81
CORRIB FIELD DEVELOPMENT PROJECT Onshore Works – Glengad METHOD STATEMENT Rev 01 LVI, GLENGAD COMPOUNDS and ACCESS ROAD CONSTRUCTION

Appendix L Method Statements.pdf

  • Upload
    trandat

  • View
    222

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Appendix L Method Statements.pdf

  

CORRIB FIELD DEVELOPMENT PROJECT   

Onshore Works – Glengad      

  

     

METHOD STATEMENT Rev 01 LVI, GLENGAD COMPOUNDS and ACCESS ROAD CONSTRUCTION 

    

      

Page 2: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: LVI, Glengad Compounds and Access Road 

Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 EMP  Method Statement  Revision: 01 Page 2 of 8

SUMMARY 

The  construction  of  the  Landfall  Value  Installation  (LVI) within  a  dished  area will  be  facilitated  by  the establishment  of  a  construction  compound.  This  compound  will  also  facilitate  the  onshore  works associated with  the umbilical  installation, onshore pipeline  construction, and pipeline  commissioning. A second  compound will  be  established  to  construct  the  reception  shaft  for  the  Tunnel  Boring Machine (TBM)1. A permanent access road to the LVI will also be constructed. 

PURPOSE  This method  statement  defines  the method  for  the  construction of  the  LVI, establishing  the Glengad construction  compounds and permanent LVI access road at Glengad. 

LOCATION  Glengad Headland. The temporary working area from chainage 83.38 – 83.92 lies within the Glenamoy Bog Complex candidate Special Area of Conservation (cSAC)  Site  Code  0000500  and  is  adjacent  to  the  Blacksod  Bay/Broadhaven proposed  Special  Protection  Area  (pSPA)  Site  Code  004037.  The  northern section of the access road from the L1202 is also in the cSAC. 

HABITATS / CONSERVATION STATUS 

The habitats located within the temporary working areas at Glengad comprise improved  agricultural  grassland  and  improved  wet,  rushy  grassy  grassland, neither of which are EU annexed habitats.  

With the exception of the southern section of the reception shaft compound, these habitats are located within the cSAC. 

TIMESCALE  

The entire work scope will take approximately 26 months. The LVI construction compound will be in operation for the entire duration of the onshore pipeline construction  including  LVI  surface  water  outfall  pipe  installation,  LVI construction,  Umbilical  pull‐in,  onshore  pipeline  construction,  tie‐in  of  the onshore and offshore pipeline and final commissioning activities.  

TECHNIQUE  Establishment of Glengad Compounds 

The compounds will be installed as follows: 

• A 3m high palisade  fence will be  erected on  grassland  and  secured by concrete road barriers.  

• In  designated  sections  the  perimeter  fence  will  be  screened  with  a suitable solid board to visually and acoustically screen the works in order to minimise disturbance to birds and non‐avian fauna. 

• A palisade fence fixed to precast concrete slabs will be positioned on the foreshore to facilitate the LVI outfall pipe  installation. This fence will be removed upon  reinstatement of  the  cliff  face and  replaced with a  land based fence installed along the top of the cliff.  

• The  temporary  fences around  the  construction  compounds and  the  LVI will be mammal proof. 

• A  temporary access road and hardstand areas will be constructed using locally sourced imported gravel/stone.  

• Temporary  welfare  facilities  will  be  installed  on  prepared  ground separate  from  the main working areas. Containers will be positioned as required within the compound. 

• All  necessary  electrical/telecom  wiring,  site  services,  lighting,  piping, ducting and fixtures will be installed. 

 

 

Page 3: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: LVI, Glengad Compounds and Access Road 

Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 EMP  Method Statement  Revision: 01 Page 3 of 8

Earthworks and Civil Works 

• Topsoil will be stripped from LVI  location and stockpiled  in a designated location separate from sub soil and other excavated material. 

• The dished area will be excavated, and the material stockpiled separate to topsoil. 

• Individual LVI structures within dished area will be excavated. • Construction of LVI structures, pipeline and ancillary services  installation 

will be completed simultaneously.  • Once  all  installation,  inspection  and  testing  has  been  completed,  all 

structures will be backfilled to their designated finished levels. • Permanent fencing and associated security systems will be erected. • Topsoil  will  be  placed  on  new  embankment  slopes.    An  open  mesh 

biodegradable  textile  (GeoJute) maybe used on  the  slopes  surrounding the LVI to stabilise topsoil against erosion.  

LVI Mechanical , Electrical and Commissioning works 

• The  piping,  valves,  structures,  and  chambers  will  be  erected  on  the prepared LVI foundations.  

• The relevant LVI components will be welded/jointed and inspected. • The offshore pipeline will be connected to the LVI. • The required LVI and pipeline commissioning, including hydrotesting, will 

take place within the construction compound.   

Offshore Umbilical Installation (Onshore Works) 

• The  compound will  also be used  to  support  the offshore umbilical pull ashore. 

• Prior  to  the  pull  ashore  a  winch  base  will  be  constructed  and  winch installed.  This  winch  will  be  used  to  pull  the  offshore  umbilical  line through the existing umbilical conduit to a termination point onshore at the LVI. 

• Following  the  pull  ashore  the  umbilical  will  be monitored  and  tested during offshore installation. 

• Following the offshore  lay of the umbilical, the onshore winch and base will be removed and area reinstated. 

Reinstatement 

The compound will not be reinstated until the end of the construction period however, some reinstatement will take place prior to this if progress allows. In general, reinstatement will progress as follows: 

• Excess materials  from  the  excavation  of  the  LVI  “dished”  area will  be reused elsewhere if possible and the surplus removed to a licensed waste facility. 

• Construct permanent access road to LVI using the specified mix of stone and soil. 

• Remove temporary facilities. 

• The site will be reinstated using the stockpiled topsoil and vegetation will be allowed to regenerate naturally. No seed will be imported. 

• All drains will be reinstated to their previous condition or, as agreed with 

Page 4: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: LVI, Glengad Compounds and Access Road 

Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 EMP  Method Statement  Revision: 01 Page 4 of 8

the relevant parties. 

• Where appropriate, simple, surface gravel field drains will be put in place to prevent water logging. 

• The  temporary palisade  fencing will  then be removed off site and stock proof fencing will be erected to protect the reinstated areas. 

 

EQUIPMENT/MATERIALS  Excavators 

Articulated flatbeds and tipper trucks 

Front tipping trucks 

Temporary welfare cabins 

Palisade security fence 

Winches and hydraulic power packs 

Hydrotest equipment 

Cranes and lifting equipment 

Side booms 

Concrete pump 

Electrical tools 

Welding equipment 

Synthetic fabrics  

Commissioning plant and equipment 

Storage tanks 

RESTRICTIONS  Some  sections of  the  temporary working area    lie within  the Glenamoy Bog Complex  Complex  cSAC    and  adjacent  to  the    Blacksod  Bay/Broadhaven BaypSPA  

• General working hours are restricted to between 07:00 – 19:00 weekdays and 07:00 and 16:00 Saturday.  

• Noise and vibration limits  • Lighting constraints 

CONTINGENCY  • Excavated material may have to be screened for potential reuse.  

  1 See Tunnelling Operations and Reception Shaft Method Statements

Page 5: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: LVI , Glengad Compounds and Access Road 

Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 EMP 

 Method Statement  Revision: 01 Page 5 of 8 

POTENTIAL ENVIRONMENTAL IMPACT 

MITIGATION 

Noise, vibration and lighting Disturbance. 

• Noise  and  vibration  will  be  minimised  through  design,  and appropriate section of plant and machinery. 

 • Proactive maintenance of plant and equipment. 

• Cladding of stationary machinery such as generators. 

• A  3m  high  non‐transparent  noise  barrier  will  be  installed  in designated  places  around  the  perimeter  of  the  construction compounds to prevent disturbance to birds in the pSPA . 

• Mobile  and  fixed  site  lighting  will  be  designed  to  limit  light spillage. 

Increased dust levels  • Roads/working  area  will  be  dampened  down,  as  required  to ensure  dust  levels  due  to  construction  activities  are  kept  to  a minimum. 

Page 6: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: LVI , Glengad Compounds and Access Road 

Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 EMP 

 Method Statement  Revision: 01 Page 6 of 8 

POTENTIAL ENVIRONMENTAL IMPACT 

MITIGATION 

Damage to habitats, including  cSAC habitats  

Access Road 

• The sod bank which  forms the boundary on the eastern side of the  access  road  (from  the  public  road)  will  be  fenced  off  to protect  it  from  damage  during  construction.  Any  temporary widening of the access road will be done on the western side. 

LVI and Glengad Compounds 

• An earthen (sod) bank forms the cSAC boundary to the south of the  temporary working  area  adjacent  to  the  LVI  and  onshore pipeline  temporary working  area. This  sod bank will be  fenced off to prevent construction activities encroaching on it. 

• Fencing  will  be  put  in  place  to  protect  the  Annex  1  habitats located to the north of the compounds. 

• No seed will be imported in order to prevent the pollution of the native gene pool by alien genotypes. 

• The top soil removed from the footprint and compounds will be carefully stored (separately from the sub‐soil). 

• Following construction this topsoil will then be used on the areas to be reinstated, including the slopes of the LVI and they will be left to re‐vegetate naturally. 

• To  aid  topsoil  stability  and  vegetation  regeneration,  an  open mesh  geotextile membrane  (GeoJute) may  be  laid  on  the  side slopes of the LVI excavation. 

• Surface drainage will be put in place at the time of reinstatement to prevent water logging where appropriate. 

• Stone used will be locally sourced. 

Page 7: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: LVI , Glengad Compounds and Access Road 

Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 EMP 

 Method Statement  Revision: 01 Page 7 of 8 

POTENTIAL ENVIRONMENTAL IMPACT 

MITIGATION 

Disturbance to Birds 

 

Ground nesting birds 

• Prior to construction, the temporary working area will be mowed in order  to discourage ground nesting birds  from attempting  to breed on the temporary working area.  

• A walkover  survey will  be  undertaken  prior  to  construction  in order  to  ensure  that  no  ground  nesting  birds  are  present  on lands to be disturbed.   

Sand Martin 

A  Sand Martin  colony  is  located  in  the  soft  cliffs  to  the  north  and north  east  of  the  landfall  at  Glengad.    Mitigation  measures  as outlined below will be put in place. 

• An  exclusion  zone  will  be  defined  above  and  behind  the colony such that no construction activities affect the existing burrows  or  threaten  the  stability  of  the  cliff  in which  the burrows are situated.  

• Apart from specialists conducting monitoring, no personnel, traffic or  construction  activities will  be permitted between the  temporary  fencing  and  the  cliff‐top  directly  above  the colony. 

• Soil  stockpiles will be  covered where necessary with a  fine mesh  netting  to  prevent  sand  martins  from  making  nest burrows therein. 

• Lighting  in site compounds will be directed downwards and be designed  to minimise  light  spillage  outside  the working area. 

pSPA 

• Visual and acoustic screening will be placed on the palisade fence in designated places to prevent disturbance to birds in the pSPA. 

• Lighting will be directed downwards and be designed to minimise light spillage outside the working area. 

Page 8: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: LVI , Glengad Compounds and Access Road 

Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 EMP 

 Method Statement  Revision: 01 Page 8 of 8 

POTENTIAL ENVIRONMENTAL IMPACT 

MITIGATION 

Construction activities may have negative impact on local wildlife (otters and badgers etc). 

• The  palisade  fence  around  the  LVI  and  reception  shaft compounds will be mammal proof.  

• The remainder of the fencing demarking the temporary working area,  including  the access  road, will have mammal gates at  the base  at  75m  intervals.  These  will  allow mammals  (otters  and badgers etc) free access across, and a means of escape from, the temporary working area.  

• During construction ramps will be provided at open trenches to provide  a means  of  escape  for  otters  and  badgers  and  other wildlife. 

Pollution of terrestrial / aquatic habitats due to spillage or leaks of oil/diesel from plant and equipment. 

• Machinery  and plant will be  inspected prior  to mobilisation  to site. 

• Refuelling of plant/machinery will take place in designated areas only.  

• Spill kits will be available on site 

Release of suspended solids from the works may have negative impact on water quality. 

 

• The  LVI  surface  water  outfall  pipe  will  not  be  used  for dewatering of excavations. 

• A  surface water management  system will be utilised  to ensure removal  of  suspended  solids  prior  to  discharge  to  receiving waters at an agreed location. 

• Surface drainage will be put in place at the time of reinstatement to prevent water logging where appropriate. 

Visual impact from the LVI structure. 

• The  LVI will  be  constructed  in  a  dished  area  to  reduce  visual impact of structure. 

Earthworks may disturb archaeological remains. 

• A licensed archaeologist will be on site to monitor all excavations in previously undisturbed areas. 

Page 9: Appendix L Method Statements.pdf

  

CORRIB FIELD DEVELOPMENT PROJECT   

Onshore Works – Glengad      

  

     

METHOD STATEMENT Rev 01  

LVI Surface Water Outfall Pipe and Cliff Reinstatement  

   

   

   

Page 10: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: LVI  Surface  Water  OutfallDraft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMP

Method Statement  Revision: 01 Page 1 of 5

SUMMARY 

The Landfall Valve  Installation (LVI) Surface Water Outfall will be constructed by excavating a trench and installing  the  pipe,  headwall  and  gabion  basket  structure  within  the  cliff  face.  The  cliff  face  will  be subsequently reinstated and the outfall pipe trench backfilled with excavated material.  

PURPOSE  This document defines the method for installation of the LVI surface water outfall pipe and subsequent reinstatement of the cliff section at Glengad. 

LOCATION  Glengad Headland.     The  temporary working area  from Chainage 83.38 – 83.50  lies within  the Glenamoy  Bog  Complex  candidate  Special  Area  of Conservation  (cSAC) and  the Blacksod Bay/Broadhaven proposed  Special Protection Area (pSPA).  

HABITATS / CONSERVATION STATUS 

Habitats comprise non‐annexed improved agricultural grassland (cliff top), reinstated sedimentary cliff; upper shoreline; and non‐qualifying intertidal Annex I habitat (1140 ‐ Mudflats and sandflats not covered by sea water at low tide).   

TIMESCALE  

The works will take approximately 8 weeks to complete, timed so that the works associated with the cliff face will be undertaken between April and September. This is to avoid disturbance to feeding Brent Geese during the overwintering  period.  The  remaining  works  will  take  place  outside  this time period. 

TECHNIQUE  LVI Outfall Pipe Trench and Cliff Excavation 

• Temporary  site palisade  fencing will extend  through  the cliff cut and extend  onto  a  limited  section  of  the  foreshore  (Ch  83.38 approximately). 

• A  trench will  be  excavated  from  the  cliff  face  and material will  be stored  temporarily within  the Glengad  compound  for  reinstatement. This material will also be used to form a suitable access ramp onto the foreshore for the installation of the surface water outfall pipe. 

• The  excavation of  the  trench  in  the  cliff  face may be up  to  5.5m  in depth  and  up  to  15m  wide.  All  trench  arisings  will  be  temporarily stored in the Glengad compound.  

• The trench will be excavated towards the LVI, sloping trench sides as necessary. 

• In sections of restricted working area or where ground conditions are poor, the surface water outfall pipe will be  laid using a trench box or support structure. 

Installation of Pipe Headwall and Gabion Basket Structure 

• The  headwall  will  be  constructed  by  means  of  hand  filled  gabion baskets around the outfall pipe blended in to the existing cliff face.   

