Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Appendix A – GLNG Environmental authority visible smoke
allowance review, prepared by KBR, dated July 2020
Santos GLNG l PFL 10 EPPG00712213 - Amendment Application l 26 August 2020
KBR Energy Solutions, Consulting
Level 16, 300 Murray Street, Perth, Postal address: Locked Bag #3, 66 St George’s Terrace, Perth Western Australia 6831
www.kbr.com | Tel: +61 8 6444 3000 | ABN No: 91 007 660 317
The future, designed and delivered
GLNG OPERATIONS PTY LTD
GLNG ENVIRONMENTAL AUTHORITY
VISIBLE SMOKE ALLOWANCE REVIEW
THIRD-PARTY REVIEW
July 2020
92201-SAN-RT-A-00001
Revision: 0
REV DATE DESCRIPTION PREPARED CHECKED APPROVED QA
A 26/06/2020 Issued for GLNG Review F den Boer M McLean
B 10/07/2020 Re-issued for GLNG Review F den Boer M McLean
0 15/07/2020 Issued for Use F den Boer M McLean M McLean M McLean
RELIANCE NOTICE
This document is issued pursuant to an Agreement between KBR Pty Ltd and/or its subsidiary or affiliate companies (“KBR”) and GLNG OPERATIONS PTY LTD which agreement
sets forth the entire rights, obligations and liabilities of those parties with respect to the content and use of the document. Reliance by any other party on the contents of the
document shall be at its own risk. KBR makes no warranty or representation, expressed or implied, to any other party with respect to the accuracy, completeness, or usefulness
of the information contained in this document and assumes no liabilities with respect to any other party’s use of or damages resulting from such use of any information,
conclusions or recommendations disclosed in this document.
This document/software contains technical information that is subject to U.S. and any other applicable export control regulations, including restrictions on the export, sale, or
transfer of U.S.-origin items (goods, technology, or software) to sanctioned or embargoed countries, entities, or persons. It may not be exported or re-exported except as
authorized under applicable export control requirements.
92201-SAN-RT-A-00001 Page 2 of 26 Revision: 0
July 2020
CONTENTS
ABBREVIATIONS 3
EXECUTIVE SUMMARY 4
INTRODUCTION 6
BASIS AND ASSUMPTIONS 7
3.1 Plant Flare Facilities 7
3.2 Definitions 7
3.3 LNG Plant Terminology 8
3.4 EA Flare Permit 9
3.5 Flare Ringelmann Readings 10
3.6 Measured Plant Data 10
NORMAL OPERATIONS 12
PLANNED MAINTENANCE 14
MAJOR SHUTDOWN / START-UP 17
PLANT UPSET EVENTS 20
TOTAL VISIBLE SMOKE FLARING ALLOWANCE AND MANAGEMENT 23
8.1 Total Visible Smoke Flaring Events 23
8.2 Comparison to QGC EA Permit 23
8.3 Visible Smoke Flaring Management 24
8.4 EA Permit Definition Recommendations 24
REFERENCES 26
92201-SAN-RT-A-00001 Page 3 of 26 Revision: 0
July 2020
ABBREVIATIONS
APC Advanced Process Control
AS Australian Standard
BOG Boil-Off Gas
DES Department of Environment and Science
EA Environmental Authority
EDP Emergency Depressurisation
ESD Emergency Shutdown
ESDF Emergency Shutdown Inlet Feed
ESDP Emergency Shutdown Process
FG Fuel Gas
GLNG Gladstone Liquified Natural Gas
LNG Liquified Natural Gas
mtpa Millions of tonnes per annum
N2 Nitrogen
NRU Nitrogen Rejection Unit
PCV Pressure Control Valve
PSV Pressure Safety Valve
QCLNG Queensland Curtis Liquified Natural Gas
QGC Queensland Gas Company, operator for QCLNG facility
S Ringelmann Number
SDP Shutdown Process
TIAC Turbine Inlet Air Chilling System
XV Shutdown (Solenoid) Valve
92201-SAN-RT-A-00001 Page 4 of 26 Revision: 0
July 2020
EXECUTIVE SUMMARY
The GLNG facility is equipped with an elevated pipe type flare and from time to time visible smoke is
produced, as a result of maintenance or plant upset operations. GLNG’s EA currently includes provisions for “visible smoke and particulate emissions” (black smoke) during normal operating
conditions, limited to no more than five minutes in any two hour period. However, no quantified
flaring limits have been specified for abnormal operating conditions e.g. planned maintenance, upset
conditions or shutdown / start-up. An allowance for visible smoke emissions during abnormal
operating conditions is required to reflect operating requirements at the LNG plant.
GLNG has undergone an internal exercise to identify operational scenarios which have historically
produced visible smoke emissions from the flare. This has included quantification of the expected
duration and frequency of each event with consideration of mitigation methods already employed at
the LNG plant. GLNG have requested KBR to perform a third-party review and endorsement of the
visible smoke scenarios and mitigations, which is the subject of this report.
GLNG have analysed flaring events from 4 May 2019 to 3 May 2020, as a typical year of operation,
including a major train shutdown and start-up. Events were categorised and visible smoke allowances
given for each type of event. ‘Visible’ smoke for the purposes of this review is smoke with a Ringelmann number greater than 2 occurring in daylight hours, with night-time events excluded. As
part of this review, the events and allowances were reviewed, considering other events which may
occur based on the plant configuration and experience with other plants. Reasonable visible smoke
allowances were given to each type of event, in order to allow safe and efficient plant operation
considering the installed facilities.
The proposed allowances per category of event are summarised in Table 1.1. Most events are of a
duration less than 30 minutes, however an allowance of up to 90 minutes is required in some
instances.
Table 1.1: Visible Smoke Flaring Allowance Summary
Category Events/yr Duration/yr
Normal Operations 0 0
Planned Maintenance 4 160 mins
Major Shutdown / Start-up 4 180 mins
Plant Upsets 7 130 mins
Total 15 470 mins (7.8 hrs)
These allowances are considered reasonable and reflect a balance between enabling safe and efficient
operation of the LNG plant and a strong drive to minimise visible smoke emissions affecting public
visual amenity.
92201-SAN-RT-A-00001 Page 5 of 26 Revision: 0
July 2020
The actual number of visible smoke flaring events will vary significantly from year to year, depending
on the maintenance and shutdown work planned for that year, actual plant experience with
improperly functioning valves or other equipment, and the number of plant upsets experienced.
These tend to be somewhat random in occurrence, and long periods of no upsets may be followed by
several in short succession. The overall proposed visible smoke allowance is considered reasonable to
allow for what may occur in one year, based on the plant recent experience, the level of plant
equipment and complexity and GLNG personnel expertise to manage operations. It is expected that
in many years the actual number and duration of visible smoke events will be less than the total in
Table 1.1, however this may not always be the case.
The neighbouring QGC LNG plant has an amended EA Permit which allows up to 14 events and 7 hours
of visible smoke per year. The totals in Table 1.1 slightly exceed the QGC EA limits. It should be noted
that the estimated allowances are not precise, and are based on what may occur in one year. It is
expected that in many years a reduced allowance will be adequate, and careful sustained
management of flaring activities will allow operation within the QGC EA allowances.
Visible smoke flaring management includes:
• Trip reduction campaign, with every trip investigated and mitigations implemented to
prevent/minimise future trips.
• Transfer of refrigerant to an on-line compressor string (including to the other train if necessary),
rather than flaring.
• High rate flare purge to minimise lingering visible smoke after release of heavier hydrocarbons to
the flare system.
• Strategies to avoid/minimise requirement for plant defrosting outside of major shutdowns.
• Plan simultaneous flaring where feasible from multiple sources rather than separately.
• Plan for necessary flaring at night.
• Defer unplanned flaring till night-time where possible.
92201-SAN-RT-A-00001 Page 6 of 26 Revision: 0
July 2020
INTRODUCTION
The Gladstone LNG (GLNG) plant is located at Curtis Island near Gladstone in Queensland, Australia
and is operated by GLNG Operations Pty Ltd on behalf of Joint Venture Participants including Santos,
PETRONAS, Total and KOGAS. The plant takes gas delivered from onshore gas fields and converts it
into LNG for sale. The plant commenced operation in 2015 and has a nameplate capacity of 7.8 mtpa
in two trains.
GLNG’s EA currently includes provisions for “visible smoke and particulate emissions” (black smoke) during normal operating conditions. However, no time or event flaring limits have been specified for
abnormal operating conditions e.g. planned maintenance, upset conditions, shutdown / start-up, etc.
An allowance for visible smoke emissions during abnormal operating conditions is required to reflect
operating requirements at the LNG plant.
GLNG has undergone an internal exercise to identify operational scenarios which have historically
produced visible smoke emissions from the flare. This has included identification of the expected
duration and frequency of each event with consideration of mitigation methods already employed at
the LNG plant.
GLNG have commissioned KBR to perform an independent third-party review of the visble smoke
events associated with operation of the LNG plant. The scope of the review includes:
• Review of the operating scenarios identified by GLNG and verification to GLNG historical flaring
events;
• Review of the frequency and duration of events; and
• Review of mitigation methods for reduction of visible smoke events.
The scope of the review is limited to visibility aspects of smoke (for public visual amenity impact) and
does not address health or safety aspects.
The purpose of this report is to document the findings of this review.
92201-SAN-RT-A-00001 Page 7 of 26 Revision: 0
July 2020
BASIS AND ASSUMPTIONS
3.1 Plant Flare Facilities
The GLNG plant generally operates with no flaring apart from very minor flare pilots and flare purge
gas. Flaring is required from time to time, in order to safely perform maintenance activities and to
effectively manage plant upset scenarios including start-up, shutdown, trip events, etc.
The GLNG facility is serviced with 4 elevated flares:
• B-1901 Wet flare
• B-1902 Dry flare
• B-1903 Marine / Storage flare
• B-1906 Wet / Dry flare
The Wet, Dry and Wet / Dry flares share a common support structure and ancillaries. The Wet / Dry
flare is a common spare for the Wet and Dry flares and is not normally in use. These flares are elevated
and are subject to generate visible smoke when heavier hydrocarbons are combusted. Visible smoke
results from incomplete oxidation of heavier hydrocarbons, with some generation of carbon
particulates in addition to other combustion products. When flaring feed gas (or methane refrigerant
gas), negligible visible smoke generation is expected, as the feed gas is devoid of heavier hydrocarbons
for the GLNG facility (in contrast to many other LNG facilities). Flaring from the propane or ethylene
refrigerant circuits is expected to result in visible smoke, with some generation of carbon particulates
from these molecules.
The Marine / Storage flare is dedicated to boil-off gas from the LNG storage tanks and from LNG
tankers and associated equipment. This gas is normally essentially all methane, with a small amount
of nitrogen, and burns with a clean flame (Ringelmann number of 0 to 1).
3.2 Definitions
The review is based on Environmental Authority definitions (from Ref. 1 and 2) as follows.
“Normal operating conditions” means the ongoing operation of the LNG plant following commissioning and excludes start-up, shut-down, maintenance or calibration of emission monitoring
devices.
This definition is assumed to exclude ‘upset’ conditions, and LNG ship management is included in
‘normal operating conditions’ (from Ref. 2).
“Flaring event” means an event where flammable gas is combusted through a flare and produces
visible smoke continuously for more than 5 minutes. (Ref. 2).
“Visible smoke” means a visible suspension of carbon or other particles in air measured by a Ringelmann number greater than 2. (Ref. 2)
92201-SAN-RT-A-00001 Page 8 of 26 Revision: 0
July 2020
Ringelmann scores are generally given in whole numbers from 0 (clear) to 5 (black), and therefore by
this definition visible smoke is a smoke intensity of Ringelmann score of 3, 4 or 5. However, quarter
numbers are allowed according to AS 3543 (see Section 3.5), and therefore “greater than 2” can be considered 2.25 or higher.
“Plant maintenance activities” means the maintenance shutdowns (and subsequent start-ups) where
equipment at the plant is inspected and, if needed, repaired or replaced to ensure the ongoing safe
operation of the plant (adapted from Ref. 2).
Based on Ref. 2 EA, flaring events are to be restricted if they occur in daylight hours, with night-time
flaring events being unrestricted. “Daylight hours” means those between sunrise and sunset times as
shown on the Australian Government Geoscience Australia webpage
<http://www.ga.gov.au/geodesy/astro/sunrise.jsp>. (Ref. 2).
From the EA Permit, flaring limits do not apply in the event of an emergency. An “emergency” is defined in Ref. 5, clause 466B as:
An emergency exists if—
(a) either—
(i) human health or safety is threatened; or
(ii) serious or material environmental harm has been or is likely to be caused; and
(b) urgent action is necessary to—
(i) protect the health or safety of persons; or
(ii) prevent or minimise the harm; or
(iii) rehabilitate or restore the environment because of the harm.
Specifically for the purposes of this review, an emergency event is considered to have occurred and
resulted in flaring in situations where the pressure in a system has reached PSV set pressure resulting
in a PSV lifting, or where a hydrocarbon release to atmosphere has occurred from an item of piping
or equipment, and depressurisation to flare is initiated in order to minimise and limit the release to
atmosphere. Events of this nature are not considered as subject to flaring limits.
3.3 LNG Plant Terminology
The GLNG LNG plant consists of two independent parallel processing facilities called trains. Each train
contains the gas processing and liquefaction facilities in order to produce LNG, using three
refrigeration cycles (based on propane, ethylene and methane). Refrigeration cycles are driven by gas
turbine powered compressors, arranged in two strings for each LNG train, with each string consisting
of three gas turbine driven compressors (one each for propane, ethylene and methane). An LNG train
may operate with either one or both strings operational. Each refrigerant compressor contains
multiple stages, operating at distinct pressure levels, in order to maximise plant efficiency.
92201-SAN-RT-A-00001 Page 9 of 26 Revision: 0
July 2020
At natural gas liquefaction temperatures, substances such as water or heavier hydrocarbons will
freeze and will tend to cause blockages within the liquefaction facilities. These substances may
potentially be introduced from the feed gas or when facilities are open to the atmosphere during
maintenance activities, and must be removed to ensure proper operation of the facilities. This is
achieved in a process called defrost (or dry out following maintenance), where warm dry feed gas is
used to vaporise these substances and remove them from the facilities. Defrost gas must be directed
to flare for safe disposal. The defrost procedure may also be used in order to warm up cold sections
of the plant in order to achieve a safe working temperature prior to maintenance activities.
In order to safely conduct intrusive maintenance activities on the LNG train facilities, hydrocarbons
must first be removed. Propane and ethylene refrigerants are transferred as far as practicable to
storage, another train or another compressor string. Remaining vapours need to be flared. Residual
vapour at atmospheric pressure is still hazardous and is purged from the facilities using nitrogen
vapour. Multiple purging steps are required to ensure all affected areas have a safe very low level of
hydrocarbons prior to intrusive maintenance work being conducted. Purged vapours (a mixture of
hydrocarbons and nitrogen) are safely disposed of to the plant flare.
Following completion of intrusive maintenance work, any oxygen which has entered the processing
facilities must be removed, and this is also achieved using a nitrogen purge. When oxygen content is
reduced to a very low level, hydrocarbons may be safely introduced. The first hydrocarbons
introduced may be defrost gas (warm dry feed gas), following which the defrost gas is displaced by
refrigerant in the propane and ethylene circuits.
3.4 EA Flare Permit
3.4.1 Current Regulations
The current EA Permit (Ref. 1) limits visible smoke according to clause B19:
(B19) Visible smoke and particulate emissions must not be permitted for more than five minutes in
any two hour period during normal operating conditions.
This clause is specifically applicable to normal operating conditions, and no specific guidance is given
for limitations associated with maintenance, start-up and shutdown operations. Due to the public
visibility of the flare however, public visual amenity may be affected by visible smoke events, and this
could be limited according to clause J1:
(J1) When the administering authority advises the holder of a complaint alleging environmental
nuisance, the holder must investigate the complaint and advise the administering authority in writing
of the action proposed or undertaken in relation to the complaint.
3.4.2 Visible Smoke Flaring Event
Visible smoke is not currently defined in the GLNG EA Permit. This review is premised on visible smoke
being defined as smoke of intensity greater than Ringelmann number 2, occurring in daylight hours
(from Ref. 2). Flare smoke events occurring at night are not quantified in this report.
92201-SAN-RT-A-00001 Page 10 of 26 Revision: 0
July 2020
The definition of what constitutes ‘an event’ is important to properly quantify visible smoke
occurrences. Some events may result in sporadic flaring, with a valve to flare cycling through open
and closed positions. This should properly be considered as a single event, from a single initiating
cause. This should be clarified in the definitions, such that any allowance is not prematurely and
unreasonably exhausted. A proposed guideline is that: a single event may include multiple instances
of visible smoke appearance, provided that each instance of visible smoke occurs due to the same
underlying cause, discharges through the same valve or flare source and occurs within a two hour
window. (The two hour limit is derived from the criteria used for visible smoke allowance in normal
operations, and is considered a reasonable guideline without being overly restrictive or unlimited).
3.4.3 Visible Smoke in Normal Operations
Note that the current stipulation of EA clause B19 (Visible smoke and particulate emissions must not
be permitted for more than five minutes in any two hour period during normal operating conditions)
is assumed to remain with any revised EA Permit. This clause is not specific to daylight hours, and
therefore could be interpreted to also apply at night-time. Considering visible smoke affecting public
amenity is essentially a daytime issue, it would be reasonable to conclude that night-time flaring from
normal operations is acceptable, and has been assumed for this report.
3.5 Flare Ringelmann Readings
Visible smoke is defined in terms of a Ringelmann number, which is a method commonly used to
assess the opacity of flares and exhausts. The method requires a trained operator and is somewhat
subjective. To obtain consistent results as far as possible, the guidelines in Australian Standard AS
3543 (Ref. 3) should be followed.
The flare should be observed from a location:
• perpendicular to the direction of the plume (wind direction).
• at least 3 stack heights away from the flare base.
• have good lighting (sun at right angles to line of observation).
A video record allows later viewing and assessment of Ringelmann number and durations, which may
not be practicable for an operator required to perform other tasks at the time of flaring. The zoom on
the camera should be such as to obtain a similar reading as a manual standard reading under AS 3543
conditions.
Ringelmann (S) numbers are generally noted in whole numbers, though AS 3543 does allow estimation
to the nearest quarter number in favourable conditions.
3.6 Measured Plant Data
The GLNG plant has been operating for approximately 5 years, and can be considered to be in a stable,
mature operating phase, focused on continuous and incremental improvement and optimisation.
Operations are focused on minimising flaring due to the economic impact (particularly refrigerant is
expensive and main cause of visible smoke flaring) as well as the environmental and societal impact.
92201-SAN-RT-A-00001 Page 11 of 26 Revision: 0
July 2020
Plant flaring data over a period of 1 year from 4 May 2019 to 3 May 2020 has been assessed by GLNG.
This data records the time, duration, intensity (Ringelmann number, S) and cause of the flaring that
occurred. In total, 188 flare entries were recorded. These entries were categorised into the following
categories:
• Normal operations;
• Planned maintenance;
• Major shutdown / start-up; and
• Plant upset events.
For this third-party review, the same categorisation was used, and mostly events were kept in the
same category, with some modifications to stay in line with definitions. Proposed allowances were
reviewed to determine if these were reasonable considering plant experience, possible mitigations
and controls, as well as experience on other plants. Allowances were adjusted in some instances to
better reflect plant requirements in the future. Events which were not experienced by GLNG over the
one year of recorded data, but which have occurred on other LNG plants and could reasonably occur
at GLNG based on the plant configuration, were also noted and added to the listing of possible events.
Note that historical data was assessed by GLNG based on S = 2 or greater. This provides a conservative
basis, as visible smoke is defined as S > 2, and therefore would not include readings of 2. This
conservatism is appropriate considering the subjective nature of smoke intensity readings, and the
possibility of intermediate Ringelmann number readings.
Visible smoke flaring mitigations have been considered for each flaring event according to the
following hierarchy:
1. Avoid /eliminate event occurring.
2. Minimise flaring amount and duration.
3. Perform flaring during night hours.
4. Perform flaring during daylight hours if essential.
This follows the premise that night-time flaring, while undesirable from an operational perspective,
will not be regulated and will not be subject to allowances. Activities resulting in visible smoke flaring
that can reasonably be conducted at night are therefore not given an allowance in the following
sections.
Visible smoke flare mitigation by major plant modifications and capital works is outside the scope of
this review.
92201-SAN-RT-A-00001 Page 12 of 26 Revision: 0
July 2020
NORMAL OPERATIONS
As noted in Section 3.1, visible smoke flaring is generally not expected at the GLNG facility in normal
operations. The events recorded in Table 4.1 have been identified as occurring during normal
operations which may potentially result in visible smoke flaring. Note that short duration flaring (less
than 5 minutes per 2 hours) is not considered to constitute a flaring event (Section 3.4). As per Section
3.4, visible smoke is not permitted in normal operations, and therefore no allowances have been
made, with mitigations required to avoid this occurring. One of the mitigations is to perform flaring
activities at night, and this should be included as an allowable exception in any EA revision.
In the following tables, S is used as abbreviation for Ringlemann number (per Ref. 3.).
Table 4.1: Normal Operation Flare Events
Event Visible Smoke
Allowance Mitigation Comment
Propane Compressor
Start (compressor
casing drain)
0 events/yr Transfer to on-line
compressor string
(depressurise off-line
string).
Minor drainage (after
pressure reduction) will
generally not result in S
> 2.
Start-up at night.
Compressor start would generally be
associated with an upset or major
maintenance operation, however may
be classified as normal operation if
shutdown and start-up for production
planning reasons or minor
maintenance.
Procedure has been developed to
minimise flaring, though total
elimination is not possible.
Ethylene Compressor
Start (pressure
reduction maybe
required)
0 events/yr
Propane reclaimer
operation
0 events/yr
Efficient reclaimer
column operation will
minimise refrigerant
losses and visible smoke
generation. Most light
ends can be removed
with S < 2.
Operated at night
where possible.
Removing non-condensables
associated with a major shutdown
should be considered as part of
shutdown event. Reclaimer operation
for built up non-condensables e.g. N2
from seals or from refrigerant supply
can be considered normal operations.
This is a relatively rare event and can
be planned for night operation.
A leaking exchanger may cause a
significant increase in requirement for
reclaimer operation. This should still
be able to be managed nightly. Other
options e.g. piping to methane loop
could be considered.
Ethylene reclaimer
operation
0 events/yr
Propane refrigerant
delivery via tanker
0 events/yr Frequency of tanker
delivery has been
reduced with
implementation of seal
gas recovery.
Transfer hoses gravity
drained as far as
possible.
Flaring involved to purge transfer
hoses. Propane tankers are required
to be a day activity. Minor (low rate,
short duration) flare smoking as
propane progresses through flare
header, generally S < 2.
92201-SAN-RT-A-00001 Page 13 of 26 Revision: 0
July 2020
Event Visible Smoke
Allowance Mitigation Comment
Ethylene refrigerant
delivery
0 events/yr Requirement minimised
with seal gas recovery.
Night activity.
Fuel Gas (FG) purge to
flare for compressor
restart (where FG
temperature less than
agreed limit)
0 events/yr
Duration expected to be
< 5 minutes Fuel gas purge should be S = 0 to 1
Vapour return line
maintain <0°C (BOG
control valve opening)
0 events/yr Duration expected to be
< 5 minutes BOG flaring should be S = 0 to 1
Gas up / cool down
(warm LNG ship) 0 events/yr
Generally non-visible (S
= 0 to 1)
Flaring of return vapour from the ship
is required until the dewpoint is less
than -90°C.
Generally project ships are used, with
residual LNG essentially methane.
Risk of occasional non-project ships
with significant heavies content in
future, which would result in
significant visible smoke flaring. This
has not occurred at GLNG to date.
This is a risk to be managed with ships
in this condition to be minimised.
Flaring to be conducted at night as far
as possible.
Heavies purge from
propane, ethylene
circuits
0 events/yr Make up refrigerant
specification to
minimise heavies
content.
Plan as night activity.
Possible requirement in future
(reduced purge with seal gas
recovery).
Bleed down pressure
in compressors when
shutdown (for
pressure control, not
part of re-start)
0 events/yr Generally not required
if pressures can be
contained.
Bleed to on-line
compressor string if
possible.
Plan as night activity if
required.
Can be required in some cases where
pressure is building up in compressor
circuit.
As summarised in Table 4.1, normal operation is generally conducted without visible smoke flaring.
Some events as noted in the table may result in minor flaring. Minor daytime visible smoke flaring is
consistent with the GLNG EA Permit clause B19 which allows visible smoke not exceeding 5 minutes
in a 2 hour period for normal operations. Flaring events will be planned to be conducted at night as
far as possible, though there is some risk that longer events will be required in daytime in order to
maintain safe and efficient operations (non-normal operation). This will be considered as a plant upset
event (allowances in Section 7).
92201-SAN-RT-A-00001 Page 14 of 26 Revision: 0
July 2020
PLANNED MAINTENANCE
Planned maintenance includes all ongoing maintenance activities conducted on the LNG facilities to
ensure facilities are kept in a safe, efficient and proper operating state, outside of major shutdown
maintenance periods. These maintenance activities tend to be based on short to medium term
planning resulting from plant condition monitoring, and not from long term planning.
Planned maintenance events will involve visible smoke flaring in order to create a safe working
environment, and events and proposed allowances are summarised in Table 5.1.
Table 5.1: Planned Maintenance Flare Events
Event Visible Smoke
Allowance Mitigations Comments
Project based
maintenance
activities.
Flaring from
depressurisation
where required to
break containment.
0 events/yr
Project work to be
conducted in major
shutdown as far as
practicable (unless part
of a compressor string).
Conduct at night as far
as possible.
Minor project work is planned, and
associated flaring is conducted at
night.
Some risk of carryover work into day
hours.
Valve testing /
stroking / repair.
Flaring from
depressurisation
around valve.
2 events/yr,
40 mins
Valve maintenance
program during major
shutdowns to minimise
work between
shutdowns.
Valve stroking/testing
to be with blocked in
valve as far as possible
to avoid flaring.
Conduct activities at
night (not always
feasible).
Valve testing for the identification of a
passing valve, valve stroking to ensure
valves can act when required (i.e.
does not get stuck) and the planned
repair of known problematic valves.
Multiple valve stroking /
depressurisation to flare may be
required in some instances – should
be classified as 1 flare event.
Ethylene fan bank
internal inspection 0 events/yr
Depressurise to other
compression string.
Coincide with other
compressor
maintenance program
or major shutdown.
Conduct flaring at night.
Ethylene coolers included in
compressor isolations, may require
scheduled or unscheduled inspection
/ repair. To be included with other
compressor activity.
Propane fan bank
internal inspection 0 events/yr
Bank operated warm
prior to isolation to
minimise inventory.
Conduct flaring at night.
Configuration of propane condenser
does not allow each bank to be lined
up to flare, however temporary hoses
may be used for purging. This
requirement can be minimised by
operating bank warm and eliminating
condensed liquid prior to purging.
92201-SAN-RT-A-00001 Page 15 of 26 Revision: 0
July 2020
Event Visible Smoke
Allowance Mitigations Comments
Turbine Inlet Air
Chilling System (TIAC)
maintenance
Flaring where
required to break
containment. For
purging non-
condensables and
potentially for
compressor start-up
0 events/yr
Transfer propane to on-
line machines.
Conduct at night as far
as possible.
TIACs provide additional capacity /
efficiency for the main refrigerant
drivers, and planned shutdowns are
possible whilst maintaining
production.
Some risk of carryover work into day
hours.
General maintenance
for refrigeration units
- XV repair,
inspections, strainer
cleaning, etc. Flaring
to depressurise
equipment to be
worked on.
