Upload
others
View
8
Download
0
Embed Size (px)
Citation preview
EcIA - Ecological Impact Assessment (EcIA) August 2020 County Donegal Towns & Villages Sewerage Schemes. Ramelton – Milford – Rathmullan (RMR) Sewerage Scheme
214
Appendix I – The Proposed Leannan Crossing HDD Methodology
Ramelton, Milford and Rathmullan Sewerage
Scheme
Ramelton Estuary Crossing
HORIZONTAL DIRECTIONAL DRILLING
METHODOLOGY
March 2020
Jennings O’Donovan & Partners Ltd. Consulting Engineers,
Finisklin Business Park, Sligo.
Tel.: 071 9161416 Fax: 071 9161080
email: [email protected]
____________________________________________________________________________________
Directors: D. Kiely, C. McCarthy
Regional Director: A. Phelan
Consultants: C. Birney, M. Gavin, R. Gillan
Senior Associates: R. Davis, S. Gilmartin, J. Healy, J. McElvaney, T. McGloin
Associates: L. Brennan, S. Lee, S. Martyn, L. McCormack, S. Molloy
Company Reg No. 149104 VAT Reg. No. IE6546504D
JENNINGS O’DONOVAN & PARTNERS LIMITED
Project, Civil and Structural Consulting Engineers, FINISKLIN BUSINESS PARK,
SLIGO,
IRELAND.
Telephone (071) 9161416 Fax (071) 9161080
Email [email protected] Web Site www.jodireland.com
DOCUMENT APPROVAL
PROJECT
Ramelton, Milford and Rathmullan Sewerage Scheme
CLIENT / JOB NO
Irish Water 4940
DOCUMENT TITLE Ramelton Estuary Crossing Horizontal Directional Drilling Methodology
Prepared by Reviewed/Approved by
This document, and information or advice which it contains, is provided by JENNINGS O’DONOVAN & PARTNERS LIMITED solely for internal use and reliance by its Client in performance of JENNINGS O’DONOVAN & PARTNERS LIMITED’s duties and liabilities under its contract with the Client. Any advice, opinions, or recommendations within this document should be read and relied upon only in the context of the document as a whole. The advice and opinions in this document are based upon the information made available to JENNINGS O’DONOVAN & PARTNERS LIMITED at the date of this document and on current standards, codes, technology and construction practices as at the date of this document. Following final delivery of this document to the Client, JENNINGS O’DONOVAN & PARTNERS LIMITED will have no further obligations or duty to advise the Client on any matters, including development affecting the information or advice provided in this document. This document has been prepared by JENNINGS O’DONOVAN & PARTNERS LIMITED in their professional capaci ty as Consulting Engineers. The contents of the document does not, in any way, purport to include any manner of legal advice or opinion. This document is prepared in accordance with the terms and conditions of JENNINGS O’DONOVAN & PARTNERS LIMITED contract with the Client. Regard should be had to those terms and conditions when considering and/or placing any reliance on this document. Should the Client wish to release this document to a Third Party for that party's reliance, JENNINGS O’DONOVAN & PARTNERS LIMITED may, at its discretion, agree to such release provided that: (a) JENNINGS O’DONOVAN & PARTNERS LIMITED written agreement is obtained prior to such release, and
(b) By release of the document to the Third Party, that Third Party does not acquire any rights, contractual or otherwise, whatsoever against JENNINGS O’DONOVAN & PARTNERS LIMITED and JENNINGS O’DONOVAN & PARTNERS LIMITED, accordingly, assume no duties, liabilities or obligations to that Third Party, and
(c) JENNINGS O’DONOVAN & PARTNERS LIMITED accepts no responsibility for any loss or damage incurred by the Client or for any conf lict of JENNINGS O’DONOVAN & PARTNERS LIMITED’s interests arising out of the Client's release of this document to the Third Party.
Document
Rev 0
Name Name
Date
5th March 2020
Signature Signature
Document
Rev 1
Name Name
Date
31st March 2020
Signature Signature
Jennings O’Donovan Consulting Engineers Sligo _________________________________________________________________________________________________
_________________________________________________________________________________________________ 4940-CN4-RMR-Esturary HDD Methodology Rev 1 i March 2020
Ramelton, Milford and Rathmullan Sewerage Scheme
Horizontal Directional Drilling Methodology
Ramelton Estuary Crossing
Table of Contents
1 INTRODUCTION 1
2 ESTUARY CROSSING 1
3 SCOPE OF WORK 2
4 SITE PREPARATION 2
5 SITE LAYDOWN DESIGN 2
6 RIG ANCHORAGE AND SET UP 3
7 EXAMPLE OF PLANT LIST FOR HDD 3
8 PILOT HOLE 3
9 SURVEY AND TRACKING 3
9.1 Drill Guide – Gyro Steering Tool (GST) 3
10 PILOT HOLE DRILLING 4
11 REAMING 4
12 DRILLING FLUID – USAGE AND CONTROL 5
13 DRILLING FLUID PRODUCTS 6
14 DRILLING FLUID PARAMETERS 6
15 DRILLING FLUID LOSS 6
16 PIPE INSTALLATION 7
17 PIPE PIGGING AND PROVING 8
18 PILOT HOLE CONTINGENCIES 8
APPENDIX 1 - PLAN AND LONGITUDINAL SECTION OF THE RISING MAIN CROSSING
APPENDIX 2 - ROCK PROFILE
APPENDIX 3 - SITE INVESTIGATIONS
Jennings O’Donovan Consulting Engineers Sligo _________________________________________________________________________________________________
_________________________________________________________________________________________________ 4940-CN4-RMR-Esturary HDD Methodology Rev 1 1 March 2020
Ramelton, Milford and Rathmullan Sewerage Scheme
HDD Methodology Estuary Crossing at Ramelton
1 INTRODUCTION
The estuary crossing involves the construction of a 200mm OD HPPE PE 100 SDR 11 rising main
under the Leannan Estuary which is a designated SAC and SPA. The overall length of the crossing
is approximately 260m. There is a combination of both sandy gravels and rock in the channel bed.
A drawing showing the plan and longitudinal section of the crossing is attached as Appendix 1. A
sketch of the rock profile is attached as Appendix 2 and the site investigations along the crossing
is attached as Appendix 3. This report relates to the methodology for the horizontal directional
drilling (HDD) of the estuary between approximately Ch 0 and Ch 260.
