GUIDELINES - APPENDIX E Appendix E – Guidelines Table of Contents GUIDELINES FOR MODEL 170 TRAFFIC CONTROL EQUIPMENT...................................................................... E-1 SPECIAL FUNDED PROJECTS: http://www.dot.ca.gov/hq/esc/osfp/ DEVELOPING SPECIAL FUNDED PROJECTS DEPUTY DIRECTIVE 23-R-2 (Rev 12/18) ....................................... E-6 TRANSPORTATION MANAGEMENT PLAN GUIDELINES: http://www.dot.ca.gov/hq/traffops/trafmgmt/tmp_lcs/index.htm ENCROACHMENT PERMIT - H SUPPORT DIAGRAM FOR AERIAL CROSSINGS (TR-0108) ............................. E-15 ENCROACHMENT PERMIT - SETTLEMENT ROD DETAIL (TR-0152)................................................................ E-16 ENCROACHMENT PERMIT - SURVEY GRID (TR-0151) ................................................................................... E-17 ENCROACHMENT PERMIT - TRENCH DETAIL (TR-0153)................................................................................ E-18 ...................................................................................................................................................................... E-19 GUIDELINESS FOR THE PLACEMENT OF NEWSPAPER VENDING MACHINES IN SAFETY ROADSIDE REST AREAS JOINT OPERATIONAL POLICY STATEMENT - SPECIAL EVENTS ON CONVENTIONAL HIGHWAY RIGHTS-OF-WAY ...................................................................................................................................................................... E-25 PROFESSIONAL ENGINEERS ACT (EXCERPTS FROM THE BUSINESS AND PROFESSIONS CODE).................... E-30 INCLUSION OF EXPIRATION DATE ON ENGINEERING AND LAND SURVEYING DOCUMENTS MEMO………… E-31 GUIDELINES FOR KIOSK ADVERTISING/DISPLAYS IN SAFETY ROADSIDE REST AREAS .................................. E-32 GUIDELINES FOR SUBMITTING TRANSPORTATION INFORMATION FROM A REPORTING OR MONITORING PROGRAM TO THE CALIFORNIA DEPARTMENT OF TRANSPORTATION ........................................................ E-37 GUIDELINES FOR THE PLACEMENT OF TRAVELER DISCOUNT BOOKLETS IN SAFETY ROADSIDE REST AREAS ..... ..................................................................................................................................................................... .E-45 GUIDELINES AND SPECIFICATIONS FOR TRENCHLESS TECHNOLOGY PROJECTS ......................................... E-52 ENCROACHMENT PERMITS MANUAL | TRAFFIC OPERATIONS CURRENT AS OF: 03/2019 E-i
Appendix E – GuidelinesSPECIAL FUNDED PROJECTS:
http://www.dot.ca.gov/hq/esc/osfp/
DEVELOPING SPECIAL FUNDED PROJECTS DEPUTY DIRECTIVE 23-R-2 (Rev
12/18) ....................................... E-6
TRANSPORTATION MANAGEMENT PLAN GUIDELINES:
http://www.dot.ca.gov/hq/traffops/trafmgmt/tmp_lcs/index.htm
ENCROACHMENT PERMIT - H SUPPORT DIAGRAM FOR AERIAL CROSSINGS
(TR-0108) ............................. E-15
ENCROACHMENT PERMIT - SETTLEMENT ROD DETAIL
(TR-0152)................................................................
E-16
ENCROACHMENT PERMIT - SURVEY GRID (TR-0151)
...................................................................................
E-17
ENCROACHMENT PERMIT - TRENCH DETAIL
(TR-0153)................................................................................
E-18
......................................................................................................................................................................
E-19 GUIDELINESS FOR THE PLACEMENT OF NEWSPAPER VENDING MACHINES IN
SAFETY ROADSIDE REST AREAS
JOINT OPERATIONAL POLICY STATEMENT - SPECIAL EVENTS ON CONVENTIONAL
HIGHWAY RIGHTS-OF-WAY
......................................................................................................................................................................
E-25
PROFESSIONAL ENGINEERS ACT (EXCERPTS FROM THE BUSINESS AND
PROFESSIONS CODE).................... E-30
INCLUSION OF EXPIRATION DATE ON ENGINEERING AND LAND SURVEYING
DOCUMENTS MEMO………… E-31
GUIDELINES FOR KIOSK ADVERTISING/DISPLAYS IN SAFETY ROADSIDE REST
AREAS .................................. E-32
GUIDELINES FOR SUBMITTING TRANSPORTATION INFORMATION FROM A
REPORTING OR MONITORING PROGRAM TO THE CALIFORNIA DEPARTMENT OF
TRANSPORTATION........................................................
E-37
GUIDELINES FOR THE PLACEMENT OF TRAVELER DISCOUNT BOOKLETS IN
SAFETY ROADSIDE REST AREAS.....
.....................................................................................................................................................................
.E-45
GUIDELINES AND SPECIFICATIONS FOR TRENCHLESS TECHNOLOGY PROJECTS
......................................... E-52
ENCROACHMENT PERMITS MANUAL | TRAFFIC OPERATIONS CURRENT AS OF:
03/2019 E-i
Privately funded projects without a Cooperative Agreement - Project
proponent pays costs for Department furnished controller
assembly.
These costs are updated annually, if necessary, after determining
the average actual cost for the Department to acquire, test, stock
and ship the equipment to the local District. For additional
equipment and their associated costs, please see the attached price
list.
These costs should be included in the deposit prior to the issuance
of the contractor's encroachment permit. In cases where there is a
long lead-time before starting work, these costs may be submitted
immediately prior to performing work on a signal system.
Districts should determine and charge additional fees covering the
actual cost to deliver, install, inspect, and turn on traffic
signal controllers.
Projects involving Cooperative Agreements - Project proponent pays
costs for Department furnished controller assembly
The traffic signal controllers, and all other actual costs incurred
by Caltrans, are charged against the appropriate Cooperative
Agreement Expenditure Authorization. When there is Department
participation in the project, the Department's share of the actual
costs of the project will be reduced by the actual cost of the
controllers, which include controller fee, testing costs and any
other mandatory charges.
Procedures to order controller assemblies from the Department’s
warehouse
To allow time for delivery to the District, controller assemblies
shall be ordered from the Sacramento warehouse a minimum of 10
working days before a permittee plans to pick up an assembly in the
district (controller not included). Caltrans Maintenance or Traffic
staff will deliver actual controllers and auxiliary equipment to
job sites at the time of a scheduled signal turn on.
Charges for Encroachment Permit projects
As each controller assembly is ordered, the districts shall
instruct the Caltrans warehouse in Sacramento to charge the
equipment to the Encroachment Permit Expenditure Authorization (EA)
937700, using Subjob 3EPIC and Object Code 118. A Special
Designation (SD) of 7CONTROL must also be used if the permittee has
paid a fee for the equipment.
Charges for Cooperative Agreement projects
For Cooperative Agreement projects, the district should instruct
the warehouse to charge the equipment to the appropriate
Cooperative Agreement EA, with any applicable SD identified for the
project (do not use an Encroachment Permit EA or SD on these
Cooperative Agreement Project
Rev. 10/2009
TYPE OF PROJECT FEE PAYMENTS
PROJECT CONTROLLER INSPECTION DELIVERY AND
INSTALLATION
PRIVATELY FUNDED YES YES YES
LOCALLY FUNDED W/O AGREEMENT YES (Paid by Contractor) YES (Paid by
Contractor) YES (Paid by Contractor)
JOINT FUNDED PROJECTS WITH COOPERATIVE AGREEMENTS
YES (As part of Department’s Contribution and Charged to Coop
EA)
YES (As part of Department’s Contribution and Charged to Coop
EA)
YES (As part of Department’s Contribution and Charged to Coop
EA)
100% SPECIAL FUNDED PROJECTS
Item Number
Description Price
7440 0055 5 15' LONG HARNESS #1 FOR MODEL 500, 510 & 520 CMS
325.16
7440 0056 7 30' LONG HARNESS #1 FOR MODEL 500, 510 & 520 CMS
382.80
7440 0065 6 MODULE POWER SUPPLY MODEL 206L 138.65
7440 0070 6 MODEL 332L CABINET FOR 170/2070 CONTROLLER UNIT
3866.94
7440 0075 7 MODEL 334L CABINET FOR 170/2070 CONTROLLER UNIT
2893.70
7440 0090 8 MODEL 2070E ENHANCE ATC 1082.83
7440 0130 4 MODEL 400 MODEM LER SYSTEM 5004 171.43
7440 0131 6 HARNESS FOR MODEL C2P MODEM 36.43
7440 0134 2 MODEL 2070-7A EIA-232 SERIAL COMMUNICATION CARD
106.13
7440 0136 7 MODEL 2070-6A MODEM 456.78
7440 0137 9 2070-6B MODEM 539.47
7440 0140 5 MODEL 510 CMS SYSTEM LEFT HAND 58783.59
7440 0173 4 CONTROLLER,MODEL170E WITH QUAD ACIA AND MODEL
412C PROGRAM MODULE 1004.25
7440 0175 9 MODEL 500 CMS SYSTEM W/CMS CABINET AND #4 &
#5
HARNESS RIGHT HAND 78038.62
7440 0177 3 MODEL 500 CMS CONTROL CABINET 4338.03
7440 0181 1 MODEL 510 CMS SYSTEM RIGHT WITH CMS CABINET AND
#4
& #5 HARNESS 58642.52
7440 0188 6 MODEL 520 CMS SYSTEM WITH CMS CABINET AND #4 &
#5
HARNESS 35676.03
7440 0196 3 MODEL 252RR ISOLATOR 2-CHANNEL AC 35.21
7440 0218 1 MODEL 500 CMS SYSTEM W/CMS CABINET AND #4 &
#5
HARNESS LEFT HAND 59408.09
7440 0330 8 MODEL 210 MONITOR 230.31
Electrical Price List
24 7440 0350 0 MODEL 222 DUAL LOOP VEHICLE DETECTOR
48.67
156.97
26 7440 0475 5 MODEL 242 TWO CHANNEL DC ISOLATOR MODEL DCI-82
27.13
325.50
16.03
126.29
9.29
POWER DISTRIBUTION ASSEMBLY #4 FOR CHANGEABLE MSG SIGNS 500
709.59
32 7440 0613 9 HARNESS #4 FOR MODEL CMS - 300 FT
2240.25
33 7440 0614 1 HARNESS #5 FOR MODEL 500 CMS - 300CT
690.68
34 7440 0615 4 HARNESS #1 FOR 500, 510 OR 520 CMS SYSTEM
189.83
35 7440 0672 3 CABINET, EXTERNAL BATTERY FOR MODEL 332A
CABINET
527.31
BATTERY BACKUP SYSTEM FOR TRAFFIC SIGNALS WITHOUT BATTERIES
917.74
37 744001239 Model 20706D, Fiber Optic Modem $1,241.14
38 744005531 Model 20707G card (GPS), Universal Time Base Module
$754
39 744002015 Model 342LX Cabinet $4,214.00
40 744002039 Model 344LX Cabinet $3,640.00
41 744001456 Advanced Variable Message Sign, Model 710 AVMS
$69,300.00
42 744000579 Model C11 Harness $38.00
43 744001874 Model 20704A, Power Supply $381.00
44 744001165 Model 20706W Wireless Comm Modem $1,070.00
45 744001191 Model 20709D, Dialup Comm Modem $363.53
46 744005556 Model 20709B, FSK/Dialup Comm Modem $583.85
47 744001177 Model 20709A, FSK/Dialup Comm Modem $436.97
ElectricalPriceListUpdated_03_29_2017.xlsx 3/29/2017
744005517 Model 20701C, CPU Card $374.00
744000668 Model 206LS Power Supply $162.00
744001052 PDA #2LS, Power Distribution Assembly $564.00
AVMS 1
2070 2
Management and Operations (TSMO)
Effective Date: 12/04/2018
Division of Design
TITLE Roles and Responsibilities for Development of Projects on the
State Highway System
POLICY
The California Department of Transportation (Caltrans), as
owner/operator of the State Highway System (SHS), has the statutory
(Government Code section 14000(c)) and inherent goal to ensure that
all modifications or additions to the SHS are: Safe, operational,
maintainable, environmentally compatible, and of good
value. Efficient in providing multimodal movement of people and
goods. In the best interest of the general public. Developed and
constructed in compliance with laws and regulations that
govern the use of state and federal transportation funds. Developed
and constructed in partnership with vested stakeholders.