1 event/yr, 90
mins
Train maintenance
generally planned for
major shutdown.
Conducted at night as
far as practicable.
XV repair may be covered by valve
repair above.
Allows for train shutdowns, with
partial train purging, defrosting.
Only 1 event allowed for, for
carryover from planned night-time
work into the day. Max duration of 90
minutes is reasonable to achieve full
purging (e.g. propane circuit).
P1601 defrost recorded S = 2, cold gas
can sometimes result in higher S
scores, possibly due to residual
refrigerant or accumulated heavies in
the process.
Defrosting as required
for hydrate / heavies
removal
1 event/yr, 30
mins
(One event
also allowed
for in major
shutdown)
Proper operation of mol
sieve beds to minimise
risk of water
accumulation.
Coincide with other
maintenance activity.
Operation at night (risk
of carryover into day).
Accumulation of heavies may be able
to be avoided using a dedicated layer
in the mol sieve beds – could be
considered in future if this is an
ongoing issue.
Operation should be S < 2 for the
main part of the flaring, however will
be higher when heavies are released.
Compressor start-up
after maintenance
activity. Flaring from
casing drains etc..
0 events/yr
Transfer to other string
or train if possible.
Start-up at night.
Similar to compressor start-up in
normal operations.
Can take ~35 mins.
Reclaimer operation
following
maintenance
0 events/yr
(Allowance for
displacement
given in major
shutdown)
Minimise volume of N2
ingress.
Efficient reclaimer
operation.
Operate at night.
May not always be practicable to
restrict to night operation. With
reclaimer properly running, low rate
venting from reclaimer can be
achieved with S < 2.
The total allowance is 4 events per year, with a total duration of 160 minutes.
92201-SAN-RT-A-00001 Page 16 of 26 Revision: 0
July 2020
As in normal operations, no allowance is given for compressor start-up. The main mitigation should
be to transfer fluids from casings drains or excess pressure (if applicable) to another compressor
string. Procedures and minor modifications (e.g. bypass of check valves if required) to allow this
operation should be developed as required. Similarly an allowance is not given for reclaimer operation
as visible smoke should not be produced when this is operated efficiently.
The main mitigation for planned maintenance is to conduct essential flaring events at night as far as
possible. This may become overly restrictive in some cases, e.g. additional requirements are identified
during the day and need to be actioned to ensure safe work can continue. This is addressed under
valve testing / repair.
Historically GLNG have conducted flaring for defrost activities to manage accumulation of
components which may freeze inside equipment, and this requirement can be expected in the future.
It may not always be feasible to conduct this at night, and further work on feed gas treatment
processing to minimise the requirement for this activity may be considered.
Plant equipment in feed gas, LNG storage & loading and methane circuit are generally excluded –
flaring from these areas should be S = 0 to 1. Flaring from these areas may result in S = 2 to 3 in some
cases, as a result of residual heavies in the gas or associated with residual propane (or ethylene) in
the flare lines. At times this can result in visible smoke flaring in excess of 5 minutes and will need to
be carefully monitored. A mitigation method used by the plant is to temporarily increase the flare
purge rate following release of heavier gas / liquids into the flare line. In order to avoid additional
flaring (to reduce visible smoke), nitrogen sweep should be used where possible.
92201-SAN-RT-A-00001 Page 17 of 26 Revision: 0
July 2020
MAJOR SHUTDOWN / START-UP
Major shutdown maintenance is conducted on each LNG train once every 4 years. This involves
complete shutdown of the train, gas freeing of the entire train and internal inspection / maintenance.
This is required for safety mandated inspections, to ensure the plant remains safe, efficient and
operable. As far as possible, preventative maintenance will be conducted during this shutdown, to
minimise the risk of train shutdowns in intervening periods. Flaring is reduced by minimising the
number of shutdowns as far as practicable. This shutdown will typically be over a period of weeks and
is followed by removal of air and moisture which may have entered piping and equipment using
nitrogen followed by defrost gas (dry, warm feed gas). Refrigerants can then be introduced and the
train restarted.
Visible smoke events and allowances are summarised in Table 6.1. Allowances are on a per year basis,
(similar to the QGC EA Permit allowances which are on an annual basis). A major shutdown is not
required every year (typically every second year), and this will result in a greater allowance for
planned maintenance and other events in non-shutdown years.
Table 6.1: Major Shutdown / Start-up Flare Events
Event
Visible smoke
allowance
GLNG request
Mitigations Comments
Propane de-inventory
for a train 0 events
Recovery to online train
minimises flaring
required.
Planned night activity
Ensure all liquid is drained from all
points prior to flaring.
Consider possibility to line up to low
stage in on-line train to allow recovery
of propane vapour.
Propane de-inventory
for a train - purges
1 event/yr
90 minutes
Planned night activity
(risk of carryover to day-
time)
Risk of carryover into day, e.g. if
effective isolation has not been
achieved at all points.
Flare allowance for carryover into day
(share allowance with ethylene). Later
purges with high N2 concentration
should have S < 2. An allowance of 90
minutes for purging of an entire
system is appropriate.
Note that each purge is considered a
separate flaring event due to the time
interval between purges.
Ethylene de-inventory
for a train 0 events
Recovery to online train
minimises flaring
required.
Planned night activity
Consider possibility to line up to low
stage in on-line train.
Ethylene de-inventory
for a train - purges
(incl. in
propane
purge
allowance)
Planned night activity
Risk of carryover into day, e.g. if
effective isolation has not been
achieved at all points. Purging should
be able to be simultaneous with
propane system if planned.
92201-SAN-RT-A-00001 Page 18 of 26 Revision: 0
July 2020
Event
Visible smoke
allowance
GLNG request
Mitigations Comments
Warm up/ defrost (to
allow safe working on
cold equipment)
1 event/yr
30 mins
Mostly at night and with
S = 0 to 1, however may
be periods with S > 2
when accumulated
heavies are displaced.
Not always required (e.g. 2018). Total
expected duration is 18 hours.
Potential to partially warm up using
compressor circulation can be
considered.
Dry out/ defrost to
remove any water
which may have
entered equipment
0 events/yr
Procedures to ensure
water is properly
drained prior to defrost
operations.
Use N2 sweep where
safe to do so during
shutdown.
Plan for night, however
typically extends to
daytime.
Required procedure to remove
moisture prior to restart to ensure
restart can be conducted without
formation of hydrates.
Defrost gas is warm, dry feed gas,
expect S = 0 to 1.
Propane re-inventory
(gas displacement to
remove defrost gas)
1 event/yr
30 mins
Use reclaimer as soon
as possible following
main gas displacement
to minimise refrigerant
loss and visible smoke.
Keep daytime use < 5
mins where possible
(risk of lingering visble
smoke from heavies in
flare line).
Planned night activity
Initial displacement direct to flare,
followed by reclaimer operation for
residual gas removal. May require
multiple valve openings – considered
one event per start-up (per 2 hours).
High system pressures may require
immediate purging to flare (cannot
wait for night-time).
Ethylene re-inventory
(gas displacement to
remove defrost gas)
1 event/yr
30 mins
Cooldown and start-
up 0 events/yr
Flash gas rate to be
maintained within
methane compressor
capacity as far as
possible.
Flaring expected to be S
= 0 to 1 associated with
feed gas
Risk of visible smoke expected to be
low.
In total, 4 visible smoke events are allowed per major shutdown and start-up, with a total of 180
minutes of visible smoke. These are partly associated with the start-up, when gases introduced into
the refrigerant circuit must be purged to prevent excessive pressures being generated and proper
operation of the refrigerant systems. One event associated with over-run of planned night-time
activity into daytime is also allowed. This is reasonable considering the duration required for 5 purges
of the refrigerant circuits in order to achieve a low concentration of hydrocarbons. One event is also
associated with warm-up or defrost, which is similar to the defrost allowance in planned maintenance
(Table 5.1).
92201-SAN-RT-A-00001 Page 19 of 26 Revision: 0
July 2020
Major shutdowns, particularly if extensive internal work is involved, are typically associated with
higher volumes of gas being flared in order to safely manage the transition from a closed, pressurised
refrigerant system to an open, atmospheric system suitable for safe work and then back again.
Managing these transitions with 4 relatively brief periods of daytime flaring will require careful
planning particularly for the shutdown and de-inventory activities, to avoid the requirement for
daytime flaring. The requirement for systems to be opened to atmosphere should be minimised as far
as possible, using risk based inspection and non-intrusive inspection techniques. Systems which have
been opened to atmosphere should be sealed as soon as work is completed and defrost commenced
with N2 if possible.
An allowance of 4 flaring events is associated with specific events, however it is assumed that this
allowance can be used in any combination of events as requirements are not fully predictable and will
change as the particular requirements for each shutdown / start-up materialise.
There is a risk that two major shutdowns occur in one year, though this would not normally be
planned. A second shutdown may occur in case of equipment failure, or may be opportunistic e.g. in
case of enforced shutdown due to gas supply or demand issues. Work on common equipment such
as common flare headers and flare stack may require simultaneous shutdown of both trains. This is
not currently allowed for, and may need to be negotiated at the time (for example transfer of some
allowance from one year to another).
92201-SAN-RT-A-00001 Page 20 of 26 Revision: 0
July 2020
PLANT UPSET EVENTS
Plant upset events occur from time to time and are generally a result of the programmed actions
taken by control or safety systems, not intentionally caused by an operator. They may result from
instrumentation failure, poor response of the control system to a particular event, inadvertent action
by an operator or by maintenance personnel, etc.
Plant upset events do not include emergency events (excluded from flaring limits – see Section 3.2),
which includes events such as gas releases to atmosphere and PSV lifting.
Plant upset events recorded at the GLNG facility and other potential events are summarised in
Table 7.1. Note that for this table, visible smoke allowance in this case covers all recorded events, day
and night and will be adjusted later.
Table 7.1: Plant Upset Flare Events
Event Visible smoke
allowance1 Mitigations Comments
ESDF (black start) 1 event/yr
15 mins Minimise number of
events.
EDP valves not designed
to open for ESD upset,
except for compressor
valves depending on
scenario.
ESD initiation does not necessarily
directly result in flaring, however may
occur due to related events such as
EDP valve opening (e.g. compressors),
PCV opening for rising pressures – to
be minimised by control tuning and
setpoint adjustment.
Flaring required for restart.
ESDP 2events/yr
30 mins
SDP 1 event/yr
15 mins
Minimise number of
events.
Valves to flare not
designed to open on
SDP, system designed to
contain gas.
Most flaring expected to be S = 0 to 1
from methane system. Sometimes
recorded as S = 2
Flaring required for restart
Compressor trip 1 event/yr
15 min
Minimise number of
events.
Flaring minimised when
trip occurs (< 5 mins).
Trip of refrigerant compressors may
result in visible smoke flaring.
Compressor restart may also incur
flaring.
(Event originally based on BOG
compressor trip, with S=3 which is
unlikely to be accurate. Scenario
expanded to consider other
compressors).
Leaking valve /
inadvertent valve
operation - general
0 events/yr
Generally results in non-
visible smoke flaring.
Flaring contained to < 5
mins.
Recorded events occurred on feed gas
/ BOG, with S = 0 to 1. Events on
refrigerant circuits are also possible
(assume covered elsewhere).
Upset during start-up /
start-up following ESD
/ SDP
2events/yr
30 min
Flaring generally
contained to < 5 mins.
Start-up procedure
minimises flaring.
Risk of longer duration events,
complications during restart.
Includes compressor restart allowance
from other events.
92201-SAN-RT-A-00001 Page 21 of 26 Revision: 0
July 2020
Event Visible smoke
allowance1 Mitigations Comments
Emergency
depressurisation /
control valve failure
1 events/yr
20 mins
Flaring contained to < 5
mins (close manual
valve if possible).
Position indicators on
EDP valves to alert
operator.
Valve maintenance
program.
Valve failures generally detected and
isolated quickly.
PSV failure /
premature lifting
1 events/yr
45 mins
Regular PSV
maintenance.
Instrumented
protection systems
minimise occurrence of
PSVs opening.
Spare PSV required to be brought on-
line prior to isolating a PSV – may be
difficult to achieve quickly (also
determination of which PSV is leaking
may take some time). Frequency
expected to be low (< 1/yr).
Upset during LNG ship
loading e.g. off spec
gas, high tank pressure
0 events/yr
Loading procedures,
particularly during
ramp-up, minimise
flaring
BOG flaring generally S = 0 to 1
Gas turbine upset 1 event/yr
15 mins
Minimise number of
events.
Operator response to
minimise durations.
Flaring may result from Unit 16 flash
vessels due to rising pressures.
Generally expect S = 0 to 1 for feed
gas flaring, however can be recorded
as S = 2 on some occasions. Propane,
ethylene gas turbine trips may also
result in flaring.
Repairs for fan bank
leaking tubes 0 events/yr
Planned maintenance /
inspection.
Flaring at night for
purging.
Leak to atmosphere constitutes an
emergency situation, and priority is to
make the situation safe, not on flare
minimisation.
Event relates to flaring due to purging,
i.e. after isolations are achieved. This
should be a planned night-time event.
NRU off-specification 0 events/yr APC / operator training
to minimise upsets
Occurred on numerous occasions,
however S = 0 to 1.
Notes:
1. Includes allowance for day and night-time events.
The total allowance is 10 events/yr to a total of 185 minutes. These events are both day and night-
time, and it is estimated that 70% of these events occur during the daytime (related to higher
personnel activity). This results in a daytime visible smoke allowance of 7 events/yr to a total of 130
minutes. Most events are relatively short duration (~ 15 minutes), however in some cases the duration
is extended due to time for detection and potential complications occurring with the event. PSV
failures are expected to be low frequency. A longer allowance is retained as an annual allowance as
this may occur in a given year, and this allowance also provides for other events which may require
additional time to rectify and end flaring.
92201-SAN-RT-A-00001 Page 22 of 26 Revision: 0
July 2020
Plant upset events cannot be mitigated by planning for night-time operation, and a major mitigation
is avoidance of the event in the first place. GLNG have formed a reliability team tasked with event
investigation and mitigations, and this is appropriate to avoid upsets as far as possible. Each trip event
should be properly investigated, and mitigations implemented to avoid/minimise future occurrences.
92201-SAN-RT-A-00001 Page 23 of 26 Revision: 0
July 2020
TOTAL VISIBLE SMOKE FLARING ALLOWANCE AND MANAGEMENT
8.1 Total Visible Smoke Flaring Events
Based on the event allowances in Sections 4 to 7, the total visible flaring allowance is summarised in
Table 8.1.
Table 8.1: Visible Smoke Flaring Allowance Summary
Category Events/yr Duration/yr
Normal Operations 0 0
Planned Maintenance 4 160 mins
Major Shutdown / Start-up 4 180 mins
Plant Upsets 7 130 mins
Total 15 470 mins (7.8 hrs)
The total number of flare entries over a one year period (4 May 2019 to 3 May 2020) was 188. Many
of these events were at night, or with a non-visible smoke flare (S = 0 to 1). Remaining entries were
further rationalised by further planning events to be conducted at night and revising procedures to
minimise visible smoke flaring, to achieve a final allowance of 15 events. In order to achieve the
proposed visible smoke limits, careful management of operations will be required.
The actual number of visible smoke flaring events will vary significantly from year to year, depending
on the maintenance and shutdown work planned for that year, actual plant experience with
improperly functioning valves or other equipment, and the number of plant upsets experienced.
These tend to be somewhat random in occurrence, and long periods of no upsets may be followed by
several in short succession. The proposed allowances should therefore be seen as indicative of what
may occur and should be flexible to be used for whatever event actually occurs in any given year. The
overall proposed visible smoke allowance is considered reasonable to allow for what may occur in one
year, considering the plant recent experience, the level of plant equipment and complexity and GLNG
personnel expertise to manage operations.
8.2 Comparison to QGC EA Permit
Visible smoke flaring limits have been established for the neighbouring QCLNG facility in their EA
Permit (Ref. 2), in essence clauses B12 and B13:
(B12) Flaring events, except for those resulting from an emergency, occurring outside of normal
operating conditions must not exceed:
a) 7 hours per annum during daylight hours; and
b) 14 times per annum during daylight hours; and
c) 30 minutes of continuous visible smoke during daylight hours except as authorised under condition
(B13).
92201-SAN-RT-A-00001 Page 24 of 26 Revision: 0
July 2020
(B13) Notwithstanding condition (B12)(c), individual flaring events must not exceed 90 minutes of
continuous visible smoke in the following circumstances:
a) A flaring event associated with a plant maintenance activity that was planned to be completed
outside of daylight hours, but was required to be undertaken during daylight hours to ensure the safe
operation of the plant; or
b) A flaring event associated with a plant maintenance activity that was not planned and was required
to be undertaken during daylight hours to ensure the safe operation of the plant.
The key limitations are a maximum of 7 hours (cumulative) of flaring per annum, and no more than
14 times or events. In most cases an individual flaring event should be less than 30 minutes but could
be up to 90 minutes duration in some cases.
The totals in Table 8.1 slightly exceed the QGC EA limits. It should be noted that the estimated
allowances are not precise, and are based on what may occur in one year. It is expected that in many
years a reduced allowance will be adequate, and careful sustained management of flaring activities
will allow operation within the QGC EA allowances.
8.3 Visible Smoke Flaring Management
In order to stay within any visible smoke flaring allowance, mitigations as noted in Sections 4 to 7
should be considered. Visible smoke flaring management includes:
• Trip reduction campaign, with every trip investigated and mitigations implemented to
prevent/minimise future trips.
• Transfer of refrigerant to an on-line compressor string (including to other train if necessary) rather
than flaring.
• High rate flare purge to minimise lingering visible smoke after release of heavier hydrocarbons to
the flare system.
• Strategies to avoid/minimise requirement for plant defrosting outside of major shutdowns.
• Plan simultaneous flaring where feasible from multiple sources rather than separately.
• Plan for necessary flaring at night.
• Defer unplanned flaring till night-time where possible.
8.4 EA Permit Definition Recommendations
It is recommended that any EA Permit revision for GLNG include the following clarifications for
definition of key terms.
1. ‘Normal operating conditions’ should be clarified to exclude ‘upset’ conditions, and include LNG ship management.
2. “Plant maintenance activities” should not be restricted to major shutdowns, and include more
minor plant maintenance. It is recommended to not include ‘major’ in the definition in any EA
Permit revision for GLNG.
92201-SAN-RT-A-00001 Page 25 of 26 Revision: 0
July 2020
3. A single visible smoke flaring event should be clarified as potentially including multiple
instances of visible smoke appearance, provided that each instance of visible smoke occurs
due to the same underlying cause, discharges through the same valve or flare source and
occurs within a two hour window.
4. The current EA stipulation of visible smoke flaring for normal operations limited to a
maximum of 5 minutes in any 2 hours should be clarified as applying in daylight hours only.
92201-SAN-RT-A-00001 Page 26 of 26 Revision: 0
July 2020
REFERENCES
1. Permit, Environmental Protection Act 1994, Environmental Authority EPPG00712213, for GLNG,
11 February 2019.
2. Permit, Environmental Protection Act 1994, Environmental Authority EPPG00711513, for QC LNG
Operating Company Pty Ltd, 29 June 2018.
3. Use of standard Ringelmann and Australian Standard miniature smoke charts, Australian Standard
AS 3543:2014
4. Flare Documentation from GLNG Operations, Received via email from R McLaughlin 6 June 2020,
including EA Amendment Proposal.pdf, EA Amendment Table v1.xlsx and supporting
documentation.
5. Queensland Environmental Protection Act 1994
Appendix B – GLNG: Air Quality Assessment of Dry and Wet
Flares, prepared by Katestone, dated July 2020
Santos GLNG l PFL 10 EPPG00712213 - Amendment Application l 26 August 2020
GLNG: Air Quality Assessment of Dry and
Wet Flares
Prepared for:
Santos
August 2020
Final
Prepared by:
Katestone Environmental Pty Ltd
ABN 92 097 270 276
Ground Floor, 16 Marie Street | PO Box 2217
Milton, Brisbane, Queensland, 4064, Australia
www.katestone.global
Ph +61 7 3369 3699
Disclaimer
https://katestone.global/report-disclaimer/
Copyright
This document, electronic files or software are the copyright property of Katestone Environmental Pty. Ltd. and the information contained therein is solely for the use of the authorised recipient and may not be used, copied or reproduced in whole or part for any purpose without the prior written authority of Katestone Environmental Pty. Ltd. Katestone Environmental Pty. Ltd. makes no representation, undertakes no duty and accepts no responsibility to any third party who may use or rely upon this document, electronic files or software or the information contained therein.
© Copyright Katestone Environmental Pty. Ltd.
Document Control
Deliverable #: D19116-3
Title: GLNG: Air Quality Assessment of Dry and Wet Flares
Version: 1.0 (Final)
Client: Santos
Document reference: D19116-3_Santos_GLNG_Flare.docx
Prepared by:
Reviewed by:
Approved by:
04/08/2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page i
Contents
Executive Summary ........................................................................................................................................ v 1. Introduction ....................................................................................................................................... 1 2. Dry and wet gas flares ..................................................................................................................... 2
2.1 Overview ............................................................................................................................................. 2
2.2 Air pollutants........................................................................................................................................ 2
2.3 Scenarios ............................................................................................................................................. 2
2.4 Emissions .............................................................................................................................................. 4
3. Legislative context............................................................................................................................ 8 4. Assessment methodology .............................................................................................................. 10
4.1 Overview ........................................................................................................................................... 10
4.2 Dispersion modelling ......................................................................................................................... 10
4.2.1 Flares .................................................................................................................................. 10
4.2.2 Other plant equipment .................................................................................................... 11
4.2.3 NOx to NO2 conversion .................................................................................................... 12
4.3 Presentation of results ....................................................................................................................... 12
4.4 Cumulative impacts ......................................................................................................................... 14
5. Dispersion modelling results ........................................................................................................... 15 5.1 Flares in isolation ............................................................................................................................... 15
5.2 Flare including background............................................................................................................. 25
6. Conclusions ..................................................................................................................................... 29 7. References ...................................................................................................................................... 31 Appendix A Shutdown/startup scenarios ............................................................................................ 35
A1 Flared gas quantities, mass rates, and duration of events ............................................................ 35
A2 Emissions summary ............................................................................................................................ 39
A3 Other plant equipment .................................................................................................................... 41
Appendix B Meteorological and dispersion modelling methodology............................................. 43 B1 Development of site-specific meteorology .................................................................................... 43
B1.1 TAPM meteorological simulations .................................................................................... 43
B1.2 CALMET meteorological simulations................................................................................ 44
B2 CALPUFF dispersion modelling methodology ................................................................................. 45
B2.1 Model configuration ......................................................................................................... 45
B2.2 Other plant source characteristics .................................................................................. 45
Appendix C – Dispersion modelling results ................................................................................................. 47
Tables
Table 1 Major shutdown / startup scenarios ...................................................................................................... 3
Table 2 Emission factors and emission rates for the dry and wet gas flare scenarios ..................................... 4
Table 3 Composition of hydrocarbon emissions from the flare based on US EPA AP-42 emission factors .... 4
Table 4 Emission factors for particulate matter based on Equation 1 - McEwen et al. (2012) ....................... 5
Table 5 Emission factors for PAHs ........................................................................................................................ 5
Table 6 Emission rates of NOx, CO, particulates and total hydrocarbons (g/s) .............................................. 6
Table 7 Emission rates of PAHs (g/s) .................................................................................................................... 7
Table 8 Ambient air quality objectives (Air EPP) ................................................................................................ 8
Table 9 Relevant ambient air quality objectives and standards for hydrocarbons ....................................... 9
Table 10 Source characteristics for each dispersion modelling scenario ....................................................... 10
Table 11 Other plant equipment included in the assessment .......................................................................... 11
Table 12 Location of sensitive receptors ............................................................................................................ 12
Table 13 Background concentrations used in modelling assessment ............................................................. 14
Table 14 Predicted ground-level concentrations of NO2, CO, particulates and hydrocarbons due to Scenario
1 (flare in isolation) ................................................................................................................................ 16
Table 15 Predicted ground-level concentrations of PAHs due to Scenario 1 (flare in isolation) ................... 17
Table 16 Predicted ground-level concentrations of NO2, CO, particulates and hydrocarbons due to Scenario
2 (flare in isolation) ................................................................................................................................ 19
Table 17 Predicted ground-level concentrations of PAHs due to Scenario 1 (flare in isolation) ................... 20
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page ii
Table 18 Predicted ground-level concentrations of NO2, CO, particulates and hydrocarbons due to Scenario
3 (flare in isolation) ................................................................................................................................ 22 Table 19 Predicted ground-level concentrations of PAHs due to Scenario 1 (flare in isolation) ................... 23 Table 20 Predicted cumulative impacts of NO2, CO, PM10 and PM2.5 for Scenario 1 ..................................... 26 Table 21 Predicted cumulative impacts of NO2, CO, PM10 and PM2.5 for Scenario 2 ..................................... 27 Table 22 Predicted cumulative impacts of NO2, CO, PM10 and PM2.5 for Scenario 3 ..................................... 28
Table A1 Major shutdown/start up and upset scenarios (1) ............................................................................. 35 Table A2 Major shutdown/start up and upset scenarios (2) ............................................................................. 36 Table A3 Major shutdown/start up and upset scenarios (3) ............................................................................. 37 Table A4 Major shutdown/start up and upset scenarios (4) ............................................................................. 38 Table A5 Major shutdown/start up and upset scenarios (5) ............................................................................. 39 Table A6 Summary of other plant equipment .................................................................................................... 41 Table A7 Stack characteristics of GLNG Plant included in the assessment ..................................................... 46
Table C1 Predicted concentrations of NO2, CO and PM10/PM2.5 in isolation, with plant and with plant and
background for Scenario 1 .................................................................................................................. 48 Table C2 Predicted concentrations of NO2, CO and PM10/PM2.5 in isolation, with plant and with plant and
background for Scenario 2 .................................................................................................................. 49 Table C3 Predicted concentrations of NO2, CO and PM10/PM2.5 in isolation, with plant and with plant and
background for Scenario 3 .................................................................................................................. 50
Figures
Figure 1 GLNG and sensitive receptors ............................................................................................................. 13
Figure A1 Summary of emission rates for all flare scenarios considered ........................................................... 40
Contour Plates
Plate 1 Predicted maximum 1-hour average ground level concentrations of NO2 due to Scenario 1 – 2019
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
in isolation) ............................................................................................................................................ 32 Plate 2 Predicted maximum 8-hour average ground level concentrations of CO due to Scenario 1 – 2019
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
in isolation) ............................................................................................................................................ 33 Plate 3 Predicted maximum 24-hour average ground level concentrations of PM due to Scenario 1 – 2019
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
in isolation) - all PM10 is assumed to be PM2.5 ...................................................................................... 34
Plate C1 Predicted maximum 1-hour average ground level concentrations of NO2 due to Scenario 1 – 2019
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
in isolation) ............................................................................................................................................ 52 Plate C2 Predicted maximum 1-hour average ground level concentrations of NO2 due to Scenario 1 – 2019
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
+ GLNG plant + GAMS background) .................................................................................................. 53 Plate C3 Predicted maximum 8-hour average ground level concentrations of CO due to Scenario 1 – 2019
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
in isolation) ............................................................................................................................................ 54 Plate C4 Predicted maximum 8-hour average ground level concentrations of CO due to Scenario 1 – 2019
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
+ GLNG plant + ambient background) .............................................................................................. 55 Plate C5 Predicted maximum 24-hour average ground level concentrations of PM due to Scenario 1 – 2019
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
in isolation). All PM10 is assumed to be PM2.5. ..................................................................................... 56 Plate C6 Predicted maximum 24-hour average ground level concentrations of PM10 due to Scenario 1 – 2019
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
+ GLNG plant + ambient background) .............................................................................................. 57
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page iii
Plate C7 Predicted maximum 24-hour average ground level concentrations of PM2.5 due to Scenario 1 – 2019
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
+ GLNG plant + ambient background) .............................................................................................. 58 Plate C8 Predicted maximum 1-hour average ground level concentrations of fluoranthene due to Scenario 1
– 2019 major shutdown: single train propane system de-inventory for planned maintenance activities
(flare in isolation)................................................................................................................................... 59 Plate C9 Predicted maximum 1-hour average ground level concentrations of propylene due to Scenario 1 –
2019 major shutdown: single train propane system de-inventory for planned maintenance activities
(flare in isolation)................................................................................................................................... 60 Plate C10 Predicted maximum 1-hour average ground level concentrations of NO2 due to Scenario 2 – 2016
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
in isolation) ............................................................................................................................................ 61 Plate C11 Predicted maximum 1-hour average ground level concentrations of NO2 due to Scenario 2 – 2016
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
+ GLNG plant + GAMS background) .................................................................................................. 62 Plate C12 Predicted maximum 8-hour average ground level concentrations of CO due to Scenario 2 – 2016
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
in isolation) ............................................................................................................................................ 63 Plate C13 Predicted maximum 8-hour average ground level concentrations of CO due to Scenario 2 – 2016
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
+ GLNG plant + ambient background) .............................................................................................. 64 Plate C14 Predicted maximum 24-hour average ground level concentrations of PM due to Scenario 2 – 2016
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
in isolation). All PM10 is assumed to be PM2.5. ...................................................................................... 65 Plate C15 Predicted maximum 24-hour average ground level concentrations of PM10 due to Scenario 2 – 2016
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
+ GLNG plant + ambient background) .............................................................................................. 66 Plate C16 Predicted maximum 24-hour average ground level concentrations of PM2.5 due to Scenario 2 – 2016
major shutdown: single train propane system de-inventory for planned maintenance activities (flare
+ GLNG plant + ambient background) .............................................................................................. 67 Plate C17 Predicted maximum 1-hour average ground level concentrations of fluoranthene due to Scenario 2
– 2016 major shutdown: single train propane system de-inventory for planned maintenance activities
(flare in isolation)................................................................................................................................... 68 Plate C18 Predicted maximum 1-hour average ground level concentrations of propylene due to Scenario 2 –
2016 major shutdown: single train propane system de-inventory for planned maintenance activities
(flare in isolation)................................................................................................................................... 69 Plate C19 Predicted maximum 1-hour average ground level concentrations of NO2 due to Scenario 3 – Upset
event: Emergency Depressuring Valve (EDP) valve failed open (flare in isolation) ........................ 70 Plate C20 Predicted maximum 1-hour average ground level concentrations of NO2 due to Scenario 3 – Upset
event: Emergency Depressuring Valve (EDP) valve failed open (flare + GLNG plant + GAMS
background) ......................................................................................................................................... 71 Plate C21 Predicted maximum 8-hour average ground level concentrations of CO due to Scenario 3 – Upset
event: Emergency Depressuring Valve (EDP) valve failed open (flare in isolation) ........................ 72 Plate C22 Predicted maximum 8-hour average ground level concentrations of CO due to Scenario 3 – Upset
event: Emergency Depressuring Valve (EDP) valve failed open (flare + GLNG plant + ambient
background) ......................................................................................................................................... 73 Plate C23 Predicted maximum 24-hour average ground level concentrations of PM due to Scenario 3 – Upset
Train 1 Propane and Ethylene Valves Open to Flare (flare in isolation). All PM10 is assumed to be PM2.5.
