62
APPENDIX B QUALITY ASSURANCE PROJECT PLAN AR305067

APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

APPENDIX B

QUALITY ASSURANCE PROJECT PLAN

AR305067

Page 2: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

QUALITY ASSURANCE PROJECT PLANHALBY CHEMICAL SUPERFUND SITE

WILMINGTON, NEW CASTLE COUNTY, DELAWAREEPA DOCKET NO III-95-55-DC

Prepared For:

Witco CorporationOne American Lane

Greenwich, Connecticut 06831

Prepared By:

Langan Engineering and Environmental Services, Inc.River Drive Center 1

Elmwood Park, New Jersey 07407

8 August 19951 September 1995 Revised20 November 1995 Revised

2061601

Robert McGrady DateEpvirotech Project Manager

Kevin Hoogerhyde DateEnvirotech QA Manager

William F. Mercuric DateLangan Project Director

Gerald J. Zambrella DateLangan QA Manager

Eric Newman DateEPA Remedial Project Manager

Jeffrey A. Dodd DateEPA QA Reviewer AR 30 5 068

Page 3: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPP T ofPage II of

Revision #220 November 1995

TABLE OF CONTENTS

Page No.

1.0 INTRODUCTION 11.1 Objective 11.2 Quality Assurance Methodology 2

2.0 PROJECT ORGANIZATION AND RESPONSIBILITIES 22.1 Witco Corporation 32.2 Primary Contractor - Langan Engineering and Environmental Services, Inc. 32.3 Oversight Contrator / Risk Assessment - ERM 52.4 Treatability Studies Contractor - Fahrenthold & Associates 52.5 Subcontractors 5

3.0 QUALITY ASSURANCE OBJECTIVES 6

4.0 SAMPLING PROCEDURES 94.1 Sampling Techniques 94.2 Sample Preservation 94.3 Field Log Books 10

5.0 SAMPLE CUSTODY 105.1 Sample Identification 115.2 Field Custody 115.3- Chain-of-Custody Record/Analysis Request Forms 125.4 Sample Packaging and Shipment Procedures 125.5 Sample Receipt Procedures 13

6.0 CALIBRATION PROCEDURES 136.1 Field Activities 136.2 Out of Calibration Equipment 146.3 Calibration and Maintenance Records 146.4 Laboratory Equipment 15

7.0 ANALYTICAL PROCEDURES 17

8.0 DATA REDUCTION, VALIDATION, AND REPORTING 188.1 Data Reduction . 188.2 Data Validation 188.3 Data Reporting 19

9.0 QUALITY CONTROL PROCEDURES 199.1 Laboratory Quality Control Procedures 229.2 Field Quality Control Sample Frequency 249.3 Laboratory Quality Assurance 24

[ AR305069

Page 4: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPP T of C %» *Page iii of if

Revision #220 November 1995

10.0 PERFORMANCE AND SYSTEM AUDITS 2610.1 System Audits • 2610.2 Laboratory Performance Audits 26

11.0 PREVENTATIVE MAINTENANCE PROCEDURES 27

12.0 PROCEDURES TO ASSESS DATA PRECISION, ACCURACY, AND COMPLETENESS 27

13.0 CORRECTIVE ACTION 27

14.0 QUALITY ASSURANCE REPORTS TO MANAGEMENT 28

15.0 REFERENCES 28

LIST OF TABLES

Table 1 Analytical Parameters and Methodology Summary - Water Main Investigation - FirstEvent

Table 2 Analytical Parameters and Methodology Summary - Water Main Investigation -Second Event

Table 3 Analytical Parameters and Methodology Summary - Drainage Ditch DelineationTable 4 Analytical Parameters and Methodology Summary - Sump Area DelineationTable 5 . Parameters, Sample Containers, Sample Volumes, Preservation and Holding TimesTable 6 Reporting LimitsTable 7 Quantitative QA/QC Limits

LIST OF FIGURES

Figure 1 Project Organization Chart

LIST OF ATTACHMENTS

Attachment A Revised Quality Assurance Manual — Envirotech Research, Inc.Attachment B ResumesAttachment C Standard Operating ProceduresAttachment D Equipment ManualsAttachment E Corrective Action Report

DISTRIBUTION LIST

Eric Newman — EPAJane Biggs-Sanger - DNRECRobert Root-CH2M HillRaj Vyas - Witco

AK305070

Page 5: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPP T of fl/Page iv of fffe

Revision #220 November 1995

James Nortz -- WitcoRichard Dulcey - ERMPaul Fahrenthold — FahrentholdJohn Phillips -PhillipsKevin Hoogerhyde — Envirotech

AR30507I

Page 6: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPP ACRONYMS ;%Page 1 of 1

Revision #220 November 1995

ACRONYMS

ASTM American Society for Testing Materials

CAR Corrective Action Report

CLP Contract Laboratory Program

COCR Chain-of-Custody Record

Dl Deionized

DNREC Department of Natural Resources and Environmental Control

FSP Field Sampling Plan

GC/MS Gas Chromatograph/Mass Spectrometer

MS Matrix Spike

MSD Matrix Spike Duplicate

NIST National Institute of Standards and Technology

O2-LEL Explosimeter - Oxygen Deficiency Meter

PID Photionization Detector

PSA Preliminary Site Assessment

QA Quality Assurance

QAPP Quality Assurance Project Plan

QC Quality Control

RAP Response Action Plan

ROD Record of Decision

RPD Relative Percent Difference

RPM Remedial Project Manager

SOPs Standard Operating Procedures

SOQ Statement of Qualifications

SOW Statement of Work

USEPA United States Environmental Protection Agency

AR305072

Page 7: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No.Page of 27-

Revision #220 November 1995

QUALITY ASSURANCE PROJECT PLANHALBY CHEMICAL SITE

WILMINGTON, NEW CASTLE COUNTY, DELAWARE

1.0 INTRODUCTION

This Quality Assurance Project Plan (QAPP) has been prepared to establish sampling andanalysis protocols and Quality Assurance (QA) procedures for data collection and data analysisactivities during implementation of the RAP at the Halby Chemical Site in Wilmington, NewCastle County, Delaware. These procedures are to be used in conjunction withimplementation of the Field Sampling Plan (FSP) at the site in response to an AdministrativeOrder for Removal Response Action, issued to Witco Corporation by the United StatesEnvironmental Protection Agency (USEPA).

This QAPP has been prepared in accordance with the USEPA guidance document, "InterimGuidelines and Specifications for Preparing Quality Assurance Project Plans" (USEPA, 1980)and USEPA NE1C Policies and Procedures Manual (August 1991). The procedures in thisQAPP will be implemented to ensure that the precision, accuracy, completeness,comparability, and representatives of the data generated during implementation of the FSP canbe documented. Project organization, policies, objectives, field investigation procedures, andlaboratory activities are presented in this QAPP.

The selected laboratory will have a documented quality assurance program that complies withUSEPA guidance document QAMS-005/80, is a participant in USEPA's Contract Laboratory

Program (CLP) and will adhere to procedures specified in the Statement of Work (SOW)OLM03.1, ILM03.0 (USEPA, 1994) and other methods specified in this QAPP.

1.1 Objective

The objective of this plan is to provide assurance that samples collected adhere toquality control policies stipulated in the Record of Decision (ROD) and USEPA RegionIll/Department of Natural Resources and Environmental Control (DNREC) QualityAssurance protocols.

AR305073

Page 8: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPPPage_2_of_27\

Revision #2 v20 November 1995

1.2 Quality Assurance Methodology

This plan presents an integrated system of management activities involving planning,

quality control, quality assessment, reporting, and quality improvement to ensure thatthe sampling and analysis activities meet the standards of quality, given in this plan,

with a stated level of confidence. The quality control component of quality assurancewill consist of the overall system of technical activities, presented herein, whosepurpose is to measure and control the sampling and analysis activities so that it meetsthe previously stated need. The overall aim is to provide quality that is satisfactory,adequate, dependable and economical. This approach addresses the essence ofquality assurance and quality control as defined in the USEPA Data Quality ObjectivesProcess for Superfund. ;

2.0 PROJECT ORGANIZATION AND RESPONSIBILITIES

A general description of the project has been presented in Section 1.0 of the Response ActionPlan (RAP). Summaries of project history and existing data are included in the Preliminary SiteAssessment (PSA). A brief summary of project history is included in subsection 1.2 of the RAP.The project overview and detailed work plan are provided in Section 2.0 of the RAP. Thespecific objectives of the soil sampling and intended uses of the data are discussed in Sections1.0 and 2.0 of the FSP. The air sampling objectives are summarized in the HASP. Acompletion schedule, showing anticipated start and completion dates, is given in Section 4.0of the RAP. The identification and responsibilities of key personnel and contractors associatedwith this project are provided in Section 5.0 of the RAP.

This section describes the organization and reporting relationships of key project personneland their responsibilities during any sampling activities and other ongoing activities. Anorganizational structure for sampling and ongoing activities is provided on Figure 1.

A.R 30507 k

Page 9: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPPPage _3_ of 27

Revision #220 November 1995

2.1 Witco Corporation

Project Coordinator

The Project Coordinator, Mr. Rajnikant Vyas has overall technical responsibility for theproject and reports project progress to the USEPA Remedial Project Manager.

2.2 Primary Contractor - Langan Engineering and Environmental Services, Inc.

Langan personnel may change based upon scheduling reauirements. Resumes areincluded in Attachment B.

Project Director

The Project Director, Mr. William Mercuric, is the senior management representativeof Langan for the project and has overall responsibility for completion of the project.The Project Director is responsible for the project scope, schedule, and resolution ofany technical QA issues. The Project Director is responsible for ensuring all samplingplans and procedures have been established, approved, and implemented.

Project OA Reviewer

The Project QA Reviewer, Mr. Bernard Langan will provide overall review of technicalissues and deliverables.

Project OA Manager

The Project QA Manager, Mr. Gerald Zambrella, is independent of direct siteresponsibilities, but provides the indoctrination and training to site personnel for theproper implementation of the sampling plans and procedures, and supervises allaspects of these programs.

AR305075

Page 10: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPPPage 4 of 27

Revision #220 November 1995

Project Manager———— < — — -

The Project Manager, Ms. Carole Sforza will provide assistance to the Project Directorto ensure the project scope, schedule, and budgets are met.

Project Health and Safety Officer

The Project Health and Safety Officer, Mr. Robert Koto, is also independent of directsite responsibilities, but is responsible for ensuring the development andimplementation of an effective safety program for the sampling activities.

Field Operations Leader

The Field Operations Leader, Mr. Edward Zofchak, is the senior on-site representativeand is responsible for managing all site activities including supervising and schedulingof sampling activities.

Field OA Officer

The Field QA Officer, Mr. Charles McCusker, reports to the Project QA Manager andinterfaces with the Field Operations Leader. The Field QA Officer is responsible forimplementing the sampling plans and procedures and ensures the work is properlyconducted.

Site Health and Safety Officer

The Site Health and Safety Officer, Mr. Charles McCusker, reports to the ProjectHealth and Safety Officer and interfaces with the Field Operations Leader. The SiteHealth and Safety Officer is responsible for implementing the Health and Safety Planduring the sampling activities.

AR305076

Page 11: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPPPage 5 of 27

Revision #220 November 1995

2.3 Oversight Contrator / Risk Assessment - ERM ^r£><x>''<

Oversight Manager

The Oversight Manager, Mr. Richard Dulcey, reports to Witco Corporation to ensurethat the Primary Contractor is performing consistent with technical protocols,budgetary requirements, and other contract requirements. The Oversight Manager isalso responsible for the development of the Site Screening Levels for site contaminants.

2.4 Treatability Studies Contractor - Fahrenthold & Associates

Treatability Manager

The Treatability Manager, Mr. Paul Fahrenthold, reports to Witco Corporation and isresponsible for the development of proposed treatability studies.