• A geotextile separation layer will be placed at the base of the cliff face, on  top  of  which  a  headwall  will  be  constructed  using  gabion mattresses and baskets. 

• The baskets will be  filled with  locally  sourced  stone  to maximise  the integration  of  the  headwall  with  the  existing  cliff  and  surrounding environment. 

 

Page 11: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: LVI  Surface  Water  OutfallDraft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMP

Method Statement  Revision: 01 Page 2 of 5

 

• The  area  in  front  of  the  headwall  will  be  reinstated  with  locally sourced stone chosen to maximise the  integration of the outfall with the existing cliff and surrounding environment. 

 

Installation of LVI surface water outfall pipe 

• The LVI surface water outfall pipe will be placed in sections and joined in the prepared trench. 

• The LVI surface water outfall pipe will be backfilled after testing.  • The  backfill  material  shall  consist  of  compacted  fine  material  with 

progressive  layers  of  excavated material  being  utilised  to  complete trench backfill. 

 

Cliff and Trench Reinstatement 

• The  cliff  face will be  reinstated once  the outfall pipe  installation has progressed  an  adequate  distance  from  the  cliff  to  enable  full  cliff reinstatement. 

• As  the  gabions  are  installed  the  cliff material will  be  compacted  in layers progressing to original ground  level. The subsoil will be graded to reflect the original contours of the headland. 

• Geotextile may be  required on  steep  sections of  the  cliff  to prevent wind erosion and silt run off. 

• The  foreshore  area  will  be  reinstated  to  the  highest  achievable standard with maximum reuse of original foreshore material. 

• Surplus foreshore material will be reused or disposed of at a  licensed facility. 

• Any surplus imported rock will be removed off‐site for reuse. • The temporary fencing will be removed from the foreshore during cliff 

reinstatement. • A  stock proof  fence will be erected on  the cliff  top  for protection of 

people and livestock. 

Page 12: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: LVI  Surface  Water  OutfallDraft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMP

Method Statement  Revision: 01 Page 3 of 5

EQUIPMENT/MATERIALS  Excavators 

Articulated tipper trucks 

Front tipping trucks 

Cranes 

Welding Equipment  

Pallisade Fencing 

Surface Water Outfall Pipe 

Gabian Baskets and locally sourced stone 

Synthetic fabrics 

RESTRICTIONS  The working area lies within the  Glenamoy Bog Complex  

Blacksod Bay/Broadhaven Bay cSPA 4037 

• Normal working hours are restricted to between 07:00 – 19:00 weekdays and 07:00 and 16:00 Saturday.  

• Noise and vibration limits Lighting constraints. 

CONTINGENCY  A  rock  breaker mounted  on  an  excavator, maybe  required  to  achieve  the required  depth  for  the  LVI  outfall  pipe  or  the  LVI  outfall  pipe  termination gabion installation.   

 

Page 13: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: LVI Surface Water OutfallDraft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMP

Method Statement  Revision: 01 Page 4 of 5

 POTENTIAL ENVIRONMENTAL IMPACT 

MITIGATION 

Noise, vibration and lighting Disturbance. 

• Noise  and  vibration  will  be  minimized  through  design,  and appropriate selection of plant and machinery . 

 • Proactive maintenance of plant and equipment. 

• Cladding of stationary machinery such as generators. 

• Screening  will  be  placed  on  the  palisade  fence  in  designated places to prevent disturbance to birds in the pSPA. 

• Mobile  and  fixed  site  lighting  will  be  designed  to  limit  light spillage. 

Increased dust levels  • Roads/working  area  will  be  dampened  down,  as  required  to ensure  dust  levels  due  to  construction  activities  are  kept  to  a minimum. 

Damage to habitats in the cSAC and pSPA 

• No  machinery  or  personnel  will  be  permitted  outside  the temporary  fencing  on  the  foreshore  with  the  exception  of specialists who are conducting monitoring / survey work. 

• Works  will  be  restricted  to  the  section  of  cliff  which  was reinstated  in  2009.  Fencing  will  protect  the  previously undisturbed  cliff  on  either  side  of  the  currently  reinstated section of cliff. 

• Sediment / pollutant run off control measures (see below) will be implemented  to  minimise  impact  on  shoreline,  intertidal  and marine habitats.  

• Imported  stone,  including  that used  for  cliff  reinstatement, will be locally sourced. 

Construction activities may have negative impact on local wildlife ‐ otters and badgers. 

 

• Pre‐construction  surveys  for  otters  and  badgers  will  be undertaken within 1‐3 months prior  to  construction. The areas to  be  included  are  approximately  50‐100m  either  side  of  the centre line of the pipeline for otters, and 30m either side of the centre line for badgers.   

• Wildlife  will  be  excluded  from  the  temporary  works  area  by means of mammal proof fencing. 

Page 14: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: LVI Surface Water OutfallDraft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMP

Method Statement  Revision: 01 Page 5 of 5

POTENTIAL ENVIRONMENTAL IMPACT 

MITIGATION 

Disturbance to Birds and the pSPA 

 

Ground nesting birds 

• Prior  to  construction  a walkover  survey will  be  undertaken  to check  for ground nesting birds and the temporary working area onshore will be mowed to discourage these birds.  

• A walkover  survey will  be  undertaken  prior  to  construction  in order  to  ensure  that  no  ground  nesting  birds  are  present  on lands to be disturbed.  

 

Sand Martin 

A  Sand Martin  colony  is  located  in  the  soft  cliffs  to  the  north  and north  east  of  the  landfall  at  Glengad.    Mitigation  measures  as outlined below will be put in place. 

• An  exclusion  zone  will  be  defined  above  and  behind  the colony such that no construction activities affect the existing burrows  or  threaten  the  stability  of  the  cliff  in which  the burrows are situated.  

• Apart from specialists conducting monitoring, no personnel, traffic and construction activities will be permitted between the  Temporary  Working  Area  fencing  and  the  cliff‐top directly above the colony. 

• A wide  foreshore exclusion zone will be  in place to prevent any  activity  on  the  foreshore  below  and  in  front  of  the burrows which may deter normal behaviour and could result in lowered breeding success.  

• Soil  stockpiles will be  covered where necessary with a  fine mesh  netting  to  prevent  sand  martins  from  making  nest burrows therein. 

• Lighting  will  be  directed  downwards  and  designed  to minimise light spillage outside the working area.  

• Acoustic & visual screening of construction activities will be in place. 

Page 15: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: LVI Surface Water OutfallDraft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMP

Method Statement  Revision: 01 Page 6 of 5

POTENTIAL ENVIRONMENTAL IMPACT 

MITIGATION 

  Brent Geese 

Brent Geese over winter in the pSPA from October to the end of April and feed on algal beds adjacent to the Glengad landfall site. 

• Construction  activities  for  the  LVI  outfall,  including  cliff reinstatement  works  will  be  carried  out  during  summer months and outside the overwintering period.  

Pollution of terrestrial / aquatic habitats due to spillage or leaks of oil/diesel from plant and equipment. 

• Machinery  and plant will be  inspected prior  to mobilisation  to site. 

• Refuelling of plant/machinery will take place in designated areas only. 

• Refuelling will not take place on the foreshore. 

• Spill kits will be available on site. 

Release of suspended solids from the works could have negative impact on water quality. 

 

• As much as possible, construction works associated with the cliff cut will be carried out during  low  tide or neap  tides  to prevent inundation  and  subsequent mobilisation  of  sediment  into  the marine environment. 

• In  drain  mitigation  will  be  placed  as  required  to  reduce  silt impact on associated surface waters.   

• The LVI surface water outfall will not be used for dewatering of excavations during construction works. 

• A  surface water management  system will be utilised  to ensure removal  of  suspended  solids  prior  to  discharge  to  receiving waters at an agreed location. 

• Pumped water will be subject to sediment control measures. 

 

Earthworks may disturb archaeological remains 

• A licensed archaeologist will be on site to monitor all excavations in previously undisturbed areas. 

Page 16: Appendix L Method Statements.pdf

  

CORRIB FIELD DEVELOPMENT PROJECT   

Onshore Works – Glengad      

  

     

METHOD STATEMENT Rev 01  

ONSHORE PIPELINE CONSTRUCTION (Glengad)  

   

      

Page 17: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Onshore Pipeline Construction Glengad Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMPMethod Statement  Revision: 01 Page 1 of 6

SUMMARY 

This method statement outlines the methodology for the construction of onshore gas pipeline and services from  the  tie  in of  the offshore pipeline  to  the  Landfall Valve  Installation  (LVI)  and  from  the  LVI  to  the tunnel reception pit.  

PURPOSE  This method statement defines the methodology for construction of the pipeline and services in Glengad, to include preparation of the pipeline temporary working area, pipeline installation and reinstatement. 

LOCATION  Glengad Headland, between chainage 83.49 and 83.86.     Most of  the  temporary working  area  is  within  the  Glenamoy  Bog  Complex  candidate  Special  Area  of Conservation  (cSAC).  It  is  in  close  proximity  to  the  Blacksod  Bay/Broadhaven proposed Special Protection Area (pSPA). 

HABITATS / CONSERVATION STATUS 

The  habitats  located within  the  temporary working  areas  at  Glengad  comprise improved agricultural grassland and improved wet, rushy grassy grassland, neither of which are EU annexed habitats.  

With  the  exception  of  a  short  section  of  the  pipeline  route,  these  habitats  are located within the cSAC. 

TIMESCALE  

Preparation of  the  temporary working area and construction of  the pipeline are expected  to  take  approximately  two  months.  It  should  be  noted  that  the temporary working area will remain fenced off until the completion of tunnelling operations to facilitate removal of the tunnel boring machine (TBM) and to allow connection of the pipe within the tunnel to the pipe laid onshore. 

TECHNIQUE  Temporary Working Area Preparation  

• The  temporary working  area will be  fenced off using 3m high palisade fencing. 

• In designated sections on the northern side of the works, the perimeter fence will be screened with a suitable solid board to provide a visual and acoustic screen. 

• Topsoil  within  the  temporary  working  area  will  be  stripped  and stockpiled onsite. Subsoil will be stockpiled separately. 

• Any earthen (sod) banks to be impacted will be carefully dismantled with the  surface  sods  being  stored  separately  and  maintained  during construction.  Those  earthen  (sod)  banks  which  do  not  require  to  be dismantled will be fenced off to protect them from construction traffic.  

• A  running  track,  consisting  of  geotextile  overlaid  with  materials excavated during  LVI  construction and/or  locally  sourced  stone, will be constructed to allow access for construction plant. 

• Drains within  the  temporary working  area will be  identified by marker posts  

• Interceptor  drains  and  flume  pipes  will  be  installed,  as  necessary,  to isolate and divert surface water arising off site to receiving waters.   

 

Page 18: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Onshore Pipeline Construction Glengad Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMPMethod Statement  Revision: 01 Page 2 of 6

• Limited access across the temporary working area for landowners will be provided  for by agreement with  the  landowner and when  construction works allow safe access. 

Pipeline Construction 

• All pipelines will be strung out, welded and tested prior to excavating the trench. 

• The pipeline trench will be excavated and the material stockpiled onsite. Should  any  distinct  layers  in  the  subsoil  be  encountered,  they  will  be excavated and stockpiled separately.  

• The excavated  trench will be dewatered  if required,  from a sump box at the lowest point.  

• The pipe sections will be lowered into the trench by means of side booms and  inspected and backfilled with  selected  imported material. The main body of  the  trench will be backfilled with materials excavated  from  the trench. All soil  layers will be reinstated  in reverse order to the manner  in which they were excavated. 

 Reinstatement  As  stated  previously,  the  temporary  working  area  and  running  track  will  be maintained until after completion of the tunnel and associated tie‐in works. Some reinstatement of the pipeline trench may be permitted after pipeline installation. Final reinstatement will be as follows; • The temporary running track will be removed off site for re‐use, if 

appropriate and its route reinstated. 

• The site will be reinstated using the stockpiled topsoil and vegetation will be allowed to regenerate naturally. No seed will be imported. 

• All drains will be reinstated to their previous condition or as agreed with the relevant parties. 

• Where appropriate, simple, surface gravel field drains will be put in place to prevent water logging. 

• Earthen (sod) banks will be fully reinstated.  

• The temporary palisade fencing will then be removed off site and stock proof fencing will be erected to protect the reinstated areas. 

 Note: All movement of materials will be through the Glengad compound entrance. 

Page 19: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Onshore Pipeline Construction Glengad Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMPMethod Statement  Revision: 01 Page 3 of 6

EQUIPMENT  Excavators 

Articulated Dumptrucks 

Tracked Dumpers 

Side booms 

RESTRICTIONS  Some  sections  of  the  temporary  working  area  lie  within  the  Glenamoy  Bog Complex Candidate cSAC and are adjacent to Blacksod Bay/Broadhaven Bay pSPA. 

• Construction works will be sequenced  to  facilitate  the early commencement of reinstatement works if possible.  

• Normal  construction work  is  restricted  to between 07:00 – 19:00 weekdays and 07:00 and 16:00 Saturday.  

• Noise and vibration limits. • Lighting constraints. 

  

Page 20: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Onshore Pipeline Construction Glengad Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMPMethod Statement  Revision: 01 Page 4 of 6

POTENTIAL ENVIRONMENTAL IMPACT 

MITIGATION 

Noise, vibration and lighting Disturbance. 

• Noise and vibration will be minimised  through design, and appropriate selection of plant and equipment. 

• Proactive maintenance of machinery to minimise noise and vibration. 

• Cladding of stationary machinery such as generators. 

• Acoustic screening & fencing to minimise noise. 

• Site and mobile lighting will be designed to limit light spillage. 

Increased dust levels  • Roads/working area will be dampened down, as required to ensure dust levels due to construction activities are kept to a minimum. 

Damage to habitats, including those in the cSAC 

• Fencing  will  be  put  in  place  to  protect  the  Annex  1  dune  grassland located to the north of the proposed pipeline route. 

• The top soil removed will be carefully stored (separately from the sub‐soil) in order to maintain the seedbank.  

• No seed will be imported to prevent pollution of the native gene pool by alien genotypes. 

• Sod  banks  impacted  by  construction will  be  carefully  dismantled  and reinstated by hand. 

 

Page 21: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Onshore Pipeline Construction Glengad Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMPMethod Statement  Revision: 01 Page 5 of 6

POTENTIAL ENVIRONMENTAL IMPACT 

MITIGATION 

Disturbance to Birds and the pSPA 

 

Ground nesting birds 

• Prior  to  construction,  the  temporary  working  area  will  be mowed  in order  to discourage ground nesting birds  from attempting  to breed on the temporary working area.  

• A walkover survey will be undertaken prior  to construction  in order  to ensure  that  no  ground  nesting  birds  are  present  on  lands  to  be disturbed. 

Sand Martin  

A Sand Martin colony is located in the soft cliffs to the north and north east of  the  landfall at Glengad.   Mitigation measures as outlined below will be put in place. 

• An exclusion zone will be defined above and behind the colony such that  no  construction  activities  affect  the  existing  burrows  or threaten the stability of the cliff in which the burrows are situated.  

• Apart  from  specialists conducting monitoring, no personnel,  traffic or  construction  activities  will  be  permitted  between  the  fenced temporary working area and the cliff‐top directly above the colony. 

• Soil  stockpiles will  be  covered where  necessary with  a  fine mesh netting to prevent sand martins from making nest burrows therein. 

• Lighting will be directed downwards and be designed  to minimise light spillage outside the working area. 

pSPA 

• At  the  northern  side  of  the  pipeline  works,  visual  and  acoustic screening will be placed on the palisade fence  in designated places to prevent disturbance to birds in the pSPA. 

