Upload
prateek43513
View
225
Download
0
Embed Size (px)
Citation preview
8/2/2019 Appl of ITs-VT
1/25
Voltage Transformers
Voltage Transformers for
- Metering Should Maintain accuracy Between 80 % and 120 %
of Rated Voltage and 25 % to 100 % of Rated Burden
- Protection Should Maintain Accuracy Between 5 % of Rated
Voltage and Voltage Factor times Rated Voltage
Voltage Factors:
- 1.5 for 30 seconds for effectively Earthed System
- 1.9 for 30 seconds for Non-effectively Earthed Systems
_ 1.9 for 8 hours for Resonance Earthed System
8/2/2019 Appl of ITs-VT
2/25
VECTOR DIAGRAM OF VOLTAGE TRANSFORMER
Fig1(C)Fig 1(B)
Fig1(A)
8/2/2019 Appl of ITs-VT
3/25
8/2/2019 Appl of ITs-VT
4/25
ACCURACY REQUIREMENTS OF PROTECTIVE
VOLTAGE TRANSFORMERS
lass Ratio Error % Phase
Displacement
(Minutes)
3P +/- 3.0 +/- 120
6P +/- 6 +/- 240
8/2/2019 Appl of ITs-VT
5/25
Hypothetical 9 MVAr
Capacitor Bank
Number of Groups (X) : 3
No. of capacitor units/
group:(M)
10 of 100 kVAr 6.35 kV
8/2/2019 Appl of ITs-VT
6/25
Rated Residual Voltages
Preferred Values Non-Preferred Values
100 or 110 V 200 V
100/3 or 110 /3 V 200/3 V
100/3 or 110/3 200/3
Taking the Case of Hypothetical Bank shown in theprevious slide:-
Voltage on the remaining units with %Rise Reflected value with 200V
n capacitor removed in a group RVT winding voltage
One unit - 6885 V 108 0.65 V
Two units - 7520 V 118 0.675 V
As the difference is very low for better discrimination
Residual voltages of 380 V or 570 V are used
8/2/2019 Appl of ITs-VT
7/25
8/2/2019 Appl of ITs-VT
8/25
N 2
Oil
Single Stage Dead Tank Voltage Transformer
8/2/2019 Appl of ITs-VT
9/25
Schematic Diagram of Layer type Primary Winding
and Multiple Secondary Windings
layers
Inter-layer Capacitance
Earth shield
Secondary Windings
8/2/2019 Appl of ITs-VT
10/25
Multiple Secondary windings-Special Precautions
National and International Standards specify that--
In case of multiple secondary windings the accuracy on individual windings
should be maintained between 25 % and 100 % rated burden,
- while the burden on the other windings is varying between zero to 100% of
their rated value.
In case of a three secondary windings with say,
Winding 1: 200 VA with metering accuracy 0.5
Winding 2 : 200 VA with protection accuracy 5P
Winding 3: 200 VA for residual voltage voltage measurement
-the accuracy of the metering winding 1, will have to be maintained 25% of its
rated burden i.e 50 VA to virtually 300 VA when the other windings are
simultaneously loaded(considering that primary and secondary contributeequally for errors)
As the some of protection windings like winding 3 come into
operation for a short duration under fault condition,it is
advantageous to except load on this winding for purposes of
accuracy measurement on winding 1
8/2/2019 Appl of ITs-VT
11/25
Circuit Diagram
Oil
Two Stage Cascade
Voltage Transformer
N 2
8/2/2019 Appl of ITs-VT
12/25
Four Stage Cascade Voltage Transformer
N 2
Oil
8/2/2019 Appl of ITs-VT
13/25
8/2/2019 Appl of ITs-VT
14/25
FAILURE OF VOLTAGE
TRANSFORMERS DUE TO DISCHARGE OF CAPACITOR CHARGE
THRO THE PRIMARY WINDING
DUE TO FERRORESONANCE
MECHANICAL FAILURE OF PORCELAIN DUE TO
GROUND VIBRATIONS - LIKE
EARTHQUAKEAS
8/2/2019 Appl of ITs-VT
15/25
Discharge of capacitor charges:
q Discharge of residual charge from switched off linesq Discharge of capacitor banksRemedy:
1. Determine magnitude and waveform of discharge current.
2.Refer to manufacturer.
3.Divide capacitor bank into two or more banks
8/2/2019 Appl of ITs-VT
16/25
High Voltage Busbar
Isolator
Isolator
Circuit Breaker
with Grading Capacitors
Voltage
Transformer
Cb - Grading CapacitorsCs -Capacitance to Ground
V.T - Iron Cored Voltage Transformer
V.T
8/2/2019 Appl of ITs-VT
17/25
Fig 26. Points of operation of the circuit(Only first quqdrant shown)
Vl = f(I)
Vc+V Vc-V
8/2/2019 Appl of ITs-VT
18/25
1)
2)
)
Under Ferro-resonance
condition the voltage waveform
exhibits presence of higher
harmonics and increasedvoltage.
The voltage magnitude goes up
to 1.4 P.U.
The current magnitude jumpsup almost hundred-fold,
resulting in severe dielectric
and thermal overloading of V.T
and eventual failure
8/2/2019 Appl of ITs-VT
19/25
FAILURE OF V.Ts DUE TO FERRO RESONANCE
IN INDIA
1. RISHIKESH S/S OF UPSEB2. SHARAVATI S/S OF KSEB
3. MSEB (PROBABLY IN 1987)
ABROAD
1. LABORELEC REPORT MENTIONS OF FAILURES
AT 8 PLACES BETWEEN 1967 AND 1975
FERRO RESONANCE IS KNOWN TO HAVE CAUSED FAILURE OFPOWER TRANSFORMER CONNECTED ON THE IDLE CIRCUIT OF
A DOUBLE CIRCUIT POWER LINE . FERRORESONANCE OCCURREDACROSS THE CAPACITANCE BETWEEN THE LINES AND THE Xr.
8/2/2019 Appl of ITs-VT
20/25
REMEDIES:
1. OPEN THE BREAKER ISOLATOR IMMEDIATELY
AFTER OPENING THE BREAKER ( Isolators to be motor
operated and remotely controlled)
2. USE VTs WITH LINEAR MAGNETISATION
CHARACTERISTIC ACROSS BUSBARS
FERRORESONANCE
8/2/2019 Appl of ITs-VT
21/25
V.T FAILURES ARE KNOWN TO OCCUR BECAUSE OF
INCIDENCE OF HIGH VOLTAGE HIGH FREQUENCYSURGES DURING CAPACITOR SWITCHING
MODE OF OCCURRENCE
1. PD ONSET BECAUSE OF INCIDENCE OF SURGE
2. SUSTAINED PARTIAL DISCHARGES EVEN AFTERRESTORATION OF NORMAL VOLTAGE
3. GRADUAL DETERIORATION OF INSULATION AND EVENTUAL FAILURE
REMEDY:
EMTP STUDY OF SUBSTATIONS WHERE LARGECAPACITOR BANKS ARE LOCATED
8/2/2019 Appl of ITs-VT
22/25
OTHER MECHANICAL REASONS FOR FAILURE
SEALING FAILURE---Allowing free breathing ofatmospheric air
DRY BAND FORMATION--During pre-monsoon showers
and un-seasonal rains OPEN EARTH CONNECTION OF PRIMARY WINDING --
Causing arcing,failure of enamel insulation on windingwire and eventual failure .
FAILURE OF FRAGILE PORCELAIN DUE TO GROUNDVIBRATIONS.
FAILURE OF HIGH VOLTAGE TERMINAL DUETO MECHANICAL FORCES LIKE WIND LOADS -TESTS FOR COMPLIANCE ADDED IN IEC 60044-2 Part 2
8/2/2019 Appl of ITs-VT
23/25
Routine Maintenance
At the time of Installation:
Porcelain:
Inspect Porcelain for Chipping, Cracks and
Leakage of Oil through flanges.
Oil Sampling:- To be kept to the barest minimum
- BDV to be not less than 60 kV
8/2/2019 Appl of ITs-VT
24/25
Routine Maintenance
After Three months of Service :
Nitrogen Pressure to be Checked.
Pressure at the Top through N2 Filling Valve:- to be between 0.2 and 0.3 kg/ sq.cm in the
temperature range of 20 to 30 deg C.
Pressure at the Tank Valve:- to be between 0.38 and 0.48 kg/sq.cm taking into
account static head of oil.
8/2/2019 Appl of ITs-VT
25/25
Periodic Maintenance
Yearly:
-Inspect Porcelain for chipping, cracks and
oil leakage through flanges.
-Clean porcelain with dry cloth
Once in two years:
BDV and moisture content of oil.Depleted
oil can be made up through valve on tank