2.5 Subcontractors

Subcontractors selected may change during future activities. Bids for work will berequested for different tasks.

Analytical Laboratory

The analytical laboratory, Envirotech Research, Inc. was selected by Witco, andaccepted by USEPA, to perform laboratory services.

Fence/Subsurface Investigation

The subcontractor selected by Witco, and accepted by USEPA, to perform subsurfaceinvestigation work (test pits) and fence installation is Republic Environmental Systems.

A.R305077

Page 12: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

,Section No. QAPP., %Page 6 of 27%/

Revision #220 November 1995

Corrosion Studies

The subcontractor selected by Witco to conduct a corrosion evaluation of the areanear the water main is RAM Services. USEPA has not yet contacted Witco with theirdetermination of acceptability of this subcontractor.

Data Validation

The subcontractor for data validation has not yet been identified, by Witco, as bidrequests are in progress.

3.0 QUALITY ASSURANCE OBJECTIVES

The purpose of this section is to define goals for the level of QA effort and data requirementsin terms of precision, accuracy, representativeness, completeness, and comparability. The

overall QA objective is to adhere to quality assurance protocols and to produce useable databy ensuring development and implementation of procedures for field sampling, chain ofcustody records, laboratory analysis, and reporting that will provide legally defensible data ofknown quality.

The specific data objectives for each investigation are summarized in Section 2.0 of the FSP.Data will be compared to the Site Screening Levels (SSLs).

As summarized from the FSP, the sampling objectives are to supplement the existing data andto identify and evaluate remedial alternatives for the site. Witco believes that sufficient dataexists to fully delineate the site contaminants at present; however, the proposed fieldinvestigation is needed to further define the "clean" areas, assist in the development of actionlevels, and evaluate the condition of the water main. Witco may propose additional fieldinvestigations to further identify the vertical and horizontal extent of contamination. Additionalfield investigations may consist of test borings.

AR305078

Page 13: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPP J'%,Page _Z_ of 27 , V

Revision #220 November 1995

The data collected as part of this field investigation will be comparable to and compatible withthe previous data collection activities, therefore, providing a 'mechanism for meeting thespecific sampling objectives of this investigation. The data collected also serves as a basis forevaluating remedial alternatives.

Any laboratory selected to perform analysis of samples must have a demonstrated ability toaccurately perform the USEPA CLP, Series 500/600 and/or SW-846 series methods as requiredfor sample analysis. The laboratory will provide documentation of recent performanceevaluation sample analysis, QA manuals, and Standard Operating Procedures (SOPs) for thesample analysis required for the review and approval of the Witco Corporation and theUSEPA/DNREC.

• Precision - Measures the mutual agreement among individual measurements of thesame property, usually under prescribed similar conditions. Precision is expressedquantitatively as the measure of variability of a group of measurements compared totheir average value. Precision is usually expressed in terms of the standard deviations,relative standard deviations, range, and relative range, or relative percent difference(RPD). Various measures of precision exist depending upon the "prescribed similarconditions". Total measurement precision will be assessed using field duplicates. Theprecision of field measurements will be assessed through replicate measurements, andacceptable results will vary by less than 30 percent (RPD). Analytical precision willbe addressed using laboratory replicates.

• Accuracy - References to the degree of agreement of a measurement, X, with anaccepted reference or true value, T, usually expressed as the difference between thetwo values, X-T, or the difference as a percentage of the reference or true value, 100(X-T)/T, and sometimes expressed as a ratio, X/T. Accuracy is a measure of the bias ina measurement system. Sources of error that introduce bias are the sampling process,

field contamination, preservation, handling, sample matrix, sample preparation,analysis techniques, and data reduction. Accuracy will be assessed using surrogatespikes and matrix spikes and is generally expressed as percent recovery. Goals foraccuracy are those published by the USEPA for the methods being used.

AR305079

Page 14: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No.Page 8 of 27-

*•• * Revision #220 November 1995

Completeness - Measures the amount of valid data obtained from a measurementsystem compared to the amount that was expected to be obtained under normalconditions. Completeness will be assured by collecting extra sample volumes so thatif breakage occurs during shipment, sufficient sample will remain to complete analysesif it is still within the method-specified holding times. For manual sampling andanalytical methods, completeness is based upon the number of valid samples collected

over a specified period. The equation used to recalculate completeness is:

Completeness = NA(/Nptx100%WhereNA, = the number of actual valid samples over a given time period, t.

Np, = the number of possible samples over a given time period, t.The completeness goal for the sample collection and analysis activities is 100%.

Representativeness - Expresses the degree to which data accurately and preciselyrepresents the characteristics of a population, parameter variations at a sampling point,a -process condition, or an environmental condition. To assure samplerepresentativeness, all sample collection will be performed in accordance with USEPA-recommended procedures for collection as set forth in the following sections of thisQAPP. The representativeness of the data will be assessed in three areas as follows:(1) the number of locations, matrices, and samples sufficient to accurately depict siteconditions; (2) the sampling procedures that must be designed so that individualsamples accurately represent the chemistry of the matrix from which they werecollected; and (3) the appropriateness of the analytical method used to the type of

sample obtained. The goal of the sampling activities is 100% representatives.

Comparability- Expresses the confidence with which one data set can be comparedto another. In order to establish a degree of comparability such that observations andconclusions can be directly compared with all historical data, standardized methodsfor holding times, preservations, shipping, and analysis will be used and certifiedcalibration standards.

AB305080

Page 15: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPP, ;Page_9_of_27_'VRevision #2

20 November 1995

4.0 SAMPLING PROCEDURES

The specific methods and techniques to be followed during field activities are presented in theFSP and in Tables 1 through 5 of the QAPP.

4.1 Sampling Techniques

Procedures for sample collection, reagents for preservation, sample holding times, andtime considerations for shipment to the laboratory are included in the FSP. Samplingprocedures are drawn from the USEPA documents, "A Compendium of SuperfundField Operations Methods: Volume 1 and Volume 2". Standard operating procedures(SOPs) will be in accordance with the above-referenced USEPA document, ASTMSOPs, and Conrail SOPs. The ASTM and Conrail SOPs are included in Attachment Cof the QAPP.

4.2 Sample Preservation

The analytical laboratory will provide all sample containers, preservatives, trip blanks,and sample shuttles for compliance with the USEPA test methods. Sample containers

• made of glass or plastic and of varying sizes will be supplied by the laboratory withrequired preservatives already added in compliance with the requirements of theUSEPA CLP SOW or other methods as appropriate. Requirements are summarized inTable 5.

Samples will be shipped daily following collection, by overnight mail or an equallyefficient means of transport to the contract laboratory for receipt the next day followingsample collection.

All sample material, sample containers, and laboratory personal protective equipmentwill be disposed by the contract laboratory in a manner which meets all local, state,and federal requirements and in accordance with an approved contract laboratory QAPlan.

AR30508I

Page 16: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPPPage 10 of '27

Revision #220 November 1995

The integrity of the samples will be maintained throughout the sampling process;

collection, packaging, shipment, and analysis. All samples will be preservedimmediately after collection by sealing the containers and maintaining them at a low

temperature with the utilization of ice or an ice substitute and sample shuttles. Thispreservation procedure is described in the FSP.

4.3 Field Log Books

Field log books will be maintained in accordance with the FSP. Records of samplescollected, data measurements taken, and observations of events and conditions whichcould affect data quality will be recorded in the log books. These log books areintended to provide sufficient data and observations to enable participants toreconstruct events that occurred during the data collection process, help qualify data,and refresh the memory of field personnel. The sample labeling procedure is describedin the FSP.

The original data collected in the field will be considered permanent records and willbe recorded in field notebooks, data forms, sample identification tags, chain of custodyrecords and other data forms in waterproof ink. All of these documents will beauthenticated by the signature and date of the originator.

Errors will be corrected by crossing a single line through the error and entering thecorrect information. Pages will not be removed from the log book. Corrections willbe initialed and dated by the person making the correction.

5.0 SAMPLE CUSTODY

The following custody documentation procedure will be used in conjunction with thelaboratory sample documentation procedure for all samples processed through the laboratory.Sample custody procedures are designed to provide documentation of the preparation,handling, storage, shipment, and receipt of samples.

A,R305082

Page 17: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPPPafle 11 of 27

Revision #220 November 1995

All outgoing samples will be accompanied by a Chain-of-Custody Record (COCR). This recordwill document sample collection, transfer between personnel and sample shipment to andreceipt by the laboratory. The personnel performing the sampling will be responsible forcompleting the COCR and for the care and custody of the samples collected until they aretransferred to the laboratory or a common carrier (e.g., Federal Express).

The COCR will be used as physical evidence of sample custody. Each time the sample istransferred to another custodian, the parties relinquishing and receiving the sample will signand date the record at the time of transfer.

The original signature copy of the COCR will be signed by the individual preparing theshipment. A copy of the COCR will be retained in the project file.

5.1 Sample Identification

Each sample will be assigned a unique number that will be recorded on the followingdocuments: the daily log, the label affixed to the sample container, and the Chain-of-Custody Record/Analysis Request form.

All sampling information will be recorded in the field log book, including identificationof blind duplicate samples.

Further details of sample identification are included in the FSP.

5.2 Field Custody

The sampling team will be responsible for the care and custody of the samples untilthey are delivered to the laboratory courier. The sample containers used for shipment

will be sealed on-site by the field sampling team using strapping tape and chain-of-custody seals. Sample bottles will be kept in the shipping containers except when theyare being filled. Sample shipping and handling procedures will be in compliance withthe requirements of the CLP SOW. The CLP considers sample holding times to begin

AR305083

Page 18: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPPPage 12 of 27 £

Revision20 November 1995

at the time the sample is received by the laboratory. The laboratory will comply With

sample holding times beginning at the time of sample collection. The original Chain-Of-Custody Record/Analysis Request will be dated and signed and included along withthe sample analysis request in the shipping container. The forms will be placed in aplastic bag and taped to the underside of the cooler lid.

5.3 Chain-of-Custody Record/Analysis Request Forms

The FSP and the QAPP describe the sampling and chain-of-custody paperwork to be

completed prior to, during, and after sampling activities. Chain-of-CustodyRecord/Analysis Request forms will be completed prior to sample shipment and will

identify the samples collected, the date and time of collection, the number of bottlesfilled, the requested analyses, and the sampling team members.

Quality Control (QC) samples will be clearly identified by the Matrix Spike (MS) andMatrix Spike Duplicate (MSD) notation. Field duplicate samples will be given routine,unique sample numbers which do not indicate their duplicate nature to the laboratory.

Chemical preservatives will be noted in the remarks section on the chain-of-custodyrecord.

5.4 Sample Packaging and Shipment Procedures

All samples will be promptly chilled with ice or an ice substitute to an approximatetemperature of 4° Celsius and packaged in an insulated cooler for shipment to thelaboratory. All Chain-of-Custody Record/Analysis Request forms will be placed in aplastic bag and taped to the inside cover of the cooler. Samples will be packed in amanner to avoid breakage of jars. The outside of the cooler will be sealed withcustody seals, and clear tape will be placed over the seals, completely encircling thecooler to allow the receiver to quickly ascertain whether any tampering has takenplace during transport. The shipping containers will be relinquished daily to a

AR30508U

Page 19: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No.Page_jl3_of_2Z_

Revision #220 November 1995

. • ilaboratory courier or common carrier (e.g., Federal Express) for immediatetransportation to the laboratory facility.

5.5 Sample Receipt Procedures

Upon accepting custody of the shipping containers, the laboratory will document thereceipt of the shipping containers by signing the Chain-Of-Custody Record/AnalysisRequest. The laboratory will Record the date and time of receipt, and assess thecondition of the shipping containers and sample bottles, and any other potentialdiscrepancies. The laboratory is also responsible for an internal sample trackingsystem. When all sample analyses and QA checks have been completed in thelaboratory, the unused portions of the samples, as well as the sample containers, willbe retained for 90 days or until otherwise directed by the Project Director. The projectand laboratory implementation of chain-of-custody controls may be audited.

