Appl of ITs-VT

Embed Size (px)

Citation preview

  • 8/2/2019 Appl of ITs-VT

    1/25

    Voltage Transformers

    Voltage Transformers for

    - Metering Should Maintain accuracy Between 80 % and 120 %

    of Rated Voltage and 25 % to 100 % of Rated Burden

    - Protection Should Maintain Accuracy Between 5 % of Rated

    Voltage and Voltage Factor times Rated Voltage

    Voltage Factors:

    - 1.5 for 30 seconds for effectively Earthed System

    - 1.9 for 30 seconds for Non-effectively Earthed Systems

    _ 1.9 for 8 hours for Resonance Earthed System

  • 8/2/2019 Appl of ITs-VT

    2/25

    VECTOR DIAGRAM OF VOLTAGE TRANSFORMER

    Fig1(C)Fig 1(B)

    Fig1(A)

  • 8/2/2019 Appl of ITs-VT

    3/25

  • 8/2/2019 Appl of ITs-VT

    4/25

    ACCURACY REQUIREMENTS OF PROTECTIVE

    VOLTAGE TRANSFORMERS

    lass Ratio Error % Phase

    Displacement

    (Minutes)

    3P +/- 3.0 +/- 120

    6P +/- 6 +/- 240

  • 8/2/2019 Appl of ITs-VT

    5/25

    Hypothetical 9 MVAr

    Capacitor Bank

    Number of Groups (X) : 3

    No. of capacitor units/

    group:(M)

    10 of 100 kVAr 6.35 kV

  • 8/2/2019 Appl of ITs-VT

    6/25

    Rated Residual Voltages

    Preferred Values Non-Preferred Values

    100 or 110 V 200 V

    100/3 or 110 /3 V 200/3 V

    100/3 or 110/3 200/3

    Taking the Case of Hypothetical Bank shown in theprevious slide:-

    Voltage on the remaining units with %Rise Reflected value with 200V

    n capacitor removed in a group RVT winding voltage

    One unit - 6885 V 108 0.65 V

    Two units - 7520 V 118 0.675 V

    As the difference is very low for better discrimination

    Residual voltages of 380 V or 570 V are used

  • 8/2/2019 Appl of ITs-VT

    7/25

  • 8/2/2019 Appl of ITs-VT

    8/25

    N 2

    Oil

    Single Stage Dead Tank Voltage Transformer

  • 8/2/2019 Appl of ITs-VT

    9/25

    Schematic Diagram of Layer type Primary Winding

    and Multiple Secondary Windings

    layers

    Inter-layer Capacitance

    Earth shield

    Secondary Windings

  • 8/2/2019 Appl of ITs-VT

    10/25

    Multiple Secondary windings-Special Precautions

    National and International Standards specify that--

    In case of multiple secondary windings the accuracy on individual windings

    should be maintained between 25 % and 100 % rated burden,

    - while the burden on the other windings is varying between zero to 100% of

    their rated value.

    In case of a three secondary windings with say,

    Winding 1: 200 VA with metering accuracy 0.5

    Winding 2 : 200 VA with protection accuracy 5P

    Winding 3: 200 VA for residual voltage voltage measurement

    -the accuracy of the metering winding 1, will have to be maintained 25% of its

    rated burden i.e 50 VA to virtually 300 VA when the other windings are

    simultaneously loaded(considering that primary and secondary contributeequally for errors)

    As the some of protection windings like winding 3 come into

    operation for a short duration under fault condition,it is

    advantageous to except load on this winding for purposes of

    accuracy measurement on winding 1

  • 8/2/2019 Appl of ITs-VT

    11/25

    Circuit Diagram

    Oil

    Two Stage Cascade

    Voltage Transformer

    N 2

  • 8/2/2019 Appl of ITs-VT

    12/25

    Four Stage Cascade Voltage Transformer

    N 2

    Oil

  • 8/2/2019 Appl of ITs-VT

    13/25

  • 8/2/2019 Appl of ITs-VT

    14/25

    FAILURE OF VOLTAGE

    TRANSFORMERS DUE TO DISCHARGE OF CAPACITOR CHARGE

    THRO THE PRIMARY WINDING

    DUE TO FERRORESONANCE

    MECHANICAL FAILURE OF PORCELAIN DUE TO

    GROUND VIBRATIONS - LIKE

    EARTHQUAKEAS

  • 8/2/2019 Appl of ITs-VT

    15/25

    Discharge of capacitor charges:

    q Discharge of residual charge from switched off linesq Discharge of capacitor banksRemedy:

    1. Determine magnitude and waveform of discharge current.

    2.Refer to manufacturer.

    3.Divide capacitor bank into two or more banks

  • 8/2/2019 Appl of ITs-VT

    16/25

    High Voltage Busbar

    Isolator

    Isolator

    Circuit Breaker

    with Grading Capacitors

    Voltage

    Transformer

    Cb - Grading CapacitorsCs -Capacitance to Ground

    V.T - Iron Cored Voltage Transformer

    V.T

  • 8/2/2019 Appl of ITs-VT

    17/25

    Fig 26. Points of operation of the circuit(Only first quqdrant shown)

    Vl = f(I)

    Vc+V Vc-V

  • 8/2/2019 Appl of ITs-VT

    18/25

    1)

    2)

    )

    Under Ferro-resonance

    condition the voltage waveform

    exhibits presence of higher

    harmonics and increasedvoltage.

    The voltage magnitude goes up

    to 1.4 P.U.

    The current magnitude jumpsup almost hundred-fold,

    resulting in severe dielectric

    and thermal overloading of V.T

    and eventual failure

  • 8/2/2019 Appl of ITs-VT

    19/25

    FAILURE OF V.Ts DUE TO FERRO RESONANCE

    IN INDIA

    1. RISHIKESH S/S OF UPSEB2. SHARAVATI S/S OF KSEB

    3. MSEB (PROBABLY IN 1987)

    ABROAD

    1. LABORELEC REPORT MENTIONS OF FAILURES

    AT 8 PLACES BETWEEN 1967 AND 1975

    FERRO RESONANCE IS KNOWN TO HAVE CAUSED FAILURE OFPOWER TRANSFORMER CONNECTED ON THE IDLE CIRCUIT OF

    A DOUBLE CIRCUIT POWER LINE . FERRORESONANCE OCCURREDACROSS THE CAPACITANCE BETWEEN THE LINES AND THE Xr.

  • 8/2/2019 Appl of ITs-VT

    20/25

    REMEDIES:

    1. OPEN THE BREAKER ISOLATOR IMMEDIATELY

    AFTER OPENING THE BREAKER ( Isolators to be motor

    operated and remotely controlled)

    2. USE VTs WITH LINEAR MAGNETISATION

    CHARACTERISTIC ACROSS BUSBARS

    FERRORESONANCE

  • 8/2/2019 Appl of ITs-VT

    21/25

    V.T FAILURES ARE KNOWN TO OCCUR BECAUSE OF

    INCIDENCE OF HIGH VOLTAGE HIGH FREQUENCYSURGES DURING CAPACITOR SWITCHING

    MODE OF OCCURRENCE

    1. PD ONSET BECAUSE OF INCIDENCE OF SURGE

    2. SUSTAINED PARTIAL DISCHARGES EVEN AFTERRESTORATION OF NORMAL VOLTAGE

    3. GRADUAL DETERIORATION OF INSULATION AND EVENTUAL FAILURE

    REMEDY:

    EMTP STUDY OF SUBSTATIONS WHERE LARGECAPACITOR BANKS ARE LOCATED

  • 8/2/2019 Appl of ITs-VT

    22/25

    OTHER MECHANICAL REASONS FOR FAILURE

    SEALING FAILURE---Allowing free breathing ofatmospheric air

    DRY BAND FORMATION--During pre-monsoon showers

    and un-seasonal rains OPEN EARTH CONNECTION OF PRIMARY WINDING --

    Causing arcing,failure of enamel insulation on windingwire and eventual failure .

    FAILURE OF FRAGILE PORCELAIN DUE TO GROUNDVIBRATIONS.

    FAILURE OF HIGH VOLTAGE TERMINAL DUETO MECHANICAL FORCES LIKE WIND LOADS -TESTS FOR COMPLIANCE ADDED IN IEC 60044-2 Part 2

  • 8/2/2019 Appl of ITs-VT

    23/25

    Routine Maintenance

    At the time of Installation:

    Porcelain:

    Inspect Porcelain for Chipping, Cracks and

    Leakage of Oil through flanges.

    Oil Sampling:- To be kept to the barest minimum

    - BDV to be not less than 60 kV

  • 8/2/2019 Appl of ITs-VT

    24/25

    Routine Maintenance

    After Three months of Service :

    Nitrogen Pressure to be Checked.

    Pressure at the Top through N2 Filling Valve:- to be between 0.2 and 0.3 kg/ sq.cm in the

    temperature range of 20 to 30 deg C.

    Pressure at the Tank Valve:- to be between 0.38 and 0.48 kg/sq.cm taking into

    account static head of oil.

  • 8/2/2019 Appl of ITs-VT

    25/25

    Periodic Maintenance

    Yearly:

    -Inspect Porcelain for chipping, cracks and

    oil leakage through flanges.

    -Clean porcelain with dry cloth

    Once in two years:

    BDV and moisture content of oil.Depleted

    oil can be made up through valve on tank