7/28/2019 Appendix 9A - Monthly Site Photos March 2013
1/5
Activity : Trial Trench for 500mm dia PUB Asbestos Pipe Activity : Clearing of Tree Roots from the proposed New Road
Location : Upper Changi Road South Bound near Sunbird
RoadLocation : ACCESS ROAD TO CHANGI NORTH INDUSTRIAL PARK
Date: 07/03/2013 Date: 07/03/2013
Activity :Noise Meter- Chainage 130 MCO2 East Bound:
Noise Monitoring Meter Installed Near Lamp Post 50,
relocated nearer to Residential Houses
Activity : Trial Trench-Chainage MCO2 60 : New trial Hole to Locate
alignment of 500mm Diameter Asbestos Pipe, Found approximately
1metre below footpath level.
Location :Upper Changi Road East Bound Location : Upper Changi Road West Bound
Date : 08/03/2013 Date : 08/03/2013
Activity : LTA Logo: Installed three (3 ) LTA Logo along
Hoarding facing Upper Changi Road, One (1 ) BCA SignBoard
and One (1) LTA Logo Facing Upper Changi Road East
Activity : BCA Sign Board: Installed One (1 ) BCA SignBoard Near
Main Entrance Gate at Upper Changi Road East
Location : Upper Changi Road West Bound Location :Near Main Entrance Gate- Upper Changi Road East
Date : 8/03/2013 Date : 9/03/2013
Activity : Boundary Fencing Activity : Clearing of Existing U- Drains
Location : Along the Slope of the proposed New Link RoadLocation : Near 900mm wide Drain of the proposed New Road North
Bound Side
Date : 9/03/2013 Date : 12/03/2013
5 6
APPENDIX 9A - PROGRESS PHOTOGRAPHS MARCH 2013 FOR PROJECT - ER420QP
1 2
3 4
7 8
7/28/2019 Appendix 9A - Monthly Site Photos March 2013
2/5
APPENDIX 9A - PROGRESS PHOTOGRAPHS MARCH 2013 FOR PROJECT - ER420QP
Activity : Tree Cutting : 2 Trees cut near the existing Bus StopActivity : Warning Signs in Place and Workers signalling the Traffic
during Tree Cutting Works
Warning Signs in Place and Workers signalling the Traffic Warning Signs in Place and Workers signalling the Traffic
Date: 13/03/2013 Date: 13/03/2013
Activity : Formwork Fabrication for 900mm RC Drain Activity : Fixing of damaged Silt Fence near ECM Area
Location : Near Site office Location : Near ECM Machine
Date :14/03/2013 Date :14/03/2013
Activity : Excavation works. Preparation for 900mm RC Drain Activity : Wire Installation for Internet Connection
Location : Upper Changi Road East West Bound Location : Along the Perimeter Fencing
Date: 15/03/2013 Date : 15/03/2013
Activity : Soil Sample taken for Laboraory testing Activity : Soil Samples taken for Laboratory testing
Location : New Road CH 90 West Bound Location : Upper Changi Road -CH 35 New Road North Bound
Date: 19/03/2013 Date: 19/03/2013
1211
9
15
10
13 14
16
7/28/2019 Appendix 9A - Monthly Site Photos March 2013
3/5
APPENDIX 9A - PROGRESS PHOTOGRAPHS MARCH 2013 FOR PROJECT - ER420QP
Activity : Working on 900mm RC Drain Activity : Precast 900mm RC Drain installed
Location : Upper Changi Road CH 185 West Bound Location : Upper Changi Road-West Bound CH 190~170
Date: 19/03/2013 Date : 2103/2013
17 18
7/28/2019 Appendix 9A - Monthly Site Photos March 2013
4/5
APPENDIX 9A - PROGRESS PHOTOGRAPHS MARCH 2013 FOR PROJECT - ER420QP
Activity : Welded Wire Mesh and soil Samples sent to AL
Technologies (Laboratory for Material Testing)Activity : On- going 900mm RC Drain works
Location : AL Technologies (Testing laboratory) Location : Upper Changi Road -West Bound CH 160~190
Date: 21/03/2013 Date : 22/03/2013
Activity : 900mm RC Drain excavation works Activity : Pegging of Under Ground Water Pipe
Location : West Bound Upper Changi Road Location : Upper Changi Road -West Bound
Date: 25/03/2013 Date : 25/03/2013
Activity : Checking and identification of Excavator operator
Registration Cert.
Activity : Meeting on site with N-Parks Officer and PUB Officers:
discusssed about PUB Pipe Diversion and protection of the tree
near proposed RCBC
Location : Proposed New Road Location : Upper Changi Road
Date: 25/03/2013 Date : 25/03/2013
Activity : Tree Cutting at Upper Changi Road East Activity : C5 in place Prior to Benching Works
Location : Upper Changi Road East, Near Proposed Road
Junction Location : New Road: CH 20-30
Date: 26/03/2013 Date : 27/03/2013
19 20
18
21 22
17
23 24
7/28/2019 Appendix 9A - Monthly Site Photos March 2013
5/5
APPENDIX 9A - PROGRESS PHOTOGRAPHS MARCH 2013 FOR PROJECT - ER420QP
Activity : On -going Benching works at 900mm RC Drain Activity : C5 in place - Benching Works
Location : CH 150- 190 West Bound Upper Changi Road Location : CH 150- 190 West Bound Upper Changi Road
Date: 27/03/2013 Date : 27/03/2013
Activity : Geo Textile in Place at 900mm RC Drain Prior to
Back filling worksSilt Fence properly installed near ECM Area
c v y : ee ng w ower r r. an eng oe an
Singtel Mr. Ronald Tan: regarding Diversion of underground
Location : CH150- 160 West Bound Upper Changi Road Location : Upper Changi Road
Date: 27 March 2013 Date: 27 March 2013
Activity : C5 in place Prior to Benching Works Activity : Silt Fence properly installed near ECM Area
Location : CH150- 160 West Bound Upper Changi RoadworksLocation : ECM AREA beside ULT Site officeCH150- 160 West Bound
U er Chan i Road
Date: 30 March 2013 Date:
27 28
29 30
25 26