Envirotech's laboratory custodian is Mr. Robert McGrady.

6.0 CALIBRATION PROCEDURES

Calibration and maintenance of all equipment used for field measurements and analysis ofsamples as well as laboratory analyses are discussed here.

6.1 Field Activities

All equipment and instruments used in the field sampling program will be maintainedand calibrated to operate within the manufacturer's specifications to ensure that therequired traceability, sensitivity and precision of the equipment/instrument ismaintained. Calibration frequency and standards will be recorded for each major pieceof equipment. Normally, manufacturers calibration instructions are followed forcalibration, calibration checks and maintenance. Procedures for control andmaintenance of measuring and test equipment include identification and control of theequipment, calibration records requirements, frequency of calibration and calibration

AR305085

Page 20: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPPPane 14 of 27

Revision #220 November 1995

checks, corrective actio'n required when equipment is found out of calibration, andspecific calibration and calibration check instructions. Reference calibration standardswill be used which are certified traceable to the National Institute of Standards andTechnology (NIST) or other acceptable standards. These may be laboratory standardswhich are prepared using laboratory procedures. All field equipment calibration andmaintenance activities will be documented in a bound notebook that is dedicated toa single instrument.

6.2 Out of Calibration Equipment

If equipment is found to be out of calibration, an evaluation will be performed to

determine the validity of the measurements made since the last calibration. When theout of calibration equipment creates a condition in which the validity of measurementsand tests are suspect, such tests or measurements should be repeated. If data has beenaffected and cannot be repeated, such data shall be annotated. The calibration logbook or calibration/maintenance file, as appropriate for the instrument in question shallbe annotated with the results of the out of calibration evaluation.

6.3 Calibration and Maintenance Records

Air monitoring instrumentation and field equipment to be used during field activitiesincludes a Photoionization Detector (PID), an Explosimeter - Oxygen Deficiency meter(O2-LEL), dra'ger tubes (carbon disulfide and hydrogen sulfide) and an Air Samplingpump. Instruments will be used alone or in conjunction with each other to gather datafor health and safety purposes as well as sampling monitoring. All instruments andother equipment will be calibrated using the appropriate standards at least once eachday during field activities, unless the manufacturers requirement and the methodologyfollowed are less stringent. Those units on rechargeable batteries will be kept on re-charge over night and power levels tested before being brought into the field.

AR305086

Page 21: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAp'pPage _15 of 27

Revision #220 November 1995

A calibration/maintenance file will be kept on all instrument and equipment used insampling or field analysis. It will include the following information for equipmentrequiring periodic calibration and for instruments requiring daily calibration:

• Name of the equipment• Equipment identification/serial number• Manufacturer• Calibration frequency (Daily, weekly, monthly, etc.)• Calibration certifications provided by the manufacturer or other outside agency

(periodic calibrations only)• Date of last calibration and date when next calibration is due• Manufacturers operating instructions• Manufacturers calibration and maintenance instructions• Local location for purchase of spare and replacement parts (when applicable)

A calibration log book(s) will be maintained and would include the followinginformation for each instrument calibrated daily and/or during use by field personnel:

• Name of the equipment• Equipment identification/serial number• Calibration frequency (daily, weekly, monthly, etc.)• Date and time of calibration/calibration check, results of the calibration,

standards used (reference lot no., batch no.), signature/initials of the personwho performed the calibration, and any maintenance performed.

Maintenance and calibration of the field equipment will be in accordance with themanufacturer's instructions. The field equipment manuals were added as AttachmentD to the QAPP.

AH305087

Page 22: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAP^Page 16 of 27 •

Revision #220 November 1995

6.4 Laboratory Equipment

Instruments and equipment used in the analytical laboratory will be controlled by aformal calibration program. The calibration program verifies that the instrumentationis capable of producing the proper type of data requested and will attain the requiredlevel of accuracy and precision. All instruments and equipment that measure a

property or quantity are subject to calibration. Calibration will be performed internallyusing primary or secondary prepared standards, and checked externally by analyzing

audit samples.

Initial calibration steps will consist of tuning and mass standardization of the MSsystem, to be performed per the manufacturer's instructions and the laboratory SOP.The entire Gas Chromatograph/Mass Spectrometer (GC/MS) system will then becalibrated by introducing standards into the system. The resulting mass spectra will becompared against the known quantities of introduced standards. Data processing forthe GC/MS calibration will be described in the laboratory SOP. Instrument parametersand operational procedures will be adjusted as necessary to meet the calibrationacceptance criteria described herein.

The requirements for the calibration of instruments or equipment are dependent on thetype of data to be collected and the expected range of instrument performance of thespecific analytical application. The guidelines herein will be used to develop aspecific calibration program that will form part of the SOP for the analytical laboratory.

Operational calibration routinely performed as part of instrument usage, such as thedevelopment of relative response factors and standard calibration curves for gaschromatographic analytical procedures, will be performed on a periodic basis. Therepetitive analysis to analysis precision of a chromatographic system can be monitoredby using a specific test mixture, such as a primary calibration standard. Calibrationperformed at specific intervals for equipment such as the use of column performancemixtures may be necessary for more diverse sample matrices.

M305088

Page 23: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPP >Page 17 of 27

Revision #220 November 1995

It is the responsibility of the analytical laboratory to calibrate all laboratory equipmentused for analyses as required by the USEPA or other administrative agencies and at thefrequencies mandated in the appropriate test methods. Compliance with theserequirements will be verified by QA audits as appropriate.

7.0 ANALYTICAL PROCEDURES

Samples and blanks collected during the field investigation will be analyzed using theanalytical methods from USEPA CLP SOW OLM03.0 and ILM03.0 or USEPA SW846. Thesemethods have been chosen to meet the various data quality objectives for the tasks discussedin the FSP. The CLP Methods were chosen because these contain a well defined set ofprocedures including the analytical and reporting requirments to achieve the highest level ofdata quality. Also, the USEPA informed Witco that it had no preference to the use of USEPAversus DNREC analytical methods. Methodologies are summarized in Tables 1, 2, 3, and 4.Sampling containers and preservation is summarized in Table 5. Quantitation limits aresummarized in Table 6.

The sources of reagents and standards used by Envirotech are listed below:

• Inorganic Ventures, Lakewood, NJ;• Aldrich Chemical, Milwaukee, Wl;• Fisher Scientific, Springfield, Nj;• Baxter Scientific, Edison, NJ;» Leeman Labs, Lowell, MA;• Environmental Resource Associates, Arvada, CO;• RICCA Chemical, Arlington, TX;

HACH, Loveland, CO;• Sigma Chemical, St. Louis, MO;• Chem Service, Westchester, PA;• AccuStandard, New Haven, CT;• Supelco, Bellefonte, PA;• MG Industries, Malvern, PA; and,

AR305089

Page 24: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Hi.Section No. QAPP

Revision #220 November 1995

Malinckrodt, Chesterfield, MO.

Screening of sample locations in the field, using portable instruments, will be performedaccording to the instrument manufacturer's instructions and/or recommendations for healthand safety purposes.

8.0 DATA REDUCTION, VALIDATION, AND REPORTING

Procedures in the QAPP describe the data reduction, validation, and reporting activities to beperformed on any sample analysis results. Original data from the field and laboratory datapackages will be entered into the project records.

8.1 Data Reduction

The data is received from the analytical laboratory on a computer disk, and summarytables are then generated by adding appropriate titles and deleting non-detectedvalues, to show only parameters with detected values. This is stored in a separatecomputer file so that the original disk is not changed.

The data reduction will consist of summarizing the raw field data into a format that willfacilitate interpretation, analysis, and evaluation. Thus, the data will be presented astables, illustrations, maps, or graphs, as deemed appropriate by the Project Director.

8.2 Data Validation

A partial validation of all laboratory analytical data will initially be performed. Thevalidation will include review of Lab Chronicles - to determine sample holding times,review of sample analysis request forms - to determine if the proper analysis wereperformed, and review of chain-of-custody records - to track sample shipments. A

second individual will then perform the full data validation according to Region Ill'sLaboratory Data Validation Functional Guidelines for Evaluating Organic Analyses andRegion Ill's Laboratory Data Validation Functional Guidelines for Evaluating Inorganic

AR305090

Page 25: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPP/2.'Page 19 of 27 %

Revision #220 November 1995

Analyses. The reviewer will also utilize the USEPA Contract Laboratory ProgramNational Functional Guidelines for Organic Data Review and for Inorganic DataReview (1994). The reviewer will certify that the data have been validated,discrepancies have been resolved if possible, and the appropriate qualifiers have beenprovided.

8.3 Data Reporting

Laboratory deliverables will consist of a complete hard copy data package inaccordance with the CLP SOW protocols and SW846.

For the report, the analytical data, including quality control samples, will be reportedin tabular form with sample identifications, matrix, parameters, and concentrations asapplicable. These tables will include any qualifiers placed on the data as a result ofvalidation procedures and/or by the laboratory. The project QA Manager is ultimatelyresponsible for the data generated in the field investigation.

Any laboratory results which are to be summarized will be entered into a spreadsheetformat. These spreadsheets will then be incorporated into the progress reports andremedial action workplans, as necessary.

All data and reports received from subcontractors, and all data and reports generatedby the Contractor will be kept maintained in the project file. The project file will beretained by the Contractor for a minimum of three years from the final completiondate.

9.0 QUALITY CONTROL PROCEDURES

QC procedures will be followed in the field as well as in the laboratory as specified in this

QAPP. The laboratory will be responsible for performing QC samples at the frequenciesspecified in the CLP SOW protocols and other methodologies used in support of the fieldinvestigation.

AR30509I

Page 26: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPPPage 20 of'S?-*

Revision #220 November 1995

QC samples will be used to:

Assess data quality in terms of precision and accuracy.Verify that sampling procedures such as chain of custody records, decontamination,

packaging and shipping are not introducing variables into the sampling chain whichcould render the validity of samples questionable. QC samples will be regularly

prepared in the field and laboratory so that all phases of the sampling process aremonitored.The types of QC samples which will be collected and their application are discussedbelow.

Duplicates

Duplicate samples will be collected by the sampling team and will be used as arelative measure of the precision of the sample collection process. These samples willbe collected at the same time, by the same personnel, using the same procedures, thesame equipment, and in the same types of containers as used for the original samples.Duplicates are matrix specific.

The Percent Ratio is figured for each duplicate pair as follows:

Relative Percent Difference (RPD) = XI-X2 x 100%x

Percent Ratio = X1-X2 x 100%x

Where:X, = Concentration of sample 1 of duplicateX2 = Concentration of sample 2 of duplicatex = Mean of samples 1 and 2

Calculate the standard deviation for the RPDs using the sum of the squares methodshown below:

AR305092

Page 27: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPPPage_21_of_274'vv.

Revision JM -, '•(20 November 1995

— _ i \' r »x \.*\£ I "

[ ... iWhere:S „ = Standard Deviationn = Number of RPDs used in calculationX = Individual Calculated RPD valuex = Mean of calculated RPDs

Blanks

Blanks will be used by the sampling team to assess if contaminants are beingintroduced into the sampling event at any given point. Three kinds of blanks will beused: trip blanks, field blanks, and Equipment Rinsate Blanks.

Aqueous Trip Blanks will be prepared by the laboratory for volatile organics samplingusing ASTM Type 2 water and would be included in the shipment of sample containerswhen they are shipped to the site. The purpose of Trip Blanks is to detect anyproblems caused by sample handling or container preparation. Trip blanks will beincluded in each cooler containing samples for volatile organic analyses.

