythatthereisariskthatcouldbeachievedorrealizedbyatimeframesomewherebetween2070or2130.Butdonotholdmetothat,Iwouldhavetolookatthecurves.Wealltalkaboutwhatisgoingtohappenatcertaintimehorizonsbuttheotherwaytolookatitistotakeacertainheight,thenyouhaveaverywiderangeofpotentialtimehorizonsdependingonwhatoccurs;wedonotreallyknow.
ButwhatIamseeingisthat-andthisisconsistentwithwhattheECRBhastoldotherfolksbeforeyouall-isthatthe3feetseemstobereasonable.Itisthemid-rangeprojectionfromtheNationalResearchCouncil2012report,whichwasadoptedbythestatein2013,theOceanProtectionCouncil,isabout3feetbytheyear2100atthemid-rangeprojected.Sothatiskindofwherethe3footcomesin.
Butifyoulookatsomeofthenewguidanceorothernumbersorthenewinformationthatisnotguidance,thatmaynothappenuntillater.Andthereisalwaysawhat-ifkindofworstcaseandthenitcouldhappenalotsooner.Icannotbemorespecificthanthatintermsoftiming.
14
ECRBMINUTESMay24,2017
Mr.Affaskedforclarification:Whenyousaid11+3+1,isthe1feetfreeboard?Whatisthe1?
BoardMemberBattalio:Yes,Iwasthinkingfreeboard.IthinkonethingtolookatiswhatFEMArequiresofthefinishedfloorelevationorlowerstructuralmember,whichwouldbeyourconditionatsomefuturetimewithcertaincriteriaandwhetherornottheyactuallyrequirefreeboard.
TheotherpointaboutafreeboardisonasitelikethisIamsurethereisgoingtobeslopesandmaybeevensomeuncertaintyatcertainplaces.
Mr.Aff:Becausewewouldbeathalfafoot.Weareat14.5forthoseelevations.
Mr.White:Isyourrecommendationforthe3feetplus1footoffreeboard?IsthatforthebuildingelevationortheBayTrailorthewharforalloftheabove?
BoardMemberBattalio:Thesearemycomments,IamnotsuretheBoardhasactuallyprovidedyouarecommendation.Thepublicaccessareacanaccommodatesomeovertopping.Oneoftheadaptationmeasurescouldbetocloseitduringanextremeeventinthefuture.Alotoffolksarelookingataccommodatingsomeofthefloodingintheshorelinebandthatisalsousedforpublicaccessandrecreationalviewing.
ChiefofPermitsJaimeMichaelscommented:TheCommission'scurrentpoliciesonpublicaccessdorequirethatitremain,toparaphrase,usable,eveninextremefloodingsituations.Thosepoliciesmaychangeoverthenextfewyearsbutwewouldwantthispublicaccesstoremainusable.
BoardMemberBattalioasked:Evenduringa100yearevent?
Ms.Michaelsreplied:Ideally.Itmaynothappenbutideally.Thatiswhatweareadvising.Andweknowthatwehavesomeworktodotomakesureitisapplicable.
BoardMemberBattaliocontinued:Inmymindthereissomerelaxationofdesigncriteriaforpublicaccessifitisonlyoccasionallyimpactedandstillreusable.
SeniorEngineerMontescitedpolicy:PolicyNumber5ofthepublicaccesspoliciesoftheBayPlanreads:
"[p]ublicaccessshouldbesited,designed,managedandmaintainedtoavoidsignificantadverseimpactsfromsealevelriseandshorelineflooding."
Ms.Michaelsadded:It'sthegoal.
Mr.Whitecommented:Theshorelinetrailcouldeventuallybecomealevee.Itcouldberaisedtoprovideprotection.
BoardMemberComeriospoke:Yourplanshowsthepromenadeatalowerelevationandyouneedbeawareofaccessanddesignissuesasyouuseitforpedestrians.Thiswillaffectallofyourotherdesigncriteria.
15
ECRBMINUTESMay24,2017
RegulatoryDirectorBradMcCreacommented:ItwouldbehelpfultogettheBoard’sadviceonhowmuchflexibilitywehaveatthewharf’sedgeforpotentialelevations.
Mr.Yaocontinued:SGHdidasiteinspectionanddidsomeengineeringassessmentsoftheshorelineprotection.Iwilladdresstheshorelineprotectionthatexistsnow.
Theexistingriprapcanbedividedintothreeareas.Thefirstareaisdirectlyunderthewharfanditiscategorizedas,“light”;thatis,200poundsorless.Ifyougonorthwestyouhaveprettybigriprap;one-quartertooneton.Thesoutheastsidealsohasthissizeofriprappresent.
Themostexposedareaistothenorthwest.Theslopesinthisareavaryabit.
Mr.Montesasked:Areyoudescribingthedikebeingusedasshorelineprotectionasriprap?
Mr.Yaoreplied:Yes-correct.WeranawaveanalysisandthebathymetryisbaseduponNOAA’sDigitalElevationModel(DEM)forSanFranciscoBay.
TheCaltransShorelineManualrequiresprotectionofalightorsmallsizeriprapforthesite.Wehavedeterminedthattheriprapattheexistingsiteisadequatefora100yearstorm.
BoardMemberBattalioobserved:Youhavetwodifferentconditionshere;youhavetheshorelineandyouhavethewharf.Atthesoutheastpartoftheshoreyouarelookingatitmorestructurallyfromanerosionprotectionperspective.Thequestionthengoesbacktothefloodmanagementforthestructuresontheshore.
Mr.Yaoreplied:Ourscopeofworkinvolvesprotectingtheriprap.
BoardMemberBattalioadded:Iftheprojectreliesontheshoreprotectionthroughitsprojectlifeitalsoneedstoconsidersealevelriseandtheincreasedovertoppingpotential.Structuralfailurepotentialneedstobeaddressedifthesoilbehinditismobilized.
Wewouldalsoexpectthegeotechtotakealookatthedifferentslopestoseehowstableitmightbe.
WhateverdesigncriteriaisusedfortheBayTrailshouldalsoextendtotheaccesscorridorweseeherethatgoestotheshoreline.