• Lighting will be directed downwards and be designed  to minimise light spillage outside the working area. 

 

Page 22: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Onshore Pipeline Construction Glengad Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMPMethod Statement  Revision: 01 Page 6 of 6

POTENTIAL ENVIRONMENTAL IMPACT 

MITIGATION 

Construction activities may have negative impact on local wildlife. 

 

• Pre‐construction  fauna  surveys will  be  undertaken within  1‐3 months prior to construction,  including for otters and badgers. The areas to be included  for  these  two species are approximately; 50‐100m either side of the centre  line of the pipeline for otters, and 30m either side of the centre line for badgers.  

• During construction, ramps will be provided at open trenches to provide a means of escape  for otters and badgers and other wildlife. Mammal gates will  be  provided  at  the  base  of  the  fencing  at  75m  intervals  to allow otters and badgers free access across, and a means of escape from the Temporary Working Area. 

Pollution of terrestrial and aquatic habitats  due spillage or leaks of oil/diesel from plant and equipment. 

• Machinery and plant will be inspected prior to mobilisation to site. 

• Refuelling of plant/machinery will take place in designated areas only. 

• Spill kits will be available on site. 

Release of suspended solids from the works may have negative impact on water quality. 

 

• The  LVI  outfall  will  not  be  used  for  discharge  from  dewatering  of excavations during construction works. 

• A surface water management system will be utilised to ensure removal of suspended solids prior to discharge to receiving waters at an agreed location. 

• Pumped water will be subject to sediment control measures. 

• Surface  drainage will  be  put  in  place  at  the  time  of  reinstatement  to prevent water logging where appropriate. 

 

Earthworks may disturb archaeological remains. 

• A  licensed  archaeologist will  be  on  site  to monitor  all  excavations  in previously undisturbed areas. 

Page 23: Appendix L Method Statements.pdf

CORRIB FIELD DEVELOPMENT PROJECT

Onshore Works – Aughoose

METHOD STATEMENT Rev 1

Aughoose Compound Construction

Page 24: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Aughoose Compound Construction

Draft Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 1 of 9

SUMMARY

The works involve the erection of security fencing, site enabling works and all associated works to facilitate

the erection and construction of various temporary structures required to service the tunnelling

operations and subsequent pipeline installation.

PURPOSE This method statement outlines the general method and sequence for installation

of all temporary structures and services required for tunnelling. Actual tunnel

operations and launch shaft construction is detailed elsewhere.

LOCATION Aughoose Compound, pipeline chainage 88.67 to 89.11. The Aughoose Compound

is adjacent to the Glenamoy Bog Complex cSAC (Site Code 000500) and the

Blacksod Bay/Broadhaven pSPA (Site Code 004037).

HABITATS /

CONSERVATION

STATUS

Habitats comprise non-annexed modified blanket bog habitats, eroding blanket

bog and cutover. They do not form part of any designated conservation site.

TIMESCALE

Approximately 6-8 months to construct the compound which will be operational

for a further 20 months depending on seasonal reinstatement. Construction of a

2nd

entrance (Access B) will take place approximately 10 months after the main

entrance is constructed.

TECHNIQUE The construction of the temporary compound comprises a number of main

construction operations; security fencing, entrance road construction, services

installation, initial welfare area construction, peat/stone handling area

construction, peat stockpiling, shear key construction, settlement pond

construction, site drainage installation, bulk earthworks, flexible pavement

construction, rigid pavement construction, retaining wall construction and

acoustic barrier construction. These operations are completed generally as

follows;

Security Fencing

• A 3m high palisade fence is to be erected along the site boundary with the

L1202. This will involve a period of temporary traffic control to facilitate

this operation. All traffic control measures will be in accordance with

Chapter 8 of the Dept. of Transport Traffic Signs Manual and will be of

short duration.

• A 3m high palisade fence situated on bog mats will be used where the site

boundaries are on peat (east, north and western sides).

• In designated sections, the perimeter fence will be fitted with a suitable

solid board liner to visually and acoustically screen the works in order to

minimise disturbance to birds in the pSPA and otters on shorelines and

along the Leenamore River.

Entrance Road Construction

• The site entrance road will be constructed using the stone road method of

peat replacement/displacement with selected imported locally sourced

stone.

• The stone road will consist of a peat stone matrix (approximately 0.5m of

peat left insitu with a 300mm to 500mm single size stone pushed into it,

Page 25: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Aughoose Compound Construction

Draft Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 2 of 9

forming a peat stone matrix).

• Starting at the L1202 (incorporating the traffic control measures in

Chapter 8 of the Dept. of Transport Traffic Signs Manual) the road

construction will proceed northwards into the site.

• All excavated peat will be placed directly into the peat storage area and

spread as required.

• The initial 50m will consist of a widened site entrance to facilitate the

correct sightlines and a double gate security system for deliveries, visitors,

etc.

• The entrance road will be widened inside the 2nd

access gate to allow

laden vehicles turn around once they have passed through the gate. This

widened area will be removed once the entrance road opens out into the

peat handling area.

• The stone road construction operation will also involve a temporary

surface water treatment system involving the construction of lined v*

shaped drainage channels, temporary settlement lagoons and a mobile

settlement/treatment unit. All surface water runoff from the stone road

construction will flow through the water treatment system prior to

discharge to the existing surface water ditch.

• A secondary entrance (Access B) will also be constructed using a

temporary bog mat access from the peat handling area. A temporary

ramp will be installed to allow vehicular access from Access B onto the

L1202. For the initial construction phase of the project, Access B will only

be used in the case of emergency.

* V-ditches will be lined with impermeable high density polyethylene (HDPE) liner.

Services Installation

• Trenches will be excavated within the site roads to facilitate the

installation of a surface water collection system, a watermains and

ducting for temporary power and telecoms.

• All services will be installed to relevant engineering standards using an

open trench method in the installed stone road.

• Services will be continuously tested and backfilled as excavation

progresses using the same materials excavated.

Peat/Stone Handling Area

• In order to facilitate the export of peat to Srahmore a specific vehicle

turning and loading area (peat/stone handling area) will be constructed to

separate road traffic from site traffic.

• Peat excavated from various locations of the site will be transported to

this location.

• Peat suitable for stockpiling will be separated from peat which is to be

transported to Srahmore.

• Part of this area will also be used for stockpiling stone used in

Page 26: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Aughoose Compound Construction

Draft Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 3 of 9

construction operations.

• A wheel wash facility will be installed in this area.

Initial Welfare Area Construction

• The initial welfare area and materials laydown area will be constructed

within the peat handling area on the north-west side of the main access

road.

• Welfare facilities will consist of toilets, offices, drying rooms, storage

containers, waste compactors and skips, canteens and bunded chemical

stores.

Peat Stockpiling

• The peat from the surface of the site (generally 0.6 m), including the

surface vegetation, will be stockpiled onsite for reinstatement after

tunnelling completion.

• It should be noted that an additional quantity of peat will be stored onsite

for reinstatement of locations where mineral soil will be excavated.

• Peat stockpiling will involve the construction of a temporary bog mat

access into the designated areas.

• Peat stored in the peat handling area will be transferred to the peat

storage area.

• The vegetation layer will be placed (roots downwards) on top of the stored

peat so that it can continue to grow during storage and be available for

subsequent reinstatement.

• The bog mat access will be removed as the area fills and will be reinstalled

again during reinstatement operations.

Shear Key Construction

• In order to mitigate against geotechnical risks associated with peat

excavation (e.g. slippage of peat), a shear key will be installed around the

perimeter of the tunnelling compound by means of the stone road

method.

• This will be completed prior to any excavation of the main body of peat

from the tunnel compound.

• Peat excavated during shear key construction will be brought to the peat

handling area prior to stockpiling in the peat storage area or transport to

Srahmore.

Settlement Lagoon Construction

• Prior to excavation of the main body of peat (bulk earthworks), a

settlement lagoon will be constructed at the low point of the site.

• The lagoon will be constructed and lined/sealed with a HDPE liner. All

water collected in the various drainage ditches and pipes will flow to this

lagoon.

Page 27: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Aughoose Compound Construction

Draft Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 4 of 9

• An additional water tank will be constructed at the same time as the

settlement lagoon to provide additional storage capacity if required.

• Settlement ponds will be covered by firm wire mesh (WeldMesh) of small

enough mesh size to prevent access to birds.

Site Drainage Installation

• A surface water drainage system will be installed in the roads, shear keys

and main site as each section of works progresses.

• The drainage system will consist of gullies, underground pipework,

manholes and a number of lined open ditches.

• This system will collect all rainwater by gravity flow to the settlement

lagoon, passing through a bypass separator.

Acoustic Barrier Construction

• The entire tunnelling compound will be surrounded by an acoustic fence.

• Acoustic fence construction will progress in conjunction with shear key

construction.

• This fence will be in place prior to commencement of bulk earthworks.

Bulk Earthworks

• Once the shear keys, settlement lagoon and overground water storage

tank have been installed bulk excavation of the main body of peat will

commence.

• This will be completed by means of excavators and dumptrucks and will

coincide with the replacement of the peat by imported fill.

• In general, an approximate 0.5m depth of peat will be left insitu to form

the peat stone matrix, the surface peat will be stored onsite and the

remainder transported off site.

• The peat will be completely removed where required in settlement critical

locations.

Flexible Pavement Construction

• A flexible bitumen bound surface will be constructed over the majority of

the site (i.e access roads, shear keys etc).

• This flexible pavement will consist of imported stone and bitumen bound

macadam materials to NRA specifications.

• This will provide an impervious surface to reduce run off from the stone

roads and will provide an easily maintained clean surface for tunnelling

works.

Rigid Pavement Construction

• In certain locations on the site the standard flexible pavement will be

replaced by a rigid pavement.

Page 28: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Aughoose Compound Construction

Draft Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 5 of 9

• The rigid pavement will be constructed from reinforced concrete and will

generally form foundations and bunded areas at various locations.

Retaining Wall Construction

• At various locations retaining walls will be installed where a level platform

or a gradual fall is required for tunnelling works.

• These walls will be constructed from precast items where possible for

future recycling. Where precast structures cannot be used, in situ concrete

walls will be constructed.

Stringing Area

• Once tunnelling operations commence the stringing area construction can

begin.

• This will be completed by means of excavators and dumptrucks and will

coincide with the replacement of the peat by a mixture of tunnel arisings

and imported fill.

• In general, an approximate 0.5m depth of peat will be left in situ to form

the peat stone matrix, the surface peat and vegetation layer will be stored

on site, as for the tunnelling compound, and the remainder transported off

site.

• A stone road will be constructed from the stringing area over to access B,

replacing the original bog mat emergency access. This road will be

constructed 10 months after initial site mobilisation.

Reinstatement

• Once all tunnelling, pipelaying, testing and commissioning are complete

the entire compound will be reinstated with a layer of peat which was

previously stored in the peat storage area.

• All construction materials that can be reused (fencing, bogmats, precast

retaining walls, underground pipework, etc.) will be carefully dismantled

and transported off site.

• Other materials such as surplus stone will be returned to local quarries or

used elsewhere in the locality if possible.

• Materials which cannot be immediately reused (i.e. tarmacadam, concrete

etc) will be transported to a recycling facility.

• Any materials which do not fit the above criteria will be removed to a

licenced waste facility.

• In locations where peat was entirely removed during construction (e.g

crane locations) the imported fill will be excavated and a 1m layer of peat

will be installed on top of the mineral soil level and the fill placed back on

top of this peat layer again.

• The top 300mm to 500mm of stone will be excavated and removed off

site.

• Finally, the entire area will be covered with a layer of peat from the peat

storage area with the site being returned to its original levels in

preparation for habitat restoration.

Page 29: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Aughoose Compound Construction

Draft Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 6 of 9

• The surface vegetation layer will then be reinstated under the direction of

the Project Ecologist.

• Once the area is reinstated, the original drainage system will be reinstated

and the perimeter security fence will be removed off site.

• Stock proof fencing will be erected to protect the reinstated areas.

EQUIPMENT LGP Excavators Tracked Excavators

Articulated Dumptrucks Wheeled Excavators

Front Loading Dumpers Tracked Dumpers

Articulated Trucks (road going) Road sweepers

Water Bowsers Tractors

Rollers Vibrating wackers

Concrete pumps Cranes

Loadalls Generators

Lighting towers Pavers

Chip spreaders Tar sprayers

Tack coaters Pitch cart

Thermoplastic lining trucks

Turving bucket (for use during reinstatement)

RESTRICTIONS • Working adjacent to:

� Blacksod Bay/Broadhaven pSPA.

� Glenamoy Bog Complex cSAC.

• Normal construction work will take place between 07:00 and 19:00

weekdays and 07:00 and 16:00 on Saturday. Only essential works will

carried out between the hours of 19:00 and 07:00.

• Noise and vibration limits.

• Lighting constraints.

Page 30: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Aughoose Compound Construction

Draft Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 7 of 9

POTENTIAL

ENVIRONMENTAL

IMPACT

MITIGATION

Noise, Vibration,

Lighting - Disturbance

• Noise and vibration will be minimized through design, and appropriate

selection of plant and equipment.

• Proactive maintenance of plant and machinery.

• Cladding of stationary machinery such as generators.

• A 3m high non-transparent noise barrier will be installed around the

perimeter of the tunnelling compound.

• Mobile and fixed site lighting will be designed to limit light spillage.

Increased dust levels • Roads/working area will be dampened down, as required to ensure

dust levels due to construction activities are kept to a minimum.

Potential for indirect

impact on habitats and

species in the adjacent

cSAC /pSPA

• Robust measures (see below) will be implemented to prevent

sedimentation and pollution of the adjacent Annex I estuarine and

interidal habitats in Sruwaddacon Bay and species which depend upon

them, including salmon.

Direct impact on

habitats as a result of

construction activities

Habitat reinstatement and vegetation restoration

• During the initial site establishment works, plant material will be

harvested from areas which will be impacted during construction. This

will be removed from the site for propagation and for use during

reinstatement.

• The surface layer of peat will be stored on site. The stripped vegetation

layer will be placed, right way up – roots downwards, on top of the

peat in the peat storage areas for use in reinstatement.

• If required, stored peat will be covered with Geo-jute to stabilise it and

to encourage vegetation growth following storage.

• During re-instatement, the entire area will be re covered with a layer of

peat, and the vegetation from the top of the peat storage areas will be

replaced under direction from the Project Ecologist.

• A phased re-instatement programme will be undertaken over 1 to 5

years.

• Once the reinstated peat has stabilised, peat forming conditions will be

created by means of pool creation and Sphagnum inoculation.

• Native scrub species will be planted in places in the reinstated peat

storage areas.

Construction activities

may affect local wildlife

(otters and badgers)

• Fencing for the tunnelling compound will be fully wildlife proofed to

prevent mammals entering site.

• Acoustic and visual screening on fences will minimise disturbance to

otters on shorelines of the bay.

• During construction, ramps will be provided at any open trenches

accessible to wildlife to provide a means of escape.

• Work activities will be limited to between the hours of 07:00 and 19:00.

• Night caps will be placed over all pipe ends.

Page 31: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Aughoose Compound Construction

Draft Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 8 of 9

POTENTIAL

ENVIRONMENTAL

IMPACT

MITIGATION

Construction activities

may affect amphibians

• Any frogs (adults, spawn and tadpoles) identified prior to, and during,

construction will be translocated under licence to a suitable location.

• Habitat reinstatement will re-create the former channel and drain

systems so that frogs may use these post construction.