Aqueous Field Blanks will be prepared by the sampling team using ASTM Type 2 waterby transferring the ASTM Type 2 water into laboratory prepared bottles. Field Blankswill be included in the sample shuttle with the collected samples.

Aqueous Equipment Rinsate Blanks will be prepared by the sampling team using ASTMType 2 water in the same manner as actual samples. Equipment Rinsate Blanks willbe included in the sample shuttle with the collected samples. The purpose ofEquipment Rinsate Blanks and Field Blanks is to assess the origination of contaminantsin'conjunction with the Trip Blanks should contaminants be identified duringlaboratory analysis.

AR305093

Page 28: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No.

Revision #220 November 1995

Splits

The offsite laboratory splits the samples into two parts and analyzes each separatelyusing the same methods and equipment. The purpose of split samples is similar to fieldduplicates and the results will be evaluated in the same manner.Spikes (MS/MSP)

Spikes are intended to evaluate data accuracy through verification of the laboratory'sability to recover compounds from actual samples. Spikes are prepared by thelaboratory. They are prepared by spiking field samples with known amounts of thecompounds of interest. The results are reported with the laboratory data and arecalculated as percent recovery.

Percent Recovery = (T-X)/A X 100%Where:T = Total concentration found in the spiked sampleX = Original concentration in sampleA = Actual spiked concentration added to the sample

The mean and standard deviation are figured and may be plotted on Quality ControlCharts. Limits are those provided by the USEPA for the test methods used and areincluded in Table 7. Spikes are performed at a frequency of one per twenty samples,or part thereof.

Other OC Samples

Laboratory calibration blanks and calibration standards are routinely used by thelaboratory during analysis as required by the methods being conducted. These arespecified in the analytical procedure (test method) and would be included in thecontract laboratory QA Plan submitted for approval.

Page 29: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPPPage_23_of_27_

Revision#220 November 1995

.- .9.1 Laboratory Quality Control Procedures

Internal QC checks for laboratory activities will be carried out as specified by theUSEPA CLP SOW. The QC checks will include, but not be limited to, the following:laboratory duplicates, method blanks, surrogate spikes, matrix spike/spike duplicates,laboratory control samples, calibration verification blanks and standards, internalstandards, and reference standards. The frequency of these QC checks will be asspecified by the SOW or the analytical method.

9.2 Field Quality Control Sample Frequency

The QC samples discussed will be introduced into the sampling program to qualify thedata and assure that the data quality objectives are met. Field duplicates, trip blanks,field blanks, equipment/rinsate blanks, matrix spikes, and matrix spikeduplicates/laboratory duplicates will be prepared and the analytical results obtainedfor these samples will be used to assess the quality of the field sampling and theanalytical effort. The type and frequency of field QC samples which will be collected

. is shown below.

Field OC Sample Frequency

•• Trip Blanks will be included at a frequency of one per cooler containingsamples for volatile organic analyses.

• Field Blanks will be prepared at a frequency of one per sample collection day.

• Equipment Rinsate Blanks will be prepared at a frequency of one per samplecollection day.

• Field duplicates will be collected at a frequency of one per 1 0 samples, or partthereof.

AR305095

Page 30: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPPPage 24 of 27

Revision #220 November 1995

• USEPA split samples will be performed at a frequency of one per 10 samples,or part thereof.

• Matrix Spike/Matrix Spike Duplicates/Laboratory Duplicates will be performedat a frequency of one per Sample Delivery Group (one per 20 samples).

9.3 Laboratory Quality Assurance

The analytical laboratory will incorporate the use of split samples, surrogates, reagentblanks, duplicate Matrix Spike analyses, and calibration standards as required anddetailed in the USEPA test methods specified in the FSP. Results of the quality controltests will be reported and evaluated as part of overall QA. The revised laboratoryquality assurance manual is provided in Attachment A.

10.0 PERFORMANCE AND SYSTEM AUDITS

10.1 System Audits

System audits will be conducted to ensure the integrity of field sampling and chain ofcustody record procedures and to assess adherence to established data management,QA, and documentation procedures. These audits will be performed at the discretionof the Project QA Manager and the Project Director. The system audit report will serveto notify the project management of audit results and to identify areas requiringcorrective action.

System audits will be conducted during sampling. The audit will be prepared by theField QA Officer and submitted to the Project QA Manager. Copies of all audit reportswill be placed in the project QA file and also distributed to the Project Director.Additional copies of all audit reports will be available to USEPA/DNREC upon requestto the Project Director.

Frequency of field audits will be at a minimum of once per week.

AR305096

Page 31: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPPPage 25 of '27

Revision #220 November 1995

10.2 Laboratory Performance Audits

Laboratory performance audits will be conducted periodically during the life of thesampling and data gathering activities. The purpose of laboratory performance auditsis to assess the overall accuracy of the sampling and laboratory analysis system.

During the sampling and analysis activities, field duplicate samples will be preparedand submitted "blind" to the analytical contract laboratory to independently assess theprecision of the analysis activities. Results will be evaluated and reported as part of afield investigation report.

QC audits are dictated by the frequency of the sample analyses as specified by themethod.

11.0 PREVENTATIVE MAINTENANCE PROCEDURES

Preventative maintenance will be performed on field equipment and recorded in the log bookfor each piece of equipment in accordance with manufacturers' specifications. Themaintenance of laboratory equipment will be performed by the laboratory according to theCLP SOW or in accordance with the method and/or manufacturers' specifications.

12.0 PROCEDURES TO ASSESS DATA PRECISION, ACCURACY, AND COMPLETENESS

Laboratory data generated during the field investigation will be assessed for their precision,accuracy, and completeness as described in this QAPP. The laboratory will be required tosubmit completed data packages in a form that is in accordance with the appropriate USEPAtest method. The procedures used to assess data accuracy, precision and completeness in thelaboratory are specified by the USEPA test method requirements.

AR305097

Page 32: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

Section No. QAPPPage 26 of 27 y

Revision #220 November 1995

13.0 CORRECTIVE ACTION

If unacceptable conditions are identified as a result of systems audits or are observed duringroutine processes during the field investigations (sampling and analysis), the QA Manager andthe Project Director will be responsible for documenting the condition or deficiency andinitiating corrective action procedures. Corrective actions may include, but not be limited to,

the following:

0 resampling and reanalyzing samples that fail to meet holding time criteria;0 resampling and reanalyzing due to broken sample jars;0 amending sampling procedures and analytical procedures; and0 retraining staff.

When a corrective action is initiated, a Corrective Action Report (CAR) will be implemented(Attachment E). Copies of the CAR will be distributed to the Project Director, Project QAManager, Corrective Action Initiator, project QA file, and USEPA/DNREC (if requested).

14.0 QUALITY ASSURANCE REPORTS TO MANAGEMENT

The QA Manager will review all aspects of the implementation of the QAPP on a regular basis.Reviews will be conducted at the completion of the field activity and will include anassessment of data quality and the results of system audits.

Any sample location for which the laboratory data has been rejected due to significant QAproblems will be resampled and reanalyzed.

Any changes to the QAPP will be approved by the QA Manager. Notification of and detailsregarding these changes will be given to the Project Director, Witco, USEPA Remedial ProjectManager (RPM), and DNREC.

The laboratory will conduct internal reviews and include QA reports with the analytical datadeliverable packages. A summary of the results of all audits will be reported to management

AR305098

Page 33: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

"*

Section No. QAPP

Revision #220 November 1995

as deemed appropriate by the QA Manager. A final summary report will be made by the QAManager and distributed to the Project Director and the project file.

The laboratory, Envirotech, maintains final evidence files for 5 years, as required by New jerseyLaboratory certification.

After project completion, the Contractor will maintain all data files in a locked QA room fora minimum of five years.

15.0 REFERENCES

U.S. Environmental Protection Agency, 1990. USEPA Region III Modifications to LaboratoryData Validation Functional Guidelines for Evaluating Inorganics Analyses, United StatesEnvironmental Protection Agency Region III, Revision.

U.S. Environmental Protection Agency, 1990. USEPA Region 111 Modifications to InorganicFunctional Guidelines.

U.S. Environmental Protection Agency, 1986. Test methods for Evaluating Solid Waste, SW-846 and Revisions.

U.S. Environmental Protection Agency, 1 994. Statement of Work for Organics Analysis (Multi-media, Multi-concentration) Document Number OLM03.1 and Revisions.

U.S. Environmental Protection Agency, 1994. Statement of Work for Inorganics Analysis(Multi-media, Multi-concentration) Document Number ILM03.0 and Revisions.

20616\rapaug\QAPP.f 2

AR305099

Page 34: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

CD;m(0

.-•--.. , .-_ T=-««(.--.-- .!=«• -——-T»- -_ _:_ -- _-».

"- "" -." fi g r- ii?., ••-•""•- .r •;•._ -v-

------- -^-v 4

~:-~'-.~-Jf&'-.--•"•a

s i ^ iZi ^ ' ^ ' ^ t ifS jjlfe. : i : ^^ ^ r - s( ^ it ' :: ^ iit -jSi g y' o"- ^

- -»«-»_;:._ gg •.._ . . . •- " • _ : • • »jft

"" -.iiS?*" "-SSS,.":;:,';-' --" "zv. C1- ;--- -'- =i.-.r-* .3saKgs--.=- --,«r, --..- ,-- _ -$.-=-> • v'- ? /-;- - ---;-T=- -'r - - "--, :~-3

"T"~u ~~3":~c i-.--.-- -^

AR305IOO

t"'-f

Page 35: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

TABLE 1

ANALYTICAL PARAMETERS AND METHODOLOGY SUMMARYWATER MAIN INVESTIGATION-FIRST EVENT«»>.

HALBY CHEMICAL SUPERFUND SITEWILMINGTON, DELAWARE

Number ofParameter Method Samples

Soil Sample Analysis - 7 day Turnaround Time

CLPVOC SOWOLM01.8 12 to 18CLP SVOC SOW OLM01.8 12 to 18CLPPest/PCB SOWOLM01.8 12 to 18CLP Metals SOW ILM03.0 12 to 18CLP Cyanide SOWILM03.0 12 to 18

Thiocyanate ASTM D4193-89 12 to 18ASTM D3987-85(Extraction method)

Weak acid dissociable CN SM 18th Ed. 4500-CN I. 12 to 18

Zero Headspace TCLP Extraction SW846 Method 1311 6Non-volatile TCLP Extraction SW846 Method 1311 6TCLP VOC SW846 Method 8240A 6TCLP SVOC SW846 Method 8270A 6TCLP Metals SW846 Method 6

' 6010A/7471ATCLP Pesticides SW846 Method 8080A 6TCLP Herbicides SW846 Method 81 SOB 6

Ignitability SW846 Method 1020B 12 to 18Corrosivity SW846 Method 9045C 12 to 18Cyanide Reactivity SW846 Section 7.3.3.2 12 to 18Sulfide Reactivity SW846 Section 7.3.4.2 12 to 18pH SW846 Method 9045C(1) 12 to 18

andSOWOLM01.8

Air Sample Analysis - 48 - 72 hour Turnaround TimeHexavalent Chromium NIOSH Method 7600 none collectedArsenic NIOSH Method 7300 note'2'Chromium NIOSH Method 7300 note(2)Lead NIOSH Method 7300 note(2>Cassette CartridgeFilter medium (Cellulose Acetate or PVC)

AR305IQI

Page 36: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

TABLE 1--continued '

ANALYTICAL PARAMETERS AND METHODOLOGY SUMMARY $£'WATER MAIN INVESTIGATION - FIRST EVENT'10' V

HALBY.CHEMICAL SUPERFUND SITEWILMINGTON, DELAWARE

Quality Control SamplesNumber of

Type Parameters Samples

Soil Sampling - 7 day Turnaround TimeMS'5' VOC, SVOC, Pest/PCB, Metals, Cyanide 1 to 2'3'