The proposed works will be conducted following any associated mitigation provided within the
Ecological Impact Assessment (EcIA) (Woodrow, 2020a), Natura Impact Statement (Woodrow,
2020b) and MERC 2020 reports that have been produced to support this methodology. Such as
the need for appropriate Ecological Clerk of Works (ECoW) supervision, Seasonal Constraints,
Pollution Controls, Biosecurity Measures and Monitoring of the Works
2 ESTUARY CROSSING
The geology of the ground/seabed along the proposed pipeline route consists of mixture
gravelly sandy silt and bedrock. The rock rises to within 500mm of the estuary/river bed at
approximately the mid point of the proposed route of the estuary crossing. Therefore, the HDD
will have to pass through the gravelly sandy silt into the bedrock and back into the gravelly
sandy silt. The rock profile across the estuary can be seen in Appendix 2.
One of the methodologies been considered to install the rising main is by HDD. This is a
trenchless technology technique which is routinely used as an alternative to conventional open
cut and cover trenching or, as in this case, when minimal disturbance to the bed of the estuary is
favoured. This methodology requires the excavation of two pits.– a launch pit and a receiver pit.
In this case the launch pit would be excavated in the grounds of the proposed Ramelton main
pumping station site, commencing at Ch 0 as shown on Dwg. No 4940/CN4/RMR/SD/124.
Approximate dimensions for the excavation would be 10m long x 3m wide x 2m deep. By
reference to boreholes OWBH/RMR/16, excavation would be carried out in stiff to very stiff grey
slightly gravelly sandy SILT. Sides of the drive pit will be battered with no requirement for sheet
piling. The receiver pit would be located across the estuary on the north western side at
approximately Ch 260m. Access for plant and personnel will be via the R-247 and the wayleave
Jennings O’Donovan Consulting Engineers Sligo _________________________________________________________________________________________________
_________________________________________________________________________________________________ 4940-CN4-RMR-Esturary HDD Methodology Rev 1 2 March 2020
as per Dwg. No 4940/CN4/RMR/101. A reception pit with plan dimensions of 3m x 3m and depth
2m would be excavated. As was the case with the drive pit, sides of the excavation can be
battered with no requirement for sheet piling.
3 SCOPE OF WORK
A key component of the project is the launch pit and receiver pit where the HDD technology
and equipment will be used to install the 200mm HPPE PE 100 pipe SDR11 rising main.
The HDD crossing details are as follows:
➢ Hole length (HDD entry to exit): 260 meters approximately.
➢ Rising main diameter: 200mm O.D.
4 SITE PREPARATION
(i) Install hardstanding area or utilise existing surface if deemed acceptable to the
Contractor
(ii) Set up Environmental Control Measures
(iii) HDPE water supply line to rig site
(iv) Establish site office and welfare facilities
(v) Install rig anchor for the HDD rig
(vi) Set out centreline
(vii) Construct storage lagoon
(viii) Set up HDD rig spread
5 SITE LAYDOWN DESIGN
(i) Prepare and set out survey system for pilot hole
(ii) Tool calibration
(iii) Drill pilot hole with motor and drill bit from the launch pit to the reception pit.
(iv) Trip out pilot assembly
(v) Forward Ream using hole opener and bull nose fitted with a tri cone bit.
(vi) Trip in and out the reaming assembly to sufficiently clean the hole
(vii) Position reamer and bull nose and pump clearbore drilling fluid.
(viii) Set up Pipe puller and appropriate anchor mechanism.
(ix) Pig and test Pipeline
Jennings O’Donovan Consulting Engineers Sligo _________________________________________________________________________________________________
_________________________________________________________________________________________________ 4940-CN4-RMR-Esturary HDD Methodology Rev 1 3 March 2020
6 RIG ANCHORAGE AND SET UP
The drill rig will be set up on the proposed Ramelton Pumping Station site. The HDD should be
completed prior to commencement of the proposed Ramelton pumping station works to allow
enough space for the HDD to take place. Temporary works design will need to be undertaken to
ensure the thrust and pullback forces can be withstood during pilot drilling, reaming and pipe
pulling operations.
7 EXAMPLE OF PLANT LIST FOR HDD
➢ Drilling Rig
➢ Drilling Pump House
➢ Clear Solutions Mixing System
➢ Pipe Puller
➢ Clear Solution Re-cycling System
➢ Holding Tank
➢ Rig Power Unit
➢ Store
➢ Control Cabin
➢ Generator
➢ Trash Pump
➢ Tractor and Bowser
➢ Track Machine
8 PILOT HOLE
The drill Profile will be designed taking into account a number of considerations
➢ Hydraulic design requirements
➢ Formation and rock elevations
➢ Optimum steering radii
➢ Risk reduction on entry and exit angles
9 SURVEY AND TRACKING
9.1 Drill Guide – Gyro Steering Tool (GST)
Gyro steering tool provides highly accurate navigational information of the drill head in real time.
In doing so, it is not affected by any external influences. The Drill Guide GST is an optical gyro
tool that does not require any surface wire grids and is not affected by any external magnetic
interference. The tool does not require to be housed inside a non-magnetic drill collar and
therefore can be positioned nearer to the drill bit, giving accurate hole data as soon as possible.
Jennings O’Donovan Consulting Engineers Sligo _________________________________________________________________________________________________
_________________________________________________________________________________________________ 4940-CN4-RMR-Esturary HDD Methodology Rev 1 4 March 2020
10 PILOT HOLE DRILLING
Following completion of the survey, coil set-up drilling operations can commence. The initial stage
of drilling requires the assembly of the Bottom Hole Assembly (BHA). Before the drill motor is run
down, orientation of the bent housing and confirmation of the offset will be carried out. This
operation ensures the drillers directional display unit is accurately aligned with the drill motors
bent housing. Drilling will commence as the first length of approximately 9.5m drill pipe is run
down and the first surface survey is taken on the next joint.
The driller will progress the drill bit directed by the downhole surveyor with regard to the drilling
pattern required in achieving the radius design criteria. The drilling superintendent will determine
instructions for the drillers regarding maximum torque and push, and flow rates. Drill parameters
will be monitored and adjusted as required depending on the formation. Under direction from the
downhole surveyor the driller will be required to make minor course corrections to ensure the
design profile is achieved. From the driller’s display console the attitude of the drilling motor is
known, turning of the drill string orientates the drill bit to the required direction. A drill pattern will
be calculated whereby part of the drill rod is pushed without rotation of the drill string but with the
drill bit positioned in an orientation of 0 – 360 degrees. This dead push mode may only be required
for 1 - 2 metres of each joint depending on formation integrity. The remaining joint length will be
rotated so as to prevent a radical direction change from occurring.