Disturbance to birds in

the adjacent pSPA and

birds on migration

• Acoustic screening barriers will be installed on the temporary

perimeter palisade fencing.

• Solid acoustic fencing will be used within the compound to minimise

noise.

• Lighting will be designed to minimise light leakage into the pSPA (light

intensity no more than 0.3 lux at the shoreline).

• Green (beacon) lighting will be installed on tall structures and uprights

to reduce collision risk.

• Settlement ponds will be covered by firm wire mesh (WeldMesh) of

small enough mesh size to prevent access to birds.

• Robust sediment and pollution control measures to prevent impact on

prey species in the Bay (benthic macrofauna and fish species).

Disturbance to birds in

the locality (other than

in the pSPA)

• A walkover survey will be undertaken prior to construction in order to

ensure that no ground nesting birds are present on lands to be

disturbed.

• Vegetation restoration and planting of native scrub species during

reinstatement.

Pollution of

Land/Water/ cSAC and

pSPA habitats & species

due spillage or leaks of

oil/diesel from plant

and equipment

• Machinery and plant will be inspected prior to mobilisation to site.

• Refuelling of plant/machinery will only take place in designated areas.

• Spill kits will be available on site.

Release of suspended

solids from the works

could have negative

impact on water

quality, cSAC and pSPA

habitats & species

therein including

salmon

• The surface water treatment system will comprise a bypass separator

for removal of hydrocarbons followed by a settlement lagoon for

removal of suspended solids and the installation of a filtration system

for finer particles.

• V-ditches will be installed up slope and down slope of peat storage

areas.

• In drain mitigation will be placed as required to reduce silt impact on

associated waterways.

• Culverts will be placed at locations where access roads must cross

existing drains and ditches.

• Concrete wash system will be installed.

• Wheel wash system will be installed.

• Pumped water will be subject to sediment control measures.

• Any concrete poured in situ will be covered to prevent run off during

rainfall as per industry best practice.

Page 32: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Aughoose Compound Construction

Draft Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 9 of 9

POTENTIAL

ENVIRONMENTAL

IMPACT

MITIGATION

Change in local

hydrology/hydro-

geological regimes.

• An approximate 500mm depth of peat will be left in situ to form a peat

stone matrix in all areas except those classified as settlement critical.

• The stone for constructing the stone road will be locally sourced and

carefully selected to ensure that it is appropriate for the local

environment within the peat.

Works may disturb

archaeological remains

• A licensed archaeologist will be on site to monitor all peat excavation

and tunnelling activities.

Page 33: Appendix L Method Statements.pdf

CORRIB FIELD DEVELOPMENT PROJECT

Onshore Works – Aughoose

METHOD STATEMENT Rev 01

Construction of Start Shaft and Ramp

Page 34: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Construction of tunnel start shaft and ramp

Draft Environmental Management Plan Document No: COR-14-OP-SH-0000_SEPIL EMP

Method Statement Revision: 01 Page 1 of 5

SUMMARY

This document defines the construction methodology and sequence of works for the construction of the

starting shaft and ramp in the Aughoose Compound, for the Corrib Onshore PIpeline. In order to facilitate

commencement of the tunnelling works it is necessary to excavate a shaft and ramp into which the Tunnel

Boring Machine (TBM) will be lowered. The TBM will be lowered in sections into the shaft/ramp for

assembly prior to commencement of tunnelling.

PURPOSE The start shaft and ramp will provide the commencement point for tunnelling works

and will serve as the main access corridor between the tunnel and the surface for

transport of material, plant and labour into and out of the tunnel.

LOCATION The start shaft and ramp will be located in the Aughoose Compound at chainage

88.77. The start shaft is approximately 18m long x 9m wide and 12m deep, the

adjoining ramp is approximately 75m long x 6m wide and ranging in depth from 6m to

12m below ground level. The Aughoose Compound is adjacent to the Glenamoy Bog

Complex cSAC (Site Code 000500) and the Blacksod Bay/Broadhaven pSPA (Site Code

004037).

HABITATS /

CONSERVATION

STATUS

The habitat present at the starting shaft is non-annexed eroding blanket bog. The

Aughoose compound is not in any designated conservation site.

TIMESCALE The duration of construction of the start shaft and ramp is approximately six to seven

months. It is anticipated that construction will take place in 2011/2012.

CONSTRUCTION

METHODOLOGY

The construction of the start shaft and ramp is based on the use of a sheet piling

system with the placement of concrete for support in the lower part of the

excavation.

Under this method of construction the sequence of construction would be as follows:

• In the deeper parts of the start shaft/ramp, where it is required to install

sheet piles through bedrock, the bedrock will be pre-drilled in order to

facilitate the installation of the piles.

• Piles will then be installed to the required depth using appropriate drilling

and driving equipment.

• Commence with initial excavation of material from within the footprint of

the sheet piles (to an initial depth of approximately 2m below the original

ground level).

• Install upper level props or anchors as required to brace the sheet piles.

• Continue with excavations down to bedrock level.

• Install anchors at low level as required to brace the sheetpiles.

• Commence with breaking and excavating of bedrock to the required level.

• Place and construct reinforced concrete support in the lower part of the

excavation.

• Construction of the TBM soft eye / sealing body.

Piling Works

• The ground conditions expected to be encountered in the construction of the

Page 35: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Construction of tunnel start shaft and ramp

Draft Environmental Management Plan Document No: COR-14-OP-SH-0000_SEPIL EMP

Method Statement Revision: 01 Page 2 of 5

shaft/ramp will consist of an upper layer of engineering fill, mineral soil and

overlying bedrock. It is expected that bedrock will be encountered along the

entire length of the start shaft and ramp. As such the rock will be required to be

predrilled prior to the installation of the piles.

• The size and geometry of the piles installed through the bedrock will be varied to

suit the installation process and the requirements of the detailed design. Where

piles are installed into bedrock it is envisaged that the piles will terminate below

the base of the excavation.

• Following the initial installation of the piles, excavation will commence. As these

progress the sheet piles will have to be propped. To do this a series of walers will

be lifted into position inside the excavation and secured in place onto the

sheetpiles once the upper 2m of excavation has been carried out.

• Where upper level anchors are required in the walls then they will be installed

prior to the positioning of the walers and later tensioned following the

installation of the walers. Lower level anchors may also be required depending

upon the outcome of the detailed design.

Excavations

• Upon installation of the sheet piles it will be required to excavate the material

from within the area enclosed by the sheet piles. Excavation will be carried out in

various stages. Initially, the upper 2m of material will be removed using an

excavator(s) after which a series of struts/wailers will be installed to support the

upper level of the sheet piles. The struts will act as props spanning across the

excavation – props will be secured to walers placed on the face of the sheet piles

within the excavation.

• If necessary, a series of anchors will be installed as described above. Excavations

will then re-commence and be progressed down to bedrock.

• Where bedrock level is reached within the excavation it may be necessary to

install additional anchors through the sheet piles in order to ensure the stability

of the sheet pile structure prior to works progressing deeper. These anchors will

be installed using a drill rig working within the excavation.

• Following the installation of the anchors, excavation for the lower section of the

shaft/ramp will recommence. In order to remove the bedrock from the lower

level of the excavation, excavator(s) will be fitted with hydraulic breaker(s) which

will be used to break out the rock. Depending on the integrity of the rock

encountered additional excavation measures may be required (such as pre-

drilling) to facilitate the extraction/removal of rock.

• As and when sufficient volumes of rock have been broken, an excavator(s) will

remove the broken rock from the excavation. A crane may also be utilised to assit

with the removal of rock from within the lower level of the shaft/ramp.

• Groundwater ingress into the excavation will be controlled by pumping from

sumps located in the floor of the excavation. Water from pumps will be

Page 36: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Construction of tunnel start shaft and ramp

Draft Environmental Management Plan Document No: COR-14-OP-SH-0000_SEPIL EMP

Method Statement Revision: 01 Page 3 of 5

discharged into the settlement lagoon or to an alternative temporary

storage/treatment facility, if necessary.

• Excavated material brought to the surface will generally be loaded into a dump

truck and either reused on site or transported to a temporary stockpile within the

Aughoose compound from where it will be transported off site.

Placement of Concrete

• Concrete will be required to support the piles in the lower part of the excavation

(through the bedrock) and also for the construction of the required slab at the

bottom of the excavation.

• Upon completion of the excavation works to the required level, reinforced

concrete, 0.5 to 1.0 m thick will be constructed in situ at the bottom of the shaft

and ramp. To prevent uplift of the concrete it may be required to install a series

of rock anchors into the bedrock underlying the reinforced concrete slab. These

anchors will be installed using a drill rig working from within the partially

completed ramp/shaft excavation.

• Low strength concrete will be used to form the TBM soft eye / sealing body.

Reinstatement

• Once the onshore pipeline and associated services have been installed in the

tunnel and the tunnel fully grouted, the start shaft and ramp will be backfilled.

The pipeline and associated services will be backfilled with suitable bedding and

surround material.

• The remaining excavation will be backfilled with suitable material compacted in

layers to within 1m of the underside of the original peat depth where a 1m layer

of low permeability reworked peat will be placed. Further backfilling of suitable

compacted material will continue to the underside of the surface reinstatement

layer, which will comprise peat.

• As backfilling progresses upwards, sheet piles left in situ will be cut to a depth of

1m below finished ground level. Anchors used for bracing of the sheet piles will

be distressed and props/walers removed.

• Reinstatement of the peat layer will be in accordance with the method statement

for the Aughoose Compound.

• The surface vegetation layer will then be reinstated under the direction of the

Project Ecologist.

EQUIPMENT Piling rigs Hydraulic breakers

Mobile cranes Dump trucks

Telehandlers/ Lifting and loading

devices

Rotary drilling equipment

Excavators Drilling rigs for anchor installation

Various pumps Miscellaneous small tools

Page 37: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Construction of tunnel start shaft and ramp

Draft Environmental Management Plan Document No: COR-14-OP-SH-0000_SEPIL EMP

Method Statement Revision: 01 Page 4 of 5

Noise, vibration and lighting. • Noise and vibration will be minimised through design, and

appropriate selection of plant and equipment.

• Proactive maintenance of machinery.

• Cladding of stationary machinery such as generators.

• Acoustic screening & fencing.

• Site and mobile lighting will be designed to limit light spillage.

Increased dust levels • Roads/working area will be dampened down, as required to ensure

dust levels due to construction activities are kept to a minimum.

Potential for indirect impact

on habitats and species in the

adjacent cSAC /pSPA

• Robust measures (see below) will be implemented to prevent

sedimentation and pollution of the adjacent Annex I estuarine and

intertidal habitats in Sruwaddacon Bay and species which depend

upon them, including salmon.

Direct impact on habitats as a

result of construction

activities

• Careful reinstatement of the area will be carried out following the

completion of the tunnelling works.

• Habitat reinstatement and vegetation restoration will be carried out

as set in the Aughoose Compound Method Statement.

Disturbance to birds in the

adjacent pSPA and birds on

migration

• Mitigation measures, as set out for the Aughoose Compound as a

whole, will be implemented

Disturbance to birds in the

locality (other than in the

pSPA)

• A walkover survey will be undertaken prior to construction in order

to ensure that no ground nesting birds are present on lands to be

disturbed.

RESTRICTIONS Working adjacent to:

• Blacksod Bay/Broadhaven pSPA

• Glenamoy Bog Complex cSAC

Noise and vibration limits

Lighting constraints

Normal construction works will be restricted to between the hours of 07:00 and 19:00

weekdays and 07:00 and 16:00 Saturday.

POTENTIAL ENVIRONMENTAL

IMPACT

MITIGATION

Page 38: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Construction of tunnel start shaft and ramp

Draft Environmental Management Plan Document No: COR-14-OP-SH-0000_SEPIL EMP

Method Statement Revision: 01 Page 5 of 5

Pollution of Land/Water/ cSAC

and pSPA habitats & species

due spillage or leaks of

oil/diesel from plant and

equipment.

• Machinery and plant will be inspected prior to mobilisation to site.

• Refuelling of plant/machinery will take place in designated areas

only.

• Spill kits will be available on site.

Release of suspended solids

from the works could have

negative impact on water

quality, cSAC and pSPA

habitats & species therein

including salmon.

• Groundwater which may ingress into the excavation will be

controlled by setting up temporary sumps in the floor of the

excavation to dewater the excavation. Pumped water will be subject

to sediment control measures.

• A surface water managment will be utilised to ensure removal of

suspended solids prior to discharge to receiving waters at an agreed

location.

• Please refer to the Aughoose Compound Method Statement

Earthworks may disturb

archaeological remains

• A licensed archaeologist will be on site to monitor all excavations in

previously undisturbed areas.

Page 39: Appendix L Method Statements.pdf

CORRIB FIELD DEVELOPMENT PROJECT

Onshore Works – Construction of Tunnel

METHOD STATEMENT Rev 01

Tunnelling Operations

Page 40: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Tunnelling Operations

Draft Environmental Management Plan Document No: COR-14-OP-0000_SEPIL EMP

Method Statement Revision: 01 Page 1 of 6

SUMMARY

This document describes the construction of the 4.9km segment lined tunnel in which the Corrib Onshore

Pipeline between Glenagd and Aughoose will be installed.

PURPOSE A 4.9km segment lined tunnel will be constructed using a Tunnel Boring Machine

(TBM) between Aughoose and Glengad.

LOCATION The segment lined tunnel will be constructed from the starting shaft located at

Aughoose (approx. Chainage 88.77). From there, the pipeline route traverses

(underneath) the Glenamoy Bog Complex cSAC and the Blacksod Bay/Broadhaven

pSPA at Sruwaddacon Bay in a north-westerly direction towards Glengad for

approximately 4.9km, where the reception shaft (Chainage 83.88) will be

constructed in the cSAC. The tunnel will be constructed with a minimum depth of

cover of 5.5m.

TIMESCALE

It is anticipated that the tunnelling process will take approximately 15 months to

complete (at an average of 11m/ day).

The tunnelling construction will be carried out on a 24 hours a day/ 7 days a week

basis.

Other associated works, such as material transport and tunnel arisings disposal will

be executed between the hours of 07:00 and 19:00 weekdays and 07:00 and 16:00

Saturday.

CONSTRUCTION

METHODOLOGY

The scope of works for the construction of the segment lined tunnel can be

generally divided into the following work steps:

• Construction of the 4.9km tunnel including access ramps, starting shaft

and reception shaft;

• Installation and testing of the 20 inch gas pipeline and services in the

tunnel; and

• Grouting of the tunnel and re-instatement of the shafts.

Further details on the construction of the start and reception shafts are provided in

other method statements.

• Prior to the commencement of tunnelling, the Aughoose compound is

constructed and associated utility systems, e.g. an appropriate surface water

management system, are made available. A separate method statement

describes the construction of the Aughoose compound.

• Plant and equipment required for the tunnelling, including the TBM, are then

mobilised to site.

• All TBM assembly and material supply will be managed from the starting shaft

in Aughoose.

Page 41: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Tunnelling Operations

Draft Environmental Management Plan Document No: COR-14-OP-0000_SEPIL EMP

Method Statement Revision: 01 Page 2 of 6

Plant and Equipment

The main plant and equipment required for the tunnelling process include:

• Gantry crane;

• Grout mortar Silos

• Slurry treatment plant

• Bentonite tanks and silos

• Freshwater tank

• Water storage tanks

• Filter press

• Power generation units

Following the installation of all the required plant and the set up of the site

compound and function testing the tunnelling process will commence.