Caltrans meets this goal by: Applying quality management practices.
Engaging in early and continuous partnerships and ensuring
accountability
amongst project sponsors, implementing agencies, stakeholders,
Caltrans functional units, local, regional, and transit agencies,
tribal governments, developers and consulting firms employed by
Caltrans or its partners.
Ensuring that all projects on or proposed for the SHS are planned,
developed, and constructed efficiently and effectively resulting in
a quality project in accordance with Caltrans standards and
practices.
“Provide a safe, sustainable, integrated and efficient
transportation system to enhance California’s economy and
livability”
Deputy Directive DD-23-R2 Page 2
Ensure one implementing agency undertakes the project’s
advertising, awarding, and administration of a construction
contract.
Maintaining ultimate approval authority for all projects on the
SHS. Keeping the public informed through appropriate
outreach.
DEFINITION/BACKGROUND
The roles and responsibilities in planning, designing, and
constructing transportation projects on the SHS continue to
increase in complexity due to the influx of various transportation
funding sources, the ability to use alternative project delivery
methods, regional transportation planning agencies’ active roles in
selecting and programming transportation projects, and these
agencies’ ability to contract with private architectural and
engineering firms to deliver those projects. Caltrans as steward of
the SHS strives to ensure the appropriate accountability and
professional liability remain with project sponsors, implementing
agencies, and product suppliers. Caltrans seeks to ensure the
integrity of the SHS by defining the various roles and
responsibilities of all parties involved, and by ensuring the
quality of transportation projects. The definitions provided below
are recognition of the parties’ interests related to transportation
project development.
Owner/Operator is the entity ultimately responsible for the
planning, design, construction, operation, maintenance, and
liability of a facility. Government Code section 14520.3 (b) and
Streets and Highways Code section 90 establishes Caltrans as the
owner/operator of the SHS.
Project is the undertaking by a project sponsor of a transportation
related construction, erection, alteration, repair, or improvement
to the SHS, including all work necessary to fulfill the
owner/operator’s requirements and commitments while satisfying all
state and federal laws and regulations. (Public Contract Code
section 10105).
Project Sponsor is the project advocate that acquires funding
partners to ensure adequate project funding.
Project Components are prescribed in Government Code section
14529(b) and describe the resources during the life of a project in
the State Transportation Improvement Program. Components are
synonymous to phases which are used to indicate the progression of
a project in the project development process.
Implementing Agency is an entity charged with successful completion
of a project component, and assumes project management
responsibilities for the component. There is only one implementing
agency per component.
“Provide a safe, sustainable, integrated and efficient
transportation system to enhance California’s economy and
livability”
Deputy Directive DD-23-R2 Page 3
Supplier is the entity that provides a service or product to the
implementing agency.
Delegation is the process of transferring powers, duties,
obligations, or actions from one person/entity to another.
Quality Project is the result in the fulfillment of project
responsibilities in the delivery of products and services that
considers stakeholders’ interests and fulfills Caltrans’
requirements and outcomes.
Quality Control (QC) is the methods, means, or procedures used by a
supplier to monitor and assess products or services to ensure that
the final product will fulfill the established quality
requirements.
Quality Assurance (QA) is the performance of all the planned and
systematic activities that provide confidence that the product
requirements will be fulfilled.
Quality Management Plan (QMP) is a document prepared by the
implementing agency that describes by who, what, when, and how QC
and QA activities will be performed for each project component as
specified in the quality assurance program.
Quality Assurance Program (QAP) is the implementing agency’s
promulgated quality related policies, procedures, and guidelines
necessary to ensure the work performed for each project component
results in a quality project.
Quality Management Assessment (QMA) is the performance of all
planned systematic activities by the owner/operator that verifies
the implementing agency’s QAP effectiveness and precedes the
owner/operator approval.
Quality Management Practices are all the implementing agency’s
systematic activities used to direct, control, and coordinate the
development of a quality project. These activities include the QAP
and QMP implementation, the performances of QC and QA activities,
and quality improvements originating from QMA, QC, or QA.
Owner/Operator Approval is a non-delegable project related decision
which can only be performed by the owner/operator.
Stakeholder Approval is a project related decision which can only
be performed by an external individual or organization whose duties
are established by law (e.g. National Environmental Policy Act
(NEPA) permitting agencies, California Environmental Quality Act
(CEQA) permitting agencies, railroads, or the California
Transportation Commission (CTC)).
“Provide a safe, sustainable, integrated and efficient
transportation system to enhance California’s economy and
livability”
Deputy Directive DD-23-R2 Page 4
California Environmental Quality Act Lead Agency (CEQA) (Public
Resources Code section 21067) is the public agency which has the
principal responsibility for carrying out or approving a project
which may have a significant effect on the environment.
National Environmental Policy Act Lead Agency is the public agency
which ensures federal compliance and approvals for a project.
CEQA Responsible Agency (Public Resource Code section 21069) is the
public agency, other than the lead agency, that has discretionary
authority over a project.
RESPONSIBILITIES
Owner/Operator: Performs QMA for all projects to ensure a quality
project on the SHS. Provides owner/operator approval as needed.
Provides written approval on risks the project sponsor is unable to
mitigate or
avoid. Fulfills the FHWA Stewardship and Oversight Agreement
responsibilities. Fulfills NEPA lead agency role and
responsibilities when assigned by FHWA. Fulfills CEQA lead agency
role and responsibilities. Performs CEQA responsible agency
responsibilities, when not a CEQA lead
agency.
Project Sponsor: Secures funding for the preparation and completion
of all the project
components including quality management practices. Identifies and
seeks approval for the transportation need and purpose that
conforms to Caltrans Strategic Management Plan. Evaluates and
compares project outcomes to the established project goals. Chooses
an implementing agency for each project component. Mitigates
project risks and does not create undue risk for the
owner/operator
unless necessary approvals are obtained using proper procedures.
Ensures the project management plan is implemented, including, but
not
limited to, the QMP and risk management plan.
CEQA Lead Agency: Determines the appropriate type of environmental
documentation. Exercises its independent judgment and analysis for
the adequacy and
objectivity of the CEQA environmental document. Reviews and
approves the need and purpose for the project as it relates to
the
environmental documentation.
“Provide a safe, sustainable, integrated and efficient
transportation system to enhance California’s economy and
livability”
Deputy Directive DD-23-R2 Page 5
Reviews and approves a reasonable range of alternatives in relation
to the environmental documentation.
Reviews, comments, approves, and certifies the environmental
documentation at appropriate stages of project development as
prescribed in the Caltrans Standard Environmental Reference
(SER).
NEPA Lead Agency: Performed by the US Department of Transportation,
Federal Highway Administration (FHWA) unless assigned to Caltrans.
Reviews, comments, and approves the NEPA environmental
documentation at
appropriate stages of project development. Reviews and approves the
need and purpose for the project as it relates to the
environmental document. Ensures a reasonable range of alternatives
are considered in relation to the
environmental document. Reviews, comments, approves, and revaluates
environmental documentation
at each project component. Ensures the project sponsor complies
with the project’s environmental
mitigation and other environmental commitments disclosed in the
environmental document.
CEQA Responsible Agency: Ensures its concerns are met by providing
early consultation to the CEQA
lead agency. Participates in the CEQA process. Prepares and issues
its own findings. Certifies its review and consideration of the
CEQA lead agency’s CEQA
document. Acts on or approves the project.