It is the responsibility of the downhole surveyor to calculate drill patterns as drilling progresses,
with the driller following pre-set positions marked on the drill pipe where slide and rotation modes
are required. The sequence of drilling procedures outlined will continue until the drill bit exits at
the receiver pit.
11 REAMING
Verification of the survey data and validation of the pilot hole must be approved before
commencement of reaming operations. The reaming assembly will be used in a pull mode of
operation from the receiver pit
A survey tool may be run behind the hole opener (depending on the formation experienced during
pilot drilling) to confirm the tool is running true. It should be noted that the survey tool will only
provide inclination data as the surrounding drill pipe will affect the azimuth readings which will be
unacceptable for use. The inclination data will be beneficial in confirming that the tool is following
the previous drill line, particularly when building out of the first curve onto the horizontal section
Jennings O’Donovan Consulting Engineers Sligo _________________________________________________________________________________________________
_________________________________________________________________________________________________ 4940-CN4-RMR-Esturary HDD Methodology Rev 1 5 March 2020
of the hole. The hole opener will be progressed as the pilot hole with a length of drill pipe drilled
down and the next placed onto the rig floor for screw in.
If a survey tool is being run the wireline will be connected as with pilot drilling operations. A
conventional Tensor survey probe (TruTrack) will be used behind the hole opener. Surveys will
not be required as with the pilot hole drilling, the raw inclination data provided by the drillers
console will be sufficient for confirming the accuracy of hole openers.
As the hole opener progresses, swabbing of each joint to improve hole cleaning will be carried
out if the formation offers suitable resistance when cut. Swabbing the hole is the final step before
installing the product line and is performed by pulling a plug through the hole to remove cutting
debris and drilling fluid. Swabbing with the hole opener cannot be considered if formation strength
cannot support the tool, which could result in the tool dropping and losing its alignment with the
pilot hole.
12 DRILLING FLUID – USAGE AND CONTROL
During all phases of pilot drilling, hole opening and hole cleaning drilling fluid will be pumped. The
drilling fluid is pre-mixed on the surface before being pumped downhole via high pressure plunger
pumps. The flow rate of the fluid will be variable and depends on formation strengths and
particular tooling / nozzle configuration in use.
Prior to commencing works the mud pumps will be checked. As drilling progresses replacement
of the fluid end components may be required. Such components are a standard inclusion in the
spare parts inventory that will be mobilised with the high pressure pump.
On the surface, drilling fluid is mixed and delivered to the static active tank, which directly feeds
the high pressure plunger pump. Controls for the pressure pump is housed in the driller’s cabin
where volumes pumped can be adjusted to compensate for formation strengths encountered.
During pilot hole drilling and upsizing stages of the reaming process mud pumped downhole will
return to the surface and will be contained in the lagoon at the entry position. By way of an
electrical submersible slurry pump the drilling fluid will be transferred to the mud cleaning system.
The multi screened cleaning system will separate the cuttings from the fluid enabling the fluid to
be returned to the mixer and static holding tanks and then re-used downhole. Solids removed
from the mud returns will be collected in the holding pit excavated beneath the discharge chutes
Jennings O’Donovan Consulting Engineers Sligo _________________________________________________________________________________________________
_________________________________________________________________________________________________ 4940-CN4-RMR-Esturary HDD Methodology Rev 1 6 March 2020
attached to the mud cleaning shaker units. When sufficient solids have been deposited into the
holding pit they will be disposed to an approved disposal site.
13 DRILLING FLUID PRODUCTS
The drilling fluid used during the works will be clearbore. Clearbore is a polymer-based product
that is designed to instantly break down and become chemically destroyed in the presence of
small quantities of calcium hypochlorite. The product is not toxic to aquatic organisms and
biodegradable.
Mud mixing will be monitored to suit the ground conditions encountered and will initially be based
on a mud programme developed by the specialised HDD Contractor and the drilling fluid supplier
and Environmental expert.
The drilling fluids will be constantly monitored, and any changes required to the mix will be
performed on site by specialised HDD Contractor upon consultation with the drilling fluid supplier
and Ecological Clerk of Works (ECoW), appointed during the construction stage of the project by
the Employer.
14 DRILLING FLUID PARAMETERS
While drilling progresses mud returned to the lagoon will be checked for solids content and overall
fluid weight. It is envisaged that fluid returns will be maintained throughout the pilot, reaming and
cleaning stages. It is expected that mud weights will be high once all stages are completed. The
magnitude of the mud weight will depend on many factors but it could be as high as 1.4 (SG).
Mud testing equipment will be available at all times during drilling operations to monitor key mud
parameters.
15 DRILLING FLUID LOSS
The loss of drilling fluid can occur as a result of the geological formation that is being drilled
through. A brecciated or fractured formation will result in the loss of drilling fluid through cracks,
voids and fractures. If a frac-out occurs there will be a loss in drilling pressure, this is a signal to
the operator that an issue has arose with the drilling process. Clearbore drilling fluid is used to
minimise the risk to the environment in the case of a frac-out. There are a number of contingency
options available.
The method for reducing the drilling fluid losses and thereby control the consumption of water and
drilling fluid products is to identify the point of losses and seal the area off. The task is complex
and relies heavily on the experience of personnel and reliable, accurate drilling records interpreted
Jennings O’Donovan Consulting Engineers Sligo _________________________________________________________________________________________________
_________________________________________________________________________________________________ 4940-CN4-RMR-Esturary HDD Methodology Rev 1 7 March 2020
in relation to the geotechnical information available. Trends during the pilot drilling will be
monitored and tracked so as to maximise the chances of accurately establish a point where the
formation is causing drilling fluid losses.
At the location a number of measures can be implemented as follows:
➢ Pump drilling fluid with a higher density into the formation.
➢ Circulate and pump organic lost circulation materials (LCM) into the loss zone to physically
seal the fracture. Lost circulation occurs when drilling fluid, flows into one or more
geological formations instead of returning to the launch area.
➢ Grout the loss zone; and/or
➢ Launch a packer before the loss zone. A packer is a mechanical device sent down the
hole to the area of concern. It is designed for blocking the system for sealing grout to set.
It is recommended that all options are prepared for application during the HDD works.
All equipment will be carefully checked on a daily basis by the Site Supervisor prior to use within
the estuary to ensure plant and machinery is in good working order with no leaks or potential for
spillages. In order to minimise any risk of pollution in the first instance.
Spill kits, including an appropriate hydrocarbon boom will be available on the site in the event of
any unforeseen hydrocarbon spillages and all staff shall be trained in their use.
