23
Appendix B Noise

Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Appendix B

Noise

Page 2: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Appendix B1

Process Plant Measured and Modelled Calibration Points

Page 3: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Syncrude Canada Ltd. Mildred Lake Extension Project Volume 3 – EIA Appendices December 2014

Appendix B1 – Page 1

Process Plant Measured and Modelled Calibration Points

Cadna/A ID Date of

Measurement Location of

Measurement Measured Leq

(dBA) Modelled Leq

(dBA) Difference

UTM Coordinates (NAD83, Zone 12) (m)

Easting Northing

M072 August 16-18, 2011 MLX Process Plant 70.5 69.6 -0.9 463378 6322788

M002 August 16-18, 2011 MLX Process Plant 61.4 61.4 0.0 462105 6321832

M005 August 16-18, 2011 MLX Process Plant 60.0 59.5 -0.5 462110 6321789

M007 August 16-18, 2011 MLX Process Plant 65.0 65.4 0.4 462232 6321862

M008 August 16-18, 2011 MLX Process Plant 69.3 67.6 -1.7 462300 6321837

M009 August 16-18, 2011 MLX Process Plant 67.8 67.2 -0.6 462113 6321919

M011 August 16-18, 2011 MLX Process Plant 63.0 63.0 0.0 462078 6321895

M013 August 16-18, 2011 MLX Process Plant 65.4 65.3 -0.1 462002 6322091

M014 August 16-18, 2011 MLX Process Plant 68.4 68.5 0.1 461932 6322062

M016 August 16-18, 2011 MLX Process Plant 66.0 66.2 0.2 461982 6321943

M018 August 16-18, 2011 MLX Process Plant 62.4 61.5 -0.9 462059 6321863

M019 August 16-18, 2011 MLX Process Plant 74.9 74.1 -0.8 462183 6322295

M021 August 16-18, 2011 MLX Process Plant 79.3 80.1 0.8 462201 6322163

M023 August 16-18, 2011 MLX Process Plant 68.9 68.5 -0.4 461996 6322254

M025 August 16-18, 2011 MLX Process Plant 69.5 69.0 -0.5 461947 6322399

M045 August 16-18, 2011 MLX Process Plant 71.4 71.8 0.4 457880 6328916

M047 August 16-18, 2011 MLX Process Plant 60.8 58.8 -2.0 459958 6322756

M053 August 16-18, 2011 MLX Process Plant 66.7 66.5 -0.2 462579 6323145

M054 August 16-18, 2011 MLX Process Plant 66.9 66.9 0.0 462306 6323050

M057 August 16-18, 2011 MLX Process Plant 75.5 75.4 -0.1 462151 6322889

M059 August 16-18, 2011 MLX Process Plant 70.3 70.7 0.4 462032 6322737

M071 August 16-18, 2011 MLX Process Plant 70.2 68.5 -1.7 463419 6322671

M074 August 16-18, 2011 MLX Process Plant 65.4 65.8 0.4 463357 6323178

M076 August 16-18, 2011 MLX Process Plant 70.1 69.6 -0.5 463416 6322908

M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307

M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214

M082 August 16-18, 2011 MLX Process Plant 79.9 79.9 0 462322 6322097

M085 August 16-18, 2011 MLX Process Plant 72.6 72.7 0.1 462483 6321881

M086 August 16-18, 2011 MLX Process Plant 64.5 65.1 0.6 462911 6322225

M087 August 16-18, 2011 MLX Process Plant 72.7 72.7 0.0 462758 6321959

M063 August 16-18, 2011 MLX Process Plant 70.0 70.3 0.3 462009 6322866

Page 4: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Appendix B2

Stationary Sound Source Sound Power Levels

Page 5: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Syncrude Canada Ltd. Mildred Lake Extension Project Volume 3 – EIA Appendices December 2014

Appendix B2 – Page 1

Stationary Sound Source Sound Power Levels

Source Source Type

Quantity Octave Spectrum (dB) Overall

Sound Power (dBA)

Overall Sound Power

(dB) Reference

31.5 63 125 250 500 1000 2000 4000 8000

BML - HyperSpikes Point6 15 68.3 65.3 61.3 59.3 74.3 87.3 110.3 135.3 126.3 136.6 135.8 2

EIP - HyperSpikes Point6 11 68.3 65.3 61.3 59.3 74.3 87.3 110.3 135.3 126.3 136.6 135.8 2

MLX Diesel Pumphouse Point 1 122.9 137.9 137.9 120.9 121.9 119.9 118.9 112.9 106.9 126.9 141.2 1

MLX Process Plant Cooling Tower 1 Point 1 124.8 121.8 118.8 114.8 109.8 108.8 107.8 107.8 105.8 115.7 127.7 1

MLX Process Plant Cooling Tower 2 Point 1 126.8 123.8 120.8 116.8 111.8 110.8 109.8 109.8 107.8 117.7 129.7 1

MLX Process Plant Cooling Tower 3 Point 1 126.8 123.8 120.8 116.8 111.8 110.8 109.8 109.8 107.8 117.7 129.7 1

MLX Process Plant Cooling Tower 4 Point 1 128.8 125.8 122.8 118.8 113.8 112.8 111.8 111.8 109.8 119.7 131.7 1

MLX Process Plant Nitrogen Plant Point 1 112.1 109.1 108.1 105.1 106.1 104.1 102.1 101.1 92.1 109.6 116.5 1

MLX Sulfur Pile - Steam Escape Point 1 79.6 81.6 80.6 81.6 87.6 91.6 94.6 93.6 90.6 99.7 99.5 2

MLXW Ore Prep 3rd Stage Pumphouse Exhausts

Point 8 0.0 105.0 94.0 92.0 91.0 84.0 80.0 77.0 70.0 91.5 105.7 3

MLXW Ore Prep MLSB Pumphouse BUILDING Louvres

Point 4 0.0 88.0 88.0 89.0 89.0 91.0 89.0 84.0 75.0 95.0 97.2 3

MLXW Ore Prep PW Pumphouse BUILDING Exhausts

Point 7 0.0 88.0 88.0 89.0 89.0 91.0 89.0 84.0 75.0 95.0 97.2 3

MLXW Ore Prep Screening Building Large Vents

Point 8 0.0 96.0 87.0 88.0 89.0 91.0 89.0 85.0 78.0 95.1 99.2 3

MLXW Ore Prep Screening Building Roof Exhausts

Point 7 0.0 92.0 89.0 95.0 93.0 93.0 91.0 86.0 81.0 97.5 100.5 3

MLXW Ore Prep Screening Building Small Vents

Point 6 0.0 93.0 85.0 86.0 86.0 88.0 86.0 82.0 76.0 92.2 96.4 3

MLXW Ore Prep Trim Heater Building Heaters

Point 6 0.0 37.0 49.0 61.0 73.0 85.0 89.0 90.0 90.0 95.3 94.9 3

MLXW Surge Facility Building Exhaust Fans Point 4 100.1 100.1 99.1 95.1 94.1 92.1 91.1 87.1 80.1 97.7 105.7 4,5

MLXW Surge Facility Building Louvres Point 4 103.0 103.0 102.0 97.0 97.0 95.0 93.0 90.0 82.0 100.3 108.6 4,5

SWIP - HyperSpike Point6 8 68.3 65.3 61.3 59.3 74.3 87.3 110.3 135.3 126.3 136.6 135.8 2

SWSS - HyperSpike Point6 14 68.3 65.3 61.3 59.3 74.3 87.3 110.3 135.3 126.3 136.6 135.8 2

Tailings Pond Pump Point 1 117.9 127.9 125.9 124.9 117.9 119.9 120.9 112.9 106.9 125.7 132.3 1

MLSB - HyperSpike Point6 21 68.3 65.3 61.3 59.3 74.3 87.3 110.3 135.3 126.3 136.6 135.8 2

MLXW Ore Preparation Train 1 Conveyor 1 Line 1 117.2 121.2 116.2 114.2 117.2 116.2 110.2 102.2 95.2 119.4 125.5 2

MLXW Ore Preparation Train 1 Conveyor 2 Line 1 109.7 113.7 108.7 106.7 109.7 108.7 102.7 94.7 87.7 111.9 118.0 2

MLXW Ore Preparation Train 2 Conveyor 1 Line 1 116.1 120.1 115.1 113.1 116.1 115.1 109.1 101.1 94.1 118.3 124.4 2

MLXW Ore Preparation Train 2 Conveyor 2 Line 1 109.7 113.7 108.7 106.7 109.7 108.7 102.7 94.7 87.7 111.9 118.0 2

Page 6: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Syncrude Canada Ltd. Mildred Lake Extension Project Volume 3 – EIA Appendices December 2014

Appendix B2 – Page 2

Source Source Type

Quantity Octave Spectrum (dB) Overall

Sound Power (dBA)

Overall Sound Power

(dB) Reference

31.5 63 125 250 500 1000 2000 4000 8000

MLX Ore Preparation Train 2 Conveyor 2 Drive Building

Area 1 97.5 104.5 107.5 100.5 109.5 107.5 95.5 89.5 82.5 110.3 114.0 2

MLX Process Plant Hydro-processing Area 1 134.0 131.0 136.0 129.0 121.0 115.0 113.0 109.0 96.0 125.3 139.4 1

MLX Power House Area 1 114.9 119.9 115.9 112.9 112.9 113.9 109.9 107.9 96.9 117.7 123.9 1

MLX Process Plant Cokers Area 1 121.9 126.9 124.9 132.9 127.9 125.9 122.9 113.9 109.9 131.0 136.2 1

MLX Process Plant Extraction 1 Area 1 114.2 118.2 116.2 124.2 119.2 118.2 114.2 106.2 102.2 122.7 127.7 1

MLX Process Plant Extraction 2 Area 1 120.0 116.0 111.0 107.0 105.0 104.0 99.0 90.0 72.0 108.0 122.1 1

MLX Process Plant Extraction 3 Area 1 121.8 117.8 112.8 108.8 107.8 105.8 100.8 91.8 73.8 110.1 124.0 1

MLX Process Plant Extraction 4 Area 1 122.1 118.1 113.1 109.1 107.1 105.1 101.1 92.1 74.1 109.7 124.2 1

MLX Process Plant Extraction 5 Area 1 124.0 120.0 115.0 111.0 109.0 108.0 103.0 94.0 76.0 112.0 126.1 1

MLX Process Plant Extraction 6 Area 1 122.1 118.1 113.1 109.1 107.1 105.1 101.1 92.1 74.1 109.7 124.2 1

MLX Process Plant Flare Building Area 1 123.9 124.9 122.9 118.9 110.9 102.9 98.9 90.9 77.9 114.0 129.2 1

MLX Process Plant Sub Station Area 1 109.0 111.0 105.0 105.0 106.0 100.0 94.0 85.0 70.0 105.8 115.0 1

MLX Process Plant Surge Pile Area 1 120.7 124.7 118.7 112.7 111.7 112.7 115.7 103.7 93.7 119.2 127.6 4,5

MLXW Ore Prep 3rd Stage Pumphouse 1 Area 1 -3.1 111.9 98.9 95.9 85.9 78.9 67.9 57.9 43.9 91.4 112.3 3

MLXW Ore Prep 3rd Stage Pumphouse 2 Area 1 -3.1 111.9 98.9 95.9 85.9 78.9 67.9 57.9 43.9 91.4 112.3 3

MLXW Ore Prep 3rd Stage Pumphouse 3 Area 1 -3.1 111.9 98.9 95.9 85.9 78.9 67.9 57.9 43.9 91.4 112.3 3

MLXW Ore Prep 3rd Stage Pumphouse 4 Area 1 -3.1 111.9 98.9 95.9 85.9 78.9 67.9 57.9 43.9 91.4 112.3 3

MLXW Ore Prep Chemical Injection and Strainer Building

Area 1 -2.5 49.5 43.5 40.5 31.5 24.5 14.5 5.5 0.5 35.2 50.9 3

MLXW Ore Prep PW Pumphouse Building Area 1 -1.8 104.2 99.2 95.2 85.2 78.2 68.2 57.2 43.2 89.8 105.8 3

MLXW Ore Prep Screening Building Area 1 -3.3 115.7 103.7 99.7 90.7 82.7 73.7 63.7 49.7 95.5 116.1 3

MLXW Ore Prep Train 1 Conveyor 2 Drive Building

Area 1 95.0 101.0 105.0 104.0 106.0 102.0 96.0 92.0 87.0 106.7 111.3 3

MLXW Ore Prep Train 2 Conveyor 2 Drive Building

Area 1 95.0 101.0 105.0 104.0 106.0 102.0 96.0 92.0 87.0 106.7 111.3 3

MLXW Ore Prep Trim Heater Building Area 1 -1.9 98.1 93.1 90.1 82.1 74.1 64.1 54.1 42.1 85.0 99.9 3

MLXW Ore Preparation Train 1 Conveyor 1 Dump Building

Area 1 102.2 105.2 106.2 110.2 108.2 103.2 97.2 91.2 84.2 108.9 114.7 3

MLXW Ore Preparation Train 2 Conveyor 1 Dump Building

Area 1 102.2 105.2 106.2 110.2 108.2 103.2 97.2 91.2 84.2 108.9 114.7 3

MLXW Ore Preparation Train 2 Conveyor 2 Drive Building

Area 1 97.5 104.5 107.5 100.5 109.5 107.5 95.5 89.5 82.5 110.3 114.0 3

MLXW Surge Facility Building Walls Area 4 -2.3 103.7 98.7 94.7 84.7 77.7 67.7 56.7 42.7 89.3 105.3 4,5

Sulfur block Water Station Area 1 114.6 114.6 110.6 112.6 109.6 107.6 107.6 107.6 101.6 114.6 120.6 2

Page 7: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Syncrude Canada Ltd. Mildred Lake Extension Project Volume 3 – EIA Appendices December 2014

Appendix B2 – Page 3

Source Source Type

Quantity Octave Spectrum (dB) Overall

Sound Power (dBA)

Overall Sound Power

(dB) Reference

31.5 63 125 250 500 1000 2000 4000 8000

MLX Ore Preparation Train 1 Conveyor 1 Dump Building

Vertical Area

4 103.8 106.8 107.8 111.8 109.8 104.8 98.8 92.8 85.8 110.5 116.3 3

MLX Ore Preparation Train 1 Conveyor 1 Dump Building

Vertical Area

2 102.4 105.4 106.4 110.4 109.4 103.4 97.4 91.4 85.4 109.5 115.1 3

MLX Ore Preparation Train 2 Conveyor 2 Drive Building

Vertical Area

1 104.8 111.8 114.8 107.8 116.8 114.8 102.8 96.8 89.8 117.6 121.3 3

MLX Process Plant Extraction 6 Vertical Area

1 128.1 124.1 119.1 115.1 113.1 111.1 107.1 98.1 80.1 115.7 130.2 1

MLX Process Plant Flare Building 1 Vertical Area

1 123.9 124.9 122.9 118.9 110.9 102.9 98.9 90.9 77.9 114.0 129.2 1

MLX Process Plant Flare Building 2 Vertical Area

1 121.9 122.9 120.9 116.9 108.9 100.9 96.9 88.9 75.9 112.0 127.2 1

MLX Process Plant Flare Building 3 Vertical Area

1 123.9 124.9 122.9 118.9 110.9 102.9 98.9 90.9 77.9 114.0 129.2 1

MLX Process Plant Flare Building 4 Vertical Area

1 119.9 120.9 118.9 114.9 106.9 98.9 94.9 86.9 73.9 110.0 125.2 1

MLXW Ore Prep 3rd Stage Pumphouse 1 Vertical Area

2 -7.0 108.0 95.0 92.0 82.0 75.0 64.0 54.0 40.0 87.5 108.4 3

MLXW Ore Prep 3rd Stage Pumphouse 1 Vertical Area

2 -12.7 102.3 89.3 86.3 76.3 69.3 58.3 48.3 34.3 81.8 102.7 3

MLXW Ore Prep 3rd Stage Pumphouse 2 Vertical Area

2 -7.0 108.0 95.0 92.0 82.0 75.0 64.0 54.0 40.0 87.5 108.4 3

MLXW Ore Prep 3rd Stage Pumphouse 2 Vertical Area

2 -12.7 102.3 89.3 86.3 76.3 69.3 58.3 48.3 34.3 81.8 102.7 3

MLXW Ore Prep 3rd Stage Pumphouse 3 Vertical Area

2 -7.0 108.0 95.0 92.0 82.0 75.0 64.0 54.0 40.0 87.5 108.4 3

MLXW Ore Prep 3rd Stage Pumphouse 3 Vertical Area

2 -12.7 102.3 89.3 86.3 76.3 69.3 58.3 48.3 34.3 81.8 102.7 3

MLXW Ore Prep 3rd Stage Pumphouse 4 Vertical Area

2 -7.0 108.0 95.0 92.0 82.0 75.0 64.0 54.0 40.0 87.5 108.4 3

MLXW Ore Prep 3rd Stage Pumphouse 4 Vertical Area

2 -12.7 102.3 89.3 86.3 76.3 69.3 58.3 48.3 34.3 81.8 102.7 3

MLXW Ore Prep Chemical Injection and Strainer Building

Vertical Area

2 -10.4 41.6 35.6 32.6 23.6 16.6 6.6 -2.4 -7.4 27.3 43.0 3

MLXW Ore Prep Chemical Injection and Strainer Building

Vertical Area

2 -8.8 43.2 37.2 34.2 25.2 18.2 8.2 -0.8 -5.8 28.9 44.6 3

MLXW Ore Prep MLSB Pumphouse Building

Vertical Area

2 -12.2 93.8 88.8 84.8 74.8 67.8 57.8 46.8 32.8 79.4 95.4 3

Page 8: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Syncrude Canada Ltd. Mildred Lake Extension Project Volume 3 – EIA Appendices December 2014

Appendix B2 – Page 4

Source Source Type

Quantity Octave Spectrum (dB) Overall

Sound Power (dBA)

Overall Sound Power

(dB) Reference

31.5 63 125 250 500 1000 2000 4000 8000

MLXW Ore Prep MLSB Pumphouse Building

Vertical Area

2 -8.3 97.7 92.7 88.7 78.7 71.7 61.7 50.7 36.7 83.3 99.3 3

MLXW Ore Prep PW Pumphouse Building Vertical Area

2 -13.3 92.7 87.7 83.7 73.7 66.7 56.7 45.7 31.7 78.3 94.3 3

MLXW Ore Prep PW Pumphouse Building Vertical Area

2 -8.9 97.1 92.1 88.1 78.1 71.1 61.1 50.1 36.1 82.7 98.7 3

MLXW Ore Prep Screening Building Vertical Area

2 -10.3 108.7 96.7 92.7 83.7 75.7 66.7 56.7 42.7 88.5 109.1 3

MLXW Ore Prep Screening Building Vertical Area

2 -7.6 111.4 99.4 95.4 86.4 78.4 69.4 59.4 45.4 91.2 111.8 3

MLXW Ore Prep Train 1 Conveyor 3 Drive Building

Vertical Area

2 101.6 107.6 111.6 110.6 112.6 108.6 102.6 98.6 93.6 113.3 117.9 3

MLXW Ore Prep Trim Heater Building Vertical Area

2 -11.9 88.1 83.1 80.1 72.1 64.1 54.1 44.1 32.1 75.0 89.9 3

MLXW Ore Prep Trim Heater Building Vertical Area

2 -9.5 90.5 85.5 82.5 74.5 66.5 56.5 46.5 34.5 77.4 92.3 3

MLXW Ore Preparation Train 1 Conveyor 1 Dump Building

Vertical Area

2 103.6 106.6 107.6 111.6 109.6 104.6 98.6 92.6 85.6 110.3 116.1 3

MLXW Ore Preparation Train 2 Conveyor 2 Drive Building

Vertical Area

1 104.8 111.8 114.8 107.8 116.8 114.8 102.8 96.8 89.8 117.6 121.3 3

MLXW Surge Facility Building Walls Vertical Area

2 117.1 116.1 113.1 105.1 95.1 90.1 87.1 79.1 70.1 101.4 120.6 4,5

MLXW Surge Facility Building Walls Vertical Area

2 120.6 119.6 116.6 108.6 98.6 93.6 90.6 82.6 73.6 104.9 124.1 4,5

Notes: 1 Noise measurement at the Syncrude MLX facility 2011. 2 Noise measurement at the Syncrude MLX facility 2013. 3 Sound powers from Internal Syncrude noise study. 4 Equipment based on Bies and Hansen (2009). 5 Equipment based on Beranek and Ver (2006). 6 Operating time applied to spectra and sound powers.

Page 9: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Appendix B3

Baseline Noise Measurements at Fort MacKay – Summer 2011 and Winter 2012

Page 10: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Syncrude Canada Ltd. Mildred Lake Extension Project Volume 3 – EIA Appendices December 2014

Appendix B3 – Page 1

Baseline Noise Measurements at Fort MacKay – Summer 2011 and Winter 2012

Page 11: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Syncrude Canada Ltd. Mildred Lake Extension Project Volume 3 – EIA Appendices December 2014

Appendix B3 – Page 2

Page 12: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Syncrude Canada Ltd. Mildred Lake Extension Project Volume 3 – EIA Appendices December 2014

Appendix B3 – Page 3

Page 13: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Syncrude Canada Ltd. Mildred Lake Extension Project Volume 3 – EIA Appendices December 2014

Appendix B3 – Page 4

Page 14: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Syncrude Canada Ltd. Mildred Lake Extension Project Volume 3 – EIA Appendices December 2014

Appendix B3 – Page 5

Page 15: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Syncrude Canada Ltd. Mildred Lake Extension Project Volume 3 – EIA Appendices December 2014

Appendix B3 – Page 6

Page 16: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Appendix B4

Baseline Year 2014 Mining Equipment Sound Power Levels

Page 17: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Syncrude Canada Ltd. Mildred Lake Extension Project Volume 3 – EIA Appendices December 2014

Appendix B4 – Page 1

Baseline Year 2014 Mining Equipment Sound Power Levels

Source Source Type

Quantity Octave Spectrum (dB) Overall

Sound Power (dBA)

Overall Sound Power

(dB) Reference

31.5 63 125 250 500 1000 2000 4000 8000

MLXN CAT 777 Reclaim Hauling 2014 Moving Line

1 127.7 127.7 134.7 129.7 129.7 130.7 128.7 118.7 111.7 134.6 139.0 1

MLXN CAT 793 Cake Hauling 2014 Moving Line

1 130.7 133.7 134.7 131.7 127.7 123.7 119.7 116.7 112.7 130.0 139.5 2

MLXN CAT 793 Ore Hauling 2014 Moving Line

1 126.8 130.8 131.8 127.8 123.8 120.8 116.8 113.8 108.8 126.6 136.3 2

MLXN CAT 793 Over Burden Hauling 2014 Moving Line

1 129.2 133.2 134.2 130.2 126.2 123.2 119.2 116.2 111.2 129.0 138.7 2

MLXN CAT 797 Ore Haul Empty 2014 Moving Line

1 125.5 125.5 128.5 128.5 123.5 123.5 121.5 116.5 111.5 128.5 134.5 1

MLXN CAT 797 Ore Haul Loaded 2014 Moving Line

1 126.6 130.6 131.6 127.6 124.6 123.6 120.6 114.6 106.6 128.3 136.3 1

MLXN CAT 24M Ore 2014 Area5 116 110.6 114.6 117.6 121.6 119.6 114.6 111.6 106.6 104.6 120.9 125.9 1

MLXN CAT 24M Ore IDLE 2014 Area5 116 109.7 102.7 106.7 103.7 103.7 102.7 99.7 88.7 80.7 106.8 113.7 2

MLXN CAT 24M Overburden 2014 Area5 116 110.6 114.6 117.6 121.6 119.6 114.6 111.6 106.6 104.6 120.9 125.9 1

MLXN CAT 24M Overburden Idle 2014 Area5 116 109.7 102.7 106.7 103.7 103.7 102.7 99.7 88.7 80.7 106.8 113.7 2

MLXN CAT 993 Reclaim Loader 2014 Area 136 113.1 115.1 129.1 127.1 118.1 117.1 116.1 109.1 101.1 123.8 131.9 3

MLXN CAT D11 Ore 2014 Area5 76 115.3 114.3 116.3 114.3 108.3 108.3 106.3 104.3 101.3 114.0 121.8 1

MLXN CAT D11 Ore Idle 2014 Area5 76 123.9 118.9 114.9 103.9 105.9 105.9 100.9 93.9 83.9 109.6 125.7 2

MLXN CAT D11 Overburden 2014 Area5 76 115.3 114.3 116.3 114.3 108.3 108.3 106.3 104.3 101.3 114.0 121.8 2

MLXN CAT D11 Overburden Idle 2014 Area5 76 123.9 118.9 114.9 103.9 105.9 105.9 100.9 93.9 83.9 109.6 125.7 1

MLXN Hitachi EX5600 Hydraulic Ore Mine Shovel 2014

Area5 16 110.3 118.3 124.3 119.3 115.3 114.3 112.3 105.3 90.3 119.5 127.1 4

MLXN Hitachi EX5600 Hydraulic Overburden Mine Shovel 2014

Area5 16 110.3 118.3 124.3 119.3 115.3 114.3 112.3 105.3 90.3 119.5 127.1 4

MLXN P&H 410C Ore Mine Shovel 2014 Area5 106 122.5 121.5 119.5 119.5 117.5 115.5 110.5 105.5 100.5 119.9 127.8 1

MLXN P&H 410C Ore Mine Shovel Idle 2014

Area5 106 108.8 107.8 110.8 105.8 111.8 107.8 103.8 108.8 103.8 114.6 118.0 1

Notes: 1 Measurement of similar equipment at Syncrude Aurora North Mine 2013. 2 RWDI Library measurements from other Alberta oil sands operations. 3 Deer Creek Energy Ltd. Joslyn North Mine Noise Impact Assessment 2005. 4 Whitehaven Coal Ltd. Werris Creek Coal Environmental Management System: Noise Management Plan 2014. 5 Operating time applied to spectra and sound powers. 6 Area source modelled as a single area source, quantity represents number of equipment present in the area source.

Page 18: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Appendix B5

Application Year 2023 Mining Equipment Sound Power Levels

Page 19: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Syncrude Canada Ltd. Mildred Lake Extension Project Volume 3 – EIA Appendices December 2014

Appendix B5 – Page 1

Application Year 2023 Mining Equipment Sound Power Levels

Source Source Type

Quantity Octave Spectrum (dB) Overall

Sound Power(dBA)

Overall Sound Power

(dB) Reference

31.5 63 125 250 500 1000 2000 4000 8000

MLXN CAT 777 Reclaim Hauling 2023 Moving Line

1 119.9 118.9 126.9 121.9 121.9 122.9 120.9 110.9 103.9 126.8 131.1 1

MLXN CAT 793 Cake Hauling 2023 Moving Line

1 128.3 132.3 133.3 130.3 125.3 122.3 118.3 115.3 110.3 128.3 137.9 2

MLXN CAT 793 Ore Hauling 2023 Moving Line

1 124.7 127.7 129.7 125.7 121.7 117.7 114.7 111.7 106.7 124.3 133.9 2

MLXN CAT 793 Overburden Hauling 2023 Moving Line

1 125.3 129.3 130.3 127.3 123.3 119.3 115.3 112.3 108.3 125.6 135.0 2

MLXN CAT 797 Ore Haul Empty 2023 Moving Line

1 127.8 127.8 130.8 130.8 126.8 126.8 123.8 119.8 114.8 131.4 137.0 1

MLXN CAT 797 Ore Haul Loaded 2023 Moving Line

1 128.7 133.7 134.7 130.7 127.7 126.7 122.7 117.7 109.7 131.2 139.3 1

MLXW CAT 777 Reclaim Hauling 2023 Moving Line

1 121.0 120.0 128.0 123.0 123.0 123.0 122.0 112.0 105.0 127.6 132.2 1

MLXW CAT 793 Overburden Hauling 2023 Moving Line

1 129.9 133.9 134.9 131.9 127.9 123.9 119.9 116.9 112.9 130.2 139.6 2

MLXW CAT 797 Ore Haul Empty 2023 Moving Line

1 125.4 125.4 128.4 128.4 123.4 123.4 121.4 116.4 112.4 128.4 134.4 1

MLXW CAT 797 Ore Haul Loaded 2023 Moving Line

1 126.3 130.3 131.3 127.3 125.3 123.3 120.3 114.3 106.3 128.2 136.1 1

MLXN CAT 24M Ore 2023 Area5 46 105.4 109.4 113.4 117.4 115.4 110.4 106.4 102.4 99.4 116.5 121.5 1

MLXN CAT 24M Ore Idle 2023 Area5 46 104.9 98.9 102.9 99.9 99.9 97.9 94.9 84.9 76.9 102.4 109.4 2

MLXN CAT 24M Overburden 2023 Area5 46 105.4 109.4 113.4 117.4 115.4 110.4 106.4 102.4 99.4 116.5 121.5 1

MLXN CAT 24M Overburden Idle 2023 Area5 46 104.9 98.9 102.9 99.9 99.9 97.9 94.9 84.9 76.9 102.4 109.4 2

MLXN CAT 993 Reclaim Loader 2023 Area 26 105.0 107.0 121.0 119.0 110.0 109.0 108.0 101.0 93.0 115.7 123.8 3

MLXN CAT D11 Ore 2023 Area5 96 116.4 115.4 117.4 115.4 109.4 109.4 107.4 105.4 102.4 115.1 122.9 1

MLXN CAT D11 Ore Idle 2023 Area5 96 124.4 119.4 115.4 104.4 106.4 107.4 102.4 94.4 84.4 110.7 126.1 2

MLXN CAT D11 Overburden 2023 Area5 96 116.4 115.4 117.4 115.4 109.4 109.4 107.4 105.4 102.4 115.1 122.9 1

MLXN CAT D11 Overburden Idle 2023 Area5 96 124.4 119.4 115.4 104.4 106.4 107.4 102.4 94.4 84.4 110.7 126.1 2

MLXN Hitachi EX5600 Hydraulic Ore Mine Shovel 2023

Area5 16 110.3 118.3 124.3 119.3 115.3 114.3 112.3 105.3 90.3 119.5 127.1 4

MLXN P&H 410C Ore Mine Shovel 2023 Area5 96 122.5 121.5 119.5 118.5 116.5 115.5 109.5 104.5 99.5 119.4 127.6 1

MLXN P&H 410C Ore Mine Shovel Idle 2023

Area5 96 108.9 107.9 109.9 105.9 111.9 106.9 103.9 107.9 102.9 114.1 117.7 1

MLXW CAT 24M Ore 2023 Area5 116 110.6 114.6 117.6 121.6 119.6 114.6 111.6 106.6 104.6 120.9 125.9 1

Page 20: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Syncrude Canada Ltd. Mildred Lake Extension Project Volume 3 – EIA Appendices December 2014

Appendix B5 – Page 2

Source Source Type

Quantity Octave Spectrum (dB) Overall

Sound Power(dBA)

Overall Sound Power

(dB) Reference

31.5 63 125 250 500 1000 2000 4000 8000

MLXW CAT 24M Ore Idle 2023 Area5 116 109.7 102.7 106.7 103.7 103.7 102.7 99.7 88.7 80.7 106.8 113.7 2

MLXW CAT 24M Overburden 2023 Area5 116 110.6 114.6 117.6 121.6 119.6 114.6 111.6 106.6 104.6 120.9 125.9 1

MLXW CAT 24M Overburden Idle 2023 Area5 116 109.7 102.7 106.7 103.7 103.7 102.7 99.7 88.7 80.7 106.8 113.7 2

MLXW CAT 993 Reclaim Loader 2023 Area 36 106.7 108.7 122.7 120.7 111.7 110.7 109.7 102.7 94.7 117.4 125.5 3

MLXW CAT D11 Ore 2023 Area5 46 112.4 111.4 114.4 111.4 105.4 105.4 104.4 102.4 99.4 111.6 119.3 1

MLXW CAT D11 Ore Idle 2023 Area5 46 121.8 115.8 111.8 101.8 102.8 103.8 98.8 90.8 81.8 107.2 123.3 2

MLXW CAT D11 Overburden 2023 Area5 46 112.4 111.4 114.4 111.4 105.4 105.4 104.4 102.4 99.4 111.6 119.3 1

MLXW CAT D11 Overburden Idle 2023 Area5 46 121.8 115.8 111.8 101.8 102.8 103.8 98.8 90.8 81.8 107.2 123.3 2

MLXW Hitachi EX5600 Hydraulic Ore Mine Shovel 2023

Area5 26 113.3 121.3 127.3 122.3 118.3 117.3 115.3 108.3 93.3 122.5 130.1 4

MLXW Hitachi EX5600 Hydraulic Overburden Mine Shovel 2023

Area5 56 117.3 125.3 131.3 126.3 122.3 121.3 119.3 112.3 97.3 126.5 134.1 4

MLXW P&H 410C Ore Mine Shovel 2023 Area5 26 115.5 114.5 112.5 112.5 110.5 108.5 103.5 98.5 93.5 112.9 120.8 1

MLXW P&H 410C Ore Mine Shovel Idle 2023

Area5 26 101.8 100.8 103.8 98.8 104.8 100.8 96.8 101.8 96.8 107.6 111.0 1

Notes: 1 Measurement of similar equipment at Syncrude Aurora North Mine 2013. 2 RWDI Library measurements from other Alberta oil sands operations. 3 Deer Creek Energy Ltd. Joslyn North Mine Noise Impact Assessment 2005. 4 Whitehaven Coal Ltd. Werris Creek Coal Environmental Management System: Noise Management Plan 2014. 5 Operating time applied to spectra and sound powers. 6 Area source modelled as a single area source, quantity represents number of equipment present in the area source.

Page 21: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Appendix B6

Application Year 2029 Mining Equipment Sound Power Levels

Page 22: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Syncrude Canada Ltd. Mildred Lake Extension Project Volume 3 – EIA Appendices December 2014

Appendix B6 – Page 1

Application Year 2029 Mining Equipment Sound Power Levels

Source Source Type

Quantity Octave Spectrum (dB) Overall

Sound Power(dBA)

Overall Sound Power

(dB) Reference

31.5 63 125 250 500 1000 2000 4000 8000

MLXE CAT 777 Reclaim Hauling 2029 Moving Line

1 121.9 120.9 128.9 123.9 122.9 123.9 121.9 112.9 105.9 128.0 132.9 1

MLXE CAT 793 Ore Hauling 2029 Moving Line

1 121.1 125.1 126.1 122.1 118.1 115.1 111.1 108.1 103.1 120.9 130.6 2

MLXE CAT 793 Overburden Hauling 2029 Moving Line

1 119.4 123.4 124.4 120.4 116.4 113.4 109.4 106.4 101.4 119.2 128.9 2

MLXE CAT 797 Ore Haul Empty 2029 Moving Line

1 125.4 125.4 128.4 128.4 123.4 123.4 121.4 116.4 112.4 128.4 134.4 1

MLXE CAT 797 Ore Haul Loaded 2029 Moving Line

1 126.3 130.3 131.3 127.3 125.3 123.3 120.3 114.3 106.3 128.2 136.1 1

MLXW CAT 777 Reclaim Hauling 2029 Moving Line

1 120.2 119.2 127.2 122.2 121.2 122.2 120.2 111.2 104.2 126.3 131.2 1

MLXW CAT 793 Ore Hauling 2029 Moving Line

1 121.6 125.6 126.6 122.6 118.6 115.6 111.6 108.6 103.6 121.4 131.1 2

MLXW CAT 793 Overburden Hauling 2029 Moving Line

1 122.8 126.8 127.8 124.8 120.8 116.8 112.8 109.8 104.8 123.1 132.5 2

MLXW CAT 797 Ore Haul Empty 2029 Moving Line

1 129.7 128.7 131.7 131.7 127.7 127.7 125.7 120.7 115.7 132.5 138.0 1

MLXW CAT 797 Ore Haul Loaded 2029 Moving Line

1 130.6 134.6 135.6 131.6 128.6 127.6 124.6 118.6 110.6 132.3 140.3 1

MLXE CAT 24M Ore 2029 Area5 36 76.4 80.4 84.4 88.4 85.4 81.4 77.4 73.4 70.4 87.2 92.3 1

MLXE CAT 24M Ore Idle 2029 Area5 36 104.0 98.0 102.0 98.0 98.0 97.0 94.0 83.0 75.0 101.1 108.3 2

MLXE CAT 24M Overburden 2029 Area5 36 104.4 108.4 112.4 116.4 113.4 109.4 105.4 101.4 98.4 115.2 120.3 1