Implementing Agency: Chooses the supplier for each project
component. Establishes and implements QAP and generates a QMP for
each component. Delivers quality project components on time, and
within budget. Verifies and accepts work performed by the supplier
provided appropriate
documentation is obtained to allow for verification and acceptance.
Advertises, awards, and administers the construction contract.
Ensures that all project component closeout activities are
completed in a
timely manner, including, but not limited to, survey control and
right of way monumentation, as-built plans, environmental
commitments compliance, and right-of-way.
“Provide a safe, sustainable, integrated and efficient
transportation system to enhance California’s economy and
livability”
Deputy Directive DD-23-R2 Page 6
Deputy Director, Project Delivery: Ensures establishment and
implementation of Caltrans policies, standards,
procedures, and best practices for each project component affecting
project development.
Ensures establishment of the QAP for each project component
affecting Project Delivery that includes QC, QA, QMA, and
owner/operator approval activities.
Ensures allocation of capital outlay support (COS) resources for
the timely delivery of quality products and services.
Deputy Director, Maintenance and Operations: Ensures establishment
and implementation of Caltrans policies, procedures,
and best practices for maintenance and operations of SHS. Ensures
allocation of maintenance and operations support resources for
the
timely delivery of products and services related to project
development. Ensures establishment and implementation of Caltrans
policies, procedures,
and best practices for issuance of encroachment permits. Ensures
allocation of maintenance and operations support resources for
the
timely delivery of products and services including CEQA lead agency
or responsible agency.
Deputy Director, Planning and Modal Programs: Ensures establishment
and implementation of Caltrans policies, procedures,
and best practices for Transportation Planning of the SHS. Ensures
that implementation of projects on or proposed for the SHS
are
consistent with all Caltrans transportation planning documents.
Provides resources for the development of project initiation
documents in the
project initiation phase. Establishes and ensures the QAP for the
project initiation phase includes QC,
QA, QMA, and owner/operator approval activities. Ensures allocation
of Transportation Planning support resources for the timely
delivery of products and services including CEQA lead agency or
responsible agency.
Division Chiefs: For each Division’s respective area of
responsibility pertaining to the efficient and timely delivery of
quality projects and services: Develop and implement standards,
procedures, and best practices that are
aligned with Caltrans’ Strategic Management Plan. Develop and
implement guidance, tools, and training to ensure successful
delivery of quality projects. Develop a QAP pertaining to their
product and services for which Caltrans is
the implementing agency and responsible agency.
“Provide a safe, sustainable, integrated and efficient
transportation system to enhance California’s economy and
livability”
Deputy Directive DD-23-R2 Page 7
Provide statewide direction, policies and standards for activities
required to ensure compliance with Caltrans policies, standards,
and best practices.
Measure and monitor critical program and project deliverables and
outcomes by districts and regions in alignment with Caltrans’
Strategic Management Plan.
Act as the approval authority for owner/operator approvals for
those decisions delegated.
Provide guidance, policies, tools, and training for QMA activities.
Perform audit, surveillance, or process reviews for ensuring the
consistent and
effective application of Caltrans standards, procedures, best
practices, and quality management activities.
Implement a system of continuous quality improvement using
information learned from measuring and monitoring deliverables and
from process reviews.
District Directors: Assess the feasibility of the project sponsor’s
ability to obtain funding for the
proposed project component(s) before Caltrans begins work. Act as
the Caltrans authority for any owner/operator approval for
those
decisions delegated. Concur on the project’s need and purpose
relative to its public benefit and
impacts to the SHS. Appoint a primary point of contact for each
project. Determine and provide those activities that ensure a
quality project on the
SHS, including, but not limited to: o Implementation of the QAP for
each project component for which
Caltrans is the implementing agency. o Implementation of QMA for
all project components.
Ensure project decisions are made considering information gathered
through public outreach and involvement of stakeholders.
Enter into cooperative or highway improvement agreements as
appropriate with project sponsor(s) prior to expenditure of COS
resources.
Inform stakeholders of the policies, standards, procedures, and
best practices required by Caltrans and FHWA.
Deliver on commitments made to partners and customers, based on
statutory authority and available resources, and ensure the timely
delivery of quality products and services for which Caltrans is the
implementing agency.
Ensure that Caltrans functional units are properly resourced to
deliver quality products and services in a timely manner.
Determine the appropriate agency to be the lead under CEQA. Approve
and certify the CEQA environmental document if Caltrans is
the
CEQA lead agency or approve the project if Caltrans is the
responsible agency.
“Provide a safe, sustainable, integrated and efficient
transportation system to enhance California’s economy and
livability”
Deputy Directive DD-23-R2 Page 8
Review and approve the project report or equivalent after
consideration of the CEQA.
If assigned, approve the NEPA environmental documentation. Ensures
all proposed projects are evaluated and prioritized for
funding.
Public Information Officers: Communicate to the public specific
actions that will be taken to restore or minimize effects of all
construction, maintenance, permitting, planned emergency
restoration, or other activities on the SHS.
District Deputies, Office Chiefs, and Branch Chiefs: Provide QA for
the products, and services within their functional area. Empower
employees with the tools, resources, time, and training to deliver
the
products and services for which Caltrans is the implementing
agency. Participate in the development of work plans and quality
management
activities defining project scope, cost, schedule, resource, and
quality requirements.
Prioritize commitments to ensure the successful delivery of both
Caltrans’ and external project sponsors’ projects.
Ensure that work does not begin without appropriate written
authorization. Notify their District Director and/or Deputy
District Directors, via established
reporting relationship, of any changes, problems, or risks that
could affect the scope, cost, schedule, and overall quality of
projects on the SHS, or owner/operator approval.
Apply the QAP, and develop the QMP if Caltrans is the implementing
agency. Perform QMA, if assigned this responsibility. Assess and
manage risk affecting the owner/operator responsibilities.
Project Managers: Lead the project development team on issues and
risks related to quality
management, scope management, schedule management, or cost
management issues for each project component utilizing appropriate
documentation.
Facilitate resolutions and seek approvals for project related
issues and risks affecting the quality, scope, schedule or
cost.
Ensure funding requirements are met.
Task Managers or Employees: Participate in the deployment of the
QAP by performing quality control or
quality assurance, if assigned, on work or services. Provide
quality and timely products and services by using appropriate
tools,
resources, time, documentation, and training.
“Provide a safe, sustainable, integrated and efficient
transportation system to enhance California’s economy and
livability”
STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION
ENCROACHMENT PERMIT H - SUPPORT DIAGRAM FOR AERIAL CROSSINGS
TR-0108 (REV. 03/2007)
POLES
Line Line
CONSTRUCTION NOTES:
A MINIMUM OF 18' SHALL BE MAINTAINED OVER AND ACROSS HIGHWAY OR
FREEWAY LANES.
NETTING SHALL BE MAINTAINED OVER AND ACROSS LANES UNTIL AERIAL
FACILITIES ARE PROPERLY SECURED IN PLACE.
H - SUPPORTS SHALL BE INSTALLED OUTSIDE OF STATE R/W, UNLESS
PERMITTED BY THE STATE'S REPRESENTATIVE.
CHP BREAKS SHALL NOT EXCEED 5 MINUTES FOR THE PLACEMENT OF
NETTING.
PLACEMENT OF AERIAL LINES: Installation or removal of overhead
conductors crossing a freeway require traffic control by the
California Highway Patrol (CHP) and usually occur on weekend
mornings. The CHP can perform a rolling break in traffic on most
highways to allow up to a five-minute clearing. These breaks are
adequate for simple cable installation. Utility personnel carry the
conductors across the freeway lanes and hoist them into place on
the opposite side of the freeway.
On larger conductor crossings such as transmission lines, 1" or
greater in diameter, districts may determine that safety nets are
needed to prevent transmission lines from falling on traffic during
cabling installations. Temporary safety-net support poles are
placed at protected locations outside shoulders and in medians. If
locations for temporary supports are not available, the utility
company may use K-rail and sand barrel crash cushions. After rope
nets are strung during CHP traffic breaks other work is then
allowed to proceed. Placement of the aerial line may be by
helicopter.
STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION
ENCROACHMENT PERMIT SETTLEMENT ROD DETAIL TR-0152 (REV.
09/2006)
Road Box, H-20 loading when required to be installed withing the
pavement area.
PVC threaded cap to be removed by hand.
Small chain attached to rebar with hose clamp to restrict maximum
movement on chain to allow for 3" of settlement on rod. Slot top of
PVC to hold chain.
BETONITE SEAL
2 - 1/2" DIAMETER PVC CASING
3/4" REBAR driven 6" to 12" past the bottom of the borehole
NOTE:
( SOLIDLY ANCHORED )
It shall be installed over the centerline of the installation,
within the median, shoulder area, or within the pavement as
directed by the State's Representative.
1. Remove PVC cap, rebar, and restriction chain.
2. Fill borehole with sand to 24" below bottom of Road Box when
within the median or shoulder areas.
3. Fill remainder of borehole with Bentonite seal mixture.
24"
ABANDONMENT PROCEDURES
4. Remove Road Box and back fill with an approved backfill.
STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION
ENCROACHMENT PERMIT TRENCH DETAIL TR-0153 (REV. 09/2006)
TYPICAL TRENCH DETAIL
TRACER WIRE ( IF REQ'D )
UW - Width of Utility or Culvert CLR - CLSM - Controlled Low
Strength Material
CLR
Existing Base
Existing Subgrade
New Pavement Base
New Subgrade
HMA - Hot Mix Asphalt Clearance between product and trench wall TW
- Trench Width
STRUCTURE BACKFILL SHALL CONFORM TO SECTION 19 - 3.06 OF THE
STANDARD SPECIFICATIONS
SLURRY CEMENT BACKFILL SHALL CONFORM TO SECTION 19 - 3.062 OF THE
STANDARD SPECIFICATIONS
HMA SHALL CONFORM TO SECTION 39 OF THE STANDARD
SPECIFICATIONS
ALL METHODS OF COMPACTION SHALL BE BY MECHANICAL MEANS. PONDING,
JETTING OR FLOODING SHALL NOT BE ALLOWED. AGGREGATE BASE SHALL
CONFORM TO SECTION 26 OF THE STANDARD SPECIFICATIONS
WHEN CLSM IS UTILIZED THE MIX DESIGN AND TEST RESULTS SHALL BE
SUBMITTED TO THE STATE'S REPRESENTATIVE.