16 PIPE INSTALLATION
The 200mm HPPE PE 100 SDR11 rising main will be welded in one section using fully automatic
butt-welding techniques.
➢ All external beads will be removed and tested detailed in the welding procedure and
retained for reference.
➢ Sample welds will be cut out during the welding process and will be subjected to
destructive testing.
➢ The joint will be allowed to fully cool prior to testing.
➢ The section of pipe will be hydrostatically tested to the required standard
➢ The procedure of the pipe pulling operation will take place.
Jennings O’Donovan Consulting Engineers Sligo _________________________________________________________________________________________________
_________________________________________________________________________________________________ 4940-CN4-RMR-Esturary HDD Methodology Rev 1 8 March 2020
17 PIPE PIGGING AND PROVING
Pipe pigging and proving assembly will be set up at the launch pit. The pigging assembly will pass
through the pipe using compressed air. Pigging is completed to clean the internal of the pipe of
any debris and inspect the pipeline for any damage after installation.
18 PILOT HOLE CONTINGENCIES
The pilot hole drilling will progress from entry to exit, however there are several reasons why the
drill string may need to be recovered back to surface before completion of the pilot hole has been
achieved for e.g.
➢ Unable to maintain acceptable profile / alignment caused by steering difficulties
➢ Mud fracture to surface / formation.
Damaged or malfunctioning components will be required to be replaced as required for the HDD
works to continue.
Jennings O’Donovan Consulting Engineers Sligo _________________________________________________________________________________________________
_________________________________________________________________________________________________ 4940-CN4-RMR-Esturary HDD Methodology Rev 1 March 2020
APPENDIX 1 – PLAN AND LONGITUDINAL SECTION OF
THE RISING MAIN CROSSING
(ED R
athmelton)
BALLYBOE
Quay
(Site of)
Rathm
elton Castle
2.9
Mud
15.0
Leannan Bank
15.9
16.9
RO
SSREAG
H
17.2
26.6
18.0
23.5
18.0 UN
D
17.2
25.5
25.5
13.1
13.9
25.7
26.4
25.6
25.6
CR
4.5
HW
M
Hall
HW
M3.8 Under const
3.4
HWM
Mud
Rossreagh Point
BH/RMR/184: MEDIUM STRONGPSAMMITE AT 11m BGL
OWBH/RMR/14:
PSAMMITE BEDROCKAT 0.5m BRBL
OWBH/RMR/15:
WEATHERED PSAMMITE
AT 6.6m BRBLOWBH/RMR/16:
STIFF SILT TO10.5m BRBL
OWBH/RMR/13:
PSAMMITE BEDROCKAT 1m BRBL
R-247
LEANNAN ESTUARYRATHMELTONPUMPING STATION
STRIP OF MATURE OAK WOODLAND
L-5672
COPYRIGHT OFC
modificationsrev.
bydate
4940/CN4/RMR/101Drawing No.
Revision
Client
ProjectRATHMELTON, MILLFORD ANDRATHMULLAN SEW
ERAGESCHEME - CONTRACT NO.4
StagePLANNINGTitle
Scales
SurveyedPrepared By
CheckedDate
JENNINGS O'DONOVAN & PARTNERS LIMITEDCONSULTING ENGINEERS,FINISKLIN,SLIGO,IRELAND.TEL. (0035371) 9161416.FAX. (0035371) 9161080.Em
ail. [email protected]
eb. www.jodireland.com
LEANNAN ESTUARY RISING MAINCROSSING
NOTES:1 FIGURED DIMENSIONS ONLY TO BE TAKEN FROM THIS DRAWING.2 ALL DRAWINGS TO BE CHECKED BY THE CONTRACTOR ON SITE.3 ENGINEER TO BE INFORMED OF ANY DISCREPANCIES BEFORE ANY WORK COMMENCES.4 THIS DRAWING TO BE READ IN CONJUNCTION WITH ALL OTHER RELEVANT DRAWINGS AND SPECIFICATIONS.
1:1250 (A1) 1:2500 (A3)
IRISH WATER
LEGEN
D
Ordnance Survey Ireland Licence N
o.EN 0002620
© O
rdnance Survey Ireland / Governm
ent of IrelandO
s Map R
ef: 0186-D
LOU
GH
SWILLY SAC
Jan. 2020
LOU
GH
SWILLY SPA
WAYLEAVE
TEMPO
RAR
Y WO
RKIN
G AR
EA
PERM
ANEN
T ACQ
UISITIO
N
200mm
OD
RISIN
G M
AIN
BOR
EHO
LE LOC
ATION
(Note:
BRBL - Below
River Bed Level)
N
Leannan Bank
HWM
Market Sq.
StreetPoun
d
Market Sq.
StreetPoun
d
HWM
ROSSREAGH
HWM HWM
Quay
Mud
Rathmelton Castle (Site of)
Hall
26.4
9.2
23.5
26.6
15.9
16.9
17.2
18.0
18.0
3.4
3.6
2.9
4.5
6.5
-4 -3 -2 -1 0 1 2 3 4 5 6 7 8 9
10 11 12 13 14
15 16 17
-5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Chainage
Ground Level
Pipe
Valve Chainage
Surface
RISIN
G M
AIN PIPELIN
E FRO
M R
ATHM
ELTON
TO L-1392-2 JU
NC
TION
- SHEET 1
Scale: Horizontal 1:1000
Scale: Vertical 1:100
CU
MU
LATIVE CH
AINAG
E 0m.
CU
MU
LATIVE CH
AINAG
E 560m.
01.RT
RT-D
AV-01
RT-SV-H
P-01
WATER
RO
AD
200mm
O.D
. HPPE PE 100 SD
R 11 R
ISING
MAIN
WATER
FIELD
PIPE GR
ADED
02.RT02.RT
FIELD
RISIN
G M
AIN PIPELIN
E FRO
M R
ATHM
ELTON
TO L-1392-2 JU
NC
TION
- SHEET 1
Scale: Horizontal 1:2000
Scale: Vertical 1:200
COPYRIGHT OFC
modificationsrev.
