6
16 th International Conference on Electrical Engineering, July 11-14, 2010 Busan Korea 1 Application of Phasor Measurement Unit (PMU) Data for Out-of-Step Detection Dikpride Despa *,** , Yasunori Mitani *, Masayuki Watanabe* , Changson Li,* Bessie Monchusi* Abstract The algorithm based on equal area criterion is developed and the stability of generators after a fault is assessed. The power swing equation is integrated to calculate the accelerating and decelerating area under the power delta curve. Phasor Measurement Unit (PMU) data from a four generators power system is utilized in detecting out-of-step condition. A three phase to ground fault on the power system is simulated by MATLAB and Dymola with ObjectStab. The algorithm developed is tested by simulations on the four generator power system. Keywords: Phasor Measurement Unit (PMU), Out of Step Detection, Equal Area Criterion, Transient Stability. 1. Introduction The stability of an interconnected power system is its ability to return to normal or stable operation after having been subjected to some form of disturbance [1]. Certain disturbances may cause the interconnected power systems to lose synchronism, which may lead to cascading blackouts and equipment damage. In order to avoid these severe results, controlled separation of the system using out-of-step protection is an effective way to preserve stability in several smaller islands. Traditional out-of-step protection uses distance relays and timers to detect the out- of-step condition by assessing that the voltage and current during a power swing is gradual instead of a step change. Faults and out-of-step condition lead to a change of measured apparent impedance, but the change is much slower during out-of-step conditions. After the out-of-step condition is detected, out-of-step protection must block other fault relays prone to malfunction during out of-step conditions. Meanwhile, the controlled separation at the pre- selected points provides load-generation balance in each separated area with the help of a load-shedding program. However, the disadvantage of the traditional out of step protection scheme is that it only uses local measurements to estimate the condition of the entire power system network, which inevitably affects its ability to detect the out-of-step conditions in certain circumstances. Phasor Measurement Unit (PMU) is widely applied for detecting out of step condition. A PMU is a device that can measure voltage and current phasors, i.e. as complex quantities, with a common time reference for all the PMUs in the system. Line parameters such as; resistance, inductance and capacitance can be calculated, even corona and zero sequence parameters can be determined with the PMU. PMU provides more precise data at a much faster rate. It is possible to receive accuracy of synchronization of 1 microsecond or 0.021 for 60 Hz signal [2]. This offers new opportunities in power system control. The research focused on a method to detect out of step condition using phasor measurement, voltage phase angle difference between different buses and simulate the out of step scenarios on a four generators power system. The rest of the paper discusses; 2. Equal Area Criterion, 3. Phasor Measurements Units, 4. Out-of-step algorithm, 5. Simulations and 6. Conclusion. 2. Equal Area Criterion The power-angle relationship and the swing equation are essential in understanding transient stability and can be * Dept. of Electrical and Electronic Engineering, Kyushu Institute of Technology, Japan ([email protected] ) ** Dept. of Electrical Engineering, Lampung University, Indonesia

Application of.....(ICEE2010).pdf

Embed Size (px)

Citation preview

  • 16th International Conference on Electrical Engineering, July 11-14, 2010 Busan Korea

    1

    Application of Phasor Measurement Unit (PMU)

    Data for Out-of-Step Detection

    Dikpride Despa*,**

    , Yasunori Mitani *, Masayuki Watanabe* ,

    Changson Li,* Bessie Monchusi*

    Abstract The algorithm based on equal area criterion is developed and the stability of generators after a fault is assessed. The power swing equation is integrated to calculate the accelerating and decelerating area under the power

    delta curve. Phasor Measurement Unit (PMU) data from a four generators power system is utilized in detecting

    out-of-step condition. A three phase to ground fault on the power system is simulated by MATLAB and Dymola with

    ObjectStab. The algorithm developed is tested by simulations on the four generator power system.

    Keywords: Phasor Measurement Unit (PMU), Out of Step Detection, Equal Area Criterion, Transient Stability.