Tunnel construction:

• The tunnel will be constructed using a slurry shield tunnelling method which

involves the drilling/boring of the soil face using a TBM and then installing

precast concrete segments as the TBM progresses.

• The cutting wheel at the front of the TBM tunnels into the ground. The TBM is

controlled by the steering cylinders within the TBM which pushes the cutter

head in the desired direction.

• Power switchboards, hydraulic and logistic units are all installed near the TBM

on a number of back-up trailers. These trailers (typically of 8 – 10 m length) are

interconnected and pulled by the TBM through the tunnel.

• Concrete segments are transported to the front of the tunnel on a train that

runs on tracks within the tunnel during construction. These tracks are installed

in parallel to the tunnelling operation on one of the TBM back-up trailers.

• The stacked segments are transported through the tunnel to the tail skin by a

supply system with train cars and cranes. An erector unit located within the

TBM is used to pick up the segments from the train and it installs the segments

into the designated position. Once installed they are bolted to the already

installed ring and segments.

• Concrete segments which are erected inside the back end of the tunnelling

machine (the tail skin) and assembled to form a complete segment ring which

is connected, grouted and when in position acts as the tunnel lining.

• After completion of one segment ring, all jacking cylinders are extended for a

further advance cycle. By using this method of tunnel lining, the already built

concrete tunnel remains stationary and serves as an abutment for the advance

of the TBM. Grout (annulus grouting) is injected into the overcut behind the

installed segment rings, which is created by the cutting wheel during

excavation.

Page 42: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Tunnelling Operations

Draft Environmental Management Plan Document No: COR-14-OP-0000_SEPIL EMP

Method Statement Revision: 01 Page 3 of 6

• Slurry lines for spoil transport, air duct for ventilation, pressurised air supply

and power/communication cables are installed inside the tunnel to support

the drilling process.

• Drilling fluid consisting of a suspension of water and bentonite (bentonite

slurry) is used for lubrication and cooling of the cutting head, removal of

cuttings and stabilisation of the cutting face.

• Bentonite slurry suspension will be pumped through the feeding pipe into the

TBM working chamber. It is mixed with the excavated soil / rock and pumped

back through the slurry discharge pipe to the separation plant at Aughoose

Compound. The soil is separated and the recycled bentonite slurry suspension

pumped through the tunnel back into the TBM working chamber.

• The excavated materials from tunnelling (tunnel arisings) is separated from the

drilling fluid/bentonite slurry mixture using a separation plant where shakers

are deployed and stockpiled temporarily within the Aughoose Compound in

designated area.

• The surplus bentonite slurry will be removed and dewatered in a filter press.

After being treated in the filter press the filter cake is dry enough for

transportation to a licensed waste facility.

Mixing of Grout Mortar

• Grout mortar will be used for grouting the annulus of the tunnel (voids behind

the segments). The grout mortar will also be used for filling the tunnel

following the installation of the pipeline and services.

• Mixing of grout will take place in a controlled and contained environment

using automated mixing tanks located in the Aughoose Compound. Grout silos,

located adjacent to the mixing tanks, will be filled with dry cement brought in

by container truck. The cement will be ‘blown’ into the storage silos from the

container truck using a sealed unit and stored there for mixing as required

during the works.

• The mixing operation will involve the grouting mix and water. This is then

pumped in containers which are transferred to the tunnel using the tunnel

railway.

• To prevent ingress of water and grout into the TBM, brush seals between the

tail skin and the erected segments are filled with grease.

Demobilisation and Reinstatement:

• When the TBM reaches the receiving shaft in Glengad, it will be recovered and

the installation of the gas pipeline and services can start. Installation of the

pipeline and services is from Aughoose.

Page 43: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Tunnelling Operations

Draft Environmental Management Plan Document No: COR-14-OP-0000_SEPIL EMP

Method Statement Revision: 01 Page 4 of 6

• Demobilisation of the TBM will be carried out at the Glengad site. Tunnelling

equipment, such as separation plant, bentonite treatment plant, grout silos,

etc. at the Aughoose Compound will be demobilised in stages upon completion

of the significant elements of the works.

• Once the onshore pipeline and associated services have been installed in the

tunnel and the tunnel fully grouted, the start shaft and ramp will be backfilled.

Backfilling of the Tunnel & Pipeline Installation:

• The grout mortar will also be used for filling the tunnel following the

installation of the pipeline and services.

• The equipment associated with this backfilling operation will be located at the

Aughoose compound and the backfilling operation will be carried out from one

side only by pumping the backfilling mix through the pre-installed grouting.

EQUIPMENT Tunnel boring machine (TBM) Filter press

TBM back-up system Supply system, feeding pipes / cables

Tunnel segments Control Station

Track and train system Lifting and loading devices

Separation plant Tanks

Bentonite handling unit Gantry crane

Bentonite silos Mortar silos

RESTRICTIONS Tunnel will be constructed underneath:

• Blacksod Bay/Broadhaven pSPA

• Glenamoy Bog Complex cSAC

Noise and vibration limits

Lighting constraints

Non-essential activities may require to be suspended at the Aughoose Compound

on Easter Sundays during periods when Mass is taking place at the nearby

commemorative site.

Page 44: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Tunnelling Operations

Draft Environmental Management Plan Document No: COR-14-OP-0000_SEPIL EMP

Method Statement Revision: 01 Page 5 of 6

POTENTIAL

ENVIRONMENTAL

IMPACT

MITIGATION

Release of bentonite to

environment

• The composition of slurry is designed to suit the geotechnical conditions.

• Bentonite pressure and rate of usage will be monitored constantly. In the

event of bentonite release the bentonite operating pressure will be reduced

immediately to reduce bentonite loss.

• Bentonite sensors will be installed in the excavation chamber. The chamber

can be separated from the slurry system.

• The TBM speed will be altered to suit the ground conditions.

• In the unlikely event of a bentonite release the design and operation of the

TBM will limit the volume to 7m3.

• Measures will be implemented at Aughoose and Glengad to prevent any

egress of bentonite into watercourses leading into the cSAC /pSPA. A hard

standing area for bentonite handling plant will be located in the Aughoose

Compound. There is a separate drainage system where the run-off is

collected and pumped into a used bentonite tank. During removal of the

TBM at Glengad, the shaft will be partially flooded. This water will be

contained within the shaft and removed offsite for treatment at an

appropriate licensed water treatment facility. Robust measures will be

taken to ensure there is no bentonite release during the loading, handling

and transport of the TBM in Glengad.

Noise, vibration and

lighting disturbance.

• Noise and vibration will be minimised through design, and appropriate

selection of plant and equipment.

• Proactive maintenance of machinery.

• Cladding of stationary machinery such as generators and separation plant.

• Acoustic screening & fencing.

• Site and mobile lighting will be designed to limit light spillage.

Page 45: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Tunnelling Operations

Draft Environmental Management Plan Document No: COR-14-OP-0000_SEPIL EMP

Method Statement Revision: 01 Page 6 of 6

POTENTIAL

ENVIRONMENTAL

IMPACT

MITIGATION

Disturbance to birds in

the adjacent pSPA and

birds on migration

• Acoustic screening barriers will be installed on the temporary perimeter

palisade fencing.

• Solid acoustic fencing will be used within the compound to minimise noise.

• Lighting will be designed to minimise light leakage into the pSPA (light

intensity no more than 0.3 lux at the shoreline).

• Green (beacon) lighting will be installed on tall structures and uprights to

reduce collision risk.

• Settlement ponds will be covered by firm wire mesh (WeldMesh) of small

enough mesh size to prevent access to birds.

• Robust sediment and pollution control measures to prevent impact on prey

species in the Bay (benthic macrofauna and fish species).

• See LVI, Glengad Compounds and Access Road MS for details of further

mitigation.

Potential for indirect

impact on habitats and

species in the adjacent

cSAC /pSPA

• Robust measures (see below and Aughoose Compound Construction MS)

will be implemented to prevent sedimentation and pollution of the adjacent

Annex I estuarine and interidal habitats in Sruwaddacon Bay and species

which depend upon them, including salmon.

Pollution of

Land/Water /cSAC and

pSPA habitats & species

due spillage or leaks of

oil/diesel from plant

and equipment.

• Machinery and plant will be inspected prior to mobilisation to site.

• Refuelling of plant/machinery will take place in designated areas only.

• Spill kits will be available on site.

Release of suspended

solids from the works

could have negative

impact on water quality

• A surface water management system will be utilised to ensure removal of

suspended solids prior to discharge to receiving waters at an agreed

location.

• Pumped water will be subject to sediment control measures.

Earthworks may disturb

archaeological remains

• A licensed archaeologist will be on site to monitor all excavations of the

tunnel start and reception shafts.

• In the event of an archaeological find the archaeologist may have work on

the site stopped, pending a decision as to how best to deal with the

archaeology by the Department of Arts, Heritage and Gaeltacht Affairs

(DAHGA) (previously assigned to the Department of Environment, Heritage

and Local Government (DoEHLG).

Page 46: Appendix L Method Statements.pdf

CORRIB FIELD DEVELOPMENT PROJECT

Onshore Works – Construction of Tunnel

METHOD STATEMENT Rev 01

Bentonite Handling and Monitoring

Page 47: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Bentonite Handling and Monitoring

Draft Environmental Management Plan Document No: COR-14-OP-0000_SEPIL EMP

Method Statement Revision: 01 Page 1 of 6

SUMMARY

This document describes the handling and monitoring of bentonite during tunnelling for the Corrib

Onshore Pipeline project.

WHAT IS

BENTONITE?

Bentonite is a natural product comprising very fine inert clay which is widely used

in an aqueous suspension in tunnelling construction projects.

Bentonite is considered by the OSPAR Commission* as being a substance that

Poses Little or No Risk to the Environment (PLONOR)

PURPOSE The Corrib Onshore Pipeline will be installed into a 4.9km segment lined tunnel.

4.6km of this tunnel will be constructed beneath Sruwaddacon Bay which

comprises part of the Glenamoy Bog Complex cSAC and the Blacksod

Bay/Broadhaven pSPA.

A tunnel boring machine (TBM) will be used to construct the tunnel by excavating

material in front of the TBM, behind which concrete segments will be installed.

A drilling fluid consisting of a suspension of water and bentonite (bentonite

slurry) is used for lubrication and cooling of the cutting head, removal of cuttings

and stabilisation of the cutting face.

BENTONITE USE • The bentonite slurry will be pumped to the TBM via pipes within the tunnel

where it is introduced at the cutting face. As the soil is excavated by the TBM,

it passes through a crusher at the rear of the cutting head.

• All material is reduced to a maximum size of approximately 40mm and then

hydraulically transported as a bentonite slurry to the surface via the slurry

discharge line.

• The bentonite slurry containing the excavated material is pumped back to the

seperation plant located at the Aughoose Compound.

• Excavated materials from tunnelling (tunnel arisings) will be separated from

the bentonite slurry mixture and stock-piled temporarily on the site in

purpose designated area.

• Recycled slurry will be pumped back to the TBM excavation chamber by

means of feed pumps located at the separation plant and in the tunnel where

the process is repeated.

• Solids will be removed from the excess bentonite slurry in a filter press and

the solid cake (filter press outcome) will be disposed of at licensed waste

facility. Process water from the filter press requiring disposal is tankered

away and disposed off at a licensed water treatment plant.

BENTONIITE

HANDLING

Bentonite handling will occur in the following areas: and the process is outlined in

Figure 1 below :

Bentonite mixing plant

• Bentonite will be delivered as powder to the Aughoose Compound where it

Page 48: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Bentonite Handling and Monitoring

Draft Environmental Management Plan Document No: COR-14-OP-0000_SEPIL EMP

Method Statement Revision: 01 Page 2 of 6

will be stored in silos.

• The supply of dry bentonite powder to the mixing plant is fully automated via

a closed screw conveyor system. Bentonite will be mixed with water in the

bentonite mixing plant prior to being pumped to the fresh bentonite storage

tank. This process will be carried out within a closed system.

Fresh Bentonite Storage Tank

The fresh bentonite storage tank is used to store the drilling fluid before it is used

at the TBM tunnelling process.

Separation Plant

• The purpose of the separation plant is to separate the excavated material

from the transporting medium (bentonite slurry).

• The separation plant is the central facility where the bentonite slurry coming

from the TBM is treated and recycled. It is then fed back to the header tank

(linked to the fresh bentonite storage tank) through the slurry circuit to the

TBM.

Filter Press

• The function of the filter press is to separate the remaining solids from the

used slurry from the separation plant.

• After being treated in the filter press the solids are stored prior to been

disposed off at a licensed waste facility.

• The remaining liquid will be disposed of at licensed wastewater treatment

plant.

* OSPAR commission: Administrator of the Oslo and Paris Conventions for the protection of the marine environment

of the North-East Atlantic

Page 49: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Bentonite Handling and Monitoring

Draft Environmental Management Plan Document No: COR-14-OP-0000_SEPIL EMP

Method Statement Revision: 01 Page 3 of 6

FIGURE 1: TYPICAL BENTONITE SLURRY FLOWCHART

Page 50: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Bentonite Handling and Monitoring

Draft Environmental Management Plan Document No: COR-14-OP-0000_SEPIL EMP

Method Statement Revision: 01 Page 4 of 6

CONTROLS The bentonite slurry system is a controlled operation from the silos to the cutting

face and back through the slurry system to the separation plant.

During Tunnelling

• Bentonite slurry will penetrate the surrounding ground over a short distance

in order to support TBM face during tunnelling. The pressure of the slurry at

the soil face will be controlled by a compressed air cushion inside the TBM,

which allows for rapid changes of the slurry volume in mixed ground

conditions, while automatically maintaining a pre-set face support pressure.

The pressure at the soil face will be continuously measured and monitored by

the TBM operator and alarmed when limit values are met.

• The design and the operation of the TBM will ensure that any break-out

release will be contained to around 7m3

• In the unlikely event of a:

• Bentonite loss beyond the immediate vicinity of the tunnel bore; the

bentonite operating pressure will be reduced.

• Uncontrolled bentonite leakage within the slurry circuit; internal actions

will be initialised immediately to identify and eliminate the cause of the

problem.

• Uncontrolled bentonite breakout on the TBM cutting head; the

bentonite operating pressure will be reduced immediately to reduce

bentonite loss. Immediate actions will be initialised to identify, eliminate

the cause of the problem.

Onsite at Aughoose Compound

• Bentonite handling will be carried out within a closed system and located in a

hard standing area. It will have a separate drainage system from which all

run-offs will be collected and pumped into a used bentonite tank.

• Bentonite, though not considered to be a hazardous material, will be stored

and handled within a contained unit. Surplus bentonite slurry following

completion of tunnelling will be treated and disposed of at an appropriate

licensed water treatment facility.

Onsite at Glengad Reception Shaft Compound

• During removal of the TBM at Glengad, the shaft will be partially flooded. This

water will be contained within the shaft and removed offsite for treatment at

an appropriate licensed water treatment facility.

• Robust measures will be taken to ensure there is no bentonite release during

the loading, handling and transport of the TBM in Glengad.

MONITORING The use and consumption of drilling fluid in the tunnelling process will be

monitored throughout the works by material balance calculations and pressure

Page 51: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Bentonite Handling and Monitoring

Draft Environmental Management Plan Document No: COR-14-OP-0000_SEPIL EMP

Method Statement Revision: 01 Page 5 of 6

control.

• The bentonite slurry level in the cutter head is continuously monitored by

a series of level sensors.

• The volume imbalance or the reduction in pressure and bentonite levels

would alert the operator and mitigation measures as listed below would

quickly be put in place to control any localised breakout.

• The feed and discharge pipes of the TBM are equipped with a flow

indicator and a density measurement system to monitor the most

important parameters of the bentonite suspension and mass balance. All

values will be stored electronically and can be monitored at any time in

the control cabin of the TBM as well as in the site office and the

Separation Plant.

• The separation plant control cabin is also equipped with monitoring

equipment where all the bentonite suspension data is shown.

• In the TBM the face pressure will be monitored by the TBM operator via

pressure sensors located in the excavation chamber. The pressure values

will be electronically stored and can be monitored continuously in the

control cabin of the TBM as well as in the site office and the separation

plant.

EQUIPMENT TBM

Separation Plant

Filter press (secondary slurry process)

Fresh bentonite tank

Used bentonite tank

Slurry pipes

Slurry pumps

Page 52: Appendix L Method Statements.pdf

Shell Exploration and Production Ireland Ltd. Title: Bentonite Handling and Monitoring

Draft Environmental Management Plan Document No: COR-14-OP-0000_SEPIL EMP

Method Statement Revision: 01 Page 6 of 6

POTENTIAL

ENVIRONMENTAL

IMPACT

MITIGATION

Release of bentonite to

environment

• The composition of slurry is designed to suit the geotechnical conditions.

• Bentonite pressure and rate of usage will be monitored constantly.

• Bentonite sensors will be installed in the excavation chamber. The chamber

can be separated from the slurry system;

• The TBM speed will be altered to suit the ground conditions.

• Measures will be implemented to prevent any egress of bentonite into

watercourses leading into the cSAC /pSPA at Sruwaddacon Bay. A hard

standing area for bentonite handling plant will be located in the Aughoose

Compound. There is a separate drainage system where the run-off is

collected and pumped into a used bentonite tank. During removal of the

TBM at Glengad, the shaft will be partially flooded. This water will be

contained within the shaft and removed offsite for treatment at an

appropriate licensed water treatment facility. Robust measures will be

taken to ensure there is no bentonite release during the loading, handling

and transport of the TBM in Glengad.

• In the unlikely event of a bentonite release the design and operation of the

TBM will limit the volume to 7m3.

Page 53: Appendix L Method Statements.pdf

CORRIB FIELD DEVELOPMENT PROJECT

Onshore Works – Aughoose

METHOD STATEMENT Rev 2

Construction under Leenamore Inlet

Page 54: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction under Leenamore Inlet

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 02 Page 1 of 6

SUMMARY

The works involve the construction of the Corrib Onshore Pipeline across the Leenamore inlet and the wet

marshy areas either side.

PURPOSE Outline the general methodology for the construction of the onshore

pipeline through the Leenamore inlet and wet grasssland areas either side

of the river inlet.

LOCATION Leenamore inlet crossing and wet marshy areas either side (pipeline

chainage 89.11 to 89.35.)

The Leenamore inlet lies within the Glenamoy Bog Complex cSAC (Site Code

000500) and the Blacksod Bay/Broadhaven pSPA (Site Code 004037).

HABITATS/CONSERVATION

STATUS

Habitats comprise non-annexed improved wet rushy agricultural grassland

on either side of the inlet.

Intertidal habitats (EU annexed i: Mudflats and sandflats not covered by sea

water at low tide and Upper and Lower Saltmarsh) are non-qualifying

habitats located within the cSAC and pSPA. The approximate area of these

habitats to be disturbed at this location is 2,000 m², which equates to less

than 0.002% of the cSAC’s total land cover.

TIMESCALE/ TIMEFRAME

Approximately 6 weeks (river crossing period is approximately 2 days). It

will be completed during a period of optimum conditions (dry period of low

river flow coinciding with a period of neap tides). Construction will not take

place during the salmon spawning season without prior written agreement

from IFI and DCENR.

TECHNIQUE Temporary working area preparation works

• A 85 metre wide area will be fenced with 3m high fencing.

• A section of this fence will be located on the foreshore.

• The fence will be situated on bogmats or on precast concrete slabs

where ground conditions require.

Crossing Preparation works

• Concrete coated pipes will be prepared prior to construction.

• Cobbles within the river inlet to which epifauna & flora are attached will

be preserved by relocating to a similar position in the intertidal zone on

the shore, away from the works area. These will then be reinstated on

completion of construction works. A survey of the intertidal area will be

carried out on a receding tide to mark tidal lines in advance of

cobble/stone relocation and storage during the works.

• Areas of salt marsh likely to be impacted by the works will be turved by

means of an excavator with a specially designed turving bucket. The

machine used for salt marsh turving will work in the inter-tidal area and

transfer turves to a turve storage area. Machinery will not be allowed to

track across the salt marsh during the separation of upper layers of the

foreshore.

• The salt marsh turves will be stored in the intertidal area in a single

layer, on the foreshore which will be cleared of large stones prior to

placement. This will provide an even surface for storage.

• A geotextile will be used at the seaward edge of the stored turves to

protect against wave action in high winds. The geotextile will be

Page 55: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction under Leenamore Inlet

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 02 Page 2 of 6

removed prior to lifting of turves during reinstatement.

• The salt marsh turves will be stored at the western edge of the

Leenamore Inlet, to the north of the pipeline route but within the

temporary working area, as this area is least susceptible to wave action

during prevailing westerly winds.

• The surface layer (approximately 300mm) of the intertidal area will be

carefully lifted and stored to reduce the impact to the organisms

therein. This material will be used for reinstatement.

• The two processes (salt marsh turving and separation of upper layer of

foreshore) will be undertaken at the same time, at low tide, allowing

gradual access across the inlet.

Onshore preparation works

• The top soil in the wet grassland areas on either side of the inlet will be

stripped and stockpiled to one side of the temporary working area and

stored separately from the underlying peat /peaty soil.

River Crossing Preparation

• The Leenamore River crossing will be carried out using an open-cut

trench. A stone road will be constructed using locally sourced, washed

stone (screened to remove fines) within 10 metres either side of the

river crossing.

• A sand bag dam structure will be placed across the river inlet on both

sides of the excavation area. This structure will assist in containing

sediments, mobilised during excavation works, within the working area.

• A flume pipe will be laid on the bed of the river to direct flow through

the temporary working area. The flume pipe will be used to divert river

flow during construction activities and will allow installation of the

onshore pipeline.

• If required by the Inlands Fisheries Ireland (IFI), electrofishing will be

carried out, under permit, prior to instream works. All fish encountered

will be removed and relocated upstream. A strip net will be placed

upstream to prevent fish from entering the area. The stop net will be

removed upon completion of the works.

• A temporary access bridge for construction traffic will be installed for

crossing of the Leenamore Inlet during pipeline installation works.

Pipeline Installation

• The trench will be excavated so that the cover above the pipeline to the

riverbed will be a minimum of 1.6m.

• Excavation will be carried out using two excavators located at opposite

sides of the river inlet. Machinery movement within the inter-tidal area

will be avoided.

• Excavation will be carried out using perforated buckets to allow

separation of solid material from water.

• Excavated material will be loaded into dumpers and transferred to the

Aughoose Compound for storage.

• Once the trench is ready the prefabricated pipelines (one pipeline, one

sleeve) will be transported from the Aughoose compound and placed

into the trench.

Page 56: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction under Leenamore Inlet

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 02 Page 3 of 6

Reinstatement of the inlet

• Following the laying of the pipeline and sleeve, the trench will be

backfilled initially with a 150mm sand or pea gravel surround followed

by coarse, silt free material (natural gravel) or, depending on quality, the

excavated material. Impact protection in the form of precast concrete

slabs will be placed over the pipeline and sleeve.

• The upper layer of river bed sediment (300mm), that was stored

separately, will be replaced to reinstate the area where the open trench

existed.

• The geotexile protection will be removed prior to lifting the turves from

the storage area. The salt marsh turves will then be moved back into

place. Temporary staking and horizontal timber boards (planks) will be

used to protect the outer edges of the turves against wave action during

recovery. Biodegradable geogrid may be used on the surface of the

turves if considered necessary.

• The banks of the inlet will be stabilised to prevent bank erosion. Any

excess stone will be removed.

• The temporary access bridge will be removed during reinstatement of

the salt marsh.

• Finally, the large cobbles will be reinstated.

Reinstatement of the fields either side of the inlet

• The wet grassland areas on either side of the inlet will be reinstated by

means of replacing the underlying peat /peaty soil and then spreading

the stockpiled top layer material in readiness for landscaping and

planting.

• All security fencing will removed after reinstatement completion.

Page 57: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction under Leenamore Inlet

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 02 Page 4 of 6

EQUIPMENT

Lifting Booms Turving bucket

Bulldozer. Articulated trench rollers

Dump trucks. 6 inch water pumps

Rubber tyred excavators Filtration tank

Tracked Excavators

RESTRICTIONS • The Leenamore inlet is within the Glenamoy Bog Complex cSAC and the

Blacksod Bay / Broadhaven pSPA.

Intertidal habitats are EU Annex I habitats (EU Habitats Directive):

1. Atlantic salt meadows (Salt marsh).

2. Mudflats and sandflats not covered by sea water at low tide.

• Requirement to turve areas of upper and lower salt marsh.

• Tidal conditions in the estuary and fluvial flows from the Leenamore

River.

• Works will be completed during suitable tides and during a period of low

flow in the Leenamore River.

• Construction work will be restricted to take place between 07:00 and

19:00 weekdays and 07:00 and 16:00 on Saturdays.

• Noise and vibration limits.

• Lighting constraints .

• Works will be undertaken only after prior agreement with relevant

statutory bodies, in consultation with the Project ecologist.

Page 58: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction under Leenamore Inlet

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 02 Page 5 of 6

POTENTIAL

ENVIRONMENTAL

IMPACT

MITIGATION

Construction Works

negatively impacting

local environment

• Duration of construction will be minimised.

• Mammal gates will be provided at the base of the fencing at 75m intervals to

allow otters and badgers free access across and a means of escape from the

temporary working area.

• Ramps will be provided at intervals along the trench line to allow a means of

escape for wildlife should they enter the trench.

• Weather forecast and tide tables to be observed before commencement of

construction in this area to ensure works are undertaken in suitable

conditions.

• Works will be undertaken in summer time i.e outside the overwintering

period for the pSPA.

• A walkover survey of onshore sections including shorelines will be undetaken

prior to construction in order to ensure that no ground nesting birds are

present on lands to be disturbed.

• Water monitoring will be carried out in line with section 2.5.3 of the

Environmental Monitoring Programme (EMP, Appendix A).

Release of suspended

solids from the works

could have negative

impact on estuarine,

intertidal, and

riparian habitats and

species.

• Containment, settlement and /or filtration methods will be used where

necessary and will be put in place prior to commencement of preparation

works.

• Once the river flow is isolated, river bed excavation works can commence.

Operation of machinery within the river inlet and use of machinery in the

immediate vicinity of the inlet will be kept to a minimum to avoid any

unnecessary disturbance.

• Disturbance of bankside soils and inlet sediments will be kept to the

minimum required for the pipe laying process to avoid unnecessary impact

on the river habitat.

• If pumps are utilised, care will be taken to screen pump inflows to protect

fish and to ensure that the watercourse upstream of the barriers is not

pumped dry.

• Splash plates will be placed at the outflow of pumps to ensure that scouring

and suspension of fine sediments does not take place.

• Locally sourced quarry stone will be used adjacent to the inlet

(approximately 10m each side).

• Upon completion of the instream work, the inlet will be restored to its

original configuration and stabilised to prevent bank erosion by means of

timber stakes, timber planks and geotextiles as required.

Pollution of terrestrial

/ aquatic habitats due

spillage or leaks of

oil/diesel from plant

and equipment.

• Machinery and plant will be inspected for potential leaks prior to being used

in the crossing works.

• Refuelling of plant/machinery will only take place in designated areas.

• Spill kits will be available on site.

Page 59: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction under Leenamore Inlet

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 02 Page 6 of 6

POTENTIAL

ENVIRONMENTAL

IMPACT

MITIGATION

Release of sediment

from works could

have negative impact

on estuarine,

intertidal, and

riparian habitats and

species.

• Sediment Control measures will be put in place prior to commencement of

preparation works.

Interference with the

chemical balance

caused by non-

chemically

compatible materials

such as stone.

• Locally sourced and washed quarry stone will be used adjacent to the river

inlet (approximately 10m each side).

Noise, vibration and

lighting Disturbance.

• Noise and vibration will be minimised through design, and appropriate

selection of plant and machinery

• Proactive maintenance of plant and machinery will be carried out.

• Cladding of stationary machinery such as generators.

• Mobile lighting will be designed to limit light spillage.

Construction activities

may have a negative

impact on salt

marshes due to the

friable nature of the

substrate and

relatively low

coherence of the

vegetation layer.

• Machinery will not be permitted to move across areas of salt marsh during

the separation of upper layers of foreshore.

• Control measures outlined in the construction technique must be complied

with. Particular attention will be given to protection of salt marsh prior,

during and post construction.

Damage to river

bank.

• Upon completion of the instream work, the river inlet bank will be restored

to its original configuration and stabilised to prevent bank erosion by means

of timber stakes and fencing.

Earthworks may

disturb archaeological

remains.

• A licensed archaeologist will be on site to monitor all ground disturbances.

Page 60: Appendix L Method Statements.pdf

CORRIB FIELD DEVELOPMENT PROJECT

Onshore Works – Aughoose

METHOD STATEMENT Rev 01

Onshore pipeline construction in recovering eroded blanket bog

(190m section)

Page 61: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction in recovering eroded blanket bog (190m)

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 1 of 8

SUMMARY

The works involve construction of a pipeline (and associated stone road) in a 190m section of recovering

eroded blanket bog and the reinstatement of same.

PURPOSE Outlines the general methodology for completing the onshore gas pipeline through a

190m section of recovering eroded blanket bog.

LOCATION Aughoose, pipeline chainage 89.35 to 89.54

HABITATS /

CONSERVATIO

N STATUS

Recovering eroded blanket bog which is expected to return to, but has not yet

achieved, EU Annex I habitat quality.

This is not within any designated conservation site.

TIMESCALE/

TIMEFRAME

Approximately 10 weeks to coincide with summer season

TECHNIQUE Supervision and Independent Verification

These works will be supervised by a suitably experienced and qualified geotechnical

engineer or geologist familiar with construction in peat. The role of the supervising

engineer is to ensure that the works have been carried out in accordance with the

specifications and standards as set out below. In this regard, the supervising engineer

will carry out an independent verification of the works (that is installation of reworked

peat layer) similar to a construction quality assurance (CQA) approach.

Specification, Installation, Supervision and Verification will be completed in accordance

with the following reports:

1. Reworked peat & mineral soil permeability research, AGEC, October 2009;

2. Report on Trial Trench and Impedance Layer (Chainage 89.350 to 89.540),

AGEC, May 2011.

Site Preparation

The 40m wide temporary working area will be set up as follows:

• Install 3m high palisade security fencing mounted on bog mats.

• In order to facilitate the construction of a 9m wide stone road the upper vegetation

layer of peat will be removed as turves.

• The turves will measure approximately 2m x 1m x 0.5m and will be laid carefully on

bog mats in single layers within the temporary working area and stored for

reinstatement on completion of the works. The turves will be stored close together

to prevent drying of edges. They will be monitored during storage and irrigated as

required.

Page 62: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction in recovering eroded blanket bog (190m)

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 2 of 8

Stone Road Construction

• The process of installing the stone road will be a combination of excavation and

displacement of peat with stone. The depth of stone will vary depending on the

depth of the peat.