bydate
Drawing No.Revision
ClientIRISH WATER
Project
StageCONTRACTTitle
Scales1:1000 & 100 @ (A1)Surveyed
Prepared ByChecked
Date
JENNINGS O'DONOVAN & PARTNERS LIMITEDCONSULTING ENGINEERS,FINISKLIN,SLIGO,IRELAND.TEL. (0035371) 9161416.FAX. (0035371) 9161080.Em
ail. [email protected]
eb. www.jodireland.com
MURPHYS
Ordnance Survey Ireland Licence N
o.EN 0002619
© O
rdnance Survey Ireland / Governm
ent of Ireland
LAYOUT PLANScale 1:1000 (A1)
N
PRO
POSED
RAM
ELTON
PUM
PING
STATION
OS SHEET Donegal No.0146,0164,0165,0166, 0186 & 0187
RO
SSREAG
H
LEANNAN
RAM
ELTON
01.R
T
To MILFO
RD
To RAMELTON
IND
EX PLAN - N
TS RAM
ELTON
RATH
MU
LLAN
MILFO
RD
124
4940-CN4-RMR-SD-124
RAMELTON, MILFORD ANDRATHMULLAN SEW
ERAGE SCHEMECONTRACT No. 4
RAMELTON TO L-1392-2 RISING MAINLAYOUT PLAN AND LONGITUDINALSECTIONSHEET 1 OF 6
Draft Issue for DCC ReviewA
LB12/18
225
NO
TE : THIS M
AP IND
ICATED
THE APPR
OXIM
ATE LOC
ATION
OF SER
VICES.
BEFOR
E ANY EXC
AVATION
IS UN
DER
TAKEN, TH
E ACTU
AL LOC
ATION
OF ALL
SERVIC
ES MU
ST BE ESTABLISHED
AND
VERIFIED
.
LEGEN
D:
PRO
POSED
NO
DE show
n thus
PRO
POSED
HYD
RAN
T shown thus
PRO
POSED
AIR VALVE show
n thus
PRO
POSED
SLUIC
E VALVE & HATC
H BO
Xshow
n thus
PRO
POSED
RAW
WATER
MAIN
shown thus
PRO
POSED
TRU
NK M
AIN show
n thus
PRO
POSED
DISTR
IBUTIO
N M
AIN show
n thus
EXISTING
MAIN
shown thus
ESB POW
ER LIN
ES CR
OSSIN
G R
OAD
EIRC
OM
CABLES show
n thus
ESB - MV & LV O
VERH
EAD LIN
ES
EXISTING
RO
AD SIG
N show
n thus
DAV-N
o.
Hyd-N
o
SLV-HP- N
o.
NO
TES1.
Levels are in meters O
.D and refer to M
alin Head D
atum.
2.This D
rawing is to be read in conjunction w
ith all otherrelevant docum
entation.3.
Do not scale from
this drawing, use only printed dim
ensions.4.
All dimensions in m
illimetres, all chainages, levels and coordinates are in
metres unless defined otherw
ise.5.
This drawing is to be read in conjunction w
ith the project Health and
Safety File for any identified potential risks.6.
For Existing Services see SI report and drawings from
providers.C
ontractor to identify and verify the position of all services on site.6.
All Pipework to be laid at m
inimum
gradient 1:300.7.
Minim
um cover to Pipelines 1000m
m.
8.Extensive trial holes to be dug prior to w
orks comm
encing on site -all services to be located, identified and depths recorded. Protection of allexisting services to be agreed w
ith RE on site depending on depth and
location in relation to our works.
EXISTING
SUS SU
RVEY LEG
END
Foul
Surface
Com
bined
Overflow
Pumped line
P.F.R. Plotted From
Records
U.T.F. U
nable To Find
U.T.S. U
nable To Survey
U.T.L. U
nable To Lift
Pipe diameter of
major outgoing pipe
TEXT ANN
OTATIO
N
Manhole R
ef.
Survey Status
Cover Level
Invert Level
6901
Yes
40.740
X:38.340
?.M
D
MARCH 2019
B
Post Detail Design ReviewB
LB03/19
RT-AC
C-02
RT-AC
C-03
RT-AC
C-01
02.R
T
Jennings O’Donovan Consulting Engineers Sligo _________________________________________________________________________________________________
_________________________________________________________________________________________________ 4940-CN4-RMR-Esturary HDD Methodology Rev 1 March 2020
APPENDIX 2 – ROCK PROFILE
Jennings O’Donovan Consulting Engineers Sligo _________________________________________________________________________________________________
_________________________________________________________________________________________________ 4940-CN4-RMR-Esturary HDD Methodology Rev 1 March 2020
APPENDIX 3 – SITE INVESTIGATIONS
Depth Sa ple / Tests Field Records
Casi gDepth
Water Depth
LevelOD
- .
Depth
.
.
Lege d Descrip o
Bro ish grey sa dy silty su a gular e to oarse GRAVEL. Sa d is e to oarse.
Weathered PSAMMITE: re o ered as su a gular e to oarse
Wat
er
Back ll
.
.
. B
Samples / Field Records TCR SCR RQD FI
. - .
- .
.
.
GRAVEL of psa ite ith lo o le o te t. Co les are a gular to su a gular of psa iteWeak to ediu stro g lo ally stro g i dis tly thi ly foliated light grey a d grey PSAMMITE. Par ally eathered: loser fra ture spa i g a d dis oloura o o fra ture surfa es
Dis o ui es:
. to degree joi ts, losely spa ed / / , u dula g, rough, pat hy ro ish ora ge stai i g o joi t surfa es
. to degree joi ts, ediu spa ed / / , u dula g, rough, pat hy ro ish ora ge stai i g o joi t surfa es
. to degree joi ts at . to . , slightly u dula g, rough, stro g ro ish ora ge stai i g o joi t surfa es
End of Borehole at 4.20m
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. B
. - . SPT C N= for / for Ha er SN
=
.
.
.
Project No.
- 5Project Na e:
Clie t:
Clie t's Rep:
Rath ulla Se erage S he e Site I es ga o
Irish Water
Je i gs O'Do o a a d Part ers Li ited
Borehole ID
OWBH/RMR/ 3
Coordi ates
. E
. N
Fi al Depth: .
Eleva o : . OD
Start Date:
E d Date:
/ /
/ /
Driller:
Logger:
Sheet of
S ale: :
FINAL
Core Barrel Flush Type
T - /T - Air
Re arksDrilled fro spudded oa g pla or .Ro khead hard; progressi g orehole e o d . ot possi le ith a aila le rig a d ari e pla t.
Ter i a o ReasoTer i ated at . elo ri er ed o e tre el hard
edro k; . of o pete t ore re o ered
Last Updated
/ /
Method Pla t Used Top Base Ca le Per ussio Da do . .
Rotary Cori g Ha ji D . .
Water StrikesStru k at Casi g to Ti e i Rose to
Casi g DetailsTo Dia
.
Water AddedFro To
Chiselli g DetailsFro To Ti e hh:
. . :
Depth Sa ple / Tests Field Records
Casi gDepth
Water Depth
LevelOD
- .
