Upload
dinhtuong
View
214
Download
0
Embed Size (px)
Citation preview
Abstract—Cogeneration systems and equipment suitable for
residential and small-scale commercial applications like
hospital, hotel or institutional building are available, and new
systems have developed. These products are used or aimed for
meeting the electrical and thermal demands of a building for
space and domestic hot water heating. In last years
cogeneration has played a significant role in Turkish energy
strategy, with plans to satisfy the considerable portion of
Turkey’s requirements for electricity from cogeneration. The
main purpose of this work is to supply the demand for
electricity and heat for housing complex in Turkey.
In this study, it is showed that cogeneration systems in
housing complex are an extremely profitable investment for
country and consumers. Here application of cogeneration on
housing complex was made in Istanbul. It is stressed that this
technology should be applied as an energy method in old and
new housing complex.
The aim of this paper is to maintain a study by using real
consumptions of housing complex in Turkey. Electricity and
natural gas consumption quantities have been obtained from
housing complex. Finally as it is resulted from payback period
approach the system is paid off itself in 1.33 year,
approximately 16 months.
Index Terms—Cogeneration, energy efficiency, Turkey.
I. INTRODUCTION
Cogeneration also called combined heat and power (CHP)
is the simultaneous production of electrical or mechanical
energy (power) and useful thermal energy from a single
energy stream such as oil, coal, natural or liquefied gas,
biomass or solar [1]. The conventional sources of energy are
getting consumed at a very fast rate, which has focused
attention to the clean and renewable sources of energy [2].
Cogeneration is widely recognized worldwide as an attractive
alternative to the conventional power and heat generating
options due to its low capital investment, short gestation
period, reduced fuel consumption and associated
environmental pollution, and increased fuel diversity [3].
Cogeneration is not a new concept. Industrial plants led to the
concept of cogeneration back in the 1880s when steam was
the primary source of energy in industry, and electricity was
just surfacing as a product for both power and lighting [4].
The use of cogeneration became common practice as
engineers replaced steam driven belt and pulley mechanisms
with electric power and motors, moving from mechanical
powered systems to electrically powered systems. During the
early parts of the 20th century, most electricity generation
Manuscript received October 13, 2014; revised April 23, 2015. This work
was supported in part by the Republic of Turkey Marmara University
Scientific Research Commission in Istanbul FEN-A-120514-0156. The authors are with the Faculty of Technology, Department of
Mechanical Engineering, Marmara University, Kadikoy, Istanbul 34722
Turkey (e-mail: [email protected], [email protected], [email protected]).
was from coal fired boilers and steam turbine generators,
with the exhaust steam used for industrial heating
applications. In the early 1900s, as much as 58% of the total
power produced in the USA by on-site industrial power
plants was estimated to be cogenerated [5]. Because of
energy price increases and uncertainty of fuel supplies,
systems that are efficient and can utilize alternative fuels
started drawing attention. In addition, cogeneration gained
attention because of the lower fuel consumption and
emissions associated with the application of cogeneration [6].
Today, because of these reasons, various governments
especially in Europe, US, Canada and Japan are taking
leading roles in establishing and/or promoting the increased
use of cogeneration applications not only in the industrial
sector but also in other sectors including the residential sector
[5].
In the literature, many studies can be seen about
cogeneration systems. Allen and Kovacik [7] studied
advantages of cogeneration systems with a gas turbine and
heat recovery system that uses the exhaust of a gas turbine.
Sahin et al. [8] and Sahin and Kodal [9] performed
performance analyses of cogeneration foundations with
respect to maximum exergy criterion using finite time
thermodynamics. Yilmaz [10] has carried out a performance
analysis based on alternative performance criteria for a
reversible Carnot cycle, modified for cogeneration, with
external irreversibilities. Criterions used in examining
cogeneration systems have been evaluated by Feng et al. [11];
a new thermodynamic performance criterion named
cogeneration efficiency has been propounded. According to
new criterion, not only should the energy utilization factor be
considered but also the rate of cost of heat and electric should
be determined. Benelmir and Feidt [12] studied cogeneration
systems and strategies of energy management. They
compared conventional energy systems with cogeneration
systems in terms of cost of investment, economic advantage,
and time of repayment. Bilgen [13] performed exergetics and
thermoeconomic analyses for a cogeneration unit with a gas
turbine. He examined cogeneration systems with gas turbines
and combined cogeneration systems depending on the ratio
of heat/power and the determined time of repayment based on
efficiencies of the first and second law of thermodynamics
and costs. Khaliq and Kaushik [14] examined the second-law
approach for the thermodynamic analysis of the reheat
combined Brayton/Rankine power cycle. They found that the
exergy destruction in the combustion chamber represents
over 50% of the total exergy destruction in the overall cycle.