............................................................................................................................................................... 74 Plate C24 Predicted maximum 24-hour average ground level concentrations of PM10 due to Scenario 3 – Upset
event: Emergency Depressuring Valve (EDP) valve failed open (flare + GLNG plant + ambient
background) ......................................................................................................................................... 75 Plate C25 Predicted maximum 24-hour average ground level concentrations of PM2.5 due to Scenario 3 –
Upset event: Emergency Depressuring Valve (EDP) valve failed open (flare + GLNG plant + ambient
background) ......................................................................................................................................... 76 Plate C26 Predicted maximum 1-hour average ground level concentrations of fluoranthene due to Scenario 3
– Upset event: Emergency Depressuring Valve (EDP) valve failed open (flare in isolation) ........... 77 Plate C27 Predicted maximum 1-hour average ground level concentrations of propylene due to Scenario 3 –
Upset event: Emergency Depressuring Valve (EDP) valve failed open (flare in isolation) ............. 78
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page iv
Glossary
Term Definition
µg/m3 micrograms per cubic metre
°C degrees Celsius
g/s gram per second
km kilometre
kg PM/103 m3 kilogram of particulate matter per 1000 cubic metres
kg/Sm3 Kilogram per standard cubic metre
m/s metres per second
MJ/hour megajoules per hour
MJ/m3 megajoule per cubic metres
m3/s cubic metres per second
Sm3/h Standard cubic metre per hour
t/h Tons per hour
Nomenclature Definition
CO carbon monoxide
CO2 carbon dioxide
NO2 nitrogen dioxide
NOx oxides of nitrogen
PAHs Polycyclic aromatic hydrocarbons
PM10 particulate matter with a diameter less than 10 micrometres
PM2.5 particulate matter with a diameter less than 2.5 micrometres
Abbreviations Definition
Air EPP Environmental Protection (Air) Policy 2019
DES Department of Environment and Science
EDP Emergency depressurisation
ESDP Emergency shutdown process
GLNG Gladstone Liquid Natural Gas facility
LNG Liquified natural gas
NRU Nitrogen rejection unit
SDP Shutdown process
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page v
EXECUTIVE SUMMARY
Katestone Environmental Pty Ltd (Katestone) was commissioned by Santos to conduct an air quality
assessment associated with the operation of flares at its Gladstone LNG facility (GLNG).
GLNG is operated under Environmental Authority Number EPPG00712213. Schedule B details conditions
relating to air emissions and conditions B16 to B20 relate to flares.
There is a potential for smoke to occur due to flaring at GLNG during planned and unplanned plant maintenance
and emergency situations. Major shutdowns are typically planned to occur once every four years per train.
An air quality assessment was conducted to quantify the emissions associated with the flares when they emit
smoke and the potential impact of those emissions on the receiving environment.
The key air pollutants emitted from the dry and wet gas flares at the GLNG facility were found to be:
• Oxides of nitrogen (NOX)
• Carbon monoxide (CO)
• Hydrocarbons including:
o Methane
o Ethane/ethylene
o Acetylene
o Propane
o Propylene
• Particulate matter in the form of PM2.5 and PM10 (flare gases containing propane and ethylene)
• Polycyclic Aromatic Hydrocarbons (PAHs) (flare gases containing propane and ethylene).
Katestone considered a range of potential emission scenarios and has identified three key scenarios for further
assessment through dispersion modelling. They are as follows:
• Scenario 1 – 2019 major shutdown: single train propane system de-inventory for planned maintenance
activities
• Scenario 2 – 2016 major shutdown: single train propane system de-inventory for planned maintenance
activities
• Scenario 3 – Upset event: Emergency Depressuring Valve (EDP) valve failed open.
These scenarios were identified for detailed dispersion modelling being the scenarios with maximum potential
for impact as:
• Scenario 1 and Scenario 2 represent the worst-case smoking flare scenarios due to the high propane
content associated with shutdown of a train.
• Scenario 3 represents the worst-case methane emissions as a result of an upset.
A conservative dispersion modelling assessment was conducted to determine the potential impacts due to
flaring operations. The assessment is conservative because it is based on the following assumptions:
• All flaring events have been assumed to occur continuously at their maximum intensity for 24-hours.
In reality, a flaring event may occur over a number of minutes or up to 24-hours.
• All other plant and equipment at GLNG operates at the same time as the flaring event. In reality, the
smoke events are typically associated with the shutdown of one processing train and, therefore,
emissions from other plant and equipment will be reduced.
Dispersion modelling of these scenarios found the following:
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page vi
• Predicted ground-level concentrations NO2, CO, PM10 and PM2.5 as well as hydrocarbons were well
below the relevant air quality objectives at all sensitive receptors (including residential receptors and
protected areas).
• Predicted ground-level concentrations of PAHs were well below the relevant air quality objectives at all
sensitive receptors (including residential receptors and protected areas).
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 1
1. INTRODUCTION
Katestone Environmental Pty Ltd (Katestone) was commissioned by Santos to conduct an air quality assessment
associated with the operation of flares at its Gladstone LNG facility (GLNG).
GLNG is operated under Environmental Authority Number EPPG00712213. Schedule B details conditions relating
to air emissions and conditions B16 to B20 relate to flares.
There is a potential for smoke to occur due to flaring at GLNG during planned and unplanned plant maintenance
and emergency situations. Major shutdowns are typically planned to occur once every four years per train. Santos
requires an air quality assessment to quantify the emissions associated with the flares when they emit smoke and
the potential impact of those emissions on the receiving environment.
This report details:
• Operation of the dry and wet gas flares and likely emissions (Section 2)
• Legislative context (Section 3)
• Assessment methodology (Section 4)
• Dispersion modelling results (Section 5)
• Conclusions (Section 6).
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 2
2. DRY AND WET GAS FLARES
2.1 Overview
The principle function of the wet and dry gas flares is to safely dispose of excess gas from the process. The flare
combusts the gases and the products of combustion are emitted to the atmosphere. Flaring occurs in the event of
an area blowdown due to plant maintenance, or due to a plant emergency such as a fire or blocked outlet (e.g.
inadvertent closure of a valve).
Wet and dry gas flares are provided to support the operational and emergency venting requirements of the process
facilities. The wet gas flare system is connected to the front end of the LNG train and typically processes the
blowdown of wet, warm hydrocarbon gases and some refrigerants, while the dry gas flare system is connected to
the rear end of the LNG train and processes the blowdown of dry, cold hydrocarbon gases. A common structure
supports the two flare stacks and a common spare flare stack.
2.2 Air pollutants
The key air pollutants emitted from the dry and wet gas flares at the GLNG facility are as follows:
• Oxides of nitrogen (NOX)
• Carbon monoxide (CO)
• Total hydrocarbons
o Methane
o Ethane/ethylene
o Acetylene
o Propane
o Propylene
• Particulates in the form of PM2.5 and PM10 (flare gases containing propane and ethylene)
• Polycyclic Aromatic Hydrocarbons (PAHs) (flare gases containing propane and ethylene).
The flared gases do not include compounds containing sulfur and, therefore, sulfur related compounds (e.g. sulfur
dioxide) are not likely to be emitted from the flares.
The amount of each pollutant emitted from the flare depends on the amount of and composition of the gas being
flared. A summary of dry and wet gas flare scenarios considered are summarised in Section 2.3.
2.3 Scenarios
Santos conducted a review of the major shutdown/startup and upset scenarios that have occurred over the last
four years. A summary of the major shutdowns and upset scenarios is presented in Appendix A. Three scenarios
were identified for detailed dispersion modelling assessment being the scenarios with maximum potential for
impact. These are summarised in Table 1. The summary includes the mass flow of fuel, expected duration of
flaring and energy content for each flare. These scenarios have been chosen as follows:
• Scenario 1 and Scenario 2 represent the worst-case smoking flare scenarios due to the high propane
content associated with shutdown of a train.
• Scenario 3 represents the worst-case methane emissions as a result of an upset.
Whilst the duration of flaring for Scenarios 1, 2 and 3 is shorter than for other scenarios, their short-term emission
intensity is greatest. To avoid under-estimation of short-term impact potential, all scenarios have been assumed
to occur continuously at their maximum intensity for 24 hours. Therefore, Scenarios 1, 2 and 3 represent worst-
case emissions potential (refer to Section 2.4 and Appendix A).
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
Table 1 Major shutdown / startup scenarios
SANTOS EVENT
Scenario 1 Scenario 2 Scenario 3
EVENT 70 (visible smoke flare event)
2016 - EVENT 1a EVENT 177
2019 major shutdown: single train propane
system de-inventory for planned maintenance
activities
2016 major shutdown: single train propane
system de-inventory for planned maintenance
activities
Upset event: Emergency Depressuring Valve (EDP) valve
failed open
Wet flare
Max Flared Rate (t/h) 37 53 5
Max Flared Rate (Sm3/h) 31,053 44,929 4,533
Max Flared Rate (MJ/h) 1,866,285 - -
Duration (minutes) 276 46 3
Density (kg/Sm3) 1.19 1.19 1.19
Dry flare
Max Flared Rate (t/h) 144 154 249
Max Flared Rate (Sm3/h) 75,802 81,101 358,122
Max Flared Rate (MJ/h) 7,250,461 7,757,326 13,322,138
Duration (minutes) 302 46 61
Density (kg/Sm3) 1.90 1.90 0.70
Marine flare
Max Flared Rate (t/h) - - -
Max Flared Rate (Sm3/h) - - -
Max Flared Rate (MJ/h) - - -
Duration (minutes) - - -
Density (kg/Sm3) - - -
Total flare
Max Flared Rate (t/h) 145 171 249
Max Flared Rate (Sm3/h) 76,309 95,816 358,122
Max Flared Rate (MJ/h) 7,280,942 7,757,326 13,322,138
Duration (minutes) 303 46 63
Density (kg/Sm3) 1.89 1.79 0.70
Waste Gas
Max Flared Rate (t/h) 4 - 21
Max Flared Rate (Sm3/h) 2,206 - 11,320
Max Flared Rate (MJ/h) - - -
Duration (minutes) 303 - 65
Density (kg/Sm3) 1.87 - 1.87
Propane
Max Flared Rate (t/h) 136 149 -
Max Flared Rate (Sm3/h) 71,792 78,477 -
Max Flared Rate (MJ/h) 6.87E+06 7,506,311 -
Duration (minutes) 129 46 -
Density (kg/Sm3) 1.9 1.9 -
Ethylene
Max Flared Rate (t/h) 18 8 -
Max Flared Rate (Sm3/h) 15,258 7,020 -
Max Flared Rate (MJ/h) 917,006 421,890 -
Duration (minutes) 20 46 -
Density (kg/Sm3) 1.19 1.19 -
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 4
2.4 Emissions
Because of their nature, flares cannot be practically measured in the field. Consequently, emission factors have
been employed to estimate emissions. Flare emissions have been based on US EPA AP-42 documents (Chapter
13.5, Industrial Flares), other literature information and information supplied by GLNG. The USEPA AP-42 emission
factors for industrial flares and the emission rates used in the assessment of each of the air pollutants: NOX, CO
and total hydrocarbons (in methane equivalents) are presented in Table 2.
Table 2 Emission factors and emission rates for the dry and wet gas flare scenarios
Parameter Oxides of nitrogen Carbon monoxide Total hydrocarbons1
Emission factor (g/GJ) 29.24 133.29 60.19
Table note:
1 Measured as methane equivalent
The AP-42 emission factors document for industrial flares (chapter 13.5) provides an average distribution by volume
of each hydrocarbon species that contributes to the total hydrocarbon fraction. The speciation of total hydrocarbons
is reproduced in Table 3.
Table 3 Composition of hydrocarbon emissions from the flare based on US EPA AP-42 emission factors
Composition Volume (%)
Average Range
Methane 55 14 - 83
Ethane/Ethylene 8 1 - 14
Acetylene 5 0.3 - 23
Propane 7 0 - 16
Propylene 25 1- 65
Note: The composition presented is an average of a number of test results obtained under the following sets of test conditions: steam-assisted flare using high-Btu-content feed; steam-assisted using low-Btu-content feed; and air assisted flare using low-Btu-content feed. In all tests, “waste” gas was a synthetic gas consisting of a mixture of propylene and propane.
Whilst the USEPA AP-42 emission factors for industrial flares also consider particulate emissions for a range of
flare types, the data cannot be easily related to a mass emission rate. Recent literature (McEwen J.D.N and
Johnson M.R, 2012) has reviewed available particulate matter emission factors for flares and found their accuracy
to be questionable “...or based on measurements not directly relevant to open-atmosphere flares”. McEwen et al. (2012) studied black carbon particulate matter emission factors for gas flares. The study established a relationship
between emissions of particulate matter (kg PM/103 m3 fuel) and volumetric heating value of the fuel (MJ/m3)
(Equation 1).
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 5
𝑬𝑭 𝒔𝒐𝒐𝒕 = 𝟎. 𝟎𝟓𝟕𝟖 (𝑯𝑽) − 𝟐. 𝟎𝟗 Equation 1
Where:
EF is the emission factor (kg PM/103 m3 fuel)
HV is volumetric heating value (MJ/m3)
The work of McEwen et al. (2012) shows that fuels with low volumetric heating values, such as methane, produce
no particulate matter. Whilst, fuels with higher volumetric heating values, such as propane, can produce higher
emission rates of particulate matter. Equation 1 has been used to calculate emission factors for particulate matter
for each of the flaring scenarios based on the composition of flared gases (Table 4).
Table 4 Emission factors for particulate matter based on Equation 1 - McEwen et al. (2012)
Scenario
Volumetric heating value
(MJ/Sm3)
Particulate matter emission factor
(kg PM/103 m3 fuel)
1 2019 major shutdown: single train Propane system de-inventory for planned maintenance activities
Dry flare 95.65 3.44
Wet flare 60.1 1.38
2 2016 major shutdown: single train Propane system de-inventory for planned maintenance activities
Dry flare 95.65 3.44
3 Upset event: Emergency Depressuring Valve (EDP) valve failed open
Dry flare 37.2 0.061
Table note:
1 Methane rich fuel gas such as that to be flared in Scenario 3 is unlikely to produce particulate matter; however, an emission factor has been determined to provide a conservative assessment
Emission rates of PAHs have been derived from the data contained within the Flare Efficiency Study Report,
prepared for US EPA (1983) (EPA-600/2-83-052).
A range of PAHs were measured for flares that were not smoking, lightly smoking and heavily smoking. For this
study, Katestone has taken the maximum measured value across all smoking flare scenarios and used that
emission factor for all flare scenarios. The assessment of PAHs will, therefore, be conservative.
Table 5 presents the emission factors for the individual PAHs that may occur from a flare.
Table 5 Emission factors for PAHs
PAHs Emission factor (µg of pollutant per µg of particulate
matter)
Naphthalene 1.0E-05
Acenaphthylene 3.5E-05
Acenaphthene 1.4E-06
Fluorene 3.4E-06
Phenanthrene 6.2E-05
Anthracene 8.5E-06
Pyrene 9.6E-05
Fluoranthene 1.2E-04
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 6
PAHs Emission factor (µg of pollutant per µg of particulate
matter)
Benzanthracene 2.7E-05
Chrysene 3.2E-05
Benzo(a)pyrene 6.5E-05
1,12 benzoperylene 3.0E-05
The emission rates of NOx, CO, particulates and total hydrocarbons for each flare scenario are presented in Table
6. The emission rates of PAHs for each flare scenario are presented in Table 7. Appendix A2 presents a summary
of emissions for all scenarios considered.
Table 6 Emission rates of NOx, CO, particulates and total hydrocarbons (g/s)
Scenario
Scenario 1 Scenario 2 Scenario 31
2019 major shutdown: single
train propane system de-
inventory for planned
maintenance activities
2016 major shutdown:
single train propane system
de-inventory for planned
maintenance activities
Upset event:
Emergency
Depressuring Valve
(EDP) valve failed open
Dry flare Wet flare Dry flare Dry flare
Carbon monoxide 268 69 218 493
Oxides of nitrogen 59 15 48 108
PM10 72.4 11.9 77.5 6.0
PM2.5 72.4 11.9 77.5 6.0
Total hydrocarbons (as
methane) 121 31 98 223
Methane 67 17 54 123
Ethane/ethylene 18 5 15 33
Acetylene 10 3 8 18
Propane 23 6 19 43
Propylene 80 20 65 146
Table note:
1 Methane rich fuel gas such as that to be flared in Scenario 3 is unlikely to produce particulate matter; however, a
theoretical emission factor based on an extrapolation of McEwen et al. (2012) has been calculated for PM10 and PM2.5 to
provide a conservative assessment
2 Emissions are based on assumption that flare emits continuously for 24-hours
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 7
Table 7 Emission rates of PAHs (g/s)
Scenario
Scenario 1 Scenario 2 Scenario 31
2019 major shutdown: single train propane system de-
inventory for planned maintenance activities2
2016 major shutdown: single train propane system de-inventory
for planned maintenance activities2
Upset Train 1 EDP Valve Failed Open – No Propane and Ethylene Valves Open
to Flare2
Dry flare Wet flare Dry flare Dry flare
Naphthalene 7.4E-04 1.2E-04 7.9E-04 6.1E-05
Acenaphthylene 2.5E-03 4.2E-04 2.7E-03 2.1E-04
Acenaphthene 1.0E-04 1.7E-05 1.1E-04 8.5E-06
Fluorene 2.5E-04 4.1E-05 2.7E-04 2.1E-05
Phenanthrene 4.5E-03 7.4E-04 4.8E-03 3.7E-04
Anthracene 6.1E-04 1.0E-04 6.6E-04 5.1E-05
Pyrene 7.0E-03 1.1E-03 7.4E-03 5.7E-04
Fluoranthene 8.6E-03 1.4E-03 9.2E-03 7.1E-04
Benzanthracene 1.9E-03 3.2E-04 2.1E-03 1.6E-04
Chrysene 2.3E-03 3.8E-04 2.5E-03 1.9E-04
Benzo(a)pyrene 4.7E-03 7.8E-04 5.0E-03 3.9E-04
1,12 benzoperylene 2.2E-03 3.6E-04 2.3E-03 1.8E-04
Table note:
1 Methane rich fuel gas such as that to be flared in Scenario 3 is unlikely to produce particulate matter and therefore is unlikely to produce PAHs; however, to provide a conservative assessment, the particle emissions estimated for these scenarios in Table 7 have been speciated for PAHs
2 Emissions are based on assumption that flare emits continuously for 24-hours
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 8
3. LEGISLATIVE CONTEXT
The Environmental Protection Act 1994 (EP Act) provides for the management of the air environment in
Queensland. The EP Act gives the Department of Environment and Science (DES) the power to create
Environmental Protection Policies that identify, and aim to protect, environmental values of the atmosphere that
are conducive to the health and well-being of humans and biological integrity. The Environmental Protection (Air)
Policy (Air EPP) was made under the EP Act and gazetted in 1997; the Air EPP was revised and reissued in 2019.
The objective of the Air EPP is to identify the environmental values of the air environment to be enhanced or
protected and to achieve the objective of the Environmental Protection Act 1994, i.e. ecologically sustainable
development.
The environmental values to be enhanced or protected under the Air EPP are the qualities of the environment that
are conducive to:
• protecting health and biodiversity of ecosystems
• human health and wellbeing
• protecting the aesthetics of the environment, including the appearance of building structures and other
property
• protecting agricultural use of the environment.
The administering authority must consider the requirements of the Air EPP when it decides an application for an
environmental authority, amendment of a licence or approval of a draft environmental management plan. Schedule
1 of the Air EPP specifies air quality indicators and objectives for contaminants that may be present in the air
environment.
The Air EPP air quality objectives relevant to the key air pollutants that may be generated from the GLNG flares
are presented in Table 8.
Table 8 Ambient air quality objectives (Air EPP)
Pollutant Environmental value Averaging
period
Air quality
objective
(µg/m³)
Number of days
of exceedance
allowed per year
NO2
Health and wellbeing 1-hour 250 1
1-year 62 N/A
Health and biodiversity of
ecosystems 1-year 33 N/A
CO Health and wellbeing 8-hour 11,000 N/A
PM10 Health and wellbeing 24-hour 50 N/A
1-year 25 N/A
PM2.5 Health and wellbeing 24-hour 25 N/A
1-year 8 N/A
In addition to the air pollutants detailed above, the combustion of methane, propane or ethylene in the flares is also
likely to produce small quantities of hydrocarbons. The hydrocarbon emissions likely to be emitted from the flares
are presented in Table 9 with their respective air quality objective. For air quality assessments, it is common
practice to consider, and where appropriate adopt, an air quality objective for a specific substance from another
jurisdiction if information is not available in the Air EPP. As a result, air quality objectives from the following
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 9
guidelines and standards have been adopted where the Air EPP does not provide any assessment criteria for the
hydrocarbons identified in this study:
• National Exposure Standards for Atmospheric Contaminants in the Occupational Environment
(NOHSC:1003(1995))
• Texas Commission on Environmental Quality (TCEQ) Effects Screening Levels 2008.
Table 9 Relevant ambient air quality objectives and standards for hydrocarbons
Indicator Environmental
value
Averaging
period
Air quality
objective or
standard
(µg/m³)
Source
Acenaphthylene
(as acenaphthene) Health 1-hour 1 TCEQ
Acetylene Health 1-hour 26,600 TCEQ
Anthracene Health 1-hour 0.5 TCEQ
Benz(a)anthracene Health 1-hour 0.5 TCEQ
Benzo(g,h,i)perylene Health 1-hour 0.5 TCEQ
Chrysene Health 1-hour 0.5 TCEQ
Dibenzo(a,h)anthracene
(as acenaphthene) Health 1-hour 0.5 TCEQ
Ethane Health 1-hour 12,000 TCEQ
Ethylene (Ethene) Health Simple
Asphyxiant
13.9% by
volume 3
NOHSC:1003 /
TECQ
Fluoranthene
(Benzo(j,k)fluorene) Health 1-hour 0.51 TCEQ
Fluorene Health 1-hour 0.52 TCEQ
Methane Health Simple
Asphyxiant
13.9% by
volume 3
NOHSC:1003 /
TECQ
Phenanthrene Health 1-hour 0.5 TCEQ
Propane Health 1-hour 18,000 TCEQ
Propylene Health 1-hour 8,750 TCEQ
Pyrene Health 1-hour 0.5 TCEQ
1 Air quality objective not found: Fluoranthene (or Benzo(j, k)fluorene) is a polycyclic aromatic hydrocarbon
(PAH) and a structural isomer of the alternant PAH pyrene. Consequently, the same 1-hour average air
quality objective of 0.5 μg/m3 has been applied for this assessment.
2 Air quality objective not found: Fluorene is a PAH, and consequently, in line with other PAHs referenced by
the TCEQ Effects Screening Levels an air quality objective of 0.5 μg/m3 has been applied for this assessment.
3 To maintain oxygen content in air greater than 18% by volume
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 10
4. ASSESSMENT METHODOLOGY
4.1 Overview
4.2 Dispersion modelling
For each scenario identified for dispersion modelling, the flare was modelled explicitly in the dispersion model
CALPUFF. To take into consideration the potential impact from GLNG during each flare scenario, other plant
equipment was also included in the dispersion modelling. The flare characteristics incorporated into the dispersion
modelling and details of other plant equipment are discussed in the sections below. Details of model configuration
are presented in Appendix B.
4.2.1 Flares
Due to the large amount of heat and buoyancy generated by the flare, it cannot be simply modelled as a stack
source. To model the flare emissions appropriately, the US EPA Screen 3 methodology was used to generate the
pseudo stack characteristics (effective height and diameter) for the flare. The source characteristics used in the
dispersion modelling are provided in Table 10.
Table 10 Source characteristics for each dispersion modelling scenario
Parameter Units
Scenario 1 Scenario 2 Scenario 3
2019 major shutdown: single train
propane system de-inventory for
planned maintenance activities
2016 major
shutdown: single
train propane
system de-
inventory for
planned
maintenance
activities
Upset event:
Emergency
Depressuring
Valve (EDP)
valve failed
open
Dry gas flare Wet gas flare Dry gas flare Dry gas flare
value value value value
Peak Energy out GJ hr-1 7,250.5 1,866.3 7,757.3 13,322.1
Energy out GJ/s 2.0 0.5 2.2 3.7
Flare mass rate kg/s 40.0 10.3 42.8 69.1
Gas Density at 0 degrees,
101.3 kPa kg/m3 1.9 1.2 1.9 0.7
Nominal stack height m 100.0 100 100 100
Nominal flare tip diameter m 1.473 0.965 1.473 1.473
Nominal flare tip radius m 0.737 0.483 0.737 0.737
Exit velocity (modelled) m/s 20 20 20 20
Flare release temperature
(modelled) K 1,273 1,273 1,273 1,273
Effective flare height
(modelled) m 164.5 133.7 166.6 186.2
Effective flare diameter
(modelled) m 14.54 7.38 15.04 19.72
Gross heat released (cal/s) cal/s 481,591,829 123,962,845 515,258,887 884,886,179
Net heat released (cal/s) cal/s 216,716,323 55,783,280 231,866,499 398,198,780
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 11
Parameter Units
Scenario 1 Scenario 2 Scenario 3
2019 major shutdown: single train
propane system de-inventory for
planned maintenance activities
2016 major
shutdown: single
train propane
system de-
inventory for
planned
maintenance
activities
Upset event:
Emergency
Depressuring
Valve (EDP)
valve failed
open
Dry gas flare Wet gas flare Dry gas flare Dry gas flare
value value value value
Heat not lost by radiation % 45 45 45 45
4.2.2 Other plant equipment
A conservative assessment has been conducted where it was assumed that the two trains are operating during
each flaring scenario, where in reality for the major shutdowns one train will not be in operation (refer to Appendix
A for overview of operating plant for the various flare scenarios). A summary of other plant equipment included in
the assessment and pollutants emitted from them is summarised in Table 11. The source characteristics and
locations and emission rates are based on data supplied by Santos and are summarised in Appendix B.
Table 11 Other plant equipment included in the assessment
Other plant included in cumulative assessment NOx CO PM10/PM2.5
Train 1
A1 Methane Comp. Driver Stack ✓ ✓ ✓
A2 Methane Comp. Driver Stack ✓ ✓ ✓
A3 Ethylene Comp. Driver Stack ✓ ✓ ✓
A4 Ethylene Comp. Driver Stack ✓ ✓ ✓
A5 Propane Comp. Driver Stack ✓ ✓ ✓
A6 Propane Comp. Driver Stack ✓ ✓ ✓
A7 Waste Gas / Acid Gas / Nit Vents
A8 Hot Oil heater ✓ ✓ ✓
A9 GTG Turbine Driver Stack ✓ ✓ ✓
A10 GTG Turbine Driver Stack ✓ ✓ ✓
A11 GTG Turbine Driver Stack ✓ ✓ ✓
A12 GTG Turbine Driver Stack ✓ ✓ ✓
Train 2
B1 Methane Comp. Driver Stack ✓ ✓ ✓
B2 Methane Comp. Driver Stack ✓ ✓ ✓
B3 Ethylene Comp. Driver Stack ✓ ✓ ✓
B4 Ethylene Comp. Driver Stack ✓ ✓ ✓
B5 Propane Comp. Driver Stack ✓ ✓ ✓
B6 Propane Comp. Driver Stack ✓ ✓ ✓
B7 Waste Gas / Acid Gas / Nit Vents
B8 Hot Oil heater ✓ ✓ ✓
B9 GTG Turbine Driver Stack ✓ ✓ ✓
B10 GTG Turbine Driver Stack ✓ ✓ ✓
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 12
4.2.3 NOx to NO2 conversion
Measurements around power stations in Central Queensland show, under worst possible cases, a conversion of
25-40% of the nitric oxide to nitrogen dioxide occurs within the first ten kilometres of plume travel. During days
with elevated background levels of hydrocarbons (generally originating from bush-fires, hazard reduction burning
or other similar activities), the resulting conversion is usually below 50% in the first thirty kilometres of plume travel
(Bofinger et al 1986).
For this assessment, a conservative ratio of 30% conversion of the NOX to NO2 has been assumed.
4.3 Presentation of results
This assessment provides predictions of nitrogen dioxide, particulate matter less than 10 microns (PM10),
particulate matter less than 2.5 microns (PM2.5), carbon monoxide and hydrocarbon concentrations at sensitive
receptors. Ground-level concentrations are presented for short-term 1-hour and 24-hour averaging periods as the
releases from the flares are expected to range from minutes to up to 24-hours. An assessment against longer term
averaging periods has therefore not been made.
The locations of these receptors are presented in Table 12 and Figure 1. The assessment has also considered
potential impacts at protected areas as shown in Figure 1. The protected areas are as follows:
• Curtis Island National Park
• Curtis Island Conservation Park
• Curtis Island State Forest
• Curtis Island Environmental Management Precinct
• Targinie State Forest.
Table 12 Location of sensitive receptors
Receptor ID Easting (m)a Northing (m)a
Distance (km) and
direction from
receptor to facility
boundary
Orientation from
GLNG Facility
R1 307,206 7371,489 10.0 WNW
R2 307,048 7370,022 9.9 W
R3 307,088 7368,713 9.6 W
R4 307,340 7367,515 9.3 WSW
R5 308,026 7366,635 8.9 WSW
R6 308,162 7365,715 8.9 WSW
R7 311,952 7365,281 5.8 SW
R8 309,092 7361,741 10.2 SW
R9 322,211 7362,744 7.0 SSE
R11 319,653 7366,625 2.4 SSE
R12 320,910 7366,472 3.4 SSE
R13 322,795 7367,791 4.4 SE
R14 323,149 7367,160 5.0 SE
R15 325,103 7366,683 7.0 SE
R16 325,438 7365,648 7.5 SE
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 13
R17 325,396 7373,889 8.2 NE
R18 327,460 7371,898 9.3 ENE
R19 327,781 7371,714 9.5 ENE
R20 328,033 7371,495 9.8 ENE
R21 - QCLNG
accommodation camp 316,449 7370,786 1.0 NW
R22 - APLNG
accommodation camp 316,350 7371,808 2.0 NW
Note a Coordinates in GDA94 MGA55
Contour plots of ground-level concentrations of air contaminants have been used to illustrate the spatial distribution
of pollutant levels as a result of GLNG. Contour plots were created from the CALPUFF model output at each grid
point in the modelling domain, for each model scenario, using a standard interpolation technique.
Figure 1 GLNG and sensitive receptors
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 14
4.4 Cumulative impacts
For the assessment of impacts to air quality associated with NOX emissions, a two-level approach was adopted to
predict the cumulative effect of emissions from the other sources from GLNG and existing, approved and other
potential industrial developments in the Gladstone region. This assessment utilised the Gladstone Airshed
Modelling System Version 3 (GAMSv3), a regional airshed dispersion modelling tool developed by Katestone for
the Department of Infrastructure and Planning for use in planning studies. GAMv3 was used to predict background
levels of NOX.
Background concentrations of CO, PM10 and PM2.5 were based on DES monitoring data in the region. No
background concentrations were assumed for the assessment of hydrocarbons or PAHs in accordance with
conventional practice.
The cumulative impacts for NO2, CO, PM10 and PM2.5 have also been assessed. Table 13 provides a summary of
background levels used in the assessment
Table 13 Background concentrations used in modelling assessment
Pollutant Value Source
NO2
GAMS – existing and approved
industries in the Gladstone region plus
other LNG plants
GAMSv3
CO Modelled GLNG plant plus 250 µg/m3 DES monitoring data from Beacon Avenue, Boyne
Island, 2016
PM10 Modelled GLNG plant plus 36 µg/m3 DES monitoring data average 95th percentile 24-hour
from South Gladstone, 2019
PM2.5 Modelled GLNG plant plus 17.7 µg/m3 DES monitoring data for South Gladstone, 95th
percentile 24-hour average for 2019
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 15
5. DISPERSION MODELLING RESULTS
5.1 Flares in isolation
The results for all flare scenarios modelled are presented in Table 14 to Table 19. The predicted ground-level
concentrations are the maximum predicted and are due to the flare in isolation.
The results show predicted ground-level concentrations of pollutants are well below the relevant air quality
objectives, as follows:
• Maximum 1-hour average ground-level concentrations of NO2 predicted at a receptor less than 3% of the
objective
• Maximum 8-hour average ground-level concentration of CO predicted at a receptor less than 1% of the
objective
• Maximum 24-hour average ground-level concentrations of PM10 predicted at a receptor less than 5% of
the objective
• Maximum 24-hour average ground-level concentrations of PM2.5 predicted at a receptor less than 9% of
the objective
• Maximum 1-hour average ground-level concentrations of hydrocarbons (ethane, ethylene, acetylene,
propane and propylene) predicted at a receptor less than 0.4% of the relevant objectives
• Maximum ground-level concentrations of PAHs are well below (less than 0.7% of) the relevant objectives.
Plate 1 presents contours of the maximum 1-hour average concentrations of NO2 predicted due to Scenario 1 –
2019 major shutdown: single train propane system de-inventory for planned maintenance activities in isolation.
Plate 2 presents contours of the maximum 8-hour average concentrations of CO predicted due to Scenario 1 –
2019 major shutdown: single train propane system de-inventory for planned maintenance activities in isolation.
Plate 3 presents contours of the maximum 24-hour average concentrations of particulates (PM10 and PM2.5)
predicted due to Scenario 1 – 2019 major shutdown: single train propane system de-inventory for planned
maintenance activities in isolation.
Contours of predicted concentrations of NO2, CO, PM10 and PM2.5 for the three scenarios in isolation are presented
in Appendix A. Contours of fluoranthene (the PAH with the highest predicted concentrations relative to air quality
objectives) is also presented for all dry and wet gas scenarios.
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 16
Table 14 Predicted ground-level concentrations of NO2, CO, particulates and hydrocarbons due to Scenario 1 (flare in isolation)
2019 major shutdown: single train propane system de-inventory for planned maintenance
activities
1-hour NO2
8-hour CO
24-hour PM10
24-hour PM2.5
1-hour methane
1-hour ethane/
ethylene
1-hour acetylene
1-hour propane
1-hour propylene
µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3
R1 3.5 12.2 1.0 1.0 13.3 3.6 2.0 4.7 15.8
R2 2.1 15.0 1.3 1.3 8.0 2.2 1.2 2.8 9.5
R3 3.4 9.2 0.8 0.8 13.0 3.5 1.9 4.5 15.5
R4 3.3 8.7 0.7 0.7 12.4 3.4 1.8 4.4 14.9
R5 2.7 9.6 0.8 0.8 10.3 2.8 1.5 3.6 12.3
R6 2.7 11.5 1.0 1.0 10.1 2.8 1.5 3.6 12.1
R7 1.3 6.8 0.5 0.5 4.8 1.3 0.7 1.7 5.8
R8 2.9 6.5 0.5 0.5 10.9 3.0 1.6 3.8 13.1
R9 0.9 4.9 0.4 0.4 3.2 0.9 0.5 1.1 3.9
R11 1.0 3.3 0.3 0.3 3.6 1.0 0.5 1.3 4.3
R12 0.5 3.0 0.3 0.3 2.0 0.5 0.3 0.7 2.3
R13 0.8 3.1 0.3 0.3 3.2 0.9 0.5 1.1 3.8
R14 0.6 2.2 0.2 0.2 2.2 0.6 0.3 0.8 2.6
R15 0.8 3.1 0.3 0.3 3.2 0.9 0.5 1.1 3.8
R16 0.6 2.1 0.2 0.2 2.3 0.6 0.3 0.8 2.7
R17 0.7 2.9 0.3 0.3 2.7 0.7 0.4 0.9 3.2
R18 0.7 3.9 0.3 0.3 2.8 0.8 0.4 1.0 3.4
R19 0.7 3.9 0.3 0.3 2.6 0.7 0.4 0.9 3.1
R20 0.6 3.8 0.3 0.3 2.3 0.6 0.3 0.8 2.8
R21 - QCLNG accommodation camp 0.9 3.4 0.2 0.2 3.5 1.0 0.5 1.2 4.2
R22 - APLNG accommodation camp 1.5 3.6 0.2 0.2 5.7 1.5 0.8 2.0 6.8
Curtis Island National Park 6.5 24.2 2.0 2.0 24.6 6.7 3.6 8.6 29.3
Curtis Island Conservation Park 2.7 9.0 0.8 0.8 10.0 2.7 1.5 3.5 12.0
Curtis Island State Forest 4.5 8.7 0.8 0.8 17.1 4.7 2.5 6.0 20.4
Curtis Island Environmental Management Precinct 7.3 26.2 2.1 2.1 27.6 7.5 4.1 9.7 33.0
Targinie State Forest 3.2 13.3 1.1 1.1 12.2 3.3 1.8 4.3 14.5
Objective 250 11,000 50 25 - 12,000 26,600 18,000 8,750
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 17
Table 15 Predicted ground-level concentrations of PAHs due to Scenario 1 (flare in isolation)
2019 major shutdown: single train propane system de-inventory for planned maintenance activities
Nap
hth
ale
ne
Ace
na
ph
thy
len
e
Ace
na
ph
the
ne
Flu
ore
ne
Ph
en
an
thre
ne
An
thra
ce
ne
Py
ren
e
Flu
ora
nth
en
e
Ben
za
nth
rac
en
e
Ch
rys
en
e
Ben
zo
(a)p
yre
ne
1,1
2
be
nzo
pe
ryle
ne
µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3
R1 1E-04 4E-04 2E-05 4E-05 8E-04 1E-04 1E-03 2E-03 3E-04 4E-04 8E-04 4E-04
R2 9E-05 3E-04 1E-05 3E-05 6E-04 8E-05 9E-04 1E-03 2E-04 3E-04 6E-04 3E-04
R3 1E-04 5E-04 2E-05 5E-05 8E-04 1E-04 1E-03 2E-03 4E-04 4E-04 9E-04 4E-04
R4 1E-04 4E-04 2E-05 4E-05 8E-04 1E-04 1E-03 1E-03 3E-04 4E-04 8E-04 4E-04
R5 1E-04 4E-04 2E-05 4E-05 7E-04 1E-04 1E-03 1E-03 3E-04 4E-04 8E-04 3E-04
R6 1E-04 4E-04 2E-05 4E-05 7E-04 9E-05 1E-03 1E-03 3E-04 3E-04 7E-04 3E-04
R7 5E-05 2E-04 6E-06 2E-05 3E-04 4E-05 4E-04 5E-04 1E-04 1E-04 3E-04 1E-04
R8 1E-04 4E-04 2E-05 4E-05 7E-04 1E-04 1E-03 1E-03 3E-04 4E-04 8E-04 3E-04
R9 3E-05 1E-04 5E-06 1E-05 2E-04 3E-05 3E-04 4E-04 9E-05 1E-04 2E-04 1E-04
R11 3E-05 1E-04 4E-06 1E-05 2E-04 3E-05 3E-04 4E-04 8E-05 1E-04 2E-04 9E-05
R12 1E-05 5E-05 2E-06 5E-06 9E-05 1E-05 1E-04 2E-04 4E-05 4E-05 9E-05 4E-05
R13 4E-05 1E-04 5E-06 1E-05 2E-04 3E-05 3E-04 4E-04 9E-05 1E-04 2E-04 1E-04
R14 2E-05 8E-05 3E-06 8E-06 1E-04 2E-05 2E-04 3E-04 6E-05 7E-05 2E-04 7E-05
R15 3E-05 1E-04 5E-06 1E-05 2E-04 3E-05 3E-04 4E-04 9E-05 1E-04 2E-04 1E-04
R16 2E-05 8E-05 3E-06 8E-06 1E-04 2E-05 2E-04 3E-04 6E-05 7E-05 1E-04 7E-05
R17 3E-05 1E-04 4E-06 1E-05 2E-04 3E-05 3E-04 4E-04 8E-05 9E-05 2E-04 9E-05
R18 3E-05 1E-04 4E-06 1E-05 2E-04 3E-05 3E-04 4E-04 8E-05 1E-04 2E-04 9E-05
R19 3E-05 1E-04 4E-06 1E-05 2E-04 2E-05 3E-04 3E-04 7E-05 9E-05 2E-04 8E-05
R20 3E-05 9E-05 4E-06 9E-06 2E-04 2E-05 2E-04 3E-04 7E-05 8E-05 2E-04 8E-05
R21 - QCLNG accommodation camp 3E-05 9E-05 4E-06 9E-06 2E-04 2E-05 2E-04 3E-04 7E-05 8E-05 2E-04 7E-05
R22 - APLNG accommodation camp 4E-05 1E-04 6E-06 1E-05 3E-04 4E-05 4E-04 5E-04 1E-04 1E-04 3E-04 1E-04
Curtis Island National Park 3E-04 1E-03 4E-05 1E-04 2E-03 2E-04 3E-03 3E-03 7E-04 9E-04 2E-03 8E-04
Curtis Island Conservation Park 1E-04 4E-04 2E-05 4E-05 7E-04 9E-05 1E-03 1E-03 3E-04 3E-04 7E-04 3E-04
Curtis Island State Forest 2E-04 6E-04 3E-05 6E-05 1E-03 2E-04 2E-03 2E-03 5E-04 6E-04 1E-03 5E-04
Curtis Island Environmental Management Precinct
3E-04 1E-03 4E-05 1E-04 2E-03 3E-04 3E-03 4E-03 8E-04 9E-04 2E-03 9E-04
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 18
2019 major shutdown: single train propane system de-inventory for planned maintenance activities
Nap
hth
ale
ne
Ace
na
ph
thy
len
e
Ace
na
ph
the
ne
Flu
ore
ne
Ph
en
an
thre
ne
An
thra
ce
ne
Py
ren
e
Flu
ora
nth
en
e
Ben
za
nth
rac
en
e
Ch
rys
en
e
Ben
zo
(a)p
yre
ne
1,1
2
be
nzo
pe
ryle
ne
µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3
Targinie State Forest 1E-04 5E-04 2E-05 5E-05 9E-04 1E-04 1E-03 2E-03 4E-04 5E-04 9E-04 4E-04
Objective - 1 1 0.52 0.5 0.5 0.5 0.5 0.51 0.5 - 0.5
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 19
Table 16 Predicted ground-level concentrations of NO2, CO, particulates and hydrocarbons due to Scenario 2 (flare in isolation)
2016 major shutdown: single train propane system de-inventory for planned maintenance
activities
1-hour NO2
8-hour CO
24-hour PM10
24-hour PM2.5
1-hour methane
1-hour ethane/
ethylene
1-hour acetylene
1-hour propane
1-hour propylene
µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3
R1 2.4 6.6 0.8 0.8 9.0 2.5 1.3 3.2 10.7
R2 1.5 7.8 0.9 0.9 5.7 1.6 0.8 2.0 6.8
R3 2.0 5.8 0.7 0.7 7.6 2.1 1.1 2.7 9.0
R4 1.6 5.6 0.7 0.7 6.0 1.6 0.9 2.1 7.2
R5 2.2 7.2 0.9 0.9 8.5 2.3 1.3 3.0 10.1
R6 1.8 8.9 1.1 1.1 6.6 1.8 1.0 2.3 7.9
R7 0.5 2.8 0.3 0.3 1.8 0.5 0.3 0.6 2.2
R8 1.9 3.7 0.4 0.4 7.2 2.0 1.1 2.5 8.6
R9 0.5 2.2 0.3 0.3 2.1 0.6 0.3 0.7 2.5
R11 0.2 0.8 0.1 0.1 0.9 0.2 0.1 0.3 1.1
R12 0.1 0.8 0.1 0.1 0.5 0.1 0.1 0.2 0.6
R13 0.7 1.8 0.3 0.3 2.5 0.7 0.4 0.9 3.0
R14 0.4 1.1 0.2 0.2 1.7 0.5 0.2 0.6 2.0
R15 0.4 1.1 0.2 0.2 1.6 0.4 0.2 0.6 2.0
R16 0.3 0.6 0.1 0.1 1.0 0.3 0.1 0.4 1.2
R17 0.5 1.8 0.3 0.3 1.7 0.5 0.3 0.6 2.0
R18 0.6 2.8 0.3 0.3 2.4 0.6 0.4 0.8 2.8
R19 0.6 2.5 0.3 0.3 2.1 0.6 0.3 0.7 2.5
R20 0.5 2.3 0.3 0.3 1.8 0.5 0.3 0.6 2.2
R21 - QCLNG accommodation camp 0.2 0.7 0.2 0.2 0.6 0.2 0.1 0.2 0.7
R22 - APLNG accommodation camp 0.2 0.7 0.2 0.2 0.7 0.2 0.1 0.3 0.9
Curtis Island National Park 1.8 8.8 1.0 1.0 6.7 1.8 1.0 2.3 7.9
Curtis Island Conservation Park 2.1 5.6 0.7 0.7 7.9 2.2 1.2 2.8 9.4
Curtis Island State Forest 3.0 6.0 0.7 0.7 11.4 3.1 1.7 4.0 13.6
Curtis Island Environmental Management Precinct 4.3 15.0 1.8 1.8 16.3 4.4 2.4 5.7 19.4
Targinie State Forest 2.4 8.2 1.0 1.0 9.0 2.5 1.3 3.2 10.8
Objective 250 11,000 50 25 - 12,000 26,600 18,000 8,750
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 20
Table 17 Predicted ground-level concentrations of PAHs due to Scenario 1 (flare in isolation)
2016 major shutdown: single train propane system de-inventory for planned maintenance activities
Nap
hth
ale
ne
Ace
na
ph
thy
len
e
Ace
na
ph
the
ne
Flu
ore
ne
Ph
en
an
thre
ne
An
thra
ce
ne
Py
ren
e
Flu
ora
nth
en
e
Ben
za
nth
rac
en
e
Ch
rys
en
e
Ben
zo
(a)p
yre
ne
1,1
2
be
nzo
pe
ryle
ne
µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3
R1 1E-04 5E-04 2E-05 4E-05 8E-04 1E-04 1E-03 2E-03 3E-04 4E-04 8E-04 4E-04
R2 8E-05 3E-04 1E-05 3E-05 5E-04 7E-05 8E-04 1E-03 2E-04 3E-04 5E-04 2E-04
R3 1E-04 4E-04 2E-05 4E-05 7E-04 9E-05 1E-03 1E-03 3E-04 3E-04 7E-04 3E-04
R4 9E-05 3E-04 1E-05 3E-05 5E-04 7E-05 8E-04 1E-03 2E-04 3E-04 6E-04 3E-04
R5 1E-04 4E-04 2E-05 4E-05 8E-04 1E-04 1E-03 1E-03 3E-04 4E-04 8E-04 4E-04
R6 1E-04 3E-04 1E-05 3E-05 6E-04 8E-05 9E-04 1E-03 3E-04 3E-04 6E-04 3E-04
R7 3E-05 9E-05 4E-06 9E-06 2E-04 2E-05 3E-04 3E-04 7E-05 8E-05 2E-04 8E-05
R8 1E-04 4E-04 1E-05 4E-05 6E-04 9E-05 1E-03 1E-03 3E-04 3E-04 7E-04 3E-04
R9 3E-05 1E-04 4E-06 1E-05 2E-04 3E-05 3E-04 4E-04 8E-05 9E-05 2E-04 9E-05
R11 1E-05 5E-05 2E-06 4E-06 8E-05 1E-05 1E-04 2E-04 3E-05 4E-05 8E-05 4E-05
R12 7E-06 2E-05 1E-06 2E-06 4E-05 6E-06 7E-05 8E-05 2E-05 2E-05 5E-05 2E-05
R13 4E-05 1E-04 5E-06 1E-05 2E-04 3E-05 3E-04 4E-04 9E-05 1E-04 2E-04 1E-04
R14 2E-05 8E-05 3E-06 8E-06 1E-04 2E-05 2E-04 3E-04 6E-05 8E-05 2E-04 7E-05
R15 2E-05 8E-05 3E-06 8E-06 1E-04 2E-05 2E-04 3E-04 6E-05 7E-05 2E-04 7E-05
R16 1E-05 5E-05 2E-06 5E-06 9E-05 1E-05 1E-04 2E-04 4E-05 5E-05 9E-05 4E-05
R17 2E-05 9E-05 3E-06 8E-06 2E-04 2E-05 2E-04 3E-04 6E-05 8E-05 2E-04 7E-05
R18 3E-05 1E-04 5E-06 1E-05 2E-04 3E-05 3E-04 4E-04 9E-05 1E-04 2E-04 1E-04
R19 3E-05 1E-04 4E-06 1E-05 2E-04 3E-05 3E-04 4E-04 8E-05 1E-04 2E-04 9E-05
R20 3E-05 9E-05 4E-06 9E-06 2E-04 2E-05 3E-04 3E-04 7E-05 8E-05 2E-04 8E-05
R21 - QCLNG accommodation camp 9E-06 3E-05 1E-06 3E-06 5E-05 7E-06 8E-05 1E-04 2E-05 3E-05 5E-05 3E-05
R22 - APLNG accommodation camp 1E-05 4E-05 1E-06 4E-06 6E-05 9E-06 1E-04 1E-04 3E-05 3E-05 7E-05 3E-05
Curtis Island National Park 1E-04 3E-04 1E-05 3E-05 6E-04 8E-05 9E-04 1E-03 3E-04 3E-04 6E-04 3E-04
Curtis Island Conservation Park 1E-04 4E-04 2E-05 4E-05 7E-04 1E-04 1E-03 1E-03 3E-04 4E-04 7E-04 3E-04
Curtis Island State Forest 2E-04 6E-04 2E-05 6E-05 1E-03 1E-04 2E-03 2E-03 4E-04 5E-04 1E-03 5E-04
Curtis Island Environmental Management Precinct
2E-04 8E-04 3E-05 8E-05 1E-03 2E-04 2E-03 3E-03 6E-04 7E-04 2E-03 7E-04
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 21
2016 major shutdown: single train propane system de-inventory for planned maintenance activities
Nap
hth
ale
ne
Ace
na
ph
thy
len
e
Ace
na
ph
the
ne
Flu
ore
ne
Ph
en
an
thre
ne
An
thra
ce
ne
Py
ren
e
Flu
ora
nth
en
e
Ben
za
nth
rac
en
e
Ch
rys
en
e
Ben
zo
(a)p
yre
ne
1,1
2
be
nzo
pe
ryle
ne
µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3
Targinie State Forest 1E-04 5E-04 2E-05 4E-05 8E-04 1E-04 1E-03 2E-03 3E-04 4E-04 8E-04 4E-04
Objective - 1 1 0.52 0.5 0.5 0.5 0.5 0.51 0.5 - 0.5
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 22
Table 18 Predicted ground-level concentrations of NO2, CO, particulates and hydrocarbons due to Scenario 3 (flare in isolation)
Upset event: Emergency Depressuring Valve (EDP) valve failed open
1-hour NO2
8-hour CO
24-hour PM10
24-hour PM2.5
1-hour methane
1-hour ethane/
ethylene
1-hour acetylene
1-hour propane
1-hour propylene
µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3
R1 4.3 11.6 0.04 0.04 16.2 4.4 2.4 5.7 19.4
R2 3.5 7.6 0.03 0.03 13.0 3.6 1.9 4.6 15.6
R3 6.7 19.9 0.07 0.07 25.1 6.9 3.7 8.8 30.0
R4 2.6 5.2 0.02 0.02 9.7 2.7 1.4 3.4 11.6
R5 3.5 7.7 0.03 0.03 13.0 3.6 1.9 4.6 15.6
R6 2.4 9.4 0.03 0.03 8.9 2.4 1.3 3.1 10.7
R7 1.0 5.1 0.02 0.02 3.8 1.0 0.6 1.3 4.6
R8 0.9 3.4 0.01 0.01 3.3 0.9 0.5 1.2 4.0
R9 1.1 3.6 0.01 0.01 4.0 1.1 0.6 1.4 4.7
R11 0.4 1.8 0.007 0.007 1.3 0.4 0.2 0.5 1.6
R12 0.2 0.7 0.003 0.003 0.8 0.2 0.1 0.3 0.9
R13 0.3 1.3 0.005 0.005 1.1 0.3 0.2 0.4 1.3
R14 0.3 1.0 0.004 0.004 1.0 0.3 0.1 0.4 1.2
R15 0.3 0.9 0.003 0.003 1.2 0.3 0.2 0.4 1.4
R16 0.2 0.5 0.002 0.002 0.8 0.2 0.1 0.3 0.9
R17 2.2 6.2 0.02 0.02 8.4 2.3 1.2 2.9 10.0
R18 1.5 7.0 0.03 0.03 5.7 1.6 0.8 2.0 6.8
R19 1.4 5.9 0.02 0.02 5.2 1.4 0.8 1.8 6.3
R20 1.3 5.0 0.02 0.02 4.7 1.3 0.7 1.7 5.7
R21 - QCLNG accommodation camp 0.2 0.9 0.003 0.003 0.7 0.2 0.1 0.2 0.8
R22 - APLNG accommodation camp 0.2 0.9 0.003 0.003 0.7 0.2 0.1 0.3 0.9
Curtis Island National Park 5.0 10.0 0.04 0.04 18.9 5.2 2.8 6.6 22.6
Curtis Island Conservation Park 5.1 13.8 0.05 0.05 19.1 5.2 2.8 6.7 22.8
Curtis Island State Forest 4.9 14.2 0.05 0.05 18.7 5.1 2.8 6.6 22.3
Curtis Island Environmental Management Precinct 5.0 13.8 0.05 0.05 18.9 5.2 2.8 6.6 22.6
Targinie State Forest 4.0 15.2 0.06 0.06 15.0 4.1 2.2 5.3 17.9
Objective 250 11,000 50 25 - 12,000 26,600 18,000 8,750
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 23
Table 19 Predicted ground-level concentrations of PAHs due to Scenario 1 (flare in isolation)
Upset event: Emergency Depressuring Valve (EDP) valve
failed open
Nap
hth
ale
ne
Ace
na
ph
thy
len
e
Ace
na
ph
the
ne
Flu
ore
ne
Ph
en
an
thre
ne
An
thra
ce
ne
Py
ren
e
Flu
ora
nth
en
e
Ben
za
nth
rac
en
e
Ch
rys
en
e
Ben
zo
(a)p
yre
ne
1,1
2
be
nzo
pe
ryle
ne
µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3
R1 8E-06 3E-05 1E-06 3E-06 5E-05 7E-06 8E-05 9E-05 2E-05 3E-05 5E-05 2E-05
R2 6E-06 2E-05 9E-07 2E-06 4E-05 5E-06 6E-05 8E-05 2E-05 2E-05 4E-05 2E-05
R3 1E-05 4E-05 2E-06 4E-06 8E-05 1E-05 1E-04 1E-04 3E-05 4E-05 8E-05 4E-05
R4 5E-06 2E-05 7E-07 2E-06 3E-05 4E-06 5E-05 6E-05 1E-05 2E-05 3E-05 1E-05
R5 6E-06 2E-05 9E-07 2E-06 4E-05 5E-06 6E-05 8E-05 2E-05 2E-05 4E-05 2E-05
R6 4E-06 2E-05 6E-07 2E-06 3E-05 4E-06 4E-05 5E-05 1E-05 1E-05 3E-05 1E-05
R7 2E-06 7E-06 3E-07 6E-07 1E-05 2E-06 2E-05 2E-05 5E-06 6E-06 1E-05 6E-06
R8 2E-06 6E-06 2E-07 6E-07 1E-05 1E-06 2E-05 2E-05 4E-06 5E-06 1E-05 5E-06
R9 2E-06 7E-06 3E-07 7E-07 1E-05 2E-06 2E-05 2E-05 5E-06 6E-06 1E-05 6E-06
R11 7E-07 2E-06 9E-08 2E-07 4E-06 6E-07 6E-06 8E-06 2E-06 2E-06 4E-06 2E-06
R12 4E-07 1E-06 5E-08 1E-07 2E-06 3E-07 4E-06 5E-06 1E-06 1E-06 2E-06 1E-06
R13 5E-07 2E-06 8E-08 2E-07 3E-06 5E-07 5E-06 6E-06 1E-06 2E-06 3E-06 2E-06
R14 5E-07 2E-06 7E-08 2E-07 3E-06 4E-07 5E-06 6E-06 1E-06 2E-06 3E-06 1E-06
R15 6E-07 2E-06 8E-08 2E-07 4E-06 5E-07 6E-06 7E-06 2E-06 2E-06 4E-06 2E-06
R16 4E-07 1E-06 5E-08 1E-07 2E-06 3E-07 4E-06 4E-06 1E-06 1E-06 2E-06 1E-06
R17 4E-06 1E-05 6E-07 1E-06 3E-05 3E-06 4E-05 5E-05 1E-05 1E-05 3E-05 1E-05
R18 3E-06 1E-05 4E-07 1E-06 2E-05 2E-06 3E-05 3E-05 7E-06 9E-06 2E-05 8E-06
R19 3E-06 9E-06 4E-07 9E-07 2E-05 2E-06 2E-05 3E-05 7E-06 8E-06 2E-05 8E-06
R20 2E-06 8E-06 3E-07 8E-07 1E-05 2E-06 2E-05 3E-05 6E-06 7E-06 2E-05 7E-06
R21 - QCLNG accommodation camp 3E-07 1E-06 5E-08 1E-07 2E-06 3E-07 3E-06 4E-06 9E-07 1E-06 2E-06 1E-06
R22 - APLNG accommodation camp 4E-07 1E-06 5E-08 1E-07 2E-06 3E-07 3E-06 4E-06 9E-07 1E-06 2E-06 1E-06
Curtis Island National Park 9E-06 3E-05 1E-06 3E-06 6E-05 8E-06 9E-05 1E-04 2E-05 3E-05 6E-05 3E-05
Curtis Island Conservation Park 9E-06 3E-05 1E-06 3E-06 6E-05 8E-06 9E-05 1E-04 2E-05 3E-05 6E-05 3E-05
Curtis Island State Forest 9E-06 3E-05 1E-06 3E-06 6E-05 8E-06 9E-05 1E-04 2E-05 3E-05 6E-05 3E-05
Curtis Island Environmental Management Precinct
9E-06 3E-05 1E-06 3E-06 6E-05 8E-06 9E-05 1E-04 2E-05 3E-05 6E-05 3E-05
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 24
Upset event: Emergency Depressuring Valve (EDP) valve
failed open
Nap
hth
ale
ne
Ace
na
ph
thy
len
e
Ace
na
ph
the
ne
Flu
ore
ne
Ph
en
an
thre
ne
An
thra
ce
ne
Py
ren
e
Flu
ora
nth
en
e
Ben
za
nth
rac
en
e
Ch
rys
en
e
Ben
zo
(a)p
yre
ne
1,1
2
be
nzo
pe
ryle
ne
µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3 µg/m3
Targinie State Forest 7E-06 3E-05 1E-06 3E-06 5E-05 6E-06 7E-05 9E-05 2E-05 2E-05 5E-05 2E-05
Objective - 1 1 0.52 0.5 0.5 0.5 0.5 0.51 0.5 - 0.5
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 25
5.2 Flare including background
Table 20 to Table 22 summarise the cumulative maximum concentrations of NO2, CO, PM10 and PM2.5 for all gas
flare scenarios. Table C1 to Table C3 in Appendix C present the predicted ground-level concentrations for each
modelled dry and wet gas flare scenario as well as a breakdown of predicted concentrations due to flare in isolation,
flare with other plant equipment and flare with other plant equipment plus background.
The results show that the predicted ground-level concentrations NO2, CO, PM10 and PM2.5 are well below the
relevant air quality objectives for all modelled scenarios, as follows:
• Maximum 1-hour average ground-level concentrations of NO2 predicted at a receptor less than 30% of
the objective
• Maximum 8-hour average ground-level concentration of CO predicted at a receptor less than 4% of the
objective
• Maximum 24-hour average ground-level concentrations of PM10 predicted at a receptor less than 84% of
the objective
• Maximum 24-hour average ground-level concentrations of PM2.5 predicted at a receptor less than 94% of
the objective.
Contours of predicted concentrations of NO2, CO, PM10 and PM2.5 including other plant equipment and background
are presented in Appendix C.
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 26
Table 20 Predicted cumulative impacts of NO2, CO, PM10 and PM2.5 for Scenario 1
2019 major shutdown: single train propane
system de-inventory for planned maintenance
activities
1-hour
average
NO2
8-hour
average
CO
24-hour
average
PM10
24-hour
average
PM2.5
µg/m3 µg/m3 µg/m3 µg/m3
R1 43.2 262 37.0 17.7
R2 41.5 265 37.5 17.7
R3 47.5 259 36.8 17.7
R4 48.9 259 36.7 17.7
R5 57.0 260 36.9 17.7
R6 74.5 262 37.0 17.7
R7 67.4 258 36.5 18.2
R8 73.0 257 36.6 18.3
R9 50.9 255 36.4 18.1
R11 40.2 259 36.4 18.1
R12 45.6 256 36.3 18.0
R13 28.5 255 36.3 18.0
R14 30.7 255 36.2 17.9
R15 23.0 255 36.3 18.0
R16 17.5 253 36.2 17.9
R17 27.5 254 36.3 17.9
R18 20.4 255 36.4 18.1
R19 20.0 255 36.4 18.1
R20 20.2 255 36.4 18.1
R21 53.2 271 37.6 19.2
R22 50.6 268 36.9 18.5
Curtis Island National Park 36.0 276 38.0 19.7
Curtis Island Conservation Park 44.8 259 36.8 18.5
Curtis Island State Forest 38.5 260 36.8 18.5
Curtis Island Environmental Management Precinct 75.4 397 42.0 23.6
Targinie State Forest 63.2 264 37.3 19.0
Objective 250 11,000 50 25
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 27
Table 21 Predicted cumulative impacts of NO2, CO, PM10 and PM2.5 for Scenario 2
2016 major shutdown: single train propane
system de-inventory for planned
maintenance activities
1-hour
average
NO2
8-hour
average
CO
24-hour
average
PM10
24-hour
average
PM2.5
µg/m3 µg/m3 µg/m3 µg/m3
R1 43.2 257 37.0 18.7
R2 41.5 258 37.4 19.1
R3 47.5 257 36.9 18.6
R4 48.9 256 36.9 18.5
R5 57.0 258 37.1 18.7
R6 74.5 259 37.4 19.0
R7 67.4 255 36.5 18.1
R8 73.0 254 36.6 18.3
R9 50.9 253 36.4 18.1
R11 40.2 259 36.4 18.1
R12 45.6 256 36.3 17.9
R13 28.5 255 36.3 18.0
R14 30.7 255 36.2 17.9
R15 23.0 254 36.3 18.0
R16 17.5 253 36.2 17.9
R17 27.5 254 36.4 18.0
R18 20.4 253 36.4 18.0
R19 20.0 253 36.4 18.0
R20 20.2 253 36.4 18.0
R21 53.2 271 37.6 19.2
R22 50.6 268 36.9 18.5
Curtis Island National Park 36.0 260 38.2 19.9
Curtis Island Conservation Park 44.8 256 37.0 18.7
Curtis Island State Forest 38.4 257 37.0 18.7
Curtis Island Environmental Management
Precinct 75.4 397 41.9 23.6
Targinie State Forest 63.2 262 37.3 19.0
Objective 250 11,000 50 25
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 28
Table 22 Predicted cumulative impacts of NO2, CO, PM10 and PM2.5 for Scenario 3
Upset event: Emergency Depressuring Valve
(EDP) valve failed open
1-hour
average
NO2
8-hour
average
CO
24-hour
average
PM10
24-hour
average
PM2.5
µg/m3 µg/m3 µg/m3 µg/m3
R1 43.2 262 36.4 17.7
R2 41.5 258 36.2 17.7
R3 47.5 270 36.2 17.7
R4 49.0 255 36.2 17.7
R5 57.0 258 36.1 17.7
R6 74.5 260 36.1 17.7
R7 67.4 256 36.2 17.9
R8 73.0 254 36.1 17.8
R9 50.9 254 36.1 17.8
R11 40.2 259 36.3 18.0
R12 45.6 256 36.3 17.9
R13 28.5 255 36.2 17.9
R14 30.7 255 36.2 17.9
R15 23.0 254 36.2 17.8
R16 17.5 253 36.1 17.8
R17 27.5 256 36.1 17.8
R18 20.4 257 36.1 17.8
R19 20.0 256 36.1 17.8
R20 20.2 255 36.1 17.8
R21 53.2 271 37.6 19.2
R22 50.6 268 36.9 18.5
Curtis Island National Park 36.0 260 36.3 18.0
Curtis Island Conservation Park 44.8 264 36.3 18.0
Curtis Island State Forest 38.4 264 36.3 18.0
Curtis Island Environmental Management Precinct 75.4 397 41.9 23.6
Targinie State Forest 63.2 265.3 36.4 18.1
Objective 250 11,000 50 25
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 29
6. CONCLUSIONS
Katestone Environmental Pty Ltd (Katestone) was commissioned by Santos to conduct an air quality assessment
associated with the operation of flares at its Gladstone LNG facility (GLNG).
GLNG is operated under Environmental Authority Number EPPG00712213. Schedule B details conditions relating
to air emissions and conditions B16 to B20 relate to flares.
There is a potential for smoke to occur due to flaring at GLNG during planned and unplanned plant maintenance
and emergency situations. Major shutdowns are typically planned to occur once every four years per train.
An air quality assessment was conducted to quantify the emissions associated with the flares when they emit
smoke and the potential impact of those emissions on the receiving environment.
The key air pollutants emitted from the dry and wet gas flares at the GLNG facility were found to be:
• Oxides of nitrogen (NOX)
• Carbon monoxide (CO)
• Hydrocarbons including:
o Methane
o Ethane/ethylene
o Acetylene
o Propane
o Propylene
• Particulate matter in the form of PM2.5 and PM10 (flare gases containing propane and ethylene)
• Polycyclic Aromatic Hydrocarbons (PAHs) (flare gases containing propane and ethylene).
Katestone considered a range of potential emission scenarios and has identified three key scenarios for further
assessment through dispersion modelling. They are as follows:
• Scenario 1 – 2019 major shutdown: single train propane system de-inventory for planned maintenance
activities
• Scenario 2 – 2016 major shutdown: single train propane system de-inventory for planned maintenance
activities
• Scenario 3 – Upset event: Emergency Depressuring Valve (EDP) valve failed open.
These scenarios were identified for detailed dispersion modelling being the scenarios with maximum potential for
impact as:
• Scenario 1 and Scenario 2 represent the worst-case smoking flare scenarios due to the high propane
content associated with shutdown of a train.
• Scenario 3 represents the worst-case methane emissions as a result of an upset.
A conservative dispersion modelling assessment was conducted to determine the potential impacts due to flaring
operations. The assessment is conservative because it is based on the following assumptions:
• All flaring events have been assumed to occur continuously at their maximum intensity for 24-hours. In
reality, a flaring event may occur over a number of minutes or up to 24-hours.
• All other plant and equipment at GLNG operate at the same time as the flaring event. In reality, the smoke
events are typically associated with the shutdown of one processing train and, therefore, emissions from
other plant and equipment will be reduced.
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 30
Dispersion modelling of these scenarios found the following:
• Predicted ground-level concentrations NO2, CO, PM10 and PM2.5 as well as hydrocarbons were well below
the relevant air quality objectives at all sensitive receptors (including residential receptors and protected
areas).
• Predicted ground-level concentrations of PAHs were well below the relevant air quality objectives at all
sensitive receptors (including residential receptors and protected areas).
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 31
7. REFERENCES
Bofinger ND, Best PR, Cliff DI and Stumer LJ, 1986. “The oxidation of nitric oxide to nitrogen dioxide in power station plumes”, Proceedings of the Seventh World Clean Air Congress, Sydney, 384-392
McEwan J.D.N and Johnson M.R, 2012, Black Carbon Particulate Matter Emission Factors for Buoyancy Driven
Associated Flares, Journal of the Air & Waste Management Association
National Occupational Health and Safety Commission, 1995. Adopted National Exposure Standards for
Atmospheric Contaminants in the Occupational Environment (NOHSC:1003(1995))
Texas Commission on Environmental Quality, 2008, Effects Screening Levels, Texas, United States.
United States Environmental Protection Agency (USEPA), 2018, Industrial Flares, AP-42 Chapter 13.5 USEPA
Office of Air Quality Planning and Standards
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 32
Plate 1 Predicted maximum 1-hour average ground level concentrations of NO2 due to Scenario 1 – 2019 major shutdown: single train propane system de-inventory for planned maintenance activities (flare in isolation)
Location:
Gladstone
Averaging period:
1-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
250 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 33
Plate 2 Predicted maximum 8-hour average ground level concentrations of CO due to Scenario 1 – 2019 major shutdown: single train propane system de-inventory for planned maintenance activities (flare in isolation)
Location:
Gladstone
Averaging period:
8-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
11,000 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 34
Plate 3 Predicted maximum 24-hour average ground level concentrations of PM due to Scenario 1 – 2019 major shutdown: single train propane system de-inventory for planned maintenance activities (flare in isolation) - all PM10 is assumed to be PM2.5
Location:
Gladstone
Averaging period:
24-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
PM10: 50 µg/m³
PM2.5: 25 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 35
APPENDIX A SHUTDOWN/STARTUP SCENARIOS
A1 FLARED GAS QUANTITIES, MASS RATES, AND DURATION OF EVENTS
This section presents the major shutdown/startup and upset scenarios that have occurred over the last four years
at GLNG. Table A1 to Table A5 summarise the mass flow of fuel, expected duration of flaring and energy content.
Information is provided for the dry, wet and marine flares for each scenario.
Table A1 Major shutdown/start up and upset scenarios (1)
GLNG EVENT
EVENT 70 (start of de-inventory)
EVENT 70 (visible smoke)
EVENT 82 EVENT 83/84
Train 1 shutdown 2019
Train 1 shutdown 2019
Train 1 shutdown 2019
Train 1 shutdown 2019
Description
Flaring Train 1 Propane system,
Shutdown activities (start of de-inventory)
Flaring Train 1 Propane system de-inventory, Shutdown
activities
Purging procedure for Propane
system (train1 Start up)
Ethylene vapour re-inventory
Wet flare
Max Flared Rate (t/h) 165 37 174 61
Max Flared Rate (Sm3/h) 139,398 31,053 146,594 51,221 Max Flared Rate (MJ/h) - 1,866,285 - 3,078,382
Duration (minutes) 837 276 75 99
Density (kg/Sm3) 1.19 1.19 1.19 1.19
Dry flare
Max Flared Rate (t/h) 54 144 97 85
Max Flared Rate (Sm3/h) 77,494 75,802 81,276 121,718 Max Flared Rate (MJ/h) 2,882,777 7,250,461 4,884,688 4,527,910
Duration (minutes) 1,342 302 75 111
Density (kg/Sm3) 0.70 1.90 1.19 0.70
Marine flare
Max Flared Rate (t/h) - - - -
Max Flared Rate (Sm3/h) - - - - Max Flared Rate (MJ/h) - - - -
Duration (minutes) - - - -
Density (kg/Sm3) - - - -
Total flare
Max Flared Rate (t/h) 167 145 247 104
Max Flared Rate (Sm3/h) 141,533 76,309 207,630 121,718 Max Flared Rate (MJ/h) 2,882,777 7,280,942 4,884,688 5,369,158
Duration (minutes) 1,409 303 75 111
Density (kg/Sm3) 1.18 1.89 1.19 0.85
Waste Gas
Max Flared Rate (t/h) 11 4 - 2 Max Flared Rate (Sm3/h) 6,003 2,206 - 1,324
Max Flared Rate (MJ/h) - - - -
Duration (minutes) 1,413.5 303 - 5
Density (kg/Sm3) 1.873 1.87 - 1.87
Propane
Max Flared Rate (t/h) - 136 - 54 Max Flared Rate (Sm3/h) - 71,792 - 28,471
Max Flared Rate (MJ/h) - 6.87E+06 - 2,723,274
Duration (minutes) - 129 - 1.0
Density (kg/Sm3) - 1.9 - 1.9
Ethylene
Max Flared Rate (t/h) - 18 30 2 Max Flared Rate (Sm3/h) - 15,258 25,261 1,273
Max Flared Rate (MJ/h) - 917,006 1,518,196 76,536
Duration (minutes) - 20 75 60
Density (kg/Sm3) - 1.19 1.19 1.19
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 36
Table A2 Major shutdown/start up and upset scenarios (2)
GLNG event EVENT 85 EVENT 88 2016 - EVENT 1a 2016 - EVENT 1b
Train 1 shutdown 2019
Train 1 shutdown 2019
Train 1 shutdown Propane Peak
Train 1 shutdown Peak Wet Flare
Description
Ethylene vapour re-inventory
Note Event 85 and 88 scenarios overlap
in time
Ethylene vapour re-inventory Note Event 85 and 88 scenarios
overlap in time
Train 1 Unit 15 warm ethylene circuit
defrost, Unit 16 warm methane and NRU
system defrost, depressuring Unit 12
& 13
Train 1 Unit 15 warm ethylene circuit
defrost, Unit 16 warm methane and NRU
system defrost, depressuring Unit 12
& 13 Note peak methane event from dry flare
Wet flare
Max Flared Rate (t/h) 8 14 53 9
Max Flared Rate (Sm3/h) 6,896 11,567 44,929 7,874
Max Flared Rate (MJ/h) 414,450 695,177 - -
Duration (minutes) 72 43 46 46 Density (kg/Sm3) 1.19 1.19 1.19 1.19
Dry flare
Max Flared Rate (t/h) 52 54 154 198
Max Flared Rate (Sm3/h) 75,299 77,661 81,101 284,253
Max Flared Rate (MJ/h) 2,801,123 2,888,989 7,757,326 10,574,212
Duration (minutes) 94 138 46 46 Density (kg/Sm3) 0.70 0.70 1.90 0.70
Marine flare
Max Flared Rate (t/h) - - - -
Max Flared Rate (Sm3/h) - - - -
Max Flared Rate (MJ/h) - - - -
Duration (minutes) - - - - Density (kg/Sm3) - - - -
Total flared
Max Flared Rate (t/h) 59 59 171 198
Max Flared Rate (Sm3/h) 80,739 80,739 95,816 284,743
Max Flared Rate (MJ/h) 3,144,005 3,144,005 7,757,326 10,574,212 Duration (minutes) 94 138 46 46
Density (kg/Sm3) 0.73 0.73 1.79 0.70
Waste gas
Max Flared Rate (t/h) 3 3 - -
Max Flared Rate (Sm3/h) 1,420 1,517 - -
Max Flared Rate (MJ/h) - - - - Duration (minutes) 37 115 - -
Density (kg/Sm3) 1.87 1.87 - -
Propane
Max Flared Rate (t/h) - - 149 4
Max Flared Rate (Sm3/h) - - 78,477 2,270
Max Flared Rate (MJ/h) - - 7,506,311 217,097 Duration (minutes) - - 46 1,414
Density (kg/Sm3) - - 1.9 1.9
Ethylene
Max Flared Rate (t/h) 3 3 8 5
Max Flared Rate (Sm3/h) 2,612 2,612 7,020 4,003
Max Flared Rate (MJ/h) 156,964 156,964 421,890 240,563 Duration (minutes) 59 99 46 35
Density (kg/Sm3) 1.19 1.19 1.19 1.19
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 37
Table A3 Major shutdown/start up and upset scenarios (3)
GLNG event 2016 - EVENT 1c 2017 - EVENT 6 EVENT 60 EVENT 109/110
Train 1 shutdown Peak Ethylene
Train 1 Shutdown Upset Upset
Description
Train 1 Unit 15 warm ethylene circuit
defrost, Unit 16 warm methane and NRU
system defrost, depressuring Unit 12
& 13
Propane and Ethylene re-inventory
T1 TC-1611 Trip Ethylene flare event
Wet flare
Max Flared Rate (t/h) 69 270 23 4
Max Flared Rate (Sm3/h) 57,663 228,031 19,685 3,207 Max Flared Rate (MJ/h) 3,465,576 - - -
Duration (minutes) 541 1,213 38 56
Density (kg/Sm3) 1.19 1.19 1.19 1.19
Dry flare
Max Flared Rate (t/h) 81 29 45 101
Max Flared Rate (Sm3/h) 67,882 41,016 64,836 84,417 Max Flared Rate (MJ/h) 4,079,680 1,525,795 2,411,899 5,073,462
Duration (minutes) 540 1,439 76 63
Density (kg/Sm3) 1.19 0.70 0.70 1.19
Marine flare
Max Flared Rate (t/h) - - 45.99267216 -
Max Flared Rate (Sm3/h) - - 65,275 - Max Flared Rate (MJ/h) - - 2,345,326 -
Duration (minutes) - - 12 -
Density (kg/Sm3) - - 1 -
Total flared
Max Flared Rate (t/h) 138 272 52 102 Max Flared Rate (Sm3/h) 115,769 230,548 74,590 85,490
Max Flared Rate (MJ/h) 6,957,723 1,525,795 2,691,844 5,073,462
Duration (minutes) 541 1,441 76 63
Density (kg/Sm3) 1.19 1.18 0.70 1.19
Waste gas
Max Flared Rate (t/h) 3 3 - - Max Flared Rate (Sm3/h) 1,420 1,517 - -
Max Flared Rate (MJ/h) - - - -
Duration (minutes) 37 115 - -
Density (kg/Sm3) 1.87 1.87 - -
Propane
Max Flared Rate (t/h) - 7 29 - Max Flared Rate (Sm3/h) - 3,502 15,665 -
Max Flared Rate (MJ/h) - - - -
Duration (minutes) - 1,113 76 -
Density (kg/Sm3) - 1.87 1.87 -
Ethylene
Max Flared Rate (t/h) 8 64 - - Max Flared Rate (Sm3/h) 4,103 33,783 - -
Max Flared Rate (MJ/h) 392,472 3,231,373 - -
Duration (minutes) 1 38 - -
Density (kg/Sm3) 1.9 1.9 - -
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 38
Table A4 Major shutdown/start up and upset scenarios (4)
GLNG event EVENT 125 EVENT 165 EVENT 177 EVENT 180
Upset Upset Upset Upset
Description EDP on 3415-C-1521
tripped open SDP on train 1
Train 1 EDP valve 15075 failed open. Note no propane or
ethylene valves open to flare.