Depth
.
.
Lege d Descrip o
Greyish ro silty sa dy su a gular to su rou ded e to oarse GRAVEL. Sa d is e to oarse.
WEATHERED PSAMMITE BEDROCK: re o ered as sa dy slightly silty
Wat
er
Back ll
.. B
Samples / Field Records TCR SCR RQD FI
. - .
- .
- .
- .
.
.
.
.
.
.
su a gular e to oarse GRAVEL of psa ite ith lo o le o te t. Sa d is e to oarse. Co les are a gular to su a gular of
psa ite.Mediu stro g lo ally eak thi ly foliated light grey a d dark grey PSAMMITE. Par ally eathered: loser fra ture spa i g, dis oloura o a d silt deposits o fra ture surfa es. Dis o ui es:
. to degree folia o fra tures, losely spa ed / / slightly u dula g, s ooth, pat hy ro ish ora ge a d pat hy light grey silt o fra tures.
Mediu stro g lo ally eak thi kly foliated grey ith losely spa ed irregular la k a ds SEMI-PELITE. Par ally eathered: loser fra ture spa i g a d silt deposits o fra ture surfa es.
Dis o ui es:. to degree folia o fra tures, losely spa ed / /
pla ar, s ooth, pat hy light grey silt o fra ture surfa es. . to degree joi ts at . to . , a d . to . ,
stepped, rough, lea .
Mediu stro g lo ally eak thi ly foliated grey PSAMMITE. Par ally eathered: loser fra ture spa i g a d silt deposits o fra tures surfa es. Dis o ui es:
. to degree folia o fra tures, losely spa ed / / slightly u dula g, s ooth ith pat hy light grey silt o fra ture surfa es.
End of Borehole at 7.40m
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. B
. - . SPT C N= for / for Ha er SN
=
.
.
.
.
.
.
Project No.
-Project Na e:
Clie t:
Clie t's Rep:
Rath ulla Se erage S he e Site I es ga o
Irish Water
Je i gs O'Do o a a d Part ers Li ited
Borehole ID
OWBH/RMR/
Coordi ates
. E
. N
Fi al Depth: .
Eleva o : - . OD
Start Date:
E d Date:
/ /
/ /
Driller:
Logger:
Sheet of
S ale: :
FINAL
Core Barrel Flush Type
SK L/T - Air
Re arksDrilled fro spudded oa g pla or .Ro khead hard; progressi g orehole e o d . ot possi le ith a aila le rig a d ari e pla t.
Ter i a o ReasoTer i ated at . elo ri er ed o e tre el hard
edro k; . of o pete t ore re o ered
Last Updated
/ /
Method Pla t Used Top Base Ca le Per ussio Da do . .
Rotary Cori g Ha ji D . .
Water StrikesStru k at Casi g to Ti e i Rose to
Casi g DetailsTo Dia
.
Water AddedFro To
Chiselli g DetailsFro To Ti e hh:
. . :
Depth Sa ple / Tests Field Records
Casi gDepth
Water Depth
LevelOD
- .
- .
Depth
.
.
Lege d Descrip o
Greyish ro silty sa dy su a gular to su rou ded e to oarse GRAVEL ith lo o le o te t. Sa d is e to oarse.
Possi le Weathered PSAMMITE: re o ered as su a gular e to oarse GRAVEL of psa ite ith lo o le o te t. Co les are
a gular to su a gular of psa ite.End of Borehole at 1.43m
Wat
er
Back ll
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. - . SPT S N= for / for Ha er SN =
.
Project No.
-Project Na e:
Clie t:
Clie t's Rep:
Rath ulla Se erage S he e Site I es ga o
Irish Water
Je i gs O'Do o a a d Part ers Li ited
Borehole ID
OWBH/RMR/ A
Coordi ates
. E
. N
Fi al Depth: .
Eleva o : - . OD
Start Date:
E d Date:
/ /
/ /
Driller:
Logger:
Sheet of
S ale: :
FINAL
Re arksDrilled fro spudded oa g pla or .To o r shallo ro khead fou d i OWBH/RMR/
Ter i a o Reaso
Refusal o eathered edro k at . elo ri er ed
Last Updated
/ /
Method Pla t Used Top Base Ca le Per ussio Da do . .
Water StrikesStru k at Casi g to Ti e i Rose to
Casi g DetailsTo Dia eter
.
Water AddedFro To
Chiselli g DetailsFro To Ti e hh:
. . :
Depth Sa ple / Tests Field Records
Casi gDepth
Water Depth
LevelOD
- .
- .
- .
Depth
.
.
.
.
Lege d Descrip o
G eyish o sa dy silty su a gula to su ou ded e to oa se GRAVEL. Sa d is e to oa se.
Ve y so g eyish o slightly sa dy slightly g a elly o ga i SILT ith shell f ag e ts. Sa d is e to oa se. G a el is su a gula to
su ou ded e to ediu .
Mediu de se g eyish o sa dy slightly silty su a gula e to oa se GRAVEL. Sa d is e to oa se.
BOULDER of PSAMMITE.
Wat
er
Back ll
.
.
.
.
. B
. B
. - . SPT S N= , / , , , Ha e SN = .
. B
- .
- .
- .
- .
.
.
.
.
Fi to s o ish g ey slightly sa dy g a elly SILT ith lo o le a d oulde o te t. Sa d is e to oa se. G a el is su a gula to su ou ded e to oa se. Co les a d oulde s a e su ou ded.
BOULDER of PSAMMITE.
Ve y s g ey slightly g a elly sa dy SILT ith lo o le a d oulde o te t. Sa d is e to oa se. G a el is su a gula to su ou ded
e to oa se. Co les a d oulde s a e su a gula to su ou ded.
Weathe ed PSAMMITE. D ille s Des ip o
.
.
.
.
.
.
.
.
.
.
. - . SPT S N= fo / fo Ha e SN =
.
. - . SPT C N= , / , , , Ha e SN = .
. - . SPT C N= , / , , , Ha e SN =
.
Wate st ike at .
Samples / Field Records TCR SCR RQD
NR
FI
- .
- .
.
.
Mediu st o g lo ally e y st o g i dis tly thi ly foliated da k g ey PSAMMITE. Pa ally eathe ed: lose f a tu e spa i g, dis olou a o a d silt deposits o f a tu e su fa es.Dis o ui es:
. to deg ee joi ts, losely spa ed / / u dula g, ough, o a gish o stai i g a d o ish g ey pat hy silt o
f a tu e su fa es.