ALL WORK SHALL BE AS AUTHORIZED BY THE APPROVED ENCROACHMENT PERMIT
PLANS, AND/OR AS DIRECTED BY THE STATE'S REPRESENTATIVE.
WHEN THE UW IS > 6" THEN THE MINIMUM CLR SHALL BE 6"
COLD PLANING AND RE-SURFACING OVERLAY SHALL BE PARALLEL TO THE
ROADWAY AND TO THE NEAREST LANE LINE FOR THE ENTIRE LENGTH OF THE
TRENCH/DISTURBED AREAS, AND/OR AS DIRECTED BY THE STATE'S
REPRESENTATIVE.
WHEN COLD PLANING IS REQUIRED, THE MINIMUM SHALL BE 0.10' OR AS
DIRECTED BY THE STATE'S REPRESENTATIVE TO ACCOMODATE FIELD
CONDITIONS.
COLD PLANING MAY BE REQUIRED AT THE DIRECTION OF THE STATE'S
REPRESENTATIVE TO ACCOMODATE THE PLACEMENT OF STEEL PLATES.
WHEN TRENCH PLACEMENT IS WITHIN 4' OF CURB & GUTTER, ADDITIONAL
COLD PLANING MAY BE REQUIRED AT THE DISCRETION OF THE STATE'S
REPRESENTATIVE.
ANY PAVEMENT MARKINGS AND/OR STRIPING REMOVED OR DAMAGED DURING
CONSTRUCTION SHALL BE REPLACED AS DIRECTED BY THE STATE'S
REPRESENTATIVE.
A TRACER WIRE SHALL BE PLACED ON TOP OF THE FACILITY, WHEN REQUIRED
BY THE STATE'S REPRESENTATIVE.
OTHER TRENCH RELATED DETAILS ARE SHOWN IN FIGURE 6.1, CHAPTER 6 OF
THE ENCROACHMENT PERMITS MANUAL.
A PAINT BINDER (TACK COAT) OF ASPHALTIC EMULSION CONFORMING TO
SECTION 39-4.02, PRIME COAT & PAINT BINDER (TACK COAT) SHALL BE
FURNISHED AND APPLIED.
NEW PAVEMENT BASE SHALL CONSIST OF EITHER CL. II AGGREGATE BASE,
2-SACK SLURRY CEMENT, OR CLSM. WHEN TW IS < 24," CL. II
AGGREGATE BASE IS NOT RECOMMENDED FOR BACKFILL.
NEW SUBGRADE SHALL CONSIST OF EITHER CL. II AGGREGATE BASE, 2-SACK
SLURRY CEMENT, OR CLSM. WHEN TW IS < 24," CL. II AGGREGATE BASE
IS NOT RECOMMENDED FOR BACKFILL.
NEWSPAPER
DISTRIBUTION
GUIDELINES
For
& HEADQUARTERS LANDSCAPE ARCHITECTURE PROGRAM
APPLICATION SUBMITTAL
Streets and Highway Codes Sectio n 220.5 authorizes the placem ent
of Newspaper Vending Machines, herein after referred to as
“distribution boxes,” at Safety Roadside Rest Areas (SRRA).
• Section 220.5 (c) authori zes the Department the rights of
determination in which SRRA are suitable for placement of these
facilities.
• Section 220.5 (d) authorizes the Department the right to
determine a suitable fee.
Newspaper distribution boxes at Safe ty Roadside Rest Areas (SRRA)
a nd Vista Points are permissible when a Newspaper Entity has
entered into a “Newspap er Distribution Agreement,” hereinafter
referred to as “Agreement”, through the District Landscape
Architect.
The District Landscape Architect is responsible for all reviews,
field studies, and document preparation before sending the
completed package, consisting of the Agreem ent, the required
fee/deposit and a completed Encroachment Permit Application to the
District Encroachment Permits Office for perm it issuance.
The Department retains all rights in determ ining whether or not
the placem ent of Newspapers and distribution boxes will be allowed
within any SRRA a nd/or Vista Point. W hen the Department grants
permission to allow plac ement of these facilities, they shall be
lim ited to a total of four units per SRRA location. A copy of the
agreem ent, permit and guidelines shall be provided to the
requestor, and a copy forwarded to Headquarters Landscape
Architecture Program.
FEE / DEPOSIT
A check in the amount of four (4) hours of the encroach ment
standard hourly rate shall be submitted with the package to the
District Perm its Office. This deposit/fee will cover proces sing
of the application, review, issuance of the perm it and inspection.
All perm its issued for the placem ent of a Newspaper within a SRRA
shall be issued for a period of one year.
The permittee is responsible for all actual costs of the permitting
process. When there are issues of non- conformance that could resu
lt in additional time expenditures the permittee shall be re quired
to compensate re-imbursement of that time expended.
SPECIAL PROVISIONS & CONDITIONS
Subcontracting under this permit will not be allowed for the
placement of the newspapers.
The permittee is required to provide weekly maintenance checks on
their distr ibution facility, to ensure cleanliness of the area
surrounding their facility.
Storage of newspapers on State rights-of-way will not be
allowed.
A copy of the newspaper is the only item that will be allowed in
the window of the door on the distribution box.
The permittee is required to no tify the Distr ict Landscape
Architect p rior to start of any work in the States’ right-of-way,
to include performing weekly inspections.
Vehicles shall be parked in the parking lot when filling or
re-filling of the distribution boxes.
Any three violations of the special provisions or permit conditions
within the term of the permit will result in revocation of your
permitted privileges.
INSTALLATIONS & CONDITIONS
All new installations of distribution facilities shall be installed
and maintained by the permittee under the direction of the District
Landscape Architect and shall be in compliance with the following
criteria:
Within each Safety Roadside Rest Area (SRRA), all di stribution
facilities (boxes and pedestals) shall all be of the sam e type,
model, m anufacturer and color (s ee Attachment #1 & #2) so
that a uniform appearance is m aintained as d irected by the
District Lan dscape Architect and per th e attachments
provided.
The distribution facilities sh all be located within the SRRA as di
rected by the District Landscape Architect, in the planted areas
wherever practicable, ad jacent to walkways and electroliers to
reduce the exposure to vandalism and theft.
The distribution facili ty should be located in an area where it
will be unobtru sive and not detract from other elements of the S
RRA. It will b e located so that it is conven ient and easily
accessib le to th e traveling public.
The front of the distribution facility should be parallel with the
edge of the walkway.
The distribution boxes are to be securely fastened to square steel
pedestal mounts, which are to be set in a concrete footing located
within the planted a rea. The top of the concrete footing is to be
covered with soil, mulch or ground cover to restore the area to its
prev ious appearance to as great an extent as possible.
Distribution boxes furnished with a pedestal mount equipped with a
st eel flange base designed to be bolted to concrete surfaces are
to used only where directed by the District Landscape
Architect.
All distribution facilities shall be f ree of any advertisements
and shall be maintained in a clean, neat and attractive condition
and in good repair at all times. Any facilities (boxes, pedestals)
that are damaged, in a state of disrepair, or due to wear and tear
which are no longer in a presentable condition (clean, neat and
attractive) shall be replaced or rep aired by the permittee within
(48) hours after discovery or notification by the States’
representative to do so.
All distribution facilities which have been lost, stolen or
vandalized and facilities that are no longer to be used, shall be
rem oved, replaced or repaired by the permittee within (48) hours
after discovery or notification by the District Landscape Architect
to do so.
Any distribution facility that is missing, vandalized or unused and
is not to be replaced shall be rem oved, and the site shall be
returned to its original condition.
THESE GUIDELINES ARE SUBJECT TO CHANGE AT THE DISCRETION OF THE
HEADQUARTERS OFFICE OF ENCROACHMENT PERMITS. IT IS THE
RESPONSIBILITY OF THE PERMITTEE TO REMAIN CURRENT WITH THE SPECIAL
PROVISIONS AND PERMIT CONDITIONS OF THESE GUIDELINES.
ATTACHMENT #1
DISTRIBUTION BOXES
FACE VIEW
24 1/8”
BEIGE COLOR
24 1/8”
SIDE VIEW
17 3/16”
BEIGE COLOR
The distribution boxes are to be securely fastened to square steel
pedestal mounts, which are to be set in a concrete footing located
within the planted area. The top of the concrete footing is to be
covered with soil, mulch or ground cover to restore the area to its
previous appearance to as great an extent as possible. Distribution
boxes furnished with a pedestal mount and equipped with a steel
flange base that are designed to be bolted to concrete surfaces are
to be used only where directed by the Department.
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION NEWSPAPER
DISTRIBUTION AGREEMENT TR-0150 (NEW 05/2009)
The undersigned newspaper distributor, hereinafter referred to as
DISTRIBUTOR, desires to place and maintain a newspaper and
newspaper vending machine, hereinafter referred to as “Machine”, at
certain identified safety roadside rest areas owned and operated by
the State of California, Department of Transportation, hereinafter
referred to as STATE. DISTRIBUTOR agrees that the following
conditions apply:
1. DISTRIBUTOR shall comply with the applicable provisions of the
California Administrative Code and directions from the State’s
representative as to the location and placement of each Machine and
including its associated pedestal.
2. DISTRIBUTOR shall indemnify, protect and hold harmless the
STATE, its officers and employees from all claims for injury to
persons or damage to property by reason of the presence, location
and/or maintenance of the Machine on STATE property, or by reason
of claims based on acts of DISTRIBUTOR’S agents, employees or
workers.