Two Train ESDP - Black Start
Wet flare
Max Flared Rate (t/h) 11 - 5 98
Max Flared Rate (Sm3/h) 9,510 - 4,533 82,232 Max Flared Rate (MJ/h) - - - 4,942,143
Duration (minutes) 173 - 3 142
Density (kg/Sm3) 1.19 - 1.19 1.19
Dry flare
Max Flared Rate (t/h) 1 8 249 11
Max Flared Rate (Sm3/h) 994 11,478 358,122 16,448 Max Flared Rate (MJ/h) 59,739 426,982 13,322,138 611,866
Duration (minutes) 196 69 61 534
Density (kg/Sm3) 1.19 0.70 0.70 0.70
Marine flare
Max Flared Rate (t/h) - - - 16
Max Flared Rate (Sm3/h) - - - 23,503 Max Flared Rate (MJ/h) - - - 844,448
Duration (minutes) - - - 124
Density (kg/Sm3) - - - 1
Total flared
Max Flared Rate (t/h) 12 8 249 113
Max Flared Rate (Sm3/h) 10,188 11,478 358,122 103,497 Max Flared Rate (MJ/h) 59,739 426,982 13,322,138 5,719,505
Duration (minutes) 196 69 63 303
Density (kg/Sm3) 1.19 0.70 0.70 1.09
Waste gas
Max Flared Rate (t/h) 19 11 21 7 Max Flared Rate (Sm3/h) 10,150 5,693 11,320 3,692
Max Flared Rate (MJ/h) - - - -
Duration (minutes) 196 69 65 30
Density (kg/Sm3) 1.87 1.87 1.87 1.87
Propane
Max Flared Rate (t/h) - - - - Max Flared Rate (Sm3/h) - - - -
Max Flared Rate (MJ/h) - - - -
Duration (minutes) - - - -
Density (kg/Sm3) - - - -
Ethylene
Max Flared Rate (t/h) 12 - - 24 Max Flared Rate (Sm3/h) 10,188 - - 20,350
Max Flared Rate (MJ/h) 612,299 - - 1,223,035
Duration (minutes) 0 - - 7
Density (kg/Sm3) 1.19 - - 1.19
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 39
Table A5 Major shutdown/start up and upset scenarios (5)
GLNG event 2016 - EVENT 3
Upset Event - Power upset
Description Power generation load shedding caused Train 1 and
Train 2 SDP
Wet flare
Max Flared Rate (t/h) 62
Max Flared Rate (Sm3/h) 89,330 Max Flared Rate (MJ/h) 3,323,076
Duration (minutes) 841
Density (kg/Sm3) 0.70
Dry flare
Max Flared Rate (t/h) 107
Max Flared Rate (Sm3/h) 153,272 Max Flared Rate (MJ/h) 5,701,718
Duration (minutes) 699
Density (kg/Sm3) 0.70
Marine flare
Max Flared Rate (t/h) 20
Max Flared Rate (Sm3/h) 28,847 Max Flared Rate (MJ/h) 1,036,475
Duration (minutes) 110
Density (kg/Sm3) 1
Total flared
Max Flared Rate (t/h) 181
Max Flared Rate (Sm3/h) 260,353 Max Flared Rate (MJ/h) 9,656,476
Duration (minutes) 841
Density (kg/Sm3) 0.70
Waste gas
Max Flared Rate (t/h) 38 Max Flared Rate (Sm3/h) 20,236
Max Flared Rate (MJ/h) -
Duration (minutes) 676
Density (kg/Sm3) 1.87
Propane
Max Flared Rate (t/h) 130 Max Flared Rate (Sm3/h) 68,330
Max Flared Rate (MJ/h) 6,535,743
Duration (minutes) 841
Density (kg/Sm3) 2
Ethylene
Max Flared Rate (t/h) 1 Max Flared Rate (Sm3/h) 627
Max Flared Rate (MJ/h) 37,653
Duration (minutes) 27
Density (kg/Sm3) 1.19
A2 EMISSIONS SUMMARY
Figure A1 presents a summary of emissions of particulates (PM10 and PM2.5), NOx, total hydrocarbons and total
PAHs for all scenarios considered for the dry and wet flares.
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 40
Figure A1 Summary of emission rates for all flare scenarios considered
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
A3 OTHER PLANT EQUIPMENT
A summary of other plant equipment operating for each scenario is provided below. Note that all equipment was assumed to be operating for the purposes of dispersion modelling.
Table A6 Summary of other plant equipment
No. Description
Major Shutdown / Start-ups Upset Scenarios
EV
EN
T 7
0
EV
EN
T 8
2
EV
EN
T 8
3
EV
EN
T 8
4
EV
EN
T 8
5
EV
EN
T 8
8
20
16
-
EV
EN
T 1
a
20
16
-
EV
EN
T 1
b
20
16
-
EV
EN
T 1
c
20
17
-
EV
EN
T 6
EV
EN
T 6
0
EV
EN
T
10
9
EV
EN
T
11
0
EV
EN
T
12
5
EV
EN
T
16
5
EV
EN
T
17
7
EV
EN
T
18
0
20
16
-
EV
EN
T 3
Train 1 Air Emission Point Locations
A1 Methane Comp. Driver Stack
x x x
A2 Methane Comp. Driver Stack
x x x x x x x
A3 Ethylene Comp. Driver Stack
x x x x
A4 Ethylene Comp. Driver Stack
x x x x x x x
A5 Propane Comp. Driver Stack
x x x x x x
A6 Propane Comp. Driver Stack
x x x x
A7 Waste Gas / Acid Gas / Nit Vents
x x x x x x x x x x x x x x x x x x
A8 Hot Oil heater x x x x x x x x x x x x x x
A9 GTG Turbine Driver Stack
x x x x
A10 GTG Turbine Driver Stack
x x x x x x x x x x x
A11 GTG Turbine Driver Stack
x
A12 GTG Turbine Driver Stack
x x x x x
A13 Wet Gas Flare x x x x x x x x x x x x x x x x x
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
No. Description
Major Shutdown / Start-ups Upset Scenarios
EV
EN
T 7
0
EV
EN
T 8
2
EV
EN
T 8
3
EV
EN
T 8
4
EV
EN
T 8
5
EV
EN
T 8
8
20
16
-
EV
EN
T 1
a
20
16
-
EV
EN
T 1
b
20
16
-
EV
EN
T 1
c
20
17
-
EV
EN
T 6
EV
EN
T 6
0
EV
EN
T
10
9
EV
EN
T
11
0
EV
EN
T
12
5
EV
EN
T
16
5
EV
EN
T
17
7
EV
EN
T
18
0
20
16
-
EV
EN
T 3
A14 Marine Flare x x x
A15 Dry Gas Flare x x x x x x x x x x x x x x x x x x
A16 Backup Wet and Dry Gas Flare
Train 2 Air Emission Point Locations
B1 Methane Comp. Driver Stack
x x x x x x x x x x x x x x x x
B2 Methane Comp. Driver Stack
x x x x x x x x x x x x x x
B3 Ethylene Comp. Driver Stack
x x x x x x x x x x x x x x x x
B4 Ethylene Comp. Driver Stack
x x x x x x x x x x x x x x
B5 Propane Comp. Driver Stack
x x x x x x x x x x x x x x x x
B6 Propane Comp. Driver Stack
x x x x x x x x x x x x x x
B7 Waste Gas / Acid Gas / Nit Vents
x x x x x x x x x x x x x x x x x x
B8 Hot Oil heater x x x x x x
B9 GTG Turbine Driver Stack
x x x x x x x x x x x x
B10 GTG Turbine Driver Stack
x x x x x x x x x x x x x
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 43
APPENDIX B METEOROLOGICAL AND DISPERSION MODELLING
METHODOLOGY
Air dispersion modelling was conducted using a two-stage approach. Firstly, the CSIRO’s meteorological model,TAPM (The Air Pollution Model) Version 4.0.5 (Hurley 2005), was used to simulate the regional meteorology in the
Gladstone region. Further refinement of the wind field was then made through the CALMET Version 6.3
meteorological pre-processor. Secondly, the CALPUFF plume dispersion model was used to predict ground-level
concentrations of air pollutants emitted from GLNG.
B1 DEVELOPMENT OF SITE-SPECIFIC METEOROLOGY
B1.1 TAPM meteorological simulations
TAPM was developed by the CSIRO and has been validated by the CSIRO, Katestone Environmental and others
for many locations in Australia, Southeast Asia and in North America (see www.dar.csiro.au/TAPM/ for more details
on the model and validation results from the CSIRO). Katestone Environmental has used the TAPM model
throughout Australia as well as in parts of New Caledonia, the United States of America, Bangladesh and Vietnam.
This model generally has performed well for simulating winds in a region.
TAPM required synoptic meteorological information for the Gladstone region. This information was generated by a
global model similar to the large-scale models used to forecast the weather. The data are supplied by the BoM on
a grid resolution of approximately 75 km, and at elevations of 100 m to five kilometres above the ground. TAPM
uses this synoptic information, along with specific details of the location such as surrounding terrain, land-use, soil
moisture content and soil type to simulate the meteorology of a region as well as at a specific location.
TAPM solves the fundamental fluid dynamics equations to predict meteorology at a mesoscale (20 kilometre to
200 kilometre) and at a local scale (down to a few hundred metres). TAPM includes parameterisations for
cloud/rain micro-physical processes, urban/vegetation canopy and soil, and radiative fluxes. TAPM is skilled at
simulating the flows important to regional and local scale meteorology, such as the southeast trade winds and sea
breezes.
TAPM was configured as follows:
• Mother domain of 30 km with 3 nested daughter grids of 10 km, 3 km and 1 km
• 40 x 40 grid points for all modelling domains resulting in a 40 x 40 km grid at 1 kilometre resolution
• 25 vertical levels, from the surface up to an altitude of 8000 metres above ground level
• Geosciences Australia 9 second DEM terrain data
• The TAPM defaults for sea surface temperature
• Default options selected for advanced meteorological inputs
• Year modelled: 1 April 2006 to 31 March 2007
• Landuse and coastline data was refined based on high resolution images sourced from Google Earth and
vegetation maps obtained from DES
• Local data assimilation using observations from three regionally representative sites.
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 44
The land use for the inner grid required significant modification due to the coarseness of the TAPM dataset.
Representative data was derived from vegetation maps obtained from DES and from aerial imaging by Google
Earth. The coastline was also re-defined in the database to better represent the complex coastline around Curtis
Island. Detailed 9-second arc DEM elevation data (resolution approximately 100 metre) was obtained from
Geosciences Australia for this modelling domain.
TAPM was used as the prognostic mesoscale meteorological model to provide three-dimensional hourly
meteorological fields to CALMET, a diagnostic meteorological model and wind field pre-processor for the CALPUFF
air dispersion model. The CALMET modelling grid was positioned within the TAPM simulation, effectively becoming
a fifth nested grid. The three-dimensional meteorological fields generated by TAPM were then input into CALMET
model to generate a fine resolution meteorological field.
B1.2 CALMET meteorological simulations
CALMET is an advanced non-steady-state diagnostic three-dimensional meteorological model with micro-
meteorological modules for overwater and overland boundary layers. The model is the meteorological pre-
processor for the CALPUFF dispersion model. CALMET is capable of assimilating hourly meteorological data from
multiple sites within the modelling domain, and can also be initialised with the gridded three-dimensional prognostic
output from other meteorological models such as TAPM. This can improve dispersion model output, particularly
over complex terrain as the near surface meteorological conditions are calculated for each grid point.
CALMET was used to simulate meteorological conditions around Curtis Island. The modelling domain was setup
to be nested within the one kilometre TAPM domain. CALMET treats the prognostic model output as the initial
guess field for the diagnostic model wind fields. CALMET then adjusts the initial guess field for the kinematic
effects of terrain, slope flows, blocking effects and 3-dimensional divergence minimisation. The coupled approach
unites the mesoscale prognostic capabilities of TAPM with the refined terrain and land use capabilities of CALMET.
The use of the three-dimensional wind field provides a complete set of meteorological variables for every grid point
and vertical level for each hour of the simulation period. This is a significant improvement in modelling approach
to the method of data assimilation from discrete surface stations. No data assimilation was used in CALMET as
no local data were available for the Curtis Island site. Regionally representative sites were, however, assimilated
into TAPM.
The model was set up with twelve vertical levels with heights at 20 m, 60 m, 100 m, 180 m, 260 m, 360 m, 460 m,
600 m, 800 m, 1600 m, 2600 m and 4600 m at each grid point. The terrain and land use were further refined from
those used in the TAPM model to account for the increased resolution. The terrain was generated from the
Geosciences Australia 9-second arc DEM dataset at a resolution of 300 m. All default options and factors were
selected except where noted below.
Key features of CALMET used to generate the wind fields for the GLNG model are as follows:
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 45
• Domain area of 22.8 by 22.8 km with 300 m grid spacing
• 1 year time scale (1 April 2006 to 31 March 2007), divided into individual months for analysis
• Prognostic wind fields input as MM5/3D.Dat "initial guess" field only (as generated from TAPM)
• Step 1 wind field options include kinematic effects, divergence minimisation, Froude adjustment to a
critical Froude number of 1 and slope flows
• Terrain radius of influence set at 2 kilometre
• Cloud cover calculated from prognostic relative humidity.
B2 CALPUFF DISPERSION MODELLING METHODOLOGY
B2.1 Model configuration
Atmospheric dispersion modelling was carried out using the CALPUFF dispersion model. CALPUFF is a non-
steady-state puff dispersion model, and is accepted for use by the DERM for application in environments where
wind patterns and plume dispersion is strongly influenced by complex terrain and the land-sea interface. The
Gladstone region consists of highly complex meteorology, and includes complex terrain, highly variable land uses
and a land-sea interface and coastal islands. The CALPUFF dispersion model was used to predict ground-level
concentrations of air contaminants downwind of this source. The same grid size and resolution developed for the
fine resolution CALMET model was used for the dimensions of the CALPUFF domain.
B2.2 Other plant source characteristics
CALPUFF was configured with default options and parameters, with the following exceptions:
• Modelling period from 1 April 2006 to 31 March 2007
• 94 x 94 grid point domain with 0.3km resolution
• Gridded three-dimensional hourly-varying meteorological conditions generated by CALMET
• No chemical transformation or wet removal modelled
• PDF used for dispersion under convective conditions
• Dispersion coefficients calculated internally from sigma v and sigma w using micrometeorological
variables.
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 46
Table A7 Stack characteristics of GLNG Plant included in the assessment
Train Source East
Coord (m) North
Coord (m) Height
(m)4
Diameter (m)
Temp (oC) Exit
velocity1
(m/s)
Emissions (g/s)
NOX2 CO3 PM10/PM2.53
A1 Methane Comp. Driver Stack 317,497 7,369,554 32 3.58 508.5 12 3.6 1.94 0.2
A2 Methane Comp. Driver Stack 317,511 7,369,554 32 3.58 507 12 3.6 1.94 0.2
A3-W Ethylene Comp. Driver Stack 317,525 7,369,554 44 2.5 240.5 8.5 3.6 1.94 0.2
A4-W Ethylene Comp. Driver Stack 317,539 7,369,554 44 2.5 244.5 8.5 3.6 1.94 0.2
A5 Propane Comp. Driver Stack 317,553 7,369,554 32 3.58 494 12 3.6 1.94 0.2
A6 Propane Comp. Driver Stack 317,567 7,369,554 32 3.58 504 12 3.6 1.94 0.2
A8 Hot Oil Heater 317,687 7,369,565 41 2.00 179.33 1.2 0.95 0.99 0.09
A9 GTG Turbine Driver Stack 317,821 7,369,568 30 1.95 546 26 1.74 0.43 0.04
A10 GTG Turbine Driver Stack 317,821 7,369,552 30 1.95 305 26 1.74 0.43 0.04
A11 GTG Turbine Driver Stack 317,821 7,369,536 30 1.8 517.5 19 1.74 0.43 0.04
A12 GTG Turbine Driver Stack 317,821 7,369,519 30 1.83 532 19 1.74 0.43 0.04
B1 Methane Comp. Driver Stack 317,497 7,369,332 32 3.58 498.5 12 3.6 1.94 0.2
B2 Methane Comp. Driver Stack 317,511 7,369,332 32 3.58 481 12 3.6 1.94 0.2
B3-W Ethylene Comp. Driver Stack 317,525 7,369,332 44 2.5 250.5 2.4 3.6 1.94 0.2
B4-W Ethylene Comp. Driver Stack 317,539 7,369,332 44 2.5 265 2.4 3.6 1.94 0.2
B5 Propane Comp. Driver Stack 317,553 7,369,332 32 3.58 490.5 12 3.6 1.94 0.2
B6 Propane Comp. Driver Stack 317,567 7,369,332 32 3.58 504 12 3.6 1.94 0.2
B8 Hot Oil Heater 317,687 7,369,343 41 2 184.25 1.2 0.95 0.99 0.09
B9 GTG Turbine Driver Stack 317,821 7,369,297 30 1.9 374 19 1.74 0.43 0.04
B10 GTG Turbine Driver Stack 317,821 7,369,314 30 1.95 470 19 1.74 0.43 0.04
Table note: 1 Minimum exit velocity as per Schedule B – Table 1 EPPG00712213 2 Maximum mass rate as per Schedule B – Table 2 EPPG00712213’ 3 Emission rates from EIS (Appendix S GLNG Environmental Impact Statement – Air Quality (URS, 2009)) 4 Minimum exit velocity as per Schedule B – Table 1 EPPG00712213
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 47
APPENDIX C – DISPERSION MODELLING RESULTS
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 48
Table C1 Predicted concentrations of NO2, CO and PM10/PM2.5 in isolation, with plant and with plant and background for Scenario 1
2019 major shutdown: single train propane system de-
inventory for planned maintenance activities
Flare in isolation µg/m3 Flare with plant µg/m3 Flare with plant, plus background µg/m3
1-hourNO2
8-hourCO
24-hourPM10
24-hourPM2.5
1-hourNO2
1
8-hourCO
24-hourPM10
24-hourPM2.5
1-hourNO2
1
8-hourCO
24-hourPM10
24-hourPM2.5
R1 3.5 12.2 1.0 1.0 4.9 12.4 1.0 1.0 43.2 262.4 37.0 17.67
R2 2.1 15.0 1.3 1.3 4.4 15.4 1.5 1.5 41.5 265.4 37.5 17.67
R3 3.4 9.2 0.8 0.8 3.8 9.3 0.8 0.8 47.5 259.3 36.8 17.67
R4 3.3 8.7 0.7 0.7 3.9 9.0 0.7 0.7 48.9 259.0 36.7 17.67
R5 2.7 9.6 0.8 0.8 3.8 10.4 0.9 0.9 57.0 260.4 36.9 17.67
R6 2.7 11.5 1.0 1.0 4.9 11.5 1.0 1.0 74.5 261.5 37.0 17.67
R7 1.3 6.8 0.5 0.5 4.6 8.1 0.5 0.5 67.4 258.1 36.5 18.2
R8 2.9 6.5 0.5 0.5 2.8 7.2 0.6 0.6 73.0 257.2 36.6 18.3
R9 0.9 4.9 0.4 0.4 3.3 4.9 0.4 0.4 50.9 254.9 36.4 18.1
R11 1.0 3.3 0.3 0.3 6.1 8.6 0.4 0.4 40.2 258.6 36.4 18.1
R12 0.5 3.0 0.3 0.3 5.2 6.2 0.3 0.3 45.6 256.2 36.3 18.0
R13 0.8 3.1 0.3 0.3 4.7 5.5 0.3 0.3 28.5 255.5 36.3 18.0
R14 0.6 2.2 0.2 0.2 3.9 4.8 0.2 0.2 30.7 254.8 36.2 17.9
R15 0.8 3.1 0.3 0.3 2.9 4.5 0.3 0.3 23.0 254.5 36.3 18.0
R16 0.6 2.1 0.2 0.2 3.2 3.4 0.2 0.2 17.5 253.4 36.2 17.9
R17 0.7 2.9 0.3 0.3 2.5 3.6 0.3 0.3 27.5 253.6 36.3 17.9
R18 0.7 3.9 0.3 0.3 2.9 5.1 0.4 0.4 20.4 255.1 36.4 18.1
R19 0.7 3.9 0.3 0.3 2.8 5.0 0.4 0.4 20.0 255.0 36.4 18.1
R20 0.6 3.8 0.3 0.3 2.4 4.8 0.4 0.4 20.2 254.8 36.4 18.1
R21 - QCLNG accommodation camp
0.9 3.4 0.2 0.2 14.9 21.4 1.6 1.6 53.2 271.4 37.6 19.2
R22 - APLNG accommodation camp
1.5 3.6 0.2 0.2 11.8 17.5 0.9 0.9 50.6 267.5 36.9 18.5
Curtis Island National Park 6.5 24.2 2.0 2.0 6.2 25.7 2.0 2.0 36.0 275.7 38.0 19.7
Curtis Island Conservation Park 2.7 9.0 0.8 0.8 5.7 9.4 0.8 0.8 44.8 259.4 36.8 18.5
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 49
2019 major shutdown: single train propane system de-
inventory for planned maintenance activities
Flare in isolation µg/m3 Flare with plant µg/m3 Flare with plant, plus background µg/m3
1-hourNO2
8-hourCO
24-hourPM10
24-hourPM2.5
1-hourNO2
1
8-hourCO
24-hourPM10
24-hourPM2.5
1-hourNO2
1
8-hourCO
24-hourPM10
24-hourPM2.5
Curtis Island State Forest 4.5 8.7 0.8 0.8 5.8 9.9 0.8 0.8 38.5 259.9 36.8 18.5
Curtis Island Environmental Management Precinct
7.3 26.2 2.1 2.1 58.2 146.9 6.0 6.0 75.4 396.9 42.0 23.6
Targinie State Forest 3.2 13.3 1.1 1.1 13.4 13.8 1.3 1.3 63.2 263.8 37.3 19.0
Objective 250 11,000 50 25 250 11,000 50 25 250 11,000 50 25
Table note: 1 Cumulative NO2 presented as 99.9th highest
Table C2 Predicted concentrations of NO2, CO and PM10/PM2.5 in isolation, with plant and with plant and background for Scenario 2
2016 major shutdown: single train propane system de-
inventory for planned maintenance activities
Flare in isolation µg/m3 Flare with plant µg/m3 Flare with plant, plus background µg/m3
1-hourNO2
8-hourCO
24-hourPM10
24-hourPM2.5
1-hourNO2
1
8-hourCO
24-hourPM10
24-hourPM2.5
1-hourNO2
1
8-hourCO
24-hourPM10
24-hourPM2.5
R1 2.4 6.6 0.8 0.8 4.9 7.2 1.0 1.0 43.2 257 37 18.7
R2 1.5 7.8 0.9 0.9 4.4 8.2 1.4 1.4 41.5 258 37 19.1
R3 2.0 5.8 0.7 0.7 3.8 6.9 0.9 0.9 47.5 257 37 18.6
R4 1.6 5.6 0.7 0.7 3.8 6.3 0.9 0.9 48.9 256 37 18.5
R5 2.2 7.2 0.9 0.9 3.8 8.0 1.1 1.1 57.0 258 37 18.7
R6 1.8 8.9 1.1 1.1 4.9 8.9 1.4 1.4 74.5 259 37 19.0
R7 0.5 2.8 0.3 0.3 4.6 4.5 0.5 0.5 67.4 255 36 18.1
R8 1.9 3.7 0.4 0.4 2.7 4.4 0.6 0.6 73.0 254 37 18.3
R9 0.5 2.2 0.3 0.3 3.3 3.2 0.4 0.4 50.9 253 36 18.1
R11 0.2 0.8 0.1 0.1 6.1 8.6 0.4 0.4 40.2 259 36 18.1
R12 0.1 0.8 0.1 0.1 5.2 5.6 0.3 0.3 45.6 256 36 17.9
R13 0.7 1.8 0.3 0.3 4.7 5.5 0.3 0.3 28.5 255 36 18.0
R14 0.4 1.1 0.2 0.2 3.9 4.6 0.2 0.2 30.7 255 36 17.9
R15 0.4 1.1 0.2 0.2 2.9 3.5 0.3 0.3 23.0 254 36 18.0
R16 0.3 0.6 0.1 0.1 3.2 3.2 0.2 0.2 17.5 253 36 17.9
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 50
2016 major shutdown: single train propane system de-
inventory for planned maintenance activities
Flare in isolation µg/m3 Flare with plant µg/m3 Flare with plant, plus background µg/m3
1-hourNO2
8-hourCO
24-hourPM10
24-hourPM2.5
1-hourNO2
1
8-hourCO
24-hourPM10
24-hourPM2.5
1-hourNO2
1
8-hourCO
24-hourPM10
24-hourPM2.5
R17 0.5 1.8 0.3 0.3 2.5 3.5 0.4 0.4 27.5 254 36 18.0
R18 0.6 2.8 0.3 0.3 2.9 2.8 0.4 0.4 20.4 253 36 18.0
R19 0.6 2.5 0.3 0.3 2.8 2.7 0.4 0.4 20.0 253 36 18.0
R20 0.5 2.3 0.3 0.3 2.4 2.6 0.4 0.4 20.2 253 36 18.0
R21 - QCLNG accommodation camp
0.2 0.7 0.2 0.2 14.9 21.4 1.6 1.6 53.2 271 38 19.2
R22 - APLNG accommodation camp
0.2 0.7 0.2 0.2 11.8 17.5 0.9 0.9 50.6 268 37 18.5
Curtis Island National Park 1.8 8.8 1.0 1.0 6.0 9.9 2.2 2.2 36.0 260 38 19.9
Curtis Island Conservation Park 2.1 5.6 0.7 0.7 5.7 5.8 1.0 1.0 44.8 256 37 18.7
Curtis Island State Forest 3.0 6.0 0.7 0.7 5.8 7.2 1.0 1.0 38.4 257 37 18.7
Curtis Island Environmental Management Precinct
4.3 15.0 1.8 1.8 58.2 146.9 5.9 5.9 75.4 397 42 23.6
Targinie State Forest 2.4 8.2 1.0 1.0 13.4 12.4 1.3 1.3 63.2 262 37 19.0
Objective 250 11,000 50 25 250 11,000 50 25 250 11,000 50 25
Table note: 1 Cumulative NO2 presented as 99.9th highest
Table C3 Predicted concentrations of NO2, CO and PM10/PM2.5 in isolation, with plant and with plant and background for Scenario 3
Upset event: Emergency Depressuring Valve (EDP) valve failed open
Flare in isolation µg/m3 Flare with plant µg/m3 Flare with plant, plus background µg/m3
1-hourNO2
8-hourCO
24-hourPM10
24-hourPM2.5
1-hourNO2
1
8-hourCO
24-hourPM10
24-hourPM2.5
1-hourNO2
1
8-hourCO
24-hourPM10
24-hourPM2.5
R1 4.3 11.6 0.04 0.04 4.9 11.8 0.4 0.4 43.2 261.8 36.4 17.67
R2 3.5 7.6 0.03 0.03 4.4 7.8 0.2 0.2 41.5 257.8 36.2 17.67
R3 6.7 19.9 0.07 0.07 4.0 19.9 0.2 0.2 47.5 269.9 36.2 17.67
R4 2.6 5.2 0.02 0.02 3.8 5.2 0.2 0.2 49.0 255.2 36.2 17.67
R5 3.5 7.7 0.03 0.03 3.9 7.9 0.1 0.1 57.0 257.9 36.1 17.67
R6 2.4 9.4 0.03 0.03 4.9 10.2 0.1 0.1 74.5 260.2 36.1 17.67
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 51
Upset event: Emergency Depressuring Valve (EDP) valve failed open
Flare in isolation µg/m3 Flare with plant µg/m3 Flare with plant, plus background µg/m3
1-hour NO2
8-hour CO
24-hour PM10
24-hour PM2.5
1-hour NO2
1 8-hour
CO 24-hour
PM10 24-hour
PM2.5 1-hour NO2
1 8-hour
CO 24-hour
PM10 24-hour
PM2.5
R7 1.0 5.1 0.02 0.02 4.6 6.0 0.2 0.2 67.4 256.0 36.2 17.9
R8 0.9 3.4 0.01 0.01 2.7 4.1 0.1 0.1 73.0 254.1 36.1 17.8
R9 1.1 3.6 0.01 0.01 3.3 3.6 0.1 0.1 50.9 253.6 36.1 17.8
R11 0.4 1.8 0.01 0.01 6.1 8.6 0.3 0.3 40.2 258.6 36.3 18.0
R12 0.2 0.7 0.00 0.00 5.2 5.6 0.3 0.3 45.6 255.6 36.3 17.9
R13 0.3 1.3 0.00 0.00 4.7 5.5 0.2 0.2 28.5 255.5 36.2 17.9
R14 0.3 1.0 0.00 0.00 3.9 4.6 0.2 0.2 30.7 254.6 36.2 17.9
R15 0.3 0.9 0.00 0.00 2.9 3.5 0.2 0.2 23.0 253.5 36.2 17.8
R16 0.2 0.5 0.00 0.00 3.2 3.2 0.1 0.1 17.5 253.2 36.1 17.8
R17 2.2 6.2 0.02 0.02 2.6 6.2 0.1 0.1 27.5 256.2 36.1 17.8
R18 1.5 7.0 0.03 0.03 2.9 7.1 0.1 0.1 20.4 257.1 36.1 17.8
R19 1.4 5.9 0.02 0.02 2.8 6.0 0.1 0.1 20.0 256.0 36.1 17.8
R20 1.3 5.0 0.02 0.02 2.4 5.1 0.1 0.1 20.2 255.1 36.1 17.8
R21 - QCLNG accommodation camp
0.2 0.9 0.00 0.00 14.9 21.4 1.6 1.6 53.2 271.4 37.6 19.2
R22 - APLNG accommodation camp
0.2 0.9 0.00 0.00 11.8 17.5 0.9 0.9 50.6 267.5 36.9 18.5
Curtis Island National Park 5.0 10.0 0.04 0.04 6.0 10.0 0.3 0.3 36.0 260.0 36.3 18.0
Curtis Island Conservation Park 5.1 13.8 0.05 0.05 5.7 13.8 0.3 0.3 44.8 263.8 36.3 18.0
Curtis Island State Forest 4.9 14.2 0.05 0.05 5.8 14.4 0.3 0.3 38.4 264.4 36.3 18.0
Curtis Island Environmental Management Precinct
5.0 13.8 0.05 0.05 58.2 146.9 5.9 5.9 75.4 396.9 41.9 23.6
Targinie State Forest 4.0 15.2 0.06 0.06 13.5 15.3 0.4 0.4 63.2 265.3 36.4 18.1
Objective 250 11,000 50 25 250 11,000 50 25 250 11,000 50 25
Table note: 1 Cumulative NO2 presented as 99.9th highest
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 52
Plate C1 Predicted maximum 1-hour average ground level concentrations of NO2 due to Scenario 1 – 2019 major shutdown: single train propane system de-inventory for planned maintenance activities (flare in isolation)
Location:
Gladstone
Averaging period:
1-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
250 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 53
Plate C2 Predicted maximum 1-hour average ground level concentrations of NO2 due to Scenario 1 – 2019 major shutdown: single train propane system de-inventory for planned maintenance activities (flare + GLNG plant + GAMS background)
Location:
Gladstone
Averaging period:
1-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
250 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 54
Plate C3 Predicted maximum 8-hour average ground level concentrations of CO due to Scenario 1 – 2019 major shutdown: single train propane system de-inventory for planned maintenance activities (flare in isolation)
Location:
Gladstone
Averaging period:
8-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
11,000 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 55
Plate C4 Predicted maximum 8-hour average ground level concentrations of CO due to Scenario 1 – 2019 major shutdown: single train propane system de-inventory for planned maintenance activities (flare + GLNG plant + ambient background)
Location:
Gladstone
Averaging period:
8-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
11,000 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 56
Plate C5 Predicted maximum 24-hour average ground level concentrations of PM due to Scenario 1 – 2019 major shutdown: single train propane system de-inventory for planned maintenance activities (flare in isolation). All PM10 is assumed to be PM2.5.
Location:
Gladstone
Averaging period:
24-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
PM10: 50 µg/m³
PM2.5: 25 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 57
Plate C6 Predicted maximum 24-hour average ground level concentrations of PM10 due to Scenario 1 – 2019 major shutdown: single train propane system de-inventory for planned maintenance activities (flare + GLNG plant + ambient background)
Location:
Gladstone
Averaging period:
24-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
50 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 58
Plate C7 Predicted maximum 24-hour average ground level concentrations of PM2.5 due to Scenario 1 – 2019 major shutdown: single train propane system de-inventory for planned maintenance activities (flare + GLNG plant + ambient background)
Location:
Gladstone
Averaging period:
24-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
25 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 59
Plate C8 Predicted maximum 1-hour average ground level concentrations of fluoranthene due to Scenario 1 – 2019 major shutdown: single train propane system de-inventory for planned maintenance activities (flare in isolation)
Location:
Gladstone
Averaging period:
1-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
0.5 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 60
Plate C9 Predicted maximum 1-hour average ground level concentrations of propylene due to Scenario 1 – 2019 major shutdown: single train propane system de-inventory for planned maintenance activities (flare in isolation)
Location:
Gladstone
Averaging period:
1-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
8,750 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 61
Plate C10 Predicted maximum 1-hour average ground level concentrations of NO2 due to Scenario 2 – 2016 major shutdown: single train propane system de-inventory for planned maintenance activities (flare in isolation)
Location:
Gladstone
Averaging period:
1-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
250 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 62
Plate C11 Predicted maximum 1-hour average ground level concentrations of NO2 due to Scenario 2 – 2016 major shutdown: single train propane system de-inventory for planned maintenance activities (flare + GLNG plant + GAMS background)
Location:
Gladstone
Averaging period:
1-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
250 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 63
Plate C12 Predicted maximum 8-hour average ground level concentrations of CO due to Scenario 2 – 2016 major shutdown: single train propane system de-inventory for planned maintenance activities (flare in isolation)
Location:
Gladstone
Averaging period:
8-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
11,000 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 64
Plate C13 Predicted maximum 8-hour average ground level concentrations of CO due to Scenario 2 – 2016 major shutdown: single train propane system de-inventory for planned maintenance activities (flare + GLNG plant + ambient background)
Location:
Gladstone
Averaging period:
8-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
11,000 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 65
Plate C14 Predicted maximum 24-hour average ground level concentrations of PM due to Scenario 2 – 2016 major shutdown: single train propane system de-inventory for planned maintenance activities (flare in isolation). All PM10 is assumed to be PM2.5.
Location:
Gladstone
Averaging period:
24-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
PM10: 50 µg/m³
PM2.5: 25 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 66
Plate C15 Predicted maximum 24-hour average ground level concentrations of PM10 due to Scenario 2 – 2016 major shutdown: single train propane system de-inventory for planned maintenance activities (flare + GLNG plant + ambient background)
Location:
Gladstone
Averaging period:
24-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
50 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 67
Plate C16 Predicted maximum 24-hour average ground level concentrations of PM2.5 due to Scenario 2 – 2016 major shutdown: single train propane system de-inventory for planned maintenance activities (flare + GLNG plant + ambient background)
Location:
Gladstone
Averaging period:
24-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
25 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 68
Plate C17 Predicted maximum 1-hour average ground level concentrations of fluoranthene due to Scenario 2 – 2016 major shutdown: single train propane system de-inventory for planned maintenance activities (flare in isolation)
Location:
Gladstone
Averaging period:
1-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
0.5 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 69
Plate C18 Predicted maximum 1-hour average ground level concentrations of propylene due to Scenario 2 – 2016 major shutdown: single train propane system de-inventory for planned maintenance activities (flare in isolation)
Location:
Gladstone
Averaging period:
1-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
8,750 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 70
Plate C19 Predicted maximum 1-hour average ground level concentrations of NO2 due to Scenario 3 – Upset event: Emergency Depressuring Valve (EDP) valve failed open (flare in isolation)
Location:
Gladstone
Averaging period:
1-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
250 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 71
Plate C20 Predicted maximum 1-hour average ground level concentrations of NO2 due to Scenario 3 – Upset event: Emergency Depressuring Valve (EDP) valve failed open (flare + GLNG plant + GAMS background)
Location:
Gladstone
Averaging period:
1-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
250 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 72
Plate C21 Predicted maximum 8-hour average ground level concentrations of CO due to Scenario 3 – Upset event: Emergency Depressuring Valve (EDP) valve failed open (flare in isolation)
Location:
Gladstone
Averaging period:
8-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
11,000 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 73
Plate C22 Predicted maximum 8-hour average ground level concentrations of CO due to Scenario 3 – Upset event: Emergency Depressuring Valve (EDP) valve failed open (flare + GLNG plant + ambient background)
Location:
Gladstone
Averaging period:
8-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
11,000 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 74
Plate C23 Predicted maximum 24-hour average ground level concentrations of PM due to Scenario 3 – Upset Train 1 Propane and Ethylene Valves Open to Flare (flare in isolation). All PM10 is assumed to be PM2.5.
Location:
Gladstone
Averaging period:
24-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
PM10: 50 µg/m³
PM2.5: 25 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 75
Plate C24 Predicted maximum 24-hour average ground level concentrations of PM10 due to Scenario 3 – Upset event: Emergency Depressuring Valve (EDP) valve failed open (flare + GLNG plant + ambient background)
Location:
Gladstone
Averaging period:
24-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
50 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 76
Plate C25 Predicted maximum 24-hour average ground level concentrations of PM2.5 due to Scenario 3 – Upset event: Emergency Depressuring Valve (EDP) valve failed open (flare + GLNG plant + ambient background)
Location:
Gladstone
Averaging period:
24-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
25 µg/m³
Prepared by:
P McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 77
Plate C26 Predicted maximum 1-hour average ground level concentrations of fluoranthene due to Scenario 3 – Upset event: Emergency Depressuring Valve (EDP) valve failed open (flare in isolation)
Location:
Gladstone
Averaging period:
1-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
0.5 µg/m³
Prepared by:
P. McDowell
Date:
2020
Katestone Environmental Pty Ltd D19116-3 Santos – GLNG: Air Quality Assessment of Dry and Wet Flares – Final
4 August 2020
Page 78
Plate C27 Predicted maximum 1-hour average ground level concentrations of propylene due to Scenario 3 – Upset event: Emergency Depressuring Valve (EDP) valve failed open (flare in isolation)
Location:
Gladstone
Averaging period:
1-hour
Data source:
CALPUFF
Units:
µg/m³
Type:
Maximum contours
Objective:
8,750 µg/m³
Prepared by:
P. McDowell
Date:
2020
Appendix C - Flaring Contingency Management Plan
Santos GLNG l PFL 10 EPPG00712213 - Amendment Application l 26 August 2020
This document contains confidential information and is not to be disclosed to any third parties without prior written permission from the CEO GLNG Operations Pty Ltd.
UNCONTROLLED IF PRINTED
Flaring Contingency Management Plan Document Number: 3310-GLNG-5-1.3-0013
Author: Name Title
Environmental Adviser
Checked by: Name Title
Team Leader LNG Plant Process Engineering
Approved by: Name Title
Plant Manager
Date Rev Reason For Issue Author Checked Approved0 DH BC
29/04/2019 1 For issue MR RM GJ
UNCONTROLLED IF PRINTED
Table of Contents
1. PURPOSE ........................................................................................................................ 2 2. SUMMARY OF RESPONSIBILITIES ............................................................................... 2 3. BACKGROUND ................................................................................................................ 3
3.1. Facility Flares ........................................................................................................ 4 3.2. Flare Emissions ..................................................................................................... 6 3.3. Flaring Events ........................................................................................................ 6
Planned Flaring Events ......................................................................... 6 Unplanned/Upset Flaring Events .......................................................... 6
3.4. Flaring Environmental Impacts .............................................................................. 8 4. OBJECTIVES ................................................................................................................... 8 5. PERFORMANCE CRITERIA ............................................................................................ 8
5.1. Legislation and Standards ..................................................................................... 8 5.2. Performance Criteria ............................................................................................. 9
6. MANAGEMENT MEASURES ......................................................................................... 10 7. MONITORING AND REPORTING ................................................................................. 14 8. AUDITING ....................................................................................................................... 14 9. CORRECTIVE ACTIONS ............................................................................................... 14 10. DEFINITIONS ................................................................................................................. 15
Page 2 UNCONTROLLED IF PRINTED 3310-GLNG-5-1.3-0013
1. PURPOSEThis Plan addresses the objectives and performance criteria, management measures, and monitoring, auditing, and corrective action requirements relating to flaring for the Santos GLNG OPL LNG Facility on Curtis Island.
Management measures and reporting and auditing requirements specified are intended to ensure compliance with the requirements of the Environmental Authority (EA) EPPG00712213, and other relevant approvals under applicable Queensland and Commonwealth legislation.
This document applies to operation of the LNG Facility. It addresses flaring activity relating to LNG Operations within the bounds of Petroleum Facility Licence (PFL) 10 on Curtis Island, near Gladstone.
2. SUMMARY OF RESPONSIBILITIESThe following, summary of responsibilities apply for personnel undertaking activities covered by this document.
Table 1: Summary of Responsibilities Role Responsibilities
Plant Manager Operate the plant to minimise flaring, achieve optimalperformance and meet the flaring related criteria asstipulated in the EA.
Ensure that key stakeholders, as stipulated in this plan,are provided with timely information regarding plannedshutdowns and associated flaring activity to facilitatenotifications to stakeholders.
Engage key stakeholders during the shutdown planningprocess.
Provide key stakeholders with timely, accurate informationin relation to unplanned flaring events.
Provide input to MOC assessments to assess the viabilityof recommended initiatives to reduce flaring activity.
Ensure that process controls identified by Engineering areimplemented in order to reduce flaring activity as far aspracticable.
Maintenance Manager Maintain the plant to improve reliability and reduce flaringactivity as far as practicable.
Manage flare maintenance. Actively participate in planning of shutdowns and execute
all shutdown activities such that flaring is minimisedthrough management of shutdown schedules, purging andisolation of equipment.
Shift Superintendent Ensure logging of planned and unplanned flaring events inthe Flaring Register.
Engineering Manager Provide engineering technical input for responses to acomplaint or information request from the AdministeringAuthority.
Page 3 UNCONTROLLED IF PRINTED 3310-GLNG-5-1.3-0013
Role Responsibilities Provide technical advice regarding initiatives to reduce
flaring activity. Actively drive all Management of Change on the facility,
with due consideration to potential impacts on Flaring,Principal Environment Advisor Liase with regulatory environmental departments regarding
any flaring issues Communicate flaring related non-compliances with the EA
to the Administering Authority. Oversee the evaluation of compliance with environmental
legislation and regulations, permits, licences andapprovals.
Oversee incident investigations and development ofcorrective actions for operations implementation.
Provide input to Management of Change (MOC)assessments to assess the viability of recommendedinitiatives to reduce flaring activity.
Environmental Advisor (note this can also be a Senior Environmental Advisor)
Coordinate the collation of information required fromDownstream Operations in response to a complaint orinformation request from the Administering Authority.
Provide the Operations Manager and MaintenanceManager with environmental technical and regulatorycompliance support with regard to this management plan.
Participate in flaring related environmental incidentinvestigations as required.
Collate environmental incident reports and associatedregulatory notifications
Monitor the implementation of the management measuresand identify corrective actions.
Communicate the need for corrective actions to QBU-Environment Team, Site Management and GLNG OPLEHSS&T Manager.
Interact with Administering Authority, as directed. Participate in audits against the SMS. Facilitate site aspects of third party auditing of the EA
conditions.Community Engagement Advisor
Provide timely notifications to key stakeholders on flaringactivity.
Provide EQ Assets – Environment and the DSOEnvironmental Advisor with the details of any flaringrelated complaints or information requests.
Provide technical advice to External Affairs in relation toany complaints or information requests from thecommunity.
3. BACKGROUNDSantos GLNG OPL processes Coal Seam Gas to produce Liquefied Natural Gas (LNG). The feed gas stream is primarily methane and both propane and ethylene refrigerants are used in the liquefaction process. These three components comprise over 99.9% of materials that
Page 4 UNCONTROLLED IF PRINTED 3310-GLNG-5-1.3-0013
can enter the flares. During normal operations, natural gas and other hydrocarbons flow continuously through the LNG Facility. The flaring system facilitates purging of the Facility during planned shutdowns for routine maintenance activities, unplanned repairs to defective infrastructure or emergency situations. The system includes three separate flare systems and is common for both Train 1 and Train 2. Flaring ensures that hydrocarbons are safely combusted and are not emitted to atmosphere.
3.1. Facility Flares
The Santos GLNG OPL Facility flare system is comprised of the following components:
Wet Process Flare: Designed to handle warm hydrocarbon streams that may besaturated with water vapour and/or contain free liquid hydrocarbons and water;
Dry Process Flare: Designed to handle cryogenic hydrocarbons, both vapour andliquid;
Back-up Wet and Dry Flare; and Marine Flare: Designed to handle LNG vapours from the LNG Storage Tanks in the
event of Boil Off Gas Compressors failure and/or shiploading.
Flare locations are provided in Figure 1 (N.B. On Figure 1 - A13 is Wet Gas Flare, A14 is the Marine Flare, A15 is the Dry Flare and A16 is the back-up Wet and Dry Flare).
Page 5 UNCONTROLLED IF PRINTED 3310-GLNG-5-1.3-0013
Figure 1: Flare Locations (A13 to A16)
Page 6 UNCONTROLLED IF PRINTED 3310-GLNG-5-1.3-0013
3.2. Flare Emissions
Coal seam gas processed at the Facility is comprised of the following:
Approximately 98% Methane; and The remaining 2% is comprised of small quantities of Nitrogen (N2), Carbon
Dioxide (CO2) and Ethane (C2H6) and traces of heavier hydrocarbons.
During normal operating conditions, some gas is combusted in the flares in a pilot flame, designed to provide a continuous ignition source such that any gas sent to the flare as a result of upset conditions is immediately combusted. The pilot flare is a small, smokeless flame which emits small volumes of carbon dioxide, nitrogen oxides and water vapour. The flare purge is a necessary safety requirement to prevent any ingress of air into the flare system.
Non-normal operations refer to conditions at the LNG Facility that are outside the general operating parameters of the plant and occur intermittently for a short duration resulting in flaring events. Emission rates for these activities may also be variable and, consequently, do not impact air quality on a continual basis. During non-normal operations, the combustion efficiency of the flare may be reduced by the presence of refrigerants and Nitrogen (used for purging gas lines in the Facility). This results in the emission of Oxides of Nitrogen, Carbon Monoxide (CO), Total Hydrocarbons (Methane, Ethane, Ethylene, Propane), Particulates in the form of PM2.5 and PM10 and trace Polycyclic Aromatic Hydrocarbons (PAH’s).
3.3. Flaring Events
Planned Flaring Events
Planned flaring occurs several times per annum during routine maintenance activities and are normally associated with plant and equipment shut-down and start-up processes.
During some shutdowns, de-inventory of the gas process lines and or refrigerant lines will be required to enable safe access whilst the plant is shut down for maintenance/inspection purposes. Refrigerant vapours may need to be sent to the flare during these situations which may result in flaring events.
Planned flaring can also occur during shiploading activities. It should however be noted that unplanned events can also occur during shiploading activities. Whilst every attempt is made to eliminate flaring during ship loading at times it may be required in the case of the arrival of a warm ship requiring cool down or in the management of larger volumes of boil off gas.
Unplanned/Upset Flaring Events
Page 7 UNCONTROLLED IF PRINTED 3310-GLNG-5-1.3-0013
Unplanned flaring can occur at any time during upset conditions on either or both LNG Trains.
Typical causes of unplanned flaring events include the following:
Regeneration Gas Compressor Trips: The Regeneration Gas Compressor isused to recover natural gas used for regeneration of the molecular sieve beds.The molecular sieves are used to remove moisture from the gas, which is arequirement prior to liquefaction. Whenever the regeneration gas compressortrips, gas is diverted to the Wet Process Flare. The duration of flaring can vary,and takes place until such time that the regeneration gas compressor is returnedto service. Flaring is also required during the compressor restart;
Nitrogen Rejection Unit (NRU) Off Specification: The NRU extracts Nitrogenfrom the feed gas, an essential efficiency component of the liquefaction process.When this unit malfunctions, the feed gas to the NRU is typically diverted to theDry Process Flare;
Gas Turbine Compressor Trips: Gas Turbine Compressors (GTCs) are criticalto the liquefaction process. These units form part of the refrigerant loops whichchill feed gas, leading to liquefaction. When GTCs shutdown, they may requiredepressurisation prior to restarting, which results in flaring activity.Depressurisation of the GTC casings can result in gas or refrigerant vapour beingsent to flare, which causes varying degrees of smoke emissions (dependent onwhich GTC is being depressurised). Re-start of the propane compressors canalso require drainage of liquid propane from the compressor casings to the flare.Re-start of gas turbines associated with the refrigerant compressors can alsorequire flaring of fuel gas as part of the start-up operation of the turbines;
Boil Off Gas (BOG) Compressor Failure: The GLNG Facility has three (3) BOGcompressors, which recycle boil off gas from the LNG Storage Tanks and shiploading back into the liquefaction process. This is an energy saving operationwhich also prevents unnecessary flaring of methane gas. When the BOGcompressors malfunction, gas is diverted to the Marine Flare. The volume of gasthat is diverted to the Marine Flare varies and is dependent on the number ofBOG compressors that are unavailable, as well as, whether or not there is shiploading activity;
Overpressure Release of Hydrocarbon by Pressure Controller or ReliefValve: During upset conditions, correct functioning of pressure controllers andrelief valves will prevent equipment overpressure by releasing hydrocarbons toflare. This is only expected to be for short duration until the process is broughtback to normal operating pressure. However, in the event of passing pressurecontrol valves or relief valves, the flaring may continue until the plant can beshutdown for rectification work;
Emergency Shutdown of LNG Train: During emergencies, the LNG train canbe shutdown automatically or manually. Depending on the nature of the
Page 8 UNCONTROLLED IF PRINTED 3310-GLNG-5-1.3-0013
emergency, hydrocarbon may need to be sent to the flare to depressurise the train or pressure controller may open to flare as the train warms up and inventory pressures rise;
Emergency Depressurisation of Gas Process and Refrigeration Circuits:During emergency depressurisation of the gas process stream and refrigerationcircuits and subsequent train shutdown, gas or refrigerants will be sent to theflare to deinventory the train;
Flaring during Shiploading: Unplanned flaring can occur during ship loadingwhen return vapours exceed the capacity of the plant’s BOG compressors tomanage the vapour load. This gas is flared at the marine flare; and,
Emergency Depressurisation of the Gas Transmission Pipeline (GTP): TheLNG facility flare system can be used as part of the process required foremergency depressurisation of the GTP.
3.4. Flaring Environmental Impacts
As part of the performance test of the plant prior to hand over to GLNG, each flare stack was tested on its performance to meet flame stability requirement and designed operation at individual flare design flow rates with feed gas.
4. OBJECTIVESThe objectives of this management plan are to:
Reduce flaring activity as far as practicable. Manage social impacts associated with unavoidable flaring by providing timely and
accurate notifications to key stakeholders. Operate in a manner that minimises impacts on ambient air quality. Preserve ambient air quality to the extent that ecological health, public amenity or
safety is maintained.
5. PERFORMANCE CRITERIA
5.1. Legislation and Standards
The performance criteria and implementation strategy has been developed withreference to:
Environmental Protection Act (1994) (EP Act) (Qld). Environmental Protection Regulation (2008) (Qld). Environment Protection (Air) Policy (2008) (EPP (Air)) (Qld). National Environment Protection Measure (Air). Environmental Authority EPPG00712213.
Page 9 UNCONTROLLED IF PRINTED 3310-GLNG-5-1.3-0013
5.2. Performance Criteria
The performance criteria for this management plan are as follows:
Visual smoke and particulate emissions will not occur for more than five (5)minutes in any two (2) hour period during normal operating conditions.
Key stakeholders to be notified of planned flaring events a minimum of 24 hoursprior to the event.
Key information regarding unplanned flaring events to be captured as per theProceduire for Recording Flaring Events 3301-GLNG-5-1.3-0023.
Flaring event details shall be reviewed on a regular basis and where appropriatemitigation measures implemented to reduce future flaring activity.
Duration and extent of flaring to be reduced as low as reasonably practicablethrough implementation of operational controls.
Timely responses to information requests to be provided to all stakeholders. Corrective actions identified will be implemented as soon as practicable following
an unplanned flaring event.
Page 10 UNCONTROLLED IF PRINTED 3310-GLNG-5-1.3-0013
6. MANAGEMENT MEASURES
Management Criteria Management Measure Responsibility 6.1 Competency Based Training Appropriately training personnel Training and Operations
Governance 6.2 Operator Essential Care Operations routine monitoring of flare is included in Operator Essentail Care Tasks.
Routine tasks undertaken by Operators to ensure flare is operating satisfactorily. Operations
6.3 Operating Envelope Management Process alarms in place to advise operators and minimise possibility of operational upsets and train trip.
GLNG Engineering
6.4 Plant process efficiency monitoring (including flare monitoring)
Flaring is reported in monthly operations meetings. GLNG Engineering
6.5 GE Remote Monitoring and diagnostics
24 hour monitoring of refrigerant compressors and turbines to ensure equipment is operating at optimal performance. RM&D (Remote Monitoring & Diagnostics), AHM (Asset health management), DDE (Dedicated Diagnostic Engineer).
GLNG Engineering
6.6 Reliability and Maintenance Management Standards
Improve reliability reduce trips, reducing flaring events. Focus on defect elimination. GLNG has a robust risk based system for the prioritisation of break in work outside of a disciplined schedule.
GLNG Engineering
6.7 Asset Reliability Improvement Plan (ARIP)
Monitoring of equipment reliability and management of bad actors via TRP (Trip Reduction Program) and PEP (Performance Enhancement Program) to predict and improve equipment efficiency and performance.
GLNG Engineering
6.8 Flaring only to be undertaken from the Process and Marine Flares, as detailed in the EA.
The design of the Plant only facilitates flaring at these locations. Therefore no additional management measures are required.
N/A
Page 11 UNCONTROLLED IF PRINTED 3310-GLNG-5-1.3-0013
Management Criteria Management Measure Responsibility 6.9 Visible smoke (Ringleman >2) and particulate emissions will not occur for more than five (5) minutes in any two (2) hour period during normal operatingconditions.
Design of the flares has addressed the requirement that visible smoke and particulate emissions are not to occur for more than five (5) minutes in any two (2) hour period during normal operating conditions.
Record events which do not meet this criteria as per the Procedure for Recording Flaring Events” – Document Number 3310-GLNG-5-1.3-0023.
Emergency Procedures have been developed and are implemented for non-routine situations to deal with foreseeable risks and hazards including corrective responses to prevent and mitigate environmental harm (Santos GLNG OPL Emergency Response Plan 3301-GLNG-5-1.6-0024).
Operations / GLNG Engineering
6.10 Key stakeholders to be notified of planned flaring events a minimum of 24 hours prior to the event.
Key stakeholders to be engaged during shutdown planning process and provided with a forecast flaring schedule for the event. The forecast is to be updated regularly throughout the event.
Key community stakeholders to be notified a minimum of 24 hours ahead of planned flaring events.
DES to be notified a minimum of 24 hours ahead of planned significant flaring events. Planned significant flaring events to be entered into the Flaring Register.
Community Relations Officer
6.11 Unplanned flaring events that produce visible smoke and particulate emissions (as per 6.9 above) are to be recorded.
These should be recorded as per the requirements of the “Procedure for Recording Flaring Events” – Document Number 3310-GLNG-5-1.3-0023.
Operations Shift Superintendents
6.12 Duration and extent of flaring to be reduced as low as reasonably practicable through implementation of operational controls.
The following typical upset conditions result in unplanned flaring events. The following mitigation measures are to be implemented where possible to reduce the extent and severity of flaring:
Regeneration Gas Compressor Trips: Whenever practical, pause dehydrationsequence;
Nitrogen Rejection Unit (NRU) Off Specification: Limited options availabletherefore bring NRU back to specification as soon as practicable;
Operations / GLNG Engineering
Page 12 UNCONTROLLED IF PRINTED 3310-GLNG-5-1.3-0013
Management Criteria Management Measure Responsibility Gas Turbine Compressor Trips Limit time taken to restart compressors; and
abide by vendor recommended casing pressure to initiate restart of each GTC; Overpressure Release of Hydrocarbon by Pressure Controller or Relief
Valve: Correct functioning of pressure controller and relief valve would preventoverpressure by releasing hydrocarbon to flare. This is only expected to be forshort duration until the process is brought back to normal operating pressure.However, in the event of passing pressure controller valve or relief valve, theflaring may continue until the plant can be shutdown for rectification work.