Weak lo ally ediu st o g thi kly foliated g ey ith losely pa ed i egula la k a ds SEMI-PELITE ith losely spa ed a o
a ds of hite ua tzite. Pa ally eathe ed: lose f a tu e spa i g, dis olou a o a d silt deposits o f a tu e su fa es.Dis o ites:
.
.
.
.
.
Project No.
- 5Project Na e:
Clie t:
Clie t's Rep:
Rath ulla Se erage S he e Site I es ga o
Irish Water
Je i gs O'Do o a a d Part ers Li ited
Borehole ID
OWBH/RMR/ 5
Coordi ates
. E
. N
Fi al Depth: .
Eleva o : - . OD
Start Date:
E d Date:
/ /
/ /
Driller:
Logger:
Sheet of
S ale: :
FINAL
Core Barrel Flush Type
SK L Air
Re arksDrilled fro spudded oa g pla or .
Ter i a o Reaso
Borehole ter i ated i edro k at . elo ri er ed
Last Updated
/ /
Method Pla t Used Top Base Ca le Pe ussio Da do . .
Rota y D illi g Ha ji D . .Rota y Co i g Ha ji D . .
Water StrikesSt u k at Casi g to Ti e i Rose to
. .
Casi g DetailsTo Dia
.
Water AddedF o To
Chiselli g DetailsF o To Ti e hh:
. . :
Depth Sa ple / Tests Field Records
Casi gDepth
Water Depth
LevelOD
- .
- .
Depth
.
.
Lege d Descrip o
Fir to s ro ish grey sa dy gra elly silty CLAY ith lo o le a d oulder o te t. Sa d is e to oarse. Gra el is su a gular to su rou ded e to oarse. Co les a d oulders are su rou ded.
S to ery s grey slightly sa dy slightly gra elly layey SILT ith lo o le a d oulder o te t. Sa d is e to oarse. Gra el is su a gular to su rou ded e to oarse. Co les a d oulders are su a gular to su rou ded.
S to ery s grey slightly sa dy slightly gra elly silty CLAY ith lo o le a d oulder o te t. Sa d is e to oarse. Gra el is su a gular to su rou ded e to ediu .
Wat
er
Back ll
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. B
. B
. D
. - . SPT S N= , / , , , Ha er SN = .
. B
. D
. - . SPT S N= , / , , , Ha er SN = .
. B
. D
. - . SPT S N= , / , , , Ha er SN = .
. B
. D
. - . SPT S N= , / , , , Ha er SN = .
. B
. D
. - . SPT S N= , / , , , Ha er SN =
.
. B
. D
. - . SPT S N= , / , , , Ha er SN = .
Project No.
-Project Na e:
Clie t:
Clie t's Rep:
Rath ulla Se erage S he e Site I es ga o
Irish Water
Je i gs O'Do o a a d Part ers Li ited
Borehole ID
OWBH/RMR/
Coordi ates
. E
. N
Fi al Depth: .
Eleva o : - . OD
Start Date:
E d Date:
/ /
/ /
Driller:
Logger:
Sheet of
S ale: :
FINAL
Re arksDrilled fro spudded oa g pla or .
Ter i a o Reaso
Refusal o eathered edro k at . elo ri er ed
Last Updated
/ /
Method Pla t Used Top Base Ca le Per ussio Da do . .
Water StrikesStru k at Casi g to Ti e i Rose to
Casi g DetailsTo Dia eter
.
Water AddedFro To
Chiselli g DetailsFro To Ti e hh:
Depth Sa ple / Tests Field Records
Casi gDepth
Water Depth
LevelOD
- .
- .
Depth
.
.
Lege d Descrip o
S to ery s grey slightly sa dy slightly gra elly silty CLAY ith lo o le a d oulder o te t. Sa d is e to oarse. Gra el is su a gular to su rou ded e to ediu .
S to ery s grey slightly sa dy slightly gra elly SILT ith lo o le a d oulder o te t. Sa d is e to oarse. Gra el is
su a gular to su rou ded e to oarse. Co les a d oulders are su a gular to su rou ded.
End of Borehole at 10.50m
Wat
er
Back ll
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. B
. D
. - . SPT S N= , / , , , Ha er SN = .
. B
. D
. - . SPT S N= , / , , , Ha er SN = .
. B
. D
. - . SPT S N= , / , , , Ha er SN =
.
Project No.
-Project Na e:
Clie t:
Clie t's Rep:
Rath ulla Se erage S he e Site I es ga o
Irish Water
Je i gs O'Do o a a d Part ers Li ited
Borehole ID
OWBH/RMR/
Coordi ates
. E
. N
Fi al Depth: .
Eleva o : - . OD
Start Date:
E d Date:
/ /
/ /
Driller:
Logger:
Sheet of
S ale: :
FINAL
Re arksDrilled fro spudded oa g pla or .
Ter i a o Reaso
Refusal o eathered edro k at . elo ri er ed
Last Updated
/ /
Method Pla t Used Top Base Ca le Per ussio Da do . .
Water StrikesStru k at Casi g to Ti e i Rose to
Casi g DetailsTo Dia eter
.
Water AddedFro To
Chiselli g DetailsFro To Ti e hh:
Depth Sa ple / Tests
Casi gDepth
Water Depth Field Records Level
OD.
.
.
Depth Thick ess
..
.
.
.
.
.
.
Lege d Descrip o
TOPSOILFir ro slightly sa dy slightly gra elly SILT ith lo o le o te t. Sa d is e to oarse. Gra el is su rou ded e to ediu . Co les are su rou ded.
S ro slightly sa dy slightly gra elly SILT ith lo o le o te t. Sa d is e to oarse. Gra el is su rou ded e to ediu . Co les are su rou ded.
Very s grey slightly gra elly sa dy SILT. Sa d is e to oarse. Gra el is su rou ded e to ediu .
Wat
er Back ll
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. - . B
. - . B
. - . U . U lo = %
. D
. - . B
. - . SPT SN=
. N= , / , , ,
. - . U . U lo = %
. - . B
. D
. - . B
. - . SPT SN=
. N= , / , , ,Water Strike at
.
. - . U . U lo = %
. - . B
. D
. - . B
. - . SPT SN=
N= , / , , ,
. D
. - . B
. - . SPT SN=
N= , / , , ,
. D
. - . B
. - . SPT SN=
N= , / , , ,
. D
TCR SCR RQD FI
- .
- .
- .
.
.
.
.
.
BOULDER
Fir grey slightly sa dy gra elly CLAY. Sa d is e to oarse. Gra el is su a gular to su rou ded e to oarseFir greyish ro slightly sa dy gra elly CLAY. Sa d is e to oarse. Gra el is su rou ded e to ediu
.