Mr.Yao:WewillcertainlyconsiderthevariouscommentstheBoardhasmaderegardingelevations,wavesandassociatedriskswhendoingouranalysis.
BoardMemberBattalioadded:Itseemsthatthewaterisrelativelydeepsotheaddeddepthofsealevelriseshouldnotaffectyourwind-wavegenerationoryourtransformations.Butitdoesaffecttheelevationofthetotalwaterlevel,thewaverun-up,becausewhateveryourrun-upvalueis,itisnowonahigherpeg.Soitdoesrelatetothecrestofthestructureandthepotentialforerosionofthesoilbehindthestructure,whichisactuallypartofthestructuralperformance.
Mr.Yaoreplied:Yes,Iunderstandthat.
16
ECRBMINUTESMay24,2017
BoardMemberBattaliocontinued:AlsotheFEMAworkispublicnow,theydidpublishmodelwaveheightsandwaterlevelsandstuffsoyoucouldalwaysjusttakealookatthat,althoughIhadnocommentonyourmodeling.
Mr.Yaoanswered:Althoughthecriteriahavedesignforit,thesitehashistoricallyneverrecordeda100-yearstormasyet.
BoardMemberBattaliostated:IthinkIunderstandwhereyouaregoingwiththat.IdonotknowtowhatresolutiontheFEMAanalysiswasdoneandtowhatextenttheyconsideredthewavecrestelevationorthewaverun-upatthewharf,whichisdifferentthantheshore.Thatwouldbeuptoyoutoevaluateifyoufeltitwaspertinenttoyourcriteria.
Mr.Yaocontinued:ThedesigncodewefollowisCaliforniaBuildingCode2013,ASCE61-14.ASCE61-14isSeismicDesignofPiersandWharves.Weusethemasareferenceandnotadesigncode.AndthenASCE7-10,everybodyknowsthatistheloaddesigncriteria.AndthenNCHRP611,thatiswhatENGEOusedfordesigningtheseismiccriteria.Sowehavejustfourdesigncodes.
Mr.Yaowentintovaryingdetailandexplanationofdifferentcodesandcriteriausedfortheproject.
Mr.Yaostated:Forseismicloadweused100percentinonedirectionplus30percentintheotherdirection.Wealsolookedatkinematicload.TheCaliforniaBuildingCodeallowedustocombinethemtogether.
BoardChairBorcherdtasked:SowheredoestheDSMsitwithrespecttothefailurecircle?
Mr.Yaoexplained:TheDSMissittingoverherebutthereisamuchbiggercirclebehinditifyoudonotviewtheDSM.ButthiscircleassumestheDSMhasalreadyoccurred.
BoardChairBorcherdtinquiredfurther:IsthereevidencewithrespecttohowyouexpecttheDSMtorespond?Anumberofdifferentthingscouldtranspire.Howdoyouexpectittorespondifitexperiencesalargeearthquake?
Mr.Affreplied:Sothesizethatwehavegivenit,ouranalysisindicatesthatitisgoingtodisplacelessthan4inches,thesoilbehinditaswellastheDSMitself.
BoardChairBorcherdtcontinued:TheDSMisalargemassthatismuchdenserthanthesurroundingsoftsoil.Fromonepointofviewitcouldreflectseismicenergyinthesensethatasseismicwavescomein,ifitisalargeenoughstructureitislikegoingfromsoftsoiltohardrock,therewillbeatendencyforittoreflecthigh-frequencyseismicenergy.Sothequestionis;howwillthatmoveasthegroundarounditmoves?
Mr.Yaoreplied:Ihaveworkedonseawallsinotherprojects.Thatisaverycommontechnologynow,designedmethodology.Ithasinterconnectedbuttresses.
Buttresseshavebeenacommonwayofdealingwithittolimitthemovementoftheground.
17
ECRBMINUTESMay24,2017
Mr.Espinosaadded:DSM,wehaveuseditonTreasureIslandandotherprojectsthatwehavepresentedtotheECRB.Basicallyitisastaticmodelwhereyoulookatitintwo-dimensionalasagravityrole.SowebelievethatitwillbeasimilarcasebecausewehavesimilarsoilwiththeyoungBaymud.
BoardChairBorcherdtopined:IwouldthinktheDSMwouldbestrongerthanthesoil.
Mr.Espinosaagreed:Correct.Buttheincoherenceofthewaves,theyarenotstrongenough.Thatincoherencedoesnotcreateashearissueonthebuttressandthebuttresswillnotbreakbecauseofthat.
BoardMemberHolmesinquiredabouttheDSMaswell:ThesoilinfrontoftheDSMiswhatismoving?
Mr.Affresponded:Thatiswhatismoving,yes.Sothesoilbehinditismovingmaybesomebutsignificantlylessthanthatsoilwhichismovinginfront.ButtheamountofmovementismuchlessthanwhatwepredictedwithouttheDSMbuttressbecauseweshortenedthefailuresurface.Wehavealotlessdrivingforceandweareincludingthepinningforcesfromthestructure.
Mr.Montesinquired:SoafteragroundmotionwilltheDSMcrackandthenyouhavetoredoitorwhathappens?
Mr.Espinosaexplained:Itisusuallydesignedforthedesignearthquakesoitwouldnotcrackunderthedesignearthquake.Thatishowthemajorityofthebuttressesaredesigned.InthiscasewedonotforeseeanyareaswhereyouaregoingtolosetheshorelineandtheDSMisgoingtostaycantilever.
Mr.Fippinstated:SotherearefourdifferentchecksthatFHWArequiresthatendupdeterminingthewidthofyourbuttress.Thatishowwecomeuptothe1-to-1depthtowidthratio.
Mr.Espinosaadded:Itisdesignedfortheearthquakeanditisdesignednottocrack.
Mr.Fippincommented:Theperformanceofthesoilinfrontofthewharfisreallythecriticalsituationhere;whichis,howmuchisthesoilgoingtomovebelowthewharf?WecanmakethatDSMbuttress300feetwideanditwouldnotmakethesoilbelowthewharfmoveanyless.
