Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Appendix C
MUSIC Modelling
East Leppington - Water Cycle Management Report
Prepared for Department of Planning & Infrastructure
9 May 2013 Cardno (NSW/ACT) Pty Ltd Page C.1
C.1 Aims
The aims of the catchment based water quality modelling were to assess the:
� Impacts of the proposed development on stormwater quality; and
� Estimate the sizes of the stormwater quality improvement measures.
The Model for Urban Stormwater Improvement Conceptualisation (MUSIC) version 5 was used for water quality assessments.
C.2 MUSIC Model Parameters The following model parameters were adopted for assessment purposes.
Rainfall Data Daily rainfall data was purchased from the Bureau of Meteorology for the nearest daily rainfall station 67015 Bringelly. The daily rainfall data between 01/01/1998 and 01/01/2008 (10 calendar years) was adopted.
Table C.1 Rainfall Details
Station No. 67015
Location Bringelly at Marylands
Data period available 01/01/1867-31/12/2008
Data period used 01/01/1998 and 01/01/2008
Data type Daily
No of years 10
Average Annual (mm) 596.9
Mean Annual Rainfall (mm) 50th%ile 640.7
Wet Year Rainfall (mm) 90th%ile 929.86
Dry Year Rainfall (mm) 10th%ile 494.88
Potential Evapo-Transpiration (PET) Data
The monthly PET data that was adopted in this study are listed in Table C.2 and represent typical PET for
areas of Western Sydney.
Table C.2 Average Daily Potential Evapo-Transpiration by Month (mm)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
5.6 5.0 4.0 3.1 2.1 1.7 1.8 2.6 3.7 4.6 5.2 6.0
East Leppington - Water Cycle Management Report
Prepared for Department of Planning & Infrastructure
9 May 2013 Cardno (NSW/ACT) Pty Ltd Page C.2
Figure C.1 Comparison of Monthly Average Rainfall and Potential Evapo-Transpiration
A comparison of average monthly rainfall recorded and average monthly PET is presented in the following
Figure. C.1.
Rainfall and Runoff Parameters
The following rainfall and runoff parameters have been used:
Parameter Urban
Impervious Area Properties
Rainfall Threshold (mm/day) 1
Pervious Area Properties
Soil Storage Capacity (mm) 170
Soil Initial Storage (% of Capacity) 30
Field Capacity (mm) 70
Infiltration Capacity coefficient - a 200
Infiltration Capacity exponent - b 1
Groundwater Properties
Initial Depth (mm) 10
Daily Recharge Rate (%) 25
Daily Baseflow Rate (%) 5
Daily Deep Seepage Rate (%) 0
East Leppington - Water Cycle Management Report
Prepared for Department of Planning & Infrastructure
9 May 2013 Cardno (NSW/ACT) Pty Ltd Page C.3
Fraction Impervious
For the purpose of analysis, an overall average fraction impervious was determined based on the proposed
development layout and fraction impervious per land use as outlined in Campbelltown Council’s DCP. The
spatial distribution of the landuse categories analysed when estimating the average fraction imperviousness
are plotted in Figure C.2.
The adopted fraction imperviousness for each landuse category, total area of each landuse and the resulting
overall average imperviousness is summarised in Table C.3. The resulting overall fraction impervious
equated to 0.68. For the purpose of analysis, an overall average fraction impervious of 0.7 for the
development was adopted.
Figure C.2 Land Use Categories for Determination of Average Fraction Impervious
East Leppington - Water Cycle Management Report
Prepared for Department of Planning & Infrastructure
9 May 2013 Cardno (NSW/ACT) Pty Ltd Page C.4
Table C.3 Fraction Impervious by Land use Category
Land Use Fraction
Impervious
Total Area
(m2)
Impervious
Area (m2)
Low Density Residential 0.8 2,434,588 1,947,670
Medium Density Residential 0.9 461,858 415,672
Large Lots/Very Low Density 0.3 204,152 61,245
Open Space 0.1 659,364 65,936
Educational Uses 0.8 39,353 31,482
Community Uses 0.8 7,658 6,126
Local Centre 1.0 9,918 9,918
Neighbourhood Centre 1.0 15,657 15,657
Roads 1.0 156,091 156,091
Total 0.68 3,988,639 2,709,799
Pollutant Generation
MUSIC model default Event Mean Concentration (EMC) values for storm flows and base flows were used.