3. Maintenance of the Machine shall be the sole responsibility of
DISTRIBUTOR, including any replacement or repair of Machine stolen
or damaged by vandalism. DISTRIBUTOR shall begin to make necessary
repairs within 48 hours after receipt of written or oral
notification by STATE.
4. In the course of servicing a Machine, DISTRIBUTOR shall not
deposit in or about any safety roadside rest area any wrapping
paper, tying material or other litter, except to dispose of such
material in a receptacle intended for that purpose. Any material
that cannot be disposed of in available receptacles shall be
immediately removed from the premises by DISTRIBUTOR.
5. If distribution of the newspaper is discontinued for thirty
consecutive days, the DISTRIBUTOR shall remove the Machine and
restore the site to its original condition.
6. If the Machine to be removed is on a pedestal shared with other
machines, the DISTRIBUTOR shall modify the pedestal to properly
accommodate the remaining machines.
7. If, after such discontinuance, or if the terms of this Agreement
are violated, and DISTRIBUTOR fails to remove the Machine and
restore the site within ten days after reasonable notice and
demand, the STATE may thereafter remove the Machine and restore the
site to its original condition and the DISTRIBUTOR agrees to
reimburse the STATE for the reasonable costs of that removal and
restoration.
8. The STATE reserves the right to close, temporarily or
permanently, the safety roadside rest area for any reason without
notification to the DISTRIBUTOR.
9. This Agreement shall commence on 20 , and shall terminate on
20
The parties agree that only the following newspaper may be
distributed:
NAME OF REST AREA(S) TRAVEL DIRECTION NEWSPAPER NAME
COMPANY NAME CONTACT PERSON PHONE NUMBER
ADDRESS E-MAIL ADDRESS
DISTRIBUTOR’S SIGNATURE
DISTRICT USE ONLY DISTRICT SRRA COORDINATOR / DISTRICT LANDSCAPE
ARCHITECT NAME PHONE NUMBER
DISTRICT SRRA COORDINATOR / DISTRICT LANDSCAPE ARCHITECT NAME
E-MAIL ADDRESS
DEPARTMENT OF TRANSPORTATION
GENERAL
The California Department of Transportation (Caltrans) and the
California Highway Patrol (CHP) share responsibility for operating
the state highway system safely and efficiently. Because of the
shared responsibilities, planned lane closures impact both Caltrans
and CHP. Minimizing motorist delay while maintaining the quality of
work and public and worker safety are key goals during planned lane
closures.
PLANNED LANE CLOSURE POLICY
Transportation Management Plans (TMPs), including contingency
plans, are required for all construction, maintenance, encroachment
permit, planned emergency restoration, or other planned activities.
TMPs define the actions necessary to ensure a safe workzone that
minimizes impacts to motorists. Caltrans District offices will seek
input from local CHP personnel for the development of significant
TMPs.
When planned lane closures are necessary, some of the techniques or
considerations when developing a TMP may include:
1. Consideration of lane closure hour restriction. 2. Use of
Construction/Maintenance Zone Enhanced Enforcement Program
(COZEEP/MAZEEP). 3. Use of Freeway Service Patrol for workzone. 4.
Consideration of predictable heavy congestion, such as commute
hours and
holidays. 5. Detour routes. 6. Reduced lane widths. 7.
Consideration of impact on adjacent roads. Decisions on how to
handle public safety situations should be made collaboratively
between Caltrans and CHP at pre-job meetings and/or when they
1
occur. More information on termination of lane closures is
contained under Joint Responsibilities.
A. JOINT RESPONSIBILITIES
1. Lane Closure Review Committees. When a planned lane
closure-related traffic delay is expected to exceed 30 minutes, a
Caltrans District Lane Closure Review Committee (DLCRC) review and
approval is required. The DLCRC will include a local designated CHP
representative. The DLCRC decides when to submit lane closure
requests that are of an interregional, statewide, environmental, or
otherwise of a sensitive nature to the Caltrans headquarters Lane
Closure Review Committee (HLCRC) for their approval. The HLCRC
includes a designated CHP headquarters representative.
2. Contingency Plans. Contingency plans will be developed to
address construction process problems, and those for unexpected
traffic issues. A contingency plan addresses specific actions that
will be taken to restore or minimize effects on traffic when
traffic congestion or delay exceeds the original estimates. The
contingency plans will prescribe actions for likely problems and
provide the criteria “triggers” for initiating the planned actions.
The CHP and Caltrans will collaborate in the development of
contingency plans and will:
a. Commit personnel and resources, as available, to ensure the
efficient execution of the plan.
b. Ensure the plan provides that clearly designated responsible
personnel, with the authority to act, will be available at all
times during closure.
c. Coordinate and collaborate with other commands and agencies as
required.
d. Ensure local authorities and allied agencies as appropriate are
participants in the plan and are willing to act.
e. Ensure the TMCs are part of the plan, including interregional
TMC participation.
3. Termination of Highway Lane Closures. Either department may
terminate a lane closure because of safety concerns (e.g.,
unacceptable smoke or dust that restricts motorist visibility,
development of inclement weather, potential for flooding). Whenever
possible, a closure should be terminated collaboratively between
Caltrans and the CHP.
When a CHP field representative determines a lane closure should be
terminated
2
because of safety concerns or unacceptable traffic congestion, the
following protocol should be used:
a. Notify a CHP supervisor.
b. Contact the Caltrans person responsible for overseeing field
work. If mutual agreement to terminate the closure is not reached,
the CHP supervisor should notify the Area commander or designee,
who will contact the appropriate Caltrans manager to mutually
resolve the issue. If the decision is made to terminate the
closure, the CHP and Caltrans representatives shall:
1. Advise the TMC or Caltrans Maintenance Dispatch as
appropriate.
2. Notify all other applicable entities (e.g., highway
contractor).
When a Caltrans field representative or District Traffic Manager
(DTM) determines a lane closure should be terminated because of
safety concerns or unacceptable traffic congestion on the immediate
and/or adjacent highway/roadway system, the following protocol
should be used:
a. Notify the Caltrans person responsible for overseeing field
work, Maintenance Dispatch, CHP Communication Center, and
TMC.
b. Notify all other applicable entities (e.g., highway
contractor).
4. Evaluation. For some major TMPs, it is expected that evaluations
will be done as a joint CHP/Caltrans activity, and include any
other participants such as allied agencies.
B. CHP’S RESPONSIBILITIES
CHP Division and Area commanders, or their designees, will
collaborate and cooperate with responsible Caltrans personnel to
minimize traffic congestion (e.g., vehicle queuing, stopping, slow
bumper-to-bumper vehicles) resulting from planned lane closures.
CHP Division and Area commanders will work with the appropriate
Caltrans District Division Chief, DTM, Resident Engineer,
Maintenance Region Manager, or person(s) designated by the District
Director to ensure the CHP’s concerns are adequately addressed in
the TMPs and contingency plans.
Area commanders or their designees participating on, and/or
reviewing and commenting on project-specific TMPs and contingency
plans will:
3
1. Review the plans in a timely manner to ensure CHP concerns,
including motorist and worker safety, are adequately
addressed.
2. Provide notification to appropriate CHP commands of all
impending planned lane closures and status of associated
TMPs.
3. Notify respective CHP Division commanders of agreed upon traffic
queues (distance and amount of time for stop-and-go vehicles)
during the lane closures and any significant issues concerning
traffic control that were not resolved in the TMP.
4. Verify that TMCs have been notified and are part of impending
projects, TMPs, and contingency plans.
5. Ensure the commitment of CHP personnel and resources to
COZEEP/MAZEEP, directing traffic, and traffic monitoring is clearly
and accurately described in TMPs and contingency plans.
C. CALTRANS’ RESPONSIBILITIES
The Caltrans TMP Coordinator will confer with the respective CHP
Area commanders to determine criteria and procedures for
notification of planned highway lane closures and changes to
TMPs.
Depending on the project and impact on traffic, Caltrans may
include CHP in the development and review of TMPs.
1. Caltrans should designate a responsible representative for each
lane closure.
2. Caltrans should ensure the contractor is able and prepared to
comply with the TMP and contingency plan as they relate to its
performance of work.
D. SPECIAL EVENTS ON STATE HIGHWAYS
Special events include, but are not limited to, activities such as
parades, marathons, bikeathons, walkathons, marches, triathlons,
and other activities. Filming operations are covered under separate
guidelines.
An encroachment permit for special events is required whenever any
activity is conducted within a state highway right-of-way which
interferes with the unrestricted movement of traffic, requires
special traffic control, and/or cannot be conducted in such a
manner as to fall under the permissible uses of a highway as
authorized in the California Vehicle Code (CVC). Activities which
do not
4
PROFESSIONAL ENGINEERS ACT (Business and Professions Code §§ 6700 –
6799), CHAPTER 7. PROFESSIONAL ENGINEERS, Article 3.
6735. Preparation, signing, and sealing of civil engineering
documents (a) All civil (including structural and geotechnical)
engineering plans, calculations, specifications, and reports
(hereinafter referred to as "documents") shall be prepared by, or
under the responsible charge of, a licensed civil engineer and
shall include his or her name and license number. Interim documents
shall include a notation as to the intended purpose of the
document, such as "preliminary," "not for construction," "for plan
check only," or "for review only." All civil engineering plans and
specifications that are permitted or that are to be released for
construction shall bear the signature and seal or stamp of the
licensee and the date of signing and sealing or stamping. All final
civil engineering calculations and reports shall bear the signature
and seal or stamp of the licensee, and the date of signing and
sealing or stamping. If civil engineering plans are required to be
signed and sealed or stamped and have multiple sheets, the
signature, seal or stamp, and date of signing and sealing or
stamping, shall appear on each sheet of the plans. If civil
engineering specifications, calculations, and reports are required
to be signed and sealed or stamped and have multiple pages, the
signature, seal or stamp, and date of signing and sealing or
stamping shall appear at a minimum on the title sheet, cover sheet,
or signature sheet.
6746. Exemption - communications companies under the Public
Utilities Commission Plans, specifications, reports and documents
relating to communication lines and equipment prepared by employees
of communications companies which come under the jurisdiction of
the Public Utilities Commission, and by employees of contractors
while engaged in work on communication equipment for communications
companies which come under the jurisdiction of the Public Utilities
Commission, are not subject to the provisions of this
chapter.
6746.1. Exemption - employees of the communications industry The
provisions of this act pertaining to licensure of professional
engineers other than civil engineers, do not apply to employees in
the communication industry, nor to the employees of contractors
while engaged in work on communication equipment. However, those
employees may not use any of the titles listed in Section 6732,
6736, and 6736.1, unless licensed.
6747. Exemption – industrial corporations and public utilities (a)
This chapter, except for those provisions that apply to civil
engineers and civil engineering, shall not apply to the performance
of engineering work by a manufacturing, mining, public utility,
research and development, or other industrial corporation, or by
employees of that corporation, provided that work is in connection
with, or incidental to, the products, systems, or services of that
corporation or its affiliates. (b) For purposes of this section,
“employees” also includes consultants, temporary employees,
contract employees, and those persons hired pursuant to third-party
contracts
Rev. 04/2019
HEADQUARTERS LANDSCAPE
ARCHITECTURE PROGRAM
MAY 2009
SUBMITTAL
This program is “optional” at the discretion of the District
Office.
Requests for placem ent of an advertis ement/display within a
Traveler/Tourist In formation Center, hereinafter referred to as
“Kio sk,” shall be subm itted by the respon sible person (City,
County, Chamber of Comm erce, Organization or Business Owner) for
that activity, service or facility, hereinafter referred to as the
“Requestor,” to the District’s Representative.
Kiosk Advertising Guidelines are established from Barclays
California Code of Regulations, Title 21·Public Works, Division·2
Departm ent of Transportation, Chapter·20 Permissible Activity and
Use of Safety Roadside Rest Areas (SRRA) and Vi sta Points in and
along California State Highways, which authorize the placement of
commercial advertisements/displays within kiosks.
• Article 2, Section 2204 (b) authorizes the pl acement of c
ommercial displays under an agreement within Traveler Information
Centers for a cost.
• Article 2, Section 2204 (d) defines Traveler Information Centers
as kiosks. • Article 2, Section 22 04 (f) auth orizes the
Department to place Public Info rmation
displays/advertisements determined to be of a specific value,
interest or assistance to the traveling public, for a cost.
Streets and Highway Codes Sectio n 220.5 authorizes the placement
of kiosks, within Safety Roadside Rest Areas (SRRA), and the
following advertisements/displays are allowed for placement at no
cost.
• Section 220 authorizes the placement of agricultural displays. •
Section 221 authorizes the placement of information regarding
missing children.
Forty-percent (40%) of the kiosk space is devot ed to non-comm
ercial public infor mation. The remaining sixty-percent (60%) may
be utilized as follows:
Placement of an advertisement/display can be monthly, quarterly or
semi-annual.
The format and conten t of the advertis ement/display will be
provided f or review and consideration. The District SRRA
Coordinator or District Landscape Architect is responsible for
review, approval and processing of the submitted request.
Upon approval in writing from the Departm ent, the
advertisement/display can not be changed or altered in any way
without the written consent of the Department.
Displays approved for placement can only provide public information
regarding:
• local and state points of interest • local communities and
community service facilities • location of recreational areas and
facilities (campgrounds, etc) • identification of local automotive
service stations
• food • lodging • traveler service related facilities
FEE
The entire fee of the agreem ent, per advertisement/display, is
required due upon written approval of the request. Payment of the
fee shall be by pers onal or com pany check, m oney order or
cashier’ s check, made out to the Department of
Transportation.
Districts will assess th e fee for the placem ent of the
“advertising/display” based upon the following criteria:
1. Location of the SRRA 2. Distance of the SRRA in relation to the
District Office (round-trip travel time, etc.) 3. Size of the
advertising/display 4. Other district resources expended
The assessed advertising fee is s ubject to change at the end of
the existing agreement period entered into by the requestor and the
Department, at the discretion of the Department.
CONDITIONS OF INSTALLATION
Installation or removal of the advertisement/display upon any kiosk
will solely be the responsibility of the Department. Under no
circum stances can the requestor install, repl ace, repair, alter
or remove the advertisement/display.
The Department reserves all rights, as stipulated within Barclays
California Code of Regulations:
• to reject or refuse at its sole discretion any advertisem
ent/display which is false or m isleading, which may misinform, or
which do es not qualify as traveler in formation under the Departm
ent’s rules and regulations.
• to reject, refuse or remove any advertisement/display which does
not confor m to the Department’s specifications, which is deemed
unsightly or in a bad state of repair.
• to cancel the agreement at any time, upon ten-days written
notification. • any delay in the placement of an advertisem
ent/display or interruption of the display tim e caused
by the Department shall not constitute a breach of the agreement.
In its discretion, the Department may extend the term of the ag
reement or provide a pro rata credit equal to the period of delay
or interruption. Such extension or credit shall be the only damages
recoverable.
• to close the Safety Roadside Rest Area for a ny reason without
notific ation, temporarily or permanently, or to can cel the agreem
ent. The re questor shall have no claim for damages, or extension
of the agreement by reasons of such removal, disruption,
discontinuance or termination.
The Requestor is responsible for the production of th e
advertisement/display at their sole cost and expense.
The Requestor is responsible at their own cost and expense for, the
restorati on, repair or replacem ent of any advertisement/display
which is lost, stolen , defaced, damaged, or destroyed through no
fault of
the Department, or which is deem ed by the Departm ent to be in a
faded, or deteriorated condition, regardless of the cause.
In this event, if the requestor fails to provide an acceptable
replacement of the advertisem ent/display within thirty-days of
notification, the Department may cancel the agreement.
The advertisement/display will be of a professional quality, prin
ted on LEXAN or a com parable material pre-approved by the District
SRRA Coor dinator or District Lands cape Architect, a ble to
withstand adverse conditions, such as direct sunlight, rain or snow
and able to endure the length of the agreement. The minimal size of
the advertisement/display allowed shall be no less than 10” x 14,”
and a maximum size of 14” x 20.” Advertisem ent/displays not
enclosed within a protective casing shall be durable, and protected
with an anti graffiti coating.
SPECIAL PROVISIONS
Sub-contracting or third party agreem ents will not be allowed for
the request or placem ent of an advertisement/display. The reques
tor is required to be solely responsib le for the service or
facility, listed within the advertisement/display.
The requestor assumes full and complete responsibility and liab
ility for th e content o f the advertisement/display, and shall ag
ree to save, defend, indemnify and hold the State, the Departm ent,
its officers, agents and employees harmless against any and all
demands, claims, liability, damages and causes of action, including
attorney ’s fees and all costs of any legal actio n occasioned by
or resulting from injuries or loss es to any pers on, firm or
corporation, however occurring, resulting from their reliance on
the person’s or company’s advertis ement/display or from the f orm,
content or representations contained therein.
THESE GUIDELINES ARE SUBJECT OF CHANGE AT THE DISCRETION OF THE
DEPARTMENT. IT IS THE REQUESTOR’S RESPONSIBILITY TO REMAIN CURRENT
WITH THESE GUIDELINES.
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION KIOSK
ADVERTISING/DISPLAY AGREEMENT TR-0401 (REV. 05/2009)
The undersigned requests to place an advertisement/display within
the Traveler/Tourist Information Center, hereinafter referred to as
“kiosk” within the Safety Roadside Rest Area, and hereby agrees to
the following conditions:
I have read the Kiosk Advertising/Display Guidelines, and
conditions contained herein and agree to comply. And, understand
that any failure to do so will result in termination of this
agreement.
The requestor assumes full and complete responsibility and
liability for the content of the advertisement/display, and shall
agree to save, defend, indemnify and hold the State, the
department, its officers, agents and employees harmless against any
and all demands, claims, liability, damages and causes of action,
including attorney’s fees and all costs of any legal action
occasioned by or resulting from injuries or losses to any person,
firm or corporation, however occurring, resulting from their
reliance on the person’s or company’s advertisement/display or from
the form, content or representations contained therein.
The name on the agreement shall be that of the responsible party
for that service or facility. Sub-contracting or third-party
agreements will not be allowed for the placement of an
advertisement/display. The requestor is required to be solely
responsible for the service or facility, listed within the
advertisement/display.
The advertisement/display shall be of a professional quality,
printed on LEXAN or a comparable material pre-approved by the SRRA
Coordinator, able to withstand adverse conditions, such as direct
sunlight, rain or snow and able to endure the length of the
agreement. The minimal size of the advertisement/display allowed
shall be no less than 10” x 14,” and a maximum size of 14” x 20.”
Advertisement /displays not enclosed within a protective casing
shall be durable, and protected with an anti graffiti
coating.
The requestor is responsible for the production of the
advertisement/display at their sole cost and expense.
The format and content of the advertisement/display shall be
provided for review. Upon approval in writing from the department,
the advertisement/display shall not be changed or altered in any
way without the written consent of the Department.
The requestor is seeking placement in the following SRRA:
NAME OF BUSINESS OR ORGANIZATION OWNER OR REPRESENTATIVES NAME
PHONE NUMBER
ADDRESS E-MAIL ADDRESS
OWNER OR REPRESENTATIVES SIGNATURE
NAME OF SAFETY ROADSIDE REST AREA DIRECTION TYPE OF
ADVERTISEMENT/DISPLAY FEE ASSESSED
@ SEMI-ANNUALLY
CHECK OTHER
AGREEMENT PERIOD
TRAVELER DISCOUNT BOOKLETS In
Definition
Periodical vendors, herein after referred to as Coupon Booklet
Vendors (CBV), offer discount coupons for lodging and entertainment
to the traveling public.
Written Agreement
The Department’s representative for Amtrak-California Stations will
be the Chief of the Rail Marketing Branch, Division of Rail.
The Department’s representative for Safety Roadside Rest Areas
(SRRA) will be the District Rest Area Coordinator.
CBV companies requesting to place their coupon booklet(s) within
Amtrak-California Stations and SRRA are first required to enter
into a written agreement with the Department, administered by the
Headquarters Office of Encroachment Permits.
This written agreement shall stipulate the reserving of four
full-pages for departmental campaign advertisements within their
respective publications, to be administered by the Statewide Events
& Awards Coordinator, in the Headquarters Office of External
Affairs.
The Department’s advertisements will consist of Slow for the Cone
Zone, Amtrak-California, California Highway Information Network
(CHIN) and Don’t Trash California. These campaign advertisements
shall be effectively placed in the booklets upon finalization of
the written agreement.
The location of placement of the Department’s campaign
advertisements within the publications is at the discretion of the
CBV, so long as the pages appear either before the first page of
lodging coupons or, after the final page of lodging coupons.
The CBV agree to endeavor to place the Department’s campaign
advertisements together, facing each other whenever the paid
composition of the publication permits.
When, and if constraints are imposed upon the CBV by the placement
of paid advertising, the CBV shall still be obligated to provide
the advertisements at their discretion within the areas of the
publications as prescribed above.
The Department retains the right and privilege to prescribe the
content of the four full-page advertisements during the course of
the written agreement and thereafter.
Each CBV will deliver 2 copies of each new publication printed to
the Statewide Events & Awards Coordinator, HQ Office of
External Affairs, and 2 copies of each new publication printed to
the Chief, Rail Marketing Branch, Division of Rail, 1120 N Street,
MS-74, Sacramento, California 95814.
Application Submittal
Upon confirmation of the revised agreement, each CBV will only be
required to submit one standard encroachment permit application,
for the issuance of one statewide biennial permit allowing the
continual distribution and maintenance of their facilities. In the
box labeled “description of work to be performed”, the applicant
shall state the intent for the “placement and maintenance of
Traveler Discount Coupon Booklets, and/or facilities.”
In the event that placement is sought where there are no existing
facilities, as a new installation, will require the CBV to submit
an exempt encroachment permit rider request, and the CBV shall be
responsible for all costs incurred with the installation of new
facilities.
Permit Fee
All permits are to be issued “exempt” for periodical distribution,
and shall be issued as biennial permits (2-years).
Special Provisions
The Department will allow for the placement of these booklets for
each year following as long as the respective parties adhere to the
conditions of the written agreement entered into:
District 11 Encroachment Permit Office will issue a statewide
biennial “CU” encroachment permit, listing the specific
Amtrak-California Stations and SRRA locations statewide, following
the permit special provisions, on the following pages of the
permit. All respective districts will receive cc: copies of the
statewide permits issued.
Require the placement of a laminated placard depicting the cover of
the booklet to be placed within the window of the display
box.
The CBV booklets will be allowed in the Department's Headquarters
building, on the sixth floor outside of the cafeteria area and in
Amtrak-California Stations stipulated within their permit, to be
placed within facilities provided by the CBV.
Permit Conditions
Subcontracting under this permit will not be allowed for the
placement of the coupon booklets.
The CBV is required to provide weekly maintenance checks on all
distribution facilities, to ensure cleanliness of the area
surrounding their facilities and to ensure that the traveling
public is provided with current information at no cost to the
public.
Storage of coupon booklets upon State rights-of-way or within the
Amtrak-California termini will not be allowed.
The CBV is required to notify the Department’s representative a
minimum of two days prior to entry into any of the locations
stipulated within their respective permit and/or the States’
rights-of-way.
Any combination of three violations of the special provisions or
permit conditions within the term (two- years) of the permit will
result in suspension and/or revocation of your permitted
privileges.
Installation Conditions
All new installations of distribution facilities shall be installed
and maintained by the CBV under the direction of the Department’s
representative and shall be in compliance with the following
criteria:
Upon completion on the installation of the distribution facilities
located within an Amtrak-California Station or SRRA, said
facilities inherently become the property of the State of
California.
Within each Amtrak-California Station or SRRA, all distribution
facilities (boxes and pedestals) shall all be of the same type,
model, manufacturer and color (see Attachment #1 & #2) to
ensure a uniform appearance is maintained as directed by the
Department’s representative and per the attachments provided.
The color for new distribution facilities shall be consistent at a
location but may be a color other than Beige, as determined by the
Department’s representative.
The distribution facility should be located in an area where it
will be unobtrusive and not detract from other elements of the
SRRA.
The distribution facility should be located within the planted
areas wherever practicable, adjacent to walkways and electroliers
to reduce the exposure to vandalism and theft, or as directed by
the Department’s representative.
It will be located so that it is convenient and easily accessible
to the traveling public, as directed by the Department’s
representative. The front of the distribution facility should be
parallel with the edge of the walkway.
The maximum number of distribution boxes shall not exceed four (a
double stack of two) in any SRRA.
The distribution boxes located within SRRA are to be securely
fastened to square steel pedestal mounts, which are to be set in a
concrete footing located within the planted area. The top of the
concrete footing is to be covered with soil, mulch or ground cover
to restore the area to its previous appearance to as great an
extent as possible. Distribution boxes furnished with a pedestal
mount equipped with a steel flange base designed to be bolted to
concrete surfaces are to be used only where directed by the
Department’s representative.
All distribution facilities shall be free of any advertisements
(see Attachment #3) and shall be maintained in a clean, neat and
attractive condition and in good repair at all times. Any
facilities (boxes, pedestals, and racks) that are damaged, in a
state of disrepair, or due to wear and tear which are no longer in
a presentable condition (clean, neat and attractive) shall be
replaced or repaired by the CBV as soon as practicable after
discovery or notification by the Department’s representative to do
so.
All distribution facilities which have been lost, stolen or
vandalized and facilities that are no longer to be used, shall be
removed, replaced or repaired by the CBV as soon as practicable
after discovery or notification by the Department’s representative
to do so.
The CBV is responsible for removal of the remaining facilities when
any distribution facility is missing, vandalized or unused, and
there is not intent to replace it in kind. The site shall be
returned to its original condition.
THESE GUIDELINES ARE SUBJECT TO CHANGE AT THE DISCRETION OF THE
HEADQUARTERS OFFICE OF ENCROACHMENT PERMITS. IT IS THE
RESPONSIBILITY OF THE PERMITTEE TO REMAIN CURRENT WITH THE SPECIAL
PROVISIONS AND PERMIT CONDITIONS OF THESE GUIDELINES.
ATTACHMENT #1
BEIGE COLOR
The distribution boxes are to be securely fastened to square steel
pedestal mounts, which are to be set in a concrete footing located
within the planted area. The top of the concrete footing is to be
covered with soil, mulch or ground cover to restore the area to its
previous appearance to as great an extent as possible. Distribution
boxes furnished with a pedestal mount and equipped with a steel
flange base that are designed to be bolted to concrete surfaces are
to be used only where directed by the Department.
ATTACHMENT #3
This illustration shows the appearance in how the placements of
these distribution facilities are to appear in the Safety Roadside
Rest Areas. Also shown is what is acceptable for placement in the
door window and what is NOT.
CALTRANS ENCROACHMENT PERMITS
PROCEDURAL REQUIREMENTS FOR DESIGN AND CALCULATIONS OF STRUCTURAL
AND SUB-STRUCTURAL PROJECTS
All submittals shall be stamped by a Registered Structural
Engineer, or a Registered Civil Engineer, with a minimum of five
years’ experience in structural design and preparation of
calculations, proof of experience is required by use of
Encroachment Permits form “Certification of Structural Experience”
(form TR-0133) to be included within the project package
submittal.
STRUCTURAL DESIGN AND CALCULATIONS
All Structural Project submittals (structures and structural
falsework) will require review by Structures Maintenance, for
construction under an encroachment permit and require the
following:
Designed plans and specifications, calculations and details
(structural and falsework).
A geotechnical investigation and soil analysis by a licensed
geotechnical engineer is required. It shall provide identification
of any locations of difficulty, changes in soil formation, or mixed
face conditions that could present or create ground loss,
exploratory soil corings and logs are required along the alignment
of the project.
Construction or Structures Construction may provide
oversight.
SUB-STRUCTURAL DESIGN AND CALCULATIONS
Sub-structural projects may consist of, but are not limited to,
drainage boxes & systems, tunneling projects (mechanical or
manual tunnel excavations for the placement of tunnel supports),
and Trenchless Technologies for the installation of utilities when
the diameter is 30” or larger (jack & bore, micro- tunneling,
horizontal directional drilling, or pipe-ramming).
When the distance between the tunnel and an existing structure is
less than twenty times its diameter, it shall be sent to Structures
Maintenance for review of the potential lateral loading effects to
the pilings and foundation.
Otherwise, Sub-structural Project submittals, listed below and
submitted with the “Certification of Experience” (form TR-0133) do
not require review by Structures Maintenance or Underground
Structures.
• Micro-tunneling projects. • Bore & Jack, HDD, or Pipe Ramming
(hole-diameter is 30” or larger and requiring structural/sub-
structural design, investigations and calculations) • Tunneling for
the placement of tunnel support systems (rib & lagging, or
steel liner plate
requiring structural/sub-structural design, investigations and
calculations). • Drainage boxes and systems.
All Sub-structural Project submittals require the following:
The District Encroachment Permits Office is responsible for
verification of the Registered Engineer’s stamp, validation of the
date of expiration against the dated plan set and calculations. The
permit office engineer shall validate the RE’s stamp at the web
site listed below, by entering the RE’s number. A copy of the
results shall be printed and included within the permit file. The
encroachment permit may be issued, upon completion of the normal
review process (Traffic, Environmental, R/W, etc.).