BoardMemberHolmesstated:Iunderstandtheprocess.IamnotfamiliarwiththedesignofDSM.
Mr.Affresponded:Right.MyresponsetothatwouldbethatweareviewingthisfromtheperspectiveofprotectionofthethingsthatarebehindtheDSMbuttress;thatisaslopestabilityissue.Andtypicallyslopestabilityorsoilsthatarenotliquefiablesoilsisperformedatthesameseismiclevelthatthestructuresthatareaffectedbytheslopeisperformed.
BoardMemberGilpinstated:Pseudo-staticanalysisofslopestabilityisusuallyafactorofsafety1.1or1.2.
18
ECRBMINUTESMay24,2017
BoardMemberHolmesobserved:Itisnotthefactorofsafety,itiswhatearthquakeareyouconcernedwith.
Mr.Yaocontinued:Somuchforthekinematicloadevaluation;wejustexplainedthemethodology.
IcametotheBoardandpresentedthesamemethodologylasttimeontheBrooklynBasin;themethodologyessentiallywasacceptedonthatwharf;andMr.Holmes,youwerethere,Iremember.SoIamgoingtoskipthisnow.
Inertialloadsareessentiallyanon-linearpushover.Wehavethreepointstodefinetheperformanceofthestructure:oneisinitialyieldingofthestructure;thesecondisLevel1performance,thatisrequiredforimmediateoccupancy;andLevel2iswhenthestrainlimitofthematerialisreached,theconcretestrainlimitasdefined.Atthatlimittheconcreteisgoingtobecrushedsowearegoingtostayawayfromthat.
Basedonthiswefigureoutthedemand.Thedemandisexplicitbecauseitisanonlinearanalysis.Itisanexplicititeration.Essentiallyitisthatweguessthedisplacement,wereachtheequivalentenergybehindthis.Itisaniterationprocessuntilthestiffnessisconvergedandtheysay,hey,thisisthedemand,thedisplacementdemand,andcomparedwiththecapacity,theLevel2displacementcapacity,whatisthedemandforcapacityratio?Thatisessentiallytheamount.
Wearestillinteractingwiththelandscapearchitect.Theinertialloadanalysisheavilydependsonhowmuchweightyouaddontopofthewharf.Ofcoursethelandscapearchitectwantstodogoodwork;theywanttomaketheparkbeautifulbutalsoaddalotofweightonit.
ButwhatIcanpresenttotheBoardtodayisthatbasedonthisanalysis,theinitialanalysiswithsomeassumptionsoflandscapedesign,whatwefoundoutisthatthisslopecomingdownhasripraponitandbelowtheriprapisabunchofgravelfilloverhere.Basedonthisanalysisthatlastfourrowsofthepilesattract80percentofthelateralloads.Thepilesinthefront,theyarejustgoingalongfortheride.Butthestressesareonthosepiles;thelastthreerowsarecritical.Theycouldpotentiallyshearoff.SothatiswhatIamtryingtosayhereisthatthiscolumn,20inchby20inchcolumn,plusanothertwoorthreerowsofpiles,arecriticaltotheseismicresistance.
Now,incasethelandscapedesignexceedsthecapacityofthewharf;thenwhatarewegoingtodo?Iamgoingtopresenttoyoutheanticipatedrecommendedoption.Wehaven'treachedaconclusionyetbutIwanttopresentit.
BoardMemberHolmesopined:Alsoyougetabigtorsionfromthat.Youhaveabigtorsioncausedbythefactthattheentireloadgoestothosebackpiles.Themassiswayoutheretowardsthemiddleandthenresistanceisallonthebackside.
Mr.Yaoasked:Youaretalkingabouttorsionfortheearthquakeintheotherdirection?
BoardMemberHolmesreplied:Yes.
19
ECRBMINUTESMay24,2017
Mr.Yao:Wecounted100percent/30percent,then100percent/30percent;yes,soyouareright,thereissometorsion.Butthewharfislong,550feetlong,soallthose500-somepilesareresistingthistorsion.
Iagreewithyou,thecenterofgravityandcenterofresistancearenotaligned.
BoardMemberHolmesasked:Butstiffnessfortorsionisthesameasstiffnessforlongitudinal,right?
Mr.Yao:Thatiscorrect;Iagreewithyou,thankyou,butIhadtosimplifythepresentation.Thisiscoveredinour3Danalysis,100percentinonedirection,30percentintheotherdirectionand100percentinthisdirection,30percentintheotherdirection.
BoardMemberHolmespressedforclarification:Arethose4pilesessentiallymodeledthesameordoyouactuallyshowthatthatfirstpilealmosthasnolengthandthenthenextonehasalittlemore,thenextonehasalittlemore.Youaresayingthatloadistakenbythose4piles.Itseemsliketheloadwouldallbetakenbythefirstpile.
Mr.Yaoexplained:Thefirstpiletakesalotofloadbutkeepinmind,thosearerock.Thoseareripraprockssotheyareprettystiffresistance.Yes,thereisadistribution.Obviouslythiscarriesthemaximumloadsandthisisslightlyless,thisisslightlylessandthisisslightlyless.ButwedidseethesethreeformhingeswherethereisaLevel1hinge,level2hinges.Thejuryisstillout,arewegoingtoneedtheLevel2performance?ItverymuchdependsonhowmuchweightweputonitsoIamnotgoingtogiveyoutheconclusionasofyet,weareinteractingwiththelandscapearchitect.
BoardMemberHolmescommented:Iamfamiliarwithhillsideconcreteframesthathavethesameproblem;theuppercolumnwantstotaketheentireloadanditisveryhardtomakethemwork.
Mr.Yaoagreed:Youareright.
Anticipatedstructuralretrofitstrategies.ThisstrategyhasbeenusedinotherterminalsrightaftertheLomaPrietaearthquakesoitisapprovedandtrueandforthisprojectitisprobablytheeasiesttodo.Asweapproachthisweneedtohaveaconcreteoverlayontheexistingdeckanyway.Theconcreteoverlayisfordrainagepurposes.Thestormwaterrunoffneedstobedrainedtosomeplaceelse.AndalsotheBayTrail,youhavepeoplegoingbackandforthonthisplusthewaveslammingforcesandotherforcescomingalong.A5inchconcretedeckwithmaybesomecracksonitisbarelymakingit.