MLXE CAT 24M Overburden Idle 2029 Area5 36 104.0 98.0 102.0 98.0 98.0 97.0 94.0 83.0 75.0 101.1 108.3 2

MLXE CAT 993 Reclaim Loader 2029 Area 16 102.0 104.0 118.0 116.0 107.0 106.0 105.0 98.0 90.0 112.7 120.8 3

MLXE CAT D11 Ore 2029 Area5 36 111.6 110.6 112.6 110.6 104.6 104.6 102.6 100.6 98.6 110.4 118.2 1

MLXE CAT D11 Ore Idle 2029 Area5 36 119.7 114.7 110.7 99.7 101.7 102.7 97.7 89.7 80.7 106.0 121.4 2

MLXE CAT D11 Overburden 2029 Area5 36 111.6 110.6 112.6 110.6 104.6 104.6 102.6 100.6 98.6 110.4 118.2 1

MLXE CAT D11 Overburden Idle 2029 Area5 36 119.7 114.7 110.7 99.7 101.7 102.7 97.7 89.7 80.7 106.0 121.4 2

MLXE Hitachi EX5600 Hydraulic Ore Mine Shovel 2029

Area5 36 114.3 122.3 129.3 124.3 120.3 119.3 116.3 110.3 95.3 124.3 132.0 4

MLXE Hitachi EX5600 Hydraulic Overburden Mine Shovel 2029

Area5 26 113.3 121.3 127.3 122.3 118.3 117.3 115.3 108.3 93.3 122.5 130.1 4

MLXE P&H 410C Ore Mine Shovel 2029 Area5 36 117.2 116.2 114.2 114.2 112.2 110.2 105.2 99.2 94.2 114.6 122.5 1

MLXE P&H 410C Ore Mine Shovel Idle 2029

Area5 36 103.8 102.8 105.8 100.8 106.8 101.8 98.8 103.8 98.8 109.4 112.9 1

Page 23: Appendix B Noise - Alberta · M078 August 16-18, 2011 MLX Process Plant 81.7 79.8 -1.9 462263 6322307 M079 August 16-18, 2011 MLX Process Plant 92.1 91.1 -1.0 462396 6322214 M082

Syncrude Canada Ltd. Mildred Lake Extension Project Volume 3 – EIA Appendices December 2014

Appendix B6 – Page 2

Source Source Type

Quantity Octave Spectrum (dB) Overall

Sound Power(dBA)

Overall Sound Power

(dB) Reference

31.5 63 125 250 500 1000 2000 4000 8000

MLXW CAT 24M Ore 2029 Area5 86 108.2 112.2 116.2 120.2 118.2 113.2 110.2 105.2 103.2 119.5 124.4 1

MLXW CAT 24M Ore Idle 2029 Area5 86 107.5 101.5 105.5 102.5 102.5 101.5 97.5 87.5 79.5 105.4 112.1 2

MLXW CAT 24M Overburden 2029 Area5 86 108.2 112.2 116.2 120.2 118.2 113.2 110.2 105.2 103.2 119.5 124.4 1

MLXW CAT 24M Overburden Idle 2029 Area5 86 107.5 101.5 105.5 102.5 102.5 101.5 97.5 87.5 79.5 105.4 112.1 2

MLXW CAT 993 Reclaim Loader 2029 Area 26 105.0 107.0 121.0 119.0 110.0 109.0 108.0 101.0 93.0 115.7 123.8 3

MLXW CAT D11 Ore 2029 Area5 86 115.4 114.4 117.4 114.4 108.4 108.4 107.4 105.4 102.4 114.6 122.3 1

MLXW CAT D11 Ore Idle 2029 Area5 86 124.8 118.8 114.8 104.8 105.8 106.8 101.8 93.8 84.8 110.2 126.3 2

MLXW CAT D11 Overburden 2029 Area5 86 115.4 114.4 117.4 114.4 108.4 108.4 107.4 105.4 102.4 114.6 122.3 1

MLXW CAT D11 Overburden Idle 2029 Area5 86 124.8 118.8 114.8 104.8 105.8 106.8 101.8 93.8 84.8 110.2 126.3 2

MLXW Hitachi EX5600 Hydraulic Ore Mine Shovel 2029

Area5 26 113.3 121.3 127.3 122.3 118.3 117.3 115.3 108.3 93.3 122.5 130.1 4

MLXW Hitachi EX5600 Hydraulic Overburden Mine Shovel 2029

Area5 16 110.3 118.3 124.3 119.3 115.3 114.3 112.3 105.3 90.3 119.5 127.1 4

MLXW P&H 410C Ore Mine Shovel 2029 Area5 76 121.4 120.4 118.4 117.4 115.4 114.4 108.4 103.4 98.4 118.3 126.5 1

MLXW P&H 410C Ore Mine Shovel Idle 2029

Area5 76 107.9 106.9 108.9 104.9 110.9 105.9 102.9 106.9 101.9 113.1 116.7 1

Notes: 1 Measurement of similar equipment at Syncrude Aurora North Mine 2013. 2 RWDI Library measurements from other Alberta oil sands operations. 3 Deer Creek Energy Ltd. Joslyn North Mine Noise Impact Assessment 2005. 4 Whitehaven Coal Ltd. Werris Creek Coal Environmental Management System: Noise Management Plan 2014. 5 Operating time applied to spectra and sound powers. 6 Area source modelled as a single area source, quantity represents number of equipment present in the area source.