.
. - . N= for / for
- -
Project No.:-
Coordi ates:
. E
. N
Grou d Level:. OD
Project Na e:Ra elto Milford Rath ulla RMR Se erage Sche eClie t:Irish WaterClie t's Represe ta ve:Je i gs O'Do o a & Part ers LtdDates:
/ / - / /
Borehole No.:BH/RMR/184
Sheet of
Scale: :
Driller:
Logger:
Re arksHa d dug i spec o pit exca ated to . .
Ter i ated o irtual refusal at .
Core Barrel
Flush Type
Method Pla t Used Top BaseLight Per ussio Da do Terrier . .
Rotary Cori g D Ha ji . .
Water StrikesStru k at Casi g to Ti e i Rose to
. . .
Water AddedFro To
Casi g DetailsTo Dia
.
Chiselli g DetailsFro To Ti e hh:
Depth TCR
TCR
SCR
SCR
RQD
RQD
FI
>
>
>
>
FI
Field Records LevelOD
- .
- .
- .
- .
- .
- .
- .
Depth Thick ess
.
.
.
.
.
.
.
.
.
.
.
.
Lege d Descrip o
Mediu stro g thi ly la i ated light grey PSAMMITE. Par ally eathered: silt deposits a d dis oloura o o fra ture surfa es
Dis o ui es:
. - degree joi ts, losely spa ed / / , u dula g, rough, pat hy ora ge a d ro ish yello stai i g ith yello ish grey silt deposits o joi t surfa es
. degree folia o fra ture at . - . , pla ar, rough, pat hy ora ge stai i g a d l of yello ish grey silt of fra ture surfa esMediu stro g lo ally eak , thi kly la i ated light grey PSAMMITE,
arro ly i ter edded ith dark grey PELITE. Par ally eathered: silt deposits a d dis oloura o o fra ture surfa es
Dis o ui es:
. - degree folia o fra tures, losely spa ed / / , slightly u dula g, s ooth, stro g pat hy ora ge a d yello ish ora ge stai i g
ith yello ish grey silt deposits o fra ture surfa esMediu stro g lo ally eak thi kly la i ated light grey PSAMMITE. Par ally eathered: silt deposits a d dis oloura o o fra ture surfa es
Dis o ui es:
. - degree folia o fra tures, losely spa ed / / , pla ar, rough, pat hy ora ge, ora gish yello a d yello ish ro stai s ith pat hy yello ish hite silt deposits o fra ture surfa esMediu stro g thi ly la i ated light grey PSAMMITE. Par ally
eathered: silt deposits a d dis oloura o o fra ture surfa es
Dis o ui es:
. - degree folia o fra tures, ediu spa ed / / , slightly u dula g, rough, pat hy ora ge, yello ish ora ge a d ora gish ro stai s ith pat hy yello ish hite a d light ro silt deposits o fra ture surfa es
. - degree folia o fra tures, ediu spa ed / / , slightly u dula g, rough, pat hy ora ge, yello ish ora ge a d ora gish
ro stai s ith pat hy yello ish hite a d light ro silt deposits o fra ture surfa es
. > degree joi t at . - . , pla ar, rough, pat hy light ora ge stai i g a d pat hy yello ish hite silt deposits o joi t surfa es
At 14.35m: 30mm orangish brown clayAt 14.40m - 14.50m: very narrowly interbedded thin laminations of dark grey pelite and psammiteAt 16.00m - 16.25m: very weak thickly laminated greyish brown psammite -possible fault gouge
Weak lo ally ediu stro g , thi ly la i ated dark grey PELITE. Par ally eathered: silt deposits a d dis oloura o o fra ture surfa es
Dis o ui es:
. - degree folia o fra tures, ery losely spa ed / / , u dula g, s ooth, pat hy ora gish ro stai i g ith pat hy ro silt a d l s of light grey silt o fra ture surfa es
At 18.45m - 18.50m: gravelly dark brown clay - possible fault gouge
Mediu stro g thi ly la i ated light grey PSAMMITE. Par ally eathered: silt deposits o fra ture surfa es
Dis o ui es:
. - degree folia o fra tures, losely spa ed / / , slightly u dula g, rough, pat hy, light grey silt deposits o fra ture surfa es
Wat
er Back ll
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
Project No.:-
Coordi ates:
. E
. N
Grou d Level:. OD
Project Na e:Ra elto Milford Rath ulla RMR Se erage Sche eClie t:Irish WaterClie t's Represe ta ve:Je i gs O'Do o a & Part ers LtdDates:
/ / - / /
Borehole No.:BH/RMR/184
Sheet of
Scale: :
Driller:
Logger:
Re arksHa d dug i spec o pit exca ated to . .
Ter i ated o irtual refusal at .
Core Barrel
Flush Type
Method Pla t Used Top BaseLight Per ussio Da do Terrier . .
Rotary Cori g D Ha ji . .
Water StrikesStru k at Casi g to Ti e i Rose to
Water AddedFro To
Casi g DetailsTo Dia
.
Chiselli g DetailsFro To Ti e hh:
Depth TCR
TCR
SCR
SCR
RQD
RQD
FI
FI
Field Records LevelOD
Depth Thick ess Lege d Descrip o
Mediu stro g thi ly la i ated light grey PSAMMITE. Par ally eathered: silt deposits o fra ture surfa es
Dis o ui es:
. - degree folia o fra tures, losely spa ed / / , slightly u dula g, rough, pat hy, light grey silt deposits o fra ture surfa es
. > degree joi t at . - . , u dula g, rough, pat hy light grey silt deposits o joi t surfa es
End of Borehole at 19.90m
Wat
er Back ll
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
Project No.:-
Coordi ates:
. E
. N
Grou d Level:. OD
Project Na e:Ra elto Milford Rath ulla RMR Se erage Sche eClie t:Irish WaterClie t's Represe ta ve:Je i gs O'Do o a & Part ers LtdDates:
/ / - / /
Borehole No.:BH/RMR/184
Sheet of
Scale: :
Driller:
Logger:
Re arksHa d dug i spec o pit exca ated to . .
Ter i ated o irtual refusal at .
Core Barrel
Flush Type
Method Pla t Used Top BaseLight Per ussio Da do Terrier . .
Rotary Cori g D Ha ji . .
Water StrikesStru k at Casi g to Ti e i Rose to
Water AddedFro To
Casi g DetailsTo Dia
.
Chiselli g DetailsFro To Ti e hh: