83
Appendix E Groundwater Report 5 Appendix E Groundwater Report

Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Appendix E Groundwater Report

5 Appendix E Groundwater Report

Page 2: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

REPORT

Hydrogeological Assessments of the North Point and Princess Louise Deposits for Mine Development - Public Environmental Review

Prepared for

Burnside Operations Pty Ltd

PO Box 195 Pine Creek NT 0847

23 February 2007

42213762

J:\Jobs \42213762\Report\R001- A.doc

Hydrog eol ogical Assessments of the North Point and Princess Louise Deposits for Mi ne Devel opment - Public Envir onmental Revi ew

Page 3: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

Project Manager:

…………………………… Chris MacHunter Associate Hydrogeologist

Project Director:

…………………………… Richard Vogwill Senior Principal Hydrogeologist

URS Australia Pty Ltd

Level 3, Mitchell Street Darwin, NT 0801 GPO Box 2130, Darwin NT 0801 Australia Tel: 61 8 8980 2900 Fax: 61 8 8941 3920

Author:

…………………………… Chris MacHunter Associate Hydrogeologist

Date: Reference: Status:

23 February 2007 42213762 Final

Page 4: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Contents

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

1

Contents

1 Introduction ................................................................................................... 1-1

1.1 Background .................................................................................................................. 1-1

1.2 Project Location........................................................................................................... 1-1

1.3 Mine Development ....................................................................................................... 1-1

1.4 PER Guidelines ............................................................................................................ 1-1

2 Scope of Work and Proposed Approach..................................................... 2-1

2.1 Scope of Work.............................................................................................................. 2-1

2.2 Proposed Approach..................................................................................................... 2-1

2.2.1 Task 1 – Data Review, Model Conceptualisation and Liaison ...................... 2-1

2.2.2 Task 2 – Groundwater Drilling and Testing Programs .................................. 2-1

2.2.3 Task 3 - Groundwater Model Construction and Features ............................. 2-2

2.2.4 Task 4 - Groundwater Model Calibration....................................................... 2-2

2.2.5 Task 5 - Predictive Simulations – Dewatering Design, Environmental Impacts and Closure...................................................................................... 2-3

2.2.6 Task 6 – PER Groundwater Reporting.......................................................... 2-3

3 Drilling and Testing Program....................................................................... 3-1

3.1 Groundwater Drilling ................................................................................................... 3-1

3.1.1 Test Production Bores ................................................................................... 3-1

3.1.2 Groundwater Monitoring Bores...................................................................... 3-2

3.2 Bore and Aquifer Testing ............................................................................................ 3-2

3.2.1 Step-Drawdown Tests ................................................................................... 3-2

3.2.2 Constant Discharge and Recovery Tests...................................................... 3-2

4 Geology and Hydrogeology ......................................................................... 4-1

4.1 Geological Setting ....................................................................................................... 4-1

4.1.1 Regional Geology .......................................................................................... 4-1

4.1.2 Local Geology................................................................................................ 4-1

4.2 Hydrogeology............................................................................................................... 4-1

5 Groundwater Modelling Methodology......................................................... 5-1

5.1 Conceptual Hydrogeology Model............................................................................... 5-1

5.1.1 North Point..................................................................................................... 5-1

5.1.2 Princess Louise ............................................................................................. 5-1

5.2 Groundwater Flow Model Details ............................................................................... 5-1

Page 5: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Contents

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

2

5.2.1 Model Code ................................................................................................... 5-1

5.2.2 Model Domain................................................................................................ 5-1

5.2.3 Model Setup and Layering............................................................................. 5-2

5.2.4 Distribution of Hydraulic Properties ............................................................... 5-2

5.2.5 Boundary Conditions ..................................................................................... 5-2

5.2.6 Simplifying Assumptions for Modelling.......................................................... 5-3

5.2.7 Limitations of the Models............................................................................... 5-3

5.3 Model Calibration......................................................................................................... 5-4

5.3.1 Steady State Calibration................................................................................ 5-4

5.3.2 Transient Calibration ..................................................................................... 5-4

5.4 Predictive Simulations ................................................................................................ 5-4

5.5 Derived Hydraulic Parameters.................................................................................... 5-5

6 Groundwater Modelling Results .................................................................. 6-1

6.1 Estimated Dewatering Rates....................................................................................... 6-1

6.1.1 North Point..................................................................................................... 6-1

6.1.2 Princess Louise ............................................................................................. 6-1

6.2 Simulated Drawdown from Open Pit Development.................................................. 6-1

6.2.1 North Point..................................................................................................... 6-1

6.2.2 Princess Louise ............................................................................................. 6-1

6.3 Potential Impacts from Mine Dewatering .................................................................. 6-1

7 Conclusions and Recommendations .......................................................... 7-1

7.1 Conclusions.................................................................................................................. 7-1

7.2 Recommendations....................................................................................................... 7-1

8 References..................................................................................................... 8-1

9 Limitations..................................................................................................... 9-1

Page 6: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Tables, Figures, Plates, Drawings Appendices

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

3

Tabl es, Figures , Plates , Drawi ngs Appendices

Tables

Table 3-1 Bore Construction Details ................................................................................................... 3-1

Table 3-2 Constant Discharge Test Results ....................................................................................... 3-3

Table 4-1 Detailed Chemical Analyses ............................................................................................... 4-2

Table 5-1 Model Layers....................................................................................................................... 5-2

Table 5-2 Transient Calibration Results.............................................................................................. 5-4

Table 5-3 Hydraulic Parameters Derived from the Calibrated Models ............................................... 5-5

Figures

Figure 1 Regional Locality Plan

Figure 2 Sites and Surrounds

Figure 3 Bore Locations – North Point

Figure 4 Bore Locations – Princess Louise

Figure 5 Production Bore NPPB1 – Step-Rate Test

Figure 6 Production Bore PLPB1 – Step-Rate Test

Figure 7 Production Bore NPPB1 – Constant-Rate Test

Figure 8 Production Bore PLPB1 – Constant-Rate Test

Figure 9 Regional Geology

Figure 10 Model Grid – North Point

Figure 11 Model Grid – Princess Louise

Figure 12 Distribution of Hydraulic Parameters – North Point

Figure 13 Distribution of Hydraulic Parameters – Princess Louise

Figure 14 Transient Calibration – North Point

Figure 15 Transient Calibration – Princess Louise

Figure 16 Estimated Groundwater Pumpage – North Point and Princess Louise

Figure 17 Predicted Drawdown North Point – 300 Days Pumpage at 4146 kL/day

Figure 18 Predicted Drawdown North Point – 300 Days Pumpage at 425 kL/day

Figure 19 Predicted Extent of Drawdown – 300 Days Error! No tab le of figures entries found. Error! No tab le of figures entries found.

Appendices

A. Bore Completion Diagrams

Page 7: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 1 Introduction

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

1-1

1 Introduction

1.1 Background

Burnside Operations Pty Ltd (BOPL) plan to commence mining operations at North Point and Princess Louise deposits. Prior to mine development, a Public Environmental Review (PER) is required to obtain regulatory approval for the mines.

BOPL, as part of the project PER, requires an assessment of the environmental impacts of groundwater level lowering (drawdown) near the proposed mines, caused by pit dewatering.

To satisfy the guidelines for the PER, hydrogeological investigations comprised:

(i) the installation of test production bores (for aquifer testing) and groundwater monitoring bores at North Point and Princess Louise deposits; and

(ii) predictive groundwater flow modelling.

BOPL engaged URS Australia Pty Ltd (URS) to complete these assessments, as described in URS proposal 03036133, dated 6 September 2006.

1.2 Project Location

The Princess Louise and North Point deposits are located approximately 170 km southeast of Darwin and about 12 km northeast of Hayes Creek (Figure 1). This area occurs within the Burnside Project Area (BPA), a collection of mine sites all owned and operated by BOPL, and described as the area within a 30 km radius of the Brocks Creek Mine Site (Figure 2).

1.3 Mine Development

The proposed mine developments comprise conventional staged open pits, mined by a fleet of conventional rope shovels, hydraulic excavators and large haul trucks.

The proposed gold mining operations at Princess Louise and North Point mine sites are relatively small scale and short term, with the two open pit operations proposed to be completed within approximately 4 months.

It is anticipated that the Princess Louise pit will extend to approximately 35 m depth and produce 112,638 t of ore, while the North Point pit will be 25 m deep with 323,024 t ore extracted. Mining will intersect the water table at both sites and therefore pit dewatering will be required to ensure relatively dry and efficient mining.

1.4 PER Guidelines

Based on the Northern Territory EPA guidelines for the North Point and Princess Louise PER, the hydrogeological components of the PER need to include the following:

• Description of the site and the regional groundwater systems;

• Discuss the existing uses, beneficial uses and quality;

• Describe the impacts associated with mining and pit dewatering on groundwater; and

• Management of groundwater and groundwater monitoring.

Page 8: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 2 Scope of Work and Proposed Approach

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

2-1

2 Scope of Work and Proposed Approach

2.1 Scope of Work

The scope of work for this project was outlined in URS proposal 03036133 and is summarised below.

• Data Review, Model Conceptualisation and Liaison;

• Groundwater Drilling and Testing Programs;

• Groundwater Model Construction and Features;

• Groundwater Model Calibration;

• Predictive Simulations – Dewatering and Environmental Impacts, and

• PER Groundwater Model Reporting.

2.2 Proposed Approach

The proposed approach (as described in our proposal) to complete the scope of work is outlined below.

2.2.1 Task 1 – Data Review, Model Conceptualisation and Liaison

In order to form a conceptual model of the mining areas and surrounding region, it will be necessary to review geological and hydrogeological data. Additional information is required for the local stratigraphy and hydrogeological parameters.

We will liaise with BOPL geologists to ensure that we fully understand the geology of the deposits and then form a conceptual groundwater model of each deposit prior to commencing model construction. This would require a visit to the Brocks Creek site office to review existing datasets and log core.

2.2.2 Task 2 – Groundwater Drilling and Testing Programs

Based on our conceptual model and known geology, we will design and complete a program of groundwater drilling and testing to assist in preliminary dewatering design and allow the quantification of environmental impacts.

Based on our hydrogeological interpretation, we will locate prospective groundwater targets and specify bore drilling methods and locations. One aquifer test bore will be located at each prospect, located outside the pit perimeter at each deposit if suitable data are available. Most of these locations will be sited in order that successful bores can be used for dewatering. Groundwater monitoring bores will also be constructed to measure groundwater quality down-gradient of the mine and will be used during aquifer testing to determine aquifer parameters.

Our hydrogeologists will visit site during the groundwater drilling and testing programs and liaise often with BOPL during the programs.

Our proposed field activities comprise the following groundwater exploration and testing programmes for PER completion.

North Point

• One test dewatering bore located outside the pit perimeter if available data allow this.

• Two groundwater monitoring bores to assist in the determination of aquifer properties through aquifer testing of production bores. We would locate these bores in long-term positions suitable for inclusion in a groundwater monitoring network.

Page 9: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 2 Scope of Work and Proposed Approach

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

2-2

• Completion of aquifer tests and collection of groundwater samples for analysis.

Princess Louise

• One test dewatering bore located outside the pit perimeter if available data allow this.

• Two groundwater monitoring bores to assist in the determination of aquifer properties through aquifer testing of production bores. We would locate these bores in long-term positions suitable for inclusion in a groundwater monitoring network.

• Completion of aquifer tests and collection of groundwater samples for analysis.

2.2.3 Task 3 - Groundwater Model Construction and Features

Our proposed model will be constructed using commercially available software such as Visual MODFLOW (finite-difference). URS proposes to use MODFLOW-SURFACT with Visual MODFLOW Pro Version 4 as the pre- and post-processors. MODFLOW-SURFACT contains several flow packages which complement/supplement the widely used USGS MODFLOW by enhancing the schemes for performing unconfined simulations to rigorously model desaturation/resaturation of aquifers.

The modelled area will be discretised into different material types and layers in order to simulate the interpreted geology and hydrogeology as closely as possible. The model will take into account such features as:

• The geometry and properties of known aquifer systems;

• The geology and structural geology of the site and the impact of these structures on groundwater flow;

• The layout of the mining areas and the proposed open-pits;

• The relationship between groundwater and surface water – both flows and levels, and

• Groundwater and surface water recharge-discharge mechanisms.

The model will be designed to incorporate additional groundwater drilling and testing information as it becomes available and this will lead to gradual model refinement as the mining operations commence. In this manner, the model can be used to refine, predict and quantify the required dewatering system for mining and also the potential environmental impacts associated with dewatering.

2.2.4 Task 4 - Groundwater Model Calibration

The calibration of the model will occur in two steps:

• Steady-State – during this calibration stage, groundwater levels generated by the model will be

matched to known groundwater levels and flow directions across the mining region. This will be

achieved by small variations in model parameters, especially hydraulic parameters such as

permeability and storativity. A successful steady-state calibration is a necessary precursor to the next

stage of model development.

• Transient – this is the most difficult and time-consuming stage of model calibration. During this work,

known aquifer response to pumping by bores is matched by simulating this pumping in the model.

This can be difficult to achieve. Model parameters are varied until a satisfactory drawdown response

to actual pumping is achieved. The model is then ready to be used for predictive simulations to

forecast available groundwater supply and assess potential environmental impacts.

Page 10: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 2 Scope of Work and Proposed Approach

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

2-3

2.2.5 Task 5 - Predictive Simulations – Dewatering Design, Environmental Impacts and Closure

2.2.5.1 Preliminary Pit Dewatering Design

The calibrated model will be used to calculate groundwater inflows to the pits. These inflows will give a preliminary indication of the amount of groundwater that has to be pumped to maintain efficient and relatively dry mining conditions. These results can be used to describe the required dewatering system for each pit.

Once the necessary abstraction rates have been established, these rates will used to simulate pit dewatering and determine the regional drawdown of the water table around the mining area.

2.2.5.2 Environmental Impacts

The main potential groundwater-related environmental impacts resulting from the proposed mining are associated with groundwater level lowering near the pits. Groundwater lowering may result in vegetation stress, and have impacts on the ecological water requirements that are needed to sustain flora and fauna associated with drainages of the area.

The model will be constructed to simulate the interaction of groundwater and surface water in the major drainages of the area. Specialised model cells, which represent potential points of leakage from surface water to groundwater, will be included in the model. These cells will occur in drainages, and floodplains of these drainages. This will allow modelled leakage to occur during wet season.

Drawdown predictions from the groundwater modelling will be used to evaluate the impacts of pit dewatering. Thus, the groundwater/surface water modelling will allow a quantification of environmental impacts and therefore assist in planning the mitigation of such impacts. This will be an important aspect of regulatory approval for the proposed mine development.

2.2.5.3 Mine Closure

We consider the development of a groundwater model to also be important in mine closure planning. As with environmental impacts, studies of final void water levels will be an important aspect of obtaining regulatory approval for the mine development.

2.2.6 Task 6 – PER Groundwater Reporting

The report will describe the field program completed, the hydrogeology of the mining area, the conceptual hydrogeological model for each deposit, the modelling results at the PER stage (dewatering and closure) and will also describe the potential environmental impacts associated with groundwater abstraction for pit dewatering. Results from this report can be directly imported into the PER document or be presented as an Appendix.

Page 11: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 3 Drilling and Testing Program

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

3-1

3 Drill ing and Testing Program

3.1 Groundwater Drilling

One test production bore and 2 groundwater monitoring bores were installed at the North Point and Princess Louise deposits (Figures 3 and 4) during December 2006 and January 2007. Drilling was completed by Bores NT with a truck-mounted drilling rig using air-hammer methods.

A 146 mm diameter pilot hole was drilled at each location. All holes were lithologically logged and sampled.

Bore construction details are summarised in Table 1 and discussed below.

Table 3-1 Bore Construction Details

Mine Grid MGA Bore

Easting Northing RL Easting Northing RL Depth (m)

Screened Interval (mbgl)

Groundwater Depth (mbtoc)

North Point

NPPB1 9646.63 9974.06 1112.67 8507303.87 775723.03 112.67 61 25-61 14.18

NPMB1 9734.50 9990.09 1113.22 8507391.73 775738.83 113.22 61 55-61 14.70

NPMB2 9403.15 10031.47 1123.36 8507060.67 775781.01 123.36 67 62-67 24.26

Princess Louise

PLPB1 9746 7100 - 8504750.83 775495.74 - 78 22-78 26.60

PLMB1 7092.82 9740.30 1146.06 - - 114.6 73 67-73 22.37

PLMB2 9694 6950 - - - - 66 60-66 16.10

Notes: mbgl = metres below ground level mbtoc = metres below top of collar

Bore logs, showing descriptions of strata and graphical well construction details, are presented in Appendix A.

3.1.1 Test Production Bores

3.1.1.1 North Point

One test production bore (NPPB1, Figure 3) was constructed and cased with 203 mm internal diameter casing and slotted steel bore screens.

The bore was drilled using air-hammer techniques and encountered fractured greywacke and tuff between the depths 24-28, 40-42, 47-48, 54-56 and 60-61.

Bore development was by air-lifting and surging, using compressed air to force groundwater into and out of the screened section, and discharge groundwater from the bore. The bore was developed by this method until silt-free groundwater returns were obtained.

3.1.1.2 Princess Louise

One test production bore (PLPW1, Figure 4) was constructed and cased with 203 mm internal diameter casing and slotted steel bore screens.

The bore was drilled using air-hammer techniques and encountered fractured greywacke and tuff between the depths 36-37m and 59-59m.

Page 12: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 3 Drilling and Testing Program

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

3-2

Bore development was by air-lifting and surging, using compressed air to force groundwater into and out of the screened section, and discharge groundwater from the bore. The bore was developed by this method until silt-free groundwater returns were obtained.

3.1.2 Groundwater Monitoring Bores

Two groundwater monitoring bores were drilled at each deposit and constructed using 50 mm nominal diameter uPVC casing. Machine-slotted uPVC casing (1 mm aperture slots) was used for the screened section. Details of the bore constructions are presented in Appendix A.

3.1.2.1 North Point

Two groundwater monitoring bores were installed at North Point (NPMW1 and 2, Figure 3) to assist with the determination of groundwater drawdown response from aquifer testing. The bores intersected siltstone, mudstone and greywacke.

3.1.2.2 Princess Louise

Two monitoring bores were installed at Princess Louise (PLMW1 and 2, Figure 4) to assist with the determination of groundwater drawdown response from aquifer testing. Both bores intersected siltstone, mudstone and greywacke.

3.2 Bore and Aquifer Testing

A program of bore and aquifer testing was completed in each of the test production bores to determine bore and aquifer properties.

Three types of tests were undertaken:

• Step-drawdown tests;

• Constant-discharge tests; and

• Recovery tests.

3.2.1 Step-Drawdown Tests

The step-drawdown tests were used to determine bore pumping characteristics and estimate a pumping rate suitable for the constant-discharge test. These tests comprised pumping the bore at rates that were increased incrementally (“steps”). The steps were generally of 60 minutes duration. Analyses of these results were used to determine well and formation loss factors and to select a suitable rate for the constant -discharge test.

Plots of the step-rate tests for North Point and Princess Louise are presented in Figures 5 and 6.

3.2.2 Constant Discharge and Recovery Tests

The constant-discharge test in each production bore was commenced following the step-drawdown test and after groundwater levels had recovered to near-initial static levels. Upon completion of each constant-discharge test, recovering groundwater levels were also measured and analysed.

The test pumping was undertaken by the drilling contractors using electric submersible pumps. Pumping rates were measured through an orifice weir. Electric contact meters (dip meters) were used to measure groundwater levels in both the pumped bore and the groundwater monitoring bores.

Page 13: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 3 Drilling and Testing Program

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

3-3

The constant-discharge test results enable the hydraulic characteristics of the aquifers intersected by each test production bore to be determined. These parameters quantify the storage and transmission of groundwater in the aquifer.

The results of the constant-rate tests and the calculated hydraulic parameters are shown on Table 3-2, with drawdown plots presented in Figures 7 and 8.

Table 3-2 Constant Discharge Test Results

Observation Bores Transmissivity (m2/day) Storativity

Pumping Bore

Date of Test

Pumping Rate

(kL/day)

Final Drawdown

(m) Bore No Dist. (m)

Theis Cooper-Jacob

(-)

North Point

NPPB1 (e) 500 -

NPPB1 (l) 0

100 -

NPMB1 (e) 430 3E-05

NPMB1 (l) 243

115 4E-04

NPMB2 (e) 740 1E-04

NPPB1 22/1/2007 1,640 5.44

NPMB2 (l) 332

100 110 5E-04

Princess Louise

PLPB1 (r) 0 35 -

PLMB1 (l) 20 22 5E-06

PLMB1 (r) 70

190 -

PLMB2 (l) 20 21 1E-03

PLPB1 18/1/2007 490 9.97

PLMB2 (r) 92

150 -

Notes: (e) – Early Time (l) – Late Time (r) – Recovery

Page 14: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 4 Geology and Hydrogeology

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

4-1

4 Geo logy and Hydrogeology

4.1 Geological Setting

4.1.1 Regional Geology

Previous mining operations in the vicinity of the project area have extracted gold, tin and the base metals, lead, zinc and copper. Gold mineralisation occurs in all units of the South Alligator Group and Burrell Creek Formation (Figure 9); a sequence of regionally metamorphosed greenschist facies, fine grained volcano-metasedimentary and mafic intrusive rocks. All gold prospects are associated with regional anticlinal structures that trend around the Burnside Granite pluton, in the core of the project area.

The largest gold deposits are located on the Howley Anticline, which hosts a series of deposits along its length and which has been the major source of gold in this area. Significant gold deposits have also been discovered and periodically mined over the last century in the East Burnside area. These prospects are hosted within large anticline structures and are spatially related to the regional northwest striking Pine Creek Shear Zone, which trends northwest between the Burnside and Margaret Granite plutons (BOPL, 2006).

4.1.2 Local Geology

The North Point and Princess Louise Deposits are hosted within the Mount Bonnie Formation of the South Alligator Group that comprises of a sequence of shale, mudstone, phyllite, siltstone, feldspathic greywacke and minor tuffaceous chert, tuff, argillite with rare banded iron formation and dolomite.

Gold mineralisation at the North Point and Princess Louise deposits is associated with quartz veining and centralised shear zones, located on the western limb of a north-south trending anticline. Both the North Point and Princess Louise deposits are located within the northwest-trending Pine Creek Shear Zone that forms part of a wrench fault system (NTGS, 1993).

4.2 Hydrogeology

Aquifers at North Point and Princess Louise occur primarily (from surface) within fractured greywacke, vuggy quartz veining and weathered greywacke and tuff in the bedrock. The most significant aquifer occurs within greywacke, which appears to have a moderate permeability at Princess Louise and high permeability at North Point.

Faults and shear zones that intersect the deposits also probably transmissive and will contribute groundwater inflow to the proposed pits where they intersect the walls.

Groundwater levels are relatively flat at both deposits with slight increases associated with topography. North Point groundwater levels are approximately 14 metres below ground surface and between 16 and 26 metres below ground surface at Princess Louise, depending on the topography.

Groundwater within each of the prospects is fresh with total dissolved solids ranging between 130 and 210 mg/L, and elevated iron and arsenic concentrations, especially at the North Point deposit. Groundwater is not considered potable at either site as it exceeds NHMRC Drinking water guidelines for arsenic of 0.007 mg/L (0.392 mg/L North Point, 0.053 mg/L Princess Louise) and aesthetic iron values of 0.3 mg/L (0.48 mg/L, North Point).

Detailed chemical analyses are presented in Table 4-1.

Page 15: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 4 Geology and Hydrogeology

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

4-2

Table 4-1 Detailed Chemical Analyses

Analyte Unit NPPB1 PLPB1

pH pH Unit 6.43 7.09

TDS mg/L 132 206

Hydroxide Alkalinity as CaCO3

mg/L <1 <1

Carbonate Alkalinity as CaCO3

mg/L <1 <1

Bicarbonate Alkalinity as CaCO3

mg/L 67 101

Total Alkalinity as CaCO3

mg/L 67 101

Sulphate as SO4 2- mg/L 14 7

Sulphur as S mg/L 5 2

Chloride mg/L 2.1 10.2

Calcium mg/L 4 3

Magnesium mg/L 11 19

Sodium mg/L 12 17

Potassium mg/L 3 4

Arsenic (dissolved) mg/L 0.392 0.053

Cadmium (dissolved)

mg/L 0.0002 <0.0001

Chromium (dissolved)

mg/L <0.001 <0.001

Copper (dissolved) mg/L <0.001 <0.001

Lead (dissolved) mg/L <0.001 <0.001

Nickel (dissolved) mg/L <0.001 <0.001

Zinc (dissolved) mg/L 0.017 0.012

Iron (dissolved) mg/L 0.48 0.29

Page 16: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 5 Groundwater Modelling Methodology

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

5-1

5 Groundwat er Modelling Methodology

5.1 Conceptual Hydrogeology Model

Interpretations of conceptual hydrogeology models for North Point and Princess Louise pits are described below.

5.1.1 North Point

• The local groundwater flow direction is towards the north-west and regionally towards the north, following topography and the associated drainages to the north.

• Groundwater levels are generally 14 metres below ground surface.

• Surficial cover is generally thin or non-existent near the pit and does not contain significant aquifer zones.

• The bedrock comprises a 25 metre wide shear/fracture zone through the pit, associated with the mineralisation and vuggy quartz fracturing.

• The bedrock weathering profile deepens in the vicinity of the pit, associated with the shear zone.

• The detailed geology beyond the mining area is generally unknown. Therefore, the modelled geology in regional areas is based on large-scale mapping.

5.1.2 Princess Louise

• The deposit is located on a groundwater divide and local groundwater flow direction is to the south west and regionally towards the north, following topography and associated drainages to the north.

• Groundwater levels are generally 25 metres below ground surface, depending on topography.

• Surficial cover is generally thin or non-existent in the vicinity of the pit and does not contain significant aquifer zones.

• The bedrock comprises a 15 metre wide shear/fracture zone though the pit, associated with the mineralisation and vuggy quartz fracturing.

• The weathering profile deepens throughout the pit area, associated with the shear zones.

• The detailed geology beyond the mining area is generally unknown. Therefore, the modelled geology in regional areas is based on large-scale mapping.

5.2 Groundwater Flow Model Details

5.2.1 Model Code

The model code selected was MODFLOW. MODFLOW is a three-dimensional block-centred finite-difference code developed by the USGS to simulate groundwater flow in the saturated subsurface. Visual MODFLOW Pro Version 4 was used as the pre- and post-processors.

5.2.2 Model Domain

5.2.2.1 North Point

Page 17: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 5 Groundwater Modelling Methodology

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

5-2

The model domain measures 2 km east-west and 2 km north-south (Figure 10), and was discretised into 6512 model cells (88 columns x 74 rows x 2 layers) with variable grid sizes. Each cell block represents a homogeneous hydrogeologic sub-unit of the hydrostratigraphic unit. Finer grids (6.5 m x 10 m) were used around the proposed open-pit and in areas of specific interest (Figure 10).

5.2.2.2 Princess Louise

The model domain measures 5.5 km east-west and 6 km north-south (Figure 11), and was discretised into 12412 model cells (107 columns x 116 rows x 2 layers) with variable grid sizes. Each cell block represents a homogeneous hydrogeologic sub-unit of the hydrostratigraphic unit. Finer grids (5 m x 5 m) were used around the proposed open-pit and in areas of specific interest.

5.2.3 Model Setup and Layering

In order to capture the regional and local flow of groundwater and physical changes caused by mining, the numerical models were designed to include the groundwater flow domains. Two layers identified in the conceptual model, were modelled as individual layers (Table 5-1).

Table 5-1 Model Layers

Layer Descriptions

North Point

1 Weathered Bedrock/Weathered Shear

2 Bedrock/Fresh Shear

Princess Louise

1 Weathered Bedrock/Weathered shear

2 Bedrock/Fresh Shear

5.2.4 Distribution of Hydraulic Properties

Uniform hydraulic conductivities (permeabilities) were assigned to layers 1 and 2, but were sub-zoned, based on the interpreted distributions of: (i) weathered bedrock; (ii) shear/fracture units. Figure 12 shows the distribution of permeability in the model for North Point and Figure 13 shows the distribution for Princess Louise.

For all shear/fracture units modelled, the horizontal permeability was made anisotropic (Ky, north-south ≠ Kx, east-west).

5.2.5 Boundary Conditions

Since the presence of physical boundaries to groundwater flow within the model domain is largely unknown, the hydraulic boundaries were arbitrarily selected at the model perimeter, a significant distance from the areas where groundwater is removed from the model to simulate open-pit dewatering.

No recharge has been defined, as the mining is planned during the dry season at both deposits.

Page 18: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 5 Groundwater Modelling Methodology

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

5-3

To simulate groundwater abstraction for pit dewatering, production bores were used in each model. Scheduling the flow rates and the number of bores at each pit allowed for the determination of dewatering rates.

5.2.6 Simplifying Assumptions for Modelling

Simplifying assumptions were made in order to discretise the groundwater flow conditions into a manageable package, without sacrificing the ability to simulate features which significantly contribute to the groundwater flow regime. The assumptions used are summarised below:

Aquifer Base

The bedrock below -500 mRL (North Point) and -100 mRL (Princess Louise) does not yield water and is impermeable to groundwater flow.

Top of Model

The top of the model is the current topography (Figures 3 and 4), with the uppermost layer being unconfined.

Hydraulic Parameters and Material Types

• The calibrated hydraulic parameters are representative beyond the calibrated domain of the model;

• The permeability zoning, which is based on the published bedrock geology of the area, broadly represents the hydrogeology; and

• Only major shear and permeable fracture zones of weathered bedrock are represented in the model. In general, the fresh bedrock in the mine area has a small permeability and contains limited aquifers.

Mine Development

The mining schedule for both deposits is equally sub-divided into monthly schedules.

Model Code

MODFLOW is a groundwater flow model code for fully saturated conditions. Hydraulic conductivity does not change with the change in water content. The reduction in hydraulic conductivity in unsaturated conditions is approximated by correcting the transmissivity for changes in the saturated thickness.

5.2.7 Limitations of the Models

The developed groundwater flow model has limitations. These limitations result from generalisations, interpretations and assumptions made in attempting to simulate the interpreted hydrogeology. The model limitations include:

• MODFLOW is a fully saturated groundwater flow model code, which can lead to an overestimation of the dewatered areas;

• The area occurs within a fractured rock environment, where the only major aquifers in the bedrock are secondary structures, such as faults and shear zones in the weathered zones. The models only represent the major secondary structures (faults and shear zones) in the area; and

• The limited data surrounding the deposits and the complexities of the hydrogeological regime mean that these models should only be used as a guide to determine impact areas and the likely groundwater abstraction rates required for dewatering. The interpretation of predictive simulations should be based on the assumptions made.

Page 19: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 5 Groundwater Modelling Methodology

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

5-4

5.3 Model Calibration

Model calibration is used to establish that the model can reproduce measured groundwater levels and flows, both regionally and during aquifer tests.

Calibration of the model occurs in two steps and these are described below.

5.3.1 Steady State Calibration

A steady state calibration was completed by:

• Assigning estimated hydraulic properties to the various material types in the model;

• Assigning assumed groundwater levels to the model boundaries, based on topography and known groundwater levels in the modelled area; and

• Running the model under current known hydraulic conditions for an infinite time (i.e., steady-state) to establish the regional groundwater flow gradient, flow pattern and groundwater elevations in the area.

• For both North Point and Princess Louise, a flat groundwater table was applied.

5.3.2 Transient Calibration

The groundwater elevations resulting from the steady-state calibration were used as initial conditions for all transient simulations.

During the transient calibration process, the hydraulic parameters were varied in order to get the best fit of modelled drawdown to the actual drawdown measured in observation bores during aquifer tests. The transient calibration was repeated for each of the aquifer tests (North Point and Princess Louise) in the test production bores with simulated groundwater levels tracked at the observation bore locations.

Steady state calibration is presented in Figures 14 and 15 and Table 5-2 shows that observed and simulated groundwater levels are comparable for North Point and Princess Louise.

Table 5-2 Transient Calibration Results

Observation Bore Observed Drawdown (m) Simulated Drawdown (m)

North Point

NPMB1 3.43 3.42

NPMB2 2.82 2.84

Princess Louise

PLMB1 4.62 4.51

PLMB2 4.40 4.56

5.4 Predictive Simulations

With the calibrated model, simulations of the open-pit dewatering system were completed to help assess the potential impacts of dewatering on regional groundwater levels and the hydrological environment and to determine the pit dewatering requirements.

Page 20: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 5 Groundwater Modelling Methodology

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

5-5

In order to model the dewatering of the open-pit and to assess the environmental impacts, the model was run in transient mode, with bores used to simulate the dewatering requirements, based on the mining schedules (elevation versus time).

The dewatering scenarios investigated used a staged mining schedule (BOPL, 2005), in order to quantify dewatering rates in line with proposed mining schedule.

Dewatering bores were placed along the shear/fracture zones to simulate groundwater abstraction from each pit. Dewatering rates of each bore were varied in order to achieve the drawdown required during the mining schedule at each deposit.

5.5 Derived Hydraulic Parameters

One hundred transient calibration runs were completed at North Point in order to match simulated aquifer test drawdown to actual. A total of thirty five transient calibration runs where completed at Princess Louise. Table 5-3 summarises the hydraulic parameters derived from the calibrated models that broadly correspond with the values derived from the aquifer tests.

Table 5-3 Hydraulic Parameters Derived from the Calibrated Models

Hydraulic Conductivity

(Permeability) Material Type

Model Layer

Descriptions

Kx Ky Kz

Specific Storage

Specific Yield

(m/d) (m/d) (m/d) (1/m) (-)

North Point

1 1 Weathered Bedrock 5 5 1 2E-04 0.05

2 1 Weathered Shear 20 60 20 5E-04 0.1

3 2 Fresh Shear 20 60 20 1E-05 0.015

4 2 Bedrock 0.01 0.01 0.001 5E-06 0.007

Princess Louise

1 1 Weathered Bedrock 0.5 0.5 0.05 5E-05 0.004

2 1 Weathered Shear 10 20 10 6E-05 0.1

3 2 Fresh Shear 2.5 4 1.4 6E-06 0.01

4 2 Bedrock 0.01 0.01 0.001 1E-06 0.001

Page 21: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 6 Groundwater Modelling Results

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

6-1

6 Groundwat er Modelling Results

6.1 Estimated Dewatering Rates

Estimated dewatering rates for the North Point and Princess Louise deposits are presented in Figure 16. The rates have been estimated for both deposits using the completed depths of mining after four months, and by comparing this to the simulated drawdown observed (Section 6.3). Each production bore simulated was screened to at least 5 metres below the anticipated depth of mining.

6.1.1 North Point

Three production bores was used to simulate the required drawdown based on the mining schedule at North Point. Each bore was pumped at a rate of 692 kL/day (8 L/sec) for 120 days (4 months).

The estimated dewatering rates at North Point are 2,074 kL/day (24 L/sec), sustained throughout the anticipated mining duration of 3 months with a one month lead time prior to mining.

The long-term dewatering rates will decrease as the aquifer interval is progressively dewatered.

6.1.2 Princess Louise

One production bore was used to simulate the required drawdown based on the mining schedule at Princess Louise. The bore was initially pumped at 425 kL/day (4.9 L/sec), sustained throughout the anticipated mining duration of 3 months with a one month lead time prior to mining.

The long-term dewatering rates will decrease as the aquifer interval is progressively dewatered.

6.2 Simulated Drawdown from Open Pit Development

Figures 17 and 18 show the simulated extent of drawdown for North Point and Princess Louise after 120 days (4 months) of groundwater abstraction at the anticipated dewatering rates (Section 6.1).

6.2.1 North Point

The extent of drawdown after 4 months of abstraction at 2,074 kL/day from three production bores indicated 1 metre reductions in groundwater level between 680 and 810 m to the north and south of the planned pit, and between 360 and 425 m to the east and west. Most of the abstraction will occur from within the shear zone, weathered bedrock and permeable zones within the bedrock. By the end of mining, the groundwater level within the pit will be 15 m below the original static groundwater level or approximately 30 m below ground level.

6.2.2 Princess Louise

The extent of drawdown after 4 months of pumpage at 425 kL/day from one production bore indicated 1 metre reductions in groundwater level between 1.1 km and 2.1 km to the north and south of the planned pit, and between 700 m and 720 m to the east and west. Most of the abstraction will occur from within the shear zone, weathered bedrock and permeable zones within the bedrock.

6.3 Potential Impacts from Mine Dewatering

Based on the simulated drawdown in the groundwater modelling, bedrock/shear zone groundwater levels will be lowered in the immediate area of the open pits because of the groundwater abstraction required for mine dewatering.

Groundwater lowering associated with dewatering of the proposed pits can cause drawdown in groundwater supply bores/stock wells if these are in close proximity to the proposed pits. Based on

Page 22: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 6 Groundwater Modelling Results

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

6-2

current knowledge, no existing users are located within the predicted cone of depression for both North Point and Princess Louise.

Groundwater lowering associated with dewatering of the proposed pits can also impact:

• Groundwater dependent ecosystems (GDEs) such as wetlands and swamps, features that are largely supported by groundwater and the position of the water table. We are unaware of any such features near the mining developments.

• Stream flows in surface drainages, although most of the pit dewatering will occur during the dry season, when such drainages are dry.

Our preliminary assessment indicates that dewatering of the two open-pits will have little impact on the groundwater resources of the region or features that are supported by groundwater. Both of these mining developments require only minor dewatering for a relatively short period of time, which will minimise potential impacts on groundwater.

The proponent will incorporate the existing groundwater monitoring bores into a groundwater monitoring system to ensure that any groundwater-related impacts are recognised and can therefore be mitigated.

Page 23: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 7 Conclusions and Recommendations

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

7-1

7 Conclusions and Recommendations

Based on the results of the drilling and testing programmes and groundwater modelling, the following conclusions and recommendations are summarised below.

7.1 Conclusions

• Drilling and testing programmes were undertaken at both North Point and Princess Louise deposits to assist with pit dewatering design and predict groundwater drawdown associated with dewatering, through the use of a groundwater flow model.

• The hydrogeology away from the mining areas is generally unknown. The regional hydrogeology is based on regional geological maps and structures, but the groundwater model does not take all of these into account.

• The modelled areas occur in a fractured rock environment. As such, the occurrence of aquifers is structurally controlled and quite complex. We feel that the main aquifers in each deposit comprise a central shear zone in both the weathered and fresh bedrock zones. Away from the central shears we believe that only minor aquifers occur and these are mainly located in the weathered zone.

• As a result, the groundwater models are approximate but can be used to assess order of magnitude variations in groundwater level as a result of pit dewatering and the required abstraction rates to meet dewatering requirements. Calibration of both models is only based on one pumping test at each deposit.

• No wetlands or swamps are present in the vicinity the drawdown predicted by the modelling.

• Dewatering will occur during the dry season when streams in proximity to the pits are not flowing.

• Dewatering discharge at Princess Louise is to be used for dust suppression purposes during the life of mining. Water quality is fresh, however the groundwater is slightly elevated in arsenic and iron concentrations.

• Due to the dewatering rates required at North Point, not all of the dewatering discharge can be used for dust suppression. Therefore, other water disposal options will need to be considered, such as evaporation ponds or irrigation. Water quality is fresh, however the groundwater has elevated arsenic concentrations and slightly elevated iron concentrations.

7.2 Recommendations

• Due to the likely excessive water requirements at North Point, the preferred water disposal options need to be determined.

• Incorporate the existing monitoring and production bores at the deposits into a groundwater monitoring programme and monitor throughout the life of the mining.

• As part of licensing requirements, it will probably be necessary to regularly monitor the performance of the dewatering systems (abstraction rates, groundwater levels) and the groundwater monitoring network for environmental reasons. This monitoring is recommended because it will also be advantageous to maintain relatively dry and efficient mining conditions by optimising dewatering system performance.

• At this stage, the design of the dewatering systems is preliminary. As mining schedules and mine designs become more definitive, it is recommended that the dewatering designs are refined.

Page 24: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 8 References

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

8-1

8 References

Burnside Operation Pty Ltd (BOPL) (2006), Mine Management Plan – Cosmo Project Area, July 2006

Burnside Operations Pty Ltd (BOPL) (2005), Brocks Creek and Cosmo Open Pit Mining Study April 2005.

Northern Territory Geological Survey (NTGS), (2006), Pine Creek SD 52-8, Metallogenic Map Series Explanatory Notes and Mineral Deposit Data Sheets, Department of Mines and Energy, Northern Territory Government, 1993.

Page 25: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Section 9 Limitations

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

9-1

9 Limit ations

URS Australia Pty Ltd (URS) has prepared this report in accordance with the usual care and thoroughness of the consulting profession for the use of GBS Australia Pty Ltd and only those third parties who have been authorised in writing by URS to rely on the report. It is based on generally accepted practices and standards at the time it was prepared. No other warranty, expressed or implied, is made as to the professional advice included in this report. It is prepared in accordance with the scope of work and for the purpose outlined in the Proposal dated 6 September 2006 (3036133).

The methodology adopted and sources of information used by URS are outlined in this report. URS has made no independent verification of this information beyond the agreed scope of works and URS assumes no responsibility for any inaccuracies or omissions. No indications were found during our investigations that information contained in this report as provided to URS was false.

This report was prepared between 22 January 2007 and 23 February 2007 and is based on the conditions encountered and information reviewed at the time of preparation. URS disclaims responsibility for any changes that may have occurred after this time.

This report should be read in full. No responsibility is accepted for use of any part of this report in any other context or for any other purpose or by third parties. This report does not purport to give legal advice. Legal advice can only be given by qualified legal practitioners.

This report contains information obtained by inspection, sampling, testing or other means of investigation. This information is directly relevant only to the points in the ground where they were obtained at the time of the assessment. The borehole logs indicate the inferred ground conditions only at the specific locations tested. The precision with which conditions are indicated depends largely on the frequency and method of sampling, and the uniformity of conditions as constrained by the project budget limitations. The behaviour of groundwater and some aspects of contaminants in soil and groundwater are complex. Our conclusions are based upon the analytical data presented in this report and our experience. Future advances in regard to the understanding of chemicals and their behaviour, and changes in regulations affecting their management, could impact on our conclusions and recommendations regarding their potential presence on this site.

Where conditions encountered at the site are subsequently found to differ significantly from those anticipated in this report, URS must be notified of any such findings and be provided with an opportunity to review the recommendations of this report.

Whilst to the best of our knowledge information contained in this report is accurate at the date of issue, subsurface conditions, including groundwater levels can change in a limited time. Therefore this document and the information contained herein should only be regarded as valid at the time of the investigation unless otherwise explicitly stated in this report.

Page 26: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

H Y D R O G E O L O G I C A L A S S E S S M E N T S O F T H E N O R T H P O I N T A N D P R I N C E S S L O U I S E D E P O S I T S F O R M I N E D E V E L O P M E N T - P U B L I C E N V I R O N M E N T A L R E V I E W

Appendix A Bore Completion Diagrams

Prepared for Burnside Operations Pty Ltd, 23 February 2007 J:\Jobs\42213762\Report\R001-A.doc

A. Bor e Compl etion Di agrams

Page 27: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Cla

ssif

ica

tio

n

M

Pe

ne

tra

tio

n

Ca

sin

g

S

De

pth

(m

)

decreased gravel component

Mo

istu

re

H

Le

ge

nd

USC DESCRIPTION OF STRATA

TUFF: silt with sand, fine to very finecoarse grain sand, light grey/tan colour,minor gravels up to 10mm in diameter

increased sand component

WELL CONSTRUCTION DETAILS

EN

VIR

O_

WE

LL

_A

DE

LA

IDE

W

CC

_A

US

.GD

T J:\JO

BS

\42

21

37

62

\BO

RE

LO

GS

\LO

GS

NO

RT

H P

OIN

T.G

PJ 2

3/2

/07

R

Wa

ter

De

pth

(m

)

Air

lift

(l/

se

c)

Me

tho

d

Sample

ParametersType, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

SILTSTONE: silt with gravels up to 20mmin diameter, fine to coarse grain sand, tancolour

TUFF

SILTS

ML

silt with gravels, decreased gravelcomponent up to 7mm in diameter

D

SILT with Gravel: grey/red/brown colour,gravels up to 10mm in diameter, angular

Pre-collar -254mm

Cementtopseal

D

D

D

D

203mmdiameter solidsteel casing

Ha

mm

er

D

RN35486

Standpipe

Welded top plate

Logged By:

Checked By:

Date Started:

Date Finished:

MONITORING WELL NPPB1

08 8941 3920

MK6

Sheet 1 of 6

08 8980 2900URS Australia

Level 3, 93 Mitchell Street, Darwin

0

1

2

3

4

5

6

7

8

9

ProjectReference:

Drilling Contractor:

254 mm

61.00 m

203 mm

Bore Size:

Total Depth:

Casing Size:

Project No.: 42213762

112.67

8507303.87 mN

775723.03 mE

Client:

Down hole hammer

Drill Fluid:

BMW

CMH

12-12-06

19-12-06 Foam

Burnside Operations

North Point

Permit No:

Location:

Drill Model:

Bores NT

Relative Level:

Coordinates:

Drill Type:

BurnsideOperations

Page 28: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

GRAYWACKE: silt with sand and gravel,gravels up to 7mm in diameter, very fine tocoarse grain sand, poorly to well sorted

foam injected at 13m bgl

EN

VIR

O_

WE

LL

_A

DE

LA

IDE

W

CC

_A

US

.GD

T J:\JO

BS

\42

21

37

62

\BO

RE

LO

GS

\LO

GS

NO

RT

H P

OIN

T.G

PJ 2

3/2

/07

D

D

D

Packer at21m bgl

Standing waterlevel at 13.05mTOC at 22/1/07

D

increased gravel component, up to 12mmin diameter, poorly sorted

D

decreased gravel component, increasedsand component

increased gravel component up to 4mm indiameter

SILTSTONE: gravel with silt, gravels up to10mm in diameter, poorly to well sorted,grey/tan colour

GRAYWACKE: gravel with silt, wellsorted gravels up to 15mm in diameter,subangular to subrounded, tan colour

decreasing gravel component, increasingsilt component

USC DESCRIPTION OF STRATA

Le

ge

nd

Cla

ssif

ica

tio

n

Mo

istu

re

De

pth

(m

)

Pre-collar -254mm

SILTS

D

GRYW

S

GRYW

Ha

mm

er

203mmdiameter solidsteel casing

DTUFF

Burnside Operations

WELL CONSTRUCTION DETAILS

ProjectNo.:

ProjectReference:

10

11

12

13

14

15

16

17

18

19

20

21

Ca

sin

g

08 8980 2900

Sheet 2 of 6

08 8941 3920

MONITORING WELL NPPB1

URS Australia

Level 3, 93 Mitchell Street, Darwin

Pe

ne

tra

tio

n

M RH

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Me

tho

d

Air

lift

(l/

se

c)

42213762

Wa

ter

De

pth

(m

)

Page 29: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Cla

ssif

ica

tio

nH

TUFF: silt with gravel, dark grey, up to5mm in diameter, angular to subangular

decreased silt component, increasedgravel component up to 25mm in diameter

water cut at 24m bgl

decreasing silt component with depth

gravels up to 10mm in diameter, angular,well sorted, pale grey

W

Le

ge

nd

M

Mo

istu

re

WELL CONSTRUCTION DETAILS

De

pth

(m

)

SCa

sin

g

Pe

ne

tra

tio

n

EN

VIR

O_

WE

LL

_A

DE

LA

IDE

W

CC

_A

US

.GD

T J:\JO

BS

\42

21

37

62

\BO

RE

LO

GS

\LO

GS

NO

RT

H P

OIN

T.G

PJ 2

3/2

/07

R

USC DESCRIPTION OF STRATA

TUFF

10l/sec

18l/sec

GRYW

Pre-collar -254mm

24m bgl: 366 uS/cm 7.35 pH

28m bgl: 174.4 uS/cm 7.6 pH

Ha

mm

er

203mmdiameter slottedsteel casing

D/M

W

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

08 8941 3920

M

ProjectNo.:

ProjectReference:

22

23

24

25

26

27

28

29

30

31

32

33

URS Australia

Level 3, 93 Mitchell Street, Darwin

08 8980 2900

Sheet 3 of 6

Sample

Parameters

Me

tho

d

Air

lift

(l/

se

c)

Wa

ter

De

pth

(m

)

Burnside Operations42213762

MONITORING WELL NPPB1

Page 30: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

USC DESCRIPTION OF STRATA

W

W

W

gravels up to 15mm in diameter, angular,poorly to well sorted

GRAYWACKE: silt with gravel, gravels upto 10mm in diameter, grey colour

increased gravel component up to 20mmin diameter, dark grey colour

W

Le

ge

nd

Cla

ssif

ica

tio

n

Mo

istu

re

WELL CONSTRUCTION DETAILS

decreased gravel component up to 10mmin diameter

S

EN

VIR

O_

WE

LL

_A

DE

LA

IDE

W

CC

_A

US

.GD

T J:\JO

BS

\42

21

37

62

\BO

RE

LO

GS

\LO

GS

NO

RT

H P

OIN

T.G

PJ 2

3/2

/07

Pe

ne

tra

tio

n

M

decreased gravel component

GRYW

pyrite crystals up to 3mm in diameter

gravels up to 20mm in diameter, angular

gravels up to 15mm in diameter, angular

12l/sec

12l/sec

18l/sec

W

TUFF

W

36m bgl 186.1 uS/cm 7.86 pH

40m bgl: 168.2 uS/cm 7.86 pH

42m bgl: 153.8 uS/cm 7.69 pH

Ha

mm

er

203mmdiameter slottedsteel casing

W

W

Ca

sin

g

De

pth

(m

)

Burnside OperationsProjectNo.:

ProjectReference:42213762

URS Australia

Level 3, 93 Mitchell Street, Darwin

08 8980 2900

Sheet 4 of 6

08 8941 3920

MONITORING WELL NPPB1

34

35

36

37

38

39

40

41

42

43

44

45

H

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Me

tho

d

Air

lift

(l/

se

c)

Wa

ter

De

pth

(m

)

R

Page 31: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Le

ge

nd

R

W

W

W

W

W

W

Ha

mm

er

USC DESCRIPTION OF STRATA

54m bgl: 153.4 uS/cm 7.39 pH

Cla

ssif

ica

tio

n

Mo

istu

re

WELL CONSTRUCTION DETAILS

De

pth

(m

)

S

MUDSTONE: silt with gravel, quartzgravels up to 30mm in diameter, poorlysorted

Pe

ne

tra

tio

n

EN

VIR

O_

WE

LL

_A

DE

LA

IDE

W

CC

_A

US

.GD

T J:\JO

BS

\42

21

37

62

\BO

RE

LO

GS

\LO

GS

NO

RT

H P

OIN

T.G

PJ 2

3/2

/07

decreased quartz gravels

gravels up to 5mm in diameter, well sorted

TUFF: silt with gravel, gravels up to 15mmin diameter, poorly sorted

gravels up to 40mm in diameter

increase in gravel component

16l/sec

20l/sec

203mmdiameter slottedsteel casing

M

GRYW

MUDS

TUFF

48m bgl: 163.9 uS/cm 8.05 pH

Burnside OperationsC

asin

g

ProjectNo.:

ProjectReference:

46

47

48

49

50

51

52

53

54

55

56

57

H

08 8980 2900

Sheet 5 of 6

08 8941 3920

MONITORING WELL NPPB1

URS Australia

Level 3, 93 Mitchell Street, Darwin

Air

lift

(l/

se

c)

Wa

ter

De

pth

(m

)

Me

tho

d

Sample

ParametersType, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

42213762

Page 32: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

EN

VIR

O_

WE

LL

_A

DE

LA

IDE

W

CC

_A

US

.GD

T J:\JO

BS

\42

21

37

62

\BO

RE

LO

GS

\LO

GS

NO

RT

H P

OIN

T.G

PJ 2

3/2

/07

Cla

ssif

ica

tio

n

Mo

istu

re

WELL CONSTRUCTION DETAILS

De

pth

(m

)

SCa

sin

g

Pe

ne

tra

tio

n

USC DESCRIPTION OF STRATA

RH

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Me

tho

d

Air

lift

(l/

se

c)

decreased gravel component

M

increase in gravel component, up to15mm in diameter

quartz vein, quartz gravel up to 100mm indiameter in fine silt, increased waterproduction ~ 25 to 30 L/Sec

End of Hole at 61m bgl

Le

ge

nd

Ha

mm

er

End Cap

W

W

W

TUFF

Wa

ter

De

pth

(m

)

58

59

60

61

62

63

64

65

66

67

68

69

URS Australia

Level 3, 93 Mitchell Street, Darwin

Sheet 6 of 6

ProjectReference:08 8941 3920

MONITORING WELL NPPB1

08 8980 2900 ProjectNo.: 42213762 Burnside Operations

Page 33: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

SILTSTONE: fine grain with gravels up to2mm in diameter, brown/tan colour

MUDSTONE: fine grain, gravels up to15mm in diameter, grey colour

very fine grain, yellow/tan colour

SILTSTONE: very fine grain palegrey/cream colour, fine grain with gravelsup to 1mm in diameter

MUDSTONE: very fine grain, dark greycolour, minor rounded gravels up to 4mmin diameter

SILTSTONE: very fine grain. cream/tancolour, 10% gravels up to 4mm indiameter

DOLERITE: fine grain, cream/tan colour,gravels up to 10mm in diameter, rounded

SILT with SAND: very fine grain sand,cream/tan colour, minor gravels up to5mm in diameter

Bentonite plug

Cementtopseal

D

D

D

SILTSTONE: very fine grain, cream/tancolour, minor gravels up to 5mm indiameter

USC DESCRIPTION OF STRATA

M

Penetration

ENVIRO_WELL_ADELAIDE WCC_AUS.G

DT J:\JOBS\42213762\BORE LOGS\LOGS NORTH POINT.G

PJ 23/2/07

S

WELL CONSTRUCTION DETAILS

Moisture

Legend

D

Classification

D

MUDS

SILTS

MUDS

SILTS

DOL

SILTS

ML

Casing

D

D

D

50mm diametersolid PVCcasing.

Hammer

Pre-collar -254mm

SILTS

D

RN35483

Bores NT

ProjectReference:

PVC cap

MK6

Foam

Burnside Operations

North Point

Permit No:

Depth (m)

Location:

R

Drill Model:

Logged By:

Checked By:

Date Started:

Date Finished:

MONITORING WELL NPMB1

08 8941 3920

08 8980 2900

BMW

CMH

8-12-06

9-12-06

URS Australia

Level 3, 93 Mitchell Street, Darwin

0

1

2

3

4

5

6

7

8

9

Standpipe

Sheet 1 of 6

Relative Level:

Coordinates:

H

Sample

Parameters

Method

Airlift (l/sec)

Water Depth (m)

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Drill Type:

BurnsideOperations

Bore Size:

Total Depth:

Casing Size:

42213762

Drill Fluid:

Drilling Contractor:

146 mm

61.00 m

mm

Project No.:

113.22

8507391.73 mN

775738.83 mE

Client:

Down hole hammer

Page 34: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Moisture

ENVIRO_WELL_ADELAIDE WCC_AUS.G

DT J:\JOBS\42213762\BORE LOGS\LOGS NORTH POINT.G

PJ 23/2/07

SILTSTONE: very fine grain, yellow/tancolour

MUDSTONE: very fine grain, tan/grey,minor carbonaceous gravels up to 2mm indiameter

GRAYWACKE: fine grain, minor gravelsup to 4mm in diameter, grey colour

USC DESCRIPTION OF STRATA

Standing waterlevel at 13.5 mTOC at 22/1/07

Classification WELL CONSTRUCTION DETAILS

Depth (m)

SCasing

Penetration

M H Legend

SILTS

MUDS

GRYW

Gravel - 5mmdiameter

rounded gravelpack

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Hammer

D

D/M

M/W

08 8980 2900

R

ProjectReference:

10

11

12

13

14

15

16

17

18

19

20

21

URS Australia

Level 3, 93 Mitchell Street, Darwin

Sample

Parameters

Sheet 2 of 6

08 8941 3920

MONITORING WELL NPMB1

Method

Airlift (l/sec)

Water Depth (m)

ProjectNo.: 42213762 Burnside Operations

Page 35: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Hammer

W

W

W

W

W

W

50mm diametersolid PVCcasing.

W

30m bgl: 224 uS/cm 5.96 pH

24m bgl: 132 uS/cm 6.2 pH

fine to coarse grain sand, minor siltgravels up to 30mm in diameter, wellsorted

WSILTSTONE: very fine to coarse grain,brown/tan/grey color, gravels up to 3mmin diameter

water cut at 24m

GRAYWACKE: fine to coarse grain sand,minor silt gravels up to 30mm in diameter,poorly sorted

SILTSTONE: silt and clay with gravels,low to medium plasticity, fine to coarsesand, gravels up to 20mm in diameter

SILTSTONE: silt and clay with somegravels, low to medium plasticity, gravelsup to 30mm in diameter

SILTSTONE: silt and clay with somegravels, low to medium plasticity, gravelsup to 4mm in diameter

GRAYWACKE: fine grain, well sortedsubangular gravels with minor sandgravels from 2-3mm up to 5mm indiameter - broken ground

ENVIRO_WELL_ADELAIDE WCC_AUS.G

DT J:\JOBS\42213762\BORE LOGS\LOGS NORTH POINT.G

PJ 23/2/07

W

6l/sec

Gravel - 5mmdiameter

rounded gravelpack

W

SILTSTONE: very fine grain, gravels up to2mm in diameter

GRYW

SILTS

SILTS

GRYW

6l/sec

SILTS

SILTSTONE: well sorted, gravels up to1mm in diameter

GRYW

SILTS

SILTS

SILTS

ProjectNo.: Burnside Operations42213762

GRAYWACKE: fine grain, grey in colour,low to medium plasticity, minor gravels upto 1mm in diameter

Sheet 3 of 6

MONITORING WELL NPMB1

08 8941 3920

ProjectReference:

08 8980 2900URS Australia

Level 3, 93 Mitchell Street, Darwin

22

23

24

25

26

27

28

29

30

31

32

33

Classification WELL CONSTRUCTION DETAILS

S Moisture

Depth (m)

Legend

USC DESCRIPTION OF STRATASample

Parameters

Water Depth (m)

Airlift (l/sec)

Method

Casing

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observationsHRM

Penetration

Page 36: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Depth (m)

fine to coarse grain sand, minor siltgravels up to 30mm in diameter, wellsorted, higher percentage of gravels thansand

foam injected at 34m bgl

fine to coarse grain sand, grey in color,gravels up to 15mm in diameter

increased sand component, decreasedgravel component, minor silt

increased gravel component (quartz), upto 50mm in diameter

decreased gravel component, minor silt

USC DESCRIPTION OF STRATA

Legend

Classification

Sample

Parameters

WELL CONSTRUCTION DETAILS

SCasing

Penetration

M

6l/sec

ENVIRO_WELL_ADELAIDE WCC_AUS.G

DT J:\JOBS\42213762\BORE LOGS\LOGS NORTH POINT.G

PJ 23/2/07

H

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Moisture

50mm diametersolid PVCcasing.

6l/sec

6l/sec

GRYW34m bgl: 98.8 uS/cm 6.07 pH

36m bgl: 26.8 uS/cm 6.5 pH

Gravel - 5mmdiameter

rounded gravelpack

Hammer

W

W

W

W

W

R

42m bgl: 125.6 uS/cm 7.33 pH

MONITORING WELL NPMB1

Method

08 8941 3920

ProjectReference:

34

35

36

37

38

39

40

41

42

43

44

45

URS Australia

Level 3, 93 Mitchell Street, Darwin

08 8980 2900

Sheet 4 of 6

Airlift (l/sec)

Water Depth (m)

42213762 Burnside OperationsProjectNo.:

Page 37: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

USC DESCRIPTION OF STRATA

Gravel - 5mmdiameter

rounded gravelpack

increased gravel component

gravels up to 30mm in diameter

decreased gravel component

approximately 20% gravels up to 15mm indiameter

decreased gravel component

fine to very coarse grain sand, somegravels up to 15mm in diameter, dark greycolor

coarse grain gravel, pebbles up to 35mmin diameter

Legend

Classification

Moisture

WELL CONSTRUCTION DETAILS

Depth (m)

SCasing

6l/sec

M

ENVIRO_WELL_ADELAIDE WCC_AUS.G

DT J:\JOBS\42213762\BORE LOGS\LOGS NORTH POINT.G

PJ 23/2/07

increased gravel size, up to 70mm indiameter

50mm diametersolid PVCcasing.

6l/sec

GRYW

48m bgl: 168.8 uS/cm 7.05 pH

Hammer

50mm diameterslotted PVCcasing

W

W

W

W

W

W

W

W

54m bgl: 133 uS/cm 7.25 pH

R

Penetration

08 8941 3920

ProjectNo.:

ProjectReference: Burnside Operations

46

47

48

49

50

51

52

53

54

55

56

57

URS Australia

Level 3, 93 Mitchell Street, Darwin

08 8980 2900

Sheet 5 of 6

H

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Method

Airlift (l/sec)

Water Depth (m)

MONITORING WELL NPMB1

42213762

Page 38: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Classification

Moisture

WELL CONSTRUCTION DETAILS

Depth (m)

SCasing

Penetration

RH

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Method

6l/sec

Water Depth (m)

ENVIRO_WELL_ADELAIDE WCC_AUS.G

DT J:\JOBS\42213762\BORE LOGS\LOGS NORTH POINT.G

PJ 23/2/07

M

Hammer

GRYW

Legend

60m bgl: 130.1 uS/cm 7.34 pH

USC DESCRIPTION OF STRATA

End Cap

Wreduced gravel component

End of Hole at 61m bgl

Airlift (l/sec)

58

59

60

61

62

63

64

65

66

67

68

69

URS Australia

Level 3, 93 Mitchell Street, Darwin

ProjectReference:

Sheet 6 of 6

08 8941 3920

MONITORING WELL NPMB1

08 8980 2900 ProjectNo.: 42213762 Burnside Operations

Page 39: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

silt grey/tan colour, minor gravels up to5mm diameter, slightly friable

GRAYWACKE: silt with gravel, gravels upto 10-15mm in diameter, well sorted, palegrey/tan colour

Cementtopseal

SILTSTONE: silt grey/tan, minor gravelsup to 5mm diameter

SILTSTONE: minor gravels up to 10mm indiameter, grey colour

TUFF: silt and sand with gravel up to20mm in diameter, grounded to subrounded, dark grey in colour

SILT with SAND: very fine grain sand,cream/ tan colour, minor gravels up to5mm in diameter

Bentonite plug

Gravel - 5mmdiameter

rounded gravelpack

Airlift (l/sec)

silt with sand and minor gravels up to3mm in diameter, light brown/tan/redcolour

S

Method

Sample

Parameters

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\LOGS NORTH POINT.GPJ 23/2/07

HM

Casing

Depth (m)

WELL CONSTRUCTION DETAILS

Moisture

Classification

Legend

USC DESCRIPTION OF STRATA

Penetration

GRYW

SILTS

SILTS

TUFF

ML

Hammer

D

D

D

D

D

D

50mm diametersolid PVCcasing.

Pre-collar -254mm

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

D

Logged By:

Checked By:

Date Started:

Date Finished:

PVC cap

Location:

ProjectReference:

MK6

RN35484 Foam

Burnside Operations

R

Permit No:

Water Depth (m)

08 8980 2900

MONITORING WELL NPMB2

08 8941 3920

Sheet 1 of 6

Standpipe

URS Australia

Level 3, 93 Mitchell Street, Darwin

0

1

2

3

4

5

6

7

8

9

BMW

CMH

10-12-06

11-12-06

North Point

Down hole hammer

Drill Fluid:

123.36

8507060.67 mN

775781.01 mE

Client:

42213762

Drill Model:

Bores NT

Relative Level:

Coordinates:

Drill Type:

BurnsideOperations

Bore Size:

Total Depth:

Casing Size:

Drilling Contractor:Project No.:

146 mm

67.00 m

mm

Page 40: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Gravel - 5mmdiameter

rounded gravelpack

SILTSTONE: silt, minor gravels up to1mm in diameter, pale grey/tan

SILTSTONE: silt, minor gravels up to7mm in diameter, pale grey/, slightlyfriable

SILTSTONE: silt with minor sand gravelsup to 1mm in diameter, tan colour

SILTSTONE: silt, minor gravels up to2mm in diameter, grey colour

silt, minor gravels up to 2mm in diameter,dark grey colour

silt, minor gravels up to 2mm in diameter,lighter grey colour

M

D/M

USC DESCRIPTION OF STRATA

Legend

Classification

Moisture

WELL CONSTRUCTION DETAILS

Depth (m)

Casing

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\LOGS NORTH POINT.GPJ 23/2/07

SILTS

SILTS

SILTS

SILTS

D/M

D/M

Hammer

50mm diametersolid PVCcasing.

D/M

D/M

D/M

Penetration

S

ProjectNo.:

ProjectReference:

10

11

12

13

14

15

16

17

18

19

20

21

URS Australia

Level 3, 93 Mitchell Street, Darwin

08 8980 2900

Sheet 2 of 6

08 8941 3920

MONITORING WELL NPMB2

RH

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Method

Airlift (l/sec)

Water Depth (m)

Burnside Operations42213762

Page 41: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

SILTSTONE: silt with minor fine coarsegrain sand, minor gravels up to 1mm indiameter

W

W

Standing waterlevel at 23.52 mTOC at 22/1/07

Gravel - 5mmdiameter

rounded gravelpack

SILTSTONE: silt, minor sand, gravels upto 2mm in diameter, tan/grey colour

Depth (m)

SILTSTONE/GRAYWACKE: silt withminor fine gravels, sorted, grey/tan colour

D/M

water cut at 30m bgl

GRAYWACKE: silt with gravel, gravels upto 10mm in diameter, pale grey/tan

USC DESCRIPTION OF STRATA

4l/sec

Classification

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\LOGS NORTH POINT.GPJ 23/2/07

WELL CONSTRUCTION DETAILS

SILTSTONE: silt, grey/tan colour

SILTS

SILTS

SILTS

SILTS

GRYW

M/W

D/M

30m bgl: 64.3 uS/cm 10.89 pH

Hammer

50mm diametersolid PVCcasing.

D/M

Moisture

S Legend

ProjectNo.:

ProjectReference:42213762

URS Australia

Level 3, 93 Mitchell Street, Darwin

08 8980 2900

Sheet 3 of 6

08 8941 3920

MONITORING WELL NPMB2

22

23

24

25

26

27

28

29

30

31

32

33

Casing

Penetration

M RH

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Method

Burnside Operations

Water Depth (m)

Airlift (l/sec)

Page 42: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Classification

Gravel - 5mmdiameter

rounded gravelpack

increasing gravels up to 5mm diameter,well sorted, coarse sand

TUFF: sand with silt and gravel, fine tocoarse grain sand, minor gravels up to4mm in diameter, dark grey colour

sand with silt and gravel, fine to coarsegrain sand, minor gravels up to 2mm indiameter

GRAYWACKE: gravel and sand, fine tocoarse grain sand, gravels up to 25mm indiameter

gravel and sand, fine to coarse grain sand,gravels up to 10mm in diameter

H Legend

Moisture

WELL CONSTRUCTION DETAILS

Depth (m)

SCasing

Penetration

M

7l/sec

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\LOGS NORTH POINT.GPJ 23/2/07

USC DESCRIPTION OF STRATA

GRYW

TUFF

GRYW

40m bgl: 395 uS/cm 9.25 pH

Hammer

50mm diametersolid PVCcasing.

W

W

W

W

W

R

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

ProjectNo.:

ProjectReference:

URS Australia

Level 3, 93 Mitchell Street, Darwin

08 8980 2900

Sheet 4 of 6

08 8941 3920

34

35

36

37

38

39

40

41

42

43

44

45

Sample

Parameters

Method

Airlift (l/sec)

Water Depth (m)

MONITORING WELL NPMB2

42213762 Burnside Operations

Page 43: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Legend

Gravel - 5mmdiameter

rounded gravelpack

TUFF: sand with gravels, very fine tomedium grain sand, minor gravels up to60mm in diameter, minor silt

GRAYWACKE: gravel with sand, minorsilt component, gravels up to 25mm indiameter, well to poorly sorted

gravel with sand, gravels well to poorlysorted, up to 10mm in diameter

gravel with sand, gravels well to poorlysorted, up to 20mm in diameter

R

USC DESCRIPTION OF STRATA

Classification

Moisture

WELL CONSTRUCTION DETAILS

Depth (m)

SCasing

6l/sec

M

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\LOGS NORTH POINT.GPJ 23/2/07

6l/sec

GRYW

TUFF

GRYW

46m bgl 228 uS/cm 8.3 pH

52m bgl: 176.2 8.22 pH

Hammer

50mm diametersolid PVCcasing.

W

W

W

W

46

47

48

49

50

51

52

53

54

55

56

57

08 8941 3920

H

Penetration

ProjectNo.:

ProjectReference:

URS Australia

Level 3, 93 Mitchell Street, Darwin

08 8980 2900

Sheet 5 of 6

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Method

Airlift (l/sec)

Water Depth (m)

42213762 Burnside Operations

MONITORING WELL NPMB2

Page 44: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

WELL CONSTRUCTION DETAILS

TUFF: sand and silt with gravels, 10%gravels up to 20mm in diameter, somequartz, very fine grain sand

End of Hole at 67.0m bgl

USC DESCRIPTION OF STRATA

Legend

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Moisture

End Cap

Depth (m)

SCasing

Penetration

6l/sec

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\LOGS NORTH POINT.GPJ 23/2/07

RH Classification

6l/sec

GRYW

W

58m bgl: 218 uS/cm 8.2 pH

66m bgl: 106 uS/cm 7.94 pH

Hammer

50mm diameterslotted PVCcasing

TUFF

Sample

Parameters

08 8941 3920

M

ProjectNo.:

ProjectReference:

58

59

60

61

62

63

64

65

66

67

68

69

URS Australia

Level 3, 93 Mitchell Street, Darwin

08 8980 2900

Sheet 6 of 6

Method

Airlift (l/sec)

Water Depth (m)

42213762 Burnside Operations

MONITORING WELL NPMB2

Page 45: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

WELL CONSTRUCTION DETAILS

M

Penetration

Casing

H

Depth (m)

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Moisture

Classification

Legend

USC DESCRIPTION OF STRATA

S

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

R

Water Depth (m)

Airlift (l/sec)

Method

Sample

Parameters

TUFF203mmdiameter solidsteel casing

Hammer

GRYW

D

SILTS

Pre-collar -254mm

GRAYWACKE: silt with gravel, up to10mm in diameter, grey/tan colour

TUFF: silt with minor gravel, up to 15mmin diameter, orange colour

decrease in gravel component

DSILTSTONE: silt with gravel, pale grey/tancolour, gravels up to 20mm in diameter

D

Cementtopseal

D

D

gravels up to 10mm in diameter

RN35848

Welded top plate

Standpipe

ProjectReference:

Logged By:

Checked By:

Date Started:

Date Finished:

08 8941 3920

Sheet 1 of 7

URS Australia

Level 3, 93 Mitchell Street, Darwin

0

1

2

3

4

5

6

7

8

9

08 8980 2900

Drilling Contractor:

254 mm

78.00 m

203 mm

Bore Size:

Total Depth:

Casing Size:

Project No.:

7014.00 mN

9713.00 mE

Client:

Down hole hammer

Drill Fluid:

BMW

CMH

1-5-07

1-6-07

MONITORING WELL PLPB1

Foam

Burnside Operations

Princess Louise

Permit No:

42213762Location:

MK6Drill Model:

Bores NT

Relative Level:

Coordinates:

Drill Type:

BurnsideOperations

Page 46: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

decreased gravel component

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

D

D Packer at21m bgl

gravels up to 8mm in diameter, mediumgrey colour

increase in gravel component, up to10mm in diameter

TUFF: silt with minor gravels up to 8mm indiameter, tan/cream/grey colour

GRAYWACKE: silt with gravels up to8mm in diameter, pink colour

gravels up to 6mm in diameter, grey/tancolour

D

gravels up to 15mm in diameter, mediumgrey colour

D

decreased gravel component, up to 5mmin diameter

USC DESCRIPTION OF STRATA

Legend

Classification WELL CONSTRUCTION DETAILS

TUFF: silt with minor gravels up to 5mm indiameter, pink/tan colour

GRYW

TUFF

GRYW

D

Depth (m)

Pre-collar -254mm

Hammer

203mmdiameter solidsteel casing

D

D

D

D

TUFF

Burnside Operations

Moisture

ProjectNo.:

ProjectReference:

10

11

12

13

14

15

16

17

18

19

20

21

S

08 8980 2900

Sheet 2 of 7

08 8941 3920

MONITORING WELL PLPB1

URS Australia

Level 3, 93 Mitchell Street, DarwinCasing

Penetration

M RH

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Method

Water Depth (m)

42213762

Airlift (l/sec)

Page 47: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

SMethod

decreased gravel component, up to 6mmin diameter, pale grey colour

gravels up to 20mm in diameter

water cut at 31m bgl

decreased silt component, gravels upto17mm in diameter, well sorted

USC DESCRIPTION OF STRATA

Legend

Classification

Moisture

decreased gravel component, up to 9mmin diameter, pale grey colour

Depth (m)

gravels up to 8mm in diameter, pale greycolour

Casing

Penetration

M RH

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

WELL CONSTRUCTION DETAILS

D/M

TUFF

Hammer

203mmdiameter slottedsteel casing

D

D

decreased gravel component, up to 7mmin diameter, pale grey colour

D

Airlift (l/sec)

M/W

W

W

Standing waterlevel at 26.0m

TOC at 18/1/07

decreased gravel component, up to 20mmin diameter, pale grey

decreased gravel component, up to 15mmin diameter

D

Sheet 3 of 7

Sample

Parameters

ProjectReference:

22

23

24

25

26

27

28

29

30

31

32

33

URS Australia

Level 3, 93 Mitchell Street, Darwin

08 8980 2900

08 8941 3920

MONITORING WELL PLPB1

Water Depth (m)

ProjectNo.:

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

42213762 Burnside Operations

Page 48: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

W

gravels up to 20mm in diameter

36m bgl: 225 uS/cm 6.77 pH

42m bgl: 224.4 uS/cm 6.99 pH

Hammer

203mmdiameter slottedsteel casing

W

W

W

TUFF W

URS Australia

Level 3, 93 Mitchell Street, Darwin

34

35

36

37

38

39

40

41

42

43

44

45

ProjectReference:

ProjectNo.:

W

2l//sec

08 8980 2900

Sheet 4 of 7

08 8941 3920

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

decrease in gravel component, increasedin silt component

3l/sec

TUFF

GRYW

MONITORING WELL PLPB1

Airlift (l/sec)

Method

42213762 Burnside Operations

Depth (m)

GRAYWACKE: silt with gravel, gravels upto 15mm in diameter, grey colour

gravels up to 2mm in diameter, very fineto coarse grain sand, grey colour

gravels up to 10mm in diameter

TUFF: silt with gravel and sand, gravels upto 18mm in diameter, well sorted

USC DESCRIPTION OF STRATA

Legend

Classification

Water Depth (m)

WELL CONSTRUCTION DETAILS

SCasing

Penetration

M RH

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Moisture

Page 49: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

W

48m bgl

54m bgl

Hammer

203mmdiameter slottedsteel casing

W

W

W

W

GRAYWACKE: sand with silt and gravel,gravels up to 3mm in diameter

increase in gravel component, gravels upto 8mm in diameter

decrease in gravel component, gravels upto 10mm in diameter

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

GRAYWACKE: silt with sand and gravel,gravels up to 8mm in diameter

W

Foam

USC DESCRIPTION OF STRATA

Legend

Classification

Moisture

WELL CONSTRUCTION DETAILS

Depth (m)

SCasing

Penetration

M

Foam

gravels up to 15mm in diameter

TUFF

GRYW

MUDS

GRYW

MUDSTONE: silt with sand and gravel,very fine to coarse grain sand, gravels upto 30mm in diameter

ProjectNo.:

ProjectReference:

46

47

48

49

50

51

52

53

54

55

56

57

08 8980 2900

Sheet 5 of 7

08 8941 3920

MONITORING WELL PLPB1

URS Australia

Level 3, 93 Mitchell Street, Darwin

Airlift (l/sec)

Method

Sample

ParametersType, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Burnside Operations

H

42213762

Water Depth (m)

R

Page 50: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Casing

gravels up to 5mm diameter, evidence ofoxidation

USC DESCRIPTION OF STRATA

Legend

Classification

Moisture

WELL CONSTRUCTION DETAILS

Airlift (l/sec)

S

evidence of oxidation

Penetration

M R

Foam

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

Method

Depth (m)

Hammer

3l/sec

GRYW

minor oxidation

68m bgl: 400 uS/cm 7.3 pH

minor oxidation

203mmdiameter slottedsteel casing

W

W

W

W

Sample

Parameters

62m bgl

URS Australia

Level 3, 93 Mitchell Street, Darwin 08 8941 3920

Water Depth (m)

MONITORING WELL PLPB1

H

ProjectNo.:

58

59

60

61

62

63

64

65

66

67

68

69

08 8980 2900

Sheet 6 of 7

ProjectReference:42213762 Burnside Operations

Page 51: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

MUDSTONE: sand with silt and gravel,dark grey colour, oxidised gravels up to6mm in diameter, non oxidised gravels upto 8mm in diameter

gravels up to 20mm in diameter, oxidisedgravels up to 3mm in diameter

oxidised gravels up to 12mm in diameter,non oxidised gravels up to 20mm indiameter

gravels up to 10mm diameter, reducedevidence of oxidation

increase in oxidised material

increase in gravel component, up to13mm in diameter, oxidised gravels up to7mm in diameter

GRAYWACKE: sand with silt and gravel,up to 8mm in diameter, no oxidation

End of Hole at 78m bgl

W

USC DESCRIPTION OF STRATA

Legend

Classification

Moisture

WELL CONSTRUCTION DETAILS

Depth (m)

S

4l/sec

Penetration

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

MUDS

GRYW W

W

74m bgl: 390 uS/cm 7.0 pH

Hammer

203mmdiameter slottedsteel casing

End Cap

W

W

W

W

MCasing

ProjectNo.:

ProjectReference:

70

71

72

73

74

75

76

77

78

79

80

81

URS Australia

Level 3, 93 Mitchell Street, DarwinBurnside Operations

08 8980 2900

Sheet 7 of 7

08 8941 3920

MONITORING WELL PLPB1

RH

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Method

Airlift (l/sec)

Water Depth (m)

42213762

Page 52: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Casing

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observationsHR

Penetration

Airlift (l/sec)

S

Depth (m)

WELL CONSTRUCTION DETAILS

Moisture

Classification

Legend

M

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

Sample

Parameters

Method

Water Depth (m)

SILTS

USC DESCRIPTION OF STRATA

D

50mm diametersolid PVCcasing

Hammer

D

TUFF D

Gravel - 5mmdiameter

rounded gravelpack

TUFF: silt with minor gravels, gravels upto 5mm in diameter, orange colour

gravels up to 30mm in diameter, greycolour

gravels up to 20mm in diameter D

Bentonite plug

Cementtopseal

SILTSTONE: silt with gravels up to 30mmin diameter

PVC cap

08 8941 3920

Drill Fluid:

Sheet 1 of 7

Standpipe

URS Australia

Level 3, 93 Mitchell Street, Darwin

0

1

2

3

4

5

6

7

8

9

MK6

08 8980 2900

MONITORING WELL PLMB1

Bore Size:

Total Depth:

Casing Size:

42213762

BurnsideOperations

146 mm

73.00 m

mm

Project No.:

146.06

8504750.83 mN

775495.74 mE

Client:

Down hole hammer

Drilling Contractor: Location:

ProjectReference:

RN35487 Foam

Burnside Operations

Princess Louise

Logged By:

Checked By:

Date Started:

Date Finished:

BMW

CMH

1-5-07

1-6-07

Drill Model:

Bores NT

Relative Level:

Coordinates:

Drill Type:

Permit No:

Page 53: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

M

Gravel - 5mmdiameter

rounded gravelpack

Standing waterlevel at 21.45 mTOC at 18/1/07

gravels up to 10mm in diameter, 80%gravels 1 to 5mm in diameter, grey colour

TUFF: silt with gravel, gravels up to 5mmin diameter, pale brownish/red colour

gravel up to 5mm in diameter, darkbrown/red colour

very fine silt, minor gravels up to 3mm indiameter

GRAYWACKE: silt with gravel, gravels upto 4mm in diameter, grey colour

increased gravel component, up to 15mmin diameter, grey colour

majority coarse grain sand up to 3mm indiameter

USC DESCRIPTION OF STRATA

Legend

Classification

Moisture

WELL CONSTRUCTION DETAILS

Depth (m)

SCasing

gravels up to 5mm in diameter, tan/pinkcolour, well sorted, majority coarse grainsand up to 1mm in diameter

Hammer

TUFF

TUFF

GRYW

50mm diametersolid PVCcasing.

D

D

D

D

D

D

D

D

Penetration

ProjectNo.:

ProjectReference:

10

11

12

13

14

15

16

17

18

19

20

21

URS Australia

Level 3, 93 Mitchell Street, DarwinBurnside Operations

08 8980 2900

Sheet 2 of 7

08 8941 3920

MONITORING WELL PLMB1

RH

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Method

Airlift (l/sec)

Water Depth (m)

42213762

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

Page 54: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Depth (m)

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

increased gravel component, up to 5mmin diameter

SILTSTONE: silt with minor gravels,gravels up to 10mm in diameter, pale grey

silt with minor gravels, gravels up to15mm in diameter, pale grey

USC DESCRIPTION OF STRATA

Legend

Classification

increased gravel component, up to 5mmin diameter

WELL CONSTRUCTION DETAILS

gravels up to 4mm in diameter, greycolour, majority silt

SCasing

Penetration

M R

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Moisture

D

GRYW

SILTS

Hammer

decreased gravel component, up to 4mmin diameter

D

Sample

Parameters

D

D

M/W

W

Gravel - 5mmdiameter

rounded gravelpack

50mm diametersolid PVCcasing.

Sheet 3 of 7

ProjectNo.:

H

22

23

24

25

26

27

28

29

30

31

32

33

URS Australia

Level 3, 93 Mitchell Street, Darwin

Method

08 8980 2900

08 8941 3920

MONITORING WELL PLMB1

Airlift (l/sec)

Water Depth (m)

ProjectReference:42213762 Burnside Operations

Page 55: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

increase in gravel component, up to20mm in diameter, evidence of oxidation

S

Gravel - 5mmdiameter

rounded gravelpack

water cut at 34m bgl

gravels up to 1mm in diameter, well sorted

SANDSTONE: gravel with sand and silt,gravels up to 20mm in diameter, sand fineto corse grain

decrease in gravel component, increase insand component

W

decrease in gravel component

W

decrease in gravel component, quartzgravels/pebbles up to 30mm in diameter,evidence of oxidation

MUDSTONE: gravel with silt and sand,90% of gravels up to 10mm in diameterwith minor gravels up to 40mm indiameter, weathering evident

increased yield at 44m bgl ~ 3L/sec

increased weathering and oxidationevident

1l/sec

Legend

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

Moisture

WELL CONSTRUCTION DETAILS

Depth (m)

gravels up to 10mm in diameter

1l/sec

SILTS

SANDS

MUDS

Classification

34m bgl: 527 uS/cm 6.2 pH

34m bgl: 317 uS/cm 6.36 pH

Hammer

50mm diametersolid PVCcasing.

W

W

W

W

W

W

W

W

Casing

ProjectReference:

ProjectNo.:

34

35

36

37

38

39

40

41

42

43

44

45

URS Australia

Level 3, 93 Mitchell Street, DarwinBurnside Operations

USC DESCRIPTION OF STRATA

42213762

MONITORING WELL PLMB1

08 8941 3920

Sheet 4 of 7

08 8980 2900

Penetration

M RH

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Method

Airlift (l/sec)

Water Depth (m)

Page 56: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Casing

increase in gravel component, up to30mm in diameter, majority coarse grainsand up to 3mm in diameter

decrease in gravel component, up to15mm, evidence of oxidation

USC DESCRIPTION OF STRATA

Legend

Classification

Moisture

WELL CONSTRUCTION DETAILS

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

S

decrease in gravel component, up to10mm in diameter, increase in silt andfine to coarse grain sand

Penetration

M RH

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

2l/sec

Method

Depth (m)

W

MUDS 46m bgl: 341 uS/m 8.22 pH

Hammer

50mm diametersolid PVCcasing.

W

decrease in gravel component

Wincrease in gravel component, up to30mm in diameter

foam injected at 49m

W

W

Gravel - 5mmdiameter

rounded gravelpack

reduced weathering and oxidation,increase in gravel diameter, minor pyritecrystals evident

Airlift (l/sec)

W

Sheet 5 of 7

ProjectReference:

Sample

Parameters

46

47

48

49

50

51

52

53

54

55

56

57

URS Australia

Level 3, 93 Mitchell Street, Darwin

Water Depth (m)

08 8980 2900 ProjectNo.:08 8941 3920

MONITORING WELL PLMB1

42213762 Burnside Operations

Page 57: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Legend

R

Gravel - 5mmdiameter

rounded gravelpack

increase in gravel component up to 10mmin diameter

decreased gravel component, increase insand and silt component

MUDSTONE: gravel with sand and minorsilt, gravels up to 15mm in diameter, grey,very fine to coarse grain sand, evidence ofoxidation and weathering

increase in gravel component, minorgravels up to 25mm in diameter, evidenceof oxidation

well sorted, minor gravels up to 15mm indiameter, minor oxidised evident

USC DESCRIPTION OF STRATA

Classification

Moisture

WELL CONSTRUCTION DETAILS

Depth (m)

SCasing

3l/sec

M

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

3l/sec

MUDS

MUDS

60m bgl: 297 uS/cm 8.02 pH

66m bgl: 235 uS/cm 7.98 pH

Hammer

50mm diametersolid PVCcasing.

50mm diameterslotted PVCcasing

W

W

W

W

W

58

59

60

61

62

63

64

65

66

67

68

69

H

Penetration

ProjectNo.:

ProjectReference:

URS Australia

Level 3, 93 Mitchell Street, Darwin

08 8980 2900

Sheet 6 of 7

08 8941 3920

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Method

Airlift (l/sec)

Water Depth (m)

Burnside Operations42213762

MONITORING WELL PLMB1

Page 58: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

M

USC DESCRIPTION OF STRATA

Legend

Classification

Moisture

WELL CONSTRUCTION DETAILS

Depth (m)

S Water Depth (m)

Penetration

increase in gravel component, up to25mm in diameter, evidence ofoxidisidation

RH

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Method

Casing

Hammer

MUDS

End of Hole at 73m bgl

50mm diameterslotted PVCcasing

End Cap

W

W

W

gravels up to 4mm in diameter

gravels up to 3mm in diameter, well sortedcoarse sand with silt and very fine grainsand

Sheet 7 of 7

ProjectReference:

Airlift (l/sec)

70

71

72

73

74

75

76

77

78

79

80

81

URS Australia

Level 3, 93 Mitchell Street, Darwin

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

08 8980 2900 ProjectNo.:08 8941 3920

MONITORING WELL PLMB1

42213762 Burnside Operations

Page 59: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Depth (m)

WELL CONSTRUCTION DETAILS

Moisture

Classification

Legend

Casing

Penetration

GRAYWACKE: silt with gravel, gravels upto 30mm in diameter, yellow/tan/orangecolour

gravels up to 20mm in diameter, pink/tancolour

SILTSTONE: silt with minor gravels,gravels up to 6mm in diameter, medium todark grey

USC DESCRIPTION OF STRATA

Method

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

S

Airlift (l/sec)

GRAYWACKE: silt with gravel, pale tangravels up to 30mm in diameter

Sample

ParametersType, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observationsHRM

Water Depth (m)

GRYW

gravels up to 15mm in diameter

GRYW

Hammer

SILTS

D

Bentonite plug

Gravel - 5mmdiameter

rounded gravelpack

Cementtopseal

D

D

D

D

D

50mm diametersolid PVCcasing

gravels up to 13mm in diameter

Standpipe

PVC cap

ProjectReference:

Logged By:

Checked By:

Date Started:

Date Finished:

MK6

RN35489 Foam

Sheet 1 of 6

MONITORING WELL PLMB2

08 8941 3920

08 8980 2900URS Australia

Level 3, 93 Mitchell Street, Darwin

0

1

2

3

4

5

6

7

8

9

Burnside Operations

Down hole hammer146 mm

66.00 m

mm

Project No.:

6950.00 mN

9694.00 mE

Princess Louise

Drill Fluid:

Client:

Drill Type:BMW

CMH

1-4-07

1-8-07

Location:Drilling Contractor:

Drill Model:

Relative Level:

Coordinates:

Bores NT

BurnsideOperations

Bore Size:

Total Depth:

Casing Size:

42213762

Permit No:

Page 60: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Penetration

Water Depth (m)

USC DESCRIPTION OF STRATA

Legend

Classification

Moisture

WELL CONSTRUCTION DETAILS

Depth (m)

GRAYWACKE: silt with minor gravels,gravels up to 25mm in diameter, minorpale/grey silt, very fine silt (powder like)

Casing

SILTSTONE: silt with minor gravels,gravels up to 6mm in diameter, grey/pinkcolour

M RH

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Method

S

50mm diametersolid PVCcasing.

SILTS

GRYW

D

D

Standing waterlevel at 14.775

m TOC at18/1/07

Gravel - 5mmdiameter

rounded gravelpack

Hammer

Sheet 2 of 6

Airlift (l/sec)

10

11

12

13

14

15

16

17

18

19

20

21

URS Australia

Level 3, 93 Mitchell Street, Darwin

ProjectNo.:

08 8980 2900

08 8941 3920

MONITORING WELL PLMB2

ProjectReference:

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

42213762 Burnside Operations

Page 61: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Legend

dark grey

SILTSTONE: sand with silt and minorgravels, very fine to medium grain sand,grey colour

water cut at 25m bgl

gravels up to 5mm in diameter, very fineto coarse grain sand

increase in gravel component, up to20mm in diameter

gravels up to 5mm in diameter

gravels up to 10mm in diameter, minoroxidation

gravels up to 15mm in diameter, increasein oxidation

gravels up to 8mm in diameter, evidenceof oxidation, very fine to medium grainsand

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

USC DESCRIPTION OF STRATA

Classification

Moisture

WELL CONSTRUCTION DETAILS

Depth (m)

SCasing

Penetration

M

3l/sec

D/MGRYW

SILTS

30m bgl: 300 uS/cm 7.5 pH

Gravel - 5mmdiameter

rounded gravelpack

50mm diametersolid PVCcasing.

W

W

W

W

W

W

W

R

Hammer

MONITORING WELL PLMB2

ProjectNo.:

ProjectReference:

URS Australia

Level 3, 93 Mitchell Street, Darwin

08 8980 2900

Sheet 3 of 6

08 8941 3920

22

23

24

25

26

27

28

29

30

31

32

33

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Method

Airlift (l/sec)

Water Depth (m)

H

42213762 Burnside Operations

Page 62: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

S

gravels up to 5mm in diameter, evidenceof oxidation

decrease in gravel component, evidence ofoxidation

increase in gravel component, evidence ofoxidation

USC DESCRIPTION OF STRATA

Legend

Classification

Moisture

Method

Depth (m)

Gravel - 5mmdiameter

rounded gravelpack

Casing

Penetration

M R

3l/sec

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

WELL CONSTRUCTION DETAILS

W

3l/sec

SILTS

36m bgl: 279 uS/cm 7.0 pH

42m bgl: 300 uS/sec 6.9 pH

Hammer

very fine to medium grain sand

Wincrease in gravel component, up to10mm in diameter, evidence of oxidation

W

W

W

Sample

Parameters

50mm diametersolid PVCcasing.

Sheet 4 of 6

Airlift (l/sec)

H

34

35

36

37

38

39

40

41

42

43

44

45

URS Australia

Level 3, 93 Mitchell Street, Darwin

ProjectNo.:

08 8980 2900 ProjectReference:08 8941 3920

MONITORING WELL PLMB2

Water Depth (m)

42213762 Burnside Operations

Page 63: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Legend

R

Gravel - 5mmdiameter

rounded gravelpack

GRAYWACKE: sand with silt and gravel,very fine coarse grain sand, gravels up to5mm

increase in gravel component, up to15mm, evidence of oxidation

decrease in gravel component, up to20mm in diameter

gravels up to 6mm in diameter

increase in gravel component, evidence ofoxidation

decreased gravel component

foam injected at 56m bgl

increase in gravel component

USC DESCRIPTION OF STRATA

Classification

Moisture

WELL CONSTRUCTION DETAILS

Depth (m)

SCasing

3l/sec

M

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

Hammer

Foam

SILTS

GRYW

56m bgl

50mm diametersolid PVCcasing.

W

W

W

W

W

W

W

50m bgl: 270 uS/cm 6.8 pH

46

47

48

49

50

51

52

53

54

55

56

57

08 8941 3920

H

Penetration

ProjectNo.:

ProjectReference:

MONITORING WELL PLMB2

URS Australia

Level 3, 93 Mitchell Street, Darwin

08 8980 2900

Sheet 5 of 6

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

Sample

Parameters

Method

Airlift (l/sec)

Water Depth (m)

42213762 Burnside Operations

Page 64: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

SMethod

decreased gravel component, minoroxidation

End of Hole at 66m bgl

USC DESCRIPTION OF STRATA

Legend

Classification

Moisture

Gravel - 5mmdiameter

rounded gravelpack

Depth (m)

Casing

Penetration

M R

Foam

Type, plasticity / particle size, colour,secondary / minor components (e.g.,"trace"), moisture content, consistency /density, and additional observations

ENVIRO_WELL_ADELAIDE WCC_AUS.GDT J:\JOBS\42213762\BORE LOGS\GBS BORE LOGS.GPJ 23/2/07

WELL CONSTRUCTION DETAILS

GRYW

decreased gravel component

Sample

Parameters

62m bgl

Hammer

50mm diameterslotted PVCcasing

End Cap

W

W

08 8941 3920

MONITORING WELL PLMB2

H

ProjectReference:

58

59

60

61

62

63

64

65

66

67

68

69

08 8980 2900

Sheet 6 of 6

URS Australia

Level 3, 93 Mitchell Street, Darwin

Water Depth (m)

Airlift (l/sec)

ProjectNo.: 42213762 Burnside Operations

Page 65: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to C

OPRIG

HT. It remains the property of URS Australia

Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 1.srf

Regional Locality Plan

CMAC RIJV 19/1/20071

Page 66: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to C

OPRIG

HT. It remains the property of URS Australia

Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 2.srf

Sites and Surrounds

CMAC RIJV 19/1/20072

Page 67: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to COPRIG

HT. It remains the property of URS Australia Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 3.srf

Bore Locations - North Point

CMAC RIJV 19/1/20073

NPPB1

NPMB2

NPMB1

9800 9900 10000 10100 10200

Mine Easting (m)

9100

9200

9300

9400

9500

9600

9700

9800

9900

10000

10100

Mine Northing (m)

Topographyic Contour (m RL)

Page 68: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to COPRIG

HT. It remains the property of URS Australia Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 4.srf

Bore Locations - Princess Louise

CMAC RIJV 19/1/20074

9450 9500 9550 9600 9650 9700 9750 9800 9850 9900 9950 10000

Mine Easting (m)

6700

6750

6800

6850

6900

6950

7000

7050

7100

7150

7200

Mine Northing (m)

PLPB1

PLMB1

PLMB2

Topographyic Contour (m RL)

Page 69: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to C

OPRIG

HT. It remains the property of URS Australia

Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 5.srf

Production Bore NPPB1Step-Rate Test

CMAC RIJV 31/1/20075

110

100

1,000

10,000

0 1 2 3 4 5

Drawdown (m)

Time (min)

Step 1 - 1,120 kL/day

Step 2 - 1,300 kL/day

Step 3 - 1,470 kL/day

Step 4 - 1,640 kL/day

Page 70: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to C

OPRIG

HT. It remains the property of URS Australia

Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 6.srf

Production Bore PLPB1Step-Rate Test

CMAC RIJV 31/1/20076

110

100

1,000

10,000

0 1 2 3 4 5 6 7 8 9

10

Drawdown (m)

Time (min)

Step 1 - 260 kL/day

Step 2 - 360 kL/day

Step 3 - 430 kL/day

Step 4 - 510 kL/day

Page 71: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to C

OPRIG

HT. It remains the property of URS Australia

Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 7.srf

Production Bore NPPB1Constant-Rate Test

CMAC RIJV 31/1/20077

110

100

1,000

10,000

0 1 2 3 4 5 6 7 8 9

10

Drawdown (m)

Time (min)

NPPB1 - Pumping R

ate 1,640 kL/day

S.W

.L 14.18 m

btoc

NPMB1

Distance - 243 m

S.W

.L - 14.7 m

NPMB2

Distance - 332 m

S.W

.L - 24.26 m

btoc

Page 72: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to C

OPRIG

HT. It remains the property of URS Australia

Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 8.srf

Production Bore PLPB1Constant-Rate Test

CMAC RIJV 31/1/20078

110

100

1,000

10,000

0 2 4 6 8

10

12

14

16

18

20

Drawdown (m)

Time (min)

PLPB1 - Pumping R

ate 490 kL/day

S.W

.L - 26.60 m

btoc

PLMB1

Distance - 70 m

S.W

.L - 22.37 m

btoc

PLMB2

Distance - 92 m

S.W

.L - 16.10 m

btoc

Page 73: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to C

OPRIG

HT. It remains the property of URS Australia

Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 9.srf

Regional Geology

CMAC RIJV 19/1/20079

Page 74: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to COPRIG

HT. It remains the property of URS Australia Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 10.srf

Model Grid - North Point

CMAC RIJV 16/2/200710

9000 9200 9400 9600 9800 10000 10200 10400 10600 10800 11000

Mine Easting (m)

8600

8800

9000

9200

9400

9600

9800

10000

10200

10400

Mine Northing (m)

Page 75: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to COPRIG

HT. It remains the property of URS Australia Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 11.srf

Model Grid - Princess Louise

CMAC RIJV 16/2/200711

7000 7500 8000 8500 9000 9500 10000 10500 11000 11500 12000 12500

Mine Easting (m)

4000

4500

5000

5500

6000

6500

7000

7500

8000

8500

9000

9500

10000

Mine N

orthing (m)

Page 76: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to COPRIG

HT. It remains the property of URS Australia Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 12.srf

Distribution of HydraulicParameters - North Point

CMAC RIJV 16/2/200712

9600 9700 9800 9900 10000 10100 10200 10300 10400

Mine Easting (m)

8500

8600

8700

8800

8900

9000

Elevation m

RL

0

-100

-200

-300

-400

-500

Weathered Bedrock

Weathered Shear

Fresh Shear

Fresh Bedrock

9600 9700 9800 9900 10000 10100 10200 10300 10400

Mine Easting (m)

9100

9200

9300

9400

9500

9600

9700

9800

9900

10000

Mine Northing (m)

Page 77: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to COPRIG

HT. It remains the property of URS Australia Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 13.srf

Distribution of HydraulicParameters - Princess Louise

CMAC RIJV 16/2/200713

Weathered Bedrock

Weathered Shear

Fresh Shear

Fresh Bedrock

9 8 0 0

9500 9550 9600 9650 9700 9750 9800 9850 9900

Mine Easting (m)

-500

0

500

Elevation m

RL

-100

100

9500 9600 9700 9800 9900

Mine Easting (m)

6600

6700

6800

6900

7000

7100

7200

7300

Mine Northing (m)

Page 78: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to C

OPRIG

HT. It remains the property of URS Australia

Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 14.srf

Transient Calibration - North Point

CMAC RIJV 16/2/200714

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

5

0 0.5 1 1.5 2 2.5

Time (days)

Drawdown (m)

NPMB1

R100-NPMB1/A

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

5

0 0.5 1 1.5 2 2.5

Time (days)

Drawdown (m)

NPMB2

R100-NPMB2/A

Page 79: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to C

OPRIG

HT. It remains the property of URS Australia

Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 15.srf

Transient Calibration - Princess Louise

CMAC RIJV 16/2/200715

-5

-4.5

-4

-3.5

-3

-2.5

-2

-1.5

-1

-0.5

0

0.0 0.5 1.0 1.5 2.0 2.5

Time (d)

Drawdown (m)

PLMW01

R35 - PLM B1/A

-5

-4.5

-4

-3.5

-3

-2.5

-2

-1.5

-1

-0.5

0

0.0 0.5 1.0 1.5 2.0 2.5

Time (d)

Drawdown (m)

PLMW02

R35 - PLMB2/A

PLMB1

PLMB2

Page 80: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to C

OPRIG

HT. It remains the property of URS Australia

Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 16.srf

Estimated Groundwater PumpageNorth Point & Princess Louise

CMAC RIJV 16/2/200716

North Point

0

500

1000

1500

2000

2500

0 20 40 60 80 100 120 140

Time (days)

Dewatering Rate (kL/day)

Princess Louise

0

50

100

150

200

250

300

350

400

450

0 20 40 60 80 100 120 140

Time (days)

Dewatering Rate (kL/day)

Page 81: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to COPRIG

HT. It remains the property of URS Australia Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 17.srf

Predicted Drawdown - North Point120 Days Pumpage at 2,073 kL/day

CMAC RIJV 16/2/200717

9000 9200 9400 9600 9800 10000 10200 10400 10600 10800 11000

Mine Easting (m)

8600

8800

9000

9200

9400

9600

9800

10000

10200

10400

Mine Northing (m)

Simulated Production Bore

Simulated Drawdown

Page 82: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to COPRIG

HT. It remains the property of URS Australia Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 18.srf

Predicted Drawdown - Princess Louise120 Days Pumpage at 425 kL/day

CMAC RIJV 16/2/200718

Simulated Production Bore

Simulated Drawdown

7500 8000 8500 9000 9500 10000 10500 11000 11500

Mine Easting (m)

4500

5000

5500

6000

6500

7000

7500

8000

8500

9000

9500

Mine Northing (m)

Page 83: Appendix E Groundwater Report...Figure 5 Production Bore NPPB1 – Step-Rate Test Figure 6 Production Bore PLPB1 – Step-Rate Test Figure 7 Production Bore NPPB1 – Constant-Rate

Client: Project: Title:

Figure:Drawn: Approved: Date:

Job No: File No: A4

Rev A

Source:

This drawing is subject to C

OPRIG

HT. It remains the property of URS Australia

Pty Ltd.

Burnside Operations Pty Ltd Hydrogeological Assessments of the North Pointand Princess Louise Deposits for Mine Development

42213762 Figure 19.srf

Predicted Extent of Drawdown

CMAC RIJV 16/2/200719