• This area may need to be sheet piled prior to stone road construction to allow for

safe pipe laying activities.

• Following removal of the turves, peat will be excavated to a nominal depth of 0.5m

from the base of the peat. Imported, single size stone will be pushed into this peat

layer to form a peat stone matrix.

• Suitable peat excavated during stone road construction will be stored within the

temporary working area outside the 190m for future use in backfilling the pipe. The

specification and testing requirements to determine suitability of this peat will

conform with the recommendations outlined in the reports entitled 'Reworked peat

& mineral soil permeability research' (AGEC, October 2009), Report on Trial Trench

and Impedance Layer (Chainage 89.350 to 89.540), (AGEC, May 2011).

• Additional peat for regulating the surface of the stone road prior to reinstatement

of the turves will also be stored outside of the 190m.

• The remainder of the excavation will backfilled with a standard graded stone to a

level approximately 0.8m below the original surface level of the bog.

• An additional bog mat access will be constructed adjacent to the stone road for

pipeline installation activities only.

Page 63: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction in recovering eroded blanket bog (190m)

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 3 of 8

Pipeline installation

• In this area, the trench excavation will go below the peat stone matrix in order to

get the required cover over the pipeline. This will involve excavation into mineral

soil.

• String out pipeline and other services on bog mat road and prepare for laying.

• Excavate trench and install pipe bedding.

• Excavated material will be placed on the stone road to raise the level of the stone

road to that of the bog mat access, ensuring a level running track for operation of

side booms.

• All mineral soil excavated during trench construction will be transported to a

licensed facility for disposal.

• Install gas and service pipes, and surround services with suitable material (sand or

pea gravel) as per pipeline designer’s specification.

• Roll out a geotextile layer over the level pea gravel. The width of the placed

geotextile filter membrane shall be of sufficient width to cover the trench base, side

walls and to allow a nominal 100mm lap above the interface of the peat and

mineral soil on both sides of the trench.

• Place a 1000mm deep layer of suitable reworked peat over the geotextile as

Page 64: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction in recovering eroded blanket bog (190m)

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 4 of 8

follows:

o Suitable reworked peat will be placed into the trench using an excavator

bucket so as not to damage the geotextile filter membrane.

o Suitable reworked peat shall not be dropped from a height.

o Suitable reworked peat shall be placed uniformly into the trench to avoid

excessive dragging and to avoid spreading of peat over the geotextile.

o No compaction of the reworked peat layer is required other than light

pressing during placement using the back of an excavator bucket.

o Suitable reworked peat shall contain no large clods or other material

prohibited by the specifications (AGEC, 2009, and AGEC 2011).

o Testing of reworked peat is required; refer to Test Requirements and

Acceptable Limits for Reworked Peat Layer in Pipeline Trench, AGEC 2009,

and AGEC, 2011.

o During placement of reworked peat layer the trench shall be kept free of

water.

• Place 300mm layer of clean stone immediately above reworked peat layer.

• Backfill remainder of trench with trench arisings (that is stone road fill) stored on

stone road.

Reinstatement

It should be noted that reinstatement of this area will run concurrently with

reinstatement of the grassland area east of the Leenamore river crossing and will

proceed as follows:

• Once the pipeline trench has been backfilled, remove the bog mats from beside the

stone road.

• On reinstatement of this area, a regulation 100mm layer of peat will be spread

upon the stone road. The peat used for this process will be original peat excavated

from the area.

• Stored turves will be packed firmly over the regulation layer and any gaps will be

hand-packed with peat scraw as the process is being done.

Page 65: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction in recovering eroded blanket bog (190m)

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 5 of 8

• Care will be taken to avoid compaction during reinstatement and the turves will be

reinstated to a slightly higher level than the surrounding bog in order to allow for

settlement post construction.

• The reinstated turves are to be replaced carefully, under the supervision of the site

Environmental officer under the direction of the Project Ecologist.

• Bog mats used for turve storage will be removed immediately after turve

reinstatement.

Monitoring, Testing & Reporting

• Groundwater and peat water level monitoring will be completed in accordance with

Section 7.7 of AGEC, 2009, and in accordance with the Environmental Monitoring

Programme (SEPIL, 2011).

• Independent on-site and laboratory testing will be completed on reworked peat

samples as per requirements of AGEC, 2009, and AGEC, 2011. Tests shall include:

o Moisture content (during storage and placement)

o Laboratory hydraulic conductivity (permeability), (during storage

and placement)

o Visual homogeneity

o Geotechnical engineering description (during storage and

placement)

o Peat thickness (during excavation)

• The following reports will be prepared in accordance with Section 7.5 (7) of AGEC,

2009:

o Daily reports.

o Test Report (including field and laboratory testing).

o Validation Report Prior to Commissioning.

• For further details of monitoring, testing and reporting reference should be made

to Environmental Monitoring Programme (SEPIL, 2011) and reports AGEC 2009

and AGEC 2011.

Page 66: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction in recovering eroded blanket bog (190m)

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 6 of 8

EQUIPMENT Side Booms.

Bulldozer.

Dump trucks.

Rubber tyred excavators.

Tracked Dumpers

Tracked Excavators

Articulated trench rollers.

6 inch water pumps

Turving Bucket

RESTRICTIONS • Working in an area of recovering eroded blanket bog which will be treated as

though it were EU Annex I blanket bog habitat.

• Working in close proximity to, and upslope of, the Glenamoy Bog Complex cSAC

and Blacksod Bay / Broadhaven pSPA, and the Leenamore River.

• No vehicle movements will be permitted outside the fenced working area.

• Normal construction work will be restricted to between 07:00 and 19:00 weekdays

and 07:00 and 16:00 Saturday.

• Noise and vibration limits.

• Lighting constraints.

Page 67: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction in recovering eroded blanket bog (190m)

Environmental Management PLan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 7 of 8

POTENTIAL

ENVIRONMENTAL

IMPACT

MITIGATION

Damage to recovering

eroded blanket bog

• The temporary working area width will be approximately 40m to allow

sufficient spacing for storage of turves.

• No vehicle movements will be permitted outside the fenced working area.

• The stone road will be limited to a width of 9m to minimise impact on peat

land.

• A specially designed excavator bucket will be used to lift and place turves

carefully onto wooden bog mats so that the turves do not break up. These

mats will be located alongside the stone road within the temporary

working area.

• Turves will be stored in a single layer on bog mats, stored close together to

prevent drying of edges, and will be monitored and irrigated as required

until reinstatement.

• Stored turves will then be put back to cover the reinstated peat layer on

top of the stone road. Care will be taken to avoid compaction during

reinstatement.

• There will be minimum delay between construction and reinstatement of

this section and every effort will be made to minimise the duration of

disturbance in this area.

Loss of typical blanket

bog species due to

compaction of roots of

vegetation, surface

damage and water

logging from

compaction

• Reduce vehicle movement to a minimum.

• Temporary working area is fenced to prevent encroachment and damage

to the recovering blanket bog outside the working width.

• Low ground pressure vehicles will be used for traversing peat prior to

construction of the stone road. No tracking outside the working area

during the set out phase.

• Only essential vehicles will be used in this section.

• Bog mat access road will only be in position for duration of pipe stringing

and preparation works, they will be removed as soon as the pipes and

services are backfilled.

Hydrological changes

caused by pipeline

acting as a drain

• Placement of reworked peat impedance layer. Works to be completed in

accordance with the following reports:

1. Reworked peat & mineral soil permeability research, AGEC, October

2009;

2. Report on Trial Trench and Impedance Layer (Chainage 89.350 to

89.540), AGEC, May 2011.

• Peat plugs will be placed at approximately 50m intervals to prevent the

road acting as a preferential drainage channel.

• Raised contoured turve ridges will also be placed at 50m intervals to

deflect surface water runoff.

Interference with the

chemical balance

caused by non-

chemically compatible

materials such as stone

• The stone for constructing the stone road will be locally sourced and

carefully selected to ensure that it is appropriate for the local environment

within the peat.

Page 68: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction in recovering eroded blanket bog (190m)

Environmental Management PLan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 8 of 8

POTENTIAL

ENVIRONMENTAL

IMPACT

MITIGATION

Pollution of terrestrial

and aquatic habitats

due spillage or leaks of

oil/diesel from plant

and equipment

• Machinery and plant will be inspected for potential leaks prior to being

used in this area.

• Refuelling of plant/machinery will only take place in designated areas.

• Spill kits will be available on site.

Release of suspended

solids from the works

could have negative

impact on riparian and

intertidal habitats and

species

• Surface Water Control measures will be put in place prior to

commencement of construction works.

• Silt control barriers will be installed along the boundary fence as required

to control sediment run-off.

Noise, Vibration,

Lighting - Disturbance

• Noise and vibration will be minimised through design, and appropriate

selection of plant and equipment.

• Proactive maintenance of machinery to minimise noise and vibration.

• Cladding of stationary machinery such as generators.

• Acoustic screening & fencing to minimise noise.

• Site and mobile lighting will be designed to to limit light spillage.

Construction activities

may affect wildlife

(otters and badgers)

• Egress points will be placed at intervals along the trench line to allow

wildlife means of escape should they enter the trench.

• Mammal gates will be provided at the base of the fencing at 75m intervals

to allow otters and badgers free access across and a means of escape from

the temporary working area.

Disturbance to birds in

the locality

• A walkover survey will be undertaken prior to construction in order to

ensure that no ground nesting birds are present on lands to be disturbed

Damage during and

after reinstatement

works

• Stored turves will be packed firmly over a regulation peat layer on top of

the stone road. Gaps will be hand packed.

• Care will be taken to avoid compaction of turves during reinstatement and

the turves will be reinstated to a slightly higher level than the surrounding

bog in order to allow for settlement post construction.

• A stock-proof fence will be maintained to protect the reinstated section.

Earthworks may disturb

archaeological remains

• A licensed archaeologist will be on site to monitor all peat excavation

activities.

Page 69: Appendix L Method Statements.pdf

CORRIB FIELD DEVELOPMENT PROJECT

Onshore Works – Aughoose to Bellanaboy

METHOD STATEMENT Rev 1

Construction in Forested Area

Page 70: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction in Forested Area

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 1 of 6

SUMMARY

This method statement describes the construction of the Corrib Onshore Pipeline in a stone road through

a forested peatland area. A pipeline trench will be excavated, the pipe installed, trench backfilled and the

area reinstated.

PURPOSE This method statement outlines the general methodology for

construction of the Corrib Onshore Pipeline within a stone road through

a forested peat area.

LOCATION Pipeline Chainage 89.54 to 91.42.

This section of the route runs south east crossing commercially forested

land before changing direction where it crosses a road at Chainage

90.137. There is also a small stream crossing in this area at Chainage

90.15. It changes direction again to run south to south west falling

towards a small valley and stream crossing at 90.72 and rising again

towards the Terminal site.

HABITATS/CONSERVATION

STATUS

Habitats comprise commercial forestry plantation and are not within any

designated conservation area.

TIMESCALE/TIMEFRAME

Approximately 6 months with stream crossings, to occur during a dry

weather period.

TECHNIQUE Site Preparation

• The 40m wide temporary working area will be fenced off with 3m high

palisade fencing mounted on bog mats.

• Any necessary tree felling will be carried out under licence and in

consultation with the Project Ecologist during the winter season.

• Areas of dense vegetation, including conifer plantations, affected by the

development will be monitored by faunal experts during vegetation

clearance.

• Conifer trees will be felled and cut to ground level throughout the

working width, leaving roots intact, except along the route of the

pipeline trench, where trees – including roots – will be completely

removed.

Pipeline Construction

• The pipeline will be constructed using the stone road method. At the

western edge of the section (from chainage 89.54) washed stone will be

used in a 10m buffer zone (to protect the recovering eroded blanket bog

to the west of chainage 89.54)

• Peat will be excavated to approximately 0.5m from the base of the peat

and the excavation backfilled with stone to form a peat stone matrix.

The process of installing the stone road will be a combination of

excavation and displacement of peat with stone. The depth of placed

stone will vary depending on the depth of the peat.

• The top surface of peat including the vegetation will be removed by

excavator and kept separate from peat excavated from lower layers.

Page 71: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction in Forested Area

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 2 of 6

This material will be retained within the TWA and used during

reinstatement.

• Stockpiled peat will be stored away from the point of excavation.

• Once the stone road is in place, a trench will be excavated in the stone

road, within which the onshore pipeline and services will be laid (1m

separation between the gas pipe and the services). The trench will then

be backfilled using pipe bedding material and the excavated stone.

Stream Crossing (Chainage 90.15)

• Stream crossing will be completed in dry weather conditions.

• Sufficiently sized flume pipes will be placed within the stream and

overlaid with a geotextile membrane.

• A stone haul road is constructed on top of the flume pipes to allow

construction traffic to cross the stream and from which the pipeline

trench will be excavated.

• A dam will then be formed using impermeable clay and a sufficient

number of pumps will be set up. These will over pump any build-up of

water from the upstream side of the stream into its natural course on

the downstream side.

• The trench will be excavated to the required level, with the trench

widened at each end to allow welders to connect the pipe under the

stream to the main pipeline. Sheet piles will be installed where

necessary and imported sand will be used to bed the pipe if conditions

so require. The trench will be kept dry by means of water pumps set up

at a sump box in the low point of the trench. The water will be pumped

into suitable fitration/settlement equipment prior to discharge into the

existing stream. The pipe section, having been strung / welded will then

be laid. The pipeline’s services and outfall pipe will also be installed at

this stage.

• Backfilling of the trench in compacted layers will take place using the

excavated material where possible. Suitable selected fill will be placed

over the top of the pipeline before placing precast concrete slab across

the full width of the stream. The minimum cover over the pipe will be

1.6m at the stream crossings.

Temporary Compound (approx. Chainage 89.85)

• A temporary construction compound approximately 80m x 50m will be

fenced off by means of 3m high palisade fencing. This compound will be

located to the south of the pipeline.

• Any topsoil will be stripped and stored in a designated location within

the compound.

• This compound will facilitate waste storage and contain office and

welfare facilities and may be used as a temporary storage area.

Road Crossing (Chainage 90.14)

Page 72: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction in Forested Area

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 3 of 6

• There is a road crossing, which will be constructed using standard open-

cut techniques.

• Liaison with Mayo County Council regarding existing services will take

place and a road opening licence will be obtained prior to construction.

• Traffic control measures in accordance with Chapter 8 of the Dept. of

Transport Traffic Signs Manual will be put in place prior to excavation

works and a Traffic Management Plan will be in operation during the

works.

• A trench will be excavated across the road and pipe sleeves installed

and the trench backfilled. The sleeves will be installed with a minimum

depth of cover of 1.6m.

• A minimum clearance of 300mm will be maintained between the

onshore pipeline and any existing services.

• Impact protection in the form of pre cast concrete slabs will be placed

over the sleeves where they are located under the road.

• Road surfaces will be returned to a standard equal to or better than that

prior to construction of the pipeline.

• The pipeline and ancillary services will then be pulled through the

sleeves during pipeline installation.

Reinstatement

• Any pre existing land drains will be repaired and recorded on the as-

built survey.

• The reinstatement will take place using suitable Low Ground Pressure

(LGP) plant.

• Any remaining roots, branches, etc will be gathered and removed off-

site for later disposal.

• A regulation peat layer of approximately 0.1m will be placed over the

stone road.