Whatweproposeisoneoftwostrategies.
Oneisthatyouhaveawarehousesittingoverhere,youhaveawarehousesittingoverhereandyouhaveanotherwarehousesittingoverhere.Thosewarehousesaregoingtomoveawaysowehavetheexistingpiles,thousandsofexistingpiles.Wecouldhaveaconcreteoverlaytotiethiswharftothebacksoallofthosepilesarehelpingtheselastfewrowsofpilestoresist;sharetheloadsandreducetheloaddemandonthosepilesandwharves.
20
ECRBMINUTESMay24,2017
Orweignorethosepilesandjustdriveanewpileandtieittothedeckandsharetheloadandthisnewpilewearegoingtodesigntotaketheloads.Byanalysiswewillbeabletodesignit,makesurethatnoneofthewharfpileswillfail.SothatisthestrategyIlookforifwearegoingtomoveforward.
IftheexistingwharfdoesnotmeettheBuildingCoderequirementsIproposeoneofthetwostrategiesmovingforward.
BoardChairBorcherdtasked:Thelengthofthewharfis550feet,Ithink.That'salmostthewavelengthofaonesecondwavetravelinghorizontally,likeasurfacewave.Sohaveyoutakenintoaccountthedifferentialmotionsthatyouwouldexpectoverthelengthofthewharf?
Groundmotionscouldbehighononeendandlowontheotherendorviceversaasthewavepropagates.
Mr.Yaoanswered:Iunderstand.WedidthosethingsontheRichmond/SanRafaelBridge,ontheBayBridge.Butthestandardofengineeringpracticeassociatedwithwharvesandpiers,wedonotgetthatsophisticationandtheBuildingCodedoesnotrequireit.Thereisenoughstructuralconservatisminourapproachtoit.
Butmaybethereare56bandsandthemajorityofthebandsaregoingtohaveapile.Wehavenotchosenthepile,wehavenotdoneit,butaftertheLomaPrietaEarthquakethePortofOakland,allthosewharves,wewouldgobackanddrivenewpilesandtiethisbackandtheyarestillinuserightnow.
Therearethreewarehousesshownhere.Twowarehousesaretotallyonland.Thereisanotheronethatdoesn'tshowherethatistotallyonland.Oneissittingonthewharf.Sothosewarehousesaresittingonotherpilessotherearealotofpilessittingoverhere.IfIneeditIjusttiethiswharftothosepilesbecausethosewarehousescanberemoved.
Someofthepilesaregoingtobebadandwearegoingtorepairthem.Wearegoingtocoverthoseareas.Wherethereisseveredamagewearegoingtorepairthem.
Mr.Affspoke:ADSMbuttresswouldbebasicallyconstructedbydoingoverlappingcolumnsofdeep-soilmixingthatrunperpendiculartotheshorelinenorth/southingeneralandbasicallycreatecounter-fortsthatareinthegroundthathelptoresistsoiltryingtomovetowardsthewater.Itwouldgoalongtheentireshorelineband.Itwouldgoinbothdirectionsbeyondthewharftoprotectthelandbehindandincreasetheslopestabilityperformanceoftheentireshoreline.
BoardMemberComerio:Soarethosejustin-betweenthoseexistinglandsidepiles?
Mr.Aff:WewouldtrytocentertheDSMbetweenexistingpilesinthegroundandwewouldhavealayoutthatwouldminimizeavoidances;thatis60feetdeepby60feetwide.
BoardChairBorcherdtasked:WilltheDSMgointoBCDCjurisdictionzone.Willitbewithinthe100footshorelineband?
21
ECRBMINUTESMay24,2017
Mr.Affreplied:Thebestperformancehappensifitoccursasclosetotherockdikeaspossibletomakethefailuresurfacesassmallaspossible,whichwouldpushyouwhereverthehighwaterlineisonthiscross-section.Youareprobablystartingsome30feetfromthebeginningofBCDCjurisdiction.
BoardChairBorcherdtadded:ThatisprettystandardtechnologyforinstallingtheDSM;ithasbeendoneinquiteafewplaces.
Mr.Affstated:TheydiddoalotofitatthePortofOakland.
BoardChairBorcherdtsurmised:Butjuststandingbackandlookingatthebigpicturenow,ifwethinkaboutthisfromaBCDCperspective,itseemstomethatbasicallytheprincipalthingthatistranspiringintheBCDCjurisdictionzonewillbetheconstructionoftheDSMzoneasazonetohelpresistlateralmovementorsoilfailureandcontainanymovementthatmighttakeplacelandwardofthat.Theotheraspectoftheprojecthastodowiththesafetyofthewharfstructureanditspublicsafetyissueassociatedwithahighoccupancyrateatdifferenttimes.Sofromanengineeringcriteriapointofviewitisimportantthatthepublicsafetyissuewithrespecttothewharf,thesealevelriseissue,andotherengineeringcriteriabeaddressed.
ConstructionoftheDSMwillneedtoprovideasmuchlateralresistanceaspossible.IamnotsurewhatotherinputyouwouldwantfromtheBoardwithrespecttotheconstructionoftheDSM.IamcuriousastohowtheDSMwillrespondwithrespecttothesurroundingsoilandifthereisanyhistoricalevidenceoranymeasurementsthathavebeenmadeinthepastwithrespecttohowaDSMresponds.
IraisethatquestionthinkingintermsofthesoftsoilsinJapanandtheartificialfillsandthequaywallsthatwereinstalledtoretaintheliquefiablesoils.ItturnedoutthataftertheKobeearthquaketheporepressuresdidreallybuildupprettyhighbehindthequaywallsresultinginsomefailures.IamwonderingwhetherthatsamekindofthingmighthappeninsomeinstanceswithrespecttotheDSM.Idon'tknow,thatisjustaquestion.
Mr.Espinosaexplained:MostofwhatwearetryingtoretainistheyoungBaymudfailuresordeepfailures,softsoilfailuresduetothelateralpressuresfromtheearthquake.WedonotexpectporepressurebuildupontheyoungBaymuds,whichismostoftheDSM.Thereisgoingtobesomepressurebuilduponsomeofthefillthatmightbepotentiallyliquefiable.ButinthoseareasweareclosingthecellsoftheDSM,whichhasshowninthesameearthquake,intheKobeearthquake,wherebuildingsthatwerefoundedonconnectedcellsofDSM,liquefactionwaspreventedunderneaththosebuildings,whererightinfrontofthatbuildingeverythingliquefiedandwentoffshore.Sothatisourschemeforthisshorelineprotection.
BoardMemberGilpinasked:Couldyoutalkabouttheliquefactionpotentialfortherockdike?Howdidyousetupthecharacteristicsforunderstandingit?
22
ECRBMINUTESMay24,2017
Mr.Bradfordanswered:Thematerialidentifiedwithintherockdikewaseitherthepreviouslymentioned15poundmaxsizecobblesintermixedwithdredgematerialandyoungBaymud.Sotherewasnotanythingthatweidentifiedasbeingpotentiallyliquefiablewithintherockbankitself.
BoardMemberGilpininquiredfurther:Sothereisnopossibilityofsandorconcentrationsofthegranularmaterial?
Mr.Bradfordreplied:Theonlythingthatweidentifiedinanyoftheexplorationsalongthiscross-sectionwasthesortofteal-coloredclayeysand;anditwasonlyidentifiedinthefarthest-mostboringthatwasdoneactuallyoutatthetipofthewharf.Sowedonothavedatapastthewharfsoweconservativelyinterpolatedthatasbeingplainer.
BoardMemberGilpincommented:ButifyouaresamplingagravellylayeritisreallyhardtofindthesandlayerbecauseyouarepushinggravelinfrontofitorCPTs,whatever.
Mr.Bradfordreplied:Wedidgrabsampleswithintherockdike,wedidnotjustsimplycorethroughitandthat'showwewereabletoidentifysortofamatrixwithinthat.
BoardMemberGilpinasked:Itisapileofgarbage,right,basically?
Mr.Bradfordresponded:Sure.ButitwasdevelopedwiththedredgematerialthatwaspulledoutoftheincisionlayerwithintheyoungBaymud.
BoardChairBorcherdtcontinued:IwouldliketoaskBoardMembersiftheyhaveanyadditionalcommentsbutfirst,Brad,youraisedapointearlierandsoIwaswonderingwhatyouwouldrecommendintermsofwhatyouwouldliketoseecommentedonfurther.
Mr.McCreaexplained:Thequestionsthatareoutlinedinthestaffreportyouhaveinfrontofyou,onpage8,areagreatstart.
BoardMemberHolmesinquired:Whatdoyouknowaboutthepilesunderthelandsidewarehouse?
Mr.Yaoreplied:Thosearetimberpilesthatwereinstalledlaterbecausethestructures,thosetwowarehousesonthelandsidewerenotconstructedin1919butinthe1930sand1940s.
BoardMemberHolmesasked:Oneoftheretrofitschemesyouwouldhavetoinvestigateisthosepiles,right,becauseyouaregoingtotietothem?
Mr.Yaoreplied:That'sright,weneedtoinvestigate.Butthoseareburiedintheground.Thisisoneoftwoschemes.Ifweeventuallyadoptourschemewedoneedtoinvestigate.
BoardMemberHolmesadded:TheothercommentIhaveisInoticedinthewrite-uphereyouareusingaknowledgefactorof1onthepiles.
Mr.Yao:Ontheconcretepilesitis1.Onthetimberpilesitis0.7.
23
ECRBMINUTESMay24,2017
BoardMemberHolmescontinued:IthinkyouhavedoneasgoodaninvestigationasyoucandobutIamnotsureyouhavecompleteknowledgeof1,whichimplieslikeanewbuildingwhereeverythingisinspected.Youhavegotallthismajordamage,youdonotknowwhatthelevelofdeteriorationis,soIamnotsureyouhaveperfectknowledgeofthepiles.
Mr.Yaoexplained:Well,thereareguidelines.Wedidconcretecorings.Wedidpileratings.Itwasactuallyconservativebecauseweignoredtheshotcrete.Ithinkweknowenough.Wehavetheoriginaldesigndrawings.Wecansubstantiatewhywearesayingit.
BoardMemberHolmesclarified:Itisnotwhattherebarandconcreteis,itishowmuchdeteriorationisthere,ismyconcern.
Mr.Yaoexplained:Butthetruthisweignoredthe6inchshotcretesothatissignificant.Inmyviewitisconservativeinourassessmentofthepiles.Thatshotcrete,itdoescontributetothestrengthofthepile,especiallyinthosehingeareas.Mostofthosepilesdohave4to6inchshotcretearoundit.
BoardMemberHolmes:Ithinkthatadvantagemaybedifferentthanaknowledgefactor.
Mr.Yaostated:Wecouldgotheotherway,countingfortheshotcreteandreducetheknowledgefactor.
BoardMemberComeriocommented:Thisisaverythoroughpresentation.TheonethingthatisabsolutelymissinghereisaplanoftheareathatiswithintheBCDCjurisdiction,whichiswhywewereaskingallthosequestionsattheendaboutthoselastfewslides;graphicquestionscameupbecauseyouneedtoseewherethoseDSMsareplanned.Youneedtoseewheretheysitrelativetothoseexistingpilesorthatexistingbuildingwhichisbeingremoved.Wearenotseeingthoselayersandithasmadeithardertounderstandsomeofyourpresentation.
Itisreallyaminorpointbutitwouldreallyhavehelpedtohavehadthat.Itwouldhavehelpedtounderstandhowthepromenadeworksandconnectsattheend.LookingatthesedrawingsandIknowyouarenotveryfarwiththedesignyet,Iunderstandthat.Butjusthavingasenseofhowthatalllinkstothelandattheedgeofthepropertywouldbehelpful.Sojusthavingthat,aplanviewwithallofthoseelements,includingtheonesthataretoberemovedandtheonesthataregoingin,andseeingthoselayerswouldbeveryhelpful.
Mr.Livingstonstated:Wewillbringsomethinglikethatbacktoyounexttimeweseeyou.
Mr.Montesadded:PartofitwasmymistakebecauseoriginallytheyweregoingtopresentalotofthelandscapingandthenIthoughtthatbecausetheECRBwantedtozeroinontheseismicandfloodingthattheywouldconcentratemoreonthatportion.
BoardMemberComerioexplainedfurther:Thatplanhelpsusunderstandtherelationships.
24
ECRBMINUTESMay24,2017
Mr.Affaskedforclarification:Justtoclarify,youarenotaskingforthelandscapeplan,youareaskingfortheplanviewshowingwheretheDSMbuttressis,wherearethepiers,wherethepilesare,wherearethenewproposedpilesgoingtobe,wherethefourcriticalrowsofpilesare,allthosethings.
BoardMemberComerioadded:Wherethingsaregoingtoberemoved.Obviously,asyougoforwardwiththedesignyouwouldhavethelandscapedesignontopofthat.Inordertounderstandsomeoftheseismiccriteria,understandingthefullbaselayerandplanaswellasin-sectionisveryhelpfulbecauseyoucannotalwaysseehowallthepiecesrelatetoeachother.
BoardMemberDornhelmcommented:Idothinkithasbeenverythoroughanditwouldbewonderfulwhentheoldwarehousefacilityfinallygiveswaytoadelightful,urbanwaterfrontasyouareproposing.ButmyonlyreservationhastodowiththeearlyassumptionoftheLevel2criteria.Thatyouarecomfortablethatwhenyousay"nocollapse"doesthatmeaninsuchaneventthestructureisalossandthendoesthatmeanthedevelopmentwilltakeontheresponsibilityofcleaningthesite?Itisallpublicusesthatarebeingriskedinthiscaseandwewanttoknowifsomethingwillcomebackafterthesiteiscleaned.OrcanyourepairthewharfifithasgonetoaLevel2?
Mr.Yaoreplied:Everymajorstructureisfacingthatquestionrightafteramajorearthquake.Obviouslythedevelopmentisgoingtohireaqualifiedengineertogobackandinspectthemandseehowmuchitisgoingtocosttoretrofit/restorethestructure'sintegrity.Howmuchtojusttearthemdownandrebuildanewone.Iwanttosaythatthemajorityofthewharvesandpiersweexperiencetheformer,goingbackandretrofittingthemandrestoringthemifyouhaveanearthquakesimilartotheLomaPrietaEarthquake.
BoardMemberDornhelmstated:Thatisyourdesignearthquake.ItismuchhigherthanLomaPrieta.Soyouaredesigningitfornocollapse.
Mr.Yaoexplained:Thedesignofthepilesisveryclosetothemoderndesign.SoIthinkthehingedoesperformduringamajorearthquakeandprovidealotofductilitytothestructure.Ofcourse,ifweadoptoneoftheretrofitoptionsIthinkitcansustainamuchhigherearthquakeandstillbecomerepairableinthefuture.Butitisreallyoutofourscopetoreallyassessreparabilityofthewharf.Iappreciatethecomment;asoneofthepublicIwanttoknow.Butatthisstagewearelookingatjustonepoint.Abigearthquakelineisonepointandwedesignforitandmakesurethepublicissafe.
BoardMemberHolmesasked:Theelevationhereofthebeamsundertheplatform.Idonotseeanypositivereinforcingcontinuous.Areyouassumingthetopfixityofthepilesoristhatapininyourmodel?"
Mr.Yaoexplained:Thebeamisextendingtypically18inches.
BoardMemberHolmescontinued:Ijustdonotseeanybottomreinforcing.Itisbentuptobecomenegativereinforcing,atleastinthis.Itisasmalldiagram.Butistherebottomsteelgoingrightthroughtheconnect?
25
ECRBMINUTESMay24,2017
Mr.Yaoreplied:Therearesome.Thereareabandofrebarstherebuttherearesomecontinuousspotsalso.
BoardMemberHolmesinquired:Andareyouconsideringthediagonalsections?
Mr.Yaoreplied:No.Thecoverorthetransferisignoredfornowinouranalysis.
BoardMemberHolmesopined:Thatcouldbeamistake.
Mr.Yaoanswered:Butitisconservative.
BoardMemberHolmesdisagreed:Idonotthinkthatisconservativeatall.Caltransfoundouttheyhadsomedecorativechamfersonthecolumns.Theythoughttheywouldfalloffinanearthquakeanditturnsouttheyformedahingerightatthebottomwheretheydidnotexpectit.Rightbelowthechamfer.SoIwouldtakealookatthat.
Mr.Yaoreplied:Iwilltakealookatthat,okay.Iwillletyouknownexttime.
BoardMemberComeriocommented:Asthedesignisdevelopeditisgoingtobeimportanttoustounderstand.Thecriterionislifesafetybutwhatistheegress?Aretheregapsbetween?Dowehaveanygapsopeningupinthewharf?Dowehaveanygapsopeningupbetweenthewharfandthesoil?Howdopeoplegetoffthewharfintheimmediateaftermathofanearthquake?Whatdoyouanticipatethestructuralmovementsothatwecanbeassuredthatthereissafeegress?
Mr.Yaoreplied:Ithinkwearepreparedforthat.BecausethelasttimeyoumadethesamecommenttoourcompanyregardingtheAlamedaLandingProject.
ButthisprojectisdifferentfromAlamedaLandingbecauseItalkabout4inchdisplacement,literally4inchdisplacement.Themaximumgapyoucaneverfindis4inchessopeoplecanjuststepoverthis4inchgap;egressisnotanissue.AlamedaLandingisamuchlargerdisplacement,16inchesor20-someinches.Thatpotentiallyhasafallhazard.Butwearetalkingabout4incheshere.
BoardChairBorcherdtcontinued:IftherearenofurthercommentsIthinkwewouldliketothankyouforyourclearpresentationandyoureffortanddesiretocomebeforetheBoardandreceivecomments.Wehopeourcommentsarehelpfulandwelookforwardtoseeingasuccessfulproject.
Mr.Yaocommented:Ihaveaquickquestionhere,Chairman.WethinkthatwegavetheBoardanintroductionfromanengineeringperspectivesopossiblythenextpresentationwillbeshorter.Doyouwantustogothroughthesamepresentationordowejustmakeitmoreconciseinresponsetoyourcomments?
BoardChairBorcherdtresponded:TheBoardactuallyprovidesadvicetoBCDC.Weareaskedtofocusontheengineeringcriteriathatwillbeusedfortheproject,withaparticulareyetowardtheBCDCjurisdictionzone,safetyoffills,andvariousBCDCpolicies.
26
ECRBMINUTESMay24,2017
Inthatregard,asImentionedearlier,itseemstomethatthecriticalaspectsofthisprojecthadtodowiththesafetyofthewharf,especiallyfromthepointofviewofpublicsafety,theimpactofsealevelrisewithrespecttothedesigncriteriabeingapplied,andthenalsotheresponseortheusefulnessoftheDSMtotheassignedpurpose,whichistorestrainpotentialfailuresalongtheboundaryofthedevelopmentzone.
SoifyouweretocomebacktotheBoardthenitwouldseemtomethatthiswoulddependonBCDCwithrespecttowhatyouwantustoprovideadditionalcommentsonthecriteria.Butitdoesseemtomethattherearestillanumberofissueswithrespecttothesafetyofthewharfthatarestillinthedesignstage.Usuallywhenweseeaprojectat35percentweusuallyseeitlater.Butthisprojectisalittlebitdifferentfromthatpointofviewandsoitisreally,Ithink,dependsonwhatBCDCwantsfromtheECRB.
Mr.Montesstated:MyviewoftheassessmentthatyouprovidedtodayisyouprovidedsomegoodinputregardingMary'scommentsontheoverlaysofdifferentlandscapeversusseismiclayoutaspects.Billraisedthequestionsaboutthechamferzonewherethehingeonthepilescandevelop.Sothosearequestionsthatcanbeansweredatthenextmeeting.
Alsokeepinmindthatthegeotechswerenotheretodaysoitwillbegoodtohavethemgivetheirinputonthefullgeotechnicalreview.
Regardingthesealevelrise,IthinkthatBobBattalioandRichardDornhelmraisedsomeverygoodpointsabouttheelevationofthewharf,whethertheBayTrailwillbecomealeveeinthefuture.
BoardMemberBattaliocommented:Ifeltthatalongertimehorizonandagreateramountofsealevelrisewouldbemoretypical.Somethingontheorderof3feetwouldbegoodtoaddresswhetherornotthereisafreeboardincluded.IpersonallylikefreeboardsbutIamsureyouhaveotherconsiderations.
Theadaptationstrategyshouldhavealittlemoredescriptionsothatwewouldunderstandwhattheimplicationsaretothepublicaccessareaaswellastheefficacyofprotectingthedevelopment.
Mr.Montesadded:Onemorenote,Bob.TheStateisabouttopublishthenewguidanceonsealevelriseandperhapsyouaremorefamiliarthananyoneelseaboutthat.
BoardMemberBattalioreplied:Iknowsomethingaboutit.Iamnotinvolvedinthedecisionprocess.IdonotbelievethatisgoingtocomeonuntilJanuaryof2018.IwilljustsaywhatIhaveheardisthattheprojectionsaresimilartoormaybeslightlylowerthantheexistingguidanceforthemediumandhighcurve,thelowcurvepeoplearenotreallypayingattentionto.Butrelativetotheguidancecitedinyourapplication,thenewguidancemightbealittlebitlowerbutthenthereisthisveryhighpotentialthatismuchhigher.
Mr.Montesremarked:After2050.
27
ECRBMINUTESMay24,2017
BoardMemberBattaliocontinued:Soitissomewhatconfusing,Ithink,soitisgoingtobeinterestingtoseewhatcomesoutoftheactualpolicy.Iwouldsaythatthe3feetissomethingthatIamstickingtowhatwehavebeensaying.Ithinkthe3feetisareasonablecriterionfordesignandthenanadaptiveplanforsomethingontheorderof5to6feetwouldbereasonable.Idonotknowthatthe9to10feetthatpeoplearetalkingaboutissomethingthatwearereadytorecommendpeoplehavingtodesignforatthispoint.
BoardChairBorcherdtadded:Comingbacktoyouroriginalquestionwhichwastalkingaboutwhetheryouneededtogothroughthefullpresentationagain.IwouldthinkthatfromthepointofviewofefficiencyofbothyourtimeandourtimeIthinkthebasicswillbesufficient,sinceyouhavealreadypresentedtheoverallpictureataprecedingmeetingIwouldthinkyournextpresentationcouldbemuchbrieferandaddressedtoonlythosespecificissuesthatareofrealsignificancehere.Ithinktheissueswithrespecttothisparticularprojectareprettyclear.
Ms.Michaelscommented:IwanttoasktheBoardsomething.Ican'trememberifwehavebeenbringingriskassessmentstotheBoardforsealevelriseforyoutoseeandconsider.Thiswillbethesubjectofamajorpermitapplicationandforallmajorpermitapplicationstheprojectproponentshavetoprepareaformalriskassessmenttoaddresssealevelriseandfloodingfortheprojectsite.AndIjustcannotrememberatthispointifwehavebeenbringingthoseformallytotheBoard.
Mr.Montesstated:Wehavebroughtitonceortwice;onceforTesoro.
Ms.Michaelscontinued:Wewillgobackandfigureoutwhetherornotwehavebeenbringingthemtoyou;andifwedothatwouldmaybebeapartofthenextpresentationifoneispreparedbythattime.
BoardChairBorcherdtasked:Fromapermitpointofviewdoyouseeanyoftheengineeringcriteriathatneedanyadditionalcomment?
Ms.Michaelsreplied:Intermsofwhatmightbeintheriskassessment?
BoardChairBorcherdtanswered:Yes.
Ms.Michaelsexplained:Well,becausesealevelriseisanissueatthesiteandtheprojectwillinvolvesomefillintheBaytheywillhavetoprepareone.
AtaminimumwehavetoreceivethatandconsideritandIjustcannotremembernowifwehavebeenbringingittoyou.
BoardMemberBattaliostated:Iwouldliketoseeit;Ihavenotseenit.Ithinktotheextentthatweareadvisingonsealevelrisecriteriaitwouldbehelpful.
Ms.Michaelsreplied:Ithasnotbeenpreparedyetbutwewillbeworkingwiththeprojectproponentstodothat.
28
ECRBMINUTESMay24,2017
Mr.Livingstoncommented:WoulditbepossibletogetthetwoBoardMemberswhoarenotpresentandhavethegeotechnicalexpertise,toprovideuswithsomewrittencommentsorinputsonthevariousreportsandotherdocumentationthatwehavesubmitted?AndthereasonIammakingthatrequestisitwouldbeveryhelpfultousifweknewwhattheconcernsoftheBoardwereaswemoveintothisnextstageofdesigningourmitigationsolutionstotheproblemsthathavebeenidentified.Justtomakesurethatwearenotmissinganythingfromtheirperspective.
Mr.Montesresponded:Iunderstandyourconcerns,butunfortunatelyweareboundbythelawsthatprecludeindividualsorafewmembersoftheECRBfromgivinginputunlesstheyhappentobealltogetherinapublicforum.
Mr.Espinosaasked:Weretheyabletoreviewthematerialssincethematerialwasgiventothem?
Mr.Montesexplained:No,sincetheywerenotgoingtoparticipateinthemeeting.Thereforetheywerenotabletoviewthematerialunlesstheycommittedtobeinthemeeting.
BoardChairBorcherdtadded:WehavetomeettheOpenMeetingActrequirements.ThisisapublicmeetingsobasicallyanyinteractionwiththeBoardMembershastotakeplaceinapublicforum.
Mr.Montescontinued:Wehavetohaveanotherpublicmeetingwheretherewillbethegeotechsinvolvementandthentheinformationwillbedistributedtoallofthemforanotherpublicmeeting.IbelievethenextpublicmeetingwillbeinAugustbutIwillhavetodouble-checkonthat.
BoardMemberGilpinasked:Coulditaddressjustthegeotechaspectsoftheproject?
Mr.Montesreplied:Forthenextmeeting?
BoardMemberGilpinanswered:Iftheywantedtobringjustthegeotechpartsofwhatwelookedattodayordoesithavetoopenupthewholeproject?
Mr.Montesresponded:No.Wehavetogatherupthewholeteam.
BoardMemberGilpinexplained:Iunderstandthat.Butitcouldbeanagendaitematthenextmeetingthatisjustfocusedongeotechissuesforthisoneproject,inadditiontotheotherprojectthatwearegoingtolookat.
Mr.Montesagreed:Sure,yes,wecanhavethegeotechaspectbutyouallhavetobehere.
Mr.Fippincommented:Ithinkthattheprimaryconcernisthatiftherearesignificantcommentsthatrequireathirdvisit.IbelievetheApplicantwouldliketoshortenthetimeperiodofreview.
Mr.Livingstonstated:RightnowBCDCisbasicallyourcriticalpathsoweareveryfocusedondoingtheanalysisthatECRBbelievesisimportanttosupporttheproposalthatwearegoingtobemakingfromaplanningandsafetyperspective.
29
ECRBMINUTESMay24,2017
WearealsoveryinterestedingettingtheinputfromtheBoardsothatwecanprepareourformalapplicationandgetthatsubmittedandgettheprocessgoingfortheformalconsiderationofthatapplication.
WewerehopingtobeabletogetinfrontoftheECRBatthismeetingandgetyourfullinputsothatwecangobackandsubmitourformalapplicationbasedonthatinputwiththeadditionalworkthatwearegoingtobedoingasdescribedbySamandJeff.ButIdon'twanttowaituntilaftertheAugustmeetingtoputthatformalapplicationtogetherandgetitsubmitted.
Mr.Monteshadasuggestion:Ihaveanidea.TheAlamedaLandingthatcametotheBoardinMarch,youcanlookattheminutes.YoucanlookatJimFrench'scommentsregardingtheDSMandgeotechnicalaspectofit,sothatcouldgiveyouanidea.
Mr.Livingstonagreed:Rafael,Ithinkthatisagreatidea.BecauseatyourrecommendationIdidsitinonthatmeetingandIknowthatthereweresomecommentsmadeontheDSMthatIthinkwouldberelativelyapplicablehere.Sothatwillgiveussomethingtogowith.
Mr.Montesadded:Icanalsoprovideyouwithsimilarprojectsthathadthetwogeotechsinvolved,TreasureIslandandsomeotherones.
Ms.Michaelsstated:AlsoIwanttoaddthatyoudonotneedtowaituntiltheBoardseesthisprojectfurtherforyoutosubmityourpermitapplication.Wewillacceptitatanytimeandthiscangoonparallelalongwiththatprocess.
Mr.Livingstoncontinued:HopefullywewillbereadytocomebacktotheBoardforasecondreadingwithourwholeprograminplaceandresponsestotheconsiderationsandconcernsthathavebeenraisedtodaybythatAugustmeeting,soperhapswecangetonthatagendatofollowuponthismeeting.
Weverymuchappreciatetheinputandtheopportunitytopresenttheproject.Weareprettyexcitedaboutmovingthisprojectforward.WehavegottenmostoftheapprovalsthatweneedandBCDCisthelastthresholdweneedtogetacrosssoweareveryanxioustoworkwithyouonthat.
BoardChairBorcherdtadded:Itlookslikeaniceproject,thankyouforcomingin.
5. Adjournment.Therebeingnofurtheroldornewbusiness,themeetingwasadjournedat3:56p.m.
Respectfullysubmitted,
RAFAELMONTES,P.E.BoardSecretary
Approved,withnocorrections,attheEngineeringCriteriaReviewBoardMeetingAugust8,2017.