Thiocyanate, CNMSD/Laboratory Duplicate'5' VOC, SVOC, Pest/PCB, Metals, Cyanide 1 to 2(3>

Thiocyanate, CNField Duplicate'6' VOC, SVOC, Pest/PCB, Metals, Cyanide 2

Thiocyanate, CNUSEPA Split*7' VOC, SVOC, Pest/PCB, Metals, Cyanide none collected

Thiocyanate, CNTCLP, RCRA Characteristics

Equipment Rinsate Blank'9' VOC, SVOC, Pest/PCB, Metals, Cyanide note'4'Thiocyanate, CN

Field Blank19' VOC, SVOC, Pest/PCB, Metals, Cyanide note'4'• Thiocyanate, CN

Trip Blank'8"9' VOC note'4'

Air Sampling - 48-72 hour Turnaround TimeReagent Blank Arsenic, Chromium, Lead note""Matrix Blank Arsenic, Chromium, Lead note'111Blank Spike Arsenic, Chromium, Lead note'11'Matrix Blank Spike Arsenic, Chromium, Lead note"1'Matrix Blank Spike Duplicate Arsenic, Chromium, Lead note'11'Laboratory Control Sample Arsenic, Chromium, Lead note""

'" pH for aqueous samples analyzed by SW846 Method 9040B.(2> Two samples per day.(3) One MS/MSD sample will be collected per sample delivery group (20 samples).(4) One sample per day will be collected.(5) triple the nominal volume of a specific sample will be collected for MS and MSD/Laboratory Duplicates.(6) Double the nominal volume of a specific sample will be collected for Field Duplicates.(7) USEPA splits performed at EPA's discretion.(8) All samples for volatile organic analyses will be placed in one cooler per day. In the event that a second

cooler is needed for volatile organic analyses, then a second trip blank will be included.191 ASTM Type 2 water will be used for preparation of QC blank samples.(10) This investigation was completed on 29 August 1995. Wherever 12-18 samples were specified, 12,

samples were collected.1111 QC samples for air sampling are analyzed at a rate of 1 per 20 samples.MS - Matrix SpikeMSD - Matrix Spike DuplicateVOC-CLP Volatile Organic CompoundsSVOC-CLP Semi Volatile Organic CompoundsPest/PCB-CLP Pesticides and Polynuclear Chlorinated Biphenyls•Metals-CLP MetalsCyanide- CLP CyanideCN - Weak Acid Dissociable CN

AR305I02

Page 37: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

TABLE 2~" ~ &f$f

ANALYTICAL PARAMETERS AND METHODOLOGY SUMMARY #>'%.WATER MAIN INVESTIGATION - SECOND EVENT ^ !<

HALBY CHEMICAL SUPERFUND SITEWILMINGTON, DELAWARE

Number ofParameter Method Samples

Soil Sample Analysis -14 day Turnaround TimeCLP VOC DNRECHSCA SOP/SOW OLM03.1 12 to 18CLP SVOC SOWOLM03.1 12 to 18CLP Pest/PCB SOW OLM03.1 12 to 18CLP Metals SOWILM03.0 12 to 18CLP Cyanide SOWILM03.0 12 to 18

Thiocyanate ASTM D4193-89 12 to 18ASTM D3987-85 (Extraction Method)

Weak acid dissociable CN SM 18th Ed. 4500-CN I. 12 to 18

Zero Headspace TCLP Extraction SW846 Method 1311 6Non-volatile TCLP Extraction SW846 Method 1311 6TCLP VOC SW846 Method 8240A 6TCLP SVOC SW846 Method 8270A 6TCLP Metals SW846 Method 6

6010A/7471ATCLP Pesticides SW846 Method 8080A 6TCLP Herbicides SW846 Method 81 SOB 6

Ignitability SW846 Method 1020B 12 to 18Corrosivity SW846 Method 9045C 12 to 18Cyanide Reactivity. SW846 Section 7.3.3.2 12 to 18SuIfide Reactivity SW846 Section 7.3.4.2 12 to 18pH SW846 Method 9045C"' 12 to 18

Groundwater Sample AnalysisCLP VOC SOWOLM03.1 1CLP SVOC SOWOLM03.1 1CLP Pest/PCB SOW OLM03.1 1CLP Metals SOWILM03.0 1CLP Cyanide SOWILM03.0 1

Thiocyanate ASTM D4193-89 1Weak acid dissociable CN SM 18th Ed. 4500-CN I. 1

Air Sample Analysis - 48 - 72 hour Turnaround TimeHexavalent Chromium NIOSH Method 7600 note'21Arsenic NIOSH Method 7300 note'2'Chromium - • NIOSH Method 7300 note'2'Lead NIOSH Method 7300 note'2'Cassette CartridgeFilter medium (Cellulose Acetate or PVC)

AH3Q5I

Page 38: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

TABLE 2--contlnued

ANALYTICAL PARAMETERS AND METHODOLOGY SUMMARY *?;vWATER MAIN INVESTIGATION - SECOND EVENT '%.%

HALBY CHEMICAL SUPERFUND SITEWILMINGTON, DELAWARE

Quality Control Samples

Soil Sampling - 14 day Turnaround TimeNumber of

Type Parameters SamplesMS'5' VOC, SVOC, Pest/PCB, Metals, Cyanide 1-2'3'

Thiocyanate, CNMSD/Laboratory Duplicate'5' VOC, SVOC, Pest/PCB, Metals, Cyanide 1-2'3'

Thiocyanate, CNField Duplicate'5' VOC, SVOC, Pest/PCB, Metals, Cyanide 2

Thiocyanate, CNUSEPA Split?7' VOC, SVOC, Pest/PCB, Metals, Cyanide 2

Thiocyanate, CNTCLP, RCRA Characteristics

Equipment Rinsate Blank19' VOC, SVOC, Pest/PCB, Metals, Cyanide note'4'Thiocyanate, CN

Field Blank'9' VOC, SVOC, Pest/PCB, Metals, Cyanide note'4'Thiocyanate, CN

Trip Blank<8"9' VOC note'4'

Air Sampling - 48-72 hour Turnaround TimeReagent Blank Hexavalent Chromium, Arsenic, Chromium, & Lead note'11'Matrix Blank Hexavalent Chromium, Arsenic, Chromium, & Lead note'11'Blank Spike Hexavalent Chromium, Arsenic, Chromium, & Lead note"1'Matrix Blank Spike . Hexavalent Chromium, Arsenic, Chromium, & Lead note'11'Matrix Blank Spike Duplicate Hexavalent Chromium, Arsenic, Chromium, & Lead note'11'Laboratory Control Sample Hexavalent Chromium, Arsenic, Chromium, & Lead note'11'

"' pH for aqueous samples analyzed by SW846 Method 9040B.121 Two samples per day<31 One MS/MSD sample will be collected per sample delivery group (20 samples)141 One sample per day will be collected(5) Triple the nominal volume of a specific sample will be collected for MS and MSD/Laboratory Duplicates.(6) Double the nominal volume of a specific sample will be collected for Field Duplicates.(7> USEPA splits performed at EPA's discretion.(8) All samples for volatile organic analyses will be placed in one cooler per day. In the event that a second

cooler is needed for volatile organic analyses, then a second trip blank will be included.(9) ASTM Type 2 water will be used for preparation of QC blank samples.(11) QC samples for air sampling are analyzed at a rate of 1 per 20 samples.MS - Matrix SpikeMSD - Matrix Spike DuplicateVOC-CLP Volatile Organic CompoundsSVOC-CLP Semi Volatile Organic CompoundsPest/PCB-CLP Pesticides and Polynuclear Chlorinated BiphenylsMetals-CLP MetalsCyanide- CLP CyanideCN - Weak Acid Dissociable CN

AK305IOU

Page 39: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

£v*> -'

TABLE 3

ANALYTICAL PARAMETERS AND METHODOLOGY SUMMARYDRAINAGE DITCH DELINEATION .

HALBY CHEMICAL SUPERFUND SITEWILMINGTON, DELAWARE

Number ofParameter Method Samples

Soil Sample Analysis -14 day Turnaround Time

CLP VOC DNRECHSCA SOP/SOW OLM03.1 17 TO 34CLP SVOC "~"SOWOLM03.1 17 TO 34CLP Pest/PCB SOW OLM03.1 17 TO 34CLP Metals SOWILM03.0 17 TO 34CLP Cyanide SOW ILM03.0 17 TO 34

Thiocyanate ASTM D4193-89 17 TO 34ASTM D3987-85 (Extraction Method)

Weak acid dissociable CN SM 18th Ed. 4500-CN I. 17 TO 34

Zero Headspace TCLP Extraction SW846 Method 1311 17Non-volatile TCLP Extraction SW846 Method 1311 17TCLP VOC SW846 Method 8240A 17TCLP SVOC _______ SW846 Method 8270A 17TCLP Metals SW846 Method 17

6010A/7471ATCLP Pesticides SW846 Method 8080A 17TCLP Herbicides SW846 Method 81 SOB 17

Ignitability SW846 Method 1020B 17 TO 34Corrosivity SW846 Method 9045C 17 TO 34Cyanide Reactivity SW846 Section 7.3.3.2 17 TO 34Sulfide Reactivity SW846 Section 7.3.4.2 17 TO 34PH SW846 Method 9045C"' 17 TO 34

Air Sample Analysis - 48 - 72 hour Turnaround TimeHexavalent Chromium NIOSH Method 7600 note'2'Arsenic NIOSH Method 7300 note'2'Chromium NIOSH Method 7300 note'2'Lead NIOSH Method 7300 note'2'Cassette CartridgeFilter medium (Cellulose Acetate or PVC)

Afl305l05

Page 40: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

TABLE 3~continued ,,'-*<£•ANALYTICAL PARAMETERS AND METHODOLOGY SUMMARY 4^ '^

DRAINAGE DITCH DELINEATION & '<HALBY CHEMICAL SUPERFUND SITE •

WILMINGTON, DELAWAREQuality Control Samples

Soil Sampling -14 day Turnaround TimeNumber of

Type Parameters SamplesMS'5' VOC, SVOC, Pest/PCB, Metals, Cyanide 2 to 3'3'

Thiocyanate, CNMSD/Laboratory Duplicate'5' VOC, SVOC, Pesl/PCB, Metals, Cyanide 2 to 3'3'

Thiocyanate, CNField Duplicate'5' VOC, SVOC, Pest/PCB, Metals, Cyanide 4

Thiocyanate, CNUSEPA Splif7' VOC, SVOC, Pest/PCB, Metals, Cyanide 4

Thiocyanate, CNTCLP, RCRA Characteristics

Equipment Rinsate Blank19' VOC, SVOC, Pest/PCB, Metals, Cyanide note'4'Thiocyanate, CN

Field Blank*9' VOC, SVOC, Pest/PCB, Metals, Cyanide note'41Thiocyanate, CN

•Trip Blank18"9' VOC note'4'

Air Sampling - 48-72 hour Turnaround TimeReagent Blank Hexavalent Chromium, Arsenic, Chromium, & Lead note"1'Matrix Blank Hexavalent Chromium, Arsenic, Chromium, & Lead note'11'Blank Spike Hexavalent Chromium, Arsenic, Chromium, & Lead note"1'Matrix Blank Spike Hexavalent Chromium, Arsenic, Chromium, & Lead note"1'Matrix Blank Spike Duplicate Hexavalent Chromium, Arsenic, Chromium, & Lead note"1'Laboratory Control Sample Hexavalent Chromium, Arsenic, Chromium, & Lead note'11'