• The top layer of peat with remnant vegetation will then be replaced in

preparation for landscaping and habitat creation.

• Upon completion of instream work, the streams will be restored to their

original configuration and stabilised to prevent bank erosion by means

of geotextiles as required.

Page 73: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction in Forested Area

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 4 of 6

EQUIPMENT Tracked Excavators

Rollers

Tracked Dumpers

Articulated Dump truck

Low Ground Pressure (LGP) tracked excavators

Side booms

Marookas

RESTRICTIONS • Area to the north of the L1202 is upslope of the Glenamoy Bog

Complex cSAC and Blacksod / Broadhaven Bay pSPA.

• All watercourse crossings (streams and drains) in the catchment of

designated conservation sites, i.e. cSAC & pSPA to the north.

• Noise and vibration limits

• Lighting constraints

• Normal construction work will be carried out between 07:00 and

19:00

• Restrictions will apply in the event of encountering a badger sett

and otter holts along or in the vicinity of the pipeline route. In this

case the mitigation measures outline in EIS appendix J1, Tables 11a

and 11b will be followed.

Page 74: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction in Forested area

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 5 of 6

POTENTIAL

ENVIRONMENTAL

IMPACT

MITIGATION

Construction Works

negatively impacting

local environment

• Weather forecast to be observed before commencement of stream crossing

Noise , Vibraion,

Lighting Disturbance

• Noise and vibration will be minimised through design, and appropriate

selection of plant and equipment.

• Proactive maintenance of plant and machinery will be carried out.

• Cladding of stationary machinery such as generators.

• Mobile lighting will be designed to limit light spillage.

Construction

activities may have

negative impact on

local wildlife (non-

avian and avian)

• Pre-construction surveys for otters and badgers will be undertaken within 1-3

months prior to construction. The areas to be included are approximately; 50-

100m either side of the centre line of the pipeline for otters, and 30m either

side of the centre line for badgers.

• Areas of dense vegetation will be monitored by faunal experts during

vegetation clearance.

• During construction, ramps will be provided at open trenches to provide a

means of escape for otters and badgers and other wildlife to escape.

• Preconstruction fauna surveys, including for frogs, will be undertaken prior to

construction. Any adult frog, spawn and /or tadpoles present will be

translocated under the licence prior to and, if necessary, during construction.

• Mammal gates will be provided at the base of the fencing at 75m intervals to

allow otters and badgers free access across and a means of escape from the

temporary working area.

• A walkover survey will be undertaken prior to construction in order to ensure

that no ground nesting birded are present on lands to be disturbed.

Release of suspended

solids from the works

could have negative

impact on stream

flora and fauna.

Potential for

suspended solids to

enter drainage

network/streams

which drain towards

Sruwaddacon Bay

which could have an

impact on salmonids,

frog breeding sites

and otters.

• Containment, settlement and /or filtration methods will be used where

necessary and will put in place prior to commencement of preparation works.

• Once the stream flow is isolated, stream bed excavation works can commence.

Operation of machinery within the inlet and use of machinery in the

immediate vicinity of any stream will be kept to a minimum to avoid any

unnecessary disturbance.

• Disturbance of bankside soils and instream sediments will be kept to the

minimum required for the pipe laying process to avoid unnecessary impact on

the stream habitat.

• If pumps are utilised, care will be taken to screen pump inflows to protect fish

and to ensure that the watercourse upstream of the barriers is not pumped

dry.

• Splash plates will be placed at the outflow of pumps to ensure that scouring

and suspension of fine sediments does not take place.

• Locally sourced quarry stone will be used. Washed stone will be used adjacent

to streams (approximately 10m each side).

Upon completion of the instream work, the stream will be restored to its

original configuration and stabilised to prevent bank erosion by means of

geotextiles as required.

Page 75: Appendix L Method Statements.pdf

Shell E&P Ireland Ltd. Title: Construction in Forested area

Environmental Management Plan Document No: COR-14-OP-SH-0000 SEPIL EMP

Method Statement Revision: 01 Page 6 of 6

POTENTIAL

ENVIRONMENTAL

IMPACT

MITIGATION

The loss of habitat as

a result of tree felling

and clearing of dense

vegetation has the

potential to have

negative impact on

fauna.

• Any required tree felling will be carried out under licence and outside the bird

nesting season. In the unlikely event that any tree felling is required at any

time during the bird nesting season, such trees to be inspected by suitably

qualified ecologist in advance.

• The edges of the temporary working area will be replanted with the

appropriate tree and shrub species during reinstatement. The top surface of

peat including the vegetation will be removed by excavator and stored

separately from peat excavated from lower layers. This material will be

retained and used as a top layer during reinstatement.

Pollution of

terrestrial / aquatic

habitat / species due

to spillage or leaks of

oil/diesel from plant

and equipment.

• Machinery and plant will be inspected for potential leaks prior to being

transported to site.

• Refuelling of plant/machinery will only take place in designated areas.

• Machinery not permitted in stream.

• Spill kits will be available on site.

Change in local

hydrology/hydro-

geological regimes.

• As the stone road is constructed, peat plugs will be placed at approximately

50m intervals as required to prevent the road acting as a preferential drainage

channel.

• The stone for constructing the stone road will be locally sourced and carefully

selected to ensure that it is appropriate for the local environment within the

peat. Where possible, tunnel arisings will also be used in combination with

quarry stone for the construction of the stone road.

Earthworks may

disturb

archaeological

remains.

• A licensed archaeologist will be on site to monitor all peat excavation

activities.

Page 76: Appendix L Method Statements.pdf

  

CORRIB FIELD DEVELOPMENT PROJECT   

Onshore Works – Onshore Pipeline Termination Point      

  

     

METHOD STATEMENT Rev 01   

Terminal Tie‐in and Surface Water Management  within the Carrowmore Lake Catchment Area. 

    

  

   

Page 77: Appendix L Method Statements.pdf

Shell E & P Ireland Ltd.  Title: Terminal tie‐in & Surface Water ManagementWithin  Carrowmore Lake Catchment

Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMPMethod Statement  Revision: 01 Page 1 of 5

SUMMARY The works outlined here cover the excavation and installation of the onshore pipeline within the Terminal and  all  associated  diversion  of  services,  surface water management,  concrete works,  gas  pipeline  and ancillary services installation as well as painting, testing and reinstatement works. PURPOSE  This  methodology  describes  the  works  associated  with  tie  in  of  the  onshore 

pipeline into the Bellanaboy Gas Terminal and the associated diversion of surface water into the Leenamore Catchment. 

LOCATION  North Western corner of the Terminal. Pipeline chainage 91.42 to 91.72.  

TIMESCALE  

Approximately 6 Months 

TECHNIQUE  Site Preparation 

A  number  of  existing  services within  the  Terminal will  have  to  be  diverted  to facilitate  pipeline  installation  including;  surface  water  drainage,  groundwater drainage,  security  fence and associated  lighting,  road drainage  system and  road lighting. The sequence is as follows: 

• At  the  tie‐in  location,  remove  gabion  baskets,  strip  topsoil,  demolish concrete channel at the bottom of the embankment and strip off surface gravel and weed blanket. 

• Excavate existing buried cables and divert south of the pig receiver (point where onshore pipeline ties into terminal structure). 

• Insert water stoppers in both the surface water and ground water systems and set up over‐pumping system south of the pig receiver. 

• Remove light poles and associated cable junction boxes. • Fence  off  a  temporary  working  area  inside  the  Terminal  to  facilitate 

pipeline activities. • Dismantle  both  existing  security  fences  inside  the  temporary  working 

area. • Saw  cut  bituminous  road  layers,  excavate  and  remove  to  a  recycling 

facility. • Demolish  concrete  open  channels  and  remove  to  a  licensed  recycling 

facility.  

Pipeline Installation Pipeline  installation within  the  Terminal  consists  of  standard welding  and  pipe trenching  procedures  used  elsewhere  on  the  onshore  pipeline  in  addition  to anchor  block  construction,  valve  pit  construction  and  overground  pipe  work painting. The sequence is as follows: 

• Excavate pipeline trench from pig receiver to the anchor block location. • Excavate  anchor  block  location  and  prepare  surface  for  steel  fixing  by 

placing  blinding  layer  of  concrete.  This  will  also  control  surface  water within the anchor block excavation. 

• Install  steel  reinforcement,  erect  temporary  timber  shuttering  and pour concrete base. 

• Remove timber shuttering and backfill foundation base up to underside of the pipeline. 

• While the anchor block is being constructed the existing surface water and groundwater drainage pipes will be removed from the pipeline route. 

• The  pipeline  and  associated  ancillary  services  will  be  strung  out  and 

Page 78: Appendix L Method Statements.pdf

Shell E & P Ireland Ltd.  Title: Terminal tie‐in & Surface Water ManagementWithin  Carrowmore Lake Catchment

Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMPMethod Statement  Revision: 01 Page 2 of 5

welded/jointed and prepared for laying. • The remainder of the pipeline trench will then be excavated and prepared.• The pipeline and ancillaries will then be laid, inspected and backfilled with 

suitable material. • The remainder of the trench will be backfilled with the original excavated 

material. • The  surface  water  and  ground  water  pipes  will  be  re‐laid  during  the 

pipeline backfilling. These pipelines will be retested prior to allowing them return to normal operation. 

• Once  the pipeline has been backfilled,  the pipeline section situated over ground will be sand blasted and painted for corrosion protection. This may require the erection of a weather proof shelter.  

Surface Water Management Surface water  from pipeline  construction works  that  lie within  the Carrowmore Lake  catchment  (ch  91.42  to  91.72)  will  be  collected,  attenuated  and  taken through  a  settlement  tank  or  treatment/filtration  unit  before  being  discharged into the Leenamore River catchment (north of ch 91.42).   The anchor block and pipeline excavations will be dewatered by pumping surface water to a drain running parallel to the existing stone road. This drain will convey surface  water  to  a  settlement  tank/treatment  unit  located  upstream  of  the  discharge point into the Leenamore River.  

It should be noted that water collected  in the Terminal drainage systems will be kept separate from any water collecting in the pipeline excavations.. 

 Reinstatement 

Pipeline reinstatement has two distinct operations; reinstating the Terminal inside the  permanent  security  fencing  (ch.  91.67‐91.72),  and  reinstatement  of  the onshore pipeline temporary working area (ch. 91.42 to 91.67). It should be noted that  reinstatement  of  ch  91.67  to  91.42  is  seasonal  and  will  be  incorporated during the landscaping/reinstatement of the entire Terminal temporary facilities.   Chainage 91.67 ‐91.72 will be reinstated as follows: 

• Construct  concrete  open  channels,  reinstate  gravel  area  between  road and pig receiver and reinstall bituminous road layers. 

• Reinstall  inner  security  fences  including  reinstatement  of weed  control blanket and gravel between the fences. 

• Reinstate light poles and previously diverted underground cables. • Reinstate gravel inside the Terminal and remove temporary fencing. • Reconstruct drainage channel at bottom of embankment batter. • Reinstate topsoil on batter and seed as required.  • Reinstall gabion baskets. 

 

Page 79: Appendix L Method Statements.pdf

Shell E & P Ireland Ltd.  Title: Terminal tie‐in & Surface Water ManagementWithin  Carrowmore Lake Catchment

Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMPMethod Statement  Revision: 01 Page 3 of 5

EQUIPMENT  Minidigger                                                            Roller 

Front Tipping Dumpers                                       Vibrating compactor (whackers) 

Articulated Dump trucks                                    Tracked Excavator (14t‐46 ton) 

Road saw                                                               Concrete pump 

Consaw                                                                  Concrete poker 

Wheeled Excavator                                             Cranes (50‐100ton) 

Sand blaster                                                          Paint Sprayer 

Side booms                                                           Welding units 

RESTRICTIONS  • Surface  water  from  pipeline  construction  works  that  lie  within  the Carrowmore Lake catchment (ch 91.42 to 91.72) shall be collected, attenuated and  taken  through  settlement/treatment units before being discharged  into the Leenamore River Catchment (north of ch 91.42).  

 • Normal construction work is restricted to between  07:00 and 19:00 weekdays 

and 07:00 and 16:00 Saturday.  

• Noise and vibration limits.  

• Lighting constraints.  

Page 80: Appendix L Method Statements.pdf

Shell E & P Ireland Ltd.  Title: Terminal tie‐in & Surface Water Management  Within Carrowmore Lake Catchment

Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMPMethod Statement  Revision: 01 Page 4 of 5

POTENTIAL ENVIRONMENTAL IMPACT 

MITIGATION 

Noise & Light  Disturbance. 

• Noise  and  vibration  will  be  minimised  through  design,  and  appropriate selection of plant and machinery. 

• Proactive maintenance of plant and equipment. • Noise  will  be  reduced  by  Cladding  of  stationary  machinery  such  as 

generators. • Acoustic screening and fencing to minimise noise. • Mobile and site lighting will be designed to limit light spillage. 

Increased dust levels  • Roads/working  area will  be  dampened  down,  as  required  to  ensure  dust levels due to construction activities are kept to a minimum. 

• Sand blasting of pipe work will be carried out under a weather proof shelter. Construction activities may affect local otters and badgers.  

• A pre‐construction survey for otters and badgers will be undertaken within 1‐3  months  prior  to  construction.    The  areas  to  be  included  are approximately;  50‐100m  either  side  of  the  centre  line  of  the  pipeline  for otters, and 30m either side of the centre line for badgers.  

• Areas of dense vegetation affected by the development which could not be thoroughly  searched will  require monitoring by appropriate experts during vegetation clearance. 

• Excavations will allow otters and badgers a means of escape if they get into the excavation. This will be achieved by placing access/egress planks and/or soil ramps at necessary locations.   

• Work  activities will  be  limited  to  between  the  hours  of  07:00  and  19:00 weekdays and 07:00 and 16:00 Saturday. 

• Caps will be placed over all pipe ends at night. • Gaps will be  left at the base of the fencing at 75m  intervals to allow otters 

and  badgers  free  access  and  a  means  of  escape  across  the  temporary working area. 

Construction activities may affect amphibians 

• Any frogs identified will be translocated under license to a suitable location. • Habitat  reinstatement will  re‐create  the  former channel and drain systems 

so that frogs may use these post construction. Construction activities may affect nesting birds

• Vegetation  clearance will be undertaken outside  the breeding bird  season i.e. March to August, where feasible. 

• Re‐vegetation and planting of native scrub species will be completed during reinstatement. 

Pollution of terrestrial and aquatic habitats due spillage or leaks of oil/diesel from plant and equipment. 

• Machinery and plant will be inspected prior to mobilisation to site. • Refuelling of plant/machinery will only take place in designated areas. • Spill kits will be available on site. 

Page 81: Appendix L Method Statements.pdf

Shell E & P Ireland Ltd.  Title: Terminal tie‐in & Surface Water Management  Within Carrowmore Lake Catchment

Draft Environmental Management Plan  Document No: COR‐14‐OP‐SH‐0000 SEPIL EMPMethod Statement  Revision: 01 Page 5 of 5

POTENTIAL ENVIRONMENTAL IMPACT 

MITIGATION 

Release of pipeline discharge waters to the Carrowmore Lake Catchment could have negative impact on drinking water quality.  

• All  surface water  from  construction activities within  the Carrowmore  Lake Catchment  shall be collected, attenuated &  treated prior  to discharge  into the Leenamore River Catchment. 

• In  drain  mitigation  will  be  placed  as  required  to  reduce  silt  impact  on associated waterways.  

Works may disturb archaeological remains. 

• A licensed archaeologist will be on site to monitor all excavations.