The combined cycle efficiency and its power output were
maximized at an intermediate pressure-ratio, and increased
sharply up to two reheat-stages and more slowly thereafter.
Marrero et al. [15] analyzed a combined triple (Brayton/
Rankine/ Rankine) (gas/ steam/ ammonia) power cycle. One
goal of their study was to find what configuration would
Application of Cogeneration on a Housing Complex
M. Atmaca, E. Yilmaz, and A. B. Kurtulus
Journal of Clean Energy Technologies, Vol. 4, No. 2, March 2016
129DOI: 10.7763/JOCET.2016.V4.266
achieve a thermal efficiency of 60% when reasonably
practical constraints for system parameters are used. Lund et
al. [16] and Lund and Andersen [17] studied implementation
strategy and optimization of cogeneration plants. Recently,
optimization studies on exergetic performance of gas turbine
based cogeneration systems can be seen in the references [18],
[19].
The aim of this paper is to maintain a study by using real
consumptions of housing complex in Turkey. A cogeneration
system is considered for the study. Electricity and natural gas
consumption quantities have been obtained from housing
complex for this study. Cost analysis study was conducted.
According to cost analysis study, it is found that cogeneration
system is economical and depreciation time is very quickly.
Finally as it is resulted from payback period approach the
system is paid off itself in 1.33 year, approximately 16
months.
II. DEVELOPMENT OF COGENERATION IN TURKEY
For the last years cogeneration has played a significant part
in the Turkish energy strategy, with plans to satisfy a
considerable portion of Turkey’s requirements for electricity
from cogeneration [20]. Turkey, with its young population
and growing energy demand per person, its fast growing
urbanization, and its economic development, has been one of
the fast growing power markets of the world for the last years.
It is expected that the demand for electric energy in Turkey
will be 556 billion kWh by the year 2020 [21].
In 1998, of Turkey’s final energy consumption 38% was
used by the industrial sector, followed by residential at 34%,
transportation at 19%, the agricultural sector at 5%, and the
nonenergy use at 3%. The share of the industrial sector in this
consumption is expected to continue to grow at
approximately 9% per year and to 59% in 2020. As Turkey’s
economy has expanded in recent years, the consumption of
oil has increased. This growth in consumption is expected to
continue up to the year 2020 at a rate of about 4.5% per year.
The proportion of oil is expected to decrease somewhat as
natural gas usage increases. In this regard, oil accounted for
46% of this consumption, with coal at 20% and natural gas at
8% in 1998. It is projected that these figures will be 29% for
oil, 35% for coal, and 11% for natural gas by 2020 [22], [23].
Notable efforts are assigned to ensure the use of domestic
resources insofar as is possible in order to meet the demand of
energy, but as is already known, the meeting of energy
demand of the country totally by local resources is out of
question [24]. Because of its limited energy resources,
Turkey is heavily dependent on imported oil and gas. There
are major oil and gas pipelines going through Turkey and
additional pipelines are being constructed or are being
planned. Turkey has approximately 8 billion tons of coal
reserves, of which a large portion is of low quality [20]. This
means that there is some production of lignite, which is used
as a fuel for thermal power plants, domestic consumers, and
industry. Turkey does not have satisfactory reserves of
natural gas. As of the end of 1998, the known total reserves
were 15.5 billion m3, of which 12.4 billion m
3 is recoverable.
The production of natural gas in Turkey began in 1976 and
was realized as 253 and 565 million m3 in 1997 and 1998,
respectively. However, this production is estimated to be 150
million m3 in 2010 and 121 million m
3 in 2020 [22]. Turkey’s
potential indigenous sources available for power generation
are comprised of 105 billion kWh lignite, 16 billion kWh
hard coal, and 125 billion kWh hydroelectric resources. The
total potential adds up to 246 billion kWh [24]. The Fig. 1
shows the installed cogeneration capacity development in
Turkey [21].
Fig. 1. Installed capacity of cogeneration in Turkey.
III. APPLICATION OF COGENERATION ON A HOUSING
COMPLEX
In this study application of cogeneration on housing
complex was made in Istanbul. It is shown in Fig. 2, a
housing complex in Istanbul.
Fig. 2. A housing complex, Istanbul, Kucukcekmece — Kayabasi.
Site: Housing complex with 1340 flats
Operating hours: 8060 h
Total hours in a year = 24×365=8760 h
( )
(1)
The plant life (n) is 20 years and it is consumed natural gas
as fuel in there. There is no steam requirement at the system.
Hot water between 70-90°C is needed at the central heating
installation. Main purpose is to supply electricity demand of
housing complex and partially supplying heating demand.
In calculations, electricity produced more than
requirement is sold with 20% discount rate [25], [26]. Natural
gas used for cooking at houses is not included to calculations.
The full stop is used as thousand separators while comma is
used as decimal point. Electricity and natural gas demand of
housing complex can be seen in the Table I and Table II [26].
Journal of Clean Energy Technologies, Vol. 4, No. 2, March 2016
130
TABLE I: ELECTRICITY DEMAND OF HOUSING COMPLEX
Months Consumption
Number
of
Houses
Total
[kWh]
January 167 1340 223780
February 149 1340 199660
March 171 1340 229140
April 115 1340 154100
May 128 1340 171520
June 139 1340 186260
July 141 1340 188940
August 138 1340 184920
September 157 1340 210380
October 134 1340 179560
November 163 1340 218420
December 158 1340 211720
Ee 2358400
TABLE II: NATURAL GAS DEMAND OF HOUSING COMPLEX
Months Cons.
[m3]
Cons.
[kWh]
Number
of
Houses
Total
[kWh]
January 137 1288 1340 1726569.9
February 146 1373 1340 1839994.2
March 120 1129 1340 1512324.0
April 90 846 1340 1134243.0
May 23 216 1340 289862.1
June 17 160 1340 214245.9
July 19 179 1340 239451.3
August 17 160 1340 214245.9
September 22 207 1340 277259.4
October 84 790 1340 1058626.8
November 119 1119 1340 1499721.3
December 132 1241 1340 1663556.4
Et 10535857.2
In Table I and Table II, Ee and Et represent total annual
electricity demand and total annual natural gas demand
respectively. These consumption distributions can be seen
explicitly at Fig. 3 and Fig. 4 monthly.
Fig. 3. Monthly electricity consumption (kWh).
Fig. 4. Monthly natural gas consumption (kWh).
One of the ways to select capacity is according to peak
consumption value. As it seen from the electricity
consumption figure, the most electricity consumption in the
year was occurred in March. Electricity demand in this month
is 229140 kWh. According to assumption of facility operates
24 hours and 30 days.
Power Requirement;
(2)
When the systems losses and inner electricity
consumptions are taken in to consideration, it is suitable to
choose system power more than calculated power
requirement. GE’s Jenbacher type 2 gas engine is suitable to
supply electrical demand of the site as shown in Fig. 5. The
cost of system is 290000$. Systems’ efficiencies, outputs and
NOx emissions are at the Table III and Table IV. The
technical properties of gas engine is as shown at the Table V.
TABLE III: OUTPUTS AND ELECTRICALLY EFFICIENCIES OF GAS ENGINE
Natural Gas 1500 rpm/50 Hz
NOX Type Pel (kW) ηel (%)
500 mg/m3N 208 330 38.7
TABLE IV: OUTPUTS AND THERMAL EFFICIENCIES OF GAS ENGINE
Natural Gas 1500 rpm/50 Hz
NOX Type Pth (kW) ηth (%)
500 mg/m3N 208 363 42.6
TABLE V: TECHNICAL DATAS OF GAS ENGINE
Configuration In line
Bore (mm) 135
Stroke (mm) 145
Displacement/cylinder (L) 2.08
Speed (rpm) 1.500 (50Hz), 1.800 (60Hz)
Mean piston speed (inch/s) 7,3 (1.500 rpm), 8,7 (1.800 rpm)
Scope of supply
Generator set, cogeneration
system, generator set/
cogeneration in container
Applicable gas types
Natural gas, flare gas, propane,
biogas, sewage gas, landfill gas,
coal mine gas, special gases (e.g.
coke, wood, and pyrolysis gases)
Engine type J208 GS
Number of cylinders 8
Total displacement (L) 16.6
Fig. 5. GE Jenbacher type 2330kW gas engine.
Natural gas is used at the system, and values of natural gas
Journal of Clean Energy Technologies, Vol. 4, No. 2, March 2016
131
are given below:
( )
( )
( )
(3)
( )
( ) (4)
( ) (5)
( ) (6)
where Pth is thermal power capacity of the plant:
Heat generated from cogeneration does not supply the total
heat demand. Additional heat demand will be supplied by
using natural gas individually.
Revenues of the system consist of only the electricity sales.
The amount of electricity and heat are determined with the
specifications of chosen gas engine. More electricity which is
not needed is sold to another consumer.
A. Savings in Electricity
Turkey’s demand for energy and electricity is increasing
rapidly. Energy consumption has increased at an annual
average rate of 4.3% since 1990 [27]. As would be expected,
the rapid expansion of energy production and consumption
has brought with it a wide range of environmental issues at
the local, regional and global levels. Turkey’s carbon dioxide
(CO2) emissions have grown along with its energy
consumption.
BEDAS is responsible for electricity distribution in
European side of Istanbul.
The amount of electricity is not purchased from:
( )
( )
( ) (7)
( ) (8)
( ) (approximately 20% discount is accepted for private user)
( ) (9)
( ) (10)
B. Final Stage
Without cogeneration:
( )
( ) (11)
With cogeneration:
( )
(12)
( )
(13)
( )
(14)
( )
where ηb is efficiency of boiler and
This calculation indicates if we obtained that energy by
using boiler that is efficiency 0,95, what fuel consumption
would be. In other words, this value, also, reveals natural gas
savings from thermal energy by using cogeneration.
( ) (15)
Journal of Clean Energy Technologies, Vol. 4, No. 2, March 2016
132
( ) (16)
Natural gas consumption will be rised with cogeneration
system when compared to case without cogeneration,
because of the natural gas consumption of gas engine to
produce electricity.
C. Economic Feasibility
In this study, economic feasibility of the system is assessed
according to two different methods. One of these is payback
period, another is lifetime levelized cost method. Payback
period is the one of the simplest method to assess economic
feasibility of the system. Payback period gives information
about how much time required system pays itself off.
Payback period are calculated as follow:
(17)
( ) (18)
( )
(19)
( )
(20)
D. Lifetime Levelized Cost of Energy of CHP Plant
Lifetime levelized cost method is complicated than
payback period method. In this method, Interest and
escalation rate is taken into consideration over system life.
This method is based on finding electricity cost per kWh in a
year. This cost is compared with cost of electricity taken from
grid to decide whether system is feasible or not.
The cost per kWh is calculated via the levelized cost of
energy (Ce)
(21)
(
)
( )
(22)
( )
( ) [28]
( ) ( ) ( )
(23)
(
)
( )
(24)
(25)
( )
( ) (26)
( )
( )
( ) [29]
(27)
( )
(28)
( )
Journal of Clean Energy Technologies, Vol. 4, No. 2, March 2016
133
where Ce, levelized cost of electricity per kWh; Cc, levelized
capital cost per kWh; Cf, levelized fuel cost per kWh; Co&m,
operating and maintenance cost per kWh; r, escalation rate; E,
annual total energy demand; Ee, annual electricity energy
demand; Et, annual thermal energy demand; i, interest rate; Z,
total capital cost; Fo, annual fuel cost; CELF,
constant-escalation levelization factor; CRF, cost reduction
factor; n, plant life; , efficiency of plant; Hu, lower heating
value; f, Price of Natural Gas.
III. RESULTS AND DISCUSSION
Turkey, with its young population and growing energy
demand per person, its fast growing urbanization, and its
economic development, has been one of the fast growing
power markets of the world for the last two decades. It is
expected that the demand for electric energy in Turkey will
be by the year 2020 [30]. Turkey is heavily dependent on
expensive imported energy resources that place a big burden
on the economy and air pollution is becoming a great
environmental concern in the country. Air pollution from
energy utilization in the country is due to the combustion of
coal, lignite, petroleum, natural gas, wood and agricultural
and animal wastes. On the other hand, owing mainly to the
rapid growth of primary energy consumption and the
increasing use of domestic lignite, SO2 emissions, in
particular, have increased rapidly in recent years in Turkey.
The electricity losses come from the transmission and
distribution systems. The loss in the transmission line of
Turkey is about 2.5–3%, which is within world standards.
However, the distribution loss is considerably high at 15%
[30]. It is expected that the distribution losses will be reduced.
Cogeneration, or autoproduction, is known as Combined
Heat and Power (CHP), which has been developed by
governmental support to support the continuing need for
additional electricity generation. The main advantage of
cogeneration is that less input energy is consumed than would
be required to produce the same thermal and electrical
products in separate processes. Additional benefits of
cogeneration often are reduced environmental emissions.
There were only for cogeneration plants in operation in 1994,
with a total capacity of only 30MWe. Since then, incentives
were offered by TEDAS (Turkish Electricity Distribution
Company) in the form of a 100% tax deduction, duty
exemptions for autoproduction facilities, and guaranteed
purchasing of any surplus electricity [31].
Consequently, cogeneration systems will consume less
fuel per unit, so that consumers will be protected from
unstable energy prices. However, the distribution losses
occurring in the transmission of electricity will be prevented.
Thus, consumers will reach with a more reliable way to
electricity and heat. As the amount of fuel consumed per unit
of energy in cogeneration systems is less, cogeneration
systems will reduce air pollution and greenhouse gas
emissions.
Although this method containing the additional cost
increased the investment costs in the first phase, it is clear
that cogeneration systems are useful systems in terms of user
and an environmental in the long run. TOKI (Turkish housing
administration) should pursue innovator policies in creating a
sustainable environment and it should apply in its projects. In
addition, TOKI should guide other construction company.
IV. CONCLUSION
At the end of the study, as it is clearly seen from payback
period approach the system is paid off itself in 1.33 year,
approximately16 months. When the system is evaluated
according to levelized life cycle cost, it can be understood the
electricity production by CHP is cheaper when compared to
that sold by BEDAS. Moreover the fuel expenditure of
system consists of notable parts of cost of electricity. If the
result is checked according the administrive approach, it is
clearly seen that system is very profitable. Although the
investment cost is high, supplying energy demand, possibility
of selling surplus electricity production and using energy
resources efficiently enhance application chance of this
cogeneration system. This cogeneration system, also, will
reduce transmission line losses at grid that are formed when
electrical energy is carried to consumer.
Based on Turkish Renewable Energy Law, for maximum
500 kW installed capacity combined heat and power system,
there is no need legal obligation and establish a company.
Non-legal and legal person can be installed the system and
they can sell surplus energy.
NOMENCLATURE
ADN Annual day number
AEG Annual electricity generation
AEP Average electricity price AFC Annual fuel consumption
AHG Annual heat generation
Ce Levelized cost of electricity Cc Levelized capital cost
Cf Levelized fuel cost
COM Levelized operating and maintenance cost CELF Constant escalation levelization factor
CF Capacity factor CRF Cost reduction factor
E Annual total energy demand
Ee Annual electricity energy demand Et Annual thermal energy demand
ES Electricity sold
f Price of natural gas
fe Electricity sale price
F0 Annual fuel cost
FC Fuel cost FCGE Fuel consumption of gas engine
FCH Fuel consumption per hour
FFR Fuel flow rate HU Lower heating value of natural gas
HGC Heat generated from cogeneration
HR Heat revenue i Interest rate
IES Income from electricity sold
n Plant life NAI Net annual income
NGE Natural gas expenditure without generation
NGSC Natural gas savings for cogeneration OH Operating hours
OMC Operating and maintenance cost
Pth Thermal power capacity
Journal of Clean Energy Technologies, Vol. 4, No. 2, March 2016
134
Pel Electricity power capacity
PP Payback period
SE Saving in electricity SFC Specific fuel consumption
TAH Total annual hours
TCC Total capital cost TNDGC Total natural gas demand with cogeneration
TNGEC Total natural gas expenditure with cogeneration
TSE Total savings from electricty UOMC Unit operating and maintenance cost
Z Cost of system
REFERENCES
[1] ASHRAE, ASHRAE Handbook HVAC Systems and Equipment, USA, 2000.
[2] M. Atmaca, ―Efficiency analysis of combined cogeneration systems
with steam and gas turbines,‖ Energy Sources, Part A: Recovery, Utilization, and Environmental Effects, vol. 33, pp. 360-363, 2010.
[3] P. Purohita and A. Michaelowab, ―CDM potential of bagasse
cogeneration in India,‖ Energy Policy, vol. 35, pp. 4779-4798, 2007. [4] J. A. Orlando, Cogeneration Design Guide, USA, 1996.
[5] C. A. Frangopoulos, The European Educational Tools on
Cogeneration, European Commission, 2001. [6] H. I. Onovwiona and V. I. Ugursal, ―Residential cogeneration systems:
Review of the current technology,‖ Renewable and Sustainable Energy
Reviews, vol. 10, pp. 389–431, 2006. [7] R. P. Allen and J. M. Kovacik, ―Gas turbine cogeneration principles
and practices,‖ Journal Engineering Gas Turbines and Power, vol. 106,
pp. 725–730, 1984. [8] B. Sahin, A. Kodal, I. Ekmekci, and T. Yilmaz, ―Exergy optimization
for an endoreversible cogeneration cycle,‖ Energy, vol. 22, pp. 551–
557, 1997. [9] C. Wu, L. Chen, and J. Chen, Recent Advances in Finite-Time in
Thermodynamics, New York: Nova Science Publishers, USA, 1999.
[10] C. Wu, L. Chen, and J. Chen, Thermodynamics, New York: Nova Science Publishers, USA, 2004.
[11] T. Yilmaz, ―Optimization of cogeneration systems under alternative
performance criteria,‖ Energy Conversion Management, vol. 45, pp. 939–945, 2004.
[12] X. Feng, Y. N. Cai, and L. L. Qian, ―A new performance criterion for
cogeneration systems,‖ Energy Conversion Management, vol. 39, pp. 1607–1609, 2004.
[13] R. Benelmir and M. Feidt, ―Energy cogeneration systems and energy
management strategy,‖ Energy Conversion Management, vol. 39, pp. 1791–1802, 1998.
[14] E. Bilgen, ―Exergetic and engineering analysis of gas turbine based
cogeneration systems,‖ Energy, vol. 25, pp. 1215–1229, 2000. [15] A. Khaliq and S. C. Kaushik, ―Second-law based thermodynamic
analysis of Brayton/Rankine combined power cycle with reheat,‖
Applied Energy, vol. 78, pp. 179–197, 2004. [16] I. O. Marrero, A. M. Lefsaker, A. Razani, and K. J. Kim, ―Second law
analysis and optimization of a combined triple power cycle,‖ Energy
Conversion Management, vol. 43, pp. 557–573, 2001. [17] H. Lund, G. Siupsinskas, and V. Martinaitis, ―Implementation strategy
for small CHP-plants in a competitive market: The case of Lithuania,‖
Applied Energy, vol. 3, pp. 214–227, 2005. [18] H. Lund and A. N. Andersen, ―Optimal designs of small CHP plants in
a market with fluctuating electricity prices,‖ Energy Conversion
Management, vol. 46, pp. 893–904, 2005. [19] Y. Ust, B. Sahin, and T. Yilmaz, ―Optimization of a regenerative
gas-turbine cogeneration system based on a new exergetic performance
criterion: Exergetic performance coefficient (EPC),‖ Proceedings of the Institution of Mechanical Engineers, vol. 221, pp. 447–456, 2007.
[20] T. Yilmaz, ―Performance optimization of a gas turbine-based
cogeneration system,‖ Journal of Physics D: Applied Physics, vol. 39, pp. 2454–2458, 2006.
[21] A. Hepbasli, ―Development of cogeneration in Turkey,‖ Energy Sources, vol. 24, pp. 195–204, 2002.
[22] H. Aras, ―Condition and development of the cogeneration facilities
based on auto production investment model in Turkey,‖ Renewable
and Sustainable Energy Reviews, vol. 7, pp. 553–559, 2003. [23] World Energy Council Turkish, ―World energy council Turkish
national committee, energy statistics 1998 (in Turkish),‖ presented at
the Turkish Eighth Energy Congress, 1999. [24] M. Mendilcioglu, ―Restructuring the Turkish electricity market (in
Turkish),‖ presented at the Turkish Eighth Energy Congress, Ankara,
Turkey, 2000. [25] H. A. Danisman, ―Energy outlook of Turkey,‖ presented at the
Conference on Prospects for Cleaner Fossil Fuels Systems in
Sustainable Development, Ankara, Turkey, 1999. [26] Energy Market Regulatory Authority. [Online]. Available:
www.epdk.gov.tr
[27] S. Bilgen, S. Keles, A. Kaygusuz, A. Sarı, and K. Kaygusuz, ―Global warming and renewable energy sources for sustainable development: A
case study in Turkey,‖ Renewable and Sustainable Energy Reviews,
vol. 12, pp. 372–96, 2008. [28] Central Bank of the Republic of Turkey. [Online]. Available:
www.tcmb.gov.tr
[29] Turkish Electricity Distribution Company. [Online]. Available: www.tedas.gov.tr
[30] E. Toklu, M. S. Guney, M. Isik, O. Comakli, and K. Kaygusuz,
―Energy Production, Consumption, Policies and Recent Developments in Turkey,‖ Renewable and Sustainable Energy Reviews, vol. 14, pp.
1172–1186, 2010.
[31] F. C. Kilic and D. Kaya, ―Energy production, consumption, policies, and recent developments in Turkey,‖ Renewable and Sustainable
Energy Reviews, vol. 11, pp. 1312–1320, 2007.
Mustafa Atmaca was graduated in 1993 from Yildiz Technical University, Faculty of Mechanical
Engineering. In 1994, he was with Marmara
University, Faculty of Technical Education as a research assistant in the Department of Mechanical,
his academic life was started from here. Then he
received the master's degree in 1996 and completed doctorate study in 2003. In 2010 he was a faculty
member as well as an associate professor in Marmara
University, Faculty of Technology, Department of Mechanical Engineering. He is a member of Chamber of Mechanical Engineers. His main research
areas include wind tunnel testing and optimization, exergy, HVAC systems,
energy efficiency in building.
Ender Yilmaz was born in Istanbul in 1983. He works now in Istanbul Technical University. He is a research assistant in Marmara University. His
main research areas are energy efficiency in buildings, exergy, energy
economy. He is a member of Chamber of Mechanical Engineers.
Ahmet Berk Kurtulus was born in Istanbul in 1988. In
2010, he was graduated from the Faculty of
Engineering, Department of Mechanical Engineering, Sakarya University. Then he continued his study in
2011 at the Department of Mechanical Engineering of
Thermal-Fluid Program, Istanbul Technical University Institute of Science. In the same year, he was also
worked at the Faculty of Technology Department of
Mechanical Engineering Marmara University, as a research assistant. Currently, his graduate education and research
assistantship are continues. His main research areas include two-phase
flows, transfer mechanisms in porous media, exergy, HVAC systems, energy efficiency in buildings, cryogenic systems and applications. He is a Chamber
of Mechanical Engineers member as well as a member in Turkish Heat
Science and Technique Association.
Journal of Clean Energy Technologies, Vol. 4, No. 2, March 2016
135