Emergency Depressurisation of Gas Process and Refrigeration Circuits:Engineering investigation into the process upsets and flare performance.
Emergency Shutdown of LNG Train: During emergency, LNG train can beshutdown either automatically or manually. Depending on the nature of theemergency, hydrocarbon may need to be sent to the flare to depressurise thetrain or pressure controller may open to flare as the train warms up.
The following planned conditions result in flaring events. The following mitigation measures are to be implemented where possible to reduce the extent and severity of flaring:
De-inventory of refrigerant vapour: Where practical deinventory refrigerantvapour from an offline train into the online train rather than to flare.
Restarting Compressor Turbines: As far as practicable, minimise internaldepressurisation to flare for restarting compressor turbines
Ship Loading: Ensure minimum required BOG compressors are online inadvance of shipping operations.
Shutdown planning to identify and implement initiatives to reduce flaring activity as far as practicable throughout the shutdown period. These initiatives are to include, but not be limited to those detailed above.
6.13 Timely responses to information requests to be provided by all stakeholders.
Coordinate information request responses.
Collation of information for provision to EQ Assets - Environment, to be utilised in the response.
Operations/ GLNG Engineering
Page 13 UNCONTROLLED IF PRINTED 3310-GLNG-5-1.3-0013
Management Criteria Management Measure Responsibility
6.14 Manage complaints Field complaints and seek technical input from key stakeholders, as required. Community Relations 6.15 Corrective actions will be implemented as soon as practicable where required
The cause of the significant flaring events will be identified and where required associated corrective actions implemented in a timely manner.
Operations
Page 14 UNCONTROLLED IF PRINTED 3310-GLNG-5-1.3-0013
7. MONITORING AND REPORTINGMonitoring and reporting is to be undertaken as specified in Schedules B, I and K of the EA and in accordance with the following requirements:
An incident is to be raised in IMS and notification to relevant stakeholders if visiblesmoke and particulate emissions are observed for more than five (5) minutes in anytwo (2) hour period during normal operating conditions in accordance with EAcondition B19. The environment team must be notified of an event like this within 12hours of occurrence.
DES and other key stakeholders to be notified a minimum of 24 hours ahead ofsignificant planned flaring events.
Where required reporting on monitoring undertaken in response to complaints orspecific direction of the Administering Authority will be provided within ten (10) daysof completion of the investigation or receipt of monitoring results, whichever is thelatter, in accordance with EA condition K5.
Monitoring outcomes and corrective actions (if required) will be reported in the AnnualMonitoring Report.
8. AUDITINGThe SMS must be regularly audited to ensure its continuing suitability, adequacy and effectiveness and meet Santos GLNG OPL commitment to continual improvement. Regular internal audits of the SMS are conducted, covering all activities within the scope of the SMS. Santos GLNG OPL will also ensure that a qualified third party auditor (accepted by the Administering Authority) undertakes compliance monitoring against the EA conditions as required by the EA.
9. CORRECTIVE ACTIONS
Description Responsibility Should visible smoke and particulate emissions occur for more than five (5) minutes in any two (2) hour period during normal operating conditions the Operations Shift Superintendent will: 1. Consult with engineering to identify possible causes.2. Investigate mitigation measures.3. Implement appropriate mitigations if possible.
Operations Shift Superintendents
Investigate complaints and advise the Administering Authority in writing (within 14 days of completion of the investigation) of the proposed or undertaken action in relation to the complaint.
Senior Community Relations Advisor / Environmental Advisor
Undertake monitoring specified by the Administering Authority to investigate any complaint of environmental harm. Report results of the investigation and monitoring within 14 days of completion of the investigation or receipt of the monitoring results, whichever is the latter.
Environmental Advisor
Implement corrective actions if the monitoring indicates an exceedance of emission limits in the EA.
Operations and GLNG Engineering
Page 15 UNCONTROLLED IF PRINTED 3310-GLNG-5-1.3-0013
Description Responsibility Record the following details for all complaints received and provide the information to the Administering Authority:
Name, address and contact details of complainant. Time and date of complaint. Reasons for the complaint. Investigations undertaken. Conclusions formed. Actions taken to resolve complaint. Any abatement measures implemented. Person responsible for resolving the complaint.
Senior Community Relations Advisor / Environmental Advisor
10. DEFINITIONSTerm Meaning
Administering Authority Department of Environment and Heritage Protection. The Queensland Government Department that administers the Environmental Authority under the Environmental Protection Act 1994.
CG Coordinator General CH4 Methane CO Carbon Monoxide CO2 Carbon Dioxide DCS Distributed Control System EA Environmental Authority, specifically Environmental
Authority EPPG00712213 EHP Department of Environment and Heritage Protection EP Act Environmental Protection Act 1994 (Qld) EPP (Air) Environmental Protection (Air) Policy 2008 (Qld)
GTC Gas Turbine Compressor GTP Gas Transmission Pipeline LNG Liquefied Natural Gas N2 Nitrogen Gas Normal operating conditions
Normal operating conditions are defined as the ongoing operation of the LNG plant following commissioning and excludes non-normal operating conditions such as start-up, shutdown, maintenance, calibration of emissions monitoring devices.
NOx Nitrogen Oxides NRU Nitrogen Rejection Unit PFL Petroleum Facility Licence PM10 Particulate Matter in the order of 10 micrometres or less SMS Santos Management System
Page 16 UNCONTROLLED IF PRINTED 3310-GLNG-5-1.3-0013
APPENDIX A - EA COMPLAINT MONITORING REQUIREMENTS
In the event of a complaint or request from the Administering Authority, GLNG OPL is required to undertake monitoring specified by the Administering Authority, within a reasonable and practicable time frame nominated by the Administering Authority, to investigate any complaint of environmental harm at any sensitive or commercial place, in accordance with EA EPPG00712213 Schedule J.
The results of the investigation (including an analysis and interpretation of the monitoring results) and abatement measures implemented must be provided to the Administering Authority within ten (10) days of completion of the investigation, or receipt of monitoring results, whichever is the latter, in accordance with EA EPPG00712213 Schedule K.
Appendix D – Procedure for Recording Flaring Events
Santos GLNG l PFL 10 EPPG00712213 - Amendment Application l 26 August 2020
This document contains confidential information and is not to be disclosed to any third parties without prior written permission from the CEO GLNG Operations Pty Ltd.
UNCONTROLLED IF PRINTED
Pro ce dure fo r Re co rdin g Flarin g Eve n ts
Document Number: 3301-GLNG-5-1.3-0023
Author: Title Name Senior Environmental Advisor
Reviewed by: Title Name Principal Environment Adviser Team Leader LNG Plant Process Engineering
Approved by: Title Name Plant Manager
Date Rev Reason For Issue Author Checked Approved0 BC DH
17/01/02019 0.1 For Review MR JC 27/06/2019 1.0 For Use MR JC/ RM GJ
UNCONTROLLED IF PRINTED
Table o f Co n te n ts
1. Purpose ............................................................................................................................ 1 2. Scope ................................................................................................................................ 1 3. Definitions ......................................................................................................................... 1 4. Responsibilities ................................................................................................................. 1 5. Procedure ......................................................................................................................... 2
5.1. Monitoring Flares ................................................................................................... 2 5.2. Recording of Flaring Events .................................................................................. 2
6. Monitoring and Reporting ................................................................................................. 2 APPENDIX A - Flaring Event Register Template ................................................................... 3 APPENDIX B – Ringelmann Smoke Chart .............................................................................. 4
Page 1 of 4 UNCONTROLLED IF PRINTED 3301-GLNG-5-1.3-0023
1. PURPOSE
The Flaring Event Register Procedure defines the requirements for the recording of flaring events at the LNG facility.
Management of flaring events is required to ensure compliance with Environmental Authority (EA) EPPG00712213 conditions with respect to flaring and to minimise the potential for community complaints relating to visible smoke.
2. SCOPE
The scope of this Procedure encompasses the flaring system at the LNG Facility (wet flare, dry flare, back-up flare and marine flare).
The EA stipulates that flaring events associated with visible smoke cannot occur for longer than 5 minutes in any 2 hour period during normal operations.
The recording of flaring events in a Flaring Event Register is a requirement of the Flaring Contingency Management Plan (3310-GLNG-5-1.3-0013) whether the flaring event is planned (normal operations or planned shut-down/ start-up) or unplanned (i.e. upset).
All flaring events should be noted and recorded in the Flaring Register.
3. DEFINITIONS
EA Environmental Authority EPPG00712213
DES Department of Environment and Science, the administering authority for the EA
Flaring Event A flaring event which is associated with visible smoke (Ringelmann number greater than 2) and occurs for a minimum of 5 minutes in any 2 hour period during normal operating conditions.
4. RESPONSIBILITIES
Role Responsibilities Operations Superintendent / Team Leaders • Ensure all Operations Teams are aware of the
Procedure for Recording Flaring Events• Ensure that a Flaring Event Register entry is
completed for each Flaring Event• Resource allocation
Operations Team Members • Be aware of the Flaring Event Register Procedure• Log Flaring Events in the Flaring Event Register
with complete and accurate details
Page 2 of 4 UNCONTROLLED IF PRINTED 3301-GLNG-5-1.3-0023
Role Responsibilities Senior Environmental Advisor • Participate in flaring related environmental incident
investigations• Collate environmental incident reports and
associated regulatory notifications
5. PROCEDURE5.1. Monitoring Flares
The main flare stack and the marine flare shall be monitored by CCTV camera and visualobservations.
5.2. Recording of Flaring Events
When a flaring event has been identified, the following information shall be recorded in theFlaring Register:
Time flaring commenced; Nature of operations at the time of flaring; Specific cause of flaring; Ringlemann Score (1-5); Actions taken to minimise flaring intensity and duration; and Time flaring stopped.
An example format of the Flaring Register is shown in Appendix A.
An example Ringleman score chart is stored in Appendix B. This should be used in accordance with the instructions with the chart in Appendix B.
Notifications are to be issued prior to the end of each shift during which the event occurred. Records of all unplanned flaring events to be maintained in Flaring Register.
6. REPORTING
Monitoring and reporting is to be undertaken as specified in Schedules B, I and K of the EA.
Page 3 of 4 UNCONTROLLED IF PRINTED 3301-GLNG-5-1.3-0023
APPENDIX A - Flaring Event Register Template
EVENT NO. DATE START
TIME
PLANT OPERATING CONDITIONS
CAUSE(S) Ringelmann Score (1-5) ACTIONS TAKEN TO MINIMISE
TIME FLARING
EVENT STOPPED
Normal Shut-down / Start-up Upset
(5 min trigger)
Page 4 of 4 UNCONTROLLED IF PRINTED 3301-GLNG-5-1.3-0023
APPENDIX B – Ringelmann Smoke Chart
������������� ������������������������������������������������ !����"�����#�����"�����������������$��%#�%!��&'���()�*���+��#,����"����&-!����������#�����,�����#�����.���������#���"���������+���!���,�������!��#��&
�� /��()�0��%1�����"����&-!��!�����������������#���#�����.���������#$��,������+���!�������!���������&
2�������&�������������-����&3���4
Appendix E – QCLNG EA EPPG00711513, Schedule B – Air
Emissions
Santos GLNG l PFL 10 EPPG00712213 - Amendment Application l 26 August 2020
Permit
Environmental Authority EPPG00711513
Date Granted: 29 June 2018 Page 5 of 34
SCHEDULE B — AIR EMISSIONS
Nuisance
(B1) The release of noxious or offensive odours or any other noxious or offensive airborne contaminants
resulting from the activities must not cause an environmental nuisance at any nuisance sensitive or
commercial place.
(B2) The release of dust and/or particulate matter resulting from the activities must not cause an
environmental nuisance at any nuisance sensitive or commercial place.
(B3) Dust and particulate matter must not exceed any of the following levels when measured at any
nuisance sensitive or commercial place:
a) dust deposition of 120 milligrams per square metre per day over a 30-days averaging period,
when monitored in accordance with Australian Standard AS 3580.10.1 of 2003 (or more recent
editions); or
b) a concentration of particulate matter with an aerodynamic diameter of less than 2.5 micrometres
(PM2.5) suspended in the atmosphere of 25 micrograms per cubic metre over a 24-hour
averaging time, at a dust sensitive place downwind of the licensed place, when monitored in
accordance with the most recent version of:
i) Australian Standard AS AS/NZS3580.9.10 Methods for sampling and analysis of ambient
air—Determination of suspended particulate matter—PM (sub)2.5(/sub) low volume
sampler—Gravimetric method; or
ii) any alternative method of monitoring PM2.5 which may be permitted by the ‘Air QualitySampling Manual’ as published from time to time by the administering authority.
c) a concentration of particulate matter with an aerodynamic diameter of less than 10 micrometre
(µm) (PM10) suspended in the atmosphere of 50 micrograms per cubic metre (with five one day
exceedances allowed in any one year period); and over a 24 hour averaging time, at a dust
sensitive place downwind of the licensed place, when monitored in accordance with:
i) Australian Standard AS 3580.9.6 of 2003 (or more recent editions) 'Ambient air -
Particulate matter - Determination of suspended particulate PM10 high-volume sampler
with size-selective inlet - Gravimetric method'; or
ii) any alternative method of monitoring PM10 which may be permitted by the 'Air Quality
Sampling Manual' as published from time to time by the administering authority.
Note: The above 5 days exceedances per year are based on the expected exceedances from the
natural events such as bushfires and dust storm.
The Release of Contaminants to the Atmosphere
(B4) The release of contaminants to the atmosphere from a point source must only occur from those
release points identified in Schedule B, Table 1 – Contaminant Release Points and must be directed
vertically upwards without any impedance or hindrance.
(B5) Contaminants requiring on-going monitoring must be released to the atmosphere from a release
point at a height and a flow rate not less than the corresponding height and velocity stated for that
release point in Schedule B, Table 2 – Contaminant Release Limits to Air.
(B6) Contaminants must not be released to the atmosphere from a release point at a mass emission
rate/concentration, as measured at a monitoring point, in excess of that stated in Schedule B, Table
2 – Contaminant Release Limits to Air.
Permit
Environmental Authority EPPG00711513
Date Granted: 29 June 2018 Page 6 of 34
(B7) Contaminants must be monitored not less frequently than specified in Schedule B, Table 2 –
Contaminant Release Limits to Air.
(B8) Monitoring of any releases to the atmosphere required by a condition of this approval must be
carried out in accordance with the following requirements:
a) monitoring provisions for the emission sources listed in Schedule B, Table 2 – Contaminant
Release Limits to Air must comply with the Australian Standard AS 4323.1 - 1995 'Stationary
source emissions, Method 1: Selection of sampling positions' (or more recent editions).
b) the following tests must be performed for each determination specified in Schedule B, Table 2 –Contaminant Release Limits to Air:
i) gas velocity and volume flow rate;
ii) temperature;
iii) water vapour concentration (moisture content).
c) samples must be taken when emissions are expected to be at maximum rates.
d) during the sampling period the following additional information must be gathered:
i) production rate at the time of sampling;
ii) raw materials and fuel used;
iii) number of plant or equipment and operating units operating;
iv) reference to the actual test methods and accuracy of the methods.
(B9) All emission sources requiring monitoring must be conspicuously marked with the corresponding
release point number and equipment number as identified in Schedule B, Table 2 – Contaminant
Release Limits to Air.
Schedule B, Table 1 – Contaminant Release Points
Emission Source
Train 1 Emission Sources
Train 1 Compressor Gas Turbines (x8)
Acid Gas Removal Unit 1
Nitrogen Rejection Unit 1
Train 2 Emission Sources
Train 2 Compressor Gas Turbines (x8)
Acid Gas Removal Unit 2
Nitrogen Rejection Unit 2
Train 3 Emission Sources
Train 3 Compressor Gas Turbines (x8)
Acid Gas Removal Unit 3
Nitrogen Rejection Unit 3
Other LNG Facility Emission Sources
Gas Turbine Power Generators (x4)
Marine Flare
Process Flares (Wet and Dry Gas)
Regeneration Gas Heaters 1 & 2
Hot Oil Heaters 1 & 2
Fire Water Pumps (diesel x3)
Back-Up Power Generators (diesel x6)
Emergency Air Compressor (diesel x2)
Standby Generator at Marine Terminal Building (diesel x1)
Permit
Environmental Authority EPPG00711513
Date Granted: 29 June 2018 Page 7 of 34
Schedule B, Table 2 – Contaminant Release Limits to Air
Emission
Sources Equipment Number
Contaminant
Release
Release
Height
Above
Grade (m)
Emission
Velocity
(m/s)
Maximum
Release
Limit
Monitoring
Frequency
Train 1 Gas Compressor Turbines
Propane
Compressors
1TC-1411
1TC-1421 NOx 34 25
61 mg/Nm3
(dry) @ 15%
O2 and 4.0
g/s Note 2
One stack per
year on a
rotational basis Note 1
Ethylene
Compressors
1TC-1511
1TC-1521 NOx 34 25
Methane
Compressors
WHR* Unit Stacks
1TC-1611 (1H-3411)
1TC-1621 (1H-3421) NOx 49.2
8.2
Bypass Stacks
1TC-1611 (1H-3411-K01)
1TC-1621 (1H-3421-K01)
N/A
Train 2 Gas Compressor Turbines
Propane
Compressors
2TC-1411
2TC-1421 NOx 34 25
61 mg/Nm3
(dry) @ 15%
O2 and 4.0
g/s Note 2
One stack per
year on a
rotational basis Note 1
Ethylene
Compressors
2TC-1511
2TC-1521 NOx 34 25
Methane
Compressors
WHR* Unit Stacks
2TC-1611 (2H-3411)
2TC-1621 (2H-3421) NOx 49.2
8.2
Bypass Stacks
2TC-1611 (2H-3411-K01)
2TC-1621 (2H-3421-K01)
N/A
Train 3 Gas Compressor Turbines
Propane
Compressors
3TC-1411
3TC-1421 NOx 34 25
61 mg/Nm3
(dry) @ 15%
O2 and 4.0
g/s Note 2
All stacks during
commissioning
(see Note 1) of
the facility and
one stack per
year thereafter
on rotational
basis
Ethylene
Compressors
3TC-1511
3TC-1521 NOx 34 25
Methane
Compressors
WHR* Unit Stacks
3TC-1611 (3H-3411)
3TC-1621 (3H-3421) NOx 49.2
8.2
Bypass Stacks
3TC-1611 (3H-3411-K01)
3TC-1621 (3H-3421-K01)
N/A
Power Generation Turbines
Gas Turbine
Power
Generators
1TG-3101
1TG-3102
1TG-3103
1TG-3104
NOx 25 8.2
61 mg/Nm3
(dry) @ 15%
O2 and 4.0
g/s
All stacks during
commissioning
(see Note 1) of
the facility and
one stack per
year thereafter
on rotational
basis
* WHR = Waste Heat Recovery
Note 1: The above NOx release limits are applicable during all timings except start-up, shut-down and calibration of
emission monitoring devices. The start-up duration is allowed up to 30 minutes.
Note 2: The total mass emission rate from the WHR Unit and bypass stack from each methane gas turbine compressor
must not exceed 4.0 g/s NOx.
Permit
Environmental Authority EPPG00711513
Date Granted: 29 June 2018 Page 8 of 34
(B10) Within 3 months of commissioning the facility, the holder of this environmental authority must
conduct air emission monitoring to demonstrate compliance with air emission limits listed in
Schedule B, Table 2 – Contaminant Release Limits to Air and submit report to the administering
authority.
Flare
(B11) Visible smoke must not be produced from the flares except for a total of 5 minutes in any two hour period during normal operating conditions.
(B12) Flaring events, except for those resulting from an emergency, occurring outside of normal
operating conditions must not exceed:
a) 7 hours per annum during daylight hours; and
b) 14 times per annum during daylight hours; and
c) 30 minutes of continuous visible smoke during daylight hours except as authorised
under condition (B13).
(B13) Notwithstanding condition (B12)(c), individual flaring events must not exceed 90 minutes of
continuous visible smoke in the following circumstances:
a) A flaring event associated with a plant maintenance activity that was planned to be
completed outside of daylight hours, but was required to be undertaken during daylight
hours to ensure the safe operation of the plant; or
b) A flaring event associated with a plant maintenance activity that was not planned and was
required to be undertaken during daylight hours to ensure the safe operation of the plant.
(B14) The holder of this authority must keep records of each flaring event to determine compliance with condition (B12) and (B13) and provide these records to the administering authority on request. Records must include, but not be limited to:
a) The duration of each flaring event; andb) The operational planning that was implemented to minimise flaring; andc) The operational controls that were implemented during flaring; andd) If the flaring event exceeds 30 minutes, the circumstance under condition (B13) which
caused this exceedance.
(B15) The holder of this authority must monitor and record all flaring events in accordance with Schedule
B, Table 3 – Recording during flaring events and Condition (I3).
Schedule B – Table 3 – Recording during flaring events
Table 3 – Monitoring of point source emissions to air
Emission point
references
Parameter Units Frequency Method Commencement of Recording
Process Flares (Wet and Dry Gas) and Marine Flare
Visual recording seconds Continuously during a flaring event
Digital Video Recorder
Commencing 29 January 2016
Temperature °C Continuously during a flaring event
CEMS
Vent gas flow rate m/s Continuously during a flaring event
CEMS
Vent gas composition
Multiple Continuously during a flaring event
CEMS Within 18 months of 29 January 2016
(B16) Contingency plans and emergency procedures must be developed and implemented for non-routine
situations to deal with foreseeable risks and hazards including corrective responses to prevent and
Permit
Environmental Authority EPPG00711513
Date Granted: 29 June 2018 Page 9 of 34
mitigate environmental harm (including a contingency plan when plant shuts down for maintenance
or other reasons).
Fugitive Emissions
(B17) The holder of this environmental authority must ensure that all reasonable and practicable measures
are taken in the design and operation of the plant to minimise fugitive VOC emissions. Reasonable
and practicable measures include but are not limited to:
a) implementation of a monitoring program to regularly leak test all units/components including
pumps, piping and controls, vessels and tanks; and
b) operating, maintenance and management practices to be implemented to mitigate fugitive VOC
sources.
(B18) The ducting and extraction systems that transfer effluent gases from one location to another must be
constructed, operated and maintained so as to minimise any leakage of VOCs and vapours to the
atmosphere occurring from these sources.
(B19) In the event of emissions of contaminants occurring from industrial plant or ducting systems that
transfer effluent gases from one location to another, the fault or omission that resulted in that
emission must be corrected as soon as practicable.
Fuel Burning
(B20) This authority only permits the burning of natural gas and diesel fuel in the fuel burning equipment
under normal operating conditions at the rate of the design capacity of the equipment.
(B21) For commissioning and operation of the LNG Plant diesel fuel must only be used in the specified
diesel fuel burning equipment in Schedule B, Table 1 – Contaminant Release Points, under backup,
standby, start up and/or emergency situations.
(B22) The sulphur content of fuel burned in the power generators must not exceed 0.5 percent by weight.
Greenhouse Gas Emissions
(B23) The holder of this authority must develop and implement a greenhouse gas reduction strategy for the
LNG Facility. The strategy must include, but not limited to, the company’s policy on greenhouse gas emissions, an energy efficiency program, a continuous improvement program, better control systems
and a CO2 recovery plan.
Appendix F – Proposed Amendment to the Environmental
Authority (EPPG00712213)
Santos GLNG l PFL 10 EPPG00712213 - Amendment Application l 26 August 2020
Condition Number
Existing Condition Proposed Condition Justification
SCHEDULE B – AIR EMISSIONS
B2 The release of dust and/or particulate matter resulting from the activities must not cause an environmental nuisance at any sensitive or commercial place.
The release of dust and/or particulate matter resulting from the activities must not cause an environmental nuisance at any nuisance sensitive or commercial place unless the release occurs as a result of an emergency, or is authorised by this environmental authority or the EP Act.
Refer to section 2.5.3.1
B20 N/A Flaring events, except for those resulting from an emergency, occurring outside of normal operating conditions must not exceed:
a) 7 hours per annum during daylight hours;and
b) 14 times per annum during daylight hours;and
c) 30 minutes of continuous visible smokeduring daylight hours except as authorisedunder condition (B21).
Refer to section 2.5
B21 N/A Notwithstanding condition (B20)(c), flaring events must not exceed 90 minutes of continuous visible smoke at any one time in the following circumstances:
a) A flaring event associated with a plantmaintenance activity that was planned to becompleted outside of daylight hours, but wasrequired to be undertaken during daylighthours to ensure the safe operation of theplant; or
b) A flaring event associated with a plantmaintenance activity that was not plannedand was required to be undertaken duringdaylight hours to ensure the safe operationof the plant.
Refer to section 2.5
Santos GLNG l PFL 10 EPPG00712213 - Amendment Application l 26 August 2020
Condition Number
Existing Condition Proposed Condition Justification
B22 N/A The holder of this authority must keep records of each flaring event to determine compliance with condition (B20) and (B21) and provide these records to the administering authority on request.
Records must include, but not be limited to:
a) The duration of each flaring event; and
b) The operational planning that wasimplemented to minimise flaring; and
c) The operational controls that wereimplemented during flaring; and
d) If the flaring event exceeds 30 minutes, thecircumstance under condition (B21) whichcaused this exceedance.
Refer to section 2.5
APPENDIX 1 - DEFINITIONS
N/A “daylight hours” means those between sunrise and sunset times as shown on the Australian Government Geoscience Australia webpage < http://www.ga.gov.au/geodesy/astro/sunrise.jsp>.
Refer to section 2.5
N/A “emergency” means (a) either— (i) human health or safety is threatened; or (ii) serious or material environmental harm has been or is likely to be caused; and (b) urgent action is necessary to— (i) protect the health or safety of persons; or (ii) prevent or minimise the harm; or (iii)rehabilitate or restore the environment becauseof the harm.
Refer to section 2.5 and 2.5.3.1
N/A “flaring event” means an event where flammable gas is combusted through a flare and produces visible smoke either (i) continuously for more than 5 minutes or (ii) multiple instances of visible smoke occurring consecutively with a total duration of more than 5 minutes, provided
Refer to section 2.5.3.1
Santos GLNG l PFL 10 EPPG00712213 - Amendment Application l 26 August 2020
Condition Number
Existing Condition Proposed Condition Justification
that the consecutive instances of visible smoke occur due to the same underlying cause, discharges through the same valve or flare source and occurs within a two hour period.
“normal operating conditions” means the ongoing operation of the LNG plant following commissioning and excludes start-up, shutdown, maintenance or calibration of emission monitoring devices.
“normal operating conditions” means the ongoing operation of the LNG plant following commissioning and excludes, excluding start-up, shutdown, maintenance or calibration of emission monitoring devices and upset conditions, an emergency and LNG ship management.
Refer to section 2.5 and 2.5.3.1
N/A “plant maintenance activities” means the maintenance shutdowns (and subsequent start-ups) where equipment at the plant is inspected and, if needed, repaired or replaced to ensure the ongoing safe operation of the plant.
Refer to section 2.5 and 2.5.3.1
N/A “Ringelmann number” means a visually comparative scale used to define levels of opacity, where clear is 0, black is 5 and 1 through 4 are increasing levels of grey as used in describing smoke from combustion of hydrocarbons.
Refer to section 2.5
N/A “visible smoke” means a visible suspension of carbon or other particles in air measured by a Ringelmann number greater than 2.
Refer to section 2.5
Santos GLNG l PFL 10 EPPG00712213 - Amendment Application l 26 August 2020