Treatment Measures – Bio-retention
Estimation of the size of bio-retention measures was undertaken to achieve best practice reduction targets for
Gross Pollutants (90%), Total Suspended Solids (85%), Total Phosphorous (65%) and Total Nitrogen (45%)
respectively. The adopted properties of bio-retention measures are as given in Table C.4.
Table C.4 Adopted Properties of Bio-retention Measures
Parameter Values
Low flow By-pass (m3/s) 0
High flow By-pass (m3/s) 100
Filter Depth (m) 0.65
Extended Detention Depth (m) 0.30
Filter median particle diameter (mm) 0.24
Hydraulic Conductivity (mm/hr) 120
Outlet Properties (m) 2yr ARI basin outlet width
East Leppington - Water Cycle Management Report
Prepared for Department of Planning & Infrastructure
9 May 2013 Cardno (NSW/ACT) Pty Ltd Page C.5
C.2 MUSIC Model Results
MUSIC Model
The layout of the MUSIC model is given in Figure C.3.
Overall Results
It was found that a bio-retention filter area of approximately 0.5% of total catchment area is sufficient to meet
the best practice management targets for stormwater quality improvement. The overall MUSIC model results
are summarised in Table C.5.
Table C.5 Overall MUSIC Model Results
Parameter Source Load Residual Load Reduction (%)
Flow (ML/yr) 1,570 1,550 1.6
Total Suspended Solids (kg/yr) 295,000 22,700 92.3
Total Phosphorus (kg/yr) 625 218 65.1
Total Nitrogen (kg/yr) 4,400 1,800 59.1
Gross Pollutants (kg/yr) 51,700 0.00 100.0
Basin Sizing – Bioretention
Bioretention basins are located in the floodway of the ILP as shown in Figure C.4. The size of the basins was
calculated based on the filter area requirements plus allowances for earthworks, drainage and ancillary works.
As shown in Table C.6, on average the area of basins in the ILP is 3.3 times the filter area estimated by
MUSIC modelling.
A concept layout of a bio-retention basin is given in Figure C.5.
East Leppington - Water Cycle Management Report
Prepared for Department of Planning & Infrastructure
9 May 2013 Cardno (NSW/ACT) Pty Ltd Page C.6
Table C.6 Estimated Filter Areas and Basin Areas
ILP Basin ID Filter Area (m2)
A
ILP Area (m2) B
B / A
BR1 316 2830 9.0
BR2 / BR3 1060 6770 6.4
BR4 133 5860 44.1
BR5 286 3610 12.6
BR6 520 1840 3.5
BR7 171 1810 10.6
BR8 447 3470 7.8
BR9 943 2035 2.2
BR10 901 3240 3.6
BR11 438 3000 6.8
BR12 653 3550 5.4
BR13 525 1090 2.1
CLB1 441 1770 4.0
CLB2 142 4180 29.4
CLB3 365 1650 4.5
CLB4 344 2090 6.1
CLB5 293 2610 8.9
CLB6 1038 1870 1.8
CLB7 978 1700 1.7
CLB8 269 2060 7.7
Total 10,263 57,035 5.6
East Leppington - Water Cycle Management Report
Prepared for Department of Planning & Infrastructure
9 May 2013 Cardno (NSW/ACT) Pty Ltd Page C.7
Figure C.3 MUSIC Model Layout
East Leppington - Water Cycle Management Report
Prepared for Department of Planning & Infrastructure
9 May 2013 Cardno (NSW/ACT) Pty Ltd Page C.8
Figure C.4: Sub-catchment and Bio-retention Basin Layout
East Leppington - Water Cycle Management Report
Prepared for Department of Planning & Infrastructure
9 May 2013 Cardno (NSW/ACT) Pty Ltd Page C.9
Figure C.5 Concept Layout of Bio-retention Basin
11 April 2013 Cardno (NSW/ACT) Pty Ltd Page 3
Appendix D
WQM Implementation Plan