'" pH for aqueous samples analyzed by SW846 Method 9040B(2) Two samples per day(3) One MS/MSD sample will be collected per sample delivery group (20 samples)<4) One sample per day will be collected(5) Triple the nominal volume of a specific sample will be collected for MS and MSD/Laboratory Duplicates.(6) Double the nominal volume of a specific sample will be collected for Field Duplicates.(7) USEPA splits performed at EPA's discretion.(8) All samples for volatile organic analyses will be placed in one cooler per day. In the event that a second

cooler is needed for volatile organic analyses, then a second trip blank will be included.(9) ASTM Type 2 water will be used for preparation of QC blank samples.(11) QC samples for air sampling are analyzed at a rate of 1 per 20 samples.MS - Matrix SpikeMSD - Matrix Spike DuplicateVOC-CLP Volatile Organic CompoundsSVOC-CLP Semi Volatile Organic CompoundsPest/PCB-CLP Pesticides and Polynuclear Chlorinated BiphenylsMetals-CLP MetalsCyanide- CLP CyanideCN - Weak Acid Dissociable CN

AR3Q5I06

Page 41: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

TABLE 4 *;., ',,'*r

ANALYTICAL PARAMETERS AND METHODOLOGY SUMMARY %''SUMP AREA DELINEATION

HALBY CHEMICAL SUPERFUND SITEWILMINGTON, DELAWARE

Number ofParameter Method Samples

Soil Sample Analysis • 14 day Turnaround TimeCLP VOC DNREC HSCA SOP/SOW OLM03.1 4 to 8CLP SVOC SOWOLM03.1 4 to 8CLP Pest/PCB SOW OLM03.1 4 to 8CLP Metals SOWILM03.0 4 to 8CLP Cyanide SOWILM03.0 4 to 8

Thiocyanate ASTM D4193-89 4 to 8ASTM D3987-85 (Extraction Method)

Weak acid dissociable CN SM 18th Ed. 4500-CN I. 4 to 8

Zero Headspace TCLP Extraction SW846 Method 1311 4Non-volatile TCLP Extraction SW846 Method 1311 4TCLP VOC SW846 Method 8240A 4TCLP SVOC SW846 Method 8270A 4TCLP Metals SW846 Method 4

6010A/7471ATCLP Pesticides SW846 Method 8080A 4TCLP Herbicides SW846 Method 81 SOB 4

Ignitability SW846 Method 1020B 4 to 8Corrosivity SW846 Method 9045C 4 to 8Cyanide Reactivity" SW846 Section 7.3.3.2 4 to 8Sulfide Reactivity SW846 Section 7.3.4.2 4 to 8pH SW846 Method 9045C" 4 to 8

Air Sample Analysis - 48 - 72 hour Turnaround TimeHexavalent Chromium NIOSH Method 7600 note'2'Arsenic NIOSH Method 7300 note'2'Chromium NIOSH Method 7300 note'2'Lead NIOSH Method 7300 note'2'Cassette CartridgeFilter medium (Cellulose Acetate or PVC)

ftR305 I 07

Page 42: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

TABLE 4~continued <>„&'v'%.-

ANALYTICAL PARAMETERS AND METHODOLOGY SUMMARY V '"¥SUMP AREA DELINEATION

HALBY CHEMICAL SUPERFUND SITEWILMINGTON, DELAWARE

Quality Control Samples

Soil Sampling - 14 day Turnaround TimeNumber of

Type Parameters SamplesMS'5' VOC, SVOC, Pest/PCB, Metals, Cyanide 1 to 2'3'

Thiocyanate, CNMSD/Laboratory Duplicate'5' VOC, SVOC, Pest/PCB, Metals, Cyanide 1 to 2'3'

Thiocyanate, CNField Duplicate'6' VOC, SVOC, Pest/PCB, Metals, Cyanide 1

Thiocyanate, CNUSEPA Split17' VOC, SVOC, Pest/PCB, Metals, Cyanide 1

Thiocyanate, CNTCLP, RCRA Characteristics

Equipment Rinsate Blank'9' VOC, SVOC, Pest/PCB, Metals, Cyanide note'4'Thiocyanate, CN

Field Blank<9> VOC, SVOC, Pest/PCB, Metals, Cyanide note'4'Thiocyanate, CN

Trip Blank'8"9' VOC note'4'

Air Sampling - 48-72 hour Turnaround TimeReagent Blank Hexavalent Chromium, Arsenic, Chromium, & Lead note"1'Matrix Blank Hexavalent Chromium, Arsenic, Chromium, & Lead note"1'Blank Spike Hexavalent Chromium, Arsenic, Chromium, & Lead note""Matrix Blank Spike Hexavalent Chromium, Arsenic, Chromium, & Lead note01'Matrix Blank Spike Duplicate Hexavalent Chromium, Arsenic, Chromium, & Lead note"1'Laboratory Control Sample Hexavalent Chromium, Arsenic, Chromium, & Lead note""

'" pH for aqueous samples analyzed by SW846 Method 9040B.(2) Two samples per day(3) One MS/MSD sample will be collected per sample delivery group (20 samples)(4) One sample per day will be collected<5) Triple the nominal volume of a specific sample will be collected for MS and MSD/Laboratory Duplicates.(6) Double the nominal volume of a specific sample will be collected for Field Duplicates.<7' USEPA splits performed at EPA's discretion.(8) All samples for volatile organic analyses will be placed in one cooler per day. In the event that a second

cooler is needed for volatile organic analyses, then a second trip blank will be included.(9) ASTM Type 2 water will be used for preparation of QC blank samples."" QC samples for air sampling are analyzed at a rate of 1 per 20 samples.MS - Matrix SpikeMSD - Matrix Spike DuplicateVOC-CLP Volatile Organic CompoundsSVOC-CLP Semi Volatile Organic CompoundsPest/PCB-CLP Pesticides and Polynuclear Chlorinated BiphenylsMetais-CLP MetalsCyanide-CLP CyanideCN - Weak Acid Dissociable CN

AR305I08

Page 43: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

LU

gffi

o w 2

1o:§o1"S'•s.1

H120•*•

E'5re

SJ*•*re?(U

1

•ilsi1

Container

*— nt—"i"S

Sample Cont;

&*tn

Crec5

u>"

"oj.c 5oi 5c -*C .—

USEPA-CLP Stater

Work

for Organic

Multi-Media,

Mul

l£re-oO

rj«re"D „aQ._roo "J,U^ 2 re*#S8§£U d s=

fits

1 .g"T

3OOJ

f_y

*§l•S.«q.2- aU Q.£8

Aqueous-G,

1pla

stic s

crew

lined s

eotum

3.cregoO=re

£

Concentration

(SOWOLM03.1)

Eo(N

<n3OOI

erreO

£IE5d.re

<?S

Nonaqueous-

polypropylen

teflon

liner

.a"S S.c Soi 5P < .— .

USEPA-CLP Statei

Work

for O

rganic

Multi-Media,

Mull

Concentration

(SOWOLM03.1)

D

DSfi -—

s• s.-scu re oo 2 -" « t—

3 S.« »n 'n".— 3 c m< — p « 3- inS3ts 1SI£ S

^re•Ou"8?•oTj-

».

8(S

8 1S o

t!a.3T3

1

J

I

o"1<

2re

•oi5 £^#re *-is 013 3Z s^- uoi rein Sre xca LU

•£ P

S.«reT50•~

J 1 li

I1S*SSIzrec

-

Kov£

in3

Nonaqueo

^S3S (0 w

0V) "S C ws^ g «5"--=-SV ' Q.—

Nonaqueous-

Nonaqueous

bottle, black

t/iu'cregoO

polyethylene

i/i^1c 20) 5p < •—

USEPA-CLP

Statei

Work

for Organic

Multi-Media, Mul

Concentration

(SOWOLM03.1)

3a

35o!2a =g-.?<^Ifu cS'c£ 8

•£re•ou"cio•s>Vs

IN

II°

a.reu•a.105=£

U

1<

J/>CQyQ-•5J•D'u

I

' £-19! 4S o s"-O 3 <— 1 >•

.•K w • -g|.£ 30•£ P '*o 5 = J>'5 •=! S's.S ail ' *j; C £ reS S|Z <

011

NOvO

S •§crre

1

J> ffi ^C re uS n °.a "-1 irin « Oin .£ C Jr;

3=41

Nonaqueous

Nonaqueous

bottle, black

polyethylene

in in';/> V)

•*; - •*; >-° re 0^3I< !<fu -= g u -=

'c "3 5; 'E "53 §55 CS- S SjS cq^O.-OM ^O^-Oroo. g .re ~ o Q- c w '= o— i — "ure5 — i — "OresU f e a J t S U •- w is -J-.SSc— J^-S.? —^^Is^ ^^=85wiiso s!:=§o3§2u5/i =3^Su<£i

_

15- S. „re re >,T3 -D re00 "°oo co vo• — i — rM

MO•z.i

= VSiD-0< 9.

~Eooor—

Aqueous -

u&001•oT °in in ^g'S. ^

s s s«g"re 0 Vre _ oi I-S 'c fr£Z 3 < S

UaoJiTDTf

in in

P isD" 5re rac ~is

01OC

s 1rsi O3^ 2§° J,o-S ore £§«* IZ-t <

s(S

ui ro

Nonaqueo

4,8,

16,oi

— - D- °Q.reua._oT

1a.i«3§ S3 £D" —< a-

S3 ^™ w (ju.y cuc g _ orS|8 11 D. — ja3-g g r-g « J!|S.t §.re j) oi £ <!•

Z S. <~al

3 Sre >Ju.y.12 scrJ! §

i Q.—

Nonaqueous

bottle

, black

polyethylene

00ID.OiSa>_jnre

1 £

Page 44: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

inUJ

d < Q ««

S §I|as uj O uj S

1~o1"3Su"5-1H

1"5x

Jx5

Preservation (2)

11(32

s9si1u

~

*«1uv.a.at/i

t•sii

j(A

"°"w~m *CE .!£

5 §,0- °U •-CL

!sl

s.re-o(N

"re3•o'1

00 it:

<=>•§1 re

IIfa^

"E

in3O(U

jr«c

Q.reua.

1Q.

t/i

gs3 .E<"cl

-D'EreU

•&32 C^re .2 5

Ifl^ OI ••> - -2 £ >

CU, NA

OHto

pH>1

2,cool, 4 deg C

until

analyzed CaCOj

in

presence

of su

lfide

Nonaqueous Cool, 4

degC,

until analyzed

OI0c

NO(Nm ro

|°.

i»~z •*-

as_TO UU .—

Ill• Q.—l/l V > Ci)3 (j CcD — ^o-"°--£

111

TO

inWlnaCONO

1re

"uc

e

GJ<*s

1E.5J?u

Q.TO*z

1ore.c_y-_re

1 "O) CL.

^

,

5z

U X

AB305I10

Page 45: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

UJ

o H S tQ. C (/>

§

c ^ a.< Q

CO UJ O UJ =

UJ

1ca

fe

H|o%

,o

1

1BO

isI

2E'is

g

Ii(A

1

iy i.

*tt ™az

_a'>b

1a

e1aOl

1

1z£

oo»

NIOSH Method

;Sor

1o

1£re•OEo

0) "H?-gPS

Cassette

Cartri

(Cellulose Ace

u'cOl!£<

iK^

NIOSH Method

;

£oz

o

ssoc

S(UE»Eo

oi "of#5

Cassette

Cartri

(Cellulose Ac

eomium

U

i

NIOSH Method

;

01oZ

Olco

£Qc

Ere•5E

0

01 'o?

Cassette

Cartri

(Cellulose Ace

•ore3

1ts

NIOSH Method

;

201'

£

0

So!EreT3Eo

01DO•o

Cassette

Cartri

(PVC)

E3EJUc01

1I

Olj: oi*" -Q•£ =

In accordance w

Drager Detector

Handbook

-^

1?«".£*~* *••

m oii. W1 -— *

2 S JI--D 2

g

« 2re 0101 i2-

*l

1

Drager Tube

Ol

~3tn5|reU

01

_C 3is H-

In accordance w

Drager Detector

Handbook

.2 "o•-ICU

^ cre o>•. *" —g S J4-S 2

E 2O 3

TO

1 8.2 §to 1—

i

Drager Tube

_«oE

Ol•£ *« H

In accordance w

Drager Detector

Handbook

Jo2 g'5..0oi Si*~ ' IMffl O§i% (n -_

il-i(=-Ss

<§!- 2re oi01 Q-5 |(ft h-

|

Drager Tube

1"3

1I

_ _ cUJ ' ' ' i - i ._

reu

I,

•»"u EJ=

1 1

Page 46: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

TABLE 6

%REPORTING LIMITS #,&.HALBY CHEMICAL SDPERFDND SITE %WILMINCTON, DELAWARE

VOLATILES TARGET COMPOUND LIST AND CONTRACT REQUIRED.QUANTITATION LIMITS

Quantitation LimitsLow M e d . O n

Water Soil Soil ColumnVolatiles_________CAS Number ug/L ug/Kg ug/Kg(Eg)

1. Chloromethanc 74-87-3 10 10 1200 (50)2. Bromomethane 74-83-9 10 10 1200 (50)3, Vinyl Chloride 75-01-4 10 10 1200 (50)4. Chloroethane 75-00-3 10 10 1200 (50)5. Methylcne Chloride 75-09-2 10 10 1200 (50)

6. Acetone 67-64-1 10 10 1200 (50)7. Carbon Disulfidc 75-15-0 10 10 1200 (50)8." 1,1-Dichloroethene 75-35-4 10 10 1200 (50)9. 1,1-Dichloroethane 75-34-3 10 10 1200 (50)10. 1,2-Dichloroethene (total) 540-59-0 10 10 1200 (50)

11. Chloroform 67-66-3 10 10 1200 (50)12. 1,2-Dichloroethane 107-06-2 10 10 1200 (50)13. 2-Butanone 78-93-3 10 10 1200 (50)14. 1,1,1-Trichloroethane 71-55-6 10 10 1200 (50)15. Carbon Tctrachloridc 56-23-5 10 10 1200 (50)

16. Bromodichloromethane 75-27-4 10 10 1200 (50)17. 1,2-Dichloropropane 78-87-5 10 10 1200 (50)18. cis-l,3-Dichloropropene 10061-01-5 10 10 1200 (50)19. Trichloroethene 79-01-6 10 10 1200 (50)20. Dibromochloromethane 124-48-1 10 10 1200 (50)

21. 1,1,2-Trichloroethane 79-00-5 10 10 1200 (50)22. Benzene 71-43-2 10 10 1200 (50)23. trans-l,3-Dichloropropene 10061-02-6 10 10 1200 (50)24. Bromoform 75-25-2 10 10 1200 (50)25. 4-Methyl-2-pentanone 108-10-1 10 10 1200 (50)

26. 2-Hexanone 591-78-6 . 10 10 1200 (50)27. Tetrachloroethene 127-18-4 10 10 1200 (50)28. 1,1,2,2- Tetrachloroethane 79-34-5 10 10 1200 (50)29. Toluene 108-88-3 10 10 1200 (50)

OLM03.0

AH3Q5I 12

Page 47: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

TABLE 6

"REPORTING LIMITSHALBY CHEMICAL SUPERFUND SITE

WILMINCTON, DELAWARE

, . - - I -

Quantitation Limits

30.

31.32.33.

VolatilesChiorooenzcnc

EthylbenzeneStyreneXylenes (total)

'

CAS Number108-90-7

100-41-4100-42-51330-20-7

Waterug/L

iO

101010

LowSoilUg/Kg

10

101010

Mcd.Soilug/Kg1200

120012001200

OnColumn(ng)(50)

(50)(50)(50)

OLM03.0

A.R305M3

Page 48: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

c?,,TABLE 6 ^-^

'%• ""£REPORTING LIMITS

HALBY CHEMICAL SUPERFUND SITEWILMINCTON, DELAWARE

SEMIVOLATILES TARGET COMPOUND LIST AND CONTRACT REQUIREDQUANTITATION LIMITS

Quantitation LimitsLow Med. On

Water Soil Soil ColumnScmivolatiles CAS ug/L ug/Kg ug/Kg (ng)

Number __

34. Phenol 108-95-2 10 330 10000 (20)35. bis-(2-Chloroethyl) ether 111-44-4 10 330 10000 (20)36. 2-Chiorophenol 95-57-8 10 330 10000 (20)37. 1,3-Dichlorobenzcne 541-73-1 10 330 10000 (20)38. 1,4-Dichlorobenzenc 106 6-7 10 330 10000 (20)

39. 1,2-Dichlorobenzene 95-50-1 10 330 10000 (20)40. 2--Methylphenol 95-48-7 10 330 10000 (20)41. 2,2'-oxybis (1- 108-60-1 10 330 10000 (20)

ChloropropaneV42. 4-Methylphenol 106-44-5 10 330 10000 (20)43. N-Nitroso-di-n- 621-64-7 10 330 10000 (20)

propylamine

44. Hexachloroethanc 67-72-1 10 330 10000 (20)45. Nitrobenzene 98-95-3 10 330 10000 (20)46. Isophorone 78-59-1 10 330 10000 -(20)47. 2-Nitrophenol 88-75-5 10 330 10000 (20)48. 2,4-Dimethylphenol 105-67-9 10 330 10000 (20)

49. bis(2-Chloroethoxy) 111-91-1 10 330 10000 (20)methane

50. 2,4-Dichlorophenol 120-83-2 10 330 10000 (20)51. 1,2,4-Trichloro-benzene 120-82-1 10 330 10000 (20)52. Naphthalene 91-20-3 10 330 10000 (20)53. 4-Chloroaniline 106-47-8 10 330 10000 (20)

54. Hexachlorobutadiene 87-68-3 10 330 10000 (20)55. 4-Chloro-3-methylphenol 59-50-7 10 330 10000 (20)56. 2-Methylnaphthalene 91-57-6 10 330 10000 (20)57. Hexachlorocyclo- 77-47-4 . 10 330 10000 (20)

pentadiene

Previously known by the name bis(2-Chloroisopropyl) ether.

OLM03.0

AS305I II*

Page 49: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

TABLE 6 "

REPORTING LIMITSHALBY CHEMICAL SUPERFUND SITE

WILMINGTON, DELAWARE

Quantitation LimitsLOW Med. On

Water Soil Soil ColumnSemivolatilcs CAS ug/L ug/Kg ug/Kg (ngj

Number . -

58. 2,4,6-Trichlorophenol 88-06-2 10 330 10000 (20)

59. 2,4,5-Trichlorophenol 95-95-4 25 830 25000 (50)60. 2-Chloronaphthaienc 91-58-7 10 330 10000 (20)61. 2-Nitroaniline 88-74-4 25 830 25000 (50)62. Dimethylphthalatc 131-11-3 10 330 10000 (20)63. Acenaphthylcne 208-96-8 10 330 10000 (20)

64. 2,6-Dinitrotoluene 606-20-2 10 330 10000 (20)65. 3-Nitroaniline 99-09-2 25 830 25000 (50)66. Acenaphthene 83-32-9 10 330 10000 (20)67. 2,4-Dinitrophenol 51-28-5 25 830 25000 (50)68. 4-Nitrophenol 100-02-7 25 830 25000 (50)

69. Dibenzofuran 132-64-9 10 330 10000 (20)70. 2,4-Dinitrotolucne 121-14-2 10 330 10000 (20)71. Diethylphthalatc 84-66-2 10 330 10000 (20)72. 4-Chlorophenyl- 7005-72-3 10 330 10000 (20)

phenyl ether73. Fluorene 86-73-7 10 330 10000 -(20)

74. 4-Nitroaniline 100-01-6 25 830 25000 (50)75. 4,6-Dinitro-2- 534-52-1 25 830 25000 (50)

methylphenol76. N-Nitroso- 86-30-6 10 330 10000 (20)

diphenyiamine77. 4-Bromophenyl- 101-55-3 10 330 10000 (20)

phenylether78. Hexachlorobenzene 118-74-1 10 330 10000 (20)

79. Pentachlorophenol 87-86-5 25 830 25000 (50)80. Phenanthrene 85-01-8 10 330 10000 (20)81. Anthracene 120-12-7 10 330 10000 (20)82. Carbazole 86-74-8. 10 330 10000 (20)83. Di-n-butylphthalate 84-74-2 10 330 10000 (20)

84. Fluoranthene 206-44-0 10 330 10000 (20)

OLM03.0

AR305I15

Page 50: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

TABLE 6

REPORTING LIMITSHALBY CHEMICAL SUPERFUND SITE

WILMINGTON, DELAWARE

Quantitation LimitsLow Med. On

Water Soil Soil ColumnSemivolatiics CAS ug/L ug/Kg ug/Kg (ng)

Number _________•

85. Pyrene 129-00-0 10 330 10000 (20)86. Butylbcnzylphthalate 85-68-7 10 330 10000 (20)87. 3,3'-Dichlorobenzidinc 91-94-1 10 330 10000 (20)88. Benzo(a)anthracene 56-55-3 10 330 10000 (20)

89. Chrysenc 218-01-9 10 330 10000 (20)90. bis(2-Ethylhexyl) 117-81-7 10 330 10000 (20)

phthalate91. Di-n-octylphthalate 117-84-0 10 330 10000 (20)92. Benzo(b)fluoranthene 205-99-2 10 330 10000 (20)93. Benzo(k)fluoranthcnc 207-08-9 10 330 10000 (20)

OLM03.0

AR305I16

Page 51: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

TABLE 6

REPORTING' LIMITSHALBY CHEMICAL SUPERFUND SITE

WILMINGTON, DELAWARE

Quantitation Limits

3= =3;

94.95.

96.

97.J MtBC M

Semivolatiles= ==»=a:=B======= ===

Benzo(a)pyreneIndeno(l,2,3-cd)-pyreneDibenzo(a,h)-anthraceneBenzo(g,h,i)perylene

'CAS

Number=e5SS5 ^ ^ ^ va^ " "" "•Si S

50-32-8193-39-5

53-70-3

191-24-2 .

Waterug/L

==™= -:—

1010

10

10•——— «———••••

LowSoilUg/Kg

s a s cssr

330330

330

330-—— — ——— ™^

Med: —Soilug/Kg

a ^ SKMMMM" ^ i HBES

1000010000

10000

10000" — — ——

unColumn(ng)

=sam= m mc

(20)(20)

(20)

(20)—————

OLM03.0

AR305I 17

Page 52: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

TABLE 6

HALBY CHEMAL SITEWILMINGTON, DELAWARE

PESTICIDES/AROCLORS TARGET COMPOUND LIST AND CONTRACTREQUIRED QUANTITATI6N LIMITS2-3

Quantitation LimitsWater boil Un Column

Pesticides/Aroclors CAS ug/L ug/Kg (jpg]________Number_______________

98. alpha-BHC 319-84-6 0.050 1.7 599. beta-BHC 319-85-7 0.050 1.7 5100. delta-BHC 319-86-8 0.050 1.7 5101. gamma-BHC (Lindane) 58-89-9 0.050 1.7 5102. Heptachlor 76-44-8 0.050 1.7 5

103. Aldrin 309-00-2 0.050 1.7 5104. Heptachlor cpoxide4 111024-57-3 0.050 1.7 5105. -Endosulfan I 959-98-8 0.050 1.7 5106. Dieldrin 60-57-1 0.10 3.3 10107. 4,4'-DDE 72-55-9 0.10 3.3 10

108. Endrin 72-20-8 0.10 3.3 10109. Endosulfan II 33213-65-9 0.10 3.3 10110. 4,4'-DDD 72-54-8 0.10 3.3 10111. Endosulfan sulfatc 1031-07-8 0.10 3.3 10112. 4,4'-DDT 50-29-3 0.10 3.3 10

113. Methoxychlor 72-43-5 0.50 17 50114. Endrin ketone 53494-70-5 0.10 3.3 10115. Endrin aldehyde 7421-93-4 0.10 3.3 10116. alpha-Chlordane 5103-71-9 0.050 1.7 5117. gamma-Chlordane 5103-74-2 0.050 1.7 5

118. Toxaphene 8001-35-2 5.0 170 500119. Aroclor-1016 12674-11-2 1.0 33 100

2There is no differentiation between the preparation of lowand medium soil samples in this method for the analysis ofpesticides/Aroclors.

3The lower reporting limit for pesticide instrument blanksshall be one-half the CRQL values for water samples.

40nly the exo-epoxy isomer (isomer B) of heptachlor epoxide isreported on the data reporting forms (Exhibit B).

OLM03.0

AR305II8

Page 53: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

TABLE 6 ,.,'&?• ' • '

REPORTING LIMITS ^ HALBY CHEMICAL SUPERFUND SITE ^

WILMINGTON, DELAWARE . '*

Quantitatton LimitsWatpr *•*•' "• '• '

120.121.122.

123.124.125.

Pesticides/Aroclors

Arocior-1221Aroclor-1232Aroclor-1242

Aroclor-1248Aroclor-1254ArocIor-1260

'CASNumber11104-28-211141-16-553469-21-9

12672-29-611097-69-111096-82-5

Waterug/L

2.01.01.0

1.01.01.0

SOUUg/Kg

6/3333

333333

On Column(PS)

200100100

100100100

OLM03.0

AR30SI 19

Page 54: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

TABLE 6 >vj..

•V*REPORTING LIMITSHALBY CHEMICAL SUPERFUND SITE

WILMINGTON, DELAWARE____________INORGANIC TARGET ANALYTE LIST (TAL)_________________

Contract RequiredDetection Limit tl-JI

Analyte______\__________________(ucf/L)_______________

Aluminum 200Antimony 60Arsenic 10Barium 200Beryllium 5Cadmium 5Calcium 5000Chromium 10Cobalt 50Copper 25Iron 100Lead 3Magnesium 5000Manganese 15Mercury 0.2Nickel 40Potassium 5000Selenium 5Silver 10Sodium 5000Thallium 10Vanadium 50Zinc 20Cyanide 10

(1) Subject to the restrictions specified in the first page of Part G, Section IVof Exhibit D (Alternate Methods - Catastrophic Failure) any analytical methodspecified in SOW Exhibit D may be utilized as long as the documented instrumentor method detection limits meet the Contract Required Detection Limit (CRDL)requirements. Higher detection limits may only be used in the followingcircumstance:

If the sample concentration exceeds five times the detection limit ofthe instrument or method in use, the value may be reported even thoughthe instrument or method detection limit may not equal the ContractRequired Detection Limit. This is illustrated in the example below:

For lead: "v

Method in use = ICPInstrument Detection Limit (IDL) =40Sample concentration =220Contract Required Detection Limit (CRDL) * 3

ILM03.0

AR305I20

Page 55: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

TABLE 6 • x %.%fy .

REPORTING LIMITS , -"HALBY CHEMICAL SUPERFUND SITE

WILMINGTON, DELAWARE -*The value of 220 may be reported even though the instrument detectionlimit is greater than CRDL. The instrument or method detection limitmust be documented as described in Exhibits B and £.

(2) The CRDLs are the instrument detection limits obtained in pure water that mustbe met using the procedure in Exhibit E. The detection limits for samples maybe considerably higher depending on the sample matrix.

ILM03.0

A.R30512I

Page 56: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

i.-.

TABLE 6

REPORTING LIMITSHALBY CHEMICAL SUPERFUND SITE

WILMINGTON, DELAWARE

AIR SAMPLES

PARAMETER

Hexavalent chromium

Total Chromium

Arsenic

Lead

DETECTION LIMIT<ug)

1.0

0.15

0.3

0.2

Actual concentrations in air are determined based on the volume of air drawn through the samplingmedium which in this case is a PVC filter used for hexavalent chromium and a mixed cellulose esterfilter for the other three elements.

-AR305I22

Page 57: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

LU

zgo

to

I *oQ at

1> ->gj£OS

COMPOUND ADDED

5zUJD

u.

£^^25.

fi£LU

5^

Q.

: i ;: ! ,

co ro <-ro T— CNi i i•<*• cn oco in ix

Toluene - d8

Bromofluorobenzene

1 ,2-Dichloroethane - d4

0)Q.Ereto

1LU

"reDO23to

J*,*-»

"o>

CM t r- 'i- T-CN tN CN CN tN

CN tx CN CT) rorx ro * " ro ro

i i i i iOl CN »O 0*1 C5in vp vj3 in vo

1,1-Dichloroethane

Trichloroethene

Benzene

Toluene

Chlorobenzene

OQto8.

'5.C/J

Dto2*

1

l i l tI I I1 1 I 11 1 1 1

o tn ix rotN r- ro T-

1 1 1 1ro O CO TftN ro t— CN

Nitrobenzene-d5

2-Fluorobiphenyl

Terphenyl-d14

Phenol-d5

VQ.Eto

SiLU

se?i.jto

rt|

to

i l l !1 1 1 1

«- fN O OfN CN ro ro

in C31 O OCN i— CN CN

2-Fluorophenol

2,4,6-Tribromophenol

2-Chlorophenol-d4

1 ,2-Dichlorobenzene-d4

m o ixro m tN

o CN t

" in co^ CN CN

Phenol

2-Chlorophenol

1 ,4-Dichlorobenzene

UDtoH

'5.toQto

1

n r» o f\A u 3 U

co ro ro Ciro tN ro »—

vO Ix ro fxCN O O ro

i i i i«— CO vO T-rt- ro CN ro

-Nitroso-di-n-propylamine

1 ,2,4-Trichlorobenzene

t-Chloro-3-Methylphenol

Acenapthene

Z

3 " "

"V

O fx K Oun rf rt ro

2§§3

- S^ inr- ™ r- CO

4-Nitrophenol

2,4-Dinitrotoluene

Pentachlorophenol

Pyrene

Page 58: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

LU

to

a».1

t5Ig

Cu

t/lr*s2>• CsCtf &*raOtf

QLUQQ<OZoOL.

§U

uLU

aLUU.

UJP.

S

LUu32££D.

1

Oinoro

CU-^ cc.«CU >..c xa. re15 a>2 Eo 2S .0y •=S $

CUa.reen

9LU

"re

to

V"•S J'n in 2

O i- ro co" in Oin ro •** ro 'i- in

tx O CN J" CT> TfCN ro ro ro ro ro

i i i i i ivfl in Tt" r— CN ro~ ro ro ro CN

U"^ ~ c tCO c C C *r" LuJ1 1 1_| 2 1 9

^3-4^ ^ TJ-'DO •E

ODtoa.7HM

CU'a.toQtoS—

S? a; S° re g

° o3-D re

i O""O ">! cu c ^o S |«l-l* i §</> t/} gCU ~ O—1 U

mCN ,

A lIX

4-*

U

C

"o 11recre

U (JD Dto toCU CUCL a.r™ ?—"

(L) ^

t i.D

•~ v1/5 -Q*2 'cia-

5 " « ">Q O c _iOi CU .2 Q

*x E"! ^ S S xS3§-SD 8|n* D£ CUJK r i 4-1 (/)cu \u re v>X ' u —o — •" iz:c + a. gJ^ s-i ro4—*

—————— frfi

,

CU

1 oa» Q;3 >14 "vi cO *- O^ O Cs ^ .EOS CJ- E m2 -^o ~Z-oco

t/>g•g.•"o0)

"rere

ODtos.M

toU

on in 1 rjJU vl 1 £

S Sn_ "SE otv _ iH3 l-uO 5

liev§ 2 x!§!1 §111

i1

f

t

g/of ]§"- > re. <u <uo § i?81 Sto c cuk. CU JCcu u u5§1Q._

—— T 1 1 CU

.2 x !2a -Si «=to c 5.Q. 0 ULJ *5 i_

•fi"O

^ i. H

"%''

A

1a_.t=:"O •—CU "~ o

cu «'t3CL.X o« "re "Do "53 Si= =S !•O S" «)&••= sO *t*i TO

4r *3

1 "cSCTJ *\

"ii ^ -l!i

fCL

ret/i in

g 1'O J5

E 21 1•— </>x cu

ery gr

oup (ma

ent di

fference

upled plasma

Jes a

re pr

edig

.> 2 o g-•53 cu " E-if isi" 5!-J9 Qj *o —

j " f i?rs n_ " O7> cv*

Page 59: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

O (U fi£

03 ^^2 <

3 2tt

PsZJ_ "jrJJ >sPLU

SJtf

oLUOO2?Z.DSiU -

5LU

aLUfi£U.

ss£««

RAMETE!

*

• '

2JS!

• Q.

® 1q I1? °"!a. <-to

rf J

ESc"oCU4

"re*

oCN

HT™*

-ao

IMDOreCUDi

exavaleni

hromium

Arsenic

I U

.gC) iL® reCTi 4"

q S1? Q. *-to

4«*

E

SC

"oo;"rec^

oCN

8.•M

C ._reCQ

re

hromium

Lead

u

3£20

4-Jt/1

^

Q

O

"re*

otN

S.r~*

Qto

i

,~LnMB

T— •

LOCO

*wto

i5'oa;"re*C

oCN

8.r—

|j.

^^

~mT""

t

OO

4— « '

1S"oCUJ2

"re**•

OCN

8.r-*

'a.toc_reCO

•9 3•g uCL reS -ao cre re*-*- r- -S0 o S«3 -3J :=1 'iJ §-

-i «2 «O «XI CUre a>_i en

Qtoi

AR305I25

Page 60: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

LUa.

1ee

^_^

"C1

.2

CD

^

g

^

0Q)Q£

C7>

0 Sp is

g'etsi o5CM 2..

^>— .O O t-

T-

S2j»^O)>——K

in *CM©

p» *~

ill|i §°S •£ 5ra i "*o 2 *— "•o wO5 ^ow J£ ^1 is sQ. en

1| |si 103 >_ wZ coLM m

UJ S 4-»ri i(/) 0)2 -S OJ

CO CD T-CM T- T-0 O OO O O

CM CO O§§8000

en cp mat o o>"

co co inO 0) 0V™ T"

r*. o CMin in to o o

coco T N:T— T—

t~- CD •Vco in oO> O CMT- CM CM

0 E.9 3C -F 0co E c2 E N<5

11i0>

roco•eg.CLOoCD^- ®

1 !i .5£ 1 «•§ 1 ™CO > £JC n

^ S 7*.^3 "

eported w

ere obt

ainec

nd sh

ould be

indepen

Iter corresponds

to 5

1

*- CO ig

3 S =>"TO E «> 3 CM-~.tr> ~•55. *- S-

AR305I26

Page 61: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995

o33m

:-...----«.-

j, ' ~ i-''--- ^-T,-'-!-''ti ftjf *~'-f> ~~j_2.-~I!-;i.~-".._"=rf,'.',~ •;:'-_";'j '--' v!'-'. - - - v - '."•""- _iS|"„._-."-; ;" ' "..; -"l".! ' */ ^ iiSK * S rl - '1i -:U-i-> -_* "' -*£?5 r*:j ' .l"""- ". ;'-- - -—1 __"..4

rSj-.i™'"-1" -"— '- : '?I" ji5fefc ; ;K,'"'_,- J - ^ r--:-"-—. -v« _•-£..-_- Y1"!.!'1 "•/ _-_s-=i. ."-,"--. -_ • -'-^1

AR305I27

Page 62: APPENDIX B QUALITY ASSURANCE PROJECT PLAN · Langan Engineering and Environmental Services, Inc. River Drive Center 1 Elmwood Park, New Jersey 07407 8 August 1995 1 September 1995