3
• Designed plans and specifications, calculations and details
(liner plates, rib & lagging, bracing, etc.).
• A geotechnical investigation and soil analysis by a licensed
geotechnical engineer is required. It shall provide identification
of any locations of difficulty, changes in soil formation, or mixed
face conditions that could present or create ground loss,
exploratory soil corings and logs are required along the alignment
of the project.
• When the length of the tunnel is greater than four hundred feet
(> 400’), alignment holes may be required. Alignment holes shall
be drilled at a maximum spacing of two-hundred feet (200’) and a
casing of four to six inches (4” to 6”) in diameter installed
vertically, to a depth necessary for the installed casing to extend
into the tunnel excavation. When alignment holes fall within the
pavement area of the roadway, the pavement shall be saw-cut, a
cover shall be placed over the end of the casing at grade, and the
space around the casing within the roadway filled with concrete
(EXCEPT in controlled access right-of-way).
PROJECT OWNER’S RESPONSIBILITIES
On projects deemed by the Department as requiring full time
inspection, the project owner is responsible for providing a
third-party full-time inspector.
A full-time Safety Engineer: A Registered Structural or Civil
Engineer, with a minimum of five years’ experience in design or
inspection of Sub-structural Projects (tunnels). Proof of
experience shall be submitted on Encroachment Permits form
“Certification of Structural Experience” (form TR-0133) or
A full-time Safety Representative: State certified by Department of
Industrial Relations, Cal/OSHA Mining & Tunnel Unit, proof of
certification is required. California Code of Regulations 8406(f),
(h)
CONTRACTOR’S RESPONSIBILITIES
Prior to issuance of the “DP” permit the following shall be
submitted: • Proof of experience, as stipulated by the District
Office, in respect to diameter and length of
proposed project. • Tunnel support system construction plans and
specifications, calculations and details, method of
construction, to include the adequacy of the shield and liner
material stamped by a Registered Structural Engineer, or a
Registered Civil Engineer, with a minimum of five (5) years’
experience in sub-structural design and preparation of
calculations.
• “Notice of Materials to be used” (form CEM-3101). • Method of
construction plan. • A Licensed Surveyor. • Proof of rib expanders
and/or liner supports. • Working schedule of the project. •
Contingency plan for dealing with ground loss work. • Shaft; soil
stability at portals and ground improvement plan. • Dewatering
plans for entry and exit shafts/pits, if needed. • Installation and
monitoring of SWPPP or WPCP facilities and conditions. • Shoring
design for entry and exit shafts/pits. • Survey control plan:
lasers, laser mounting, laser checking. • Ground surface settlement
monuments and subsurface settlement monuments monitoring
program plan. o Buried points
4
All projects will vary in their own characteristics. General
similarities are listed below to provide a general understanding of
these types of projects.
Establishment of a survey-grid line and existing elevation points
shall be over the centerline and wing points of the
installation.
Designed plans and specifications, calculations and details (liner
plates, rib & lagging, bracing, etc.) shall be stamped by a
Registered Structural Engineer, or a Registered Civil Engineer,
with a minimum of five (5) years’ experience in sub-structural
design of tunnels. Proof of experience shall be submitted on
“Certification of Structural Experience” (form TR-0133) in
conjunction with project package submittal.
A geotechnical investigation and soil analysis by a licensed
geotechnical engineer/engineering geologist is required. It shall
provide identification of any locations of difficulty, changes in
soil formation, or mixed face conditions that could present or
create ground loss, exploratory soil corings and logs are required
along the tunnel alignment at intervals of twenty-five to
one-hundred feet {25’ to 100’}.
When the length of the tunnel is greater than four hundred feet
(> 400’), alignment holes may be required. Alignment holes shall
be drilled at a maximum spacing of two-hundred feet (200’) and a
casing of four to six inches (4” to 6”) in diameter installed
vertically, to a depth necessary for the installed casing to extend
into the tunnel excavation. When alignment holes fall within the
pavement area of the roadway, the pavement shall be saw-cut, a
cover shall be placed over the end of the casing at grade, and the
space around the casing within the roadway filled with concrete
(EXCEPT in controlled access right-of-way).
CAL/OSHA REQUIREMENTS
The California Code of Regulations (CCR) mandates the following
requirements for Tunneling Projects.
• The Owner or Local Entity proposing the construction of the
tunnel shall make a full submittal to the Department of Industrial
Relations, Cal/OSHA, to determine tunnel classification. CCR
8422
• Development of a check-in/check-out procedure to ensure an
accurate account of personnel underground in the event of an
emergency. CCR 8410
• Development of an Emergency Plan, that outlines duties and
responsibilities of all personnel on the project during an
emergency. The plan shall include ventilation controls,
firefighting equipment, rescue procedures, evacuation plans and
communications. CCR 8426
• Cal/OSHA requires a State of California certified person
performing the duties of gas tester or safety representative to be
certified by passing a written and an oral examination administered
by the Cal/OSHA Mining & Tunneling Unit. CCR 8406(f), (h)
• A certified safety representative shall direct the required
safety and health program and must be on-site while employees are
engaged in operations during which the Tunnel Safety Orders (TSO)
apply. CCR 8406(f)
• The certified safety representative must have knowledge in
underground safety, must be able to recognize hazards, and must
have the authority to correct unsafe conditions and procedures
subject to the TSO. CCR 8406(f)
A State of California certified gas tester is required for the
following operations:
• All classifications other than non-gassy • Projects during which
diesel equipment is used underground • Hazardous underground gas
conditions. CCR 8470
5
TUNNEL
Tunnel construction is accomplished by the method of Hand-mining,
or by Mechanical means, and the use of a protective shield.
Continuous monitoring and observation of the ground surface above
the tunnel is required. In some cases, it may be required to survey
and record elevations along the survey grid line, several times a
day, or daily.
Generally, when tunneling in good ground, tunnels with a diameter
of less than eight-feet (< 8’) and less than three-hundred feet
to four-hundred feet (300’ to 400’) in length may be holed-through
(excavated completely) before concreting the interior of the
tunnel, when placement of pre-fabricated or pre-cast pipe is to be
installed. When this is proposed, hole-through (unsupported length)
before concreting of the interior of the tunnel, it shall be
justified by the original subsurface geotechnical investigation and
design.
Tunnel lining and bracing should consist of steel ribs and steel
spreaders (dutchmen) with wood, concrete, or steel lagging, or with
bolted steel liner plates.
Fireproof materials should be utilized in all construction of plant
structures, above ground, within one hundred feet (100’) of the
shaft or tunnel. The use of flammable materials or wood shoring
would require that adequate fire protection be provided.
Ventilation systems shall be established and provide a minimum of
two hundred (200) cfm per worker.
• All equipment shall maintain a minimum clearance of twenty-five
feet (25’) from opening. • An established contingency plan in the
event of ground loss. • Cranes utilized in operations shall
maintain minimum required clearances.
TUNNEL SHIELD
• The face of the shield shall be provided with a hood or an
approved grid system. • The excavation face shall have a sufficient
length to allow for the installation of one (1) complete
ring of liner plates, or one (1) complete set of ribs and lagging
before advancing. • The contractor shall submit details and design
information of the shield.
TUNNEL LINING
Tunnel lining and bracing should consist of steel ribs and steel
spreaders with wood lagging and concrete, or steel lagging, or with
bolted steel liner plates.
The tunnel liner and bracing shall be designed (calculations
provided) of an adequate strength based upon the geotechnical
investigation, soil analysis, loading, and the diameter and depth
of cover to provide adequate support of the tunnel.
• A ring expander shall be used to expand the rib continuously
outward and upward. • Liner plates shall be designed based on joint
strength, minimum stiffness, critical buckling of the
liner plate wall, and deflection or flattening of the tunnel
section. • On tunnels with a diameter greater than ten feet (>
10’), the placement of ribs inside of liner plate
may be required. • When the geotechnical investigation has
determined that silts and fine sands exist, that may flow
under pressure, all liner plates shall include a neoprene gasket
adhered to each flange face.
6
LAGGING
Generally started at spring line and continue upwards towards the
crown. Lag spacing consists of three methods:
1. Wedging – done by driving a block of wood between the earth and
the lag at each end, or by driving a wedge between the rib and the
lag.
2. Stops – by welding small angles to the ribs outer flange to
prevent sliding. 3. Clamps – which are applied to wood or steel
lags.
If the spacing of lags between ribs is used in tunnel construction,
packing between lags with filler may be required.
• Lags are boards or steel plates placed longitudinally against the
roof and walls of the tunnel excavation.
• Steel lagging may consist of channel, liner plate or corrugated
metal. • Steel lagging thickness shall be designed on strength
based upon the geotechnical investigation,
soil analysis, and loading. • Wood lagging thickness shall be
designed on strength based upon the geotechnical
investigation,
soil analysis, loading. Generally wooden lags common size is
three-inches by six-inches (3” x 6”), and the length is cut
according to the spacing of the ribs.
• A minimum of one liner plate per ring with a two-inch (2”)
diameter coupling for grouting is required.
CONSTRUCTION OF SHAFTS / PITS
Shafts / pits should be constructed of a proper size and shape, and
equipped as to allow work to be carried on safely.
• Shafts must be constructed of driven steel sheet pilings, steel
bracing and tight wood, or steel lagging or steel liner plates and
ribs.
• The removal of spoils should be accomplished by mechanical means
(muck box). • All shafts must be provided with guardrail and a
toeboard. • When ladders are utilized within the shaft or pit,
cages and/or safety devices must be provided on
depths of 15 feet to 20 feet, platforms must be provided at depths
of greater than 20 feet. • Ventilation systems must be established
and provide a minimum of 200 cfm per worker. • All equipment must
maintain a minimum clearance of 25 feet from openings. • Upon
completion of project all shafts, pits and drifts that are not part
of the finished product must
be backfilled.
PLACEMENT OF SHAFTS / PITS
Shafts