    1. Introduction

    The stability of an interconnected power system is its

    ability to return to normal or stable operation after having

    been subjected to some form of disturbance [1]. Certain

    disturbances may cause the interconnected power systems

    to lose synchronism, which may lead to cascading

    blackouts and equipment damage. In order to avoid these

    severe results, controlled separation of the system using out-of-step protection is an effective way to preserve stability in several smaller islands. Traditional out-of-step

    protection uses distance relays and timers to detect the out-

    of-step condition by assessing that the voltage and current

    during a power swing is gradual instead of a step change.

    Faults and out-of-step condition lead to a change of measured apparent impedance, but the change is much

    slower during out-of-step conditions. After the out-of-step

    condition is detected, out-of-step protection must block

    other fault relays prone to malfunction during out of-step

    conditions. Meanwhile, the controlled separation at the pre-

    selected points provides load-generation balance in each

    separated area with the help of a load-shedding program.

    However, the disadvantage of the traditional out of step

    protection scheme is that it only uses local measurements to

    estimate the condition of the entire power system network,

    which inevitably affects its ability to detect the out-of-step

    conditions in certain circumstances. Phasor Measurement

    Unit (PMU) is widely applied for detecting out of step

    condition. A PMU is a device that can measure voltage and

    current phasors, i.e. as complex quantities, with a common time reference for all the PMUs in the system. Line parameters such as; resistance, inductance and

    capacitance can be calculated, even corona and zero sequence parameters can be determined with the PMU.

    PMU provides more precise data at a much faster rate. It is

    possible to receive accuracy of synchronization of 1

    microsecond or 0.021 for 60 Hz signal [2]. This offers new

    opportunities in power system control. The research

    focused on a method to detect out of step condition using

    phasor measurement, voltage phase angle difference

    between different buses and simulate the out of step

    scenarios on a four generators power system.

    The rest of the paper discusses; 2. Equal Area Criterion, 3.

    Phasor Measurements Units, 4. Out-of-step algorithm, 5.

    Simulations and 6. Conclusion.

    2. Equal Area Criterion

    The power-angle relationship and the swing equation are

    essential in understanding transient stability and can be

    * Dept. of Electrical and Electronic Engineering, Kyushu Institute of

    Technology, Japan ([email protected])

    ** Dept. of Electrical Engineering, Lampung University, Indonesia

  • 2

    utilized to describe the Equal-Area Criterion (EAC).The

    swing equation describes the swings of the rotor angle () during a disturbance. EAC on the other hand, describes the

    movement of the rotor angle using three graphs

    representing the pre-fault, fault and post-fault conditions.

    Based on the accelerating and decelerating areas of the

    rotor angle, under these graphs, EAC assesses transient

    stability. The swing equation is given by [3]:

    aei PPPdt

    dM ==

    2

    2 (1)

    dt

    d = (2)

    where M = the inertia constant, = the rotor angle of the synchronous machine, Pm = mechanical power, Pe =

    electrical power and = rotor speed. The inter-area oscillation component in the voltage variables resulting

    from disturbances is utilized for extrapolating system

    impedances beyond the measured buses by:

    ( )P

    SinVVxT

    21= (3)

    where |V1|, |V2|are phasor voltages, is the phase rotor angle and P is the output power. The maximum power transferred between the generators and the mechanical power are estimated using these formulas:

    TX

    VVP

    21

    max = (4)

    )( 0max SinPPm = (5)

    where XT= the total impedance, |V1|and |V2|= the synchronized phasor voltages, maxP = the maximum power,

    mP = the mechanical power and 0 = the initial power

    angle.

    Fig. 1 P- Curve

    The EAC integrates the energy gained when the turbine-generator is accelerating, during the fault (area A, in Fig. 1 )

    and compares that area with the decelerating area, (area B, in Fig. 1). When the generator exports the energy stored

    during the fault. The accelerating and decelerating area at

    the different generator conditions are calculated by integration of the power swing equation between the

    boundary angles. In Fig. 1 the simplest condition is shown,

    i.e. immediately at the occurrence of a fault, the electric

    power output drops to zero and as soon as the fault is

    cleared the electric power output returns to its initial curve.

    Equation (6) and (7) describes area A and area B. Transient stability assessment can be explained using Equal-Area

    Criterion by Fig. 1. Area A is the accelerating or positive

    area and B is the decelerating or negative area

    dPPAcl

    faultem )sin(0 , =

    (6)

    =f

    cldPPB m

    )sinmax (7)

    Where cl stands for clearing time, f is the fault time.

    Transient stability of the system is guaranteed if A

  • 16th International Conference on Electrical Engineering, July 11-14, 2010 Busan Korea

    3

    When A and B are equal, the stability limit of the system is

    reached and the accelerating power (Pa) is equal to zero.

    The unstable case is reached when A>B, the angle keeps

    increasing and goes out-of-step, or becomes unstable.

    3. Phasor Measurement Units

    PMUs are also known as synchronized phasor units for they

    allow more finely calibrated observation power flows on

    the power system. PMU data from different utilities is time-

    synchronized and combined to create a detailed and

    comprehensive view of the broader system. Conventional

    methods measure voltage, current, real and reactive power

    for determining the operating condition of the electric

    network. These technologies cannot measure voltage phase

    angles while PMU provide the phasors of voltage and

    currents measured at a given substation. PMU is able to

    measure phase difference at different locations. Instead of

    the indirect measurements or estimation used in traditional

    out-of-step protection, the voltage frequency and angle

    measurement from different buses can provide the ability to

    directly monitor system transient stability conditions.

    4. Out-of-Step Algorithm

    An out-of-step condition in a network occurs when a

    generator or a group of generators lose synchronism with

    the rest of the network. The event forces generators to

    shutdown and sometimes large parts of the network are

    forced out of service. Before losing synchronism the

    network normally experiences power oscillations between

    neighboring generator groups. The oscillations cause

    voltage and current variations throughout the power system

    and there will be a variation in power flow between two

    areas, this phenomenon is called a power swing. The out-

    of-step algorithm creates vectors of complex current,

    voltage and impedance from phasor measurements. For the

    construction the P- curve, the equivalent phase angle for

    the system is calculated using the COA algorithm [4].

    =

    ==

    N

    ii

    i

    N

    ii

    COA

    1

    1

    (8)

    The total Impedance of the power system is calculated

    using the equivalent phase angle.

    I

    VeVX

    i

    ref

    T

    = (9)

    And applied to determine the equivalent rotor angle is

    calculated by :

    =

    T

    T

    jX

    X1tan (10)

    The total power of the system is calculated by :

    ( ) ( ) += sinsin2

    T

    xref

    T X

    VV

    X

    VP (11)

    Utilizing (11) the total mechanical power can be calculated

    using the initial values of voltage, impedance, and delta. The phase angle and power value of generator 3 the steady

    state condition are used as a reference and compared to the

    phase angle and power of the other generator at different

    time step. Using time phase angle and power vector at each

    time step the P- curve is constructed. The area under the

    curves is calculated using the Riemann Integration. To

    estimate the power output for the fault and post fault at

    different time steps, a constant is calculated by:

    SinP

    tCons =tan (12)

    The new value of outP for fault and post fault at

    different steps are given by:

    2sintancos

    XtP new = (13)

  • 4

    0 20 40 60 80 100 120 140 160 1800

    0.5

    1

    1.5

    2

    2.5

    Angle [degrees]

    Power [p.u.]

    Fig. 2 Shows the power-output and the mechanical

    power for the power system in steady state

    operation.

    0 20 40 60 80 100 120 140 160 1800

    0.5

    1

    1.5

    2

    2.5

    Angle [degrees]

    Power [p.u.]

    Fig. 3 Shows the power output and mechanical

    power under fault and post fault conditions

    Its applied in calculating the output power and mechanical

    power. The new vectors of phase angle and power for all

    time steps are calculated from the above complex values.

    To detect angle change the difference between the reference

    value and a value at a specific time-step is calculated. If the

    difference is too much, the algorithm to detect the power

    swing will start. The reference value is taken from studying

    the graphs of the change of phase angle. If the phase angle

    has changed too much and the electric power output has

    decreased to a level below the mechanical power input, it is

    for sure that the system will experience a power swing. If

    the accelerating area is greater than decelerating area, the

    system will go out of step.

    5. Simulation

    The Algorithm developed is tested on the four generators,

    two areas power system (shown in Fig. 4) on MATLAB.

    The system is designed by Dymola with ObjectStab. The

    generators have an exciter and a turbine governor.

    Simulations are performed with a three phase to ground

    fault on the transmission line as shown in Fig. 4 PMUs are

    placed on the generators bus bars (1, 2, 11 and 12)

    Fig. 4 Four Generators Two Areas Power System

    Fig. 5 P- Curve for Generator 1

    In Fig. 5 the power at the state and change of power around

    the time of the instant fault are shown for Generator 1 by

    the solid graph. Generator 3 is chosen as a reference

    generator. The impedance of the equivalent power system is

    utilized in the calculation of the maximum power and

    mechanical power. The output power for the fault and after

    fault condition is shown by graphs with dashes. The

    generator is not out of step with the other generators in the

    power system.

  • 16th International Conference on Electrical Engineering, July 11-14, 2010 Busan Korea

    5

    Fig. 6 P-Curve for Generator 2

    In Fig. 6 the solid curve shows the stable electric power

    output before the fault. The dashed curves represent the

    electric power output during and after the fault. The

    mechanical power input is represented by the dotted line. In

    this case, the generator is far from losing synchronism. The

    power will oscillate back to its stable equilibrium point.

    A fault has occurred but the system remains stable.

    Fig. 7 P- Curve for Generator 4 Generator 4 does not loose synchronism even if there is a

    fault in the power system. The power at the stable point and

    the change of power around the time of the instant fault for

    generator 4 are shown in Fig. 7. From the results of the

    simulations, it can be concluded that the fault in the system

    is not severe enough to cause all the generators to loose

    synchronism.

    Fig. 8 P-Curve for Generator 1 out-of-step

    Fig. 9 P-Curve for Generator 2 out-of-step

  • 6

    Fig 10. P-Curve for Generator 4 out-of-step Figures 8-10 show the P-curves for out-of-step condition, for generators 2, 3 and 4. The out-of-step message is issued

    to warn that the generators 1 and 2 are out- of- step while

    generator 3 remains in synchronism with generator 4.

    5. Conclusion

    Phasor measurements are utilized to calculate the vectors of

    complex current, voltage and impedance which are applied

    to determine the new vectors with phase angle and power

    for all time steps. The angle change is determined by the

    difference between the reverence value and a value at a

    specific time-step is calculated. The Equal Area Criterion is

    utilized to detect if the generators are going out of step or

    not. A three phase to ground fault is simulated on the four

    generators power system.

    Acknowledgements

    This work was supported by in part by Grant-in-Aid for

    Science Research (A) 18206028 of JSPS.

    References [1] I J Nagrath, DP Kothari, Modern Power System

    Analisys, McGraw Hill, 1980.

    [2] Mark R Gerald T.H. Phasor Measurement Unit

    Data in Power System State EstimationJanuary

    2005.

    [3] Prabha Kundur Power System Stability and

    Control,McGraw Hill, 1993.

    [4] B. B. Monchusi Optimal Approach Towards Using

    Phasor Measurement (PMU) Data in Equal-Area

    Criterion Based Systems for Power System Transient

    Stability Assessment, PhD Thesis, Graduate School

    of Engineering, Kyushu Institute of Technology,

    Japan, February 2010.